Romoland School Dist v. Inland ( 2008 )


Menu:
  •                    FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    ROMOLAND SCHOOL DISTRICT;                
    CENTER FOR COMMUNITY
    ACTION AND ENVIRONMENTAL
    JUSTICE; COMMUNITIES FOR A BETTER
    ENVIRONMENT; CALIFORNIA
    UNIONS FOR RELIABLE ENERGY;
    KRISTOPHER JOHNS; DONALD LEE
    No. 06-56632
    SELBY, JR.,
    Plaintiffs-Appellants,
          D.C. No.
    CV-06-02514-AG
    v.
    OPINION
    INLAND EMPIRE ENERGY CENTER,
    LLC; SOUTH COAST AIR QUALITY
    MANAGEMENT DISTRICT
    (SCAQMD); BARRY R.
    WALLERSTEIN, D. Env. In his
    official capacity,
    Defendants-Appellees.
    
    Appeal from the United States District Court
    for the Central District of California
    Ronald S. W. Lew and Andrew J. Guilford,
    District Judges, Presiding
    Argued and Submitted
    March 3, 2008—Pasadena, California
    Filed November 18, 2008
    Before: J. Clifford Wallace, Ronald M. Gould, and
    Sandra S. Ikuta, Circuit Judges.
    Opinion by Judge Gould;
    Concurrence by Judge Wallace
    15419
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY    15423
    COUNSEL
    Marc D. Joseph and Suma Peesapati, Adams Broadwell
    Joseph & Cardozo, South San Francisco, California, for the
    plaintiffs-appellants.
    15424       ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    Robert A. Wyman, Michael G. Romey, and Ernest J. Hahn,
    Latham & Watkins, LLP, Los Angeles, California, for
    defendant-appellee Inland Empire Energy Center.
    Bradley R. Hogin, Woodruff Spradlin & Smart, Orange, Cali-
    fornia, for defendants-appellees South Coast Air Quality
    Management District and Barry R. Wallerstein.
    OPINION
    GOULD, Circuit Judge:
    The Romoland School District and several individuals and
    environmental groups, (collectively, “Plaintiffs”) appeal the
    denial of their motion for a preliminary injunction and the dis-
    missal with prejudice of their two claims against Inland
    Empire Energy Center (“IEEC”), a wholly-owned subsidiary
    of General Electric Company. Plaintiffs brought suit against
    IEEC under the citizen suit provision of the Clean Air Act
    (“CAA” or “Act”), 
    42 U.S.C. § 7604
    , in connection with
    IEEC’s plans to construct an 810-megawatt power plant
    approximately 1,100 feet from the Romoland Elementary
    School in Riverside County, California. IEEC’s motion to dis-
    miss contended, among other things, that the district court
    lacked jurisdiction over the suit because IEEC had been
    granted a permit under Title V of the CAA, 
    42 U.S.C. §§ 7661
    -7661f, and such permits may not be challenged in
    civil or criminal enforcement proceedings in federal district
    court under 
    42 U.S.C. § 7604
    .
    Plaintiffs also included as a defendant in their CAA action
    the South Coast Air Quality Management District (“the air
    district” or “SCAQMD”),1 the local air pollution control
    1
    Plaintiffs also brought suit against Barry R. Wallerstein, an executive
    officer of SCAQMD, in his official capacity. However, as Wallerstein is
    represented by the same counsel as the air district and has not filed any
    motions in his own right, the terms “air district” and “SCAQMD” will be
    used in this opinion to refer collectively to the defendant air district and
    to defendant Wallerstein.
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15425
    agency that issued the relevant permit and authorized IEEC to
    begin construction of the power plant. After the district court
    denied Plaintiffs’ motion for a preliminary injunction and dis-
    missed their claims against IEEC under Federal Rule of Civil
    Procedure 12(b)(6), Plaintiffs sought voluntarily to dismiss
    their claims against the air district under Federal Rule of Civil
    Procedure 41(a)(2) to gain “final judgment for purposes of an
    appeal.” The district court granted Plaintiffs’ motion, but the
    accompanying order did not state that the dismissal of the
    claims against the air district was with prejudice.
    We must resolve two threshold issues of jurisdiction before
    we may consider the merits of Plaintiffs’ claims: (1) whether
    the district court’s dismissals of the claims in this case present
    us with a final decision pursuant to 
    28 U.S.C. § 1291
    ; and (2)
    whether the Central District of California was an appropriate
    forum, and 
    42 U.S.C. § 7604
     an appropriate statutory basis,
    for Plaintiffs’ challenge such that the district court had juris-
    diction over it pursuant to 
    28 U.S.C. § 1331
    . We conclude
    that the orders appealed from are part of a final judgment and
    thus that we have jurisdiction over this case, but that the dis-
    trict court did not. Accordingly, we affirm the district court’s
    dismissal of the claims against IEEC with prejudice, hold that
    the claims against the air district should also be deemed to be
    dismissed with prejudice notwithstanding the voluntary dis-
    missal order’s silence on this point, and further hold that all
    proceedings on Plaintiffs’ motion for a preliminary injunction
    are void because the district court was without jurisdiction to
    entertain that motion.
    I
    A
    Congress passed the Clean Air Act in 1970 “to protect and
    enhance the quality of the Nation’s air resources so as to pro-
    mote the public health and welfare and the productive capac-
    ity of its population.” 
    42 U.S.C. § 7401
    (b)(1). Towards this
    15426     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    end, the United States Environmental Protection Agency
    (“EPA”) is responsible for identifying air pollutants that may
    endanger public health and welfare and for promulgating stan-
    dards for the maximum allowable concentrations of each such
    pollutant in the air, known as National Ambient Air Quality
    Standards or NAAQS. 
    42 U.S.C. §§ 7408
    (a), 7409. The CAA
    further requires the EPA to divide each state into air quality
    control regions, see 
    id.
     § 7407(b)-(c). SCAQMD oversees one
    such region in California, the South Coast Air Basin, compris-
    ing Orange County and portions of Los Angeles, Riverside,
    and San Bernardino Counties. See Engine Mfrs. Ass’n v.
    South Coast Air Quality Mgmt. Dist., 
    498 F.3d 1031
    , 1035
    (9th Cir. 2007). Each air quality control region is labeled as
    either “attainment” or “nonattainment” for each identified
    pollutant depending on whether the average level of that pol-
    lutant in the air in that region is at or below (attainment) or
    above (nonattainment) the level mandated by the NAAQS.
    South Coast Air Basin is an attainment area for some air pol-
    lutants like lead but is a nonattainment area for ozone, carbon
    monoxide, and particulate matter smaller than ten microns in
    diameter, known as PM10.
    Each state must also submit to EPA a State Implementation
    Plan or SIP establishing “enforceable emission limitations and
    other control measures” designed to preserve attainment of
    the NAAQS in attainment areas and achieve attainment in
    nonattainment areas. See 
    42 U.S.C. § 7410
    (a)(2)(A). One
    required element of all SIPs for states with nonattainment
    areas, introduced into the CAA through the 1977 amend-
    ments, is a permitting program for new or modified major sta-
    tionary sources of air pollution, such as electrical generators
    or factory smokestacks, in those nonattainment areas. See 
    42 U.S.C. §§ 7410
    (a)(2)(C), 7502(c)(5). Under this “new source
    review” (“NSR”) program, any new project or modification to
    an existing project that would emit more than a threshold
    amount of a pollutant for which that region has not attained
    the NAAQS must apply for a permit to construct and operate
    that pollution source, and such a permit may only be granted
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY                   15427
    if the project uses technology that will ensure “the lowest
    achievable emission rate” and obtains emission reduction
    credits to offset the emissions that it will produce. 
    42 U.S.C. § 7503
    (a)(1)-(2). SCAQMD implements its NSR program,
    now part of the California SIP, through Rule 1303,2 which
    provides that the air district “shall deny the Permit to Con-
    struct for any new or modified source which results in a net
    emission increase in a nonattainment air contaminant” unless
    the applicant shows through modeling that the proposed activ-
    ity “will not cause a significant increase” in pollution and that
    all emissions will be offset with emission reduction credits.
    See Rule 1303(b)(1)-(2).3
    Once a local rule, like SCAQMD Rule 1303, becomes part
    of an EPA-approved SIP after a public notice and comment
    period, it becomes federally enforceable in district court
    through the CAA’s citizen suit provision, 
    42 U.S.C. § 7604
    .
    This provision states that “[a]ny person may commence a
    civil action on his own behalf against any person . . . who is
    alleged . . . to be in violation of . . . an emission standard or
    limitation,” including “any . . . standard, limitation, or sched-
    ule established under . . . any . . . State Implementation Plan
    2
    The air district’s rules may be accessed at http://yosemite.epa.gov/R9/
    r9sips.nsf/Agency?ReadForm&count=500&state=California&cat=South+
    Coast+Air+Quality+Management+District-Agency-Wide+Provisions (last
    visited August 14, 2008).
    3
    The air district has promulgated another NSR provision, Rule 2005,
    which applies to the air district’s Regional Clean Air Incentives Market,
    or RECLAIM, program, a special permitting program for large emitters of
    nitrogen and sulfur oxides. (The IEEC power plant that is the subject of
    this litigation received its permit through the RECLAIM program.) Rule
    2005 contains modeling and offsets requirements that are virtually identi-
    cal to those in Rule 1303. See, e.g., Rule 2005(b)(1)(B) (“The [air district]
    shall not approve the application for a . . . permit to authorize construction
    or installation of a new or relocated facility unless the applicant demon-
    strates [through modeling] that . . . the operation of any emission source
    located at the . . . facility will not cause a violation or make significantly
    worse an existing violation of the . . . national ambient air quality standard
    at any receptor location in the District . . . .”).
    15428     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    approved by the [EPA] administrator . . . .” 
    42 U.S.C. §§ 7604
    (a)(1), 7604(f)(3)-(4). “The district courts shall have
    jurisdiction, without regard to the amount in controversy or
    the citizenship of the parties, to enforce such an emission
    standard or limitation . . . and to apply any appropriate civil
    penalties . . . .” 
    Id.
     § 7604(a).
    In 1990, Congress amended the CAA to add a nationwide
    system of operating permits like those mandated by other
    environmental laws such as the Clean Water Act. See S. Rep.
    No. 101-228, at 349 (1989) [hereinafter Senate Report]. The
    1990 amendments made it “unlawful . . . to operate” many
    sources of air pollution, including any source located in a
    nonattainment region that would already have been subject to
    the NSR requirements of 
    42 U.S.C. § 7503
    , “except in com-
    pliance with a permit issued by a permitting authority under
    this title.” 42 U.S.C. § 7661a(a). These operating permit pro-
    visions, commonly referred to as Title V of the CAA, also
    specify that “[e]ach permit issued under this title shall include
    enforceable emission limitations and standards, a schedule of
    compliance, . . . and such other conditions as are necessary to
    assure compliance with applicable requirements of this Act,
    including the requirements of the applicable [state] implemen-
    tation plan.” 42 U.S.C. § 7661c(a). Rather than imposing an
    additional set of requirements on pollution sources, this per-
    mitting scheme was intended to “incorporate the requirements
    of the Act (including SIP requirements) that are [already]
    applicable to the source.” Senate Report at 350. See also 
    57 Fed. Reg. 32250
    , 32251 (July 21, 1992) (EPA notice of regu-
    lations implementing Title V) (“While Title V generally does
    not impose substantive new requirements, . . . [t]he program
    will . . . clarify, in a single document, which requirements
    apply to a source and, thus, should enhance compliance with
    the requirements of the Act.”).
    As with the SIPs under 
    42 U.S.C. § 7410
    , each state or
    local pollution control agency was to design a program for
    administering Title V permits that EPA would either approve
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY                15429
    or disapprove after an opportunity for public comment. 42
    U.S.C. § 7661a(d)(1).4 Shortly after Title V was added to the
    CAA in 1990, EPA promulgated regulations setting out the
    minimum elements that such state programs must contain to
    gain EPA approval, and one of these elements concerned the
    available mechanisms for judicial review:
    [The state’s proposed program must] (x) [p]rovide
    an opportunity for judicial review in State court of
    the final permit action by the applicant, any person
    who participated in the public participation process
    provided pursuant to § 70.7(h) of this part, and any
    other person who could obtain judicial review of
    such actions under State laws. . . . [The program
    must also] (xii) [p]rovide that the opportunity for
    judicial review described in paragraph (b)(3)(x) of
    this section shall be the exclusive means for obtain-
    ing judicial review of the terms and conditions of
    permits, and require that such petitions for judicial
    review must be filed no later than 90 days after the
    final permit action, or such shorter time as the State
    shall designate.
    
    40 C.F.R. § 70.4
    (b)(3)(x), (xii).
    Title V differs from earlier CAA provisions in that EPA
    exercises a greater degree of ongoing oversight, reviewing not
    only the states’ permit programs but individual permit appli-
    cations and permits as well. 42 U.S.C. § 7661d(a)(1). More-
    over, EPA has veto power over Title V permits: “If any
    permit contains conditions that are determined by the [EPA]
    Administrator as not in compliance with the applicable
    4
    SCAQMD’s Title V permit program is codified in Rules 3000-3008
    and received final approval from EPA on November 30, 2001. See 40
    C.F.R. pt. 70, appendix A, California (dd)(2); 
    66 Fed. Reg. 63503
    (December 7, 2001) (notice granting final approval to 34 operating permit
    programs in California, including that of SCAQMD).
    15430     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    requirements of this Act, including the requirements of an
    applicable [state] implementation plan, the Administrator
    shall . . . object to its issuance.” 42 U.S.C. § 7661d(b)(1). If
    EPA objects to a permit, it may not be issued unless it is first
    revised to take the objection into account. Id. at
    §§ 7661d(b)(3), 7661d(c).
    If EPA does not object within 45 days of receiving a pro-
    posed permit, “any person may petition the Administrator [to
    make such an objection] within 60 days after the expiration of
    the 45-day review period . . . based only on objections to the
    permit that were raised with reasonable specificity during the
    public comment period provided by the permitting agency
    . . . .” Id. at § 7661d(b)(2). Within 60 days of receiving such
    a petition, EPA must either grant the petition and make the
    proposed objection if the petitioner successfully demonstrates
    “that the permit is not in compliance with the requirements of
    this Act,” or deny the petition. Id. “Any denial of such peti-
    tion shall be subject to judicial review under” 
    42 U.S.C. § 7607
    , a CAA provision concerning judicial review of
    agency actions. 
    Id.
     That judicial review provision allows for
    direct review of “locally or regionally applicable” EPA
    actions in the court of appeals for the circuit in which the
    action arose, but also states that “[a]ction of the Administrator
    with respect to which review could have been obtained under
    [this section] shall not be subject to judicial review in civil or
    criminal proceedings for enforcement.” 
    42 U.S.C. § 7607
    (b)(1)-(2).
    B
    New power plants in Riverside County must undergo over-
    lapping certification processes before they may be built, some
    of which track the requirements of the federal CAA and oth-
    ers that are unique to California or to the air district. The Cali-
    fornia Energy Commission (“CEC”) assesses the
    environmental and public health impacts of any proposed
    power plant with a generating capacity of more than 50 mega-
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY         15431
    watts and has the sole authority to certify the construction and
    operation of a power plant of that size. See 
    Cal. Pub. Res. Code § 25500
    . Before CEC can grant this certification, how-
    ever, it must forward the application to the local air district,
    which in turn determines whether the proposed plant meets
    the requirements of NSR and all other applicable local, state
    and federal air pollution regulations. See Cal. Code Regs tit.
    20, § 1744.5. This review process has two steps within
    SCAQMD: First, after its initial evaluation, the air district
    issues a Preliminary Determination of Compliance (“PDOC”),
    and this document contains any necessary conditions the
    applicant must meet for final approval. Second, after a public
    comment period, the air district issues a Final Determination
    of Compliance (“FDOC”). Only after the air district has
    issued an FDOC for a project may CEC grant final approval
    to that project.
    In addition to its indirect role in the CEC process,
    SCAQMD directly administers other permitting schemes
    applicable to the IEEC project at issue here. First, every piece
    of equipment that may release air contaminants must obtain
    a separate Permit to Construct under District Rule 201 and,
    once the Permit to Construct is granted and the equipment is
    evaluated for its compliance with that permit, a Permit to
    Operate under District Rule 203. Large facilities that are pro-
    jected to emit more than a certain amount of pollution and so
    are subject to Title V of the CAA must also obtain a “facility-
    wide Title V permit” in addition to the individual permits to
    construct and permits to operate required for each piece of
    equipment at the facility. Finally, large emitters of nitrogen
    and sulfur oxides that qualify for the RECLAIM program dis-
    cussed in footnote 3 receive a RECLAIM facility permit from
    the air district pursuant to District Rule 2006. See Rule
    2006(b)(3); Rule 3004(b).
    IEEC first applied to CEC for “certification of a power
    plant in Romoland, an unincorporated area of Riverside
    County” on August 17, 2001. On September 16, 2001, IEEC
    15432      ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    submitted applications to the air district for permits to con-
    struct associated with this project and on September 26 sub-
    mitted its application for a Title V permit. On July 12, 2002,
    SCAQMD issued its PDOC for the project to CEC, and on
    February 28, 2003, the air district issued an FDOC. On
    December 17, 2003, CEC published its decision to certify the
    power plant, noting the Romoland School District’s concerns
    about pollution at the nearby facility but concluding that all
    potential environmental impacts on the school were “either
    insignificant, or were mitigated to a less than significant
    level.” The air district issued a Notice of Intent to grant
    IEEC’s Title V permit in July of 2002 but never issued any
    permits to construct associated with that facility design;
    instead, in March of 2005, IEEC petitioned CEC to modify its
    project to use larger, more energy-efficient turbines that
    would increase the proposed plant’s generating capacity from
    670 to 810 megawatts. CEC deemed this proposal to modify
    to be a request for an amendment to IEEC’s CEC authoriza-
    tion, and approved this amendment on June 22, 2005 after
    holding a public hearing on the subject, concluding that “the
    modifications would not create any new or unmitigated signif-
    icant environmental impacts [and that the new turbines would
    provide] superior fuel economy and environmental perfor-
    mance.”5 The public was invited to raise objections to the new
    facility configuration at the June 22 hearing, but no one
    expressed opposition to the amendment through oral or writ-
    ten comments either before or during that hearing. Plaintiffs-
    Appellants were strikingly silent at that time.
    Because the modifications to IEEC’s proposed project
    required it to supply new emissions calculations and modeling
    analysis to the air district, IEEC canceled its pending permit
    applications and submitted twelve superseding applications in
    early 2005, including an application for a revised Title V and
    RECLAIM facility permit and eleven applications for permits
    5
    Because of the nature of the proposed amendment, the air district was
    not required to provide CEC with a new PDOC and FDOC for the project.
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY                   15433
    to construct individual pieces of equipment. On June 2, 2005,
    the air district published a new Notice of Intent to Issue Per-
    mit in a Riverside newspaper and also mailed the notice to
    more than 750 separate addresses of individuals who had
    either expressed an interest in being notified of such activities
    or who lived within a quarter-mile radius of the proposed
    power plant location. See Rule 212(c)-(d); 3006(a).6 This
    notice included a description of the project and its estimated
    emissions, an explanation of the procedures for public com-
    ment and for requesting a hearing on the proposed permit, and
    contact information for a person at the air district that mem-
    bers of the public could speak to about the plant. See Rule
    212(g); 3006(b). One of the plaintiffs in this case, California
    Unions for Responsible Energy (“CURE”), sent the air district
    a letter in April of 2005 asking to be notified of all develop-
    ments regarding the IEEC proposal, and so CURE was
    included in the mailing of the Notice of Intent and was also
    informed of other proposed SCAQMD actions on the project.7
    California Health and Safety Code § 42302.1 affords “any
    6
    Pursuant to District Rule 212(d), the mailing of notice to individuals
    within a quarter-mile radius of the facility site, as well as parents of chil-
    dren attending the Romoland Elementary School, was conducted by IEEC
    itself, with the relevant names and addresses provided to IEEC by the air
    district.
    7
    CURE, as well as the Romoland School District, had also been
    involved in the public comment proceedings before CEC prior to the
    FDOC issuance and project certification in 2003. Specifically, both of
    these plaintiffs petitioned CEC for, and were granted, formal intervenor
    status in IEEC’s certification process, which gave them the right to submit
    data requests to any other party (including IEEC), participate in CEC-
    sponsored conferences and hearings, present and cross-examine witnesses
    at hearings, and submit briefs. Neither CURE nor the Romoland School
    District, nor any of the other plaintiffs that did not have intervenor status,
    actively participated in any CEC hearings or conferences, and while
    Romoland School District did submit comments, these concerned the
    school district’s desire to receive funding from IEEC to facilitate reloca-
    tion of Romoland Elementary School to a site farther from the proposed
    power plant and did not raise any concerns about the project’s PM10 emis-
    sion levels or offsets that became the basis of this litigation.
    15434       ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    aggrieved person” the right to petition for a hearing on the
    permit before the air district’s hearing board within 30 days
    of receiving the Notice of Intent to Issue Permit and again
    within 30 days after a permit is issued; however, none of the
    plaintiffs used this administrative remedy. EPA also received
    a copy of the proposed permit and stated in a July 5, 2005 e-
    mail that it would not object to the permit’s issuance. No one
    petitioned EPA to reconsider its decision not to object. See 42
    U.S.C. § 7661d(b)(1)-(2) (requiring the EPA to object to non-
    compliant permit provisions and establishing administrative
    and judicial review of citizen petitions for EPA objection to
    state permit applications).
    Accordingly, on August 5, 2005, SCAQMD issued IEEC a
    document entitled “RECLAIM/Title V Facility Permit” which
    contained sections (F and G) describing the RECLAIM rules
    applicable to the facility, a section (K) listing administrative
    conditions associated with Title V, and two sections (D and
    H) enumerating “emission sources at [the] facility that have
    been issued a Permit to Operate or a Permit to Construct
    along with permit conditions for emission sources at [the]
    facility.” The cover letter sent with the permit also assigned
    application numbers to various pieces of equipment and
    explained that those applications “associated with this Facility
    Permit have been approved for Permits to Construct/
    Temporary Permits to Operate . . . .” This cover letter further
    stated that “the enclosed RECLAIM/Title V Facility Permit
    . . . will serve as the official permit for your facility.”
    C
    On February 22, 2006,8 Plaintiffs sent both IEEC and
    SCAQMD a “60-day notice of intent to sue” as required by
    the citizen suit provision of the CAA. 42 U.S.C.
    8
    IEEC contends that when it received this notice from Plaintiffs, it was
    already six months into construction and had committed $400 million to
    the power plant project.
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15435
    § 7604(b)(1)(A). This letter stated that, based on the terms of
    its air district-approved permit, the power plant was in viola-
    tion of the CAA’s NSR provisions in two respects: (1) the
    emission reduction credits IEEC had purchased to offset its
    emissions pursuant to Rule 1303(b)(2) were obtained from the
    district’s Priority Reserve, a bank of credits for which IEEC
    was not eligible; and (2) the plant was projected to emit more
    than the allowable amount of fine particulate matter or PM10
    in violation of Rule 1303(b)(1). Plaintiffs filed a complaint in
    federal district court for the Central District of California on
    April 21, invoking the CAA’s citizen suit provision, 
    42 U.S.C. § 7604
    (a), as the basis for jurisdiction and asserting
    the same two alleged NSR violations as distinct claims under
    the CAA. In all, the complaint contained four causes of
    action, two against IEEC for the allegedly invalid offsets and
    excessive emissions levels, and two against SCAQMD for
    granting IEEC a permit that allowed for those two violations.
    The complaint sought declaratory and injunctive relief as well
    as civil penalties from both defendants and litigation costs.
    Within a month of filing suit, Plaintiffs moved for a prelim-
    inary injunction to halt construction of the power plant until
    IEEC’s permit was modified to comply with the applicable
    CAA provisions. On June 12, 2006, IEEC moved to dismiss
    the two causes of action against it for failure to state a claim
    under Federal Rule of Civil Procedure 12(b)(6). On August
    14, 2006, after a brief hearing, District Judge Lew denied the
    motion for a preliminary injunction, concluding that “the
    injunction factors, that is, the likelihood of success on the
    merits and irreparable harm and the balance of hardships,”
    favored the defendants. In a written order entered on August
    18, the district court also granted IEEC’s motion to dismiss
    the two causes of action against it with prejudice and stated
    that leave to amend would not be granted.
    Although neither the oral ruling nor the written order of the
    district court specified that the dismissal of Plaintiffs’ claims
    against IEEC was based on a lack of subject matter jurisdic-
    15436     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    tion, the order did state that the dismissal was “[based on] the
    reasons set forth in IEEC’s motion to dismiss and the papers
    submitted in support thereof . . . .” That motion and support-
    ing documentation had contended, among other things, that
    the district court lacked jurisdiction over Plaintiffs’ claims
    because Plaintiffs were challenging a Title V permit and so
    were limited to the mechanisms for judicial review provided
    in that part of the CAA. When Plaintiffs’ claims against IEEC
    were dismissed, SCAQMD had not yet filed any dispositive
    motions. However, the air district did submit a “notice of
    position” to the district court on August 11 stating that it
    agreed with IEEC’s jurisdictional argument and would be
    incorporating that argument into a summary judgment motion.
    Responding to these developments, Plaintiffs moved on
    October 10 for voluntary dismissal of their two remaining
    claims against the air district under Federal Rule of Civil Pro-
    cedure 41(a)(2), asserting in their motion that “[i]n granting
    . . . IEEC’s motion to dismiss Plaintiffs’ Third and Fourth
    Causes of Action without leave to amend . . . Judge Lew
    made a jurisdictional decision that is determinative of Plain-
    tiffs’ entire action.” Plaintiffs also pointed out that “the
    remaining defendants in this action have stated their intention
    to file a dispositive motion that asserts some of the same juris-
    dictional arguments IEEC made in its motion [to dismiss]”
    and concluded that “[b]ecause Judge Lew’s ruling is now the
    ‘law of the case’ that applies equally to the remaining defen-
    dants, voluntary dismissal of the remaining claims for the pur-
    poses of gaining final judgment and allowing appeal serves
    judicial economy.” Finally, Plaintiffs stated that the air district
    did not oppose the voluntary dismissal and thus that a hearing
    on the Rule 41 motion was not necessary.
    On October 12, District Judge Guilford, to whom the Plain-
    tiffs’ remaining claims against the air district had been trans-
    ferred on September 20, granted the voluntary dismissal
    motion. The order signed by Judge Guilford and entered on
    the docket read, in its entirety, as follows:
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15437
    On August 18, 2006, Judge Lew entered an order
    dismissing Plaintiffs’ Third and Fourth Causes of
    Action for lack of subject matter jurisdiction. The
    Court hereby grants Plaintiffs’ unopposed applica-
    tion for voluntary dismissal. IT IS SO ORDERED.
    On November 7, Plaintiffs filed a Notice of Appeal
    (“NOA”) that listed both IEEC and SCAQMD as defendants
    and included both parties on the service list. The NOA listed
    the judgment appealed from as the October 12 “Court
    approved voluntary dismissal” and stated that Plaintiffs were
    also appealing “interlocutory orders that gave rise to the judg-
    ment, including, but not limited to, order granting motion to
    dismiss without leave to amend and order denying motion for
    preliminary injunction.”
    In January of 2007, a telephone conversation took place
    between counsel for Plaintiffs and counsel for the air district
    to which both attorneys have stipulated in signed declarations.
    The contact was initiated by SCAQMD’s counsel, Bradley
    Hogin, who raised concerns about the fact that the dismissal
    of Plaintiffs’ claims against the air district was without preju-
    dice; Hogin asked if Plaintiffs would accommodate the air
    district’s concerns by dismissing their appeal, altering the dis-
    missal in the district court to be with prejudice, and then filing
    a new appeal. Plaintiffs’ counsel, Suma Peesapati, declined,
    and Hogin stated that the air district would file a motion to
    dismiss the appeal as not relating to a final judgment. That
    motion was filed on April 12, 2007, and was joined by IEEC,
    who had not known of the voluntary dismissal of Plaintiffs’
    claims against the air district before being served with the
    NOA. On May 31, 2007, Appellate Commissioner Peter Shaw
    denied the defendants’ motion to dismiss the appeal, without
    prejudice to the issue of appellate jurisdiction being consid-
    ered by the merits panel.
    II
    [1] Except in limited circumstances not currently at issue,
    parties may only appeal from, and appellate courts only have
    15438     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    jurisdiction over, “final decisions of the district courts.” See
    
    28 U.S.C. § 1291
    . In this context, a “final decision” is one
    that “ends the litigation on the merits and leaves nothing for
    the court to do but execute the judgment . . . .” Coopers &
    Lybrand v. Livesay, 
    437 U.S. 463
    , 467 (1978) (internal quota-
    tion marks omitted). A district court order is therefore not
    appealable unless it disposes of all claims as to all parties or
    unless judgment is entered in compliance with Federal Rule
    of Civil Procedure 54(b). See Chacon v. Babcock, 
    640 F.2d 221
     (9th Cir. 1981). Related to this “one final judgment rule”
    is what might be called the “single appeal rule,” which
    requires that “a party . . . raise all claims of error in a single
    appeal following final judgment on the merits.” Flannigan v.
    United States, 
    465 U.S. 259
    , 263 (1984) (internal quotation
    marks omitted). We have previously cautioned that “[t]reating
    an order that has the potential of leading to multiple appeals
    as final would be inconsistent with Congress’s policy
    [embodied in 
    28 U.S.C. § 1291
    ] disfavoring piecemeal appel-
    late review.” Cheng v. Comm’r, 
    878 F.2d 306
    , 310 (9th Cir.
    1989). Piecemeal appellate review is not only inimical to the
    will of Congress but also “undermines the efficient use of
    judicial resources” by exposing appellate panels to “the costs
    of repeated familiarization with the [same] case.” See 
    id.
    (internal quotation marks omitted).
    SCAQMD and IEEC both argue that the order denying
    Plaintiffs’ motion for a preliminary injunction and dismissing
    their claims against IEEC with prejudice and the order grant-
    ing Plaintiffs’ motion for voluntary dismissal of their claims
    against SCAQMD, taken together, are not final within the
    meaning of 
    28 U.S.C. § 1291
     and are thus not appealable.
    Federal Rule of Civil Procedure 41 allows plaintiffs voluntar-
    ily to dismiss some or all of their claims against some or all
    defendants. Concha v. London, 
    62 F.3d 1493
    , 1506 (9th Cir.
    1995). Voluntary dismissals that are effected by court order,
    as was done in this case, are governed by Federal Rule of
    Civil Procedure 41(a)(2). Such court-ordered voluntary dis-
    missals are deemed to be without prejudice “[u]nless the order
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY           15439
    states otherwise . . . .” Fed. R. Civ. P. 41(a)(2). Here, the
    order did not state that the claims against SCAQMD were dis-
    missed with prejudice.
    For many years, the general rule in this circuit had been
    that voluntary dismissals without prejudice do not create
    appealable, final judgments. Concha, 
    62 F.3d at 1507
    . The
    rationale was that “[a] voluntary dismissal without prejudice
    is not adverse to the plaintiff’s interests,” as he or she is “free
    to seek adjudication of the same issue at another time in the
    same or another forum.” 
    Id.
     By contrast, we reasoned that
    allowing appeal of voluntary dismissals with prejudice “is not
    likely to undermine our normal appellate practice by encour-
    aging a flow of appeals that are quasi-interlocutory in nature”
    because if the appellate court rejects the plaintiff’s claim, “the
    dismissal of his action with prejudice stands” and so he “is
    precluded from bringing another action for the same cause
    . . . .” 
    Id. at 1508
    .
    [2] The pertinent legal landscape was altered slightly in
    2002 with our decision in James v. Price Stern Sloan, Inc.,
    
    283 F.3d 1064
     (9th Cir. 2002). The James court considered a
    situation in which, following the district court’s grant of par-
    tial summary judgment dismissing most of a plaintiff’s con-
    tract claims, the plaintiff sought voluntary dismissal of her
    remaining claims, relating to separate contracts with the same
    defendant, so that she could pursue an appeal of the partial
    summary judgment. 
    283 F.3d at 1065
    . The district court
    granted her motion to dismiss without prejudice, but we none-
    theless determined that the judgment was final and appeal-
    able, holding that “when a party that has suffered an adverse
    partial judgment subsequently dismisses remaining claims
    without prejudice with the approval of the district court, and
    the record reveals no evidence of intent to manipulate our
    appellate jurisdiction, the judgment entered after the district
    court grants the motion to dismiss is final and appealable
    under 
    28 U.S.C. § 1291
    .” 
    Id. at 1070
    .
    15440     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    [3] Here, as in James, the record does not reflect intentional
    manipulation. The plaintiff in James explained in her motion
    for voluntary dismissal that “[a] federal court trial on the few
    remaining [contracts] would not be an efficient use of time
    and resources” and that “once those claims are dismissed, a
    final judgment can be entered.” 
    Id. at 1068
     (first alteration in
    original). We described those “reasons for seeking a dismissal
    of . . . remaining claims” as “entirely legitimate,” 
    id.,
     and
    those are essentially the same reasons offered by Plaintiffs in
    their Rule 41 motion:
    Voluntary [d]ismissal [i]s [i]n the [i]nterest of
    [j]udicial [e]conomy [because] [d]ismissal [w]ould
    [o]bviate the [n]eed for the SCAQMD defendants’
    [d]uplicative [d]ispositive [m]otion . . . based on the
    same Title V exhaustion argument that IEEC made
    in its motion to dismiss. . . . Under the ‘law of the
    case’ doctrine, the SCAQMD Defendants’ disposi-
    tive motion would dispose of both of Plaintiffs’
    remaining causes of action for lack of subject matter
    jurisdiction . . . thus ending the case. Recognizing
    the high likelihood of this outcome, Plaintiffs seek
    this voluntary dismissal for the purpose of gaining
    final judgment in this case, thereby allowing an
    appeal of this determinative jurisdictional issue.
    As Plaintiffs clarified at oral argument, they sought dismissal
    of their claims against SCAQMD because they believed those
    claims to be resolved by the district court’s rulings on Plain-
    tiffs’ claims against IEEC and their motion for preliminary
    injunction, and they have disclaimed all intention to revive
    their claims against SCAQMD independently of their claims
    against IEEC. Moreover, the air district, like the defendant in
    James, “had an opportunity to argue that [Plaintiffs’ stated
    reasons for seeking voluntary dismissal] were a subterfuge,
    but failed to do so.” 
    283 F.3d at 1068
    . SCAQMD did not
    oppose Plaintiffs’ application for voluntary dismissal and did
    not raise any concerns about finality of the judgment until
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15441
    January of 2007, three months after the dismissal order was
    entered and two months after Plaintiffs filed their Notice of
    Appeal.
    Despite these similarities to James, our case is distinguish-
    able in several important respects. First, James involved mul-
    tiple claims against a single defendant, some of which were
    voluntarily dismissed and others of which (those subject to
    the partial summary judgment) were appealed following the
    voluntary dismissal. 
    Id. at 1065
    . By contrast, here Plaintiffs
    seek to appeal two otherwise interlocutory orders—the order
    dismissing their claims against IEEC but also the order deny-
    ing their motion for a preliminary injunction, a motion which
    had sought relief from both IEEC and SCAQMD. Specifi-
    cally, Plaintiffs’ counsel advised at oral argument that the pre-
    liminary injunction motion sought rescission from SCAQMD
    of the permit it had issued to IEEC. For this reason, Plaintiffs’
    Notice of Appeal listed both IEEC and the air district as
    defendants, and the air district submitted a brief and partici-
    pated in oral argument on appeal even though all of Plaintiffs’
    claims against it had been dismissed. This involvement by a
    defendant in an appeal of issues that it never litigated before
    the district court goes well beyond the straightforward two-
    party scenario contemplated in James, and the legal uncer-
    tainty for such a defendant is compounded where it faces the
    possibility that the original claims against it may be revived,
    depending on the outcome of the appeal, because they were
    dismissed without prejudice.
    Second, the James panel found it significant that the volun-
    tarily dismissed claims in that case related to different con-
    tracts for different pieces of artwork than the claims being
    appealed, making it likely that final judgment could also have
    been obtained through severance of the claims by the district
    court under Federal Rule of Civil Procedure 54(b). See 
    id. at 1068
     (“There is no evidence . . . that James attempted to cir-
    cumvent Rule 54(b), or that the final judgment issued by the
    district court undermines the Rule 54(b) procedures.”).
    15442     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    Although a Rule 54(b) severance was never sought in this
    case, the chances of one being granted are more remote than
    they were in James, given that the two sets of claims here
    involved the same alleged CAA violations at the same power
    plant authorized by the same permit. The closely intertwined
    nature of these claims dictates that as a practical matter, any
    further proceedings in this action or a related future action
    against either of these defendants, whether in our court or the
    district court, would require close monitoring and likely legal
    involvement by all three parties to this appeal. The concerns
    we raised in Cheng about piecemeal appellate review requir-
    ing multiple panels to familiarize themselves with the same
    case, see 
    878 F.2d at 310
    , thus apply with greater force here
    than in James because of the parallels between Plaintiffs’
    claims against IEEC and the air district.
    [4] The year after James was decided, we clarified that
    James had carved out “an exception to the general rule that
    ‘in the absence of [a Rule 54] determination . . . any order or
    other form of decision, however designated, which adjudi-
    cates fewer than all the claims . . . shall not terminate the
    action as to any of the claims[.]’ ” Am. States Ins. Co. v.
    Dastar Corp., 
    318 F.3d 881
    , 888-89 (9th Cir. 2003) (quoting
    Fed. R. Civ. P. 54(b)) (first, third and fourth alterations in
    original). We conclude that this case presents such anomalous
    procedural issues that attempting to fit it within or outside the
    exception created by James—by deciding whether and under
    what circumstances the principle established in James applies
    to cases involving multiple defendants, for example—is nei-
    ther necessary nor advisable. Instead, we adopt the “pragmatic
    evaluation of finality” counseled by our precedents, see 
    id. at 890
    , and conclude that for purposes of this appeal, we will
    treat the dismissal of Plaintiffs’ claims against SCAQMD as
    being with prejudice. We followed this approach in Concha
    v. London, where despite the parties’ stipulation under Federal
    Rule of Civil Procedure 41(a)(1) that the dismissal of remain-
    ing claims was without prejudice, we determined that “the
    label attached to the dismissal is not dispositive” and treated
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15443
    the dismissal as one with prejudice for purposes of creating
    appellate jurisdiction because this designation was consistent
    with the “effect that the Conchas, and indeed all the parties,
    intended the dismissal to have.” 
    62 F.3d at 1508-09
    .
    The Concha decision predated James and thus belonged to
    an era when only dismissals with prejudice gave rise to
    appealable, final judgments. However, many of the same con-
    siderations of intent that motivated us to deem the dismissal
    in Concha with prejudice lead to the same conclusion here.
    Whereas the parties’ stipulation in Concha explicitly stated
    that the dismissal of remaining claims was without prejudice,
    here the order dismissing Plaintiffs’ claims against the air dis-
    trict says nothing about the dismissal’s effect, and the asser-
    tion that it was without prejudice derives solely from the
    presumption in Federal Rule of Civil Procedure 41(a)(2) that
    “[u]nless the order states otherwise, a dismissal under this
    paragraph . . . is without prejudice.” However, looking
    beyond the ambiguous text of the order to Plaintiffs’ other
    statements suggests that their intent was to resolve their
    claims as quickly as possible rather than to leave open multi-
    ple avenues for continued litigation. Plaintiffs included a sen-
    tence in their proposed dismissal order, which the district
    court struck before adopting the order, applying the “law of
    the case” doctrine to their remaining claims. Because their
    claims against IEEC had been dismissed with prejudice,
    applying this doctrine to their claims against SCAQMD
    would have resulted in a dismissal with prejudice of those
    claims as well. Indeed, at oral argument Plaintiffs’ counsel
    assured us that her clients had “no intention” of relitigating
    their claims against the air district but had instead sought an
    immediate appeal in the interest of judicial economy and
    because their ultimate interests—ensuring that IEEC’s pro-
    posed power plant in Romoland does not emit unsafe levels
    of pollution in violation of the CAA—were best served by an
    expeditious resolution of all claims.
    15444       ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    [5] Accordingly, for purposes of this appeal,9 and consistent
    with the record and Plaintiffs’ representation at oral argument,
    we determine that Plaintiffs intended to dismiss their claims
    against the air district with prejudice consistent with the pre-
    vious dismissal with prejudice of their claims against IEEC,
    to which Plaintiffs believed the “law of the case” doctrine
    applied. In light of this unambiguous evidence of intent and
    the ambiguous language of the dismissal order, we will con-
    sider the October 12, 2006 dismissal of Plaintiffs’ claims
    against the air district to be with prejudice. Presented thus
    with an unquestionably final judgment, we have jurisdiction
    to hear this appeal under 
    28 U.S.C. § 1291
     and may proceed
    to consider the jurisdiction of the district court.
    III
    The jurisdictional argument first raised in IEEC’s motion to
    dismiss, and reiterated in both defendants’ briefs and at oral
    argument, has been misconstrued by Plaintiffs throughout this
    appeal as a claim that they “failed to exhaust administrative
    remedies” or a contention that Title V of the CAA “revoked”
    Title I, the part of the CAA containing the NSR and other pre-
    construction requirements. Instead, what the defendants are
    asserting is that because the air district has elected to incorpo-
    rate all federal, state and local regulations regarding air pollu-
    tion, including the requirements of NSR where applicable,
    into a consolidated permitting process for all facilities subject
    to Title V, and because Plaintiffs are not challenging IEEC’s
    compliance with the terms of its permit but are rather assert-
    ing that the permit itself violates District Rule 1303, the only
    forums in which Plaintiffs could have brought that challenge
    9
    This determination relates only to our appellate jurisdiction by making
    it unnecessary for us to rely on or expand James to establish finality for
    purposes of 
    28 U.S.C. § 1291
    . Like the panel in Concha before us, we
    decline to reach the question of what effect this determination would have
    in the district court, given that our disposition of the remaining jurisdic-
    tional question in this case will prevent further consideration of this action
    by a federal district court in any event.
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15445
    to IEEC’s permit are those authorized by Title V of the CAA
    and the SCAQMD rules implementing Title V within the air
    district. Although Plaintiffs argue that they “did not invoke”
    the “additional enforcement scheme” added by Title V and
    thus that this title is “wholly irrelevant” to their action, the
    defendants suggest that when the preconstruction require-
    ments of NSR are incorporated or “merged” into a state’s
    Title V permitting scheme, the compliance of permits granted
    under such a scheme with NSR and other Title I requirements
    may only be challenged through Title V-related judicial
    review procedures, whether a plaintiff specifically “invokes”
    Title V or not. Put another way, the defendants are not argu-
    ing that Plaintiffs failed to take certain administrative steps
    such as petitioning the EPA to object to IEEC’s permit and
    that because of this failure, their claims are not ripe for judi-
    cial review in the district court; rather Defendants are con-
    tending that the type of challenge these plaintiffs are bringing
    —an attack on a duly issued permit as inconsistent with NSR-
    related components of a SIP—can never be brought in federal
    district court under 
    42 U.S.C. § 7604
     when that permit was
    issued pursuant to Title V. To evaluate this jurisdictional chal-
    lenge, we must answer two distinct questions: (1) as a factual
    matter, has the air district merged its preconstruction require-
    ments, including those for new sources of nonattainment pol-
    lutants in nonattainment areas, into a comprehensive
    permitting scheme under the umbrella of Title V; and (2) if
    so, is it a legal consequence of such an arrangement that the
    citizen suit provision of the CAA, 
    42 U.S.C. § 7604
    , may not
    be used to challenge the validity of such a consolidated permit
    under applicable SIP requirements?
    A
    [6] In drafting Title V, Congress intended to impose the
    requirement to obtain an operating permit on a wide range of
    pollution sources, including those sources that were already
    required to gain a permit before beginning construction pursu-
    ant to 
    42 U.S.C. § 7503
    , the CAA’s NSR provision for new
    15446     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    or modified emission sources in nonattainment areas. This
    intended scope of the Title V program is made explicit in 42
    U.S.C. § 7661a(a), which requires “any . . . source required to
    have a permit under Part . . . D of Title I,” the NSR program,
    “to operate . . . in compliance with a permit issued by a per-
    mitting authority under this title.” The substantive require-
    ments of an operating permit under Title V also encompass
    the requirements imposed by NSR and other Title I programs,
    for Congress specified that “[e]ach permit issued under this
    title shall include enforceable emission limitations and stan-
    dards . . . and such other conditions as are necessary to assure
    compliance with applicable requirements of this Act, includ-
    ing the requirements of the applicable [state] implementation
    plan,” which, within the air district, include the NSR require-
    ments of District Rule 1303. See 42 U.S.C. § 7661c(a). What
    sets the preconstruction requirements of NSR apart from Title
    V, by definition, is their timing, and “[n]othing in [Title V]
    shall be construed to alter the applicable requirements of this
    Act that a permit be obtained before construction or modifica-
    tion.” 42 U.S.C. § 7661a(a) (emphasis added).
    [7] To reconcile Title V’s requirements for a permit during
    operation with Title I, Part D’s requirement that a permit be
    obtained before construction or modification, Congress pro-
    vided that state permitting programs under Title V “shall
    establish reasonable procedures to prioritize . . . approval or
    disapproval [of permit applications] in the case of applications
    for construction or modification under the applicable require-
    ments of this Act.” 42 U.S.C. § 7661b(c). See also 
    40 C.F.R. § 70.7
    (a)(3) (similar provision in EPA regulations setting out
    minimum standard for state Title V permitting programs).
    These regulations give other indications that for purposes of
    program administration, Title V permitting requirements may
    overlap with aspects of NSR and other pre-existing programs.
    For example, one regulatory provision establishes a deadline
    by which “sources required to . . . have a permit under the
    preconstruction review program approved into the applicable
    [state] implementation plan under part . . . D of the Act shall
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY       15447
    file a complete application to obtain the [Title V] permit,”
    except “[w]here an existing [Title V] permit would prohibit
    such construction or change in operation, [in which case] the
    source must obtain a permit revision before commencing
    operation.” 
    40 C.F.R. § 70.5
    (a)(1)(ii). Another provision
    defines the term “administrative permit amendment” to
    include, among other things, “a permit revision that . . .
    [i]ncorporates into the [Title V] permit the requirements from
    preconstruction review permits authorized under an EPA-
    approved program” such as a SIP. 
    40 C.F.R. § 70.7
    (d)(1)(v).
    [8] Yet by far the strongest evidence of federal intent to
    consolidate preconstruction and Title V permitting require-
    ments comes from the Federal Register notice in which EPA
    announced the final adoption of its implementing regulations
    for Title V. In a section in that notice entitled “Permit/SIP
    Relationship,” the agency explained:
    The SIP remains the basis for demonstrating and
    ensuring attainment and maintenance of the national
    ambient air quality standards (NAAQS). The permit
    program collects and implements the requirements
    contained in the SIP as applicable to the particular
    permittee. Since permits must incorporate emission
    limitations and other requirements of the SIP, all SIP
    provisions applicable to a particular source will be
    defined and collected into a single document.
    57 Fed. Reg. at 32258. Another section under the heading
    “New Source Review/Title V Relationship” is instructive. It
    states:
    Under today’s final rule State and local permitting
    authorities have the option, but not a mandate, to
    integrate requirements determined during precon-
    struction review with those required under title V.
    Such integration would be consistent with the previ-
    ously stated implementation goals of combining pro-
    15448      ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    grams and building on existing State programs
    which typically have already accomplished such
    integration at the State level. As discussed above, if
    NSR is integrated with the procedural and
    compliance-related requirements contained in [40
    C.F.R.] §§ 70.6, 70.7, and 70.8 (including opportu-
    nity for EPA and affected State review), an existing
    title V permit can be administratively revised to
    reflect the results of the integrated NSR process.
    Id. at 32259.
    [9] Analysis of the air district’s permitting rules leaves little
    doubt that it has taken advantage of this “option . . . to inte-
    grate . . . preconstruction review with . . . Title V” require-
    ments. One district rule, Rule 3003(h), creates some
    confusion of terminology when it states that “[t]he submittal
    of a complete Title V permit application . . . shall not relieve
    any person of the requirements for a pre-construction permit
    under Title I of the federal Clean Air Act, District Regulation
    XIII — New Source Review, or District Rule 2005 — New
    Source Review for RECLAIM.” Despite the use of the term
    “pre-construction permit” in this rule, the cited district NSR
    provisions nowhere refer to a “pre-construction permit” but
    speak instead of “permits to construct,” which are not to be
    granted unless the permit applicant complies with emission
    limitation and offset requirements. See, e.g., District Rule
    1303(a)(1), 1303(b). In turn, the rules that make up District
    Regulation II governing permits to construct contain repeated
    references to Title V of the CAA, such as the statement in a
    list of deadlines for approval or denial of construction permits
    that “permit revisions for Title V facilities shall follow the
    timetables for permit action” set forth in Regulation XXX,
    which contains rules implementing the district’s Title V pro-
    gram. Rule 210(d)(3). Other cross-references to Regulation
    XXX occur in Rule 204 regarding written conditions of con-
    struction permits and in Rule 212, which contains the require-
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15449
    ments for public notice and comment regarding permits to
    construct. See Rule 212(c)(1), 212(c)(3).
    Despite its emphasis on operating permits, Title V is simi-
    larly replete with references to both NSR and permits to con-
    struct. In a parallel to the federal regulations discussed above,
    District Rule 3000(b)(1)(D) defines the term “administrative
    permit revision” to include “any Title V permit revision to . . .
    issue a final permit to operate for any equipment previously
    issued a Title V permit to construct . . . .” The Federal Regis-
    ter notice in which EPA granted interim approval to
    SCAQMD’s Title V program explains the significance of this
    provision:
    Enhanced New Source Review. South Coast’s title V
    permit program provides for enhanced preconstruc-
    tion review, an optional process that allows sources
    to satisfy both new source review and title V permit
    modification requirements at the same time. Any
    modification processed pursuant to South Coast’s
    enhanced preconstruction review procedures may be
    incorporated into the title V permit as an administra-
    tive permit amendment. These enhanced procedures
    obviate the need to undergo two applications, public
    notice, and permit issuance/revision processes for
    the same change. (See [Rule] 3000(b)(1)(D).)
    
    61 Fed. Reg. 45530
    , 45532 (August 29, 1996). Another dis-
    trict rule is explicit about the degree to which the air district
    has merged its Title V permitting scheme with the source-
    specific permits to construct discussed in Rule 1303: “A writ-
    ten authorization to construct, issued as part of a Title V facil-
    ity permit, shall be deemed a permit to construct for the
    purposes of all other District rules and regulations.” Rule
    3007(a)(2).
    [10] The very permitting process at issue in this case dem-
    onstrates the extent of the integration. Although IEEC did
    15450     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    apply for a separate Permit to Construct for each piece of
    emitting equipment at its facility as well as applying for a
    Title V and RECLAIM facility permit, only one permit was
    issued to IEEC by SCAQMD: a “RECLAIM/Title V Facility
    Permit” which included a list of “emission sources at your
    facility that have been issued a Permit to Operate or a Permit
    to Construct . . . .” Not only were all of IEEC’s applicable
    permits contained in a single document, but that permit was
    also subjected to a single public review and comment process
    combining the notice and comment requirements of Rule 212
    concerning permits to construct and Rule 3006 regarding Title
    V permits. Moreover, the RECLAIM/Title V Facility Permit,
    including sections D and H with their lists of pieces of equip-
    ment granted Permits to Construct, was submitted to EPA for
    its review pursuant to Rule 3003(j). We therefore conclude
    that while all substantive requirements of preconstruction
    review remain in place in the air district, as a procedural mat-
    ter the district’s various permit application processes for
    potential emitters subject to Title V have been consolidated
    into a single comprehensive system, under the auspices of
    Title V, and IEEC’s RECLAIM/Title V Facility Permit for its
    proposed Romoland power plant was issued pursuant to this
    consolidated system.
    B
    [11] Title V permits are by no means wholly insulated from
    the CAA’s citizen suit provision. To the contrary, when the
    CAA was amended in 1990 to add Title V, the citizen suit
    provision was also amended to add to the definition of “emis-
    sion standard or limitation,” an alleged violation of which
    authorizes any person to bring an enforcement action, “any
    other standard, limitation, or schedule established under any
    permit issued pursuant to title V, . . . any permit term or con-
    dition, and any requirement to obtain a permit as a condition
    of operations.” 
    42 U.S.C. § 7604
    (f)(4). In other words, if
    IEEC had violated a term or condition of the permit the air
    district issued to it, or if it had sought to begin building and
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15451
    operating the power plant in Romoland without obtaining a
    permit under SCAQMD’s merged Title V/construction permit
    system, either of those alleged violations would have been
    grounds for a citizen suit in district court under 
    42 U.S.C. § 7604
    . However, Plaintiffs’ challenge fits into neither of
    these categories. Instead, Plaintiffs are charging that IEEC is
    complying with the terms of its permit but that those terms are
    themselves a violation of the CAA, specifically, the federally
    enforceable SIP provisions regarding NSR found in District
    Rule 1303. Because these challenged terms are part of a per-
    mit issued under Title V, we must consider Title V’s adminis-
    trative and judicial review provisions for challenging a
    permit. Those provisions require persons objecting to the issu-
    ance of a Title V permit to “petition the Administrator,” and
    provide for judicial review regarding such petitions in the
    courts of appeal under 
    42 U.S.C. § 7607
    , not through citizen
    suits in the district courts via § 7604. 42 U.S.C.
    § 7661d(b)(2). The text of § 7607, which allows for direct
    review of regionally applicable EPA action in the geographi-
    cally appropriate circuit court of appeals, also makes clear
    that this form of judicial review is exclusive, stating that
    “[a]ction of the Administrator with respect to which review
    could have been obtained under [this section] shall not be
    subject to judicial review in civil or criminal proceedings for
    enforcement.” 
    42 U.S.C. § 7607
    (b)(1)-(2) (emphasis added).
    [12] This “use it or lose it” provision of 
    42 U.S.C. § 7607
    (b)(2) does not bar enforcement proceedings only
    where an individual has taken advantage of the opportunity to
    petition the EPA Administrator and then appeals the denial of
    such a petition to the applicable appellate court; instead, judi-
    cial review through civil or criminal enforcement proceedings
    is unavailable whenever an individual “could have . . .
    obtained” such review. Thus, by creating in 42 U.S.C.
    § 7661d(b)(2) an avenue of judicial review that passes
    through 
    42 U.S.C. § 7607
    , Congress effectively foreclosed the
    alternative avenue of citizen suit enforcement through 
    42 U.S.C. § 7604
    .
    15452     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    Our interpretation of § 7607 as it relates to § 7661d is
    strengthened by the implications of Plaintiffs’ proposed alter-
    native. If Plaintiffs were able to bring this action in federal
    district court under the citizen suit provision and that action
    was appealed to our court, and if the same plaintiffs or
    another party who had petitioned EPA pursuant to 42 U.S.C.
    § 7661d(b)(2) and whose petition was denied also appealed
    that denial to our court, then two different panels of this court
    could be simultaneously confronted with similar if not identi-
    cal challenges to the same permit, perhaps even brought by
    the same party. Such a system would be entirely unworkable
    and underscores why Plaintiffs are incorrect when they con-
    tend that 42 U.S.C. § 7661d created “an additional” and not
    a superseding enforcement scheme for challenges to the valid-
    ity under the CAA of Title V permits.
    The two cases cited by Plaintiffs to support their argument
    that allegedly invalid permits may be challenged directly
    through the CAA citizen suit provision, Grand Canyon Trust
    v. Tucson Electric Power Co. and Communities for a Better
    Environment v. Cenco Refining Co., are inapposite. Grand
    Canyon Trust involved a challenge under 
    42 U.S.C. § 7604
     to
    a permit that the plaintiffs contended had lapsed when the
    defendant did not begin construction by a certain date, in vio-
    lation of a federal regulation that provided for the “automatic
    cancellation of already-issued construction permits” if con-
    struction did not commence by the deadline. 
    391 F.3d 979
    ,
    984-85 (9th Cir. 2004). This regulation thus imposed an
    implicit condition on the defendant’s permit with which the
    Grand Canyon plaintiffs alleged the defendants in that case
    did not comply; by contrast, here Plaintiffs acknowledge that
    IEEC is compliant with all applicable terms of its permit but
    argue that those terms violate the CAA.
    In Cenco, one of the plaintiffs in this action, Communities
    for a Better Environment (“CBE”), challenged, under the citi-
    zen suit provision, SCAQMD’s decision to transfer a previ-
    ously expired Permit to Operate an oil refinery to a new
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15453
    permittee who proposed to modernize the formerly non-
    operational refinery. 
    180 F. Supp. 2d 1062
    , 1069-70, 1072
    (C.D. Cal. 2001). CBE alleged various SIP violations includ-
    ing the failure to apply NSR requirements before allowing
    construction and the reactivation and transfer of the previ-
    ously expired permit, which CBE contended was a violation
    of District Rule 209 that operating permits are nontransfer-
    able. 
    Id. at 1072
    . The permitting decisions challenged in
    Cenco did not involve Title V, and when the defendant raised
    the issue of 42 U.S.C. § 7661d supplanting 
    42 U.S.C. § 7604
    as a mechanism for judicial review, the Cenco court
    responded:
    [J]ust because a federal administrative remedy is
    available for objecting to the issuance of a subchap-
    ter V permit does not mean that a legal remedy under
    § 7604 is unavailable for a defendant’s failure to
    comply with [non-Title V-related] SIP permitting
    requirements. Although Cenco may be required to
    eventually acquire subchapter V permits, the mere
    fact that plaintiffs could challenge such permits
    under § 7661d at that time does not preclude plain-
    tiffs from attacking other permits now under the
    broad language of subsection (f)(4) [of § 7604];
    indeed, the Clean Air Act nowhere states that plain-
    tiffs must wait for the issuance of subchapter V per-
    mits before they can sue on existing violations of the
    SIP.
    Id. at 1081 n.6.
    [13] This language in Cenco, coming from a case involving
    the same air district and many of the same district rules at
    issue here, aptly illustrates that there are limits to our holding
    today. We do not opine upon the general contours or scope of
    the citizen suit provision of 42 U.S.C. 7604. We hold only
    that where a state or local air pollution control district has
    integrated the preconstruction requirements of Title I with the
    15454     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    permitting requirements of Title V and a permit is issued
    under that integrated system, a claim that the terms of that
    permit are inconsistent with other requirements of the Clean
    Air Act may only be brought in accordance with the judicial
    review procedures authorized by Title V of that Act, 
    42 U.S.C. § 7661
    -7661f, and may not be brought in federal dis-
    trict court under the Act’s citizen suit provision, 
    42 U.S.C. § 7604
    . Because Plaintiffs’ action was brought in an inappro-
    priate forum under an inapplicable CAA provision in an
    untimely avenue of protest, the district court was without
    jurisdiction to hear it.
    IV
    For the foregoing reasons, we conclude that we have juris-
    diction over this appeal, and we affirm the district court’s dis-
    missal with prejudice of Plaintiffs’ claims against IEEC. We
    grant IEEC’s request for judicial notice of materials relevant
    to the dispositive jurisdictional question in this case. Because
    of our conclusion on that jurisdictional question, we decline
    to reach the merits of Plaintiffs’ claims against IEEC or their
    motion for a preliminary injunction. We further hold that the
    district court should not entertain any further proceedings in
    this case or in a future action seeking to revive Plaintiffs’
    claims against the air district pursuant to the October 12, 2006
    dismissal of those claims without prejudice, because that
    court lacks subject matter jurisdiction over such claims under
    
    28 U.S.C. § 1331
    .
    AFFIRMED.
    WALLACE, Circuit Judge, concurring in the result:
    I agree that this appeal should be dismissed, but for a dif-
    ferent reason. Our precedents dictate that the plaintiffs’ volun-
    tary dismissal pursuant to Federal Rule of Civil Procedure
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15455
    41(a)(2) cannot constitute an appealable final judgment
    because the dismissal was without prejudice. The majority,
    however, holds that the dismissal order can in fact constitute
    a final judgment for purposes of appeal under a “pragmatic
    evaluation of finality.” Although this court has sanctioned a
    pragmatic approach to determining finality in certain limited
    circumstances, the majority’s ruling impermissibly expands
    this doctrine beyond its narrow confines. In so doing, the
    majority adds uncertainty to the final judgment rule of appel-
    late jurisdiction, and undermines important values of judicial
    economy. In my view, the better course is to follow our
    clearly established rules of federal jurisdiction, and dismiss
    this appeal for lack of appellate jurisdiction. Accordingly, I
    would not reach the issue of the district court’s subject matter
    jurisdiction as discussed in Part III of the majority opinion.
    I.
    Except in limited circumstances not relevant here, the
    courts of appeals have jurisdiction to review only “final deci-
    sions of the district courts.” 
    28 U.S.C. § 1291
     (2008). A “final
    decision” under section 1291 is “a decision by the District
    Court that ends the litigation on the merits and leaves nothing
    for the court to do but execute the judgment.” Coopers & Lyb-
    rand v. Livesay, 
    437 U.S. 463
    , 467 (1978) (internal quotation
    marks, citation and footnote omitted). The final judgment rule
    is essential to the proper functioning of the federal courts, as
    it promotes judicial efficiency, prevents multiplicity of litiga-
    tion, and minimizes delay “by forbidding piecemeal disposi-
    tion on appeal of what for practical purposes is a single
    controversy.” Cobbledick v. United States, 
    309 U.S. 323
    , 325
    (1940).
    In Concha v. London, we held that a plaintiff’s “voluntary
    dismissal without prejudice is ordinarily not a final judgment
    from which the plaintiff may appeal.” 
    62 F.3d 1493
    ,1507 (9th
    Cir. 1995) (emphasis in original), citing Coursen v. A.H. Rob-
    ins Co., Inc., 
    764 F.2d 1329
    , 1342, corrected, 
    773 F.2d 1049
    15456     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    (9th Cir. 1985). We reasoned that, “[t]he policy against piece-
    meal appellate litigation is [ ] at its height in such cases”
    where a party appeals a voluntary dismissal without prejudice
    because if that party loses on appeal, he “is in no way pre-
    cluded from proceeding with the litigation following the
    adverse decision.” 
    Id.
     at 1508 n.8.
    Here, the district court approved the plaintiffs’ unopposed
    Rule 41(a)(2) motion for voluntary dismissal of their claims
    against the air district. The parties agree that because this
    order did not specify whether the dismissal was with or with-
    out prejudice, the dismissal is deemed to be without prejudice
    pursuant to Rule 41(a)(2). Therefore, under Concha, the
    plaintiffs’ voluntary dismissal cannot constitute a final judg-
    ment for purposes of exercising appellate jurisdiction.
    The plaintiffs argue that the voluntary dismissal nonethe-
    less falls within the narrow exception to Concha articulated in
    James v. Price Stern Sloan, Inc., 
    283 F.3d 1064
     (9th Cir.
    2002). In that case, we permitted the plaintiff to appeal an
    adverse partial summary judgment order after she obtained a
    voluntary dismissal without prejudice of her remaining
    claims. 
    Id. at 1068-70
    . We held that the voluntary dismissal
    without prejudice created sufficient finality for the purposes
    of appeal because it was made “with the approval of the dis-
    trict court, and the record reveals no evidence of intent to
    manipulate our appellate jurisdiction.” 
    Id. at 1070
    .
    The James exception is not applicable here. As the majority
    correctly concludes, our case “is distinguishable [from James]
    in several important respects,” including the fact that the
    plaintiffs seek to appeal issues never litigated before the dis-
    trict court, and the fact that there is a greater threat of piece-
    meal appellate review in this case given the “closely
    intertwined nature” of the claims dismissed with prejudice
    and those dismissed without prejudice. (Maj. Op. 15441-43.)
    In addition, contrary to the majority’s conclusion, the
    record reveals at least some evidence that the plaintiffs’ vol-
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY           15457
    untary dismissal without prejudice was done with an intent to
    manipulate our appellate jurisdiction. In particular, when
    counsel for the air district notified plaintiffs’ counsel about its
    concerns that the “without prejudice” dismissal could render
    the decision non-final, plaintiffs’ counsel adamantly refused
    to make the dismissal “with prejudice.” Although this is not
    direct evidence of an intent to manipulate the appellate pro-
    cess, the James exception does not require a lack of substan-
    tial evidence or even significant evidence. So long as there is
    any evidence of an intent to manipulate, the exception does
    not apply. James, 
    283 F.3d at 1068-69
     (finding “no evidence”
    that the plaintiff deliberately attempted to manipulate the
    court’s appellate jurisdiction).
    The default jurisdictional rule in Concha therefore applies
    to this case. Under this well-established precedent, voluntary
    dismissals without prejudice, like the dismissal at issue here,
    are not appealable final judgments, and this court lacks juris-
    diction to review such judgments on appeal.
    II.
    The majority acknowledges that Concha precludes volun-
    tary dismissals without prejudice from being appealable final
    judgments. (Majority Op. 15439.) The majority also concedes
    that the James exception does not apply to the facts of this
    case. (Majority Op. 15442.) Nonetheless, the majority holds
    that appellate jurisdiction exists here because the plaintiffs’
    dismissal without prejudice can be construed as being one
    with prejudice under a “pragmatic evaluation of finality.”
    (Maj. Op. 15442.) Unfortunately, this ruling cannot be
    squared with our precedent.
    In construing the plaintiffs’ dismissal as one with prejudice,
    the majority principally relies on the fact-specific inquiry
    undertaken in Concha. (Maj. Op. 15443-45.) In that case,
    although we held that voluntary dismissals without prejudice
    ordinarily do not constitute appealable final judgments, we
    15458     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    ultimately concluded that “[i]n this unusual case,” the plain-
    tiffs’ voluntary dismissal without prejudice would be treated
    as one with prejudice for the purposes of appeal. Concha, 
    62 F.3d at 1508-09
    . We justified this decision on the grounds that
    there was “no question” that the plaintiffs “intended” their
    dismissal to be with prejudice, and further that the plaintiffs
    had “absolutely nothing to gain by filing a voluntary dismissal
    without prejudice.” 
    Id. at 1508
    .
    This court’s determination of finality in Concha represents
    a fact-specific exception to the general rule that voluntary dis-
    missals without prejudice do not constitute final judgments
    for the purposes of appeal. As we have held, any exceptions
    to our established bright-line jurisdictional rules should be
    construed narrowly. Cf. Am. States Ins. Co. v. Dastar Corp.,
    
    318 F.3d 881
    , 888-89 (9th Cir. 2003) (holding that the James
    exception must be narrowly construed because “[a]ny other
    interpretation . . . would undermine [Federal Rule of Civil
    Procedure] 54(b) and add uncertainty to the final judgment
    rule”). Thus, in accordance with the specific facts addressed
    in Concha, I conclude that a court may construe a party’s vol-
    untary dismissal without prejudice to be one with prejudice
    only where (1) there is “no question” that the party “intended”
    the dismissal to be with prejudice, and (2) that party has “ab-
    solutely nothing to gain” from filing a voluntary dismissal
    without prejudice. Concha, 
    62 F.3d at 1508-09
    .
    The plaintiffs in this case cannot make these required
    showings. First, as described above, the record demonstrates
    that the plaintiffs in fact had no intention of entering a dis-
    missal with prejudice. When asked by opposing counsel to
    change their without-prejudice dismissal to one with preju-
    dice, plaintiffs’ counsel flatly refused.
    Second, it is not at all clear that the plaintiffs had “abso-
    lutely nothing to gain” from filing a without-prejudice dis-
    missal. In fact, the logical inference from their refusal to enter
    such a dismissal is that they perceived some advantage to
    ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY          15459
    obtaining a dismissal without prejudice. Moreover, although
    the plaintiffs argue that an adverse decision on this appeal
    would preclude their dismissed claims against the air district,
    nothing would prevent them from refiling their air district
    claims and seeking a different result. The majority cites the
    plaintiffs’ representations at oral argument that they do not
    seek to relitigate these claims as evidence that there is little
    possibility of such piecemeal litigation. (Maj. Op. 15444.)
    However, the whole point of having bright-line jurisdictional
    rules is to avoid the expense and effort of appeal in the first
    place. We cannot have a rule where parties are unable to
    determine appellate jurisdiction based on a facial examination
    of the record, but must instead go through the trouble of writ-
    ing briefs and preparing for oral argument to guard against the
    possibility of a last-minute determination of jurisdiction.
    Cheng v. Comm’r Internal Revenue Serv., 
    878 F.2d 306
    , 310
    (9th Cir. 1989) (“[O]ne of the primary purposes underlying
    the final judgment rule [is] the efficient use of judicial
    resources”).
    For these reasons, I would not follow the majority’s
    approach in construing the plaintiffs’ voluntary dismissal to
    be one with prejudice. To expand the exception recognized in
    Concha beyond the specific facts of that case, as the majority
    does here, risks the adoption of an all-too flexible test for fed-
    eral jurisdiction, one that would mimic former Justice Potter
    Stewart’s definition of pornography: I know it when I see it.
    This approach is diametrically opposed to our federal juris-
    prudence, which requires finality to be clear and identifiable
    on the record. 15A Wright & Miller, Federal Practice and
    Procedure § 3913, at 462 (1992) (“Although well-established
    rules of appealability might at times cause an action to be
    determined unjustly, slowly, and expensively, they have none-
    theless the great virtue of forestalling the delay, harassment,
    expense, and duplication that could result from multiple or ill-
    timed appeals”).
    Moreover, the plaintiffs had multiple avenues through
    which they could have appealed the non-final orders entered
    15460     ROMOLAND SCHOOL v. INLAND EMPIRE ENERGY
    by the district court. Most obviously, they could have simply
    specified that their dismissal was with prejudice, thereby
    adhering to this court’s established rules of federal jurisdic-
    tion. Or, if a dismissal with prejudice was unpalatable, they
    could have moved for a Rule 54(b) severance, which permits
    a party to appeal otherwise non-final orders after the district
    court has made the required determination that there is no just
    reason for delay. Fed. R. Civ. P. 54(b) (2008).
    I suggest we take an unfortunate and counter-productive
    turn when we fail to accept the dismissal with prejudice as
    necessary for appellate jurisdiction. We do not need to remind
    good lawyers to meet this standard, and we do not improve
    the appellate process by crafting rules to make up for those
    who are incompetent. Federal appellate jurisdiction is based
    on statutory requirements; and it is, in my view, misguided for
    us to stray from specific, easily discoverable requirements
    (dismissal with prejudice) to those so indefinite that guess-
    work is required (dismissal without prejudice — but I did not
    mean it).
    Therefore, I concur in the result of the majority, but for the
    reason that our court’s jurisdiction has not been demonstrated.