Sierra Pacific Power Co. v. Hartford Steam Boiler Inspection & Insurance ( 2012 )


Menu:
  •                                                                            FILED
    NOT FOR PUBLICATION                             JUL 27 2012
    MOLLY C. DWYER, CLERK
    UNITED STATES COURT OF APPEALS                       U .S. C O U R T OF APPE ALS
    FOR THE NINTH CIRCUIT
    SIERRA PACIFIC POWER COMPANY,                    No. 09-16662
    Plaintiff - Appellant,             D.C. No. 3:04-cv-00034-LRH-
    RAM
    v.
    HARTFORD STEAM BOILER                            MEMORANDUM *
    INSPECTION & INSURANCE CO.;
    ZURICH AMERICAN INSURANCE
    COMPANY,
    Defendants - Appellees.
    SIERRA PACIFIC POWER COMPANY,                    No. 09-16802
    Plaintiff - Appellee,              D.C. No. 3:04-cv-00034-LRH-
    RAM
    v.
    HARTFORD STEAM BOILER
    INSPECTION & INSURANCE CO.;
    ZURICH AMERICAN INSURANCE
    COMPANY,
    Defendants - Appellants.
    *
    This disposition is not appropriate for publication and is not precedent
    except as provided by 9th Cir. R. 36-3.
    Appeal from the United States District Court
    for the District of Nevada
    Larry R. Hicks, District Judge, Presiding
    Argued and Submitted November 2, 2010
    Submission Withdrawn, November 19, 2010
    Resubmitted July 25, 2012
    San Francisco, California
    Before: GOULD and CALLAHAN, Circuit Judges, and KORMAN, Senior District
    Judge.**
    Sierra Pacific Power Co. (“Sierra”) operates power generation stations in
    Nevada and California. Insurers Hartford Steam Boiler Inspection & Insurance
    Co. (“Hartford”) and Zurich American Insurance Co. (“Zurich”) (together
    “Insurers”) insured Sierra’s facilities, including the Farad Dam on the Truckee
    River in California, with $200 million in total coverage. The Farad Dam was
    completely destroyed by a flood in 1997, and Sierra filed a claim for the damage
    with the Insurers. A dispute arose over the value of the dam, and whether Sierra
    could recover replacement cost of the dam or only actual cash value since the dam
    had not yet been rebuilt. Following bench trial, the district court concluded that
    Sierra was entitled to the dam’s actual cash value of $1,261,200, but that Sierra
    could recover replacement cost if the dam was actually rebuilt within three years
    **
    The Honorable Edward R. Korman, Senior District Judge for the U.S.
    District Court for Eastern New York, sitting by designation.
    -2-
    from the court’s ruling. The court determined that the replacement cost of the dam
    was $19,800,000. Sierra appeals the trial court’s ruling that the actual cash value
    (“ACV”) of the dam is $1,261,200. The Insurers appeal the rulings that (1) Sierra
    can recover $4 million it spent so far in preparation for replacing the dam, (2) the
    replacement cost available to Sierra includes costs for building ordinance changes,
    and (3) Sierra has three years to replace the dam and still recover the replacement
    cost of the dam.
    1.    Choice of Laws
    The district court held that Nevada law applies to this appeal, but in a later
    ruling indicated it may have reason to reconsider its decision. Ultimately, the
    district court found no difference between California and Nevada law on the issues
    in dispute, and did not disturb its holding that Nevada law applies. Sierra argues
    that California law applies, and the Insurers argue that Nevada law applies.1
    We review a district court’s choice of law de novo. Jorgensen v. Cassiday,
    
    320 F.3d 906
    , 913 (9th Cir. 2003). “A federal court sitting in diversity must apply
    the forum state’s choice of law rules.” 
    Id.
     (citing Klaxon Co. v. Stentor Elec. Mfg.
    Co., 
    313 U.S. 487
     (1941)). Nevada “has adopted the substantial relationship test to
    resolve conflict-of-law questions.” Williams v. United Servs. Auto. Ass’n, 
    849 P.2d 1
    We note that the Insurers argued below that California law applied.
    -3-
    265, 266 (Nev. 1993). The state whose law the court applies “must have a
    substantial relationship with the transaction; and the transaction must not violate a
    strong public policy of Nevada.” 
    Id.
     The factors Nevada courts use to evaluate the
    substantial relationship include, 1) where the contract was formed, 2) where the
    negotiations for the contract took place, 3) the place of performance, 4) the
    location of the subject matter of the contract, and 5) the residence and place of
    business of the parties. Sotirakis v. United Servs. Auto. Ass’n, 
    787 P.2d 788
    , 790
    (Nev. 1990). The most significant of these factors in an insurance contract is the
    location of the insured risk. Williams v. United Servs. Auto. Ass’n, 849 P.2d at
    266-67.
    The most significant factor favors application of California law because the
    Farad Dam, the insured risk in question, was located in California. The remaining
    factors do not clearly favor one state or another. Therefore, we conclude
    California law should apply to this dispute.
    2.    Actual Cash Value of the Farad Dam
    The district court’s interpretation of an insurance contract, including whether
    a contract term is ambiguous, is reviewed de novo. Conrad v. Ace Prop. & Cas.
    Ins. Co., 
    532 F.3d 1000
    , 1004 (9th Cir. 2008). The question of what definition of
    actual cash value (“ACV”) should be used requires interpretation of the contract,
    -4-
    and therefore is reviewed de novo. The district court’s factual findings after
    examining extrinsic evidence and a bench trial, including the court’s finding
    regarding the calculation of the ACV of the dam, are reviewed under the clearly
    erroneous standard. DP Aviation v. Smiths Indus. Aerospace and Def. Sys., Ltd.,
    
    268 F.3d 829
    , 836 (9th Cir. 2001).
    A.    Method of Calculating ACV
    Under California law, ACV means fair market value (“FMV”). Jefferson
    Ins. Co. v. Super. Ct. (May), 
    3 Cal. 3d 398
    , 402 (1970). FMV is most commonly
    determined “by way of market data on sales of comparable property.”
    Redevelopment Agency of Long Beach v. First Christian Church of Long Beach,
    
    189 Cal. Rptr. 749
    , 753 (Cal. Ct. App. 1983) (disapproved of on other grounds by
    Los Angeles County Metro. Transp. Auth. v. Continental Dev. Corp., 
    16 Cal. 4th 694
    , 720 (1997)). In cases where there is no relevant market, however, the FMV
    may be “determined by any method of valuation that is just and equitable.” 
    Id.
    (quoting Cal. Code Civ. Proc. § 1263.320(b)). Specifically, “[r]ecognized
    alternatives to the market data approach to valuation are reproduction or
    replacement costs less depreciation or obsolescence.” Id. (citing 
    Cal. Evid. Code § 820
    ).
    -5-
    Moreover, California courts establish that “[i]f [Insurers] want to determine
    ‘actual cash value’ on the basis of replacement cost less depreciation all [they]
    ha[ve] to do is say so in the policy . . . . This can be accomplished by using words
    such as ‘actual cash value, with proper deduction for depreciation.’” Cheeks v.
    Cal. Fair Plan Ass’n, 
    71 Cal. Rptr. 2d 568
    , 572 n.5 (Cal. Ct. App. 1998) (quoting
    Hughes v. Potomac Ins. Co., 
    18 Cal. Rptr. 650
    , 658 (Cal. Ct. App. 1962))
    (emphasis added). The policy provision at issue here, the valuation clause,
    contains exactly that language: “actual cash value (with proper deduction for
    depreciation) of the property destroyed.”
    Sierra contends that the dam’s ACV should be calculated as the full
    replacement cost without any depreciation. None of the cases it cites supports that
    proposition, however, as they all included deductions for depreciation. See Leslie
    Salt Co. v. St. Paul Mercury Ins. Co., 
    637 F.2d 657
    , 660 (9th Cir. 1981) (“the
    actual cash value of the property damaged . . . shall be . . . ascertained according to
    such actual cash value with proper deduction for depreciation”); Redevelopment
    Agency of Long Beach v. First Christian Church of Long Beach, 
    189 Cal. Rptr. at 753
     (“[r]ecognized alternatives to the market data approach to valuation are
    reproduction or replacement costs less depreciation or obsolescence.”) (emphasis
    added). Accordingly, the ACV for the Farad Dam, a structure without a sales
    -6-
    market, is determined using replacement cost reduced by the appropriate
    depreciation.
    Although the district court did not explain in its final ruling the method by
    which it calculated the ACV of the dam, its reasoning may be gleaned from the
    record. In its ruling on Sierra’s motion for reconsideration, the court explained
    “the most persuasive evidence” it considered “concerning the dam’s actual cash
    value is a letter in which Sierra’s insurance broker stated to Sierra’s claims
    manager, ‘We are only agreeing that the [actual cash value] is $1,261,200 and
    nothing else.’” The court also stated “[o]ther evidence pertinent to the court’s
    decision includes an email from Sierra’s broker [ ] agreeing to apply Hartford and
    Zurich’s depreciation factors to the dam to reach an actual cash value of
    $1,261,200, subject to Sierra’s claim’s manager’s review.” But neither of these
    documents reflects Sierra’s agreement to the ACV. Rather, they represent Sierra’s
    insurance broker’s recommendation to Sierra as to the ACV.
    Although the district court correctly announced that it would base ACV on
    replacement cost of the dam less depreciation, it arrived at an amount for the dam’s
    ACV, $1,261,200, which is not related to the figure it found as the replacement
    cost. The district court relied on its view that Sierra and the Insurers had agreed on
    the value of $1,261,200 as the ACV, but the court explicitly found that the parties
    -7-
    did not agree on that number, or any other number, as the ACV for the dam. As
    such, the district court’s determination of ACV was clearly erroneous and must be
    vacated.
    B.     Calculation of Replacement Cost—Effect of Building Ordinances
    A primary issue in this case is whether increased costs of repair are
    effectively excluded by the policy’s Building Ordinance or Law Exclusion. The
    district court ruled that “replacement cost coverage of the dam includes design
    fees, permitting fees and other regulatory costs necessary to rebuild the dam.” The
    court also ruled that “[t]he coverage available to Sierra included the increased costs
    of construction based on intervening changes in the law.”
    The relevant exclusion in the policy states, in pertinent part, “[t]his policy
    does not insure loss or damage caused by or resulting from . . . any increase in the
    loss due to any ordinance, law or regulation, rule or ruling restricting or affecting
    repair, alteration, use, operation, construction or installation . . . .” The Ninth
    Circuit has not addressed whether such a building ordinance or law exclusion is
    effective to limit the coverage for an insured structure to rebuilding the structure
    without costs for complying with any intervening building codes.
    -8-
    Case law from California appears to be split on the issue.2 Compare Fire
    Ins. Exch. v. Super. Ct. (Altman), 
    10 Cal. Rptr. 3d 617
    , 632-36 (Cal. Ct. App.
    2004) (finding the exclusion only excludes damage caused by a building
    ordinance, but not the increased replacement costs due to a building ordinance
    where loss itself was caused by a covered peril) with Bischel v. Fire Ins. Exch., 
    2 Cal. Rptr. 2d 575
     (Cal. Ct. App. 1991) (finding the exclusion excludes increased
    replacement costs). We certified the question whether such an exclusion is
    effective to exclude the increased costs of construction due to building ordinances
    to the California Supreme Court, Sierra Pac. Power Co. v. Hartford Steam Boiler
    Inspection & Ins. Co., 
    665 F.3d 1166
     (9th Cir. 2012), however, that court declined
    to provide guidance on the issue. Forced to determine the state law, we choose to
    apply the most recent California Court of Appeal decision, Altman.
    2
    Other jurisdictions that have addressed this question have also reached
    differing conclusions. Compare Dupre v. Allstate Ins. Co., 
    62 P.3d 1024
    , 1029-30
    (Colo. App. 2002), Bering Strait School Dist. v. RLI Ins., 
    873 P.2d 1292
    , 1296
    (Alaska 1994), Farmers Union Mut. Ins. Co. v. Oakland, 
    825 P.2d 554
     (Mont.
    1992) and Garnett v. Transamerica Ins. Servs., 
    800 P.2d 656
     (Idaho 1990)
    (interpreting similar language and holding perils exclusions do not operate to
    exclude increased costs to replace due to intervening changes in building
    ordinances) with Spears v. Shelter Mut. Ins. Co., 
    73 P.3d 865
    , 867-69 (Okla. 2003)
    and Dombrowsky v. Farmers Ins. Co. Of Wash., 
    928 P.2d 1127
     (Wash. Ct. App.
    1996) (finding exclusion does limit coverage).
    -9-
    The policy and exclusion at issue in Altman were substantially similar to the
    policy and exclusion in this case. In Altman, the court gave great weight to the fact
    that the exclusion for losses caused by enforcement of building codes or
    ordinances was in a section containing only perils exclusions. 10 Cal. Rptr. at.
    632. There was no limiting language in the valuation section of the policy or in the
    insuring clause. 
    Id.
     However, there is such limiting language in the standard form
    policy in California Insurance Code Section 2071. The Altman court stated, “[t]he
    exclusion’s location in a long list of excluded perils, combined with the words
    ‘caused directly or indirectly by,’ indicate that its intended function is to exclude a
    peril, not to place a limit on replacement costs.” 10 Cal. Rptr. at. 634 (citing Bank
    of the West v. Super. Ct., 
    2 Cal. 4th 1254
    , 1265 (1992)).
    Similarly, here the exclusion at issue is in the section of the policy labeled
    “PERILS EXCLUDED” and, unlike the standard form policy of California
    Insurance Code Section 2071, there is no reference or limitation for increased costs
    due to changes in building codes in either the valuation section or the insuring
    clause of the policy. We hold, following Altman, that the exclusion at issue here
    excludes damage caused by the peril of building ordinances, but not the increased
    construction costs caused by intervening building ordinances when the loss itself is
    caused by a covered peril.
    -10-
    The Insurers also contend that any coverage for increased costs due to
    intervening changes in building codes or ordinances is limited to the $10 million in
    additional coverage offered in the Demolition and Increased Cost of Construction
    (“DICC”) coverage extension. However, the DICC is a coverage extension that
    provides additional coverage for the extra expense incurred as a result of
    complying with intervening changes in building ordinances. It does not limit
    coverage otherwise available under the policy. As described above, the policy
    itself provides coverage for replacing structures destroyed by covered perils, even
    if the cost to do so is higher due to intervening changes in building codes. This
    coverage extension provides additional coverage not available elsewhere under the
    policy for demolishing undamaged portions of the building or structure if required
    by new building ordinances and rebuilding those demolished portions in
    accordance with the new building ordinances.
    Here, the Farad Dam was completely destroyed by a flood; the loss was not
    caused by building codes. It is undisputed that flood is a covered peril under the
    policy. Coverage is not limited by the DICC coverage extension. The district
    court did not err in concluding that the replacement cost of the Farad Dam includes
    any increased costs due to intervening changes in building ordinances.
    -11-
    The district court found “[t]he evidence established that the actual estimated
    cost to replace Farad is $19,800,000.” Insurers have not shown that this finding
    was clearly erroneous. We affirm the district court’s finding of replacement cost.
    However, because the district court did not apply appropriate depreciation to this
    replacement cost to determine the ACV of the dam, we remand to the district court
    to determine the proper depreciation and to apply that depreciation to the
    replacement cost to determine the ACV.
    3.    $4 Million Sierra Spent In Preparation to Rebuild the Dam
    Insurers contend that the court erred in ruling that Sierra is entitled to
    recover approximately $4 million it has spent to date in preparation work prior to
    starting construction. Insurers argue that, because the policy does not pay
    replacement cost if the dam is not rebuilt within two years, they are not obligated
    to pay anything more than ACV (which they contend they have already done) until
    the dam is actually rebuilt.
    The cases Insurers rely on involve policies that contain specific wording that
    the policy here does not. For example, the policy at issue in Maryland Casualty
    Co. v. Knight, 
    96 F.3d 1284
     (9th Cir. 1996), contained a provision that said: “We
    will not pay on a replacement cost basis for any loss or damage: (1) Until the lost
    or damaged property is actually repaired or replaced; and, (2) Unless the repairs or
    -12-
    replacement are made as soon as reasonably possible after the loss or damage.” 
    Id. at 1292
     (emphasis added). Each of the other cases Insurers cite have similar
    provisions, and all expressly state that replacement cost will not be paid until the
    property is actually replaced.3
    The policy here has no such express timing provision. The policy limits
    only the amount of the Insurer’s liability, but says nothing about when the Insurers
    will pay replacement cost. The valuation provision of the policy states, “in the
    event of loss or damage to property which is not repaired, rebuilt or replaced
    within two years from the date of loss or damage, this company shall not be liable
    for more than the actual cash value (with proper deduction for depreciation) of the
    property destroyed.” This provision does not state that the Insurers will not pay
    more than ACV until the property is actually replaced. Rather, it merely limits the
    Insurers’ ultimate liability if the property is not replaced within the allotted time.
    3
    Ghoman v. New. Hampshire Ins. Co., 
    159 F. Supp. 2d 928
    , 934, n.6
    (N.D. Tex. 2001) (“replacement costs will not be paid ‘[u]ntil the lost or damaged
    property is actually repaired or replaced’”); Kolls v. Aetna Cas. & Sur. Co., 
    378 F. Supp. 392
    , 395 (S.D. Iowa 1974) aff’d, 
    503 F.2d 569
     (8th Cir. 1974) (no
    replacement cost recoverable “[u]nless and until the damaged property is actually
    repaired or replaced with due diligence and dispatch”); Truesdell v. State Farm
    Fire and Cas. Co., 
    960 F. Supp. 1511
    , 1513 (N.D. Okla. 1997) (“until actual repair
    or replacement is completed, we will pay the actual cash value of the damage to the
    buildings”). But see Lerer Realty Corp v. MFB Mut. Ins. Co., 
    474 F.2d 410
     (5th
    Cir. 1973)
    -13-
    Because “[i]nsurance coverage is interpreted broadly so as to afford the greatest
    possible protection to the insured[,]” MacKinnon v. Truck Ins. Exch., Inc., 
    31 Cal. 4th 635
    , 648 (Cal. 2003), the district court was not wrong to find that the expenses
    already incurred by Sierra and necessary in preparation to replace the dam are
    recoverable before replacement is actually completed.
    The district court went one step further, ruling that Sierra was entitled to
    recover this amount “even if replacement is not undertaken.” We agree that the
    money Sierra has already spent in preparation for rebuilding should be included in
    the estimate of replacement cost which is then used to determine the ACV, and we
    assume it was included in the estimated replacement cost ($19,800,000) the district
    court found reasonable. However, if the district court intended that Sierra is
    entitled to recover expenses already incurred in addition to the ACV, there is no
    support for such a ruling. We hold that the amount Sierra has already spent is
    properly included in the calculation of replacement cost, which would then be
    reduced by the appropriate depreciation to determine the ACV,4 but that Sierra is
    4
    Any amount Hartford has already paid Sierra Pacific would, of course,
    be deducted from the any recovery so that Sierra Pacific recovers an amount equal
    to, but not exceeding, the ACV.
    -14-
    not entitled to recover any amount in addition to the ACV of the dam unless the
    dam is actually rebuilt within the three-year limit imposed by the district court.5
    4.    Policy’s Two-Year Limit on Time to Rebuild
    The district court found four separate reasons excusing Sierra from
    complying with the policy’s two-year rebuilding requirement to recover
    replacement cost rather than ACV. First, there is substantial evidence that
    regulatory challenges made it impossible for Sierra to rebuild before filing its suit,
    and the evidence details the years Sierra worked to obtain the necessary permits
    and easements in order to begin work on the replacement. It was not clear error for
    the district court to conclude that it was impossible to comply with the two-year
    requirement.
    Second, the court ruled that because the two-year condition was impossible
    to satisfy, it would be contrary to public policy to enforce it. The Insurers cite no
    case that casts doubt on the district court’s finding. They failed to meet their
    burden to demonstrate that enforcing a condition that is impossible to satisfy would
    not be contrary to public policy in California. Third, the district court found that
    5
    We leave it to the district court to determine whether the same
    depreciation should be applied to the costs incurred in preparation to rebuild as to
    the costs of construction of the dam itself, or whether the prerequisites to
    rebuilding, such as environmental impact studies and building permits, should be
    subject to a different depreciation rate.
    -15-
    the Insurers’ conduct should prevent them from enforcing the two-year limit to
    recover replacement cost. The court found that Insurers unreasonably denied
    coverage and misled Sierra as to the amount of coverage ultimately available under
    the policy. An insurer’s misrepresentations regarding available coverage, and its
    delay in informing an insured as to coverage available, has been held sufficient to
    base a finding of estoppel against enforcing time limits such as the two-year
    provision here. City of Hollister v. Monterey Ins. Co., 
    81 Cal. Rptr. 3d 72
    , 98-99
    (Cal. Ct. App. 2008).
    Finally, the district court found that the two-year provision was not
    enforceable because it was waived through repeated extensions and that, because
    the Insurers granted each extension requested, the provision was not material. The
    court also noted that because the policy set the time to calculate the value of the
    dam as the time when, with diligence and dispatch the dam could be replaced, the
    Insurers were not prejudiced by any extension. The Insurers have not established
    that the court was clearly erroneous in so finding.
    The district court further determined that a reasonable time to rebuild with
    diligence and dispatch was three years from the date of its order. While the
    Insurers argue the court was wrong in ruling the two-year period was
    unenforceable, neither party specifically argues why the three-year figure is wrong.
    -16-
    Therefore, we affirm the district court’s determination that the time limit to rebuild
    the dam should be three years rather than two years.6 We also agree with the
    district court that, should Sierra actually rebuild the dam within that time, it should
    be entitled to recover the difference between ACV and the replacement cost.
    5.     Conclusion
    We vacate the district court’s finding that the ACV of the Farad Dam was
    $1,261,200, and remand for a determination of the ACV based on reducing the
    replacement cost of $19,800,000 by the appropriate depreciation. We affirm the
    district court’s finding that Sierra is entitled to the $4 million it has already spent in
    replacement costs even though the dam has not actually been replaced yet, to the
    extent that this amount is included in the estimated replacement cost used to
    calculate the ACV. We affirm the district court’s finding that the coverage
    available under the policy includes costs necessary to comply with current
    regulatory requirements and building codes. Finally we affirm the district court’s
    6
    Sierra filed a motion to stay the trial court’s order so that the time
    during this appeal would be tolled and not count toward the three-year limit.
    Because we remand to the district court for further resolution, and the district court
    has indicated it intended the three-year period to begin running only after the
    litigation is final, including all periods of appeal, we are confident the district court
    will be able to fashion its final ruling in this matter to clarify that the three-year
    period granted for rebuilding Farad Dam should be tolled until the conclusion of
    the litigation, including during the pendency of any appeal by the Insurers.
    Therefore, we DENY Sierra’s motion as moot.
    -17-
    finding that the two-year restriction for replacing the dam was impossible to
    comply with, therefore contrary to public policy and unenforceable. In sum, we
    VACATE in part, AFFIRM in part, and REMAND.
    Each side to bear its own costs.
    -18-