Barnes v. Federal Aviation Administration , 865 F.3d 1266 ( 2017 )


Menu:
  •                  FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    MICHELLE BARNES, an individual;           No. 14-71180
    PATRICK CONRY, an individual;
    BLAINE ACKLEY, an individual;
    DAVID BARNES, an individual;               OPINION
    JAMES LUBISCHER, an individual;
    OREGON AVIATION WATCH, an
    Oregon non-profit organization,
    Petitioners,
    v.
    FEDERAL AVIATION
    ADMINISTRATION,
    Respondent;
    PORT OF PORTLAND,
    Intervenor-Respondent.
    On Petition for Review of an Order of the
    Federal Aviation Administration
    Argued and Submitted October 5, 2016
    Portland, Oregon
    Filed August 3, 2017
    Before: Sidney R. Thomas, Chief Judge, and Richard R.
    Clifton and Jacqueline H. Nguyen, Circuit Judges.
    2                         BARNES V. FAA
    Opinion by Judge Clifton
    SUMMARY*
    Federal Aviation Administration
    The panel denied a petition for review of a decision of the
    Federal Aviation Administration (“FAA”), finding that a new
    runway project at Hillsboro Airport near Portland, Oregon,
    would have no significant impact on the environment
    (“FONSI”).
    The panel held that in adopting the supplemental
    environmental assessment, issuing the FONSI, and
    concluding that the project at Hillsboro Airport complied with
    the requirements of the Airport and Airway Improvement
    Act, the FAA did not act in a manner that was arbitrary,
    capricious, an abuse of discretion, or otherwise not in
    accordance of law.
    COUNSEL
    Sean Malone (argued), Eugene, Oregon, for Petitioners.
    Robert Lundman (argued), Maggie B. Smith, and Andrew C.
    Mergen, Attorneys, Appellate Section; Sam Hirsch, Acting
    Assistant Attorney General; Environment and Natural
    *
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    BARNES V. FAA                          3
    Resources Division, United States Department of Justice,
    Washington, D.C.; Patricia Deem, Office of Regional
    Counsel, NW Mountain Division, Federal Aviation
    Administration; Eric Elmore and Daphne Fuller, Office of the
    Chief Counsel, Federal Aviation Administration, Washington,
    D.C.; for Respondent.
    Jason T. Morgan (argued) and Beth S. Ginsberg, Stoel Rives
    LLP, Seattle, Washington, for Intervenor-Respondent.
    OPINION
    CLIFTON, Circuit Judge:
    This case involves a new runway at Hillsboro Airport, a
    general aviation airport near Portland, Oregon. We
    previously considered a challenge to the original
    environmental assessment done for the new runway project
    in Barnes v. United States Department of Transportation,
    
    655 F.3d 1124
     (9th Cir. 2011) (“Barnes I”). Although we
    rejected many of the arguments raised in the prior petition for
    review, we granted the petition and remanded for further
    consideration based primarily on concern for the possibility
    that the new runway would result in a larger number of
    takeoffs and landings at the airport, a possibility we
    concluded had not been adequately addressed.
    Following remand, a supplemental environmental
    assessment was prepared. It concluded that the new runway
    would cause at most a small increase in air traffic and also
    determined that, even if the runway did induce a growth in
    traffic, any impact on air quality would be immaterial. The
    Federal Aviation Administration accepted that assessment
    4                       BARNES V. FAA
    and issued a finding that the new runway would have no
    significant impact on the environment. Petitioners, five
    individuals and a non-profit organization, oppose the new
    runway and challenge the FAA’s conclusions. We have
    jurisdiction pursuant to 
    49 U.S.C. § 46110
    (a), and we deny
    their petition for review.
    I. Background
    Hillsboro Airport (“HIO”) is located in the city of
    Hillsboro in Washington County, Oregon, twelve miles west
    of downtown Portland. It is owned by Intervenor-Respondent
    Port of Portland. In terms of airport operations (the sum of
    takeoffs and landings), it became the busiest airport in
    Oregon in 2008, surpassing Portland International Airport.1
    In 2005 the Port undertook to develop a Master Plan for
    HIO. Among other things, the Plan proposed construction of
    a new third runway, which would run parallel to the existing
    primary runway and would be used by small general aviation
    aircraft. The Plan concluded that adding the new runway
    would be “the best means available for reducing delays and
    the undesirable conditions that occur due to delay.” The new
    runway would also allow for separating small, single-engine
    propeller planes from larger propeller planes and jet aircraft.
    The modifications were to be funded in part by FAA grants.
    The use of FAA funds meant that the environmental
    effects of the project had to be considered. See 
    40 C.F.R. § 1508.18
    (a). The Port produced an environmental
    1
    More background on HIO, its configuration, and the changes
    proposed by the Port is provided in our prior opinion. See Barnes I,
    
    655 F.3d at
    1126–29.
    BARNES V. FAA                          5
    assessment (“EA”) for the FAA, and the FAA issued a
    finding of no significant impact (“FONSI”) in 2010. See
    
    40 C.F.R. § 1508.13
    . That finding relieved the FAA of the
    obligation to have a more detailed environmental impact
    statement prepared. See 
    40 C.F.R. § 1501.4
    (e).
    Opponents of the new runway, including three of the
    petitioners in this action, petitioned this court for review,
    arguing, among other things, that the EA did not meet the
    requirements of the National Environmental Policy Act of
    1969 (“NEPA”), 
    42 U.S.C. § 4321
     et seq. Barnes I, 
    655 F.3d at
    1130–31. We rejected many of the opponents’ arguments,
    but we granted the petition and remanded for further
    consideration. 
    Id. at 1143
    . Although the EA concluded that
    the new runway would not increase air traffic at the airport,
    our decision concluded that the EA was inadequate because
    the FAA could not “point to any documents in the record that
    actually discusse[d] the impact of a third runway on aviation
    demand at HIO.” 
    Id. at 1136
    . Accordingly, we determined
    “that remand [was] necessary for the FAA to consider the
    environmental impact of increased demand resulting from the
    HIO expansion project, if any.” 
    Id. at 1139
    .
    On remand, the Port produced a supplemental
    environmental assessment (“SEA”), which included three
    different forecasts for demand at HIO. The forecasts
    predicted at most a small increase in air traffic operations due
    to the new runway and concluded that pollution generated by
    any increased traffic would be negligible. The FAA adopted
    the SEA, concluded that it was unnecessary to prepare an
    environmental impact statement, and, in 2014, issued a new
    FONSI. See 
    40 C.F.R. §§ 1501.4
    , 1508.13; Morongo Band
    of Mission Indians v. FAA, 
    161 F.3d 569
    , 575 (9th Cir. 1998)
    (“If a FONSI is made, the agency need not prepare an EIS.”).
    6                         BARNES V. FAA
    Following the decision of a motions panel of this court to
    deny Petitioners’ motion for an injunction pending
    consideration of the petition, the Port constructed the runway,
    and the runway is now completed and open for use.2
    Petitioners now contend that, on remand, the FAA did not
    fulfill NEPA’s requirement to take a “hard look” at the
    environmental impacts of additional air traffic generated by
    the new runway. See Envtl. Prot. Info. Ctr. v. U.S. Forest
    Serv., 
    451 F.3d 1005
    , 1009 (9th Cir. 2006). They also argue
    that the circumstances of the project necessitated preparation
    of an environmental impact statement. See 
    42 U.S.C. § 4332
    (2)(C); 
    40 C.F.R. § 1508.27
    . Finally, they contend that
    the FAA did not comply with the Airport and Airway
    Improvement Act’s requirement to ensure that the new
    runway was consistent with the plans of the appropriate local
    agencies. See 
    49 U.S.C. § 47106
    (a)(1).
    II. Discussion
    “Judicial review of agency decisions under NEPA . . . is
    provided by the [Administrative Procedure Act], which
    maintains that an agency action may be overturned only when
    it is ‘arbitrary, capricious, an abuse of discretion, or otherwise
    2
    The parties have not addressed whether this development rendered
    the case moot. We conclude that it did not. In a similar context, we
    previously held that a NEPA challenge to a completed and fully
    operational freeway interchange was not moot because the court could
    conceivably have ordered that the interchange be closed and dismantled.
    West v. Sec’y of the Dep’t of Transp., 
    206 F.3d 920
    , 925 (9th Cir. 2000);
    see also Feldman v. Bomar, 
    518 F.3d 637
    , 642–43 (9th Cir. 2008)
    (collecting cases). Potential remedies available in the instant case,
    including decommissioning the runway, are no less implausible than
    dismantling a freeway interchange.
    BARNES V. FAA                         7
    not in accordance with law.’” Pit River Tribe v. U.S. Forest
    Serv., 
    469 F.3d 768
    , 778 (9th Cir. 2006) (quoting 
    5 U.S.C. § 706
    (2)(A)). In the context of “reviewing an agency’s
    decision not to prepare an EIS under NEPA,” we consider
    “whether the agency has taken a ‘hard look’ at the
    consequences of its actions, ‘based [its decision] on a
    consideration of the relevant factors,’ and provided a
    ‘convincing statement of reasons to explain why a project’s
    impacts are insignificant.’” Envtl. Prot. Info. Ctr., 
    451 F.3d at 1009
     (alteration in original) (quoting Nat’l Parks &
    Conservation Ass’n v. Babbitt, 
    241 F.3d 722
    , 730 (9th Cir.
    2001)). The FAA’s conclusion that a proposed project meets
    the requirements specified in the Airport and Airway
    Improvement Act, 
    49 U.S.C. § 47106
    , is also reviewed under
    the arbitrary and capricious standard. See City of Dania
    Beach v. FAA, 
    628 F.3d 581
    , 588 (D.C. Cir. 2010).
    A. Petitioners’ Challenges         to   the    Supplemental
    Environmental Assessment
    Petitioners argue that the SEA was deficient in a number
    of respects and that it therefore did not constitute the “hard
    look” NEPA requires. We address each of Petitioners’
    contentions in turn.
    1. Forecasting Methodologies
    On remand, the Port produced three forecasts for air
    traffic growth at HIO: the Unconstrained Forecast, the
    Constrained Forecast, and the Remand Forecast.
    The Unconstrained Forecast modeled air traffic based on
    socio-economic data without limitations related to the
    airport’s infrastructure. In other words, the Unconstrained
    8                     BARNES V. FAA
    Forecast predicted how much air traffic HIO would see if it
    had limitless runways and other facilities. The Unconstrained
    Forecast predicted that HIO would have 224,260 total aircraft
    operations in 2016 and 242,680 total aircraft operations in
    2021.
    The Constrained Forecast modeled air traffic while taking
    account of HIO’s limited runways and assuming that the new
    runway would not be built. The Constrained Forecast
    assumed that, if HIO became so crowded that the wait time to
    use its two then-existing runways became intolerable, then
    pilots would begin using other airports, and growth at HIO
    would taper off. The Constrained Forecast determined that,
    even without the new runway, the delays at HIO would not
    have reached an intolerable level by 2021, the end of the
    forecasting period adopted by the SEA. Because a delay-
    induced curb on operations growth was the only difference
    between the Unconstrained and Constrained Forecasts, and
    because such delays were not anticipated during the
    forecasting period, the Constrained Forecast predicted the
    same number of operations as the Unconstrained Forecast.
    In order to accommodate our direction in Barnes I to
    consider demand induced by the new runway, the SEA also
    included what it called a Remand Forecast, which
    incorporated data derived from a survey. In the survey, pilots
    with planes based at HIO and other airports around Portland
    estimated whether and by how much they would increase
    their operations at HIO due to the new runway, the associated
    reduced delays at peak times, and the increased safety arising
    from separating single-engine propeller planes from larger
    planes. The SEA added the increase that the pilots projected
    to the projections from the Unconstrained Forecast to arrive
    at the Remand Forecast, which predicted that HIO would see
    BARNES V. FAA                           9
    235,610 operations in 2016 and 254,030 operations in 2021.
    Accordingly, among the three forecasts, the Remand Forecast
    predicted the largest air traffic volume. Specifically, the
    Remand Forecast predicted that HIO would have 11,350
    more takeoffs and landings each year with the new runway
    than it would without the new runway.
    The SEA contended that the Unconstrained Forecast,
    which took account of socio-economic conditions, adequately
    predicted future demand at HIO assuming the new runway
    were built. Additionally, the SEA provided extensive
    analysis about the Remand Forecast. Our primary concern in
    Barnes I was the original EA’s lack of a comparison of
    projected air traffic with and without the new runway.
    
    655 F.3d at 1134
     (“The agencies are unable to point to
    anything in the record showing that they in fact considered
    the possibility that expanding HIO’s capacity would lead to
    increased demand and increased aircraft operations . . . .”); 
    id.
    at 1136–37. By including, on the one hand, the Constrained
    Forecast, and comparing it with, on the other hand, both the
    Unconstrained and Remand Forecasts, the SEA addressed this
    concern two times over.
    Petitioners contend that the Remand Forecast
    underestimates growth. Specifically, Petitioners claim that
    the survey used to generate the Remand Forecast did not
    include a response from Hillsboro Aviation, a pilot training
    school that Petitioners state is the largest aviation operator at
    HIO. The FAA counters that Petitioners are mistaken and
    that Hillsboro Aviation did in fact respond to the survey. The
    record indicates that Hillsboro Aviation’s response was
    10                          BARNES V. FAA
    included in the survey. Accordingly, the challenge to the
    Remand Forecast is without merit.3
    The SEA concluded that even the higher activity levels
    reflected in the Remand Forecast would not have any
    significant environmental effects. With regard to air quality,
    for instance, it stated that “the proposed project would either
    reduce emissions and be de minimis, or, if the Remand
    Forecasts occurred, would slightly increase emissions but
    remain well below the de minimis level.” Petitioners
    challenge specific elements of that conclusion.
    2. Lead Pollution Baseline Measurements
    Petitioners argue that, because the SEA did not assess the
    existing amount of lead in the soil and water in the area
    surrounding HIO, it did not consider how any lead emissions
    from increased air traffic might impact the accumulation of
    lead in the soil and water. Unlike jet fuel used by commercial
    airlines, fuel used in general aviation may contain lead.
    Petitioners contend that the SEA therefore “ignore[d] an
    important aspect” of the impacts of potentially increased air
    traffic associated with the new runway in violation of
    NEPA’s requirements.
    3
    In their reply brief, Petitioners contend that, even if Hillsboro
    Aviation was included in the survey, the survey did not capture all of the
    likely growth related to pilot training. Petitioners did not raise this
    argument in their opening brief, and it is therefore waived. See McKay v.
    Ingleson, 
    558 F.3d 888
    , 891 n.5 (9th Cir. 2009) (“Because this argument
    was not raised clearly and distinctly in the opening brief, it has been
    waived.”); Fed. R. App. P. 28(a)(8)(A) (“The appellant’s brief must
    contain . . . appellant’s contentions and the reasons for them, with citations
    to the authorities and parts of the record on which the appellant relies.”).
    BARNES V. FAA                              11
    The SEA demonstrated that the new runway would have
    little effect on lead in the area around HIO. The Remand
    Forecast estimated that the new runway would result in the
    annual emission of an additional 0.03 ton of lead in 2016
    (from 0.83 ton under the Constrained Forecast to 0.86 ton
    under the Remand Forecast) and the annual emission of an
    additional 0.02 ton of lead in 2021 (from 0.90 ton under the
    Constrained Forecast to 0.92 ton under the Remand
    Forecast).4 These predictions represent an increase in lead
    emissions of less than four percent. The data underlying
    these forecasts were discussed in great detail in the “air
    quality technical memorandum” attached to the SEA.
    To assess the significance of this increase in lead
    emissions, the SEA referred to the Environmental Protection
    Agency’s regulations on lead. In certain circumstances, when
    a federal action would cause the annual emission of more
    than 25 tons of lead, EPA regulations require a “conformity
    determination” to evaluate the action’s impact on the relevant
    region’s compliance with the national ambient air quality
    standards (“NAAQS”). 
    40 C.F.R. § 93.153
    . The forecasted
    increase in lead emissions due to the new runway was very
    small in comparison to the levels of lead emissions that the
    EPA considers sufficient to necessitate study.
    The SEA reasonably determined that any increased air
    traffic would have virtually no effect on the lead levels in the
    area around HIO. If a project will have virtually no effect on
    4
    The reduced amount of pollution attributable to the new runway
    over the five year period is due to the model’s prediction that the new
    runway will decrease delays and reduce emissions from idling aircraft,
    thereby partially offsetting emissions from increased operations. The
    difference in delays with and without the new runway increases with time.
    12                        BARNES V. FAA
    the presence of a pollutant, then it would be pointless to
    measure or model the presence of that pollutant prior to
    commencing the project. Therefore, it was not arbitrary or
    capricious to refrain from conducting additional analyses
    regarding baseline lead levels in the soil or water.5
    3. Impacts on Children
    Petitioners argue that the SEA failed to consider the
    impact that increased lead emissions may have on children.
    The SEA included a section titled “Children’s Health and
    Safety Risk,” in which it explained that, even with the
    increased air traffic projected by the Remand Forecast, the air
    around HIO would remain “well below” the EPA’s NAAQS
    lead limit of 0.15 µg/m3.
    Using the FAA’s Emission & Dispersion Modeling
    System, the SEA concluded that the maximum lead
    concentration in the air around HIO was 0.00405 µg/m3 prior
    to the construction of the new runway. Using a “sensitivity
    analysis” that assumed that all emissions occurred near
    5
    The SEA’s analysis in this case is distinguishable from a different
    analysis we recently rejected on NEPA grounds, in which the Bureau of
    Land Management analyzed the effects of a proposed open pit mine.
    Great Basin Res. Watch v. Bureau of Land Mgmt., 
    844 F.3d 1095
    , 1104
    (9th Cir. 2016). The BLM, citing only a completely conclusory statement
    in an email from an “expert,” had “assumed” that the baseline levels for
    a host of pollutants around the mine was “zero.” 
    Id. at 1103
    . The BLM
    provided no explanation whatsoever justifying its adoption of this
    assumption. Unlike this case, the issue in the BLM case was not whether
    the pollutants emanating from the mine would be so negligible that a
    baseline analysis of pollutants was unnecessary. Moreover, the BLM
    analysis was grounded in nothing but an unsupported assertion, whereas
    the report on which the SEA based its conclusion regarding lead emissions
    from HIO was thorough and rigorous.
    BARNES V. FAA                         13
    ground level, the SEA found a maximum lead concentration
    in the air around HIO of 0.06567 µg/m3. Accordingly, even
    assuming that all lead emissions from the airport occurred at
    ground level, the projected lead level in the air around HIO
    was less than half of the maximum allowed under the EPA’s
    standards. Given these conditions, it was not arbitrary or
    capricious for the SEA to conclude that an increase in lead
    emissions of less than four percent would not cause the
    ambient lead concentrations surrounding HIO to exceed the
    EPA’s lead NAAQS.
    The SEA also concluded that the EPA’s NAAQS for lead
    was set at an acceptable level to protect sensitive populations,
    including children. When it issued its final rule, the EPA
    explained that the NAAQS for lead was established “to
    provide increased protection for children and other at-risk
    populations against an array of adverse health effects, most
    notably including neurological effects in children, including
    neurocognitive and neurobehavioral effects.” Environmental
    Protection Agency, National Ambient Air Quality Standards
    for Lead, Final Rule, 
    73 Fed. Reg. 66964
    , 66965 (Nov. 12,
    2008). The EPA further stated that the “standards include an
    adequate margin of safety . . . to address uncertainties
    associated with inconclusive scientific and technical
    information [and] to provide a reasonable degree of
    protection against hazards that research has not yet
    identified.” 
    Id. at 66966
    . When setting this standard, the
    EPA considered the variety of ways in which people may be
    exposed to lead, including through water, dust, soil, and food.
    
    Id. at 66971
    . It was appropriate for the FAA to defer to the
    EPA on the factual question of what level of airborne lead is
    safe for children. See WildEarth Guardians v. Jewell,
    
    738 F.3d 298
    , 311–12 (D.C. Cir. 2013) (approving of
    agency’s use of NAAQS in completing NEPA analysis).
    14                     BARNES V. FAA
    4. Flight Stage Components Included in Lead Emission
    Calculation
    Petitioners argue that the SEA did not adequately account
    for the various components of a typical flight in its lead
    emission calculations. First, Petitioners contend that the SEA
    did not adequately support its estimate for the time it takes for
    aircraft to taxi to and from the runway. The SEA stated that
    the taxi times were forecast taking into account HIO’s
    runway usage, aircraft mix, and weather conditions. This
    explanation does not, as Petitioners contend, represent a
    “void,” but rather it is a methodology selected by the FAA
    and entitled to deference. Compare Or. Nat. Desert Ass’n v.
    Bureau of Land Mgmt., 
    625 F.3d 1092
    , 1121 (9th Cir. 2010)
    (“We cannot defer to a void.”) with Nat’l Parks &
    Conservation Ass’n v. U.S. Dep’t of Transp., 
    222 F.3d 677
    ,
    682 (9th Cir. 2000) (“[T]he FAA’s determination is due
    deference—especially in areas of agency expertise such as
    aviation forecasting.”).
    Petitioners also argue that, when considering lead
    emissions in the air surrounding HIO, the SEA did not
    properly consider the altitude at which emissions were
    released during the “cruise” phase of flights. Specifically,
    Petitioners contend that the SEA should have applied a
    mixing height (the height below which air particles will mix
    to become homogeneous) of 3,000 feet. That is essentially
    what the SEA did, as the FAA pointed out in its answering
    brief. The FAA’s Emissions and Dispersion Modeling
    System (“EDMS”), approved by the EPA, calls for emissions
    released above 1,000 feet to be treated as being released
    halfway between 1,000 feet and the mixing height. The SEA
    treated those emissions as being released at a height of
    619 meters (2,031 feet), which is approximately halfway
    BARNES V. FAA                          15
    between 1,000 feet and the mixing height of 3,000 feet that
    Petitioners advocate. Petitioners did not say anything further
    on the subject in their reply.
    Petitioners argue separately that the EDMS model did not
    include lead emissions that occur during the “run-up” phase,
    when pilots conduct pre-flight checks. The FAA confirmed
    in its response to comments that it was developing a
    methodology to measure emissions during the run-up phase
    but had not yet completed that endeavor, so it continued
    relying on the existing EDMS methodology in the interim.
    The FAA is entitled to deference in its decision. See Nat’l
    Parks & Conservation Ass’n, 222 F.3d at 682.
    5. Impacts on Water Quality
    Petitioners argue that the SEA did not account for
    pollution in water and wetlands arising from potential
    increased air operations. In fact, the SEA discussed the
    project’s impact on water quality and wetlands in detail.
    Although the section of the SEA discussing water did not
    specifically address lead emissions, the NAAQS for lead
    accounts for exposure to lead through water, 73 Fed. Reg. at
    66971, and the SEA concluded that any increased lead
    emissions would be de minimis under the NAAQS.
    Accordingly, the SEA’s assessment of the impacts to lead
    content in water arising from a potential increase in air traffic
    was not arbitrary or capricious.
    6. Duration of Emissions Forecasting Period
    Petitioners argue that the SEA should have published
    twenty years of emissions projections instead of the ten years
    it provided. Petitioners contend that the FAA typically
    16                      BARNES V. FAA
    forecasts demand twenty years in advance for long-range
    planning purposes and note that the FAA prepared such a
    forecast for HIO. The SEA explained that, consistent with
    the FAA’s typical practices for NEPA analyses, the SEA
    would rely on forecasts for the period through 2021 because
    the air traffic for that period was “reasonably foreseeable[,]
    i.e.[,] . . . likely to occur or probable rather than . . . merely
    possible.”
    “The selection of the [temporal] scope of an EIS is a
    delicate choice and one that should be entrusted to the
    expertise of the deciding agency.” Selkirk Conservation
    Alliance v. Forsgren, 
    336 F.3d 944
    , 962 (9th Cir. 2003). In
    that case we concluded that, although the Forest Service had
    data that could have allowed it to forecast further into the
    future, it was within the agency’s discretion to select a three-
    year window for analyzing the future effects of its action. 
    Id.
    at 962–63. Similarly, it was not arbitrary or capricious for the
    FAA to determine that, under NEPA, the reasonably
    foreseeable emission forecasting time frame for this project
    was five to ten years, even though it had (less precise)
    demand estimates available in the twenty-year time frame.
    That was especially true for lead emissions given that the
    FAA and the EPA are working to create an unleaded aviation
    fuel for existing piston engine aircraft by 2018. See Town of
    Cave Creek v. FAA, 
    325 F.3d 320
    , 331 (D.C. Cir. 2003)
    (concluding that, especially in light of evolving technologies,
    it was permissible under NEPA for the FAA to model
    environmental impacts five years in advance, even though the
    agency possessed demand projections stretching further into
    the future).
    Because the FAA “‘based [its decision] on a consideration
    of the relevant factors,’ and provided a ‘convincing statement
    BARNES V. FAA                          17
    of reasons to explain why [the] project’s impacts are
    insignificant,’” we conclude that the FAA took the requisite
    “‘hard look’ at the consequences of its actions.” Envtl. Prot.
    Info. Ctr., 
    451 F.3d at 1009
     (first alteration in original)
    (quoting Nat’l Parks & Conservation Ass’n, 
    241 F.3d at 730
    ).
    B. Petitioners’ Arguments Related to the Significance of the
    Project
    “An agency must prepare an EIS ‘if “substantial questions
    are raised as to whether a project . . . may cause significant
    degradation of some human environmental factor.”’” Ctr. for
    Biological Diversity v. Nat’l Highway Traffic Safety Admin.,
    
    538 F.3d 1172
    , 1219 (9th Cir. 2008) (omission in original)
    (quoting Idaho Sporting Cong. v. Thomas, 
    137 F.3d 1146
    ,
    1149 (9th Cir.1998)).           Petitioners contend that the
    significance of the new runway’s potential impacts requires
    the agency to produce an EIS. Although we rejected many of
    Petitioners’ arguments in support of this contention in Barnes
    I, we left open the possibility that Petitioners might prevail on
    their arguments related to demand induced by the new
    runway. 
    655 F.3d at 1140
    .
    Petitioners contend that the new runway will result in
    increased lead emissions “significantly” affecting public
    health, especially children’s health.      See 
    40 C.F.R. § 1508.27
    (b)(2). However, the SEA concluded that any
    increase in lead emissions would be “de minimis.” An
    environmental impact statement is not required merely
    because an analysis reveals a potential for a minor impact.
    See Native Ecosystems Council v. U.S. Forest Serv., 
    428 F.3d 1233
    , 1240 (9th Cir. 2005) (“[I]t does not follow that the
    presence of some negative effects necessarily rises to the
    18                    BARNES V. FAA
    level of demonstrating a significant effect on the
    environment.”).
    Petitioners also contend that the new runway is significant
    because it involves “unique . . . risks” to children. See
    
    40 C.F.R. § 1508.27
    (b)(5). This is simply a reformulation of
    the argument regarding children’s health discussed above,
    and it is no more meritorious.
    Additionally, Petitioners contend that the new runway is
    significant because it is near residences and therefore has
    “unique geographical characteristics.” Petitioners refer to
    
    40 C.F.R. § 1508.27
    (b)(3), which states that evaluating a
    project’s significance includes considering “[u]nique
    characteristics of the geographic area such as proximity to
    historic or cultural resources, park lands, prime farmlands,
    wetlands, wild and scenic rivers, or ecologically critical
    areas.” Petitioners provided no reason to conclude that there
    is anything unique about an airport near a residential area.
    See Town of Cave Creek, 
    325 F.3d at 331
     (rejecting challenge
    to air traffic rerouting project by observing that “there is
    nothing unique about Cave Creek or Carefree. Petitioners
    concede that they are residential areas.”). Accordingly,
    Petitioners have not identified any unique issues requiring an
    EIS.
    Citing 
    40 C.F.R. § 1508.27
    (b)(4), Petitioners also contend
    that the project’s effects are likely to be “highly
    controversial” because of disputes about lead emissions from
    the airport. Under that regulation, “‘controversial’ is ‘a
    substantial dispute [about] the size, nature, or effect of the
    major Federal action rather than the existence of opposition
    to a use.’” Blue Mountains Biodiversity Project v.
    Blackwood, 
    161 F.3d 1208
    , 1212 (9th Cir. 1998) (alteration
    BARNES V. FAA                         19
    in original) (quoting Sierra Club v. U.S. Forest Serv.,
    
    843 F.2d 1190
    , 1193 (9th Cir. 1988)).
    In support of their argument, Petitioners point to another
    airport, in San Carlos, California, that was responsible for
    lead emissions lower than those attributed to HIO but had a
    higher ambient lead level than the SEA ascribed to HIO.
    Petitioners reason that this circumstance calls into question
    the accuracy of the SEA’s assessment of the ambient lead
    level at HIO. To the contrary, the study does not support
    Petitioners’ position because ambient lead levels are the
    result of emissions from all sources in a region. The non-
    airport lead sources near HIO were not the same as the non-
    airport lead sources near the other airport, and Petitioners do
    not contend otherwise.
    Petitioners also claim controversy exists because different
    analyses identified different levels of lead near HIO.
    Contrary to Petitioners’ argument, the analysis that indicated
    the highest levels of ambient lead was not the result of a
    difference of opinion but rather was the result of an error that
    was corrected in subsequent analyses. There was no
    “substantial dispute” about the SEA’s conclusion that
    ambient lead levels at HIO were well within the NAAQS.
    See Blue Mountains, 
    161 F.3d at 1212
    . Therefore, there was
    no controversy necessitating an EIS.
    C. Petitioners’ Arguments Related to the Airport and Airway
    Improvement Act
    The Airport and Airway Improvement Act requires that,
    before approving a project grant, the FAA must ensure that
    “the project is consistent with plans (existing at the time the
    project is approved) of public agencies authorized by the
    20                     BARNES V. FAA
    State in which the airport is located to plan for the
    development of the area surrounding the airport.” 
    49 U.S.C. § 47106
    (a)(1). In assessing the plans of the city of Hillsboro,
    the FONSI considered two city zoning ordinances that
    established an Airport Use Zone and an Airport Safety and
    Compatibility Overlay Zone. Petitioner Michelle Barnes
    succeeded in an effort to invalidate those ordinances in a state
    court lawsuit, arguing that the avigation easement they
    included was an unconstitutional taking and that the
    provisions governing one of the zones involved an
    impermissible delegation of legislative authority. Barnes v.
    City of Hillsboro, 
    243 P.3d 139
    , 141 (Or. Ct. App. 2010).
    The city indicated that it planned to resolve the zoning
    ordinances’ infirmities and reinstate the relevant provisions
    in substance. Accordingly, the zones represented the plans
    “of public agencies authorized by the State in which the
    airport is located,” 
    49 U.S.C. § 47106
    (a)(1), and it was not
    arbitrary or capricious for the FONSI to consider them.
    III.     Conclusion
    In adopting the SEA, issuing the FONSI, and concluding
    that the project at Hillsboro Airport complied with the
    requirements of the Airport and Airway Improvement Act,
    the FAA did not act in a manner that was arbitrary,
    capricious, an abuse of discretion, or otherwise not in
    accordance with law. The petition for review is denied.
    PETITION FOR REVIEW DENIED.
    

Document Info

Docket Number: 14-71180

Citation Numbers: 865 F.3d 1266, 47 Envtl. L. Rep. (Envtl. Law Inst.) 20098, 2017 WL 3297704, 84 ERC (BNA) 2229, 2017 U.S. App. LEXIS 14250

Judges: Thomas, Clifton, Nguyen

Filed Date: 8/3/2017

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (16)

sierra-club-a-california-non-profit-corporation-v-united-states-forest , 843 F.2d 1190 ( 1988 )

McKay v. Ingleson , 558 F.3d 888 ( 2009 )

pit-river-tribe-native-coalition-for-medicine-lake-highlands-defense-mount , 469 F.3d 768 ( 2006 )

Morongo Band of Mission Indians v. Federal Aviation ... , 161 F.3d 569 ( 1998 )

blue-mountains-biodiversity-project-blue-mountain-native-forest-alliance , 161 F.3d 1208 ( 1998 )

Barnes v. City of Hillsboro , 239 Or. App. 73 ( 2010 )

selkirk-conservation-alliance-a-non-profit-public-interest-group-sierra , 336 F.3d 944 ( 2003 )

native-ecosystems-council-v-united-states-forest-service-an-agency-of-the , 428 F.3d 1233 ( 2005 )

environmental-protection-information-center-a-california-nonprofit , 451 F.3d 1005 ( 2006 )

Oregon Natural Desert Ass'n v. Bureau of Land Management , 625 F.3d 1092 ( 2010 )

idaho-sporting-congress-and-american-wildlands-v-jack-ward-thomas-and , 137 F.3d 1146 ( 1998 )

arthur-s-west-an-individual-v-secretary-of-the-department-of , 206 F.3d 920 ( 2000 )

national-parks-conservation-association , 241 F.3d 722 ( 2001 )

Feldman v. Bomar , 518 F.3d 637 ( 2008 )

City of Dania Beach v. Federal Aviation Administration , 628 F.3d 581 ( 2010 )

Town of Cave Creek v. Federal Aviation Administration , 325 F.3d 320 ( 2003 )

View All Authorities »