Industrial Customers of Northwest Utilities v. Bonneville Power Administration , 408 F.3d 638 ( 2005 )


Menu:
  •                   FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    INDUSTRIAL CUSTOMERS OF                
    NORTHWEST UTILITIES; BENTON
    RURAL ELECTRIC ASSOCIATION;
    COLUMBIA-SNAKE RIVER IRRIGATORS
    ASSOCIATION; UMATILLA ELECTRIC;
    EASTERN OREGON IRRIGATORS
    ASSOCIATION,
    Petitioners,
    PUGET SOUND ENERGY; AVISTA
    CORPORATION; PACIFIC NORTHWEST
    
    GENERATING COMPANY (PNGC);                 No. 03-71626
    PUBLIC UTILITY DISTRICT NO. 1 OF            Power Act
    SNOHOMISH COUNTY, WASHINGTON,
    Petitioner-Intervenor,
    v.
    BONNEVILLE POWER
    ADMINISTRATION,
    Respondent,
    PACIFICORP; PORTLAND GENERAL
    ELECTRIC COMPANY,
    Respondent-Intervenor.
    
    5671
    5672      INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER
    PUBLIC UTILITY DISTRICT NO. 1 OF       
    BENTON COUNTY; PUBLIC UTILITY
    DISTRICT NO. 1 OF COWLITZ
    COUNTY; PUBLIC UTILITY DISTRICT
    NO. 1 OF FRANKLIN COUNTY; PUBLIC
    UTILITY DISTRICT NO. 2 OF GRANT
    COUNTY; PUBLIC UTILITY DISTRICT
    NO. 1 OF GRAYS HARBOR COUNTY;
    PUBLIC UTILITY DISTRICT NO. 1 OF
    PENDOREILLE COUNTY; THE CITY OF
    SEATTLE; SEATTLE CITY LIGHT
    DEPARTMENT (GENERATING PUBLIC
    UTILITIES); PUBLIC POWER COUNCIL,
    
    Petitioners,       No. 03-71894
    PACIFIC NORTHWEST GENERATING                Power Act
    COMPANY (PNGC); PUGET SOUND
    ENERGY; AVISTA CORPORATION;
    PUBLIC UTILITY DISTRICT NO. 1 OF
    SNOHOMISH COUNTY, WASHINGTON,
    Petitioner-Intervenor,
    v.
    BONNEVILLE POWER
    ADMINISTRATION,
    Respondent,
    PACIFICORP; PORTLAND GENERAL
    ELECTRIC COMPANY,
    Respondent-Intervenor.
    
    INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER           5673
    ALCOA, INC.,                             
    Petitioner,
    PACIFIC NORTHWEST GENERATING
    COMPANY (PNGC); PUGET SOUND
    ENERGY; AVISTA CORPORATION;
    PUBLIC UTILITY DISTRICT NO. 1 OF
    SNOHOMISH COUNTY, WASHINGTON,                   No. 03-71931
    Petitioner-Intervenor,
           Power Act
    v.                             OPINION
    BONNEVILLE POWER
    ADMINISTRATION,
    Respondent,
    PACIFICORP; PORTLAND    GENERAL
    ELECTRIC COMPANY,
    Respondent-Intervenor.
    
    On Petition for Review of an Order of the
    Bonneville Power Administration
    Argued and Submitted
    October 7, 2004—Seattle, Washington
    Filed May 24, 2005
    Before: Dorothy W. Nelson, Sidney R. Thomas,
    Circuit Judges, and David A. Ezra,* District Judge.
    Opinion by Judge Thomas
    *The Honorable David A. Ezra, Chief Judge, United States District
    Court for the District of Hawaii, sitting by designation.
    INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER      5675
    COUNSEL
    Michael B. Early, Portland, Oregon, for petitioner Alcoa Inc.
    5676      INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER
    Melinda J. Davison, Irion A. Sanger, Davison Van Cleve,
    Portland, Oregon, for petitioners Industrial Customers of
    Northwest Utilities, Benton Rural Electric Association,
    Columbia-Snake River Irrigators Association, Umatilla Elec-
    tric, Eastern Oregon Irrigators Association.
    Denise Peterson, Portland, Oregon, for petitioner Public
    Power Council.
    Raymond S. Kindley, Schwabe, Williamson & Wyatt, Port-
    land, Oregon, for petitioners Public Utility District No. 1 of
    Benton County, Public Utility District No. 1 of Cowlitz
    County, Public Utility District No. 1 of Franklin County, Pub-
    lic Utility District No. 2 of Grant County, Public Utility Dis-
    trict No. 1 of Grays Harbor County, Public Utility District No.
    1 of Pendoreille County, the City of Seattle, Seattle City Light
    Department.
    Michael J. Gianunzio, Eric Lee Christensen, Everett, Wash-
    ington, for petitioner Public Utility District No. 1 of Snoho-
    mish County, Washington.
    Gary A. Dahlke, R. Blair Strong, Paine, Hamblen, Coffin,
    Brooke, & Miller, LLP, Spokane, Washington, for petitioner-
    intervenor Avista Corporation.
    R. Erick Johnson, Portland, Oregon, for petitioner-intervenor
    Pacific Northwest Generating Company.
    Kirstin S. Dodge, Perkins Coie, LLP, Bellevue, Washington,
    for petitioner-intervenor Puget Sound Energy.
    Eric Lee Christensen, Michael J. Gianunzio, Everett, Wash-
    ington, for petitioner-intervenor Public Utility District No. 1
    of Snohomish County, Washington.
    Randy A. Roach, Marybeth Van Buren, Karin J. Immergut,
    United States Attorney, District of Oregon, Stephen J. Odell,
    INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER         5677
    Assistant U.S. Attorney, Kurt R. Casad, Special Assistant
    U.S. Attorney, Portland, Oregon, for respondent Bonneville
    Power Administration.
    Marcus Wood, Stephen C. Hall, Stoel Rives LLP, Portland,
    Oregon, for respondent-intervenor Pacificorp.
    Loretta Mabinton, Portland, Oregon, for respondent-
    intervenor Portland General Electric Company.
    OPINION
    THOMAS, Circuit Judge:
    This consolidated appeal presents the question, inter alia,
    of whether the Bonneville Power Administration (“BPA”)
    determination to commence a rate hearing to decide whether
    the BPA should impose Safety-Net Cost Recovery Adjust-
    ment Charges is a final agency decision subject to judicial
    review. We conclude that it is not and dismiss the petitions for
    review for lack of jurisdiction.
    I
    The BPA is a federal agency within the United States
    Department of Energy created by Congress in 1937 to market
    hydroelectric power generated by the Federal Columbia River
    Power System, a series of dams along the Columbia River in
    Oregon and Washington. 16 U.S.C. §§ 832-832m. Congress
    has since expanded the BPA’s mandate to include marketing
    authority over nearly all the electric power generated by fed-
    eral facilities in the Pacific Northwest. 
    Id. § 838f.
    The BPA
    is charged with oversight of the federal high-voltage transmis-
    sion system used to deliver power generated at a federally
    owned and operated facility, as well as non-federal power to
    its customers. 
    Id. § 838b.
    It owns and operates approximately
    5678      INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER
    eighty percent of the Pacific Northwest’s high-voltage trans-
    mission system and markets approximately forty percent of
    the electric power consumed in the Pacific Northwest. Ass’n
    of Pub. Agency Customers, Inc. v. BPA, 
    126 F.3d 1158
    , 1163
    (9th Cir. 1997).
    The BPA’s general authority is derived from four organic
    statutes: the Bonneville Project Act of 1937 (“the Project
    Act”), 16 U.S.C. §§ 832-832m; the Regional Preference Act,
    
    id. §§ 837-837h;
    the Columbia River Transmission Act (“the
    Transmission Act”), 
    id. §§ 838-838l;
    and the Pacific North-
    west Electric Power Planning and Conservation Act of 1980
    (“the Northwest Power Act”), 
    id. §§ 839-839h.
    Ass’n of Pub.
    Agency 
    Customers, 126 F.3d at 1164
    . The BPA’s rate-making
    authority is derived from the Project Act, the Transmission
    Act, the Northwest Power Act, and the Flood Control Act of
    1944, 16 U.S.C. § 825s. Pursuant to the Northwest Power Act,
    the BPA’s power rates are established by the BPA, but subject
    to approval by the Federal Energy Regulatory Commission
    (“FERC”). 
    Id. § 829e.
    After 1974, when Congress trans-
    formed the BPA into a self-financing agency, see 
    id. § 838i,
    the power rates charged by the BPA became its source of rev-
    enue. Cent. Lincoln Peoples’ Util. Dist. v. Johnson, 
    735 F.2d 1101
    , 1116 (9th Cir. 1984).
    The Northwest Power Act requires the BPA to establish
    rates that will “produce sufficient revenues to ensure BPA’s
    fiscal independence and repay the U.S. Treasury for the fed-
    eral funds that were borrowed to build the projects in the Fed-
    eral Columbia River Power System.” Cal. Energy Comm’n v.
    BPA, 
    909 F.2d 1298
    , 1303 (9th Cir. 1990); 16 U.S.C.
    §§ 838g, 839e(a)(1). At the same time, Congress requires that
    the BPA market federal power “with a view to encouraging
    the widest possible diversified use of electric power at the
    lowest possible rates to consumers consistent with sound busi-
    ness principles.” 16 U.S.C. §§ 838g, 839e(a)(1).
    The BPA Administrator is required periodically to revise
    rates to recover the capital costs and expenses associated with
    INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER         5679
    the Columbia River Power System. See 
    id. §§ 832f,
    838g,
    839e(a)(1). The procedures governing the establishment of
    rates are set by statute and include the following: issuance of
    a Federal Register notice announcing the proposed rates; one
    or more hearings; the opportunity to submit written views,
    supporting information, questions, or arguments; and a deci-
    sion by the Administrator based on the record developed dur-
    ing the hearing process. 
    Id. § 839e.
    Rates established by the
    BPA only become effective after approval by FERC. 
    Id. § 839e(a)(2).
    The rate schedules proposed by the BPA are termed “Gen-
    eral Rate Schedule Provisions” (“GRSP”). The origins of the
    present controversy arose out of a supplemental rate proposal
    promulgated by the BPA in 2001. The BPA had previously
    proposed new wholesale power rates to be effective on Octo-
    ber 1, 2001, 64 Fed. Reg. 44,318 (1999), and different rates
    to be effective Fiscal Year 2002, 65 Fed. Reg. 44,041 (2000).
    After these filings, increased load obligations and higher
    market prices caused the BPA to determine that its rate pro-
    posals would be insufficient to assure it could cover costs and
    repay U.S. Treasury obligations. On December 1, 2000, the
    BPA published its proposed amendments to the 2002 whole-
    sale power rate adjustment proposal. 65 Fed. Reg. 75,272
    (2000). Further market changes caused the BPA to issue sup-
    plemental wholesale power rate filing on June 29, 2001. 66
    Fed. Reg. 37,664 (2001). The supplemental proposal adjusted
    the previous GRSP by replacing the capped single Cost
    Recovery Adjustment Clause (“CRAC”) with a three-
    component CRAC: the Load-Based CRAC (or “LB CRAC”,
    as it is referenced in the BPA filings) designed to cover aug-
    mentations costs; the Financial-Based CRAC (or “FB
    CRAC”) designed to cover net revenue, and the Safety-Net
    CRAC (or “SN CRAC”), available if there were a likelihood
    of missing a treasury or other creditor payment.
    The CRACs were created to allow the BPA to address any
    financial shortfalls without having to raise base rates. In par-
    5680      INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER
    ticular, the CRACs were intended to increase the BPA’s Trea-
    sury Payment Probability to what it considered acceptable
    levels. FERC granted interim approval of the CRAC proposal
    on September 28, 2001 and final approval on July 21, 2003.
    104 FERC ¶ 61,093 (2003).
    When triggered, the Safety-Net CRAC allowed “an upward
    adjustment to posted power rates subject to the FB CRAC by
    modifying the FB CRAC parameters.” Under the GRSP, the
    Safety-Net CRAC would be available if the Administrator
    determined that, after implementation of the Financial-Based
    CRAC and any adjustments, either of the following condi-
    tions existed:
    •   The BPA forecasts a fifty percent or greater prob-
    ability that it will nonetheless miss its next pay-
    ment to Treasury or other creditor, or
    •   The BPA has missed a payment to the Depart-
    ment of the Treasury or has satisfied its obliga-
    tion to the Department of the Treasury but has
    missed a payment to any other creditor.
    Under the supplemental proposal, once the BPA Adminis-
    trator determined that these conditions existed, the BPA
    would “propose changes to the FB CRAC parameters that
    will, to the extent market and other risk factors allow, achieve
    a high probability that the remainder of Treasury payments
    during the FY 2002-2006 rate period will be made in full.” In
    determining its initial proposal, the BPA was to “give priority
    to prudent cost management and other options that enhance
    Treasury Payment Probability while minimizing changes to
    the FB CRAC.”
    When the Administrator determined that the Safety-Net
    CRAC had been triggered, the BPA would be required to send
    written notification to customers that purchase power under
    rates subject to the Financial-Based CRAC and to other inter-
    INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER        5681
    ested parties. The notice was required to “the documentation
    used by the BPA to determine that the SN CRAC has trig-
    gered, the amount of any forecast shortfall, and the time and
    location of a workshop on the SN CRAC.” The scheduled
    workshops are to discuss “the cause of shortfall, and any pro-
    posed changes to the FB CRAC that will achieve a high prob-
    ability that the remainder of Treasury payments . . . will be
    made timely.”
    Additionally, “[a]s soon as practicable after a determina-
    tion,” the BPA was required to publish “a Federal Register
    Notice initiating an expedited hearing process to be conducted
    in accordance with Section 7(i) of the Northwest Power Act.”
    The hearing was required to be completed within forty days
    of publication of the notice.
    The BPA experienced continued financial problems in the
    winter of 2003. Due to “lower than expected prices and less
    than expected hydro production,” the BPA ended up “selling
    less energy and at lower prices than forecasted in the Supple-
    mental Proposal.” Under the GRSP financial test, the Admin-
    istrator determined that the BPA had less than a fifty percent
    probability of making the next Treasury payment, due Octo-
    ber 1, 2003. On February 7, 2003, the BPA Administrator
    commenced an emergency rate adjustment pursuant to the
    financial test in the Safety-Net CRAC provisions. The BPA
    issued a letter to “interested parties and customers” informing
    them of the trigger determination; the letter “included a table
    summarizing the documentation used by the BPA to deter-
    mine that the SN CRAC had triggered, the amount of the fore-
    casted shortfall, and the time and location for a workshop on
    the SN CRAC.”
    Pursuant to the GRSP, the BPA conducted workshops in
    February 2003 to explain the trigger determination. In March,
    the BPA published a Federal Register Notice of “Proposed
    Safety-Net Cost Recovery Adjustment Clause Adjustment to
    2002 Wholesale Power Rates.” 68 Fed. Reg. 12048 (2003).
    5682      INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER
    The BPA held full evidentiary hearings and allowed a com-
    ment period.
    In June 2003, the BPA published its “Administrator’s Final
    Record of Decision” (“Final ROD”) for the Safety-Net
    CRAC. The Final ROD contains the BPA analysis and con-
    clusions based on the evidentiary record compiled, with
    respect to the adoption of the Safety-Net CRAC. Subse-
    quently, the BPA filed its Safety-Net CRAC rate adjustment
    proposal and record with FERC on July 29, 2003, along with
    a request for interim and final approval effective October 1,
    2003. 105 FERC ¶ 61,006 ¶¶ 2, 3 n.4 (2003). The effect of the
    Safety-Net CRAC would be to increase the BPA’s power
    rates substantially.
    The petitioners in these consolidated petitions for review
    are various public utilities and private utility consumers who
    challenge the BPA’s Final ROD approving the Safety-Net
    CRAC. They contend that the BPA Administrator was not
    entitled to impose the Safety-Net CRAC because neither of
    the two predicate conditions existed. Respondents concede
    that the BPA had not missed any payments that would cause
    the trigger. The Petitioners argue that the other predicate con-
    dition — the BPA forecast of a fifty percent probability that
    it would miss its next payment to the Department of the Trea-
    sury — was fundamentally flawed. Petitioners claim that the
    BPA acted arbitrarily and capriciously in adopting the Safety-
    Net CRAC because the BPA had sufficient financial resources
    to make its next Treasury payment, but improperly chose to
    exclude sources of revenue such as bond refinancing.
    On judicial review under the Administrative Procedures
    Act, we may grant a petition for review from a final decision
    of the BPA if it is “arbitrary, capricious, an abuse of discre-
    tion, or otherwise not in accordance with law.” 5 U.S.C.
    § 706(2)(A). We review subject matter jurisdiction de novo.
    Chang v. United States, 
    327 F.3d 911
    , 922 (9th Cir. 2003).
    INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER                  5683
    II
    The threshold question is whether we have jurisdiction over
    the consolidated petitions for review. The BPA contends that
    the Administrator’s decision to trigger the Safety-Net CRAC
    is not subject to judicial review until FERC confirms and
    approves the rate,1 reasoning that the final agency action in
    this instance rests with FERC. We agree and conclude that we
    lack appellate jurisdiction because the Final ROD was not the
    final rate determination and therefore, not the final agency
    action.
    A
    [1] Under the Northwest Power Act, we have original juris-
    diction for all cases brought challenging actions under the
    Project Act, 16 U.S.C. §§ 832 et seq. 
    Id. § 839f(e)(5).
    The act
    vests us with exclusive jurisdiction for review of final actions
    and decisions of the BPA Administrator. Pub. Util. Dist. No.
    1 of Clark County v. Johnson, 
    855 F.2d 647
    , 648 (9th Cir.
    1988). Our jurisdiction is limited to “[s]uits to challenge the
    constitutionality of [the Project Act], or any action thereunder,
    final actions and decisions taken pursuant to this [Act] by the
    Administrator or the Council, or the implementation of such
    final actions.” 
    Id. The statute
    delineates eight actions consid-
    ered “final actions subject to judicial review.” 16 U.S.C.
    § 839f(e)(1). This list includes “final rate determinations,”
    which are deemed final only “upon confirmation and approval
    by the Federal Energy Regulatory Commission.” 
    Id. § 839f(e);
    Cent. Lincoln Peoples’ Util. 
    Dist., 735 F.2d at 1109
    .
    [2] Because the BPA’s decision to trigger the Safety-Net
    CRAC is ultimately subsumed into the rate subject to FERC
    1
    Final confirmation did in fact occur on May 10, 2004. 107 FERC
    ¶ 61,138 (2004). It is the subject of a separate petition for review pending
    before this Court.
    5684      INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER
    approval, this statutory scheme would seem to present a fairly
    straightforward administrative process for review of the
    BPA’s trigger determination. However, FERC does not have
    the authority to review the BPA’s initial trigger decision.
    Although FERC must approve all rate changes before they
    become final, FERC’s power to review the BPA proposals is
    limited: It can affirm or remand the rates, but cannot modify
    them. 16 U.S.C. §§ 839e(a), 839e(k); 107 FERC ¶ 61,138
    ¶ 23. FERC has described its role in the BPA ratemaking as
    that “of an appellate body,” whose “function is to determine
    from the record before it whether ‘due process requirements
    have been met and [whether] the Administrator’s program of
    rate schedules and the decision of [the Assistant Secretary]
    are rational and consistent with the statutory standards.’ ” Alu-
    minum Co. of Am. v. BPA, 
    903 F.2d 585
    , 592-93 (9th Cir.
    1989) (quoting United States v. City of Fulton, 
    475 U.S. 657
    ,
    663 (1986)) (alterations in original).
    The basis of the Commission’s review of regional power
    and transmission rates is restricted to whether the proposed
    rates meet the three specific requirements of Section 7(a)(2),
    namely that they:
    (A) are sufficient to assure repayment of the Fed-
    eral investment in the Federal Columbia River
    Power System over a reasonable number of years
    after first meeting the Administrator’s other costs,
    (B) are based upon the Administrator’s total sys-
    tem costs, and
    (C) insofar as transmission rates are concerned,
    equitably allocate the costs of the Federal transmis-
    sion system between Federal and non-Federal power
    utilizing such system.
    16 U.S.C. § 839e(a)(2).
    INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER           5685
    FERC reviews non-regional, non-firm rates to determine
    whether such rates comply with the statutory mandates of the
    Project Act, the Flood Control Act of 1944, and the Transmis-
    sion System Act. 
    Id. § 839e(k).
    These statutes require BPA
    “to design its non-regional, non-firm rates: (1) to recover the
    cost of generation and transmission of such electric energy,
    including the amortization of investments in the power proj-
    ects within a reasonable period; (2) to encourage the most
    widespread use of Bonneville power; and (3) to provide the
    lowest possible rates to consumers consistent with sound busi-
    ness principles.” 107 FERC ¶ 61,138 ¶ 22.
    [3] Given these limitations, the Petitioners quite correctly
    point out that FERC’s rate review will not provide them with
    an opportunity to challenge the BPA’s trigger decision during
    FERC’s review. However, the absence of FERC review does
    not preclude judicial review of the BPA’s trigger determina-
    tion after final FERC action. Indeed, the BPA concedes that
    the petitioners have the full right to judicial review of its trig-
    ger decision as part of the petition for review of the ultimate
    FERC rate decision. However, because the trigger determina-
    tion was a component of the rate, it is not subject to judicial
    review until final agency action with respect to the rate. See
    Pub. Util. Comm’r of Oregon v. BPA, 
    767 F.2d 622
    , 629 (9th
    Cir. 1985) (noting that challenges to the BPA’s rate-making
    process not subject to FERC review may still be raised on
    judicial review of final FERC rate decision, but cannot be
    raised in an interlocutory petition for review). In sum, the
    petitions before us are not ripe for review, but are a proper
    part of a petition for review of the final FERC rate decision.
    B
    [4] The petitioners contend that we have appellate jurisdic-
    tion pursuant to our “catchall” jurisdiction under the North-
    west Power Act, which provides that “[n]othing in this section
    shall be construed to preclude judicial review of other final
    actions and decisions by the Council or Administrator.” 16
    5686      INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER
    U.S.C. § 839f(e)(3). The Northwest Power Act does not delin-
    eate what constitutes a “final action” under this section.
    Therefore, the courts have been left to define the term. In
    doing so, we have looked to the “more general doctrine of
    finality in administrative agency law.” See Puget Sound
    Energy, Inc. v. United States, 
    310 F.3d 613
    , 624 (9th Cir.
    2002). The finality doctrine is “concerned with whether the
    initial decisionmaker has arrived at a definitive position on
    the issue that inflicts an actual, concrete injury.” Idaho Water-
    sheds Project v. Hahn, 
    307 F.3d 815
    , 828 (9th Cir. 2002)
    (quoting Darby v. Cisneros, 
    509 U.S. 137
    , 144 (1993)).
    [5] The Supreme Court provided guidance in this determi-
    nation in Bennett v. Spear, 
    520 U.S. 154
    (1997). In Bennett,
    the Supreme Court held that an agency action is considered
    “final” when the two sets of conditions are satisfied. 
    Id. at 177-78.
    “First, the action must mark the ‘consummation’ of
    the agency’s decisionmaking process — it must not be of a
    merely tentative or interlocutory nature.” 
    Id. (citations omit-
    ted). Secondly, “the action must be one by which ‘rights or
    obligations have been determined,’ or from which ‘legal con-
    sequences will flow.’ ” 
    Id. at 178
    (citations omitted). As the
    Supreme Court has stated, “[t]he core question is whether the
    agency has completed its decisionmaking process, and
    whether the result of that process is one that will directly
    affect the parties.” Franklin v. Massachusetts, 
    505 U.S. 788
    ,
    797 (1992).
    In applying these principles, we have determined that cer-
    tain factors provide an indicia of finality, such as “whether the
    [action] amounts to a definitive statement of the agency’s
    position, whether the [action] has a direct and immediate
    effect on the day-to-day operations of the party seeking
    review, and whether immediate compliance [with the terms]
    is expected.” Cal. Dep’t of Water Res. v. FERC, 
    341 F.3d 906
    , 909 (9th Cir. 2003) (citing Mt. Adams Veneer Co. v.
    United States, 
    896 F.2d 339
    , 343 (9th Cir. 1990) (citing FTC
    v. Standard Oil Co., 
    449 U.S. 232
    , 239-40 (1980))).
    INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER          5687
    [6] The decision by the BPA Administrator to trigger the
    Safety-Net CRAC rate adjustment process fails the first prong
    of the Bennett test of finality, in that it does not “mark the
    ‘consummation’ of the agency’s decisionmaking process,” but
    is merely the beginning of the decision-making process. “An
    interlocutory order or decree is one which does not finally
    determine a cause of action but only decides some intervening
    matter pertaining to the cause, and which requires further
    steps to be taken in order to enable the court to adjudicate the
    cause on its merits.” Dalton Equip. Co. v. Brown, 
    594 F.2d 195
    , 197 (9th Cir. 1979).
    In the Final ROD, the BPA represented that “[t]he trigger
    determination for the SN CRAC is purely procedural.” As the
    Final ROD explains, “[t]he trigger determination does not
    propose an SN CRAC or establish an SN CRAC.” Instead, the
    trigger determination only initiates the process. The Adminis-
    trator considered the Safety-Net CRAC process to be com-
    prised of three phases, as delineated in the GRSP. The trigger
    determination constitutes the first phase. The second phase is
    the “SN CRAC Notification Process,” which is “intended to
    inform customers and interested third parties of the Adminis-
    trator’s determination, and the basis for it.” The third phrase
    is “SN CRAC Hearing Process,” which is governed by the
    procedural requirements of § 7(i). After the § 7(i) evidentiary
    hearing, which must be completed within forty days, the BPA
    must submit the required documentation, including the admin-
    istrative record to FERC. Only after FERC’s confirmation and
    approval are rate determinations deemed final. 16 U.S.C.
    § 839f(e)(4)(D); Cent. Lincoln Peoples’ Util. 
    Dist., 735 F.2d at 1109
    .
    Petitioners argue, with much justification, that the trigger
    decision is a discrete decision that has immediate financial
    impact. However, the fact that a statement may be definitive
    on some issue is insufficient to create a final action subject to
    judicial review. In Standard Oil, for example, Standard Oil
    Company of California (“Socal”) brought an action against
    5688      INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER
    the FTC for issuing a complaint averring that the Commission
    had “reason to believe” Socal was violating the Federal Trade
    Commission 
    Act. 449 U.S. at 234-35
    . The court found that the
    FTC’s averment of “reason to believe” was not a definitive
    statement of position, but “represent[ed] a threshold determi-
    nation that further inquiry is warranted and that a complaint
    should initiate proceedings.” 
    Id. at 242.
    As the court
    explained:
    To be sure, the issuance of the complaint is defini-
    tive on the question whether the [FTC] avers reason
    to believe that the respondent to the complaint is vio-
    lating the Act. But the extent to which the respon-
    dent may challenge the complaint and its charges
    proves that the averment of reason to believe is not
    “definitive” in a comparable manner to [other cases].
    . . . [T]he averment of reason to believe is a prerequi-
    site to a definitive agency position on the question
    whether Socal violated the Act, but itself is a deter-
    mination only that adjudicatory proceedings will
    commence.
    
    Id. at 241.
    [7] Although it is the predicate act for rate readjustment,
    the trigger determination itself has no final consequences. The
    trigger decision only determines whether a hearing will or
    will not occur. Like the complaint at issue in Standard Oil,
    the determination “[s]erv[es] only to initiate the proceedings.”
    
    Id. at 242.
    As the BPA noted in the Final ROD, “[t]he actual
    determination of whether the BPA will have an SN CRAC
    and, if so, the nature of the SN CRAC rate adjustment, is
    determined in the section 7(i) hearing.” Any change in actual
    rate only occurs after being submitted to and approved by
    FERC. Because it is not an actual rate decision, the BPA
    Administrator is allowed, and in fact required, to “make a
    decision on the trigger determination in the absence of a for-
    mal evidentiary record.” The BPA explains that “[t]he
    INDUSTRIAL CUSTOMERS v. BONNEVILLE POWER         5689
    requirements for making the trigger determination are very
    limited, which is perfectly consistent with the nature of the
    trigger determination . . . [which] has no substantive effect on
    any customer or interested party.”
    In the real world, of course, the trigger determination has
    economic consequences — sometimes profound conse-
    quences — because companies must take it into consideration
    when negotiating power contracts, particularly long-term
    power contracts. Nonetheless, the companies have a right of
    judicial review at the conclusion of FERC proceedings and do
    not waive any of their objections to the predicate determina-
    tions by failing to seek judicial review at an earlier stage.
    III
    [8] For these reasons, we dismiss the petitions for lack of
    jurisdiction. We need not, and do not, reach any other issue
    raised by the parties. Each party shall bear its own costs.
    PETITION DISMISSED.
    

Document Info

Docket Number: 03-71626, 03-71894, 03-71931

Citation Numbers: 408 F.3d 638

Judges: Nelson, Thomas, Ezra

Filed Date: 5/24/2005

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (16)

United States v. City of Fulton , 106 S. Ct. 1422 ( 1986 )

Darby v. Cisneros , 113 S. Ct. 2539 ( 1993 )

public-utility-district-no-1-of-clark-county-v-peter-t-johnson-as , 855 F.2d 647 ( 1988 )

mt-adams-veneer-co-publishers-forest-products-co-of-washington-and-puget , 896 F.2d 339 ( 1990 )

california-energy-commission-puget-sound-power-light-company-washington , 909 F.2d 1298 ( 1990 )

association-of-public-agency-customers-inc-v-bonneville-power , 126 F.3d 1158 ( 1997 )

Puget Sound Energy, Inc., a Washington Corporation v. ... , 310 F.3d 613 ( 2002 )

Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )

central-lincoln-peoples-utility-district-v-peter-johnson-as , 735 F.2d 1101 ( 1984 )

idaho-watersheds-project-committee-for-idahos-high-desert-v-martha-g , 307 F.3d 815 ( 2002 )

Dalton Equipment Company, Inc., Creditor-Appellee v. ... , 594 F.2d 195 ( 1979 )

Franklin v. Massachusetts , 112 S. Ct. 2767 ( 1992 )

california-department-of-water-resources-southern-california-edison , 341 F.3d 906 ( 2003 )

Federal Trade Commission v. Standard Oil Co. , 101 S. Ct. 488 ( 1980 )

public-utility-commissioner-of-oregon-pacific-power-light-company , 767 F.2d 622 ( 1985 )

wen-wan-chang-tsung-ming-chang-chiao-ying-chang-yi-yuan-chiang-hsien-ming , 327 F.3d 911 ( 2003 )

View All Authorities »