Verizon California Inc. v. Peevey ( 2005 )


Menu:
  •                     FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    VERIZON CALIFORNIA INC.,                  
    Plaintiff-Appellant,
    v.
    MICHAEL R. PEEVEY; LORETTA M.
    LYNCH; CARL W. WOOD; GEOFFREY
    F. BROWN; SUSAN P. KENNEDY, in
    their official capacities as
    Commissioners of the Public                      No. 04-15155
    Utilities Commission of the State
    of California, and not as                         D.C. No.
    CV-03-02838-THE
    individuals,
    Defendants-Appellees,              OPINION
    AT&T COMMUNICATIONS OF
    CALIFORNIA INC.; MCI WORLDCOM
    COMMUNICATIONS, INC.; MCIMETRO
    ACCESS TRANSMISSION SERVICES,
    LLC,
    Defendants-Intervenors-
    Appellees.
    
    Appeal from the United States District Court
    for the Northern District of California
    Thelton E. Henderson, District Judge, Presiding
    Argued and Submitted
    January 12, 2005—San Francisco, California
    Filed July 6, 2005
    Before: John T. Noonan, Carlos T. Bea, Circuit Judges, and
    Robert E. Jones, District Judge.*
    *The Honorable Robert E. Jones, Senior United States District Judge
    for the District of Oregon, sitting by designation.
    7833
    7834       VERIZON v. PEEVEY
    Opinion by Judge Noonan;
    Concurrence by Judge Bea
    7836                  VERIZON v. PEEVEY
    COUNSEL
    Henry Weissmann, Burton A. Gross, John P. Hunt and Rose-
    marie T. Ring, Munger, Tolles & Olson LLP, Los Angeles,
    California, for plaintiff-appellant Verizon California Inc.
    Randolph L. Wu, Mary F. McKenzie and Kimberly J. Lippi,
    San Francisco, California, for defendants-appellees Michael
    R. Peevey, Loretta M. Lynch, Carl W. Wood, Geoffrey F.
    Brown and Susan P. Kennedy in their official capacities as
    Commissioners of the Public Utilities Commission of the
    State of California.
    Catherine M. Barrad and Randolph W. Deutsch, Sidley, Aus-
    tin, Brown & Wood LLP, San Francisco, California, and
    David J. Miller, AT&T Communications of California, Inc.,
    San Francisco, California, for intervenor/defendant-appellee
    AT&T Communications of California, Inc.
    Donald B. Verrilli, Jr., Michael B. DeSanctis and Daniel
    Mach, Jenner & Block LLP, Washington, D.C., and Jeffrey A.
    Rackow, MCI, Inc., Washington, D.C., for intervenors/
    defendants-appellees MCI WorldCom Communications, Inc.
    and MCIMetro Access Transmission Services LLC.
    OPINION
    NOONAN, Circuit Judge:
    We must decide whether an incumbent local exchange car-
    rier’s challenge to nominally “interim” rates for access to its
    network by competitive local exchange carriers, which rates
    are set by a state utilities commission pursuant to the Tele-
    communications Act of 1996, is ripe for judicial review, even
    though such rates are subject to later adjustment by the state
    utilities commission (“a true-up”). When the incumbent local
    VERIZON v. PEEVEY                   7837
    exchange carrier has cognizable claims which cannot and will
    not be compensated by the true-up, we hold such challenge is
    ripe for judicial review.
    BACKGROUND
    The Telecommunications Act of 1996 (“the Act”), Pub. L.
    No. 104-104, 110 Stat. 56 (codified as amended in scattered
    sections of 47 U.S.C.) aims in part to introduce competition
    among local exchange carriers. Verizon Communs., Inc. v.
    FCC, 
    535 U.S. 467
    , 476-77 (2002). A “local exchange” is “a
    network connecting terminals like telephones, faxes, and
    modems to other terminals within a geographical area like a
    
    city.” 535 U.S. at 489
    . The Act recognizes two types of local
    exchange carriers. An “incumbent local exchange carrier”
    (“ILEC”) is a carrier that owns a local exchange. 
    Id. at 490
    (citing 47 U.S.C. § 251(h)). A “competitive local exchange
    carrier” (“CLEC”) is a carrier new to the market, without a
    local exchange of its own. 
    See 535 U.S. at 491-92
    . Absent
    regulation, “[a] newcomer could not compete with the incum-
    bent carrier to provide local service without coming close to
    replicating the incumbent’s entire existing network [or local
    exchange] . . . .” 
    Id. at 490
    .
    To foster competition, the Act requires that ILECs make
    available to CLECs “access” to the ILECs’ “network ele-
    ments” “on an unbundled basis.” 47 U.S.C. § 251(c)(3). A
    “network element” is “a facility or equipment used in the pro-
    vision of a telecommunications service” or those “features,
    functions, and capabilities that are provided by means of such
    facility or equipment, including subscriber numbers, data-
    bases, signaling systems, and information sufficient for billing
    and collection or used in the transmission, routing, or other
    provision of a telecommunications service.” 47 U.S.C.
    § 153(29). To provide “access” to a network element “on an
    unbundled basis” — or, said differently, to provide access to
    unbundled network elements (“UNEs”) — “is to lease the ele-
    ment, however described, to a requesting carrier at a stated
    7838                   VERIZON v. PEEVEY
    price specific to that element” without requiring that other
    elements also be leased (“bundled”). See Verizon Communs.,
    
    Inc., 535 U.S. at 531
    .
    Pursuant to the Act, CLECs requesting access to UNEs are
    first to attempt to negotiate rates for such access with the
    ILEC that owns the network. 47 U.S.C. §§ 251(c)(1),
    252(a)(1). If the parties successfully negotiate rates, the rele-
    vant state utilities commission is required to accept those rates
    unless they discriminate against a carrier not a party to the
    contract, or the rates are otherwise shown to be contrary to the
    public interest. 47 U.S.C. §§ 252(e)(1), (e)(2)(A). If the par-
    ties cannot agree on rates, any party to the negotiations may
    request arbitration to be conducted by the relevant state utili-
    ties commission. 47 U.S.C. § 252(b)(1).
    The Act assumes that a state utilities commission may
    refuse or otherwise fail to conduct the arbitration, in which
    case the Act provides that the Federal Communications Com-
    mission (“FCC”) shall act in the place and stead of the state
    utilities commission. See 47 U.S.C. § 252(e)(5). However,
    where, as here, the state utilities commission conducts the
    arbitration, such commission is bound by the Act’s provisions
    governing how the rates must be set and by the FCC’s related
    regulations, 47 U.S.C. § 252(c)(1)-(2), including regulations
    that require state utilities commissions to use the total element
    long run incremental cost (“TELRIC”) methodology. 47
    C.F.R. § 51.505; see also AT&T Corp. v. Iowa Utils. Bd., 
    525 U.S. 366
    , 385 (1999) (upholding the FCC’s jurisdiction to
    design a pricing methodology to bind state utilities commis-
    sions); Verizon Communs., 
    Inc., 535 U.S. at 497-528
    (uphold-
    ing the TELRIC regulations in particular). It is important to
    note that, in setting forth these requirements, neither the Act
    nor the FCC regulations distinguishes between “interim” rates
    and “final” rates. Cf. AT&T Communs. of Ill., Inc. v. Ill. Bell
    Tel. Co., 
    349 F.3d 402
    , 411 (7th Cir. 2003) (“[T]he possibility
    of repair in the future is no warrant for promulgating today a
    rate that deviates from the TELRIC standard. Federal law
    VERIZON v. PEEVEY                    7839
    requires that any rate for unbundled network elements,
    adopted by a state commission, comply with TELRIC when
    adopted.”) (emphasis added).
    In 1997, the California Public Utilities Commission
    (“CPUC”) established nominally interim rates for access by
    CLECs to Verizon’s UNEs. We characterize these rates as
    interim only in name because, for reasons not relevant here,
    the CPUC did not undertake the task of setting permanent
    rates until 2002. Even then, it did not set permanent rates, but
    rather held expedited proceedings to establish revised interim
    rates, which were to remain in effect until permanent rates
    could be established. After receiving several interim rate pro-
    posals from Verizon and interested CLECs, the CPUC issued
    the interim rate order that is at issue in this appeal. 2003 Cal.
    PUC LEXIS 168 (Cal. Pub. Util. Mar. 13, 2003). In brief, the
    revised interim rates were based on rates approved by the util-
    ities commission in New Jersey, where Verizon also is the
    ILEC; the rates were adjusted in an effort to reflect Verizon’s
    higher costs in California relative to New Jersey. 
    Id. at *109-
    10. Verizon alleges both that the methodology used to set the
    New Jersey rates does not comply with TELRIC as previously
    interpreted both by the FCC and CPUC, Compl. ¶¶ 36, 39, 42,
    and that “costs, network requirements, geography, demand
    levels, and other unique features [relevant to the setting of
    rates] may differ significantly by state . . . .” Verizon Compl.
    ¶¶ 35, 42-43. However, in an attempt to remedy these admit-
    ted problems, the CPUC made the interim rates subject to a
    “true-up” when the permanent rates finally were adopted.
    2003 Cal. PUC LEXIS at *110. A “true-up” is a determina-
    tion by the CPUC which adjusts the interim rates, either up or
    down, as of the earlier effective date of the interim rate order,
    so that the adjusted interim rates equal the permanent rates as
    set later in the permanent rate proceeding.
    The impact of the interim rate order entered March 13,
    2003 was immediately to reduce the rates that Verizon could
    charge CLECs for access to its UNEs relative to what it had
    7840                   VERIZON v. PEEVEY
    been able to charge under the earlier rate order. After the
    CPUC denied Verizon’s application for rehearing, Verizon
    brought an action in federal district court against Michael R.
    Peevey and other commissioners of the CPUC in their official
    capacities, in which Verizon alleged five claims: (1) that the
    interim rate order was arbitrary and capricious and not sup-
    ported by substantial evidence; (2) that the interim rate order
    was not in compliance with the Act nor with the regulations
    implementing the TELRIC methodology; (3) that the interim
    rate order was confiscatory; (4) that the interim rate order was
    in violation of due process; and (5) that the interim rate order
    was in violation of Verizon’s civil rights. Verizon sought to
    have the interim rate order declared unlawful and vacated, to
    have its enforcement enjoined, and to have the matter returned
    to the CPUC for further proceedings. Verizon also sought its
    costs and attorneys’ fees incurred in litigating the suit.
    AT&T Communications of California, Inc., MCI World-
    Com Communications, Inc., and MCIMetro Access Transmis-
    sion Services LLC intervened in the suit, after which Verizon
    filed a motion for partial summary judgment as to its first,
    second and fourth claims. However, concluding that Veri-
    zon’s first and second claims were not ripe for judicial
    review, the district court denied Verizon’s motion for partial
    summary judgment as to those two claims without reaching
    their merits, and sua sponte dismissed the same two claims.
    Then, after giving Verizon an opportunity to offer some mate-
    rial basis upon which to distinguish its remaining three
    claims, the district court dismissed those claims also for lack
    of ripeness. Verizon appealed the dismissal of its complaint.
    We have jurisdiction pursuant to 47 U.S.C. § 252(e)(6) and 28
    U.S.C. § 1291, and vacate and remand with instructions that
    the district court consider on the merits whether Verizon is
    entitled to the declaratory and injunctive relief.
    STANDARD OF REVIEW
    We review de novo whether claims are ripe for judicial
    review. Laub v. United States Dep’t of the Interior, 
    342 F.3d 1080
    , 1084 (9th Cir. 2003).
    VERIZON v. PEEVEY                    7841
    ANALYSIS
    [1] The Telecommunications Act of 1996 provides a single
    methodology for the setting of rates: TELRIC. “Federal law
    requires that any rate for unbundled network elements,
    adopted by a state commission, comply with TELRIC when
    adopted.” AT&T 
    Communs., 349 F.3d at 411
    . No provision is
    made by this law for any rate to be established in a different
    way. Verizon alleged that the CPUC had failed to comply.
    The issue was ready for judicial decision.
    [2] This obvious result has been clouded by our decision in
    US West Communs. v. MFS Intelenet, Inc., 
    193 F.3d 1112
    (9th
    Cir. 1999), understandably treated as precedent by the district
    court. In US West the contention was made and accepted by
    both parties that the rates were “interim only and may be
    adjusted by later pricing proceedings.” 
    Id. at 1118.
    But neither
    the legitimacy of interim rates nor possible adjustment by
    later pricing proceedings (a so-called true-up) is accepted by
    Verizon. As neither interim rates nor a true-up compensating
    for such costs as credit insurance are covered by TELRIC, we
    see no reason to import into this case the assumptions and
    admissions that were decisive in US West.
    [3] Verizon has presented a straightforward challenge to the
    basis on which the CPUC set the current rates; namely the
    rates set in New Jersey, with alleged inadequate adjustment
    for Verizon’s costs in California. Whether this short cut com-
    plied with federal law and the constitution is ripe for adjudica-
    tion.
    [4] Accordingly, the judgment of the district court is
    VACATED and the case is REMANDED.
    BEA, Circuit Judge, concurring:
    Although I join in the majority’s holding and its conclusion
    that Verizon’s claims are ripe for judicial review, I do not find
    7842                  VERIZON v. PEEVEY
    its distinction of US West Communications v. MFS Intelenet,
    
    193 F.3d 1112
    (9th Cir. 1999), to be compelling. I neverthe-
    less find US West to be distinguishable on a different basis,
    and take this opportunity to articulate that basis and also to
    respond to the many arguments advanced by the CPUC and
    intervenors in support of their view that Verizon’s claims are
    not ripe for judicial review even independent of US West.
    I.   US West Communications v. MFS Intelenet, Inc.
    The majority distinguishes US West on the basis that “nei-
    ther the legitimacy of interim rates nor possible adjustment by
    later pricing proceedings (a so-called true up) is accepted by
    Verizon,” slip op. at 7841, suggesting that, by contrast, US
    West did not contest “the legitimacy of interim rates.” I take
    this to mean that, according to the majority’s reading, US
    West did not contest the legitimacy of rates that, by virtue of
    being interim, need not be in compliance with the Act so long
    as US West was later made whole.
    With this I do not agree. As we explained there, “US West
    challenge[d] several of the pricing provisions as inconsistent
    with the pricing standards fixed by the Act.” 
    Id. at 1117-18.
    We nevertheless concluded that the claims were not ripe for
    judicial review primarily because US West conceded that the
    true-up would make it whole and, thus, might moot the
    appeal. 
    Id. at 1118-19.
    This does not mean that US West did
    not contest the legitimacy of such interim rates. Indeed, we
    expressly said otherwise:
    US West challenges the interim rates, but says its
    concerns would be resolved if TCG and MFS were
    ordered to compensate U.S. West for any differences
    between the interim rates and the permanent prices,
    referred to as an “administrative true-up.”
    . . . . Accordingly, we avoid unnecessary adjudica-
    tion by declining to review the interim prices now.
    VERIZON v. PEEVEY                   7843
    If a true-up is ordered, this appeal might become
    moot, as U.S. West has indicated it would be satis-
    fied with such an order.
    
    Id. at 1118-19
    (emphasis added).
    Thus, I find US West distinguishable from the case here not
    because US West did or did not contest the legitimacy of
    interim rates that do not comply with the Act and TELRIC
    methodology, but because it conceded that a true-up would
    make it whole whereas, by contrast, Verizon has made no
    similar concession. To the contrary, as I address more fully in
    Part II.B.1 below, Verizon has affirmatively alleged that the
    true-up will not make it whole in two different respects: (1)
    the loss of retail customers suffered during the period until
    permanent rates are established, which loss is claimed to be
    due to unlawfully low interim rates; and (2) the credit risk of
    nonpayment by CLECs of the difference between the rates as
    set by the interim rate order and as ultimately adjusted by the
    true-up, a risk Verizon has been and is presently forced to
    bear. Further, the CPUC agrees that these two elements of
    loss claimed by Verizon will not be considered in the true-up.
    Thus, to the extent that the district court here was obliged to
    accept Verizon’s allegations of uncompensable losses as true,
    an issue which I address in Part II.B.3 below, contrary to what
    was conceded in US West, any future true-up here cannot
    moot this appeal.
    Nor is there any merit in the argument of the CPUC and the
    intervenors that our rationale in US West applies here with
    even greater force than it did there because the true-up here
    is more certain to occur than it was in US West. Presumably
    the argument is that even in US West, we denied review where
    there was a possibility that US West would suffer losses that
    would not be compensated if, ultimately, the state utilities
    commission decided not to order a true-up. But here, to the
    extent Verizon’s allegations must be taken as true, Verizon
    has suffered, is suffering and will continue to suffer losses
    7844                   VERIZON v. PEEVEY
    uncompensable by a true-up; it is not a mere possibility. At
    the procedural phase in which we find ourselves and given
    Verizon’s allegations, it must be deemed a certainty.
    Finally, as alluded to above, the possibility that the appeal
    would be mooted was not the sole ground on which we relied
    in holding that the claims raised in US West were not ripe for
    judicial review. Rather, as we stated:
    Even if the appeal does not become moot, either
    because the true-up is denied or because [the
    CLECs] appeal[ ] the award of a true-up, this court
    will benefit from the Commission’s and the district
    court’s legal analysis of whether a true-up is autho-
    rized by the Act and from their assessment of
    whether it should be imposed in these particular
    cases.
    
    Id. at 1119.
    This rationale is inapplicable here because none
    of the parties are contesting whether a true-up is authorized
    nor whether it should be imposed here. It is admitted by all:
    The CPUC made the interim rates subject to a true-up, 2003
    Cal. PUC LEXIS 168, at *110 (Cal. Pub. Util. Mar. 13, 2003);
    there will be a true-up.
    In short, absent even the remotest possibility that Verizon’s
    claimed losses will be compensated through a true-up (assum-
    ing Verizon’s allegations to be true) thereby rendering this
    appeal moot, and in the absence of any suggestion that the
    parties intend to challenge the propriety of conducting a true-
    up either generally or as applied here, US West does not bind
    us. See Hart v. Massanari, 
    266 F.3d 1155
    , 1170 (9th Cir.
    2001) (“In determining whether it is bound by an earlier deci-
    sion, a court considers . . . the ‘reason and spirit of cases’
    [and] also ‘the letter of particular precedents.’ This includes
    not only the rule announced, but also the facts giving rise to
    the dispute . . . .”) (citation omitted).
    VERIZON v. PEEVEY                   7845
    II.    Ripeness
    Having so distinguished US West, I would consider
    whether the ripeness doctrine nevertheless bars Verizon’s
    action. The ripeness doctrine at issue here was first set forth
    in Abbott Laboratories v. Gardner, 
    387 U.S. 136
    , 153 (1967),
    and is a prudential, rather than jurisdictional, doctrine.
    National Audubon Society, Inc. v. Davis, 
    307 F.3d 835
    , 850
    (9th Cir. 2002), as amended by, 
    312 F.3d 416
    (9th Cir. 2002).
    It requires that “[i]n considering whether a case [challenging
    administrative action] is ripe for review, a court must evaluate
    [1] the fitness of the issues for judicial decision and [2] the
    hardship to the parties of withholding court consideration.”
    US 
    West, 193 F.3d at 1118
    (quoting Winter v. California
    Medical Review, Inc., 
    900 F.2d 1322
    , 1325 (9th Cir. 1990)
    (quoting Abbott 
    Laboratories, 387 U.S. at 149
    )) (internal quo-
    tation marks omitted). “A claim is fit for decision if the issues
    raised are primarily legal, do not require further factual devel-
    opment, and the challenged action is final.” 
    Id. (quoting Stan-
    dard Alaska Production Co. v. Schaible, 
    874 F.2d 624
    , 627
    (9th Cir. 1989)) (internal quotation marks omitted). “To meet
    the hardship requirement, a litigant must show that withhold-
    ing review would result in direct and immediate hardship and
    would entail more than possible financial loss.” 
    Id. (quoting Winter,
    900 F.2d at 1325) (internal quotation marks omitted).
    A.       The Fitness of the Issues for Judicial Decision
    1.    The Issues Raised Here Are Primarily Legal and
    Do Not Require Further Factual Development
    The requirements that the issues raised be primarily legal
    and not require further factual development are, in fact, the
    same. “[A] controversy is ‘essentially legal in nature’ . . .
    when no ‘further factual amplification is necessary.’ ” City of
    Auburn v. Qwest Corp., 
    260 F.3d 1160
    , 1172 (9th Cir. 2001)
    (quoting Western Oil & Gas Association v. Sonoma County,
    
    905 F.2d 1287
    , 1291 (9th Cir. 1990)). Verizon’s claims
    7846                   VERIZON v. PEEVEY
    require analysis only of the administrative record so that the
    court can determine whether the rates already imposed —
    whether interim or final — comply with the Act and relevant
    regulations, including the TELRIC methodology. See Fox
    Television Stations, Inc. v. Federal Communications Commis-
    sion, 
    280 F.3d 1027
    , 1039 (D.C. Cir. 2002) (holding that
    “whether the Commission’s determination [regarding certain
    ‘ownership rules’] was arbitrary and capricious or contrary to
    law” was a “purely legal” question). Thus, the claims require
    no further factual development and are primarily legal.
    2.   The Challenged Action Is Final
    Whether a challenged action is sufficiently “final” for judi-
    cial review depends on whether it is the sort of action which
    federal courts have jurisdiction to review. Under the Act, “[i]n
    any case in which a State commission makes a determination
    under [47 U.S.C. § 252], any party aggrieved by such deter-
    mination may bring an action in an appropriate Federal dis-
    trict court to determine whether the agreement or statement
    meets the requirements of [47 U.S.C. § 251] and [47 U.S.C.
    § 252].” 47 U.S.C. § 252(e)(6) (emphases added). We previ-
    ously have had occasion to define “a determination” for pur-
    poses of 47 U.S.C. § 252(e)(6) in the context of holding that
    a utility need not exhaust available state remedies before
    seeking judicial review in federal court of a final rate order set
    by the CPUC. AT&T Communications Systems v. Pacific Bell,
    
    203 F.3d 1183
    , 1184 (9th Cir. 2000). In so doing, we
    expressly distinguished the judicial review provision in the
    Act from that in the Administrative Procedure Act (“APA”),
    noting that whereas the APA “authorizes review only of ‘final
    agency action,’ 5 U.S.C. § 704, section 252 does not provide
    that there must be a ‘final’ determination after exhaustion of
    all available remedies.” 
    Id. Rather, we
    explained, “[i]t
    requires only that there be ‘a determination,’ ” and, thus, we
    held that “[a] state commission’s decision can be ‘a determi-
    nation’ even if it is subject to a request for rehearing so long
    VERIZON v. PEEVEY                          7847
    as the decision is operational or binding on the parties in the
    absence of a request for rehearing.” 
    Id. (emphasis added).
    At least to the extent Verizon’s allegations of uncompens-
    able harm are accepted as true, the interim rate order here is
    both operative and binding on Verizon. The order was entered
    on and effective as of March 13, 2003. 2003 Cal. PUC LEXIS
    168, at *117. If Verizon refuses to comply, it faces substantial
    penalties. Cal. Pub. Util. Code §§ 2107-08 (providing for a
    penalty of as much as $20,000 for “each offense” and provid-
    ing that “in case of a continuing violation each day’s continu-
    ance thereof shall be a separate and distinct offense”). And
    although the interim rates may be subject to a true-up, the
    losses that are alleged to result from the operation of the rates
    today are alleged to be uncompensable by means of the true-
    up.
    The CPUC and the intervenors, however, attempt to distin-
    guish AT&T Communications Systems on the grounds that the
    question there was whether exhaustion of state remedies was
    required and that the rates challenged there were final rather
    than interim. Admittedly, we faced a different question in
    AT&T Communications Systems than we face here. But, as I
    began my analysis, whether a challenged action is sufficiently
    “final” for judicial review depends on whether it is the sort of
    action which federal courts have jurisdiction to review. The
    Act authorizes judicial review for “determination[s]” by state
    commissions, 47 U.S.C. § 252(e)(6), and I see no reason why
    we should define the statutory term differently for purposes of
    the ripeness doctrine than we did for purposes of the exhaus-
    tion doctrine.1
    1
    Indeed, we recently explained that the ripeness doctrine as it pertains
    to “cases involving administrative agencies . . . recognize[s] that judicial
    action should be restrained when other political branches have acted or
    will act,” Principal Life Insurance Co. v. Robinson, 
    394 F.3d 665
    , 670
    (9th Cir. 2004), and that “[p]rinciples of federalism lend this doctrine
    additional force when a federal court is reviewing a state agency decision
    at an interim stage in an evolving process.” US 
    West, 193 F.3d at 1118
    .
    Both of these rationale are not unlike those underlying the exhaustion doc-
    trine.
    7848                   VERIZON v. PEEVEY
    Further, the CPUC and the intervenors’ emphasis on the
    fact that the rates here are nominally interim rather than final
    is misplaced for at least three reasons. First, Verizon’s argu-
    ment today is not with the final rates. Even if the final rates
    fully comply with the TELRIC methodology and even with
    the ensuing true-up, Verizon would still mount the same chal-
    lenge to the interim rates that it makes today. Thus, neither its
    claims, nor the CPUC’s nor the intervenors’ defenses, would
    differ if they were to litigate after the final rates are promul-
    gated.
    Second, the assumption that interim rates are substantially
    more fleeting than final rates and, thus, that there is or should
    be something fundamentally different about the way in which
    interim rates are or are not reviewed, is belied by the facts.
    The interim rates here have already been in effect for more
    than two years, and we are informed that although permanent
    rates may be set this year, they could be set as late as next
    year. By comparison, final rates that “are set by state commis-
    sions” are “usually” done so pursuant to “arbitrated agree-
    ments with [only] 3- or 4-year terms,” Verizon
    Communications Inc. v. Federal Communications Commis-
    sion, 
    535 U.S. 467
    , 505 (2002) (emphasis added), and likely
    change thereafter.
    Third, the CPUC and the intervenors’ position largely boils
    down to the indefensible proposition that a state commission
    can insulate its “determination[s]” from judicial review by
    labeling them “interim.” This would eviscerate the judicial
    review provided by statute and cannot be, particularly in light
    of the fact that, as the history of this case demonstrates, so-
    called interim rates can remain in effect for years, command
    immediate compliance on pain of sanctions, and can allegedly
    cause losses which are, and will be, uncompensable.
    Recognizing this potential for abuse, the CPUC concedes
    that particularly arbitrary rates should be subject to judicial
    review even if interim. See, e.g., CPUC Br. at 19-20; Jan. 21,
    VERIZON v. PEEVEY                          7849
    2005 Oral Arg. at 00:37:37 - 00:38:09. Although the degree
    of arbitrariness of an interim rate may render it more or less
    in need of judicial review, it does not render an interim rate
    more or less “a determination” and, thus, fit for judicial
    review.
    The CPUC also defends its position by arguing that interim
    and unreviewable rates are useful regulatory tools in that they
    permit the CPUC to set rates relatively quickly, without the
    considerable delay and expense of procuring and reviewing
    cost studies and holding full hearings. Hence, argues the
    CPUC, such rates better effect the purpose of the Act, which
    is to promote competition among local exchange carriers. The
    CPUC’s assumption, however, that absent its rate setting there
    will be no competition, is in error. To begin, even before the
    interim rate order at issue here, Verizon already was making
    its network available to competitors under rates set by the
    CPUC. Further, even absent such a circumstance, an ILEC
    and CLECs are always free to negotiate rates.2 If they cannot
    agree on rates, and the CPUC is without the resources to set
    rates in a timely fashion, it can defer to the determinant power
    of the FCC. See 47 U.S.C. § 252(e)(5) (“If a State commis-
    sion fails to act to carry out its responsibility under this sec-
    tion in any proceeding or other matter under this section, then
    the [FCC] shall issue an order preempting the State commis-
    sion’s jurisdiction of that proceeding or matter within 90 days
    after being notified (or taking notice) of such failure, and shall
    assume the responsibility of the State commission under this
    section with respect to the proceeding or matter and act for
    the State commission.”). Finally, even if there were no such
    provisions for the parties to negotiate rates or for the FCC to
    set rates such that the absence of interim rates would mean the
    absence of competition among local exchange carriers, the
    2
    Indeed, I note that Verizon alleges that it “proposed a voluntary reduc-
    tion of certain of its UNE rates on an interim basis in order to meet the
    Commission’s goal of expeditiously reducing rates,” but that this proposal
    was rejected. Compl. ¶ 29.
    7850                   VERIZON v. PEEVEY
    fact remains that Congress did not provide in the Act for rates
    — interim or otherwise — that are binding but that neverthe-
    less do not comply with federal law and regulations such as
    the TELRIC methodology. See AT&T Communications of Illi-
    nois, Inc. v. Illinois Bell Telephone Co., 
    349 F.3d 402
    , 411
    (7th Cir. 2003) (“[T]he possibility of repair in the future is no
    warrant for promulgating today a rate that deviates from the
    TELRIC standard. Federal law requires that any rate for
    unbundled network elements, adopted by a state commission,
    comply with TELRIC when adopted.”). We are not a junior
    varsity legislature; neither is the CPUC. Cf. Mistretta v.
    United States, 
    488 U.S. 361
    , 427 (1989) (Scalia, J., dissent-
    ing). We both must abide by what Congress has provided and
    live without that which it has withheld.
    Thus, I would conclude that the interim rate order here is
    sufficiently final for judicial review.
    B.     The Hardship to the Parties of Withholding
    Judicial Consideration
    1.    Verizon’s Alleged Uncompensable Harm
    In its complaint seeking declaratory and injunctive relief,
    Verizon alleged that the CPUC’s interim rate order caused
    immediate harm to Verizon by requiring Verizon both: (1) to
    subsidize CLECs in the form of unlawfully low rates, which
    resulted in Verizon’s loss of retail customers; and (2) to bear
    the credit risk that the CLECs benefitting from the interim
    rates will not exist at the time the true-up takes effect or will
    lack the wherewithal to pay the difference between the
    interim rates and the permanent rates for the period of time
    the interim rates were in effect. Verizon further alleged that
    the promised true-up would not compensate Verizon for either
    of these harms:
    ILECs would be irreparably harmed if state commis-
    sions could impose artificially low UNE rates sub-
    VERIZON v. PEEVEY                        7851
    ject to the promise of a later true-up. Even assuming
    that a true-up were actually to occur at some future
    date, the [interim] Rate Order’s below-cost UNE
    rates cause Verizon California irreparable harm
    because they give CLECs an arbitrary competitive
    advantage that allows them to take customers away
    from Verizon California. This harm cannot be cured
    by the prospect of a future true-up of the Commis-
    sion’s erroneous rates. Moreover, any true-up could
    be years away, thus exacerbating the harm. There is,
    moreover, no guarantee that CLECs who have
    received the benefit of below-cost rates will still exist
    and have the resources to pay back their windfall —
    let alone do so willingly without protracted litigation
    — at some future point when the Commission cor-
    rects its erroneous rates.
    ....
    . . . . As a result of the interim UNE rates set by the
    Commission, Verizon California has been aggrieved
    within the meaning of Section 252(e)(6) of the 1996
    Act, 47 U.S.C. § 252(e)(6). California’s “interim”
    UNE rates will enable Verizon California’s competi-
    tors to procure UNEs from Verizon California at
    rates well below Verizon California’s costs of pro-
    viding UNEs. Further, they will enable Verizon Cal-
    ifornia’s competitors to win over Verizon
    California’s customers, not because the competitors
    are more efficient or innovative, but because they
    have won a substantial regulatory windfall in the
    form of below-cost UNE rates.
    Compl. ¶¶ 44, 46 (emphasis added).3
    3
    There is, in my view, no merit in the argument by the CPUC and the
    intervenors that harm resulting from Verizon’s loss of customers is not
    cognizable because the very purpose of the Act is to promote competition
    7852                      VERIZON v. PEEVEY
    Nor does the CPUC contest that the future true-up will
    afford Verizon no real remedy for the losses Verizon alleged.
    Indeed, at oral arguments, the CPUC conceded not only that
    the true-up as contemplated will not account for these losses,
    but that federal law would not permit the CPUC to set future
    rates so as to compensate Verizon for past harms resulting
    from artificially low rates. Jan. 12, 2005 Oral Arg. at
    00:33:59-00:34:58.
    The CPUC’s stated position at oral arguments is quite cor-
    rect. Where any party requests compulsory arbitration by the
    state utilities commission, the commission “shall . . . establish
    any rates for . . . network elements according to subsection (d)
    of this section.” 47 U.S.C. § 252(c)(2). Subsection (d)
    requires in relevant part that “[d]eterminations by a State
    commission of . . . the just and reasonable rate for network
    elements . . . shall be . . . based on the cost . . . of providing
    the . . . network element . . . and . . . may include a reasonable
    profit.” 47 U.S.C. § 252(d) (emphasis added). The FCC, in
    turn, promulgated regulations interpreting this subsection:
    The 1996 Act requires the states to set prices for
    interconnection and unbundled elements that are
    cost-based, nondiscriminatory, and may include a
    reasonable profit. To help the states accomplish this,
    the Commission concludes that the state commis-
    sions should set arbitrated rates for interconnection
    and access to unbundled elements pursuant [to] a
    forward-looking economic cost pricing methodol-
    ogy. The Commission concludes that the prices that
    new entrants pay for interconnection and unbundled
    in the intrastate telecommunications markets. Competition does not typi-
    cally demand that firms subsidize their competitors, which, according to
    Verizon, is precisely what has happened here. Nor does the Act suggest
    otherwise. I hasten to add, however, that I express no opinion as to
    whether Verizon has proven or, on remand, will be able to prove its alle-
    gations that the interim rates here are unlawfully low.
    VERIZON v. PEEVEY                          7853
    elements should be based on the local telephone
    companies Total Service Long Run Incremental Cost
    of a particular network element, which the Commis-
    sion calls “Total Element Long-Run Incremental
    Cost” (TELRIC), plus a reasonable share of
    forward-looking joint and common costs.
    11 F.C.C.R. 15,499, at ¶ 29 (1996) (emphases added), as
    amended by 11 F.C.C.R. 22,301 (1996); see also 47 C.F.R.
    § 51.505.4 There is, in short, no provision either in the Act or
    in the FCC’s regulations for rates to be based so as to com-
    pensate ILECs for past damages of the sort alleged here.
    The CPUC and the intervenors argue, however, that any
    such alleged harm is temporary or speculative or is otherwise
    not cognizable under the ripeness doctrine either because the
    interim rates do not require Verizon to alter its “conduct” or
    because the harm is mere financial loss. I address each of
    these arguments in turn.
    4
    The Supreme Court has explained the TELRIC methodology as fol-
    lows:
    “The TELRIC of an element has three components, the operating
    expenses, the depreciation cost, and the appropriate risk-adjusted
    cost of capital.” A concrete example may help. Assume that it
    would cost $1 a year to operate a most efficient loop element;
    that it would take $10 for interest payments on the capital a car-
    rier would have to invest to build the lowest cost loop centered
    upon an incumbent carrier’s existing wire centers (say $100, at
    10 percent per annum); and that $9 would be reasonable for
    depreciation on that loop (an 11-year useful life); then the annual
    TELRIC for the loop element would be $20.
    The actual TELRIC rate charged to an entrant leasing the element
    would be a fraction of the TELRIC figure, based on a “reasonable
    projection” of the entrant’s use of the element (whether on a flat
    or per-usage basis) as divided by aggregate total use of the ele-
    ment by the entrant, the incumbent, and any other competitor that
    leases it.
    Verizon Communications 
    Inc., 535 U.S. at 496
    & n.16 (citations omitted).
    7854                        VERIZON v. PEEVEY
    First, the CPUC and the intervenors argue that Verizon’s
    harm is only temporary or speculative because any retail cus-
    tomers that Verizon may lose while the interim rates are in
    effect may return once the permanent rates are set, and
    because the true-up will compensate Verizon for any differ-
    ence in the rates it charges CLECs under the interim rate
    order and what it will be able to charge CLECs under the per-
    manent rate order. As for the loss of retail customers, even
    assuming that every customer who allegedly left Verizon
    under the interim rates returns under the permanent rates,5
    Verizon will not be compensated for the loss of revenue from
    the loss of such retail customers while the interim rates were
    in effect. The true-up adjustment will be based on the cost of
    the UNEs, and not on the basis of what the competitors’ retail
    customers might have paid Verizon had they not changed ser-
    vice providers.
    As for the adjusted rates that Verizon may charge pursuant
    to the true-up for the interim period, the credit risk that Veri-
    zon has been forced to bear exists independently of whether
    the intervenors and other CLECs ultimately pay the true-up.
    If an investor is forced to accept junk bonds, of equal amount
    and maturity, in place of Treasury bonds, he may buy credit
    insurance; but the insurance premium will reduce his return.
    Similarly here, were Verizon to buy credit insurance on the
    intervenors’ payments pursuant to the true-up, the cost of such
    credit insurance is not an element of TELRIC.6 Thus, nothing
    about Verizon’s alleged present uncompensable harm is con-
    5
    Nor is there reason to so assume. In the parlance of economists, given
    the transaction costs that customers bear when they switch service provid-
    ers and given the price differentials among service providers under the
    interim rates relative to those under the permanent rates, it may not be effi-
    cient for customers to return to Verizon even if was efficient for them to
    leave in the first place.
    6
    Of course, Verizon — like the junk-bond holder — could choose to run
    the risk of nonpayment, with the predictable effect on its financial state-
    ments and own creditworthiness, but that is an option some might not
    think prudent in these days of vigilance over corporations.
    VERIZON v. PEEVEY                   7855
    tingent upon future events and, thus, as alleged, is either tem-
    porary or speculative. Cases in which this court and others
    have found claims to be unripe for judicial review on the basis
    of the alleged harm being temporary or speculative are there-
    fore inapposite.
    Second, the CPUC and the intervenors argue that Verizon’s
    alleged harm is not cognizable under the hardship prong of
    the ripeness analysis because the interim rate order does not
    require Verizon to alter its “conduct” but only its rates. Here,
    the CPUC and the intervenors rely on language in cases stat-
    ing that claims are ripe for review only when the challenged
    agency action requires a change in “conduct.” E.g., Abbot
    
    Laboratories, 387 U.S. at 153
    (holding that “where a regula-
    tion requires an immediate and significant change in the
    plaintiffs’ conduct of their affairs with serious penalties
    attached to noncompliance, access to the courts . . . must be
    permitted”); Association of American Medical Colleges v.
    United States, 
    217 F.3d 770
    , 783 (9th Cir. 2000) (“Courts typ-
    ically read the Abbott Laboratories rule to apply where regu-
    lations require changes in present conduct on threat of future
    sanctions.”). I can discern no reason why setting rates should
    not be considered “conduct,” nor do the cases support such a
    position. Indeed, even the cases on which the CPUC and the
    intervenors rely make clear that the references to changes in
    “conduct” are meant to distinguish situations where the
    agency action has “direct and immediate” impact on plaintiffs
    from situations in which the impact may be indirect or specu-
    lative. Abbott 
    Laboratories, 387 U.S. at 152-53
    ; Association
    of American Medical 
    Colleges, 217 F.3d at 783-84
    (distin-
    guishing Abbott Laboratories from its companion case, Toilet
    Goods Association, Inc. v. Gardner, 
    387 U.S. 158
    , 163-65
    (1967), wherein the Supreme Court found the challenged
    action not ripe for judicial review, on the grounds that “the
    impact of the regulation was [there] not ‘felt immediately by
    those subject to it in conducting their day-to-day affairs’ ”).
    Here, there is no question that the interim rate order had a
    direct and immediate effect upon Verizon.
    7856                   VERIZON v. PEEVEY
    Third, the CPUC and the intervenors correctly note that we
    have often stated that mere financial loss is not a cognizable
    harm for purposes of the hardship analysis under the ripeness
    doctrine. E.g., Principal Life Insurance 
    Co., 394 F.3d at 670
    ;
    US 
    West, 193 F.3d at 1118
    ; Village of Gambell v. Babbitt,
    
    999 F.2d 403
    , 408 (9th Cir. 1993); Municipality of Anchorage
    v. United States, 
    980 F.2d 1320
    , 1325-26 (9th Cir. 1992);
    Dietary Supplemental Coalition, Inc. v. Sullivan, 
    978 F.2d 560
    , 562, 564 (9th Cir. 1992); Western Oil & Gas Associa-
    
    tion, 905 F.2d at 1291
    ; 
    Winter, 900 F.2d at 1325
    . However,
    Verizon has alleged the loss of customers, which is not mere
    financial loss. See Midcoast Interstate Transmission, Inc. v.
    Federal Energy Regulatory Commission, 
    198 F.3d 960
    , 969-
    70 (D.C. Cir. 2000) (holding that the petitioners for review of
    agency orders were sufficiently aggrieved from the resulting
    loss of customers that their claims were ripe for judicial
    review).
    Further, to the extent Verizon’s alleged harm can be char-
    acterized as mere financial loss, although we have often
    repeated the refrain that mere financial loss is insufficient to
    establish hardship, none of the cases cited above turn on the
    fact that the loss was merely financial. Indeed, I have found
    only two cases in which we held that claims were unripe for
    judicial review at least in part because the harm was mere
    financial loss, both of which are readily distinguishable from
    the case here, either because there was no suggestion that the
    financial loss was uncompensable or because the challenged
    action was otherwise not ripe for judicial review. State of Cal-
    ifornia, Department of Education v. Bennett, 
    833 F.2d 827
    ,
    833-34 (9th Cir. 1987) (holding unripe for judicial review the
    California Department of Education’s claim that Bennett was
    without authority to charge prejudgment interest on misap-
    plied Title I funds because “the harm that is presaged is lim-
    ited to financial expense,” but there, in the event that the
    California Department of Education ultimately prevailed, it
    would suffer no harm because it would not be required to pay
    the prejudgment interest); Hawaiian Electric Co. v. United
    VERIZON v. PEEVEY                           7857
    States Environmental Protection Agency, 
    723 F.2d 1440
    ,
    1445 (9th Cir. 1984) (“HECO’s alleged financial hardship . . .
    is insufficient to outweigh the inappropriateness of the issues
    for judicial resolution.”). Moreover, we have held that agency
    action that delayed indefinitely “recover[y] in tort” and “reim-
    bursement for . . . compensation payments” “creat[ed] a prac-
    tical hardship” sufficient to render a claim ripe for judicial
    review. Chavez v. Director, Office of Workers Compensation
    Programs, 
    961 F.2d 1409
    , 1415-16 (9th Cir. 1992).
    Finally, that the alleged harm here is uncompensable by
    means of the true-up is significant. The refrain regarding
    financial loss repeated in each of these cases was first uttered
    by the Supreme Court in Abbott Laboratories. There, the
    Supreme Court agreed with an argument advanced by the
    government that “ ‘mere financial expense’ is not a justifica-
    tion for pre-enforcement judicial review,” holding that “possi-
    ble financial loss is not by itself a sufficient interest to sustain
    a judicial challenge to governmental action.” Abbott Labora-
    
    tories, 387 U.S. at 153
    (emphasis added). That mere financial
    loss would not typically justify pre-enforcement judicial
    review is not at all surprising because typically “adequate
    compensatory or other corrective relief will be available at a
    later date, in the ordinary course of litigation.” See Los Ange-
    les Memorial Coliseum Commission v. National Football
    League, 
    634 F.2d 1197
    , 1202 (9th Cir. 1980) (quoting Samp-
    son v. Murray, 
    415 U.S. 61
    , 90 (1974)); cf. Toilet Goods
    
    Association, 387 U.S. at 164-65
    (holding that the challenge to
    administrative action was not ripe for judicial review in part
    because “no irremediable adverse consequences [would] flow
    from requiring a later challenge to this regulation”). There is
    no reason to conclude that is the case here.7
    7
    In so concluding, I do not assume that the statutory provisions provid-
    ing for federal review of “determination[s]” by state utilities preclude
    relief in the form of damages. See Verizon Maryland Inc. v. Public Service
    Commission of Maryland, 
    535 U.S. 635
    , 643-44, 647-48 (2002) (holding
    that the provision for federal review of “determination[s]” by state utilities
    7858                        VERIZON v. PEEVEY
    2.    Procedural Context
    The resolution of the appeal, then, must turn on whether
    Verizon’s allegations were sufficient to support its claim of
    hardship or, rather, whether the district court was correct to
    dismiss Verizon’s claims in the absence of evidence of Veri-
    zon’s hardship. Before considering this question, however,
    three preliminary points must be made regarding the proce-
    dural context in which the district court’s orders were ren-
    dered.
    First, at no point did the CPUC nor the intervenors file a
    cross-motion for summary judgment nor a motion to dismiss.
    in 47 U.S.C. § 252(e)(6) neither limits the general grant of jurisdiction in
    28 U.S.C. § 1331 nor “places [any] restriction on the relief a court can
    award”); BellSouth Telecommunications, Inc. v. Georgia Public Service
    Commission, 
    400 F.3d 1268
    , 1271 (11th Cir. 2005) (affirming the district
    court’s judgment against a state utilities commission for damages that
    BellSouth Telecommunications suffered as a result of the commission’s
    prior unlawfully established rates). Rather, I note only that the question of
    whether sovereign immunity would preclude Verizon from suing the
    CPUC for damages is very much unsettled. Compare MCI Telecommuni-
    cation Corp. v. Bell Atlantic-Pennsylvania, 
    271 F.3d 491
    , 509-13 (3d Cir.
    2001) (holding that states waive their sovereign immunity by voluntarily
    participating in the scheme established by the Act), AT&T Communica-
    tions v. BellSouth Telecommunications Inc., 
    238 F.3d 636
    , 643-47 (5th
    Cir. 2001) (same), MCI Telecommunications Corp. v. Illinois Bell Tele-
    phone Co., 
    222 F.3d 323
    , 338-44 (7th Cir. 2000) (same), MCI Telecommu-
    nications Corp. v. Public Service Commission of Utah, 
    216 F.3d 929
    , 935-
    39 (10th Cir. 2000) (same), US West Communications, Inc. v. TCG Seat-
    tle, 
    971 F. Supp. 1365
    , 1368-70 (W.D. Wash. 1997) (same), with Bell
    Atlantic Maryland, Inc. v. MCI WorldCom, Inc., 
    240 F.3d 279
    , 290-94
    (4th Cir. 2001) (holding that states do not waive their sovereign immunity
    by participating in the scheme established by the Act), vacated on other
    grounds sub nom. Verizon Maryland Inc. v. Public Service Commission of
    Maryland, 
    535 U.S. 635
    (2002), GTE North, Inc. v. Strand, 
    209 F.3d 909
    ,
    922 n.6 (6th Cir. 2000) (“[I]t is virtually certain that a state utility commis-
    sion’s decision to accept regulatory authority under the [Act] cannot legiti-
    mately be construed as a valid waiver of sovereign immunity.”).
    VERIZON v. PEEVEY                     7859
    Second, in their brief in opposition to Verizon’s motion for
    partial summary judgment, neither the intervenors nor appar-
    ently the CPUC presented any evidence contradicting Veri-
    zon’s claims of irreparable harm. Further, in its reply brief in
    support of its motion, Verizon specifically reserved the oppor-
    tunity to make a showing that Verizon had suffered and would
    continue to suffer irreparable harm if the district court deemed
    such a showing necessary.
    Third, once the district court denied in part Verizon’s
    motion for summary judgment and dismissed Verizon’s first
    two claims, Verizon had no meaningful opportunity to present
    evidence to substantiate its claim of hardship. The district
    court’s order dismissing Verizon’s first two claims in no way
    invited Verizon to submit evidence that its remaining claims
    were ripe. Rather, the district court held that “[i]t appears that
    the Court’s ruling on ripeness grounds also forecloses Plain-
    tiff’s remaining three causes of action,” but permitted Verizon
    to file “a written response demonstrating why its remaining
    three claims should not be dismissed following the Court’s
    ripeness ruling.” Verizon California, Inc. v. Peevey, No. C03-
    2838 THE, slip op. at 6-7 (N.D. Cal. Jan. 13, 2004) (emphasis
    added). In other words, the district court was inviting Verizon
    to demonstrate why the district court’s reasoning as to the first
    two claims was not also applicable to the remaining three
    claims. Further, even if Verizon did take the opportunity to
    present evidence, that would not have impacted the district
    court’s ruling as to the first two claims. The court never sug-
    gested that it would reconsider its dismissal of the first two
    claims.
    Thus, at the time the district court denied Verizon’s motion
    for partial summary judgment and dismissed Verizon’s first
    two claims, Verizon had repeatedly alleged irreparable harm,
    and neither the CPUC nor the intervenors had filed a disposi-
    tive motion nor introduced evidence to the contrary. Further,
    once the district court denied Verizon’s motion for partial
    7860                   VERIZON v. PEEVEY
    summary judgment and dismissed Verizon’s first two claims,
    Verizon had no meaningful opportunity to present evidence.
    3.   The District Court’s Order
    In denying Verizon’s motion for partial summary judgment
    and dismissing Verizon’s first two claims (and, later, the
    remainder of Verizon’s complaint), the district court first held
    as a matter of law that Verizon’s allegations of irreparable
    harm were irrelevant. As the district court stated: “The only
    discernible difference between this case and US West v. MFS
    appears to be that US West admitted that its concerns would
    be resolved by the pending true-up, whereas Verizon disputes
    this issue. The Court is unconvinced that this difference is
    material.” The district court then held in the alternative that
    even if US West did not control the case, the court would still
    hold that Verizon’s claims were not ripe for judicial review
    because “possible financial loss is not sufficient to establish
    hardship” and Verizon’s arguments regarding loss of custom-
    ers “rests on pure speculation, and such speculative harm does
    not constitute irreparable injury.” 
    Id. at 4-6.
    The district court’s first holding was error, as explained in
    Part I above. Indeed, I can think of no more of a material dif-
    ference to ripeness analysis than that US West stipulated it
    could recover its claimed damages through a true-up while
    Verizon claims it cannot, and the CPUC agrees with Verizon.
    The district court’s alternative holding likewise was error. As
    detailed in Part II.B.1 above, Verizon has alleged that its harm
    is not compensable through the true-up. This harm, as
    pleaded, is direct and immediate rather than contingent on
    future events and thus potentially temporary or speculative.
    Further, as pleaded, it is cognizable as hardship even to the
    extent resulting from the setting of rates as opposed to other
    conduct, and even to the extent limited to mere financial loss.
    This is sufficient to warrant judicial review, given the proce-
    dural posture of the case, as detailed in Part II.B.2 above.
    “The question of ripeness, like other challenges to a court’s
    VERIZON v. PEEVEY                          7861
    subject matter jurisdiction, is treated as a motion to dismiss
    under Rule 12(b)(1),” and, thus, “[i]t is the burden of the com-
    plainant to allege facts demonstrating the appropriateness of
    invoking judicial resolution of the dispute.” 15 Moore’s Fed-
    eral Practice § 101.73[1] (2005) (emphasis added).8
    Thus, in Gardner v. Toilet Goods Association, 
    387 U.S. 167
    , 168-70 (1967), a companion case to Abbott Laborato-
    ries, Toilet Goods Association challenged regulations promul-
    gated by the Secretary of Health, Education and Welfare and
    sued for injunctive and declaratory relief. The Secretary
    moved to dismiss on ripeness grounds, the district court
    denied the motion, and the Second Circuit affirmed. 
    Id. at 170-71
    & n.1. The Supreme Court likewise affirmed, 
    id. at 170,
    holding in relevant part: “We cannot say on this record
    that the burden of [compliance with the regulations at issue]
    is other than substantial, accepting, as we must on a motion
    to dismiss on the pleadings, the allegations of the complaint
    and supporting affidavits as true.” 
    Id. at 172
    (emphasis
    added).
    Likewise, in Midcoast Interstate Transmission, Inc., Mid-
    coast petitioned for review of the Federal Energy Regulatory
    Commission’s (“FERC”) orders granting Southern Natural
    Gas Company’s (“Southern”) application to construct a natu-
    ral gas pipeline and, as is relevant here, FERC’s order that
    Southern could recover the cost of the new pipeline construc-
    tion through “rolled-in” rather than “incremental” pricing.
    Midcoast Interstate Transmission, 
    Inc., 198 F.3d at 963-64
    . In
    rolled-in pricing, “the cost of the new facilities are added to
    the pipeline’s total rate base and reflected in rates charged to
    all customers system-wide,” whereas in incremental pricing,
    “an additional charge [is imposed] solely [on those] customers
    who are directly served by the expansion facilities.” 
    Id. at 8
        I emphasize that in reaching these conclusions, I do not rely on any of
    the evidence that Verizon submitted in connection with its appeal without
    first having submitted it to the district court.
    7862                  VERIZON v. PEEVEY
    964. Midcoast claimed that FERC’s approval of rolled-in
    rates ignored the agency’s own policy and precedent, 
    id., and contended
    that “but for that determination, it would not be
    faced with the loss of the Cities’ business upon completion of
    the North Alabama Pipeline.” 
    Id. at 969.
    Midcoast reasoned
    that had FERC required incremental pricing, Southern’s rates
    for users of the North Alabama Pipeline would have been so
    high relative to the rates that Midcoast proposed to charge for
    a competing project that FERC would not have authorized the
    construction of Southern’s North Alabama Pipeline. 
    Id. The D.C.
    Circuit — which, I note, has particular expertise
    in administrative law — held:
    If [Midcoast’s] claim survives analysis, there can be
    no question that Midcoast has suffered a certain,
    concrete injury that satisfies both the statutory
    and constitutional requirements for judicial review.
    Whether Midcoast is aggrieved is a question of fact;
    and where they are in dispute, a court must assume
    the correctness of the challenging party’s version of
    the facts. . . .
    . . . . Midcoast has presented facts which, if correct,
    fully support a finding that it has been aggrieved by
    the pricing determination. . . .
    Accepting, as we must for purposes of our analysis,
    the accuracy of Midcoast’s calculation of the incre-
    mental rate Southern would be required to charge,
    we are satisfied that Midcoast has been aggrieved.
    As a direct consequence of the agency’s action and
    irrespective of the outcome of a future rate proceed-
    ing, Midcoast will have lost the Cities’ business
    from the moment the North Alabama Pipeline begins
    deliveries of natural gas until the time that the Cities
    VERIZON v. PEEVEY                     7863
    are released from their obligations under the South-
    ern contracts. . . .
    It is for this reason that we also find the issue ripe
    for review. . . . Because Midcoast faces an imminent
    loss irrespective of the outcome of a future rate pro-
    ceeding, there can be no question that the Commis-
    sion’s pricing determination is ripe for review under
    the classic test established in Abbott Laboratories v.
    Gardner, 
    387 U.S. 136
    , 149, 
    87 S. Ct. 1507
    , 
    18 L. Ed. 2d 681
    (1967): the legality of the rolled-in pric-
    ing determination is fit for immediate judicial deci-
    sion, and the hardship faced by Midcoast is
    indisputable.
    
    Id. at 969-70
    (emphases added).
    Similarly, in City of New Orleans v. Federal Energy Regu-
    latory Commission, 
    67 F.3d 947
    , 948 (D.C. Cir. 1995), the
    City of New Orleans and Entergy challenged an order by
    FERC allowing Entergy to spin-off two electricity generating
    plants because the order addressed the “prudence” of the spin-
    off only as to its current effect on rates up until such time as
    the utility system would need to purchase new capacity.
    FERC argued that the petitioners were not yet “aggrieved”
    parties, 
    id. at 952,
    but the D.C. Circuit disagreed:
    The challenging parties assert that the transfer will
    aggrieve them eventually in the form of unreason-
    able rates, and so was not prudently entered into. If
    they are correct, as we must assume them to be for
    purposes of determining their aggrievement, they
    had a right to a review of FERC’s decision on the
    prudence of the transaction in terms of its effect on
    ratepayers.
    
    Id. (emphasis added).
    7864                  VERIZON v. PEEVEY
    Verizon indisputably “allege[d] facts demonstrating the
    appropriateness of invoking judicial resolution of the dis-
    pute,” 15 Moore’s Federal Practice § 101.73[1] (2005), as
    detailed in Part II.B.1 above. Nor, as detailed in Part II.B.2
    above, did the CPUC nor the intervenors file a cross-motion
    for summary judgment nor even proffer evidence in respond-
    ing to Verizon’s motion for partial summary judgment that
    might have obliged Verizon to substantiate its allegations. In
    this procedural context and particularly given Verizon’s spe-
    cific reservation of the opportunity to present evidence should
    the district court desire, the district court’s sua sponte dis-
    missal was error. Accordingly, I join with the majority in
    vacating the district court’s orders denying Verizon’s motion
    for partial summary judgment and dismissing Verizon’s com-
    plaint, and remanding with instructions that the district court
    consider on the merits whether Verizon is entitled to the
    declaratory and injunctive relief (and the costs and attorneys’
    fees) that it seeks.
    

Document Info

Docket Number: 04-15155

Judges: Noonan, Bea, Jones

Filed Date: 7/6/2005

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (34)

mci-telecommunications-corporation-a-delaware-corporation-and-mci-metro ( 2000 )

Dietary Supplemental Coalition, Inc. The Health Haus, Inc. ... ( 1992 )

Gte North, Inc. v. John G. Strand ( 2000 )

association-of-american-medical-colleges-american-medical-association-the ( 2000 )

At&T Corp. v. Iowa Utilities Board ( 1999 )

Verizon Communications Inc. v. Federal Communications ... ( 2002 )

Fox Television Stations, Inc. v. Federal Communications ... ( 2002 )

city-of-auburn-city-of-bremerton-city-of-des-moines-city-of-federal-way-a ( 2001 )

western-oil-and-gas-association-national-ocean-industries-association-v ( 1990 )

mci-telecommunication-corporation-a-delaware-corporation-mcimetro-access ( 2001 )

municipality-of-anchorage-and-the-city-of-craig-alaska-and-the-city ( 1992 )

bell-atlantic-maryland-incorporated-v-mci-worldcom-incorporated-american ( 2001 )

prudencio-chavez-v-director-office-of-workers-compensation-programs ( 1992 )

standard-alaska-production-company-exxon-corporation-chevron-usa ( 1989 )

Midcoast Interstate Transmission, Inc. v. Federal Energy ... ( 2000 )

hawaiian-electric-company-inc-v-united-states-environmental-protection ( 1984 )

los-angeles-memorial-coliseum-commission-v-national-football-league-an ( 1980 )

At&t Communications of Illinois, Inc. v. Illinois Bell ... ( 2003 )

the-people-of-the-village-of-gambell-the-people-of-the-village-of-stebbins ( 1993 )

The Toilet Goods Association, Inc. v. John w.ga Rdner, ... ( 1967 )

View All Authorities »