Pit River Tribe v. Blm ( 2019 )


Menu:
  •                     FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    PIT RIVER TRIBE; NATIVE                 No. 17-15616
    COALITION FOR MEDICINE
    LAKE HIGHLANDS DEFENSE;                   D.C. Nos.
    MOUNT SHASTA                       2:04-cv-00956-JAM-AC
    BIOREGIONAL ECOLOGY                2:04-cv-00969-JAM-AC
    CENTER; SAVE MEDICINE
    LAKE COALITION; MEDICINE
    LAKE CITIZENS FOR QUALITY                 OPINION
    ENVIRONMENT,
    Plaintiffs-Appellees,
    v.
    BUREAU OF LAND
    MANAGEMENT; U.S.
    DEPARTMENT OF THE
    INTERIOR,
    Defendants-Appellants.
    Appeal from the United States District Court
    for the Eastern District of California
    John A. Mendez, District Judge, Presiding
    Argued and Submitted May 14, 2019
    Seattle, Washington
    Filed September 19, 2019
    2                    PIT RIVER TRIBE V. BLM
    Before: William A. Fletcher and Morgan Christen, Circuit
    Judges, and Roslyn O. Silver,* District Judge.
    Opinion by Judge Christen
    SUMMARY**
    Geothermal Steam Act / Federal Leases
    The panel affirmed the district court’s summary judgment
    in favor of Pit River Tribe and several environmental
    organizations in their action against federal agencies
    responsible for administering twenty-six unproven
    geothermal leases located in California’s Medicine Lake
    Highlands.
    Pit River alleged that the Bureau of Land Management’s
    decision to continue the terms of the unproven leases for up
    to forty years violated the Geothermal Steam Act (“GSA”).
    Section 1017 of the GSA authorizes the Secretary of the
    Interior to approve cooperative or unit plans to manage
    multiple geothermal leases as a unit, and the Secretary must
    review such unit plans every five years and eliminate any
    lease not reasonably necessary for unit operations under the
    plan. Section 1005(a) of the GSA provides that geothermal
    *
    The Honorable Roslyn O. Silver, United States District Judge for the
    District of Arizona, sitting by designation.
    **
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    PIT RIVER TRIBE V. BLM                    3
    leases on federal land have primary lease terms of ten years,
    and allows the leases to be continued for as long as
    geothermal steam is produced in commercial quantities.
    Section 1005(c) states that leases subject to “unit plans” may
    be extended even if not productive during the initial ten-year
    term under certain conditions.
    The panel held that the statutory meaning of 30 U.S.C.
    § 1005(a) was clear and unambiguous. The panel held that
    the provision permitted production-based forty-year
    continuations at the end of the primary term only on a lease-
    by-lease basis, not on a unit-wide basis. It was BLM’s
    burden to provide a compelling reason for the court to depart
    from the plain language of § 1005(a), and the panel
    concluded that it had not met that burden here.
    COUNSEL
    Mary Gabrielle Sprague (argued) and Ellen J. Durkee,
    Appellate Section; Eric Grant, Deputy Assistant Attorney
    General; Jeffrey Bossert Clark, Acting Assistant Attorney
    General; Environment and Natural Resources Division,
    United States Department of Justice, Washington, D.C.; for
    Defendants-Appellants.
    Samuel Lazerwitz (argued) and Caleb G. Wright (argued),
    Certified Law Students; Alicia E. Thesing, Isaac C. Cheng,
    and Deborah Ann Sivas, Supervising Attorneys;
    Environmental Law Clinic, Mills Legal Clinic at Stanford
    Law School, Stanford, California; for Plaintiffs-Appellees.
    4                    PIT RIVER TRIBE V. BLM
    OPINION
    CHRISTEN, Circuit Judge:
    The Bureau of Land Management and the Department of
    the Interior (collectively, BLM) appeal the district court’s
    order granting summary judgment in favor of the Pit River
    Tribe and several local and regional environmental
    organizations (collectively, Pit River). We have jurisdiction
    pursuant to 28 U.S.C. § 1291 and we affirm the district
    court’s judgment.
    I. Background
    Pit River filed this action against the federal agencies
    responsible for administering twenty-six unproven
    geothermal leases located in California’s Medicine Lake
    Highlands. We refer to these leases as “unproven” because
    BLM has not determined that they are capable of producing
    geothermal steam in commercial quantities. See Pit River
    Tribe v. Bureau of Land Mgmt., 
    793 F.3d 1147
    , 1149–50 (9th
    Cir. 2015) (Pit River III).1 Calpine Corporation, the current
    leaseholder, was also named as a defendant but it did not
    appeal the judgment the district court entered on remand from
    our court. The operative complaint alleges that BLM’s
    decision to continue the terms of the unproven leases for up
    to forty years violated the Geothermal Steam Act (GSA), the
    National Environmental Policy Act (NEPA), the National
    1
    Our decision in Pit River III provides a detailed history of the case.
    We recount that history only as necessary to resolve this appeal.
    PIT RIVER TRIBE V. BLM                               5
    Historic Preservation Act (NHPA), and the Indian-fiduciary-
    trust doctrine.2 
    Id. at 1148.
    The subject leases are located within the Glass Mountain
    Unit Plan. The parties agree that the GSA requires that any
    lease be allowed to continue if it is producing geothermal
    steam in commercial quantities, or is shown to be capable of
    doing so, within its primary ten-year term. See 30 U.S.C.
    § 1005(a) (1994).3 The parties’ dispute centers on whether all
    leases committed to a “unit plan” may be collectively
    continued for up to forty years if any single lease in the unit
    becomes productive during the primary term. Pit River
    argues that § 1005(a) allows production-based continuations
    to be granted only on an individual basis. BLM argues that
    § 1005(a) allows production-based continuations to be
    granted to all leases in a unit if any one of them becomes
    productive during the primary term. BLM’s interpretation of
    the GSA is heavily informed by its view that the Mineral
    Leasing Act (MLA), 30 U.S.C. §§ 221i–236a (1964),
    provides an important backdrop against which the GSA must
    be analyzed.4
    2
    The complaint also alleges a violation of the Freedom of
    Information Act (FOIA), but the district court’s ruling on the FOIA issue
    was not appealed.
    3
    Unless otherwise specified, all citations to the GSA refer to the 1994
    edition of the United States Code because the parties agree that this
    iteration of the GSA applies to their dispute.
    4
    Unless otherwise noted, all citations to the MLA’s provisions are to
    the 1964 edition of the United States Code, which was in effect when the
    GSA was enacted.
    6                 PIT RIVER TRIBE V. BLM
    II. Procedural History
    This is the second time our court has addressed the
    controversy concerning the duration of the leases in the Glass
    Mountain Unit. See Pit River 
    III, 793 F.3d at 1148
    . In July
    of 2013, the district court granted judgment on the pleadings
    in favor of BLM on the grounds that Pit River lacked
    prudential standing to assert its GSA claim. 
    Id. at 1154–55.
    We reversed the district court’s judgment, ruling that Pit
    River’s claim fell within the GSA’s “zone of interests,” 
    id. at 1155–58,
    and we remanded to the district court so it could
    consider the merits of the claims.
    On remand from Pit River III, the district court granted
    summary judgment in favor of Pit River. The court ruled
    that, as it was written in 1994, the GSA’s primary term
    provision was unambiguous and did not authorize BLM to
    continue the twenty-six unproven leases for forty years
    simply because they were part of a unit that contained a
    single proven lease. The district court reasoned that because
    Congress referred to “unit plans” in § 1005(c) and (g), but
    omitted this term from § 1005(a), “Congress did not
    contemplate the additional [forty]-year term for
    nonproductive leases committed to a unit plan under
    [§] 1005(a).” In an amended judgment, the district court
    vacated and set aside BLM’s May 18, 1998 decision granting
    the lease continuations, and remanded the proceedings to the
    agency to determine whether to extend or cancel the twenty-
    six leases pursuant to the GSA and the implementing
    regulations in effect as of May 1998. The district court
    observed that its judgment did not affect BLM’s decision to
    continue the single proven lease, and that Pit River’s NEPA,
    NHPA, and fiduciary duty claims were mooted by the court’s
    PIT RIVER TRIBE V. BLM                      7
    vacatur of BLM’s 1998 decision letters. BLM appeals the
    district court’s judgment.
    III. Standard of Review
    We review de novo an order granting summary judgment.
    Cty. of Amador v. U.S. Dep’t of the Interior, 
    872 F.3d 1012
    ,
    1020 (9th Cir. 2017).
    IV. Jurisdiction
    We must first assure ourselves of our jurisdiction to hear
    this appeal because the district court’s order granting
    summary judgment vacated BLM’s 1998 decision letters and
    remanded to the agency. See Pit River Tribe v. U.S. Forest
    Serv., 
    615 F.3d 1069
    , 1075 (9th Cir. 2010). “[R]emand
    orders are generally not ‘final’ decisions for purposes of
    section 1291[,]” 
    id., but a
    remand order is considered final
    and appealable where: “(1) the district court conclusively
    resolves a separable legal issue, (2) the remand order forces
    the agency to apply a potentially erroneous rule which may
    result in a wasted proceeding, and (3) review would, as a
    practical matter, be foreclosed if an immediate appeal were
    unavailable.” 
    Id. (quoting Alsea
    Valley All. v. Dep’t of
    Commerce, 
    358 F.3d 1181
    , 1184 (9th Cir. 2004)). Here,
    because the district court determined that 30 U.S.C. § 1005(a)
    did not authorize BLM to continue the unproven leases based
    on the single proven lease, BLM will be constrained by this
    interpretation on remand. If the district court’s interpretation
    is incorrect, the remand will result in a wasted proceeding.
    Moreover, review of the district court’s interpretation will be
    foreclosed absent immediate appeal because, after remand to
    the agency, BLM cannot later appeal the result of its own
    agency decision. See Alsea Valley 
    All., 358 F.3d at 1184
    ;
    8                 PIT RIVER TRIBE V. BLM
    Chugach Alaska Corp. v. Lujan, 
    915 F.2d 454
    , 457 (9th Cir.
    1990). For these reasons, we conclude that we have
    jurisdiction to hear this appeal.
    V. Discussion
    A. The Geothermal Steam Act
    This appeal requires us to interpret the GSA, 30 U.S.C.
    §§ 1001–1028 (1994). Congress enacted the GSA in 1970 “to
    promote the development of geothermal leases on federal
    lands.” Geo-Energy Partners-1983 Ltd. v. Salazar, 
    613 F.3d 946
    , 949 (9th Cir. 2010). Geothermal resources include “the
    heat or energy found in steam, hot water, or geothermal
    formations.” 
    Id. The GSA
    was adopted in the wake of the
    MLA, which governs oil and gas leases on federal lands. BP
    Am. Prod. Co. v. Burton, 
    549 U.S. 84
    , 87 (2006). A brief
    explanation of the MLA’s unitization provision provides
    helpful background.
    When Congress enacted the MLA, oil and gas were
    extracted under the common-law “rule of capture,” which
    encouraged landowners to drill wells on individual leases to
    capture as much oil or gas as possible. See Frank Sylvester
    & Robert W. Malmsheimer, Oil and Gas Spacing and Forced
    Pooling Requirements: How States Balance Energy
    Development and Landowner Rights, 40 U. Dayton L. Rev.
    47, 49 (2015). The rule of capture encouraged overdrilling
    that dissipated reservoir pressure and ultimately led to
    inefficient oil and gas recovery. See Northcutt Ely, The
    Conservation of Oil, 51 Harv. L. Rev. 1209, 1219–22 (1938).
    The practice of unitization emerged in response to these
    inefficiencies. See Sylvester, et al., supra at 49–50.
    Unitization allows an entire oil or gas field “to be operated as
    PIT RIVER TRIBE V. BLM                               9
    a single entity, without regard to surface boundary issues,”
    see Norfolk Energy, Inc. v. Hodel, 
    898 F.2d 1435
    , 1438 (9th
    Cir. 1990) (internal quotation marks omitted), i.e., it allows
    drilling and production operations occurring on a single lease
    within a unit to be deemed performed on all other leases
    within the unit for purposes of showing that bona fide
    development efforts have been made, or for sharing royalties.
    See, e.g., 30 U.S.C. § 1017; 30 U.S.C. § 226(j); 43 C.F.R.
    §§ 3280–3287 (1997). By limiting the need to drill on each
    lease within a unit, unitization lessens the likelihood that an
    oil or gas reservoir will suffer from overdrilling and depleted
    reservoir pressure. Congress incorporated the unitization
    concept into the MLA, granting the Secretary of the Interior
    the authority to approve unit plans of development when
    doing so is in the public interest. See Pub. L. No. 71-853, 46
    Stat. 1523. Although significant differences exist between
    the MLA and the GSA, the GSA also permits lessees to join
    together under unit plans of development. See 30 U.S.C.
    § 1017; 43 C.F.R. § 3280.0–2 (1997).
    The GSA refers to production-based “continuations” and
    drilling-based “extensions”—concepts articulated in the
    MLA—but neither the MLA nor the GSA explicitly define
    these terms. See 30 U.S.C. §§ 221i–236a; 30 U.S.C. § 1001.
    The parties agreed at oral argument that, like the MLA, the
    GSA allows for lease continuations based on production, and
    lease extensions based on exploratory drilling activities.5
    5
    We note that the Interior Board of Land Appeals generally interprets
    a continuation based on production as a prolonged lease term that is
    “indefinite and is allowed when a lease is presently capable of producing
    oil or gas” in commercial quantities, while an “‘extension by drilling’ . . .
    requires that a lessee conduct actual drilling operations on the last day of
    10                 PIT RIVER TRIBE V. BLM
    Pit River’s claims implicate §§ 1005 and 1017 of the
    GSA, so we discuss these provisions in some detail. Section
    1017 governs unit plans. Section 1005 governs the duration
    of geothermal lease terms.
    1. 30 U.S.C. § 1017: The Unitization Provision
    Section 1017 of the GSA authorizes the Secretary of the
    Interior to approve cooperative or unit plans to manage
    multiple leases as a unit “[f]or the purpose of properly
    conserving the natural resources of any geothermal pool,
    field, or like area.” 30 U.S.C. § 1017. The Secretary must
    review such unit plans every five years “and, after notice and
    opportunity for comment, eliminate from inclusion in such
    plan any lease or part of a lease not regarded as reasonably
    necessary to cooperative or unit operations under the plan.”
    Pit River 
    III, 793 F.3d at 1150
    (quoting 30 U.S.C. § 1017).
    2. 30 U.S.C. § 1005:             The Lease Duration
    Provisions
    Section 1005(a) of the GSA provides that geothermal
    leases on federal land have primary lease terms of ten years.
    30 U.S.C. § 1005(a). If geothermal steam is produced in
    commercial quantities during the ten-year primary term,
    § 1005(a) allows the lease to be continued for as long as
    geothermal steam is produced in commercial quantities, not
    the lease term with an intent to complete a producing well.” Coastal
    Petroleum Co., 190 IBLA 347, 352, 
    2017 WL 3263839
    , at *4 (July 25,
    2017).
    PIT RIVER TRIBE V. BLM                               11
    to exceed an additional forty years.6 
    Id. At the
    end of the
    first forty-year term granted pursuant to § 1005(a), the GSA
    affords a preferential right of renewal for a second forty-year
    term if geothermal steam is still being produced in
    commercial quantities and the land is not needed for other
    purposes. 30 U.S.C. § 1005(b).
    Neither § 1005(a) nor § 1005(b) refer to “unit plans,” but
    § 1005(c) does. It is entitled “Cooperative or unit plan for
    drilling operations; extension of term; renewal.” 30 U.S.C.
    § 1005(c). Section 1005(c) states that leases subject to unit
    plans may be extended, even if the leases have not been
    productive during their initial ten-year primary terms, if
    actual drilling operations begin prior to the end of the primary
    lease terms and are being diligently prosecuted.7 
    Id. For leases
    still not producing steam nor shown to be capable of
    producing in commercial quantities by the end of an
    extension granted pursuant to § 1005(c), the agency may
    6
    30 U.S.C. § 1005(a) specifies that “[i]f geothermal steam is
    produced or utilized in commercial quantities within this term, such lease
    shall continue for so long thereafter as geothermal steam is produced or
    utilized in commercial quantities, but such continuation shall not exceed
    an additional forty years.” In turn, 30 U.S.C. § 1005(d) defines “produced
    or utilized in commercial quantities” to include a showing that a well is
    “capable of producing geothermal steam in commercial quantities.”
    (emphasis added).
    7
    30 U.S.C. § 1005(c) provides, inter alia, that a lease for which:
    actual drilling operations were commenced prior to the
    end of its primary term and are being diligently
    prosecuted at that time shall be extended for five years
    and so long thereafter, but not more than thirty-five
    years, as geothermal steam is produced or utilized in
    commercial quantities.
    12                      PIT RIVER TRIBE V. BLM
    authorize one or two additional five-year extensions if the
    lessee has made certain bona fide efforts.8 30 U.S.C.
    § 1005(g)(1). Notably, § 1005(g)(1) also expressly refers to
    leases operated under “approved cooperative or unit plan[s]
    of development.” 
    Id. If a
    lease extended pursuant to
    § 1005(g)(1) begins producing geothermal steam in
    commercial quantities during a § 1005(g)(1) extension,
    § 1005(g)(2) provides that the lease shall be continued for up
    to twenty-five additional years if it was previously extended
    under § 1005(c), “for a total of [fifty] years,” or for up to
    thirty additional years (but not to exceed a total of fifty years)
    8
    30 U.S.C. § 1005(g)(1) states:
    (1) Any geothermal lease issued pursuant to this
    chapter for land on which, or for which under an
    approved cooperative or unit plan of development or
    operation, geothermal steam has not been produced or
    utilized in commercial quantities by the end of its
    primary term, or by the end of any extension provided
    by subsection (c) of this section, may be extended for
    successive 5-year periods, but totaling not more than
    10 years, if the Secretary determines that the lessee has
    met the bona fide effort requirement of subsection (h)
    of this section, and either of the following:
    (A) [T]he payment in lieu of commercial quantities
    production requirement of subsection (i) of this
    section.
    (B) The significant expenditure requirement of
    subsection (j) of this section.
    PIT RIVER TRIBE V. BLM                           13
    if it was only previously extended pursuant to § 1005(g)(1).9
    30 U.S.C. § 1005(g)(2).
    B. The Glass Mountain Leases
    Three years after Congress enacted the GSA, BLM
    promulgated regulations authorizing holders of geothermal
    leases to enter into unit agreements for the development of
    geothermal resources. See 38 Fed. Reg. 35,068, 35,073–75
    (Dec. 21, 1973); see also 43 C.F.R. §§ 3280.0–1 to 3286.1
    (1997). These regulations included a model unit agreement.
    See 38 Fed. Reg. at 35,075–80; see also 43 C.F.R. § 3286.1
    (1997). In 1982, Calpine’s predecessors entered into the
    Glass Mountain Unit Agreement, which tracked the
    regulations’ model agreement.10
    The twenty-six unproven leases at issue in this
    appeal—plus a twenty-seventh “proven lease” that BLM
    determined was capable of producing geothermal steam in
    commercial quantities—were eventually committed to the
    Glass Mountain Unit Agreement. Pit River 
    III, 793 F.3d at 1149
    –51. The Agreement established a “Unit Area” and
    9
    30 U.S.C. § 1005(g)(2) provides:
    (2) A lease extended pursuant to paragraph (1) shall
    continue so long thereafter as geothermal steam is
    produced or utilized in commercial quantities, but such
    continuation shall not exceed an additional 25 years, for
    a total of 50 years, if such lease was also the subject of
    an extension under subsection (c) of this section or an
    additional 30 years, for a total of 50 years, if such lease
    is only extended pursuant to paragraph (1).
    10
    We do not separately identify Calpine’s predecessors to avoid
    confusion and because the predecessors’ actions do not affect our analysis.
    14                PIT RIVER TRIBE V. BLM
    “Participating Area.” The Unit Area is the area comprised of
    all leases subject to the Agreement, and the Participating Area
    is the “part of the Unit Area which is deemed to be
    productive,” i.e., it is “all land then regarded as reasonably
    proved to be productive from a pool or deposit discovered or
    developed[.]” By the fifth anniversary of the Participating
    Area’s effective date, the Agreement requires that all portions
    of unitized lands not entitled to be included in the
    Participating Area must be automatically eliminated from the
    Agreement and from the Unit Area, unless drilling operations
    are in progress on an exploratory well and these operations
    continue diligently.
    In 1989, BLM determined that a single lease in the Glass
    Mountain Unit was capable of producing geothermal steam
    in commercial quantities. Pit River 
    III, 793 F.3d at 1151
    . In
    1991 and 1992, at the request of Calpine’s predecessors,
    BLM’s California State Office extended the terms of twenty-
    four unproven leases in the Glass Mountain Unit for five
    years pursuant to § 1005(g)(1). BLM continued the term of
    the single proven lease for up to forty additional years
    pursuant to § 1005(a). 
    Id. In the
    process of responding to the
    predecessors’ requests, BLM’s California State Office
    communicated with the Nevada State Office, “which advised
    that [forty]-year lease continuations should be granted to all
    of the unproven Glass Mountain leases[.]” 
    Id. The California
    Office disagreed. 
    Id. It concluded
    that “the ‘[forty-]year
    extension [under § 1005(a)] may only be applied to the lease
    with the well capable of production and not to the other
    committed leases in the unit.’” 
    Id. (second alteration
    in
    original). The California Office noted that § 1005(a) did not
    refer to unit plans. 
    Id. PIT RIVER
    TRIBE V. BLM                           15
    In 1995, BLM sent Calpine’s predecessor a letter stating
    that the predecessor was “in default of meeting reasonable
    diligence in the unit,” and that the Glass Mountain Unit was
    “no longer of any significant benefit to the BLM or Forest
    Service” because “[t]he unit has become an impediment to
    development by causing operators to select drilling targets on
    the basis of whether a lease is or is not committed to the unit
    instead of the area with the greatest potential to support a
    development project.” On June 3, 1996, BLM notified
    Calpine’s predecessor via an additional letter that a proposed
    Participating Area should have been submitted in 1989, but
    that due to agency delay and other circumstances, BLM
    would allow submission of a proposed Participating Area
    within sixty days of receipt of the letter. Calpine’s
    predecessor submitted a proposed Participating Area on
    August 15, 1996.11
    BLM’s California State Office changed its interpretation
    of § 1005(a) in 1998. The California Office’s Program Lead,
    Sean Hagerty, circulated an internal memo that sheds light on
    the reasons for BLM’s changed position. Hagerty’s memo
    described the prior disagreement between BLM’s California
    and Nevada Offices and explained that the California Office
    was concerned about allowing the Glass Mountain Unit to
    continue for an indefinite period of time merely based on the
    single proven lease. In particular, “BLM was concerned over
    how the Unit could be managed without any effective way of
    requiring the unit operator . . . to conduct additional activities
    in the Unit prior to the submission of the initial Participating
    Area (PA).” The memo explained that BLM was initially
    uncertain whether the single proven lease, which was deemed
    11
    This information was not part of the record in Pit River 
    III, 793 F.3d at 1152
    n.6.
    16                  PIT RIVER TRIBE V. BLM
    capable of production but had not actually commenced
    production, was legally sufficient to require Calpine’s
    predecessor to submit an initial Participating Area. Because
    BLM subsequently decided that a well capable of production
    was equivalent to a well actually in production, it requested
    and received a proposed Participating Area from Calpine’s
    predecessor. Hagerty’s memo concluded that, because the
    Participating Area had been designated, “the Glass Mountain
    Unit boundary would contract down to the boundary of the
    [Participating Area],” and therefore “the Glass Mountain Unit
    Agreement no longer had an indefinite lifespan and could
    now be managed in the public interest.”               Hagerty
    recommended that BLM grant an additional term of up to
    forty years to all leases committed to the Glass Mountain
    Unit.
    On May 18, 1998—five days after Hagerty circulated his
    memo—BLM’s California Office issued decision letters
    vacating the 1991 and 1992 lease extensions for the unproven
    leases and continuing them for up to forty years pursuant to
    § 1005(a).12 Pit River 
    III, 793 F.3d at 1152
    . BLM explained
    that the decision to grant the five-year lease extensions
    pursuant to the regulation implementing § 1005(g)(1) “was in
    error.” BLM further explained that all leases committed to
    the Glass Mountain Unit should have been granted additional
    lease terms based on the paying-well determination for the
    single proven lease pursuant to the regulation implementing
    § 1005(a) and (d).
    12
    In total, BLM continued twenty-six unproven leases, which
    included two leases that were not previously extended in 1991 or 1992.
    Pit River 
    III, 793 F.3d at 1152
    n.8.
    PIT RIVER TRIBE V. BLM                   17
    C. Statutory Analysis
    It is clear that the GSA authorizes “continuations” based
    on production, see 30 U.S.C. § 1005(a), and there is no
    dispute that the GSA authorizes five-year “extensions” based
    on actual drilling or bona fide efforts. See § 1005(c), (g).
    Both parties argue that 30 U.S.C. § 1005(a) is clear and
    unambiguous, but they advocate for opposite interpretations.
    BLM argues that § 1005(a), read in light of the GSA as a
    whole and against the backdrop of the MLA, authorizes forty-
    year continuations on a unit-wide basis once a single lease in
    a unit is deemed productive. Pit River argues that § 1005(a)
    unambiguously authorizes forty-year continuations at the end
    of a primary term only on a lease-by-lease basis, not on a
    unitized basis.
    “We interpret a federal statute by ascertaining the intent
    of Congress and by giving effect to its legislative will[,]”
    beginning with the statute’s language. Artichoke Joe’s Cal.
    Grand Casino v. Norton, 
    353 F.3d 712
    , 720 (9th Cir. 2003)
    (internal quotation marks omitted). We “presume that [the]
    legislature says in a statute what it means and means in a
    statute what it says.” BedRoc Ltd., LLC v. United States,
    
    541 U.S. 176
    , 183 (2004) (internal quotation marks omitted).
    “The plainness or ambiguity of statutory language is
    determined by reference to the language itself, the specific
    context in which the language is used, and the broader
    context of the statute as a whole.” Geo-Energy Partners-
    1983 
    Ltd., 613 F.3d at 956
    (internal quotation marks omitted).
    If “the language is not dispositive, we look to the
    congressional intent revealed in the history and purposes of
    the statutory scheme.” Artichoke 
    Joe’s, 353 F.3d at 720
    (internal quotation marks omitted). “[I]f we find that the
    statutory meaning is plain and unambiguous, then our ‘sole
    18                 PIT RIVER TRIBE V. BLM
    function . . . is to enforce it according to its terms.’”
    Hernandez v. Williams, Zinman & Parham PC, 
    829 F.3d 1068
    , 1072 (9th Cir. 2016) (alteration in original) (quoting
    United States v. Ron Pair Enters., 
    489 U.S. 235
    , 241 (1989));
    see Chevron, U.S.A., Inc. v. Nat. Res. Def. Council, Inc.,
    
    467 U.S. 837
    , 842–43 (1984) (“If the intent of Congress is
    clear, that is the end of the matter; for the court, as well as the
    agency, must give effect to the unambiguously expressed
    intent of Congress.”).
    We begin with the GSA’s text, and observe that § 1005(a)
    does not include the term “unit plan.” See 30 U.S.C.
    § 1005(a). It is not our practice to read words into statutory
    provisions, see United States v. Watkins, 
    278 F.3d 961
    , 965
    (9th Cir. 2002), as a statute’s plain language is “our primary
    guide to Congress’ preferred policy.” Sandoz Inc. v. Amgen
    Inc., 
    137 S. Ct. 1664
    , 1678 (2017) (internal quotation marks
    omitted). Relatedly, we have observed that:
    It is a well-established canon of statutory
    interpretation that the use of different words
    or terms within a statute demonstrates that
    Congress intended to convey a different
    meaning for those words. Congress’s explicit
    decision to use one word over another in
    drafting a statute is material. It is a decision
    that is imbued with legal significance and
    should not be presumed to be random or
    devoid of meaning.
    SEC v. McCarthy, 
    322 F.3d 650
    , 656 (9th Cir. 2003) (internal
    citations omitted). “[W]hen Congress includes particular
    language in one section of a statute but omits it in another
    section of the same Act, it is generally presumed that
    PIT RIVER TRIBE V. BLM                     19
    Congress acts intentionally and purposely in the disparate
    inclusion or exclusion.” Barnhart v. Sigmon Coal Co.,
    
    534 U.S. 438
    , 452 (2002) (internal quotation marks omitted).
    We conclude that the use of “unit plan” in § 1005(c) and
    (g)(1) expressly memorialized congressional intent to make
    short lease extensions available on a unit-wide basis if leases
    do not become productive during their primary terms but
    lease operators can show that drilling has commenced or
    other bona fide efforts have been made. In other words, we
    conclude that the omission of the term “unit plan” in
    § 1005(a) is “imbued with legal significance.” 
    McCarthy, 322 F.3d at 656
    .
    BLM argues that Congress’s omission of the term “unit
    plan” from § 1005(a) is not a rejection of the unitization
    principle because the subsection must be read in conjunction
    with the GSA as a whole and against the historical backdrop
    of the MLA. This argument is premised on BLM’s unstated
    assertion that geothermal steam reservoirs function in the
    same way that underground pools of oil and gas do. Prior to
    oral argument, the record contained no support for this
    assertion. After oral argument, BLM submitted a letter
    explaining that overdrilling in geothermal fields results in a
    loss of well pressure, just like oil and gas fields. As support,
    BLM’s letter cited a public document that reported on the
    rapid development of a northern California hydrothermal
    system and the resulting loss of production well pressure. Pit
    River has not had a chance to respond, but even assuming that
    geothermal reservoirs function the same way as oil and gas
    reservoirs do, the general framework Congress adopted in the
    MLA does not overcome the plain language Congress chose
    for the GSA’s primary term and unitization provisions.
    20                PIT RIVER TRIBE V. BLM
    BLM argues that the MLA provides important context
    and that the incorporation of the unitization principle into the
    MLA suggests Congress intended to adopt the same statutory
    scheme for the GSA. We disagree. Congress enacted the
    MLA decades before it enacted the GSA, and we assume
    Congress is knowledgeable about existing law when it enacts
    new legislation. See Miles v. Apex Marine Corp., 
    498 U.S. 19
    , 32 (1990); see also Cty. of 
    Amador, 872 F.3d at 1022
    (“[U]nderstanding the historical context in which a statute
    was passed can help to elucidate the statute’s purpose and the
    meaning of statutory terms and phrases.”). The GSA’s
    sponsor understood the 1970 bill to generally permit the
    Secretary of Interior to lease public lands in “much the same
    manner” as the Secretary was authorized to do by the MLA.
    S. Rep. No. 91-1160, at 4 (1970). But Congress recognized
    that efforts to harness geothermal steam in an emerging
    market posed unique challenges. See H.R. Rep. No. 91-1544,
    at 3–4 (1970). By 1970, the MLA was in its fiftieth year of
    regulating oil and gas leasing but the geothermal steam
    industry was still in its infancy. Congress acknowledged that
    the mining and mineral leasing statutes “lack many of the
    requirements necessary to encourage [geothermal steam’s]
    orderly development.” 
    Id. at 5.
    The hope was that the GSA
    would “establish a framework that will make this risk-laden,
    relatively untried industry an attractive investment in the
    public interest.” S. Rep. No. 91-1160, at 9. Recognizing the
    need to encourage geothermal exploration by allowing
    leaseholders time to get the resource to market—or to bring
    the market to the geothermal steam by building
    infrastructure—the GSA’s original sponsor acknowledged
    “there may be some reasonable delay beyond the expiration
    of the primary term before a generating facility can be
    installed to receive the steam and commence actual power
    PIT RIVER TRIBE V. BLM                          21
    production.”13 S. Rep. No. 91-1160, at 8. Contrary to BLM’s
    argument, the text of the GSA, read as a whole, demonstrates
    that Congress deviated from the MLA when it adopted the
    GSA, perhaps because it was aware of the need to
    accommodate the uniquely-situated geothermal steam
    technology and developing market.
    A comparison of the GSA’s primary term provision,
    § 1005(a), and the MLA’s primary term provision, 30 U.S.C.
    § 226(e), reveals notable differences. Section 226(e) is
    entitled “Primary terms” and it expressly incorporates the
    phrase “unit plan.” Section 226(e) governs primary lease
    term continuations and extensions thereafter. Congress did
    not adopt § 226(e) wholesale when it enacted the GSA;
    rather, it split this provision into two subsections. Section
    1005(a) authorizes primary term continuations and § 1005(c)
    separately authorizes post-primary term extensions and
    production-based continuations. BLM describes the decision
    to divide § 226(e) into § 1005(a) and (c) in the GSA as a
    stylistic choice, but we are mindful that Congress could have
    replicated the MLA’s primary term provision (including the
    “unit plan” language) directly into the statutory text of GSA
    § 1005(a), and it did not do so.
    BLM goes on to argue that the GSA provision authorizing
    unit plans, 30 U.S.C. § 1017, authorizes § 1005(a)’s
    production-based continuations to be granted on a unit-wide
    13
    Indeed, even as of 1988, Congress acknowledged the challenges
    involved in harnessing geothermal energy. H.R. Rep. No. 100-664, at 6
    (1988) (“Unlike coal, oil and gas which can be transported to power
    production facilities, the steam from a geothermal well cannot be
    transported more than two miles because of heat dissipation,” and must be
    converted to electricity at or near the well site.).
    22                   PIT RIVER TRIBE V. BLM
    basis because § 1017 is fairly read to broadly incorporate the
    MLA’s unitization framework into the GSA. We are not
    persuaded that so much can be read into § 1017. First,
    BLM’s reasoning “would require us to assume that Congress
    chose a surprisingly indirect route to convey an important and
    easily expressed message.” Landgraf v. USI Film Prods.,
    
    511 U.S. 244
    , 262 (1994). See generally Zachary v. Cal.
    Bank & Tr., 
    811 F.3d 1191
    , 1198–99 (9th Cir. 2016)
    (rejecting statutory reading that reflected a policy choice
    Congress could have made “in a far more straightforward
    manner”). Section 1017 authorizes unit agreements and
    constriction of unit plans, requiring that, no more than five
    years after approval of a unit plan (and at least every five
    years thereafter), the Secretary of the Interior must eliminate
    leases “not regarded as reasonably necessary to . . . unit
    operations.”14 30 U.S.C. § 1017. Section 1017 further
    provides that leases eliminated from a unit by the constriction
    process may receive extensions pursuant to § 1005(c) and (g)
    only if they separately qualify.15 
    Id. The language
    in § 1017
    represents a significant departure from the MLA’s corollary
    provision governing unit plans, MLA § 226(j). The MLA
    allows lessees to form unit plans for development, but it
    expressly allows leases to be continued indefinitely on a unit-
    wide basis—for as long as production continues. See
    30 U.S.C. § 226(j). Setting aside renewals authorized by
    14
    Section 1017 also provides that this “elimination shall be based on
    scientific evidence, and shall occur only when it is determined by the
    Secretary to be for the purpose of conserving and properly managing the
    geothermal resource.”
    15
    BLM argues that this language reaffirms the unitization principle.
    But the impact of this language is limited. It merely confirms that leases
    constricted from a unit plan must individually qualify for extensions under
    § 1005(c) or (g); it says nothing about continuations under § 1005(a).
    PIT RIVER TRIBE V. BLM                    23
    § 1005(b) and (g)(3), all GSA lease terms are capped at fifty
    years. The MLA also differs from the GSA by not requiring
    plan review every five years for constriction of the unit plan.
    See 
    id. In sum,
    we agree that the MLA provides context for
    considering the terms of the GSA, but it cannot be doubted
    that Congress varied from the MLA when it fashioned
    §§ 1005 and 1017, and the MLA’s unitization framework
    does not require the conclusion BLM urges us to reach.
    BLM next argues that the following language in
    § 1005(g)(1) demonstrates that § 1005(a) authorizes
    continuations on a unit-wide basis:
    Any geothermal lease issued pursuant to this
    chapter for land on which, or for which under
    an approved cooperative or unit plan of
    development or operation, geothermal steam
    has not been produced or utilized in
    commercial quantities by the end of its
    primary term, or by the end of any extension
    provided by subsection (c) . . . may be
    extended for successive 5-year periods[.]
    § 1005(g)(1). Congress added this provision in 1988 to help
    non-productive leases withstand adverse market conditions
    created by a world energy glut. See H.R. Rep. No. 100-664,
    at 6 (1988). As BLM’s argument goes, because § 1005(g)(1)
    allows unproductive leases in unit plans to be extended for
    five years on a unit-wide basis if they remain unproductive at
    the end of their primary terms, and because it also provides
    that leases are ineligible for § 1005(g)(1) extensions if they
    have received § 1005(a) continuations, then § 1005(g)(1)
    must be read as confirmation that § 1005(a) authorizes
    production-based continuations on a unit-wide basis. Again,
    24                PIT RIVER TRIBE V. BLM
    we are not persuaded. BLM’s reasoning overlooks the most
    straightforward reading of the statute: Regardless of the
    combination of primary term, continuations or extensions,
    Congress capped the terms of geothermal leases at fifty years.
    Consistent with this scheme, leases that receive forty-year
    continuations under § 1005(a) after becoming productive
    during their ten-year primary terms are ineligible for the
    shorter extensions allowed for unproven leases. BLM also
    overlooks that § 1005(a) says nothing about unit plans, and
    that § 1005(g)(1) only authorizes extensions, on an individual
    or a unit-wide basis, for leases that do not become productive
    during their primary terms or § 1005(c) extensions. Contrary
    to BLM’s conclusion, it was entirely consistent for Congress
    to have provided short unit-wide extensions under § 1005(c)
    and (g)(1) for unproductive leases that do not individually
    qualify for lengthy continuations during their primary terms.
    BLM also argues that because GSA § 1005(c) and (g)(2)
    authorize continuations on a unit-wide basis for leases that
    produce steam in commercial quantities during extended
    terms, it “defies logic” to think that Congress did not intend
    to provide unit-wide rewards for production achieved during
    initial primary lease terms. The reason Congress chose not to
    incorporate the unitization principle into the GSA’s primary
    term provision is not fully explained by the statute, but in the
    ordinary case, “our obligation is to apply the statute as
    Congress wrote it.” Hubbard v. United States, 
    514 U.S. 695
    ,
    703 (1995). We have explained why we are not persuaded by
    BLM’s premise that § 1005(a) must allow continuations on
    a unitized basis because the GSA’s primary term provision
    was modeled after the MLA’s primary term provision.
    Further, given the nature of the emerging geothermal steam
    market, Congress may have opted against unit-wide
    continuations during primary terms as a way of incentivizing
    PIT RIVER TRIBE V. BLM                    25
    exploration on all leases to define the contours of the
    productive area during the primary term. The decision not to
    incorporate unit-wide continuations during the primary term
    still allows leaseholders to benefit from unitization through
    cost and royalty sharing. It is also consistent with § 1017’s
    mandatory review of unit plans every five years, and with the
    requirement that unit areas be constricted to eliminate leases
    not reasonably necessary to unit operations. See 30 U.S.C.
    § 1017. Congress may have been concerned that granting
    unit-wide continuations during the initial ten-year term would
    impede development by encouraging operators to select
    drilling targets based on whether leases were committed to
    units, rather than on the areas with the greatest potential for
    production. This is the very concern BLM expressed in 1995.
    Whatever the case, on the record before us, we do not agree
    with BLM’s assertion that it defies logic to conclude that
    Congress did not intend to authorize production-based
    continuations on a unitized basis during primary terms.
    BLM’s final argument is that § 1005(a)’s legislative
    history shows that Congress intended the terms of all leases
    in a unit to benefit if any one of them becomes productive
    during the primary term. BLM points us to a 1970 House
    Report:
    Section 6 of the bill provides that each
    geothermal lease shall be for a primary term
    of 10 years. If steam is produced or utilized
    in commercial quantities within this term the
    lease will continue for so long thereafter as
    such production or utilization continues, but
    not to exceed an additional 40 years. If at the
    end of such 40 years steam continues to be
    produced in commercial quantities, and the
    26                  PIT RIVER TRIBE V. BLM
    land is not needed for other purposes, the
    lessee is given a preferential right to a renewal
    of the lease for a second 40-year period in
    accordance with such terms and conditions as
    the Secretary deems appropriate. Comparable
    provision is also made respecting lands leased
    for development under approved cooperative
    and unit plans.
    H.R. Rep. No. 91-1544, at 7 (1970) (emphasis added). BLM
    argues that the “comparable provision” for leases committed
    to unit plans must be § 1017. But it is equally likely that,
    when Congress passed the GSA in 1970, this passage was
    intended to differentiate § 1005(a) from § 1005(c), the only
    provision then authorizing development on a unit-wide
    basis.16 In other words, the passage that BLM relies on may
    highlight that Congress adopted a lease-by-lease approach for
    production-based continuations during the primary term in
    § 1005(a), and that § 1005(c) authorized a separate but
    comparable unit-wide approach for five-year extensions
    granted after primary terms, based on drilling. Absent further
    context or explanation in the House Report, we find its
    reference to “comparable provision” to be inconclusive. See
    Flores-Arellano v. INS, 
    5 F.3d 360
    , 362 (9th Cir. 1993)
    (ruling that inconclusive legislative history was insufficient
    to overcome unambiguous statutory text). It is BLM’s burden
    to provide a compelling reason for us to depart from the plain
    language of § 1005(a), and we conclude it has not met that
    burden here.
    16
    Section 1005(g)—the other provision authorizing development on
    a unit-wide basis—was not added to the GSA until 1988.
    PIT RIVER TRIBE V. BLM                   27
    VI. Conclusion
    The statutory meaning of 30 U.S.C. § 1005(a) is clear and
    unambiguous. It only permits production-based continuations
    on a lease-by-lease basis, not on a unit-wide basis. We
    therefore affirm the district court’s order granting summary
    judgment in favor of the appellees.
    AFFIRMED.