The People of the State of Ca v. Ferc ( 2015 )


Menu:
  •                 FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    THE PEOPLE OF THE STATE OF            No. 13-71276
    CALIFORNIA, EX REL. KAMALA D.
    HARRIS, ATTORNEY GENERAL;              FERC No.
    PUBLIC UTILITIES COMMISSION OF        EL01-10-076
    THE STATE OF CALIFORNIA;
    SOUTHERN CALIFORNIA EDISON CO.,
    Petitioners,
    v.
    FEDERAL ENERGY REGULATORY
    COMMISSION,
    Respondent,
    CARGILL POWER MARKETS, LLC; EL
    PASO MARKETING COMPANY, LLC;
    EXELON GENERATION COMPANY,
    LLC; IDACORP ENERGY SERVICES
    COMPANY; IDAHO POWER
    COMPANY; TALEN MONTANA, LLC;
    TALEN ENERGY MARKETING, LLC;
    PUBLIC SERVICE COMPANY OF
    COLORADO; SHELL ENERGY NORTH
    AMERICA (US), L.P.; TRANSCANADA
    ENERGY LTD.,
    Respondents-Intervenors.
    2           STATE OF CALIFORNIA V. FERC
    THE CITY OF SEATTLE,                     No. 13-71487
    WASHINGTON,
    Petitioner,      FERC No.
    EL01-10-076
    PORTLAND GENERAL ELECTRIC
    COMPANY; DYNEGY POWER
    MARKETING; MPS MERCHANT                   OPINION
    SERVICES, INC; MPS CANADA CORP.,
    Intervenors,
    v.
    FEDERAL ENERGY REGULATORY
    COMMISSION,
    Respondent,
    TALEN MONTANA, LLC; TALEN
    ENERGY MARKETING, LLC;
    TRANSALTA ENERGY MARKETING
    (US), INC.; TRANSALTA ENERGY
    MARKETING (CALIFORNIA), INC.; EL
    PASO MARKETING COMPANY, LLC,
    Respondents-Intervenors.
    On Petition for Review of an Order of the
    Federal Energy Regulatory Commission
    Argued and Submitted
    June 16, 2015—San Francisco, California
    Filed December 17, 2015
    STATE OF CALIFORNIA V. 
    FERC 3
    Before: Sidney R. Thomas, Chief Judge, and M. Margaret
    McKeown and Richard R. Clifton, Circuit Judges.
    Opinion by Judge McKeown
    SUMMARY*
    Federal Energy Regulatory Commission
    The panel denied a petition for review from a decision of
    the Federal Energy Regulatory Commission (“FERC”) with
    respect to petitioners’ claim that the Mobile-Sierra
    presumption, which requires FERC to presume that the rate
    set in a freely negotiated wholesale-energy contract was just
    and reasonable, cannot apply to the spot sales at issue; and
    dismissed evidentiary challenges for lack of jurisdiction.
    The panel held that there was jurisdiction to review
    FERC’s decision to employ the Mobile-Sierra presumption
    in the class of contracts at issue because, pursuant to the
    inquiry in Steamboaters v. FERC, 
    759 F.2d 1382
     (9th Cir.
    1985), the test for final action under the Federal Power Act
    was met. The panel held that it lacked jurisdiction to consider
    the individual evidentiary restrictions raised in these cases
    because they were interim rulings whose consequences could
    not be determined with any finality at this juncture.
    *
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    4             STATE OF CALIFORNIA V. FERC
    The panel held that FERC reasonably applied the Mobile-
    Sierra presumption to the class of contracts at issue in these
    cases.
    COUNSEL
    Kevin J. McKeon (argued), Judith D. Cassel, Whitney E.
    Snyder, Hawke McKeon & Sniscak LLP, Harrisburg,
    Pennsylvania; Kamala D. Harris, Attorney General of
    California, Mark Breckler, Chief Assistant Attorney General,
    Martin Goyette, Senior Assistant Attorney General, San
    Francisco, California; David M. Gustafson, Deputy Attorney
    General, Oakland, California, for Petitioner People of the
    State of California ex rel. Kamala D. Harris, Attorney
    General.
    Candace J. Morey, Sarah R. Thomas, Public Utilities
    Commission of the State of California, San Francisco,
    California; Paul B. Mohler, Law Offices of Paul B. Mohler,
    PLC, Washington, D.C., for Petitioner Public Utilities
    Commission of the State of California.
    Rex S. Heinke (argued), Akin Gump Strauss Hauer & Feld
    LLP, Los Angeles, California; Jerry E. Rothrock, Moyers
    Martin, LLP, Tulsa, Oklahoma; Gregory C. Narver, Seattle
    City Attorney’s Office, Seattle, Washington, for Petitioner
    City of Seattle.
    David L. Morenoff, General Counsel, Robert H. Solomon,
    Solicitor, Lona T. Perry (argued), Deputy Solicitor, Susanna
    Y. Chu, Attorney, Washington, D.C., for Respondent Federal
    Energy Regulatory Commission.
    STATE OF CALIFORNIA V. 
    FERC
                    5
    Lawrence G. Acker, Van Ness Feldman, LLP, Washington,
    D.C.; Rex Blackburn, Brian R. Buckham, Idaho Power
    Company, Boise, Idaho, for Respondents-Intervenors Idaho
    Power Company and IDACORP Energy Services Co.
    Floyd L. Norton, IV, Morgan, Lewis & Bockius LLP,
    Washington, DC, for Respondents-Intervenors Cargill Power
    Markets, LLC and Public Service Company of Colorado.
    Andrea J. Chambers, Katharine E. Leesman, Ballard Spahr
    LLP, Washington, D.C., for Respondent-Intervenor Exelon
    Generation Company, LLC.
    Joseph B. Williams, Matthew D. Spohn, Ryan C. Norfolk,
    Norton Rose Fulbright US LLP, Washington, D.C., for
    Respondent-Intervenor El Paso Marketing Company, LLC.
    Jeffrey D. Watkiss, McDermott Will & Emery, LLP,
    Washington, D.C., for Respondent-Intervenor Shell Energy
    North America (US), L.P.
    Damien R. Lyster, Vinson & Elkins LLP, Washington, D.C.,
    for Respondents-Intervenors TansAlta Energy Marketing
    (U.S.) Inc. and TransAlta Energy Marketing (California) Inc.
    Kenneth L. Wiseman (argued), Mark F. Sundback, Andrews
    Kurth, LLP, Washington, D.C., for Rrespondent-Intervenor
    TransCanada Energy Ltd.
    6               STATE OF CALIFORNIA V. FERC
    OPINION
    McKEOWN, Circuit Judge:
    These appeals are the latest in a series of petitions that
    stem from the energy crisis in California and other western
    states in 2000 and 2001. The key issue we consider is the
    applicability of the Mobile-Sierra doctrine, which requires
    the Federal Energy Regulatory Commission (“FERC”) to
    “presume that the rate set out in a freely negotiated
    wholesale-energy contract meets the ‘just and reasonable’
    requirement” imposed by law. Morgan Stanley Capital Grp.,
    Inc. v. Pub. Util. Dist. No. 1, 
    554 U.S. 527
    , 530 (2008).
    BACKGROUND
    The circumstances of the California energy crisis are
    detailed in numerous cases.1 We recount only the history that
    is relevant to these petitions.
    After the California legislature deregulated the electricity
    market in the mid-1990s, “wholesale electricity prices
    skyrocketed.” Port of Seattle v. FERC, 
    499 F.3d 1016
    , 1022
    (9th Cir. 2007). Average rates soared in the California and
    Pacific Northwest short-term supply markets (also known as
    “spot markets”). 
    Id.
     at 1022–23. The spot markets in this
    case were somewhat unique in the particular way that rates
    were set:
    1
    See, e.g., Port of Seattle v. FERC, 
    499 F.3d 1016
    , 1022–26 (9th Cir.
    2007); Pub. Utils. Comm’n of State of Cal. v. FERC, 
    462 F.3d 1027
    ,
    1036–44 (9th Cir. 2006) (“Pub. Utils. Comm’n”); Bonneville Power
    Admin. v. FERC, 
    422 F.3d 908
    , 910–14 (9th Cir. 2005); Cal. ex rel.
    Lockyer v. FERC, 
    383 F.3d 1006
    , 1008–11 (9th Cir. 2004) (“Lockyer”).
    STATE OF CALIFORNIA V. 
    FERC 7
    Unlike the California spot market, which
    operated through a centralized power
    exchange using a central clearing price, the
    Pacific Northwest spot market operated
    through bilateral contracts negotiated
    independently between buyers and sellers,
    without a central clearing price. Most of these
    contracts were entered into under the terms of
    the Western Systems Power Pool (“WSPP”)
    Agreement, a standard form contract for
    electricity sales.
    Id. at 1023 (citation omitted). These rates became the subject
    of an investigation before FERC.
    Under the Federal Power Act (“FPA”), the rates charged
    by a public utility must be “just and reasonable, and any such
    rate or charge that is not just and reasonable is hereby
    declared to be unlawful.” 16 U.S.C. § 824d(a). Section 206
    of the FPA gives FERC the authority, on its own initiative or
    upon filing of a complaint, to investigate whether a particular
    rate is “just and reasonable.” Port of Seattle, 
    499 F.3d at 1023
    . If FERC finds a rate “unjust, unreasonable, unduly
    discriminatory or preferential,” it must determine a just and
    reasonable rate and order that rate to be “observed and in
    force.” 
    Id.
     (citing 16 U.S.C. § 824e(a)). FERC may also
    order sellers to pay refunds to those entities that bought
    energy at the unlawful rate. Id. (citing 16 U.S.C. § 824e(b)).
    Such refunds are limited to a fifteen-month period following
    the “refund effective date,” a date established by FERC that
    may be no earlier than the filing of the complaint nor later
    than five months after the filing. 16 U.S.C. § 824e(b). FERC
    may not order any refunds for the period before the refund
    effective date. Port of Seattle, 
    499 F.3d at 1023
    .
    8             STATE OF CALIFORNIA V. FERC
    The petitioners here challenge several FERC orders that
    were issued following our remand in Port of Seattle. In Port
    of Seattle we reviewed several challenges to FERC’s denial
    of refunds to wholesale buyers of electricity that purchased
    energy in the Pacific Northwest spot market at unusually high
    prices. We explained that FERC erred by initially excluding
    from the refund proceeding purchases made by the California
    Energy Resources Scheduling (“CERS”) division of the
    California Department of Water Resources, and that FERC
    abused its discretion by denying potential relief for
    transactions involving energy that was ultimately consumed
    in California. 
    Id. at 1022
    , 1032–34.
    We also held that FERC’s failure to consider evidence of
    market manipulation was arbitrary and capricious. 
    Id.
     at
    1034–36. It appeared that “Pacific Northwest sellers were
    apparently involved in Enron’s manipulation” of western
    energy markets.” 
    Id. at 1035
    . As a consequence, FERC had
    to “consider the possibility that the Pacific Northwest spot
    market was not . . . functional and competitive.” 
    Id.
     On
    remand, FERC was instructed to examine the evidence of
    market manipulation “in detail and account for it in any
    future orders regarding the award or denial of refunds in the
    Pacific Northwest proceeding.” 
    Id.
     at 1035–36. If the record
    was not sufficient to inform a reasoned decision, we noted
    that FERC may “find it necessary to call for additional
    fact-finding.” 
    Id. at 1036
    .
    After the remand, FERC proceeded to plan evidentiary
    hearings. See Puget Sound Energy, Inc. v. All Jurisdictional
    Sellers of Energy, 
    137 FERC ¶ 61,001
     (Oct. 3, 2011). For the
    first time in the history of this proceeding, FERC took the
    position that it would invoke the Mobile-Sierra doctrine,
    under which the rates set forth in “short-term bilateral power
    STATE OF CALIFORNIA V. 
    FERC
                       9
    sales contracts” like these would be presumptively just and
    reasonable. 
    Id.
     at paras. 20–21. The presumption could only
    be avoided or overcome if specific criteria were met, such as
    “where it can be shown that one party to a contract engaged
    in such extensive unlawful market manipulation as to alter the
    playing field for contract negotiations.” 
    Id.
    Adoption of the Mobile-Sierra presumption carried
    implications for the scope of evidence that FERC intended to
    permit in the proceeding. Electricity buyers would need to
    “demonstrate that a particular seller engaged in unlawful
    market activity in the spot market and that such unlawful
    activity directly affected the particular contract or contracts
    to which the seller was a party.” 
    Id.
     at para. 21. “[G]eneral
    allegations of market dysfunction” would be insufficient to
    avoid or overcome the presumption. 
    Id.
     FERC explained
    that parties could submit evidence of several specific
    violations that might entitle them to refunds: (1) violation of
    the WSPP Agreement; (2) violation of the terms of a specific
    bilateral contract underlying a particular purchase of
    electricity; or (3) certain other violations identified in a
    previous FERC case. 
    Id.
     at paras. 18–19.
    According to FERC, a market-wide remedy would be
    inappropriate because the Pacific Northwest spot market
    operated solely through bilateral contracts. 
    Id.
     at para. 24.
    These contracts distinguished the transactions from those
    conducted by California’s centralized power exchange, which
    operated through central clearing prices instead of negotiated
    contracts.
    The California Parties and Seattle requested rehearing and
    challenged FERC’s invocation of the Mobile-Sierra
    presumption and the scope of permissible evidence. A
    10            STATE OF CALIFORNIA V. FERC
    request for expedited treatment of the requests for rehearing
    initially went unanswered by the agency, and the proceeding
    continued. FERC set a schedule for parties to present
    contract-specific refund claims as a part of settlement
    procedures.
    While the requests for rehearing remained pending and
    settlement activity proceeded, FERC further addressed the
    Mobile-Sierra presumption and the scope of the Pacific
    Northwest proceeding in another order. Drawing on Morgan
    Stanley, which FERC cited to support its invocation of the
    Mobile-Sierra presumption, FERC clarified that refund
    claimants may overcome the presumption “by presenting
    evidence that a particular contract rate imposes an excessive
    burden on consumers or seriously harms the public interest.”
    
    141 FERC ¶ 61,248
     at paras. 1, 12–15 (Dec. 21, 2012).
    FERC acknowledged that it had spawned confusion regarding
    the scope of the proceeding, but claimed that it had not
    intended to modify the law as summarized in Morgan
    Stanley. 
    141 FERC ¶ 61,248
    , at paras. 12–14.
    FERC eventually denied the requests for rehearing and
    reaffirmed its application of the Mobile-Sierra presumption.
    
    143 FERC ¶ 61,020
     at para. 13 (Apr. 5, 2013). It also
    reaffirmed the limits it imposed on the scope of permissible
    evidence. 
    Id.
     at para. 23. These petitions for review
    followed.
    While these petitions were pending before us, the FERC
    proceeding marched on. Phase I of the proceeding was
    directed to whether the parties made a sufficient showing to
    avoid or overcome the Mobile-Sierra presumption with
    respect to their particular contracts and whether they were
    entitled to modification of their contracted rates. If
    STATE OF CALIFORNIA V. 
    FERC 11
    necessary, Phase II would address refund methodology.
    Following an initial decision on Phase I, 
    146 FERC ¶ 63,028
    (Mar. 28, 2014), FERC then ruled on exceptions to the
    decision, 
    151 FERC ¶ 61,173
     (May 22, 2015). FERC
    affirmed some of the Administrative Law Judge’s (“ALJ”)
    rulings and reversed others, ultimately remanding with
    instructions to the ALJ to make additional findings. 
    Id.
     at
    para. 3.
    ANALYSIS
    I. JURISDICTION
    We first address our jurisdiction over these petitions.
    Seattle and the California Parties characterize their Mobile-
    Sierra challenge as purely legal and ripe for immediate
    review. According to FERC, the refund orders are not final
    reviewable actions. We disagree with both sides in part.
    Our jurisdiction is governed by Section 313(b) of the
    FPA. 16 U.S.C. § 825l(b) (providing for review in the United
    States Court of Appeals of “an order issued by the
    Commission”). “Although section 313(b) is not limited on its
    face to final orders,” we have joined other circuits in the view
    that “review under section 313(b) is limited to orders of
    definitive substantive impact, where judicial abstention would
    result in irreparable injury to a party.” Steamboaters v.
    FERC, 
    759 F.2d 1382
    , 1387 (9th Cir. 1985) (citing Papago
    Tribal Util. Auth. v. FERC, 
    628 F.2d 235
    , 238 (D.C. Cir.
    1980) (“Papago”)). Under Steamboaters, we ask first
    “whether the order is final; second, whether, if unreviewed,
    it would inflict irreparable harm on the party seeking review;
    and third, whether judicial review at this stage of the process
    12               STATE OF CALIFORNIA V. FERC
    would invade the province reserved to the discretion of the
    agency.” 
    Id.
     at 1387–88.
    Before proceeding with the Steamboaters inquiry, we
    underscore that the petitions raise two types of issues. The
    petitioners’ threshold question is whether FERC properly
    invoked the Mobile-Sierra presumption. This challenge does
    not implicate the scope of admissible evidence; the objection
    is to the use of the Mobile-Sierra doctrine to shape the
    proceeding at all. We think of this issue as a facial
    applicability question: Did FERC appropriately invoke the
    Mobile-Sierra presumption under these circumstances?2
    Petitioners also challenge the restrictions that FERC imposed
    on the evidentiary proceeding. They want to be allowed to
    introduce evidence of, among other things, reporting
    violations, violations of obligations under the Uniform
    Commercial Code and state contract law, and violations by
    sellers that were not parties to the challenged contracts. We
    think of this issue as a question of the scope of the evidentiary
    proceeding.
    With regard to the facial applicability issue, the criteria of
    Steamboaters are satisfied. FERC’s decision to adopt the
    presumption in the context of short-term spot market
    2
    We note that the question of whether Mobile-Sierra applies at all
    admits of both a facial applicability analysis and a contract-specific, as-
    applied analysis that is more appropriate in individual proceedings before
    the agency. This distinction becomes relevant when we turn to the legal
    question of whether FERC’s interpretation of the “just and reasonable”
    standard is permissible. FERC’s application of the Mobile-Sierra doctrine
    to a class of contracts may be reasonable even if it becomes unreasonable
    when individual parties to a proceeding produce evidence that undermines
    the presumption.
    STATE OF CALIFORNIA V. 
    FERC 13
    contracts has been definitively resolved, and we therefore
    have jurisdiction to review this final agency decision.
    In order after order, FERC has not budged from its
    position. FERC’s response that the decision is not final,
    because the parties can overcome the presumption, begs the
    question. Unless the presumption applies, there is no legal
    hurdle to overcome. The petitioners challenge only the facial
    applicability of the Mobile-Sierra presumption in a particular
    class of cases, not how FERC will apply it in the specific
    proceedings before it.3 As to the facial applicability question,
    FERC has made a final decision that plainly “affects the legal
    positioning of the parties.” City of Fremont v. FERC,
    
    336 F.3d 910
    , 914 (9th Cir. 2003).
    The practical consequence of not accepting review at this
    stage is that, if FERC is wrong about the applicability of the
    Mobile-Sierra doctrine, the remaining proceedings will be
    predicated on a faulty legal ground. As in City of Fremont,
    the Mobile-Sierra presumption “will be treated as a
    benchmark” and petitioners face “the uphill task” to
    overcome it in their individual proceedings. 
    Id. at 914
    .
    These proceedings, which have multiplied and taken years to
    arrive at this stage, are no ordinary proceedings. To refrain
    from reviewing FERC’s facial applicability determination and
    introduce a risk, however slight, that FERC would change its
    invocation of Mobile-Sierra, would be to ignore the greater
    risks to the parties in these ongoing proceedings. We take to
    heart that “[t]he reviewability of an order must . . . be
    3
    To the extent that they challenge individualized determinations under
    the Mobile-Sierra doctrine, those determinations have not yet been made
    and there would be no final agency action to review.
    14            STATE OF CALIFORNIA V. FERC
    determined by reference to its practical function and
    consequences.” Papago, 
    628 F.2d at 239
    .
    Finally, the issue presents a legal question capable of
    resolution by this court in a way that does not invade the
    agency’s province. Deciding this pure legal issue in no way
    interferes with FERC’s discretion to accept evidence in
    rebuttal in the remaining proceedings. See Cal. Dep’t of
    Water Res. v. FERC, 
    361 F.3d 517
    , 520 (9th Cir. 2004);
    Papago, 
    628 F.2d at 238
    . “[I]mmediate review of the
    Commission’s determination will not disrupt the continuing
    proceeding, nor will it raise the danger of multiple appellate
    proceedings concerning identical issues.” Papago, 
    628 F.2d at 245
    .
    We thus conclude that the test for final action under the
    FPA is met and that we have jurisdiction to review FERC’s
    decision to employ the Mobile-Sierra presumption in the
    class of contracts at issue here.
    When it comes to the scope of the evidentiary proceeding,
    however, the challenged orders are preliminary and lack
    “definitive substantive impact.” Steamboaters, 
    759 F.2d at 1387
    ; see also FPC v. Metro. Edison Co., 
    304 U.S. 375
    ,
    383–84 (1938) (noting that “affording opportunity for
    constant delays. . .for the purpose of reviewing mere
    procedural requirements or interlocutory directions” would
    “do violence” to the FPA); Cities of Anaheim v. FERC,
    
    723 F.2d 656
    , 660 (9th Cir. 1984) (stating that “procedural
    orders” are not reviewable). The orders do not have the
    requisite “definitive character dealing with the merits of a
    proceeding before the Commission” to support review under
    Section 313(b) of the FPA. ASARCO, Inc. v. FERC, 777 F.2d
    STATE OF CALIFORNIA V. 
    FERC 15
    764, 771 (D.C. Cir. 1985) (quoting Metropolitan Edison Co.,
    
    304 U.S. at 384
    ) (emphasis added).
    For instance, FERC has already shifted course on the
    “shape” of the proceeding in a way that suggests some
    elements of its orders may not be sufficiently final for review.
    In October 2011, FERC articulated what evidence it would
    permit. 
    137 FERC ¶ 61,001
     (Oct. 3, 2011). More than a year
    later, in December 2012, FERC refined its statement of the
    scope of the proceeding, acknowledging that confusion had
    resulted from the prior order. 
    141 FERC ¶ 61,248
     (Dec. 21,
    2012). Significantly, it appears that despite arguments raised
    by the petitioners, at least some evidence of bad faith may
    have been admitted in the Phase I proceeding.
    While some harm might flow from proceeding under a
    flawed evidentiary framework, see City of Fremont, 
    336 F.3d at 914
    , the same risk stems from any order setting boundaries
    for a hearing. It is not enough to overcome the lack of
    finality of these orders on the scope of the evidentiary
    proceedings. The final order that results from the remand
    hearing will be reviewable and, indeed, will admit of more
    effective review of the evidentiary decisions since the court
    will be able to review all of the evidence taken together. The
    individual evidentiary restrictions challenged here are classic
    interim rulings whose consequence cannot be determined
    with any finality at this juncture.
    Judicial review of the evidentiary issues thus “properly
    follows the conclusion of the proceeding.” Papago, 
    628 F.2d at 240
    ; see also Cities of Anaheim, 
    723 F.2d at 661
    . In
    contrast, an interim or midstream determination on the scope
    of the evidentiary proceeding would invite the “disruptive
    consequences of judicial interference” and “bring[] the courts
    16             STATE OF CALIFORNIA V. FERC
    into the adjudication of the lawfulness of rates in advance of
    administrative consideration.” Papago, 
    628 F.2d at 242
    (quoting S. Ry. Co. v. Seaboard Allied Milling Corp.,
    
    442 U.S. 444
    , 460 (1979)); see also Delmarva Power & Light
    Co. v. FERC, 
    671 F.2d 587
    , 595 (D.C. Cir. 1982) (warning
    against intruding on FERC’s province where “the facts
    bearing on the interpretation of [filings and orders] are
    unclear and disputed, and these facts will bear heavily on
    determining whether the statute was violated”).
    “Under the rule in Steamboaters, the fact that one part of
    an agency order remains pending before the agency does not
    deprive this court of jurisdiction to review a discrete issue
    that has been definitively resolved by the agency.” Cal.
    Dep’t of Water Res., 
    361 F.3d at 520
    . We therefore exercise
    jurisdiction only as to the issue of whether FERC erred by
    invoking the Mobile-Sierra doctrine and hold that we lack
    jurisdiction to review FERC’s evidentiary orders.
    II. FACIAL APPLICABILITY OF THE MOBILE-SIERRA
    DOCTRINE
    The Mobile-Sierra doctrine takes its name from two cases
    that dealt with the authority of FERC’s predecessor, the
    Federal Power Commission, to determine whether rates set
    bilaterally by contract (as opposed to those set unilaterally by
    tariff) are just and reasonable. See United Gas Pipe Line Co.
    v. Mobile Gas Serv. Corp. (“Mobile”), 
    350 U.S. 332
     (1956);
    Fed. Power Comm’n v. Sierra Pac. Power Co. (“Sierra”),
    
    350 U.S. 348
     (1956). Where it applies, the doctrine requires
    FERC to presume that a contracted-for rate is “just and
    reasonable” under the FPA.
    STATE OF CALIFORNIA V. 
    FERC 17
    In 2008, after we decided Port of Seattle, the Supreme
    Court issued Morgan Stanley, its first Mobile-Sierra decision
    in decades. 
    554 U.S. 527
    . While Mobile and Sierra arose
    from suits brought by regulated sellers claiming that rates
    were too low, Morgan Stanley involved buyers’ challenges to
    high contract rates. The Court explained that “[t]here is only
    one statutory standard for assessing wholesale electricity
    rates, whether set by contract or tariff—the just-and-
    reasonable standard.” 
    Id. at 545
    . Addressing the contract
    context, the Court set forth the baseline rule that FERC must
    “presume that the rate set out in a freely negotiated
    wholesale-energy contract meets the ‘just and reasonable’
    requirement imposed by law.” 
    Id. at 530
    . In invoking the
    presumption here, FERC cited this rule from Morgan Stanley.
    
    137 FERC ¶ 61,001
    , para. 20.
    The Supreme Court emphasized that the Mobile-Sierra
    presumption is justified by the particular role that contracts
    play in the administrative scheme. “The regulatory system
    created by the [FPA] is premised on contractual agreements
    voluntarily devised by the regulated companies; it
    contemplates abrogation of these agreements only in
    circumstances of unequivocal public necessity.” Morgan
    Stanley, 
    554 U.S. at 534
     (quoting In re Permian Basin Area
    Rate Cases, 
    390 U.S. 747
    , 822 (1968)). Where the
    presumption applies, the inquiry into whether the rate is
    lawful focuses on whether the contract rate “seriously harm[s]
    the public interest.” Id. at 548.4
    4
    The Court has since explained that “the Mobile-Sierra public interest
    standard is not an exception to the statutory just-and-reasonable standard;
    it is an application of that standard in the context of rates set by contract.”
    NRG Power Mktg., LLC v. Maine Pub. Utils. Comm’n, 
    558 U.S. 165
    , 168
    (2010); see also Morgan Stanley, 
    554 U.S. at 546
     (explaining the doctrine
    18              STATE OF CALIFORNIA V. FERC
    The petitioners argue that Morgan Stanley does not
    support FERC’s decision to invoke the Mobile-Sierra
    presumption with respect to contracts of the nature at issue
    here. The circumstances here, according to petitioners,
    render the presumption illogical because the contracts were
    not freely negotiated long-term contracts with lawful prices.
    Instead, the transactions were short-term spot sales with a
    high degree of pressure on buyers. Petitioners’ argument is
    essentially that the FPA’s “just and reasonable” standard
    should not be interpreted as impliedly incorporating the
    Mobile-Sierra doctrine, as it was in Morgan Stanley. 
    Id.
     at
    545–46. Although it is true that the statutory language does
    not clearly spell out the application of the “just and
    reasonable” standard, under Chevron, we defer to FERC’s
    reasonable determination that Mobile-Sierra extends to the
    context of short-term spot sales. Chevron U.S.A. Inc. v.
    Natural Resources Defense Council, Inc., 
    467 U.S. 837
    , 843
    (1984).
    The mere short-term nature of these spot sale contracts
    does not render FERC’s application of the Mobile-Sierra
    doctrine unreasonable. Although long-term contracts may
    play a special role in stabilizing the energy market (a role
    spotlighted by the “turmoil in the spot market” in the 2000-
    2001 energy crisis, Morgan Stanley, 
    554 U.S. at
    539–40,
    547–48), the Supreme Court has drawn the rule so that the
    presumption may be invoked with regard to any contracted-
    for rate. 
    Id. at 551
    ; see also NRG Power Mktg., LLC,
    
    558 U.S. at 168
     (“The ‘venerable Mobile-Sierra doctrine’
    rests on ‘the stabilizing force of contracts.’”) (quoting
    provides “a definition of what it means for a rate to satisfy the
    just-and-reasonable standard in the contract context—a definition that
    applies regardless of when the contract is reviewed”).
    STATE OF CALIFORNIA V. 
    FERC 19
    Morgan Stanley, 
    554 U.S. at 548
    ). The fact that some
    contracts adopted the form of the WSPP Agreement (a
    FERC-jurisdictional standardized form agreement) does not
    change our analysis, as the sales were still made pursuant to
    contracts. After the presumption is invoked, the parties may
    avoid or rebut it based on an evidentiary showing,5 but
    FERC’s baseline assumption that the presumption applies to
    the contracts at issue is not unreasonable in light of Morgan
    Stanley.
    The petitioners’ numerous other arguments are also
    unconvincing. We see no reason why having notice of a
    § 206 proceeding when the contracts were formed would
    render it irrational to apply the presumption. The petitioners
    also overstate Lockyer, which stopped short of establishing
    that sellers who fail to meet reporting requirements have
    automatically charged unlawful prices so as to defeat the
    presumption. 
    383 F.3d at 1008
    .
    5
    It is important to remember that just because the presumption has been
    invoked at the beginning of a given proceeding does not mean it ultimately
    will apply to that case in the end. “FERC has ample authority to set aside
    a contract where there is unfair dealing at the contract formation
    stage—for instance, if it finds traditional grounds for the abrogation of the
    contract such as fraud or duress. In addition, if the ‘dysfunctional’ market
    conditions under which the contract was formed were caused by illegal
    action of one of the parties, FERC should not apply the Mobile-Sierra
    presumption.” Morgan Stanley, 
    554 U.S. at 547
     (citation omitted). FERC
    cited these possibilities in its December 2012 order. 
    141 FERC ¶ 61,248
    ,
    at para. 7. Where the presumption is rebutted in this way, a party
    challenging a rate no longer has to show that the “contract rates at issue
    impose an excessive burden or seriously harm the public interest” in order
    to prove that a rate is unlawful. See 
    id.
     at para. 14.
    20               STATE OF CALIFORNIA V. FERC
    The WSPP Agreement does not contain a “Memphis”
    clause6 that permits parties to amend their contracts
    unilaterally by complaint. The WSPP Agreement establishes
    standardized terms for power transactions to which individual
    terms (such as price, volume, and duration) are appended in
    separate confirmation agreements. The sections identified by
    petitioners do not permit unilateral amendments to
    confirmation agreements or the associated contractual rates.
    Finally, the factual and evidentiary issues raised by the
    petitioners are more appropriately considered in the context
    of eventual challenges to the scope of the evidentiary
    proceedings. For example, the California Parties argue that
    CERS was bullied into making purchases via these bilateral
    contracts when sellers refused to sell in the usual channels.
    Seattle claims that FERC disregarded this court’s instruction
    in Port of Seattle to take into account evidence of market
    manipulation. These arguments relate to downstream
    proceedings, such as whether the presumption can be
    overcome and whether FERC’s eventual decision is based on
    a proper record. These types of factual and evidentiary
    matters do not speak to whether FERC properly invoked
    Mobile-Sierra as a baseline, even if the evidence surrounding
    these contested circumstances ultimately warrants avoidance
    or rebuttal of the presumption. “[T]he mere fact that the
    market is imperfect, or even chaotic, is no reason to
    undermine the stabilizing force of contracts.” See Morgan
    6
    The name of the clause comes from United Gas Pipe Line Co. v.
    Memphis Light, Gas & Water Div., 
    358 U.S. 103
    , 110–13 (1958), in which
    the Supreme Court held that parties may “contract out of the Mobile-
    Sierra presumption by specifying in their contracts that a new rate filed
    with the Commission would supersede the contract rate.” Morgan
    Stanley, 
    554 U.S. at 534
    .
    STATE OF CALIFORNIA V. 
    FERC 21
    Stanley, 
    554 U.S. at
    547–48. We thus decline to extend our
    analysis to these disguised efforts to rebut the presumption as
    applied to these individual parties before FERC has had an
    opportunity to conclude the proceedings. We need only
    decide whether FERC reasonably applied Mobile-Sierra to
    the class of contracts at issue here, and we hold that FERC’s
    interpretation is reasonable.
    We deny the petition with respect to petitioners’ claim
    that the Mobile-Sierra presumption cannot apply to the spot
    sales at issue in this case and dismiss the evidentiary
    challenges for lack of jurisdiction.
    DENIED IN PART; DISMISSED IN PART.