Pge v. Lmic ( 2017 )


Menu:
  •                      FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    PORTLAND GENERAL ELECTRIC                        No. 16-35628
    COMPANY,
    Plaintiff-Appellee,                    D.C. No.
    3:16-cv-00495-HZ
    v.
    OPINION
    LIBERTY MUTUAL INSURANCE
    COMPANY; ZURICH AMERICAN
    INSURANCE COMPANY,
    Defendants-Appellants.
    Appeal from the United States District Court
    for the District of Oregon
    Marco A. Hernandez, District Judge, Presiding
    Argued and Submitted May 8, 2017
    Portland, Oregon
    Filed July 10, 2017
    Before: Jay S. Bybee and Andrew D. Hurwitz, Circuit
    Judges, and Jed S. Rakoff,* Senior District Judge.
    Opinion by Judge Rakoff
    *
    The Honorable Jed S. Rakoff, Senior United States District Judge
    for the Southern District of New York, sitting by designation.
    2                           PGE V. LMIC
    SUMMARY**
    Arbitration
    The panel vacated the district court’s judgment entering
    a preliminary injunction prohibiting sureties from pursuing
    claims against Portland General Electric Company (“PGE”)
    in arbitration and denying a mandatory stay of the judicial
    proceedings under § 3 of the Federal Arbitration Act, and
    remanded for further proceedings; and dismissed for lack of
    appellate jurisdiction the sureties’ appeal from the order
    denying their motion for a discretionary stay.
    The appeal involves the interplay of three related
    contracts: a Construction Contract entered by PGE and
    several contracting companies to build an Oregon power
    plant; a performance Bond in which appellants/sureties
    Liberty Mutual Insurance Company and Zurich American
    Insurance Company issued a bond to PGE as required by the
    Construction Contract; and a Guaranty of performance issued
    to PGE by its parent company, Abengoa S.A. The Guaranty
    provided that the parties submit any disputes to binding
    arbitration to be conducted by the International Chamber of
    Commerce (“ICC”) under its procedural rules and Oregon
    substantive law.
    PGE filed this diversity action against the sureties,
    alleging breach of the Bond and bad faith; and PGE sought a
    preliminary injunction prohibiting the sureties from
    arbitrating their claims against PGE.
    **
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    PGE V. LMIC                            3
    The panel held that the incorporation of the ICC Rules
    into an arbitration agreement constituted clear and
    unmistakable evidence of a delegation of gateway issues of
    arbitrability to the arbitrator.
    The panel rejected PGE’s contention that the ICC Rules
    did not govern the present dispute because the Bond lacked
    an arbitration clause. The panel held that the following were
    questions of the scope of the arbitration agreement in the
    Guaranty, and delegated to the arbitrators: whether Abengoa
    properly joined the sureties to the arbitration pursuant to the
    Guaranty and the ICC Rules; whether the sureties’ claim
    against PGE met the Guaranty’s test of “aris[ing] out of or in
    connection with an agreement with a subcontractor or [the]
    Guaranty,” and whether PGE had therefore agreed to arbitrate
    its disputes against the sureties. The panel concluded that the
    district court erred in enjoining the sureties from participating
    in the ICC arbitration, and preventing the arbitral tribunal
    from addressing the scope of the arbitration.
    COUNSEL
    Eric D. Miller (argued), Perkins Coie LLP, Seattle,
    Washington; David Bledsoe, Perkins Coie LLP, Portland,
    Oregon; for Plaintiff-Appellee.
    John Spencer Stewart (argued), Mario R. Nicholas, Thomas
    Ardell Larkin, and Jan D. Sokol, Stewart Sokol & Larkin
    LLC, Portland, Oregon, for Defendant-Appellants.
    Nathan D. O’Malley (argued) and Sara H. Kornblatt, Gibbs
    Giden Locher Turner Senet & Wittbrodt LLP, Los Angeles,
    California, for Amicus Curiae Abengoa.
    4                       PGE V. LMIC
    OPINION
    RAKOFF, Senior District Judge:
    If two parties enter a contract that both requires
    arbitration of their disputes and allows impleader of a third
    party, must a party that did not initiate the impleader arbitrate
    a dispute that arises out of the same transaction at issue in the
    arbitration with the impleaded third party? We hold, on the
    facts of this case, that this question is really a question about
    the scope of the arbitration clause for the arbitrator to decide.
    Since, instead, the district court undertook to decide that
    question, we vacate and remand.
    BACKGROUND
    This appeal concerns the interplay of three related
    contracts. In the first (the “Construction Contract”), entered
    into in June 2013, appellee Portland General Electric
    Company (“PGE”) hired several related contracting
    companies (collectively, the “Contractor”) to build an Oregon
    power plant. The Construction Contract allows PGE to
    terminate the agreement upon the Contractor’s default. A
    “Disputes” provision requires the parties to attempt to
    mediate any disputes, but if mediation fails, “each Party shall
    have the right to take whatever legal actions that they may
    choose.” A “Choice of Law; Jurisdiction” provision states
    that the agreement is governed by Oregon substantive law
    and that the parties “consent to the exclusive jurisdiction of
    any U.S. federal court with jurisdiction over Oregon.” The
    PGE V. LMIC                                  5
    contract passingly mentions arbitration twice, but does not
    require it.1
    The Construction Contract requires the Contractor to
    obtain a performance bond. Appellants Liberty Mutual
    Insurance Company and Zurich American Insurance
    Company (collectively, the “Sureties”) issued the required
    bond (the “Bond”) to PGE. The Bond incorporates the
    Construction Contract by reference and states that “[a]ny
    proceeding, legal or equitable, under this Bond may be
    instituted in any court of competent jurisdiction in the
    location in which the work or part of the work is located, and
    in any court(s) to which the Parties to the Construction
    Contract have agreed will have jurisdiction over disputes
    thereunder.” The Bond is silent as to arbitration.
    The Construction Contract also requires the Contractor to
    obtain a guaranty of performance from a parent company,
    Abengoa S.A. (“Abengoa”). Abengoa issued a guaranty to
    PGE (the “Guaranty”), in which both parties consented to
    submit any disputes “in connection with this Guaranty” to
    binding arbitration. Of particular relevance here, the
    Guaranty specifies that the arbitration is to be conducted by
    the International Chamber of Commerce (“ICC”) under its
    procedural rules and Oregon substantive law, and that “[o]nce
    the arbitration proceeding is commenced hereunder, either
    1
    A “Responsibilities of Contractor” provision gives PGE the right to
    audit the Contractor; PGE must “treat such audit data as confidential, but
    shall not be precluded from using such audit data in any legal proceedings
    (including without limitation mediation or arbitration) arising under this
    Agreement.” A “Costs and Attorney Fees” provision states: “In any
    litigation arising out of this Agreement, including arbitration and any case
    or proceeding under the Bankruptcy Code or any successor statute, the
    prevailing Party shall be entitled to recover [reasonable expenses].”
    6                              PGE V. LMIC
    Party may implead any other person or entity (with such
    person or entity’s consent) in, and/or raise any claim against,
    any other person or entity provided such claim arises out of
    or in connection with an agreement with a Subcontractor or
    this Guaranty.”
    On December 18, 2015, PGE declared the Contractor in
    default and terminated the Construction Contract. Abengoa
    filed a Request for Arbitration with the ICC on December 31,
    2015, naming PGE as “respondent” and the Contractor as an
    “impleaded” party. Abengoa contended that the Contractor
    had not defaulted, that PGE’s termination of the Construction
    Contract was wrongful, and that Abengoa owed PGE nothing
    under the Guaranty. The Contractor sought similar relief.
    On March 2, 2016, Abengoa filed a Request for Joinder
    in the arbitration, seeking to include the Sureties, who, under
    the Bond, would be liable to PGE if the Contractor had
    defaulted. Abengoa invoked both the impleader provision in
    the Guaranty and Article 7 of the ICC Rules.2 Abengoa also
    sought a declaration that the Sureties owed PGE nothing
    under the Bond. The Sureties consented to the arbitration and
    2
    Article 7, titled “Joinder of Additional Parties,” states in relevant
    part:
    A party wishing to join an additional party to the
    arbitration shall submit its request for arbitration
    against the additional party (the “Request for Joinder”)
    to the Secretariat. . . . Any such joinder shall be subject
    to the provisions of Articles 6(3)–6(7) [governing the
    interpretation of arbitration agreements] and 9
    [governing claims arising out of more than one
    contract].
    ICC Rules, Article 7(1).
    PGE V. LMIC                            7
    sought similar relief. On March 9, 2016, the Sureties sent
    PGE a letter denying liability under the Bond.
    Two weeks later, on March 23, 2016, PGE filed this
    diversity action in the District of Oregon against the Sureties,
    alleging breach of the Bond and bad faith. PGE sought a
    preliminary injunction prohibiting the Sureties from
    arbitrating their claims against PGE, claiming that Abengoa
    had improperly impleaded the Sureties. PGE also filed a
    Jurisdictional Objection before the ICC, arguing that “the
    entire arbitration is an improper and collusive effort
    orchestrated by Abengoa and its subsidiaries to drag into
    international arbitration claims that [PGE, the Sureties, and
    the Contractor] have agreed to litigate before the Oregon
    courts.”
    In the district court, the Sureties opposed the motion to
    enjoin arbitration, arguing, inter alia, that “[b]y virtue of
    PGE’s selection of the ICC Rules, it has expressly agreed that
    the arbitrator shall decide questions of arbitrability,” and that
    it is up to the ICC tribunal to decide whether Abengoa validly
    joined the Sureties and for what purposes. The Sureties then
    moved to stay the litigation pending the resolution of the ICC
    arbitration, invoking both the mandatory stay provision of the
    Federal Arbitration Act (“FAA”), 
    9 U.S.C. § 3
    , and the
    court’s inherent authority to manage its docket.
    The district court refused to stay the litigation and granted
    the preliminary injunction, finding that “the parties never
    agreed to arbitrate this dispute.” The Sureties timely
    appealed. This Court granted a stay of the district court
    proceedings pending appeal.
    8                       PGE V. LMIC
    DISCUSSION
    PGE does not dispute the validity of the arbitration clause
    in the Guaranty, but rather only its scope—PGE claims that
    the impleader provision and its acceptance of the ICC
    procedural rules do not extend to the resolution of its dispute
    with the impleaded Sureties. We review de novo the district
    court’s conclusion that it, rather than an arbitrator, should
    decide arbitrability. Momot v. Mastro, 
    652 F.3d 982
    , 986
    (9th Cir. 2011).
    Generally, “the [FAA] establishes that, as a matter of
    federal law, any doubts concerning the scope of arbitrable
    issues should be resolved in favor of arbitration.” Moses H.
    Cone Mem’l Hosp. v. Mercury Constr. Corp., 
    460 U.S. 1
    ,
    24–25 (1983). Certain issues, however, are presumptively
    reserved for the court. Howsam v. Dean Witter Reynolds,
    Inc., 
    537 U.S. 79
    , 83 (2002). These include “gateway”
    questions of arbitrability, such as “whether the parties have a
    valid arbitration agreement or are bound by a given
    arbitration clause, and whether an arbitration clause in a
    concededly binding contract applies to a given controversy.”
    Momot, 
    652 F.3d at 987
    .
    However, parties may delegate the adjudication of
    gateway issues to the arbitrator if they “clearly and
    unmistakably” agree to do so. Howsam, 
    537 U.S. at
    83–84
    (citation omitted). We have found such delegation when the
    parties have incorporated by reference the rules of the
    American Arbitration Association (“AAA”), which state in
    relevant part that the “arbitrator shall have the power to rule
    on his or her own jurisdiction, including any objections with
    respect to the . . . validity of the arbitration agreement.”
    Brennan v. Opus Bank, 
    796 F.3d 1125
    , 1130 (9th Cir. 2015)
    PGE V. LMIC                           9
    (alteration in original). Although we have not opined on
    whether the incorporation of the rules of the ICC into an
    arbitration agreement also constitutes clear and unmistakable
    evidence of a delegation of gateway issues to the arbitrator,
    two of our sister circuits have held that the answer is yes. See
    Shaw Grp. Inc. v. Triplefine Int’l Corp., 
    322 F.3d 115
    , 118
    (2d Cir. 2003); Apollo Comput., Inc. v. Berg, 
    886 F.2d 469
    ,
    473–74 (1st Cir. 1989).
    Because of the similarity between the ICC Rules and
    those of the AAA, we now join those circuits. In relevant
    part, the ICC Rules provide:
    [I]f any party raises one or more pleas
    concerning the existence, validity or scope of
    the arbitration agreement or concerning
    whether all of the claims made in the
    arbitration may be determined together in a
    single arbitration, the arbitration shall proceed
    and any question of jurisdiction or of whether
    the claims may be determined together in that
    arbitration shall be decided directly by the
    arbitral tribunal . . . .
    ICC Rules, Article 6(3). This language makes clear that the
    arbitrators are vested with the authority to determine
    questions of arbitrability.
    PGE nonetheless contends that the ICC Rules do not
    govern the present dispute because the Bond lacks an
    arbitration clause. Because PGE and the Sureties never
    expressly agreed between themselves to delegate issues of
    arbitrability to the tribunal, PGE argues, a court must decide
    10                           PGE V. LMIC
    whether its dispute with the Sureties is subject to ICC
    arbitration.
    We disagree. Whether Abengoa properly joined the
    Sureties to the arbitration pursuant to the Guaranty and the
    ICC Rules, whether the Sureties’ claim against PGE meets
    the Guaranty’s test of “aris[ing] out of or in connection with
    an agreement with a Subcontractor or [the] Guaranty,”3 and
    3
    A few circuits have held, or adopted variants of the rule, that “this
    delegation applies only to claims that are at least arguably covered by the
    agreement [to arbitrate].” Turi v. Main St. Adoption Servs., LLP, 
    633 F.3d 496
    , 507, 511 (6th Cir. 2011); see Douglas v. Regions Bank, 
    757 F.3d 460
    ,
    464 (5th Cir. 2014); Qualcomm Inc. v. Nokia Corp., 
    466 F.3d 1366
    , 1371
    (Fed. Cir. 2006). But this approach is not universally followed. See
    Belnap v. Iasis Healthcare, 
    844 F.3d 1272
    , 1292 (10th Cir. 2017); see also
    
    id. at 1290
     (determining that “a majority of our sister circuits” reject any
    variant of the “arguably covered” approach). Moreover, one of our own
    opinions can be read to have rejected it, although it might have been in
    dicta by which we would not be bound. See Oracle Am., Inc. v. Myriad
    Grp. A.G., 
    724 F.3d 1069
    , 1076 (9th Cir. 2013).
    We need not take a side in this circuit split, or determine if we already
    have, because the Sureties’ claim against PGE is, at least, “arguably
    covered” by the Construction Contract’s arbitrability clause. See Agere
    Sys., Inc. v. Samsung Elecs. Co., 
    560 F.3d 337
    , 340 (5th Cir. 2009)
    (declining to take a side for the same reason). The liability of both the
    Sureties and Abengoa to PGE turns on the same issue: whether the
    Contractor defaulted under the Construction Contract. In addition, the
    Sureties and Abengoa have signed an indemnification agreement between
    themselves. Cf. Mundi v. Union Sec. Life Ins. Co., 
    555 F.3d 1042
    , 1046
    (9th Cir. 2009) (noting that nonsignatory to arbitration agreement may
    compel signatory to arbitrate if the dispute is “intertwined with the
    contract providing for arbitration” and there is a sufficiently close
    “relationship among the parties” (quoting Sokol Holdings, Inc. v. BMB
    Munai, Inc., 
    542 F.3d 354
    , 359–61 (2d Cir. 2008))). It is at least arguable
    that the Sureties’ claim against PGE “arises out of or in connection with
    an agreement with a Subcontractor or [the] Guaranty,” and regardless of
    PGE V. LMIC                                  11
    whether PGE has therefore agreed to arbitrate its dispute
    against the Sureties, are questions of the scope of the
    arbitration agreement in the Guaranty, delegated to the
    arbitrators.
    The district court thus erred in enjoining the Sureties from
    participating in the ICC arbitration and denying at least a
    temporary stay of the litigation under the FAA, preventing the
    arbitral tribunal from addressing the scope of the arbitration.
    If the tribunal concludes that the arbitration agreement in the
    Guaranty extends to PGE’s dispute with the Sureties, the
    litigation should be stayed under the FAA pending the
    outcome of the arbitration or dismissed. On the other hand,
    if the tribunal concludes that PGE is not required under the
    Guaranty to arbitrate its dispute with the Sureties, the district
    court can then consider whether the litigation should proceed
    or whether a discretionary stay is appropriate pending the
    outcome of the arbitration. See Moses H. Cone, 
    460 U.S. at
    20 n.23.
    CONCLUSION
    For the foregoing reasons, the judgment of the district
    court entering a preliminary injunction prohibiting the
    Sureties from pursuing claims against PGE in arbitration and
    denying a mandatory stay of the judicial proceedings under
    § 3 of the FAA is VACATED and the matter is
    REMANDED for further proceedings consistent with this
    opinion. The Sureties’ appeal from the order denying their
    motion for a discretionary stay is DISMISSED for lack of
    which side of the circuit split the Ninth Circuit falls, it is therefore up to
    the ICC to decide whether the Sureties’ claim falls within the scope of the
    arbitration clause in the first instance.
    12                    PGE V. LMIC
    appellate jurisdiction. See Reid v. Doe Run Res. Corp.,
    
    701 F.3d 840
    , 844–45 (8th Cir. 2012); Invista S.A.R.L. v.
    Rhodia, S.A., 
    625 F.3d 75
    , 87–88 (3d Cir. 2010). Each party
    shall bear its own costs on appeal.