Great Basin Mine Watch v. Hankins ( 2006 )


Menu:
  •                  FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    GREAT BASIN MINE WATCH, and           
    MINERAL POLICY CENTER,
    Plaintiffs-Appellants,
    v.                         No. 04-16125
    HELEN HANKINS, UNITED STATES                D.C. No.
    DEPARTMENT OF THE INTERIOR, and          CV-02-00605-
    BUREAU OF LAND MANAGEMENT,                 HDM/RAM
    Defendants-Appellees,           OPINION
    NEWMONT USA LIMITED,
    Defendant-Intervenor-
    Appellee.
    
    Appeal from the United States District Court
    for the District of Nevada
    Howard D. McKibben, District Judge, Presiding
    Argued and Submitted
    February 14, 2006—San Francisco, California
    Filed August 1, 2006
    Before: J. Clifford Wallace, Michael Daly Hawkins, and
    Sidney R. Thomas, Circuit Judges.
    Opinion by Judge Wallace;
    Partial Concurrence and Partial Dissent by Judge Thomas
    8619
    GREAT BASIN MINE WATCH v. HANKINS          8623
    COUNSEL
    Roger Flynn, Jeffrey C. Parsons, Western Mining Action
    Project, Boulder, Colorado; Nicole U. Rinke, Western Mining
    Action Project, Reno, Nevada, for the plaintiffs-appellants.
    Thomas L. Sansonetti, Andrew Mergen, John E. Arbab, Dept.
    of Justice, Washington, D.C., for the defendants-appellees.
    Scott W. Hardt, Temkin Wielga & Hardt LLP, Denver, Colo-
    rado, for the intervenor-appellee.
    OPINION
    WALLACE, Circuit Judge:
    Great Basin Mine Watch and the Mineral Policy Center
    (collectively, Great Basin) appeal from the district court’s
    8624         GREAT BASIN MINE WATCH v. HANKINS
    summary judgment on their claims against the United States
    Department of the Interior and the Bureau of Land Manage-
    ment (collectively, Bureau). Great Basin alleged that the
    Bureau’s approval of two gold mining permits to the New-
    mont Mining Corporation (Newmont) violated, inter alia, the
    National Environmental Policy Act (NEPA), 42 U.S.C.
    § 4312, and the Administrative Procedure Act (APA), 5
    U.S.C. §§ 704-706. Newmont appears as an intervenor in this
    appeal. We have jurisdiction pursuant to 28 U.S.C. § 1291.
    We affirm in part, reverse in part, and remand.
    I.
    In March 1997, Newmont submitted a plan proposing
    expansion of Newmont’s existing open-pit gold mining and
    ore processing facilities to the Elko Field Office of the
    Bureau. The proposed expansion was to be located at New-
    mont’s South Operations Area Project, which was approved
    in 1993, approximately six miles northwest of Carlin, Nevada.
    The expansion was to be known as the South Operations Area
    Project Amendment (Amended South Project) and was esti-
    mated to result in a total additional disturbance of 1,392 acres
    of land, 839 of which are public. Amended South Project was
    intended to deepen the existing Gold Quarry Mine, to con-
    tinue dewatering the mine, and to continue discharging excess
    groundwater into Maggie Creek, a creek located near the
    mine.
    Pursuant to NEPA, the Bureau concluded that Amended
    South Project could cause a significant environmental impact
    and ordered the preparation of an environmental impact state-
    ment (EIS). The Bureau released a draft EIS in September
    2000, and issued a final EIS in April 2002. In April 2002, the
    Bureau also released the “Cumulative Impact Analysis of
    Dewatering and Water Management Operations for the Betze
    Project, South Operations Area Project Amendment, and
    Leeville Project,” a technical report detailing the hydrological
    GREAT BASIN MINE WATCH v. HANKINS           8625
    effects of three proposed and existing mining projects in the
    region.
    The Bureau issued a Record of Decision for Amended
    South Project in July 2002. The Decision chose an alternative
    to Newmont’s plan, consisting of Newmont’s Amended South
    Project proposal and an amended version of the 1993 South
    Project mitigation plan. The Decision found that the revised
    agency-preferred alternative would not “cause unnecessary or
    undue degradation of the public lands, and [would] not cause
    any unacceptable conflict with other significant resources in
    the area.”
    Pursuant to its regulations, the Bureau directed Newmont to
    post an incremental bond of $19,753,284 for the first phase of
    Amended South Project, which called for the expansion of a
    waste rock disposal facility, a $3,000,000 bond for possible
    stream flow augmentation, and a $465,000 bond for ground-
    water and surface water monitoring. Pursuant to the Bureau’s
    regulations, Newmont would have to post further phased
    bonds before going ahead with other activities.
    Meanwhile, in April 1997, one month after submitting the
    Amended South Project proposal, Newmont submitted a pro-
    posal for the Leeville Project (Leeville), a proposed under-
    ground gold mine located twenty miles northwest of Carlin.
    The plan, which like the Amended South Project was submit-
    ted to the Elko Field Office, called for construction of five
    shafts to depths of approximately 2,500 feet to access three
    main bodies of ore and for construction of ancillary mine
    facilities. The proposal was estimated to result in a distur-
    bance of 486 acres of land, 453 of which are public. Refrac-
    tory ore produced from Leeville was to be hauled by truck
    and processed at an existing mill located at the South Opera-
    tions Area.
    The Bureau determined that the Leeville proposal could
    potentially have a significant environmental impact and pre-
    8626         GREAT BASIN MINE WATCH v. HANKINS
    pared an EIS. The Bureau released a draft EIS in March 2002,
    and a final EIS in July 2002. The April 2000 Cumulative
    Impacts Analysis was “used as a foundation for the cumula-
    tive impacts analyses” with regard to Leeville.
    The Bureau issued a Record of Decision for Leeville in
    September 2002. The Leeville Decision selected the agency-
    preferred alternative, which modified the Leeville proposal
    and implemented a mitigation plan. As with the Amended
    South Project Decision, the Leeville mitigation plan was an
    extension of the 1993 South Project mitigation plan and
    mainly addressed impacts related to dewatering. The Bureau
    found that implementation of the agency-preferred alternative
    and the Leeville mitigation plan would not “cause unneces-
    sary or undue degradation of the public lands and [would] not
    cause any unacceptable conflict with other significant
    resources in the area.” The Bureau ordered Newmont to pro-
    vide a bond of $4,974,200 for post-mine closure reclamation,
    and a bond of $875,700 for groundwater and surface water
    monitoring.
    Two months later, Great Basin filed an action in the district
    court against the Bureau of Land Management, the Depart-
    ment of the Interior, and Helen Hankins, the manager of the
    Bureau’s Elko Field Office. The complaint sought judicial
    review of the final EISs, the Decisions, and the bonding deter-
    minations, asserting claims under federal statutes including
    NEPA and the APA. Newmont intervened as a defendant. The
    parties filed cross-motions for summary judgment. Before the
    district court acted on the motions, Great Basin sought to
    introduce an extra-record document from the Nevada Division
    of Environmental Protection. According to Great Basin, this
    document was relevant as to whether Amended South Project
    and Leeville were connected actions that should have been
    evaluated in a single EIS. The district court refused to admit
    the document or to take judicial notice of the facts contained
    in the document.
    GREAT BASIN MINE WATCH v. HANKINS             8627
    The district court entered summary judgment in favor of
    defendants on all claims.
    II.
    We review the summary judgment de novo. Hall v. Norton,
    
    266 F.3d 969
    , 975 (9th Cir. 2001). As this is a record review
    case, “we may direct that summary judgment be granted to
    either party based upon our de novo review of the administra-
    tive record.” Lands Council v. Powell, 
    395 F.3d 1019
    , 1026
    (9th Cir. 2005) (as amended). The district court’s determina-
    tion as to whether an EIS satisfies the requirements of NEPA
    is a question of law reviewed de novo. City of Carmel-by-the-
    Sea v. U.S. Dep’t of Transp., 
    123 F.3d 1142
    , 1150 (9th Cir.
    1997). Whether a plaintiff has exhausted required administra-
    tive remedies is a question of law reviewed de novo. See
    Bankston v. White, 
    345 F.3d 768
    , 770 (9th Cir. 2003).
    Judicial review of agency decisions under NEPA, the Clean
    Water Act, and the Federal Land Policy Management Act
    (Management Act) is governed by the APA, which dictates
    that an agency action may be overturned only where it was
    “arbitrary, capricious, an abuse of discretion, or otherwise not
    in accordance with law.” 5 U.S.C. § 706(2)(A); see Marsh v.
    Or. Natural Res. Council, 
    490 U.S. 360
    , 377 (1989) (applying
    arbitrary and capricious standard to the adequacy of an EIS
    under NEPA); Native Ecosystems Council v. Dombeck, 
    304 F.3d 886
    , 891 (9th Cir. 2002) (applying arbitrary and capri-
    cious standard to NEPA claims); Idaho Sporting Congress v.
    Thomas, 
    137 F.3d 1146
    , 1149 (9th Cir. 1998) (applying arbi-
    trary and capricious standard to Clean Water Act claims).
    In determining whether a decision is arbitrary and capri-
    cious, we will “consider whether the decision was based on
    a consideration of the relevant factors and whether there has
    been a clear error of judgment.” 
    Thomas, 137 F.3d at 1149
    ,
    quoting 
    Marsh, 490 U.S. at 378
    . We must also ensure that the
    agency “took a hard look at the environmental consequences
    8628         GREAT BASIN MINE WATCH v. HANKINS
    of its action.” Northwest Resource Info. Ctr., Inc. v. Nat’l
    Marine Fisheries Serv., 
    56 F.3d 1060
    , 1066 (9th Cir. 1995)
    (internal quotations and citations omitted). However, we may
    reverse under the arbitrary and capricious standard only if the
    agency has relied on factors Congress has not intended it to
    consider, entirely failed to consider an important aspect of the
    problem, offered “an explanation [for its decision] that runs
    counter to the evidence before the agency, or is so implausible
    that it could not be ascribed to a difference in view or the
    product of agency expertise.” Sierra Club v. EPA, 
    346 F.3d 955
    , 961 (9th Cir. 2003) (noting standard), amended by 
    352 F.3d 1186
    (9th Cir. 2003).
    We review the district court’s decision whether to admit
    extra-record evidence for an abuse of discretion. Southwest
    Ctr. for Biological Diversity v. U.S. Forest Serv., 
    100 F.3d 1443
    , 1447 (9th Cir. 1996).
    III.
    In 1972, Congress passed the Clean Water Act to create a
    comprehensive national system of regulation of water pollu-
    tion, in which the federal government and the states share
    responsibilities. See 33 U.S.C. §§ 1251-1376. There are two
    general types of standards under the Act: effluent standards,
    which limit the quantity of pollutants discharged from a
    source; and ambient water quality standards, which limit con-
    centrations of pollutants in a stream. The administration of
    these standards is left to the states, which are free to impose
    stricter regulations than those required by federal law.
    Great Basin contends that the Bureau violated the Clean
    Water Act and the Management Act by failing to ensure com-
    pliance with water quality standards in two ways: first,
    because the potential “drying effect” indicates that the Bureau
    failed to maintain “all beneficial uses” of the water, and sec-
    ond, because the discharges of pumped groundwater will vio-
    late water quality standards. The district court granted
    GREAT BASIN MINE WATCH v. HANKINS               8629
    summary judgment on the first claim because “[t]he relation-
    ship between water flow and aquatic life is a question of fact
    that lies within the technical expertise of the agency.” The
    district court declined to reach the second claim because it
    held that Great Basin had not presented it adequately to the
    Bureau in the first instance.
    A.   Potential “Drying Effect”
    Great Basin argues that the Bureau’s approval of Leeville
    and Amended South Project violates the Clean Water Act, the
    Management Act, and the Bureau’s own mining regulations,
    see 43 C.F.R. § 3809, because the projects will extend the
    periods during which existing springs and streams are dry.
    This, Great Basin contends, would violate federal and state
    requirements under the Clean Water Act that beneficial uses
    of waterways be maintained, and would also implicate the
    Act’s “antidegradation” requirements. While the district court
    dismissed the claim as a question of fact lying within the tech-
    nical expertise of the agency, we do not reach the factual basis
    of the claim and hold that it fails as a matter of law.
    [1] It is clear that the Clean Water Act does not supersede,
    abrogate, or otherwise impair “the authority of each state to
    allocate quantities of water within its jurisdiction.” 33 U.S.C.
    § 1251(g). States are responsible for enforcing water quality
    standards on intrastate waters. See 33 U.S.C. § 1319(a). Sec-
    tion 401 of the statute “requires States to provide a water
    quality certification before a federal license or permit can be
    issued for activities that may result in any discharge into intra-
    state navigable waters.” PUD No. 1 of Jefferson Cty. v. Wash.
    Dep’t of Ecology, 
    511 U.S. 700
    , 707 (1994), citing 33 U.S.C.
    § 1341.
    Great Basin places heavy weight on PUD No. 1, arguing
    that the case requires the Bureau to ensure that a mine opera-
    tor will maintain a minimum level of stream flow before the
    Bureau may approve a project. In PUD No. 1, the Supreme
    8630         GREAT BASIN MINE WATCH v. HANKINS
    Court held that the State of Washington could regulate stream
    flow and water quantity under its Clean Water Act authority.
    Great Basin points to the Supreme Court’s holding that the
    Clean Water Act’s definition of pollution “encompasses the
    effects of reduced water quantity.” 
    Id. at 719.
    [2] However, PUD No. 1 does not help Great Basin. PUD
    No. 1 merely holds that states may set minimum flow stan-
    dards as part of section 401 certification requirements; it does
    not hold that states must do so. In the absence of state law to
    the contrary, water withdrawals are not subject to the require-
    ments of the Clean Water Act.
    Other circuits have interpreted the Clean Water Act in the
    same way. In North Carolina v. FERC, 
    112 F.3d 1175
    (D.C.
    Cir. 1997), the D.C. Circuit reached the same conclusion in
    holding that the withdrawal of water from a lake did not trig-
    ger the provisions of section 401. “[N]either the withdrawal of
    water from the Lake nor the reduction in the volume of water
    . . . ‘results in a discharge’ for purposes of Section 401(a)(1).
    . . . [T]he word ‘discharge’ contemplates the addition, not the
    withdrawal, of a substance or substances.” 
    Id. at 1187.
    Simi-
    larly, in Save our Community v. EPA, 
    971 F.2d 1155
    (5th Cir.
    1992), the Fifth Circuit held that the draining of wetland did
    not fall under Section 404 of the Clean Water Act: “We must
    conclude that without the existence of an effluent discharge of
    some kind, there is no coverage under section 404. There is
    no jurisdiction for the agencies or the courts to act.” 
    Id. at 1164.
    The District of Colorado, in a case with similar facts,
    reached the same conclusion: “under Colorado law, water
    quality standards apply only to discharges of pollution and not
    to withdrawals or appropriations of water. . . . The withdrawal
    of water is not a discharge of pollution under the CWA.”
    Colo. Wild, Inc. v. U.S. Forest Serv., 
    122 F. Supp. 2d 1190
    ,
    1193 (D. Colo. 2000).
    The Supreme Court’s recent decision in S.D. Warren Co.
    v. Maine Board of Environmental Protection, 
    126 S. Ct. 1843
                 GREAT BASIN MINE WATCH v. HANKINS             8631
    (2006), is not to the contrary. There, the Court held that the
    release of water from a hydroelectric dam constituted a “dis-
    charge” into navigable waters that is subject to state water
    quality certification under Section 401 of the Clean Water
    Act. However, contrary to Great Basin’s assertions, the Court
    did not address whether individual states are required to regu-
    late withdrawal of water under the Act. Rather, S.D. Warren
    Co. reiterates that individual states have the responsibility of
    regulating water pollution and water use. See 
    id. at 1853
    (“Changes in the river like these fall within a State’s legiti-
    mate legislative business, and the Clean Water Act provides
    for a system that respects the States’ concerns”).
    [3] With this in mind, our next step is to determine whether
    Nevada law subjects withdrawal of water to the standards of
    the Clean Water Act, as it is permitted to do under PUD No.
    1. Nevada statutory law creates different regimes for dis-
    charge of pollutants and dewatering. Discharge of pollutants
    is governed by the Nevada Water Pollution Control Law,
    Nev. Rev. Stat. § 445A.300-.730 (2006). The statute requires
    those seeking to discharge pollutants to obtain a permit from
    the Nevada state department of conservation and natural
    resources. Nev. Rev. Stat. § 445A.500 (2006). However,
    appropriation of water, including dewatering, is governed by
    a different statute, which maintains that any person wishing
    to appropriate or divert underground water should apply to the
    Nevada state engineer for a permit, and specifically refers to
    the use of water in “exploring for oil, gas, minerals or geo-
    thermal resources.” Nev. Rev. Stat. § 534.050; 534.120. The
    Water Pollution Control Law also states that nothing in the
    law “shall be construed to amend, modify or supersede the
    provisions of [the water appropriation statutes] or any rule,
    regulation or order promulgated or issued thereunder by the
    state engineer.” Nev. Rev. Stat. § 445A.725 (2006). Because
    the quality of discharged water and the quantity of appropri-
    ated water are governed by different laws and subject to dif-
    ferent permits, it is clear that Nevada does not regulate
    dewatering under its Clean Water Act authority.
    8632         GREAT BASIN MINE WATCH v. HANKINS
    [4] Great Basin’s claims under the Clean Water Act’s anti-
    degradation provision and under the Management Act are
    equally untenable. The anti-degradation policy only refers to
    water quality standards and does not refer to water with-
    drawal. See 33 U.S.C. § 1313(d)(4). The Nevada anti-
    degradation provision, similarly, only refers to water quality.
    Nev. Rev. Stat. § 445A.565. As discussed above, the Nevada
    statutory regime clearly separates withdrawal of water from
    pollution of water, and the water pollution regime, including
    the anti-degradation statute, is defined so as not to supersede
    the water allocation regime. Thus, because Nevada does not
    regulate water withdrawal in the same regime as water qual-
    ity, the Clean Water Act’s anti-degradation provision is inap-
    plicable.
    The Management Act requires the government to “take any
    action necessary to prevent unnecessary or undue degradation
    of the lands.” 43 U.S.C. § 1732(b). However, the Act also
    provides:
    Nothing in this Act shall be construed as limiting or
    restricting the power and authority of the United
    States or —
    (1) as affecting in any way any law gov-
    erning appropriation or use of, or Federal
    right to, water on public lands;
    (2) as expanding or diminishing Federal or
    State jurisdiction, responsibility, interests,
    or rights in water resources development or
    control.
    43 U.S.C.A. § 1701, hist. note (g) (2006). We interpret this to
    mean that the Management Act does not expand the require-
    ments of the Clean Water Act.
    [5] Therefore, Great Basin’s arguments regarding the
    potential “drying effect” are untenable as a matter of law.
    GREAT BASIN MINE WATCH v. HANKINS               8633
    B.     Discharged Groundwater
    Great Basin next argues that the groundwater discharged
    from Amended South Project into Maggie Creek will violate
    federal and state water quality requirements. The district court
    ruled that the plaintiffs had not properly raised these argu-
    ments before the Bureau.
    1.    Exhaustion
    The APA requires that plaintiffs exhaust administrative
    remedies before bringing suit in federal court. 5 U.S.C. § 704.
    This requirement applies to claims under NEPA. “Persons
    challenging an agency’s compliance with NEPA must struc-
    ture their participation so that it . . . alerts the agency to the
    parties’ position and contentions, in order to allow the agency
    to give the issue meaningful consideration.” Dep’t of Transp.
    v. Pub. Citizen, 
    541 U.S. 752
    , 764 (2004) (internal punctua-
    tion omitted), quoting Vermont Yankee Nuclear Power Corp.
    v. Natural Res. Def. Council, Inc., 
    435 U.S. 519
    , 553 (1978).
    We considered the degree to which parties must raise envi-
    ronmental claims before the agency in Native Ecosystems
    Council. There, we allowed the plaintiffs to raise arguments
    before us where they “presented a much less refined legal
    argument in their administrative 
    appeal.” 304 F.3d at 898
    . We
    defined the exhaustion requirement broadly: “The plaintiffs
    have exhausted their administrative appeals if the appeal,
    taken as a whole, provided sufficient notice to the [agency] to
    afford it the opportunity to rectify the violations that the plain-
    tiffs alleged.” 
    Id. at 899.
    This, we held, comported with the
    purposes of the exhaustion requirement: “avoiding premature
    claims and ensuring that the agency be given a chance to
    bring its expertise to bear to resolve a claim.” 
    Id. at 900.
    “Re-
    quiring more might unduly burden those who pursue adminis-
    trative appeals unrepresented by counsel, who may frame
    their claims in non-legal terms rather than precise legal for-
    mulations.” 
    Id. We have
    continued to use this analysis in sub-
    8634         GREAT BASIN MINE WATCH v. HANKINS
    sequent cases. See, e.g., Idaho Sporting Congress, Inc. v.
    Rittenhouse, 
    305 F.3d 957
    , 965 (9th Cir. 2002).
    [6] Applying this standard, we conclude that the Bureau
    was on notice that Great Basin took issue with the groundwa-
    ter discharged into Maggie Creek. In its comment letter to the
    Bureau on the Amended South Project draft EIS, Great Basin
    wrote: “The [Amended South Project] indicates that ground-
    water released into Maggie Creek does not need to be treated,
    since the combined discharged water does not exceed the
    water quality standards established by the NPDES system. . . .
    This statement is different than saying that no impacts will
    occur. What are the water quality measurements in the Creek
    and in the discharged water? Are arsenic or TDS amounts
    increased over what exists naturally in Maggie Creek? Does
    the total amount of contaminants discharged add a significant
    amount to the total loads in the Humboldt River down-
    stream?”
    Under our case law, this was sufficient to preserve the
    claim for judicial review. Great Basin clearly expressed con-
    cern about the current and future levels of toxins in the dis-
    charged water, and the Bureau was on notice of these
    concerns.
    [7] The district court’s conclusion that this argument was
    unexhausted was in error. Accordingly, we proceed to the
    merits.
    2.   Merits
    The Environmental Protection Agency and the states are
    responsible for administering the Clean Water Act. Possible
    water pollution clearly comes within the ambit of the Clean
    Water Act. See 33 U.S.C. § 1341.
    [8] Newmont obtained a water pollution permit from the
    Nevada Division of Environmental Protection (NDEP), which
    GREAT BASIN MINE WATCH v. HANKINS                8635
    is responsible for regulating the discharge of pollutants into
    state waters. Great Basin’s argument is based on a table
    attached to the Amended South Project EIS, which details the
    quality of the water discharged from Newmont between 1994
    and 1998. According to Great Basin, the table shows that the
    groundwater pumped from Amended South Project has
    exceeded water quality standards and the limitations of New-
    mont’s permit. The table belies Great Basin’s argument.
    While it is true that the level of pollutants occasionally
    exceeded those allowed by Newmont’s permit, the discharge
    was generally within the range allowed. The only measure-
    ment that was frequently out of line was for total dissolved
    solids. The thirty-day average for total dissolved solids was,
    however, well under the NDEP’s permit’s daily maximum.
    Following the Clean Water Act’s stricture that states should
    enforce water quality standards, the Bureau repeatedly told
    Newmont that it had to obtain a permit from NDEP before
    Newmont could discharge any pollutants. The Bureau
    reviewed the table and decided that “[t]he mine discharge has
    been generally within its permit limitations; no significant
    non-compliance has been found.”
    [9] Great Basin cites no law to demonstrate that the
    Bureau’s analysis of the data was arbitrary or capricious, or,
    indeed, even incorrect. We therefore affirm the summary
    judgment on this claim.
    IV.
    In 1926, President Calvin Coolidge created Public Water
    Reserve No. 107 (No. 107) by executive order. It provides:
    It is hereby ordered that every smallest legal subdivi-
    sion of public land surveys which is vacant, unap-
    propriated, unreserved public land and contains a
    spring or water hole, and all land within one quarter
    of a mile of every spring or water hole located on
    8636         GREAT BASIN MINE WATCH v. HANKINS
    unsurveyed public land, be and the same is hereby
    withdrawn from settlement, location, sale or entry,
    and reserved for public use in accordance with the
    provisions of Section 10 of the Act of December 29,
    1916.
    See United States v. Idaho, 
    959 P.2d 449
    , 451 (Idaho 1998).
    According to one court, “[t]he purpose of the reservation was
    to prevent monopolization of water needed for domestic and
    stock watering purposes.” United States v. City & County of
    Denver, 
    656 P.2d 1
    , 32 (Colo. 1983); see also 
    Idaho, 959 P.2d at 453
    (“The purpose of PWR 107 was to prevent the monop-
    olization by private individuals of springs and waterholes on
    public lands needed for stockwatering”).
    Great Basin argued in the district court that the Bureau’s
    approval of the mining plans would reduce and eliminate
    springs and waterholes in the region, thus causing the plans
    to violate No. 107. The district court held that Great Basin
    could not raise this claim because it was not raised before the
    Bureau.
    A.   Standing
    As a preliminary matter, Newmont argues that Great Basin
    lacks constitutional and prudential standing to raise the No.
    107 claim, because Great Basin’s members have suffered no
    injury-in fact and their interests do not fall within the “zone
    of interest” that No. 107 was designed to protect.
    “[E]nvironmental plaintiffs adequately allege injury in fact
    when they aver that they use the affected area and are persons
    for whom the aesthetic and recreational values of the area will
    be lessened by the challenged activity.” Friends of the Earth,
    Inc. v. Laidlaw Envtl. Servs., 
    528 U.S. 167
    , 183 (2000) (inter-
    nal quotations omitted). Great Basin has submitted declara-
    tions from its members that detail the injury that the
    dewatering of the springs will cause to their recreational lives.
    GREAT BASIN MINE WATCH v. HANKINS               8637
    For example, Daniel Randolph, a member of Great Basin,
    stated that he has “spent a great deal of time in northern
    Nevada, hiking, camping, swimming, and taking pictures. A
    portion of that time has been spent in the area that will be
    affected by the [Amended South Project] and Leeville.” He
    went on to detail several occasions when he participated in
    recreational activities on the land in question. Furthermore,
    the injury complained of would not occur if the mining proj-
    ects were not approved, and an injunction would provide
    complete relief. The members of Great Basin have alleged
    injury-in-fact, causation, and redressability. Great Basin has
    Article III standing.
    With regards to prudential standing, the “zone of interest”
    test is not particularly stringent. The Supreme Court has held
    that “[t]he proper inquiry is simply whether the interest
    sought to be protected by the complainant is arguably within
    the zone of interests to be protected . . . by the statute.” Nat’l
    Credit Union Admin. v. First Nat’l Bank & Trust Co., 
    522 U.S. 479
    , 492 (1998) (internal quotations omitted) (emphasis
    in original). The plaintiffs’ declarations specifically state that
    “[m]embers of GBMW . . . utilize springs and waterholes on
    federal public land in Nevada for stockwatering and other
    water-related purposes.” This is sufficient to fall within the
    zone of interest.
    [10] We conclude that Great Basin has standing to raise the
    No. 107 claim.
    B.   Exhaustion
    Great Basin admits that it did not mention No. 107 by name
    in the proceedings before the Bureau, but argues that the
    Bureau was on notice that the public was concerned about the
    loss of these public water reserves. The district court held that
    Great Basin had failed to raise the claim before the Bureau,
    citing Vermont Yankee Power Corp.: “[A]dministrative pro-
    ceedings should not be a game or a forum to engage in unjus-
    8638         GREAT BASIN MINE WATCH v. HANKINS
    tified obstructionism by making cryptic and obscure reference
    to matters that ‘ought to be’ considered and then, after failing
    to do more to bring the matter to the agency’s attention, seek-
    ing to have that agency determination vacated on the ground
    that the agency failed to consider matters ‘forcefully pre-
    sented.’ 
    435 U.S. at 553-54
    .
    [11] We have held that “claimants who bring administrative
    appeals may try to resolve their difficulties by alerting the
    decision maker to the problem in general terms, rather than
    using precise legal formulations.” 
    Rittenhouse, 305 F.3d at 965
    . However, in this case we conclude that the connection
    between No. 107 and the concerns raised is too attenuated.
    Great Basin made general comments about groundwater,
    springs, and seeps. These comments in no way suggest an
    argument that the Bureau failed to protect federally-reserved
    water rights under an eighty-year-old Executive Order.
    [12] The district court correctly held that Great Basin’s
    claims under No. 107 were not exhausted.
    V.
    Great Basin next argues that the Bureau violated NEPA by
    not evaluating Leeville and the Amended South Project in a
    single environmental impact statement. Great Basin argues
    that the Amended South Project and Leeville are connected
    actions and thus must have been evaluated together. The dis-
    trict court held that the argument was unexhausted because
    Great Basin failed to raise it before the Bureau. In the alterna-
    tive, the district court held that the plaintiffs had failed to
    establish that the actions were connected.
    A.   Exhaustion
    In their comments on the final EIS, the plaintiffs stated,
    with regard to tailings generated by Leeville and the
    Amended South Project, that “it is essential to consider the
    GREAT BASIN MINE WATCH v. HANKINS              8639
    South Operations Area and the Leeville as linked projects.”
    The district court found this insufficient because the “com-
    ment mentions the tailings, but nothing else. It does not men-
    tion the ore, sludge, or waste water, and it does not mention
    any of the adjacent mines.”
    “Claims must be raised with sufficient clarity to allow the
    decision maker to understand and rule on the issue raised, but
    there is no bright-line standard as to when this requirement
    has been met and we must consider exhaustion arguments on
    a case-by-case basis.” 
    Rittenhouse, 305 F.3d at 965
    . Our
    review of the record indicates that Great Basin adequately
    raised the issue of connected actions. “The plaintiffs have
    exhausted their administrative appeals if the appeal, taken as
    a whole, provided sufficient notice . . . to afford [the agency]
    the opportunity to rectify the violations that the plaintiffs
    alleged.” Native Ecosystems 
    Council, 304 F.3d at 899
    . While
    the plaintiffs here did not cite to the requisite federal regula-
    tion, they “clearly expressed concern” that the projects were
    linked. 
    Rittenhouse, 305 F.3d at 966
    .
    [13] Additionally, the record indicates that the Bureau was
    on notice that the actions might appear to be connected. In its
    response to the plaintiffs’ request for judicial notice, the
    Bureau stated that “it did consider the environmental issue
    implicated by this document in detail: whether the challenged
    mining proposals were sufficiently dependent or independent
    to either have or lack an independent purpose.” “Because
    plaintiffs raised the issue . . . sufficiently for the agency to
    review these procedures . . . , we hold that the plaintiffs
    exhausted their administrative remedies . . . .” Native Eco-
    systems 
    Council, 304 F.3d at 899
    -900; see also Northwest
    Resource Info. 
    Ctr., 56 F.3d at 1067
    (“[T]he Corps was well-
    aware of the criticisms of the scope of the SEIS before, dur-
    ing, and after the . . . process”).
    B.   Merits
    NEPA “requires a federal agency to prepare an EIS for all
    ‘major Federal actions significantly affecting the quality of
    8640          GREAT BASIN MINE WATCH v. HANKINS
    the human environment.’ ” Wetlands Action Network v. U.S.
    Army Corps of Eng’rs, 
    222 F.3d 1105
    , 1115 (9th Cir. 2000),
    quoting 42 U.S.C. § 4332(2)(C). The Council on Environmen-
    tal Quality’s implementing regulation of NEPA requires,
    regarding the scope of an EIS:
    The scope of an individual statement may depend on
    its relationships to other statements. To determine
    the scope of environmental impact statements, agen-
    cies shall consider 3 types of actions, 3 types of
    alternatives, and 3 types of impacts. They include:
    (a)    Actions (other than unconnected sin-
    gle actions) which may be:
    (1)       Connected actions, which means
    that they are closely related and
    therefore should be discussed in the
    same impact statement. Actions are
    connected if they:
    (i)     Automatically   trigger   other
    actions which may require envi-
    ronmental impact statements.
    (ii)     Cannot or will not proceed
    unless other actions are taken
    previously or simultaneously.
    (iii)    Are interdependent parts of a
    larger action and depend on the
    larger action for their justifica-
    tion.
    (2)       Cumulative actions, which when
    viewed with other proposed actions
    have    cumulatively    significant
    impacts and should therefore be
    GREAT BASIN MINE WATCH v. HANKINS           8641
    discussed in the same impact state-
    ment.
    (3)   Similar actions, which when
    viewed with other reasonably fore-
    seeable or proposed agency actions,
    have similarities that provide a
    basis for evaluating their environ-
    mental consequences together, such
    as common timing or geography.
    An agency may wish to analyze
    these actions in the same impact
    statement. It should do so when the
    best way to assess adequately the
    combined impacts of similar actions
    or reasonable alternatives to such
    actions is to treat them in a single
    impact statement.
    40 C.F.R. § 1508.25 (citations omitted).
    The purpose of this requirement is “to prevent an agency
    from dividing a project into multiple ‘actions,’ each of which
    individually has an insignificant environmental impact, but
    which collectively have a substantial impact.” Wetlands
    Action 
    Network, 222 F.3d at 1118
    (internal quotations and
    citation omitted). Where, as here, the agency declines to pro-
    duce a single EIS, “plaintiffs must show that the [agency] was
    arbitrary and capricious in failing to prepare one comprehen-
    sive environmental statement.” Native Ecosystems 
    Council, 304 F.3d at 894
    , citing Kleppe v. Sierra Club, 
    427 U.S. 390
    ,
    412 (1976).
    [14] We apply an “independent utility” test to determine
    whether multiple actions are so connected as to mandate con-
    sideration in a single EIS. The crux of the test is whether
    “each of two projects would have taken place with or without
    the other and thus had ‘independent utility.’ ” Wetlands
    8642         GREAT BASIN MINE WATCH v. HANKINS
    Action 
    Network, 222 F.3d at 1118
    (internal quotations and
    citation omitted). When one of the projects might reasonably
    have been completed without the existence of the other, the
    two projects have independent utility and are not “connected”
    for NEPA’s purposes. Native Ecosystems 
    Council, 304 F.3d at 894
    .
    In Blue Mountains Biodiversity Project v. Blackwood, 
    161 F.3d 1208
    , 1215 (9th Cir. 1998), we held that five potential
    logging projects in the same watershed were cumulative and
    had to be evaluated in a single EIS, where they were reason-
    ably foreseeable and “developed as part of a comprehensive
    forest recovery strategy.” Similarly, in Thomas v. Peterson,
    
    753 F.2d 754
    , 758 (9th Cir. 1985), we held that a logging
    project and a road to facilitate the logging had to be consid-
    ered in a single EIS because “the timber sales [could not] pro-
    ceed without the road, and the road would not be built but for
    the contemplated timber sales.”
    We have held that less-interconnected projects need not be
    evaluated in the same EIS. In Wetlands, we held that a joint
    EIS was not required where details and planning for subse-
    quent phases of development had not been completed or
    authorized. “Finding that the Corps was required . . . to have
    analyzed the environmental impacts of the three phases in a
    single EA or EIS would require the government to do the
    
    impractical.” 222 F.3d at 1119
    . In Sylvester v. U.S. Army
    Corps of Eng’rs, 
    884 F.2d 394
    , 400 (9th Cir. 1989), we
    declined to require a single EIS covering both a resort com-
    plex and a golf course, where only the golf course (built on
    wetlands) implicated federal law. “[E]ach could exist without
    the other, although each would benefit from the other’s pres-
    ence.” 
    Id. Great Basin
    points to several statements in the EISs to
    argue that Leeville and the Amended South Project are con-
    nected actions. “The Leeville Project ore deposits consist of
    refractory material that would be hauled directly to processing
    GREAT BASIN MINE WATCH v. HANKINS                  8643
    facilities located at the Refractory Ore Treatment Plant at
    Newmont’s South Operations Area.” In addition, “[t]ailing
    material that would result from processing of the Leeville
    Project ore would be managed at Newmont’s tailing disposal
    facility in the South Operations Area.” The Leeville draft EIS
    also contained a diagram showing that all ore from Leeville
    would be processed at the South Operations Area. Great Basin
    does not argue that the Amended South Project is dependent
    on Leeville.
    [15] While it is true that the ore from Leeville will be pro-
    cessed at the South Operations Area, there is no indication
    that the ore will be processed at the Amended South Project,
    the new facilities at issue in this litigation. In fact, the Leeville
    draft EIS specifically states that “[t]ailing from processing
    Leeville ore at South Operations Area would be deposited in
    existing tailing disposal facilities. Modification or expansion
    of the tailing disposal facility beyond the current authorized
    capacity would not be required to process ore from the
    Leeville Project.” Ore from Leeville is to be processed at
    Mill 6, which was permitted by the Bureau to existing capac-
    ity in 1993. Leeville and the Amended South Project seem to
    have very little connectedness.
    [16] “Mindful of the deference that agencies are to be
    accorded in scientific matters, in these circumstances we
    decline at this time to require the BLM to produce a single
    document.” Klamath-Siskiyou Wildlands Ctr. v. Bureau of
    Land Mgmt., 
    387 F.3d 989
    , 1000 (9th Cir. 2004). In this situa-
    tion, we go even further: there is no factual support for Great
    Basin’s argument that Leeville and the Amended South Proj-
    ect are interdependent such that they must be evaluated in a
    joint environmental impact statement. It follows that the
    Bureau’s failure to do so was not arbitrary or capricious.1
    1
    In arguing that the Bureau should have evaluated Leeville and
    Amended South Project in a single EIS, the separate concurrence and dis-
    sent concludes that “[i]t would be not merely unwise, but also entirely
    8644            GREAT BASIN MINE WATCH v. HANKINS
    VI.
    Great Basin argues that the Bureau’s cumulative impact
    analysis was inadequate under NEPA. The district court held
    that Great Basin had failed to raise these claims adequately
    before the Bureau. In the alternative, the district court held
    that the Bureau had “comprehensively considered the proj-
    ect’s potential cumulative impacts” and rejected Great Basin’s
    argument. “Whether a particular deficiency, or combination
    of deficiencies, in an EIS is sufficient to warrant holding it
    legally inadequate, or constitutes merely a ‘fly-speck,’ is
    essentially a legal question, reviewable de novo.” Churchill
    County v. Norton, 
    276 F.3d 1060
    , 1071 (9th Cir. 2001) (quo-
    tation omitted).
    A.    Exhaustion
    According to the district court, “the record reflects that
    Plaintiffs failed to raise these issues before the administrative
    irrational to proceed with the mining of Leeville in the absence of avail-
    able processing facilities.” This fails to acknowledge that Leeville’s ore is
    to be processed in existing facilities whose operations have not been chal-
    lenged in this action. According to the record, Leeville could be mined
    regardless of whether the South Operations Area Project is ever expanded.
    Here, the Leeville Draft EIS states that the ore brought to the surface
    “would be hauled directly to processing facilities at the Refractory Ore
    Treatment Plant (Mill #6) located at Newmont’s South Operations Area.”
    There is no allegation that Mill #6 is to be expanded in any way by
    Amended South Project. Similarly, it is clear that tailings from Leeville
    are to be deposited at the existing facility. Put simply, Great Basin points
    to no evidence that the Leeville mine will use the expanded portion of the
    South Operations Area in any way.
    Accordingly, the Amended South Project and Leeville fail the “indepen-
    dent utility” test. See Wetlands Action 
    Network, 222 F.3d at 1118
    . There
    was no need to evaluate the projects in a single EIS. “[E]ach could exist
    without the other, although each would benefit from the other’s presence.”
    
    Sylvester, 884 F.2d at 400
    . The conclusion of the separate opinion to the
    contrary is supported by neither our caselaw nor the record.
    GREAT BASIN MINE WATCH v. HANKINS             8645
    agencies.” However, in comments submitted on the Amended
    South Project draft EIS, the Mineral Policy Center argued that
    the cumulative impacts analysis was inadequate: “There are
    numerous large operating gold mines in the region that must
    also be fully considered in a regional comprehensive impact
    analysis.” The Bureau responded that it had indeed identified
    all the known or reasonably foreseeable projects. Addition-
    ally, many other comments raised cumulative impacts issues.
    For example, the EPA commented on the inadequacy of the
    air pollution analysis within the cumulative impacts analysis.
    Other public comments expressed concern with the cumula-
    tive impacts analysis.
    We have held that there is no “broad rule which would
    require participation in agency proceedings as a condition pre-
    cedent to seeking judicial review of an agency decision.”
    Northwest Envtl Def. Ctr. v. Bonneville Power Admin., 
    117 F.3d 1520
    , 1534-35 (9th Cir. 1997), quoting Kunaknana v.
    Clark, 
    742 F.2d 1145
    , 1148 (9th Cir. 1984). We hold that, in
    this case, the comments were sufficient “to allow the agency
    to give the issue meaningful consideration.” Public 
    Citizen, 541 U.S. at 764
    (internal punctuation and citation omitted).
    We thus reach the merits of Great Basin’s claim.
    B.   Merits
    A cumulative impact is defined in NEPA’s implementing
    regulations as “the impact on the environment which results
    from the incremental impact of the action when added to other
    past, present, and reasonably foreseeable future actions . . . .
    Cumulative impacts can result from individually minor but
    collectively significant actions taking place over a period of
    time.” 40 C.F.R. § 1508.7. We have held that “[a] proper con-
    sideration of the cumulative impacts of a project requires
    some quantified or detailed information; general statements
    about possible effects and some risk do not constitute a hard
    look absent a justification regarding why more definitive
    information could not be provided.” Klamath-Siskiyou Wild-
    8646         GREAT BASIN MINE WATCH v. HANKINS
    lands 
    Ctr., 387 F.3d at 993
    (emphasis added) (internal quota-
    tions and citations omitted). “The analysis must be more than
    perfunctory; it must provide a useful analysis of the cumula-
    tive impacts of past, present, and future projects.” 
    Id. at 994
    (internal quotations and citations omitted). “Defendants must
    do more than just catalogue ‘relevant past projects in the
    area.’ ” Churchill 
    County, 276 F.3d at 1080
    , quoting City of
    
    Carmel-by-the-Sea, 123 F.3d at 1160
    . “[I]n assessing cumula-
    tive effects, the Environmental Impact Statement must give a
    sufficiently detailed catalogue of past, present, and future
    projects, and provide adequate analysis about how these proj-
    ects, and difference between the projects, are thought to have
    impacted the environment.” Lands 
    Council, 395 F.3d at 1028
    .
    Great Basin argues that the final EISs do not adequately
    review the environmental impacts from the other past, pres-
    ent, and reasonably foreseeable projects in the area because
    they merely list other mines in the area without detailing
    impacts from each one. In addition to this general concern,
    Great Basin argues that the cumulative impacts analysis is
    infirm in three specific ways: first, that the final EISs fail to
    address the impacts from Newmont’s Pete Project and North
    Operations, and from Barrick Corporation’s Betze/Post mine;
    second, that the Leeville final EIS fails to analyze the cumula-
    tive impacts from disposal of sludge both at Leeville and at
    the other area mines; and third, that the Leeville final EIS fails
    to review environmental impacts from disposal of Leeville
    wastewater at the Betze/Post mine.
    In Lands Council, the plaintiffs argued that the cumulative
    impacts analysis contained in an EIS for a large timber sale
    was inadequate, because the Forest Service “did not note in
    detail past timber harvesting projects and the impact of those
    projects on the . . . watershed.” 
    Id. at 1027.
    We agreed with
    the plaintiffs:
    [T]here is no catalog of past projects and no discus-
    sion of how those projects (and differences between
    GREAT BASIN MINE WATCH v. HANKINS                8647
    the projects) have harmed the environment. Apart
    from a map in the Project file that shows past har-
    vests, with general notes about total acres cut per
    watershed, there is no listing of individual past tim-
    ber harvests. Moreover, there is no discussion of the
    connection between individual harvests and the prior
    environmental harms from those harvests that the
    Forest Service now acknowledges. Instead, the Final
    Environmental Impact Statement contains only
    vague discussion of the general impact of prior tim-
    ber harvesting, and no discussion of the environmen-
    tal impact from past projects on an individual basis,
    which might have informed analysis about alterna-
    tives presented for the current project.
    
    Id. Similarly, in
    Klamath-Siskiyou, we reviewed environmental
    assessments (EAs) prepared by the Bureau involving multiple
    timber sales within the same watershed. Although each of the
    EAs included a twelve-page section headed “Cumulative
    Impacts,” we concluded that the sections were inadequate: “A
    considerable portion of each section discusses only the direct
    effect of the project at issue on its own minor watershed. In
    the parts of the section where the other projects are contem-
    plated, there is no quantified assessment of their combined
    environmental 
    impacts.” 387 F.3d at 994
    . The analysis, we
    pointed out, principally consisted of a table that included pro-
    jected impacts from the other sales. We held that the table was
    insufficient because it did not provide “objective quantifica-
    tion of the impacts. . . . [T]he reader is informed only that a
    particular environmental factor will be ‘unchanged,’
    ‘improved,’ or ‘degraded’ and whether that change will be
    ‘minor’ or ‘major.’ The reader is not told what data the con-
    clusion was based on, or why objective data cannot be provid-
    ed.” 
    Id. Under the
    standard set forth by Lands Council and
    Klamath-Siskiyou, we conclude that the cumulative impacts
    8648         GREAT BASIN MINE WATCH v. HANKINS
    analyses in the Amended South Project and Leeville final
    EISs are insufficient. The Amended South Project cumulative
    impacts review is largely based on the April 2000 analysis of
    the impacts of the groundwater pumping to be done by
    Leeville, Amended South Project, and the nearby Goldstrike
    mine. While this April 2000 document and the Amended
    South Project final EIS contain an in-depth discussion of
    impacts from groundwater pumping, other mines are men-
    tioned in almost no other part of the cumulative impacts anal-
    ysis.
    [17] In the Amended South Project final EIS, the analysis
    of the effects of existing mines in the area is limited to a
    generic map entitled “Mining Activity in the Carlin Trend”
    and three tables that list existing and reasonably foreseeable
    mines. The “Air Resources” section of the final EIS, for
    example, contains the conclusory statement that “[t]here is
    potential for cumulative effects from hazardous air pollutants
    including compounds of arsenic, hydrogen cyanide, manga-
    nese, propylene, and acid aerosols. . . . Cumulatively, these
    mining emissions are minimized to some degree because of
    project separation distances, meteorological conditions that
    promote good dispersion, and the fact that not all projects
    would produce emissions concurrently.” Nowhere is this
    somewhat alarming statement supported by data broken down
    by mine, or even by cumulative data.
    [18] Similarly, when discussing hazardous waste, the final
    EIS simply states that “[a]ll hazardous wastes must be han-
    dled according to approved permits or be disposed of accord-
    ing to state or federal regulations. The known and reasonably
    foreseeable project would cumulatively result in larger vol-
    umes of hazardous wastes stored on site, transported on state
    and federal highways, and disposed of in approved disposal
    sites.” The report states that the volumes of hazardous waste
    cannot be quantified “until future hazardous waste generators
    are identified.” However, the report could at the least quantify
    the existing volumes of hazardous waste, and fails to do so.
    GREAT BASIN MINE WATCH v. HANKINS              8649
    We hold that these vague and conclusory statements, without
    any supporting data, do not constitute a “hard look” at the
    environmental consequences of the action as required by
    NEPA. As in Lands Council, the final EIS contains “no dis-
    cussion of the environmental impact from past projects on an
    individual basis” apart from the pumping of 
    groundwater. 395 F.3d at 1027
    .
    The Bureau responds that the acreage of surface distur-
    bance with the Pete Project, at least, is implicitly included in
    the cumulative effects analysis for other resources, such as
    soils and vegetation. We have held, however, that this is
    insufficient under NEPA. “A calculation of the total number
    of acres to be [impacted by other projects] in the watershed
    is a necessary component of a cumulative effects analysis, but
    it is not a sufficient description of the actual environmental
    effects that can be expected from logging those acres.”
    
    Klamath-Siskiyou, 387 F.3d at 995
    . The Bureau also gives no
    explanation for why other mining projects were not explicitly
    discussed in the cumulative impacts analysis.
    [19] The Leeville final EIS is also insufficient, similarly
    failing to discuss the specific impacts of other mines except
    in the analysis of groundwater pumping. For example, the
    analysis of cumulative impacts on air is only five sentences
    long and includes no mine-specific or cumulative data, merely
    stating that “[a]mbient air quality data for the region currently
    reflects impacts of existing mining operations in the airshed.”
    Additionally, as Great Basin points out, the Leeville final
    EIS contains no discussion whatsoever of the cumulative
    impacts of sludge or hazardous waste disposal. The Bureau
    responds by saying that the toxicity of the sludge has not been
    determined and thus need not be analyzed. If allowed, this
    would vitiate the Bureau’s duty to take a “hard look” at the
    cumulative impacts of the action.
    [20] “The [Bureau] cannot simply offer conclusions.
    Rather, it must identify and discuss the impacts that will be
    8650         GREAT BASIN MINE WATCH v. HANKINS
    caused by each successive [project], including how the com-
    bination of those various impacts is expected to affect the
    environment, so as to provide a reasonably thorough assess-
    ment of the projects’ cumulative impacts.” 
    Id. at 1001.
    We
    conclude that the cumulative impacts analysis done by the
    Bureau was insufficient and thus reverse the district court on
    this ground.
    Because we hold that the cumulative impacts analysis was
    insufficient, we need not address whether the Newmont
    power plant should have been considered by the Bureau in the
    first instance. We observe, however, that Newmont proposed
    the power plant before the Decisions were issued, and that we
    have upheld the Environmental Protection Agency’s rule
    change to accommodate the proposal. See Great Basin Mine
    Watch v. EPA, 
    401 F.3d 1094
    , 1100-01 (9th Cir. 2005). Thus,
    the Bureau may consider in the first instance whether the
    power plant and its emissions are, at this point, “reasonably
    foreseeable” for purposes of inclusion in the cumulative
    impacts analysis.
    VII.
    43 C.F.R. § 3809.552(a) maintains that individual financial
    assurances (FAs) “must cover the estimated cost as if [the
    Bureau] were to contract with a third party to reclaim your
    operations according to the reclamation plan, including con-
    struction and maintenance costs for any treatment facilities
    necessary to meet Federal and State environmental stan-
    dards.” The Bureau allowed Newmont to bond the Amended
    South Project in phases. Great Basin argues that the financial
    assurances were invalid both procedurally and substantively.
    The district court held that Great Basin “failed to establish
    that the [Bureau] abused its discretion or was arbitrary and
    capricious in its bonding decisions.”
    “We must give substantial deference to an agency’s inter-
    pretation of its own regulations. Our task is not to decide
    GREAT BASIN MINE WATCH v. HANKINS              8651
    which among several competing interpretations best serves
    the regulatory purpose.” Thomas Jefferson Univ. v. Shalala,
    
    512 U.S. 504
    , 512 (1994) (citations omitted). “[J]udicial
    review of an agency’s interpretation of its own regulations is
    limited to ensuring that the agency’s interpretation is not
    plainly erroneous or inconsistent with the regulation.” Forest
    Guardians v. U.S. Forest Serv., 
    329 F.3d 1089
    , 1097 (9th Cir.
    2003).
    Great Basin first argues that the Bureau failed to calculate
    the full cost of reclamation before approving a bond for Phase
    I of the Amended South Project, and that such a calculation
    is required by 43 C.F.R. § 3809.552. We agree with the
    Bureau that the regulation does not require the calculation.
    The cited regulation merely requires the Bureau to obtain a
    financial guarantee before permitting.
    [21] Great Basin’s interpretation of the regulation is also in
    conflict with other regulations allowing the bond amount to
    be posted in phases. See 43 C.F.R. § 3809.553(a) (“BLM may
    authorize you to provide a financial guarantee covering a part
    of your operations”); 43 C.F.R. § 3809.553(b) (“BLM will
    review the amount and terms of the financial guarantee for
    each increment of your operations at least annually”). The
    Bureau did not act arbitrarily or capriciously in failing to cal-
    culate the bond amount for the entire project.
    Next, Great Basin contends that the amount of the bond
    was “grossly inadequate.” According to Great Basin, the
    Amended South Project Phase I FA failed to follow the
    Bureau’s binding regulations because it did not add enough
    for indirect costs. Great Basin relies primarily on two reports
    prepared by its expert, James R. Kuipers. However, as the
    Bureau points out, the fact that Great Basin’s consultant dis-
    agrees with the Bureau’s analysis does not make the analysis
    arbitrary and capricious. See Greenpeace Action v. Franklin,
    
    14 F.3d 1324
    , 1332 (9th Cir. 1993) (“an agency must have
    discretion to rely on the reasonable opinions of its own quali-
    8652         GREAT BASIN MINE WATCH v. HANKINS
    fied experts even if, as an original matter, a court might find
    contrary views more persuasive”). Additionally, though Great
    Basin argues that the Bureau has assumed that “costs will
    never rise in upcoming years,” the Bureau’s regulations man-
    date review of the “amount and terms” of phased FAs “at
    least annually,” 43 C.F.R. § 3809.553(b), and in the case of
    non-phased FAs, “periodically.” 
    Id. § 3809.552(b).
    Finally, Great Basin argues that the Bureau erroneously
    allowed Newmont to post a corporate guarantee instead of
    providing a proper financial instrument. While the Bureau
    “will not accept any new corporate guarantees or increases to
    existing corporate guarantees,” 43 C.F.R. § 3809.574, the pro-
    hibition does not apply to corporate guarantees that were in
    effect prior to January 20, 2001.
    It is clear that, in this case, the bond refers to corporate
    guarantees that existed prior to the regulation: “August 1995
    bonding documentation provided to [the Bureau] from New-
    mont shows that the Nevada Division of Environmental Pro-
    tection holds $2,250,000 in the form of Corporate Guarantees
    . . . .” Great Basin’s argument fails as a matter of law.
    [22] We conclude that the Bureau did not act arbitrarily or
    capriciously in setting Newmont’s financial assurance
    requirements.
    VIII.
    Finally, Great Basin seeks to file a notice from the NDEP
    concerning Newmont’s state water permit application.
    According to Great Basin, the document demonstrates that
    both Newmont and NDEP consider Leeville, the Amended
    South Project, and another Newmont project, Pete, to be one
    project for permitting purposes. The Notice was issued after
    the stipulated deadline for filing extra-record documents. The
    district court refused to admit the notice into evidence and
    also refused to take judicial notice of the facts contained in it.
    GREAT BASIN MINE WATCH v. HANKINS               8653
    We review for an abuse of discretion. Northcoast Envtl Ctr.
    v. Glickman, 
    136 F.3d 660
    , 665 (9th Cir. 1998).
    The Supreme Court has expressed the general rule that
    courts reviewing the agency action are limited to the adminis-
    trative record. Fla. Power & Light Co. v. Lorion, 
    470 U.S. 729
    , 743-44 (1985). However, “[i]n limited circumstances,
    district courts are permitted to admit extra-record evidence:
    (1) if admission is necessary to determine whether the agency
    has considered all relevant factors and has explained its deci-
    sion, (2) if the agency has relied on documents not in the
    record, (3) when supplementing the record is necessary to
    explain technical terms or complex subject matter, or (4)
    when plaintiffs make a showing of agency bad faith.” Lands
    
    Council, 395 F.3d at 1030
    , quoting Southwest 
    Ctr., 100 F.3d at 1450
    (internal quotations and citation omitted). The district
    court held that the plaintiffs “failed to satisfy any of these
    exceptions.”
    [23] We hold that the district court did not abuse its discre-
    tion in refusing to admit the extra-record evidence. As the dis-
    trict court stated, the plaintiffs “have not demonstrated that
    the criteria used by NDEP have any relevance to a NEPA
    analysis. . . . [T]he NDEP Notice does not assist in under-
    standing either the subject matter of this case or BLM’s deci-
    sion.” The document was not relied on by the Bureau, is not
    necessary to explain technical terms, and does not demon-
    strate bad faith on the part of the Bureau.
    [24] For the same reasons, the district court did not abuse
    its discretion in refusing to take judicial notice of the facts set
    forth in the document.
    AFFIRMED IN PART; REVERSED IN PART;
    REMANDED.
    8654         GREAT BASIN MINE WATCH v. HANKINS
    THOMAS, Circuit Judge, concurring in part and dissenting in
    part:
    I agree with the majority’s holding that the Bureau’s cumu-
    lative effects analysis was insufficient under NEPA, and its
    consequent reversal of the district court’s grant of summary
    judgment as to that issue. However, I respectfully dissent
    from the conclusion that Leeville and the Amended South
    Project are not connected actions requiring a single, compre-
    hensive EIS.
    A careful analysis of the record demonstrates that the
    Bureau should have prepared a single comprehensive EIS for
    Leeville and the Amended South Project. Leeville is depen-
    dent on the South Operations Area Project. Because the
    Amended South Project is merely, in the agency’s words, “an
    expansion of” the South Operations Area Project, Leeville
    and the Amended South Project are necessarily connected
    actions for NEPA purposes.
    Employment of the “independent utility” test does not lead
    to a different conclusion. The benchmark of “independent
    utility” is whether “ ‘each of two projects would have taken
    place with or without the other and thus had independent utili-
    ty.’ ” Wetlands Action Network v. U.S. Army Corps of Eng’rs,
    
    222 F.3d 1105
    , 1118 (9th Cir. 2000). When one of the proj-
    ects might reasonably have been completed without the other,
    each has independent utility and they are not ‘connected’ for
    NEPA purposes. Native Ecosystems Council v. Dombeck, 
    304 F.3d 886
    , 894 (9th Cir. 2002). The sole purpose behind the
    Leeville mine is to obtain gold and other minerals from the
    solids mined. For this to be accomplished, those solids must
    be processed after extraction. The solids extracted at Leeville
    are sent to the South Operations Area Project for processing.
    The Leeville draft EIS states that “[o]re hoisted to the surface
    would be hauled directly to processing facilities at the Refrac-
    tory Ore Treatment Plant (Mill #6) located at Newmont’s
    South Operations Area [Project], or placed in a refractory ore
    GREAT BASIN MINE WATCH v. HANKINS                     8655
    stockpile approximately one-half mile west of the production
    shaft.”1 The total amount of “ore [and waste rock] hoisted to
    the surface” is around 18 million tons. The two projects are
    clearly interconnected and should be considered in a single
    EIS.
    Our case law supports this conclusion. In Blue Mountains
    Biodiversity Project v. Blackwood, 
    161 F.3d 1208
    , 1215 (9th
    Cir. 1998) and Thomas v. Peterson, 
    753 F.2d 754
    , 758 (9th
    Cir. 1985), we determined (1) that five logging projects in one
    watershed, and (2) a logging project and a road to facilitate it,
    respectively, had to be considered in comprehensive EISs.
    Proper application of Blue Mountains and Thomas dictate that
    a single EIS should have been prepared in this case.
    The Bureau relies on Wetlands Action 
    Network, 222 F.3d at 1119
    , and Sylvester v. U.S. Army Corps of Engineers, 
    884 F.2d 394
    , 400 (9th Cir. 1989), in which we held that compre-
    hensive EISs were not required for (1) three phases of a wet-
    lands filling project, and (2) a resort complex and golf course.
    However, those cases are distinguishable from the present cir-
    cumstance.
    In Sylvester, we noted that the resort and golf course “each
    could exist without the other, although each would benefit
    from the other’s presence.” 
    Sylvester, 884 F.2d at 400
    . Simi-
    larly, we reasoned in Wetlands Action Network that “the util-
    ity of [the first] part of the project does not depend upon the
    completion of the later phases of the project[, and i]t would
    not be unwise or irrational to undertake the building of Phase
    I even if it was determined that the later phases could not be
    
    constructed.” 222 F.3d at 1118
    .
    1
    Presumably, the ore placed in the stockpile is stored there until it also
    goes to the South Operations Area Project for processing. Even if it does
    not, however, the analysis is unaltered, applying with the same force to a
    portion of the mined solids as to the whole.
    8656            GREAT BASIN MINE WATCH v. HANKINS
    Leeville and the Amended South Project are more akin to
    the logging project and logging road than the resort complex
    and golf course. It would be not merely unwise, but also
    entirely irrational to proceed with the mining of Leeville in
    the absence of available processing facilities.2 See id.; see
    also Trout Unlimited v. Morton, 
    509 F.2d 1276
    , 1285 (9th
    Cir. 1974) (requiring a single EIS where “[t]he dependency is
    such that it would be irrational, or at least unwise, to under-
    take the first phase if subsequent phases were not also
    undertaken”). The South Operations Area Project processing
    facilities are therefore more like the logging road in Thomas,
    which was essential to the logging operation at issue, than the
    golf course in Sylvester, which was beneficial but not essen-
    tial. Rather than merely “benefit[ting] from the . . . presence”
    of the South Operations Area Project, the Leeville project
    could not exist without a processing facility. This facility is
    in the South Operations Area Project, and so the agency
    should have prepared a single EIS to analyze the impact of
    both Leeville and the expansion of the South Operations Area
    Project, the Amended South Project.
    To the Bureau, Leeville’s dependence on the South Opera-
    tions Area Project is unproblematic; it accepts the contention
    that the South Operations Area Project and the Amended
    South Project are distinct and unconnected. However, the
    record is replete with the Bureau’s assertions that the
    Amended South Project is, for all relevant purposes, nothing
    more than an expansion of the South Operations Area Project.
    For example, the final EIS for the Amended South Project
    2
    The Bureau also relies on the fact that tailing from processing Leeville
    ore at the South Operations Area Project would be deposited in existing
    tailing disposal facilities. The tailings are the waste products that remain
    after the valuable components are isolated and extracted through process-
    ing. Because processing is itself an essential step, and processing at the
    South Operations Area Project is sufficient to defeat Leeville’s “indepen-
    dent utility,” it is irrelevant that disposal of post-processing tailing does
    not show Leeville’s further dependency on the South Operations Area
    Project.
    GREAT BASIN MINE WATCH v. HANKINS            8657
    describes the project as “activities that would support contin-
    ued operation and expansion of existing gold mining and pro-
    cessing at [Newmont’s] South Operations Area Project[,
    which] would not cause any new kinds of [environmental]
    impacts . . . but would extend the time period during which
    existing impacts would continue.” The Amended South Proj-
    ect represents the expansion from the 7,960 total acres dis-
    turbed by the South Operations Area Project to 9,352 total
    acres, disturbed by the South Operations Area Project and the
    Amended South Project together. Indeed, in preparing the
    final EIS for the Amended South Project, the Bureau noted
    that “[i]n many cases, the EIS will refer to the original South
    Operations Area Project EIS rather than repeat information
    that has not changed substantially [since the preparation of
    that document].” Similarly, in response to a comment by Min-
    eral Policy Center that “[d]ue to the complexity, size, and
    importance of the current [draft EIS] (and [cumulative
    impacts analysis]), the sixty day comment period [wa]s not
    nearly sufficient for full and competent response,” the agency
    simply noted that it “consider[ed] 60 days to be adequate
    because this Plan of Operations is an expansion of an existing
    project.”
    It is illogical for the agency to assert the Amended South
    Project’s intense connection to the South Operations Area
    Project when convenient, only to deny that same connection
    in order to justify the refusal to prepare a single EIS for the
    Leeville and Amended South Projects. Permitting the Bureau
    to do so would impermissibly allow the agency to “divid[e]
    a project into multiple ‘actions,’ each of which individually
    has an insignificant environmental impact, but which collec-
    tively have a substantial impact.” Wetlands Action 
    Network, 222 F.3d at 1118
    (internal quotation marks and citation omit-
    ted). Here, the asserted division between the Amended South
    Project and the South Operations Area Project acts to insulate
    Leeville from the Amended South Project, in contravention of
    both CEQ guidelines and our caselaw.
    8658        GREAT BASIN MINE WATCH v. HANKINS
    For these reasons, I conclude that a single, comprehensive
    EIS was required and would reverse the district court’s grant
    of summary judgment for the defendants as to this issue, as
    well as the cumulative impacts analysis. I therefore respect-
    fully dissent.
    

Document Info

Docket Number: 04-16125

Judges: Wallace, Hawkins, Thomas

Filed Date: 7/31/2006

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (34)

idaho-sporting-congress-inc-alliance-for-the-wild-rockies-v-david ( 2002 )

Thomas Jefferson University v. Shalala ( 1994 )

greenpeace-action-a-non-profit-corporation-v-barbara-h-franklin-in-her ( 1993 )

blue-mountains-biodiversity-project-blue-mountain-native-forest-alliance ( 1998 )

wetlands-action-network-a-california-non-profit-organization-ballona ( 2000 )

Marsh v. Oregon Natural Resources Council ( 1989 )

Sierra Club, Imperial County Air Pollution Control District,... ( 2003 )

Sierra Club, Imperial County Air Pollution Control District,... ( 2003 )

United States v. State ( 1998 )

idaho-sporting-congress-and-american-wildlands-v-jack-ward-thomas-and ( 1998 )

Robert W. Hall v. Gale A. Norton, Secretary of the Interior ... ( 2001 )

trout-unlimited-and-randy-berry-plaintiff-intervenor-appellant-v-rogers ( 1974 )

frederic-d-sylvester-plaintiff-appelleecross-appellant-v-us-army ( 1989 )

Pud No. 1 of Jefferson County v. Washington Department of ... ( 1994 )

native-ecosystems-council-a-non-profit-corporation-bear-creek-council-a ( 2002 )

klamath-siskiyou-wildlands-center-an-oregon-non-profit-organization-v ( 2004 )

Colorado Wild, Inc. v. United States Forest Service ( 2000 )

forest-guardians-a-nonprofit-corporation-white-mountain-conservation ( 2003 )

James R. Bankston v. Thomas E. White, Secretary of the Army ... ( 2003 )

sarah-kunaknana-and-jean-numnik-v-william-clark-secretary-of-the ( 1984 )

View All Authorities »