Aspic Engineering and Constr. v. Ecc Centcom Constructors LLC , 913 F.3d 1162 ( 2019 )


Menu:
  •                      FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    ASPIC ENGINEERING AND                             No. 17-16510
    CONSTRUCTION COMPANY,
    Plaintiff-Appellant,                D.C. No.
    4:17-cv-00224-
    v.                               YGR
    ECC CENTCOM CONSTRUCTORS
    LLC; ECC INTERNATIONAL LLC,                          OPINION
    Defendants-Appellees.
    Appeal from the United States District Court
    for the Northern District of California
    Yvonne Gonzalez Rogers, District Judge, Presiding
    Argued and Submitted December 17, 2018
    San Francisco, California
    Filed January 28, 2019
    Before: MILAN D. SMITH, JR. and JACQUELINE H.
    NGUYEN, Circuit Judges, and JANE A. RESTANI, *
    Judge.
    Opinion by Judge Milan D. Smith, Jr.
    *
    The Honorable Jane A. Restani, Judge for the United States Court
    of International Trade, sitting by designation.
    2    ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS
    SUMMARY **
    Arbitration
    The panel affirmed the district court’s order vacating
    under the Federal Arbitration Act an arbitration award
    concerning the termination for convenience of two
    subcontracts for the construction of buildings and facilities
    in Afghanistan.
    The subcontracts were in support of defendants’ prime
    contracts with the U.S. Army Corps of Engineers. The
    subcontracts incorporated by reference Federal Acquisition
    Regulation (“FAR”) clauses governing termination for
    convenience, and they contained a clause mandating that
    plaintiff, a local company, owed to defendants the same
    obligations that defendants owed to the U.S. government.
    Voiding parts of the subcontracts, the arbitrator awarded
    plaintiff some of its claimed costs despite plaintiff’s failure
    to comply with FAR requirements.
    The panel held that, in finding that plaintiff need not
    comply with the FAR provisions, the arbitrator exceeded his
    powers and failed to draw the essence of the award from the
    subcontracts. The arbitrator’s award was “irrational”
    because he improperly based his conclusion not on past
    practices, but on his rationalization that to enforce the FAR
    clauses on plaintiff would be unjust.
    **
    This summary constitutes no part of the opinion of the court. It
    has been prepared by court staff for the convenience of the reader.
    ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS      3
    COUNSEL
    Walt Pennington (argued), Pennington Law Firm, San
    Diego, California, for Plaintiff-Appellant.
    Joseph G. Martinez (argued), Dentons US LLP, Denver,
    Colorado; Andrew S. Azarmi, Dentons US LLP, San
    Francisco, California; for Defendants-Appellees.
    OPINION
    M. SMITH, Circuit Judge:
    In this opinion, we review the award to Aspic
    Engineering and Construction Company (Aspic) following
    arbitration between Aspic and ECC Centcom Constructors,
    LLC and ECC International, LLC (together, ECC). ECC and
    Aspic entered into arbitration to resolve how much money
    ECC owed Aspic after ECC terminated for convenience two
    subcontracts it had awarded to Aspic. The arbitrator
    awarded Aspic just over $1 million, but ECC sought
    successfully to vacate the award in the district court. We
    affirm the district court’s vacation of the arbitration award.
    FACTUAL AND PROCEDURAL BACKGROUND
    I. The Subcontracts
    In support of its prime contracts with the United States
    Army Corps of Engineers (USACE), ECC awarded Aspic
    two subcontracts for the construction of various buildings
    and facilities in Afghanistan. The first was to be performed
    in Badghis province (the Badghis Subcontract). The second
    required the construction of a training facility in Sheberghan
    province (Sheberghan Subcontract).
    4    ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS
    The Badghis Subcontract and the Shebergan Subcontract
    (together, the Subcontracts) contained terms and conditions
    “applicable to all U.S. Government subcontracts.”
    Specifically, the Subcontracts incorporated many Federal
    Acquisition Regulation (FAR) 1 clauses by reference, or in
    haec verba. These clauses included FAR 49.2 through 49.6,
    which govern termination for convenience.              The
    Subcontracts also contained the following clause mandating
    that Aspic owe to ECC the same obligations that ECC owed
    to the United States government, as set forth in the FAR
    clauses: “The obligations of [ECC] to the Government as
    provided in said clauses shall be deemed to be the
    obligations of Subcontractor to [ECC].”
    USACE eventually terminated ECC’s prime contract for
    convenience on the Badghis project. Days later, ECC
    notified Aspic that it was terminating the Badghis
    Subcontract for convenience. Understandably, Aspic sought
    payment for its expenses. On February 9, 2014, Aspic
    submitted its termination settlement proposal for the
    Badghis project to ECC. After review, ECC informed Aspic
    that the corroborative documents it had submitted in support
    of its settlement proposal were inadequate, and Aspic
    admitted it did not have many of the required materials.
    Nevertheless, ECC eventually submitted its termination
    settlement proposal to USACE, and included Aspic’s claim
    for $229,915 in termination costs within that proposal.
    Upon receipt of the termination settlement proposal,
    USACE notified ECC that it would not pay any of ECC’s
    subcontractor termination costs—including the money
    Aspic claimed it was owed—until the Defense Contract
    1
    Title 48 of the Code of Federal Regulations contains the FAR
    regulations.
    ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS             5
    Audit Agency had conducted an audit. Following that audit,
    USACE informed ECC that it had overpaid Aspic for its
    performance under the Badghis Subcontract. In light of that
    determination, USACE refused to pay any of Aspic’s
    claimed termination costs.
    USACE also terminated ECC’s contract for the
    Sheberghan project for convenience. Two days later, ECC
    terminated the Sheberghan Subcontract for convenience.
    Aspic again submitted a termination settlement proposal
    to ECC, this time requesting $1,032,462. ECC, however, did
    not present these claimed costs to the USACE. USACE
    eventually issued a no-cost termination settlement between
    USACE and ECC—a settlement in which USACE claimed
    that the money previously paid to ECC and its
    subcontractors, including Aspic, constituted adequate
    compensation.
    II. Prior Proceedings
    Aspic believed it deserved more money for its efforts
    under the Subcontracts. In August 2015, it submitted a
    settlement demand for $652,000 on the Sheberghan
    Subcontract. ECC refused to pay, so Aspic filed for
    arbitration. Aspic again tried to settle the dispute—issuing
    settlement offers of $830,000 to ECC Centcom Constructors
    and $150,000 to ECC International—but ECC did not accept
    either of these offers.
    In accordance with the Subcontracts, the parties
    proceeded to arbitration. 2 The Arbitrator issued a Partial
    2
    Part A “General Terms and Conditions” of the Subcontracts
    contained provisions requiring arbitration for disputes arising from the
    contracts and the application of California law.
    6    ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS
    Final Award, awarding Aspic $1,072,520.90 and holding
    ECC Centcom Constructors and ECC International jointly
    and severally liable for the total amount. Aspic then sought
    attorneys’ fees and costs. Contemporaneously, ECC moved
    to reduce the Partial Final Award by Aspic’s waived
    damages, and opposed Aspic’s request by arguing that each
    party ought to bear its own attorneys’ fees. The Arbitrator’s
    Final Award (the Award) incorporated the Partial Final
    Award, denied attorneys’ fees and costs, and awarded Aspic
    half of the administrative fees and expenses.
    Aspic filed a petition in the Superior Court for San Mateo
    County, California seeking to confirm the Award. Aspic
    also sought to reverse the Arbitrator’s determination that it
    was not entitled to attorneys’ fees. The Superior Court
    affirmed the Award and modified it to award Aspic
    attorneys’ fees of $435,840, plus all of its arbitration costs.
    The Superior Court then denied ECC’s ex parte application
    to vacate its prior order.
    ECC removed the case to the Northern District of
    California. Before the district court, ECC renewed its effort
    to vacate the Award and the Superior Court’s judgment.
    Aspic did not oppose ECC’s motion to vacate the Superior
    Court’s judgment, and the district court granted that motion.
    The district court then held a hearing on the parties’
    motions to vacate the Award and to confirm and correct the
    Award. Following the hearing, the district court vacated the
    Award. The court held that the Award conflicted with the
    contract because the arbitrator “voided and reconstructed
    parts of the Subcontracts based on a belief that the
    Subcontracts did not reflect a ‘true meetings [sic] of the
    minds.’” Aspic moved for reconsideration, which the court
    denied. Aspic then timely appealed.
    ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS       7
    JURISDICTION AND STANDARD OF REVIEW
    We have jurisdiction pursuant to 
    9 U.S.C. § 16
     and
    
    28 U.S.C. § 1291
    . The Supreme Court has held that review
    of a district court’s decision confirming an arbitration award
    “should proceed like review of any other district court
    decision finding an agreement between two parties, e.g.,
    accepting findings of fact that are not ‘clearly erroneous’ but
    deciding questions of law de novo.” First Options of
    Chicago, Inc. v. Kaplan, 
    514 U.S. 938
    , 948 (1995). We
    apply the same standard of review where the district court
    vacates an arbitration award. See Aramark Facility Servs. v.
    Serv. Emp’s Int’l Union, Local 1877, AFL CIO, 
    530 F.3d 817
    , 822 (9th Cir. 2008) (applying de novo review for legal
    rulings and clear error for findings of fact).
    ANALYSIS
    Aspic offers a litany of reasons why the Arbitrator’s
    Award was rational. However, that argument ignores our
    limited powers when reviewing arbitrated cases. Pursuant to
    the Federal Arbitration Act (FAA), we “must” confirm an
    arbitration award unless we vacate, modify, or correct the
    award as prescribed in 
    9 U.S.C. §§ 10
     and 11. Bosack v.
    Soward, 
    586 F.3d 1096
    , 1102 (9th Cir. 2009). “Neither
    erroneous legal conclusions nor unsubstantiated factual
    findings justify federal court review” of an arbitral award
    under the FAA. 
    Id.
     Review of an arbitration award is “both
    limited and highly deferential.” Comedy Club, Inc. v.
    Improv W. Assocs., 
    553 F.3d 1277
    , 1288 (9th Cir. 2009)
    (quoting Poweragent Inc. v. Elec. Data Sys. Corp., 
    358 F.3d 1187
    , 1193 (9th Cir. 2004)).
    We may vacate an arbitration award where, among other
    reasons, “the arbitrators exceeded their powers, or so
    imperfectly executed them that a mutual, final, and definite
    8    ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS
    award upon the subject matter submitted was not made.”
    
    9 U.S.C. § 10
    . We have held that arbitrators “exceed their
    powers” when the award is “completely irrational” or
    exhibits a “manifest disregard of the law.” Kyocera Corp. v.
    Prudential-Bache Trade Servs., Inc., 
    341 F.3d 987
    , 997 (9th
    Cir. 2003) (internal citations omitted).
    An award is completely irrational “only where the
    arbitration decision fails to draw its essence from the
    agreement.” Comedy Club, 
    553 F.3d at 1288
     (quoting
    Hoffman v. Cargill Inc., 
    236 F.3d 458
    , 461–62 (8th Cir.
    2001)). An arbitration award “draws its essence from the
    agreement” if the award is derived from the agreement,
    viewed “in light of the agreement’s language and context, as
    well as other indications of the parties’ intentions.” Bosack,
    
    586 F.3d at 1106
     (quoting McGrann v. First Albany Corp.,
    
    424 F.3d 743
    , 749 (8th Cir. 2005)). Under this standard of
    review, we decide “only whether the [arbitrator’s] decision
    ‘draws its essence’ from the contract,” not the “rightness or
    wrongness” of the arbitrator’s contract interpretation. 
    Id.
    (quoting Pacific Reinsurance Mgmt. Corp. v. Ohio
    Reinsurance Corp., 
    935 F.2d 1019
    , 1024 (9th Cir. 1991)).
    The question in this appeal, therefore, is not whether the
    Arbitrator’s Award was reasonable overall, but whether the
    Arbitrator exceeded his powers in finding that Aspic need
    not comply with the FAR provisions. We hold that he did.
    In this case, the Arbitrator held, in relevant part:
    The parties entered into two lengthy
    subcontract agreements for the two projects
    which were prepared by ECC and presented
    to ASPIC. Each subcontract included very
    detailed provisions relating to Federal
    regulations governing the work as well as
    ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS   9
    pass through and ‘Pay when/if Paid’ clauses.
    The subcontracts were somewhat onerous as
    to ASPIC and were clearly drafted to give
    every advantage to ECC. In light of the fact
    that the ASPIC was a local Afghanistan
    subcontractor that had some experience with
    government contracting but not nearly as
    extensive as that of ECC, and in view of the
    fact that the normal business practices and
    customs of subcontractors in Afghanistan
    were more ‘primitive’ than those of U.S[.]
    subcontractors experienced with U.S[.]
    Government work, it was not reasonable to
    expect that Afghanistan subcontractors
    would be able to conform to the strict and
    detailed requirements of general contractors
    on U.S. Federal projects. Notwithstanding
    that expectation, ECC prepared its
    subcontract agreements to require the same
    level of precision and adherence to Federal
    procedures from ASPIC as ECC had toward
    the USACE through the pass through
    provisions of the agreements.
    It was not reasonable that when the parties
    entered into the subcontract agreements, they
    both had the same expectations as to the
    performance of the agreements. ECC could
    not expect that ASPIC would be capable of
    modifying their local business practices to
    completely and strictly conform to the US
    governmental contracting practices that were
    normal to ECC. There was not a true meeting
    of the minds when the subcontract
    agreements were entered. Hence, ASPIC was
    10 ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS
    not held to the strict provisions of the
    subcontract agreements that ECC had to the
    USACE. This arbitration demonstrated that
    ASPIC conducted its business practices in a
    manner normal to Afghanistan which was
    clearly not the same as a U[.]S[.]
    subcontractor working on a Federal project in
    the U.S. (emphasis added).
    Aspic contends that vacatur of the Award is not
    warranted because the Arbitrator did not exceed his powers
    in holding that ECC never intended for Aspic to conform
    fully to the Subcontracts’ terms. Conversely, ECC argues
    that the Arbitrator erred by explicitly disregarding the
    Subcontracts’ requirements. The crux of this dispute,
    therefore, is whether the Arbitrator improperly strayed from
    the plain text of the contract.
    An arbitrator may interpret the contract “in light of . . .
    indications of the parties’ intentions” and find that the
    parties’ conduct modified the text of a contract. See Bosack,
    
    586 F.3d at 1106
    . In Metzler Contracting Co. v. Stephens,
    for example, we held that an arbitrator acted within his
    powers when he concluded that the parties, “through their
    acts and conduct,” had waived a portion of the underlying
    cost-plus contract. 479 F. App’x 783, 784 (9th Cir. 2012).
    We found “plausible” the arbitrator’s interpretation of the
    contract despite the contract’s provision limiting the parties’
    ability to waive contract provisions. 
    Id.
     at 784–85.
    What an arbitrator may not do, however, is disregard
    contract provisions to achieve a desired result. In Pacific
    Motor Trucking Co. v. Automotive Machinists Union, the
    arbitrator ruled that the company could not demote an
    employee from the Working Foreman position
    ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS      11
    notwithstanding the fact that the contract granted the
    company discretion over the position. 
    702 F.2d 176
    , 177
    (9th Cir. 1983). We noted that while the arbitrator attempted
    to “justify the award on the basis of past practice . . . there
    was no practice indicating that the employer lacked
    discretion over maintaining the [Working Foreman]
    position.” 
    Id.
     Thus, we held that the district court properly
    vacated the award because the arbitrator “dispense[d] his
    own brand of industrial justice” by “disregard[ing] a specific
    contract provision to correct what he perceived as an
    injustice.” 
    Id.
     (quoting United Steelworkers of Am. v.
    Enterprise Wheel & Car Corp., 
    363 U.S. 593
    , 597 (1960)).
    Here, the Subcontracts incorporate numerous FAR
    provisions, including those that govern termination for
    convenience and the settlement procedure. FAR § 52.249-2
    sets forth the procedure to be used in the event of termination
    for convenience. 
    48 C.F.R. § 52.249-2
    . FAR § 49.108-3
    requires that each settlement be “supported by accounting
    data and other information sufficient for adequate review by
    the Government,” and “in general conformity with the
    policies and principles . . . in this subpart and subparts 49.2
    or 49.3.” 
    48 C.F.R. § 49.108-3
    .
    As the district court determined, the Award “conflicts
    directly with the [Sub]contract[s].”         The Arbitrator
    recognized that the Subcontracts’ pass-through provisions
    obligated Aspic to meet the FAR requirements, yet he found
    that Aspic “was not held to the[se] strict provisions” based
    on Aspic “conduct[ing] its business practices in a manner
    normal to Afghanistan.” This finding alone—if based on
    past practice—would be insufficient for us to vacate an
    arbitral award.
    In arriving at that conclusion, however, the Arbitrator
    evaded the pass-through provisions by determining that
    12 ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS
    there was not a true “meeting of the minds” when the parties
    formed the Subcontracts because “the normal business
    practices and customs of subcontractors in Afghanistan were
    more ‘primitive’ than those of U.S. subcontractors,” and
    ECC could not expect Aspic to “strictly conform” to United
    States governmental contracting regulations. The Arbitrator
    then alluded to Aspic’s hand-written receipts written in the
    “native language” and the use of dates from the Islamic
    calendar. The Arbitrator found that rejecting Aspic’s
    supporting materials because they were not translated into
    English and the Gregorian calendar “would result in a
    forfeiture and unfairness in the resolution of the Aspic
    claims.”
    These facts demonstrate that despite finding that the
    Subcontracts plainly required Aspic to comply with the FAR
    sections, the Arbitrator reasoned that the expectation of a
    seemingly less sophisticated contractor complying with
    these regulations was unreasonable. Thus, the Arbitrator did
    not base his conclusion upon Aspic and ECC’s actual past
    procedures, but upon his rationalization that to enforce the
    FAR clauses on Aspic would be unjust. This an arbitrator
    may not do.
    By concluding that Aspic need not comply with the FAR
    requirements, the Arbitrator exceeded his authority and
    failed to draw the essence of the Award from the
    Subcontracts. The Award disregarded specific provisions of
    the plain text in an effort to prevent what the Arbitrator
    deemed an unfair result. Such an award is “irrational.”
    Our conclusion is further supported by the fact that
    neither party argued that the FAR provisions did not apply
    in their arbitration briefs. To the contrary, substantial
    portions of the parties’ briefs emphasize the other’s failure
    to comply with certain FAR sections: Aspic decried ECC’s
    ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS       13
    violation of its duty to settle set forth in FAR § 49.108-3, and
    ECC contended that Aspic failed to properly present its
    settlement costs to ECC pursuant to FAR § 52.249-2.
    We observe that it is a serious matter when an arbitral
    award determines that a (sub)contractor need not comply
    with the federal contracting regulations when no past
    practices demonstrate variation from those requirements.
    These regulations, while undoubtedly extensive, permit the
    government to maintain fairly uniform contracting standards
    in the many contracts it enters into with parties located in the
    United States and around the world. See 
    48 C.F.R. § 1.101
    (“The [FAR] System is established for the codification and
    publication of uniform policies and procedures for
    acquisition by all executive agencies.”).            To allow
    contractors and subcontractors, foreign or domestic, to evade
    the FAR provisions because a subcontractor was too
    unsophisticated or inexperienced to fully understand them
    would potentially cripple the government’s ability to
    contract with private entities, and would violate controlling
    federal law.
    CONCLUSION
    We have become an arbitration nation. An increasing
    number of private disputes are resolved not by courts, but by
    arbitrators. Although courts play a limited role in reviewing
    arbitral awards, our duty remains an important one. When
    an arbitrator disregards the plain text of a contract without
    legal justification simply to reach a result that he believes is
    just, we must intervene.
    The Arbitrator’s Award in this case was “irrational”
    because it directly conflicted with the Subcontracts’ FAR-
    related provisions, without evidence of the parties’ past
    practices deviating from them, in order to achieve a desired
    14 ASPIC ENG’G & CONSTR. V. ECC CENTCOM CONSTRUCTORS
    outcome. We therefore affirm the district court’s vacatur of
    the Award. Because we affirm the district court, we also
    conclude that Aspic’s argument that the Arbitrator erred in
    failing to award it attorneys’ fees and arbitral costs is moot.
    AFFIRMED.