Pacific Coast Federation v. U.S. Dept. of the Interior ( 2016 )


Menu:
  •                                                                             FILED
    NOT FOR PUBLICATION                              MAR 28 2016
    MOLLY C. DWYER, CLERK
    UNITED STATES COURT OF APPEALS                        U.S. COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    PACIFIC COAST FEDERATION OF                      No. 14-15514
    FISHERMEN’S ASSOCIATIONS; et al.,
    D.C. No. 1:12-cv-01303-LJO-MJS
    Plaintiffs - Appellants,
    v.                                              MEMORANDUM*
    UNITED STATES DEPARTMENT OF
    THE INTERIOR; et al.,
    Defendants - Appellees,
    and
    WESTLANDS WATER DISTRICT; et al.,
    Intervenor-Defendants -
    Appellees.
    Appeal from the United States District Court
    for the Eastern District of California
    Lawrence J. O’Neill, District Judge, Presiding
    Argued and Submitted February 9, 2016
    San Francisco, California
    *
    This disposition is not appropriate for publication and is not precedent
    except as provided by 9th Cir. R. 36-3.
    Submission Withdrawn February 9, 2016
    Resubmitted March 28, 2016**
    Before: SILVERMAN, FISHER, and TALLMAN, Circuit Judges.
    Pacific Coast Federation of Fishermen’s Associations, Inc., and San
    Francisco Crab Boat Owners Association, Inc. (“plaintiffs”) appeal the district
    court’s partial dismissal and partial summary judgment of their action under the
    National Environmental Policy Act (“NEPA”) against the United States
    Department of the Interior and the United States Bureau of Reclamation. We have
    jurisdiction under 
    28 U.S.C. § 1291
    . We affirm in part, reverse in part, and
    remand.
    Prior to approving eight interim two-year contracts for the delivery of water
    from the Central Valley Project to California water districts, Reclamation issued an
    environmental assessment (“EA”) and a finding of no significant impact
    (“FONSI”). Plaintiffs seek declaratory and injunctive relief on the basis of alleged
    violations of NEPA in (1) an inadequate EA and FONSI and (2) failure to prepare
    an environmental impact statement (“EIS”) for the interim contracts. The district
    court dismissed plaintiffs’ claims that an EIS was required and that the EA’s “no
    **
    This case is resubmitted the date the memorandum is filed.
    2
    action” alternative was deficient, and it granted summary judgment in favor of
    defendants on the remaining challenges to the EA.
    Even though the two-year contracts expired on February 28, 2014, this
    appeal is not moot. The short duration and serial nature of Reclamation’s interim
    water contracts place plaintiffs’ claims within the mootness exception for disputes
    capable of repetition yet evading review. See A.D. ex rel. L.D. v. Haw. Dep’t of
    Educ., 
    727 F.3d 911
    , 914 (9th Cir. 2013).
    We review de novo a dismissal for failure to state a claim under Fed. R. Civ.
    P. 12(b)(6). Chubb Custom Ins. Co. v. Space Sys./Loral, Inc., 
    710 F.3d 946
    , 956
    (9th Cir. 2013). We also review de novo the district court’s ruling on summary
    judgment. San Luis & Delta-Mendota Water Auth. v. Jewell, 
    747 F.3d 581
    , 601
    (9th Cir. 2014), cert. denied, 
    134 S. Ct. 948
     & 950 (2015). Claims under NEPA
    are reviewed under the standards of the Administrative Procedure Act, which
    provides that an agency action must be upheld unless it is “‘arbitrary, capricious,
    an abuse of discretion, or otherwise not in accordance with law.’” 
    Id.
     (quoting 
    5 U.S.C. § 706
    (2)(A)).
    I. “No Action” Alternative
    3
    The EA’s “no action” alternative complied with NEPA even though it
    assumed continued interim contract renewal. A “no action” alternative is
    “meaningless” if it assumes the existence of the very plan being proposed. Friends
    of Yosemite Valley v. Kempthorne, 
    520 F.3d 1024
    , 1038 (9th Cir. 2008).
    Nonetheless, when an agency action is mandatory, the “no action” alternative is
    properly defined as the carrying out of that action. Dep’t of Transp. v. Pub.
    Citizen, 
    541 U.S. 752
    , 769 (2004) (holding that Federal Motor Carrier Safety
    Administration was not required to produce an EIS due to the environmental
    impact of an action it could not refuse to perform); Am. Rivers v. Fed. Energy Reg.
    Comm’n, 
    201 F.3d 1186
    , 1199-1201 (9th Cir. 1999) (holding that EIS for the
    Federal Energy Regulatory Commission’s reissuance of licenses for continued
    operation of two hydroelectric power facilities properly identified the “no action”
    alternative as continued operation under the terms of the expired original licenses,
    as required by the Federal Power Act). The “no action” alternative may also be
    defined as the status quo; that is, no change from a current management direction,
    or the continuation of a historical practice or use. Ass’n of Pub. Agency
    Customers, Inc. v. Bonneville Power Admin., 
    126 F.3d 1158
    , 1188 (9th Cir. 1997)
    (holding that the EIS for the Bonneville Power Administration’s renegotiation of
    4
    long term power sales contracts properly defined the “no action” alternative as the
    status quo of continuing the existing contracts).
    We do not agree with the district court that the Central Valley Project
    Improvement Act (“CVPIA”), a part of the Reclamation Projects Authorization
    and Adjustment Act of 1992, required Reclamation to enter into the interim
    contracts. The CVPIA requires “appropriate environmental review,” including the
    preparation of a programmatic EIS (“PEIS”), before Reclamation is authorized to
    renew an existing long-term water service contract. CVPIA § 3404(c)(1). After
    the completion of the PEIS, Reclamation “shall, upon request, renew any existing
    long-term repayment or water service contract for the delivery of water from the
    Central Valley Project for a period of twenty-five years.” Id. Prior to the
    completion of the PEIS, Reclamation “may” renew water service contracts for
    interim three- or two-year periods. Id. As the district court acknowledged,
    normally, when “may” and “shall” are used in the same statute, the “‘inference is
    that each is being used in its ordinary sense—the one being permissive, the other
    mandatory.’” Ctr. for Biological Diversity v. U.S. Fish & Wildlife Serv., 
    450 F.3d 930
    , 935 (9th Cir. 2006) (quoting Haynes v. United States, 
    891 F.2d 235
    , 239-40
    (9th Cir. 1989)) (interpreting Endangered Species Act).
    5
    Nonetheless,, the status quo was the historical use of Central Valley Project
    water by the water districts. See Ass’n of Pub. Agency Customers, Inc., 
    126 F.3d at 1188
    . The EA’s “no action” alternative therefore complied with NEPA.
    II. Statement of Purpose and Need
    The EA’s statement of purpose and need did not unreasonably narrow
    Reclamation’s consideration of alternatives. See Alaska Survival v. Surface
    Transp. Bd., 
    705 F.3d 1073
    , 1084 (9th Cir. 2013). The statement did not assume
    that contract quantities would remain the same, and it was not an abuse of
    discretion. See 
    id.
    III. Reduction in Water Quantity
    Reclamation’s decision not to give full and meaningful consideration to the
    alternative of a reduction in maximum interim contract water quantities was an
    abuse of discretion, and the agency did not adequately explain why it eliminated
    this alternative from detailed study. See Te-Moak Tribe of W. Shoshone of Nev. v.
    U.S. Dep’t in Interior, 
    608 F.3d 592
    , 602 (9th Cir. 2010); Native Ecosys. Council
    v. U.S. Forest Serv., 
    428 F.3d 1233
    , 1245 (9th Cir. 2005). The four reasons set
    forth in the EA do not establish the non-viability of the alternative of maximum
    water quantity reduction. See W. Watersheds Project v. Abbey, 
    719 F.3d 1035
    ,
    6
    1050 (9th Cir. 2013) (holding that existence of viable but unexamined alternative
    renders EA inadequate).
    The first reason given by Reclamation was that the Reclamation Project Act
    mandates renewal of existing contract quantities when beneficially used. See 43
    U.S.C. § 485h-1(1) & (4). The EA stated that the water districts had complied with
    contract terms, and, according to water needs assessments performed by
    Reclamation, each water district’s needs equaled or exceeded the current total
    contract quantity. Plaintiffs exhausted administrative remedies as to their
    argument that Reclamation did not know whether existing water quantities were
    “beneficially used” because Reclamation did not conduct a proper water needs
    assessment, as contractually required, and Reclamation’s 2006 assessment was
    inadequate because it was prepared with data from 1999 that predated a land
    retirement project. See Barnes v. U.S. Dep’t of Transp., 
    655 F.3d 1124
    , 1132 (9th
    Cir. 2011) (holding that issue was exhausted when agency had independent
    knowledge of EA flaw); Lands Council v. McNair, 
    629 F.3d 1070
    , 1076 (9th Cir.
    2010) (holding that issue is exhausted if agency is provided sufficient information
    to give it a chance to bring its expertise to bear to resolve the claim). As plaintiffs
    argue, Reclamation acted unreasonably by relying on stale water needs data. See
    7
    W. Watersheds Project, 719 F.3d at 1052 (holding that “an agency errs when it
    relies on old data without showing that the data remain accurate”).
    Reclamation’s second reason for concluding that consideration of a
    reduction in interim contract water quantities was not warranted was that the
    Central Valley Project-wide PEIS for long-term contract renewal selected a
    preferred alternative of renewal “for the full contract quantities.” Additionally, the
    PEIS took into account the balancing requirements of the CVPIA, which provides,
    among other things, for the weighing of fish, wildlife, and habitat restoration goals.
    The PEIS did not, however, address site-specific impacts of individual contracts.
    See W. Watersheds Project, 719 F.3d at 1050-51 (holding that when modification
    of grazing practices was not considered at programmatic level, it must be given
    hard and careful look at site-specific level). The government’s position that the
    consideration of reduced-quantity alternatives should be required only with respect
    to “long-term contract renewals” is unreasonable under the circumstances
    presented here, involving an ongoing – and hence long-term – series of interim
    renewals.
    Reclamation’s third reason was that a shortage provision in the interim
    contracts provided it with a mechanism for annual adjustments in water supplies.
    As plaintiffs argue, however, the existence of a mechanism for adjusting water
    8
    quantities after contract approval did not relieve Reclamation of its obligation to
    consider a reduction in quantities prior to contract approval. See id. at 1050.
    Reclamation’s fourth reason was that “retaining the full historic water
    quantities under contract provides the contractors with assurance the water would
    be made available in wetter years and is necessary to support investments for local
    storage, water conservation improvements and capital repairs.” This reasoning in
    large part reflects a policy decision to promote the economic security of
    agricultural users, rather than an explanation of why reducing maximum contract
    quantities was so infeasible as to preclude study of its environmental impacts. See
    id. Moreover, given the shortage provisions in the interim contracts and recent
    drought conditions, the water districts have not been able to rely on delivery of
    consistent quantities.
    We therefore reverse as to the district court’s grant of summary judgment on
    plaintiffs’ claim that the EA was inadequate because it did not give full and
    meaningful consideration to the alternative of a reduction in maximum water
    quantities. See id.
    IV. Geographic Scope
    Plaintiffs contend that the EA’s geographic scope was improperly limited to
    the delivery areas and should also have considered the effects, including
    9
    cumulative effects, of interim contract renewal on the California River Delta, the
    source of the water, and on the Delta’s fish and other wildlife. See Save Our
    Sonoran, Inc. v. Flowers, 
    408 F.3d 1113
    , 1122 (9th Cir. 2004) (holding that agency
    must analyze all environmental consequences of action). This contention lacks
    merit because the EA was tiered off of the PEIS, which addressed Central Valley
    Project-wide effects of long-term contract renewal. See 
    40 C.F.R. § 1508.28
    (describing tiering). In light of Reclamation’s obligation to conduct a more
    comprehensive analysis in the PEIS, it would be impractical to require the agency
    to trace the incremental effects of each two-year water service contract on the Delta
    and all Central Valley Project waters. See Friends of the Wild Swan v. Weber, 
    767 F.3d 936
    , 943 (9th Cir. 2014) (stating that agency must balance need for
    comprehensive analysis against considerations of practicality).
    V. Impacts on Listed Species and Cumulative Impacts
    Plaintiffs waived their argument that the EA’s analysis of the giant garter
    snake and the California least tern impermissibly equated a finding of no jeopardy
    under the Endangered Species Act with a finding of no significant impact under
    NEPA. See Lands Council, 
    629 F.3d at 1076
    . Impacts on salmonids and green
    sturgeon, as well as cumulative impacts related to drainage and selenium, were
    more appropriately addressed in the PEIS and the San Luis Drainage Feature Re-
    10
    Evaluation Final EIS, rather than the EA for interim contract renewal. See Friends
    of the Wild Swan, 767 F.3d at 943.
    We affirm the district court’s judgment in part. We reverse in part and
    remand with instructions for the district court to vacate its grant of summary
    judgment in favor of defendants on plaintiffs’ claim that the EA was inadequate
    because it did not give full and meaningful consideration to the alternative of a
    reduction in maximum water quantities. On remand, the district court shall direct
    Reclamation consider such an alternative in any future EA for an interim contract
    renewal. In satisfying this duty, Reclamation may rely upon any water needs
    assessment for which the data remain accurate. See W. Watersheds Project, 719
    F.3d at 1052.
    Each party shall bear its own costs.
    AFFIRMED in part, REVERSED in part, and REMANDED.
    11