Apac v. Bpa ( 2013 )


Menu:
  •                 FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    ASSOCIATION OF PUBLIC AGENCY          No. 11-73178
    CUSTOMERS,
    Petitioner,
    OPINION
    v.
    BONNEVILLE POWER
    ADMINISTRATION,
    Respondent,
    CITIZENS UTILITY BOARD OF
    OREGON; EUGENE WATER &
    ELECTRIC BOARD; IDAHO POWER
    COMPANY; NORTHWEST
    REQUIREMENTS UTILITIES; PUGET
    SOUND ENERGY, INC.; PACIFICORP;
    PACIFIC NORTHWEST GENERATING
    COOPERATIVE; PUBLIC POWER
    COUNCIL; PUBLIC UTILITY
    COMMISSION OF OREGON; PUBLIC
    UTILITY DISTRICT NO. 1 OF COWLITZ
    COUNTY, WASHINGTON; PUBLIC
    UTILITY DISTRICT NO.1 OF
    SNOHOMISH COUNTY, WASHINGTON;
    PUBLIC UTILITY DISTRICT NO. 1 OF
    BENTON COUNTY, WASHINGTON;
    THE CITY OF SEATTLE,
    Respondents-Intervenors.
    2                          APAC V. BPA
    On Petition for Review of an Order of the
    Bonneville Power Administration
    Argued and Submitted
    February 19, 2013—Portland, Oregon
    Filed October 28, 2013
    Before: Arthur L. Alarcón, Stephen S. Trott,
    and Richard A. Paez, Circuit Judges.
    Opinion by Judge Paez;
    Dissent by Judge Alarcón
    SUMMARY*
    Bonneville Power Administration
    The panel denied a petition for review of a decision of the
    Bonneville Power Administration adopting the Residential
    Exchange Program Settlement Agreement, which set terms
    for refunding energy customers who were previously
    overcharged and set new rate terms for the next seventeen
    years.
    The panel held that the Association of Public Agency
    Customers, a group whose members were not direct
    customers of the Bonneville Power Administration (“BPA”),
    had constitutional and prudential standing to challenge the
    *
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    APAC V. BPA                            3
    Settlement, due to the “pass-through” contracts under which
    its members paid rates that directly reflected the rates that the
    BPA charged its direct customers. Concerning the merits, the
    panel held that the Settlement complied with the relevant
    statutory requirements of the Pacific Northwest Electric
    Power and Conservation Act, the Bonneville Project Act, and
    regulations of the Federal Energy Regulatory Commission,
    and with the court’s prior decisions in Portland Gen. Elec.
    Co. v. BPA, 
    501 F.3d 1009
     (9th Cir. 2007), and Golden Nw.
    Aluminum, Inc. v. BPA, 
    501 F.3d 1037
     (9th Cir. 2007). The
    panel also held that the Settlement did not improperly bind
    non-settling parties to the Agreement. Finally, the panel held
    that the BPA Administrator’s adoption of the Settlement in
    the Record of Decision was not arbitrary and capricious.
    Judge Alarcón dissented because he would hold that
    Association of Public Agency Customers lacked Article III
    standing, and therefore the court lacked jurisdiction to reach
    the merits of the case.
    COUNSEL
    Kathleen M. Sullivan (argued), Quinn Emanuel Urquhart &
    Sullivan, LLP, New York, New York; Michael Alcantar and
    Donald Brookhyser, Alcantar & Kahl, LLP, Portland,
    Oregon; Michael N. Kunselman, Alston & Bird, LLP,
    Washington, D.C.; John M. Rochefort, Alston & Bird, LLP,
    Los Angeles, California; Judith Endejan, Graham & Dunn,
    PC, Seattle, Washington; Jason N. Poulos, Weinberg Wheeler
    Hudgins Gunn & Dial, Atlanta, Georgia, for Petitioner.
    4                     APAC V. BPA
    Kurt R. Casad (argued), Special Assistant United States
    Attorney, S. Amanda Marshall, United States Attorney,
    Stephen J. Odell, Assistant United States Attorney, Richard
    A. Greene, Special Assistant United States Attorney,
    Portland, Oregon; Randy A. Roach and Timothy A. Johnson,
    Bonneville Power Administration, Portland, Oregon, for
    Respondent.
    Jay T. Waldron (argued) and Sara Kobak, Schwabe
    Williamson & Wyatt, PC, Portland, Oregon; Donald G. Kari
    and Jason Kuzma, Perkins Coie, LLP, Bellevue, Washington;
    Michael G. Andrea, Avista Corporation, Spokane,
    Washington; Scott G. Seidman, Tonkon Torp, LLP, Portland,
    Oregon; Dan L. Bagatell, Perkins Coie, LLP, Phoenix,
    Arizona; Ryan L. Flynn, Pacificorp, Portland, Oregon; R.
    Blair Strong, Paine Hamblen, LLP, Spokane, Washington, for
    Intervenors PacificCorp., et al.
    Paul M. Murphy (argued), Murphy & Buchal, LLP, Portland,
    Oregon; Sarah Dennison-Leonard, Portland, Oregon, for
    Intervenors Northwest Requirements Utilities, et al.
    Stephanie Andrus, Assistant Attorney General, Salem,
    Oregon; Donald L. Howell, II, Deputy Attorney General,
    Boise, Idaho; G. Catriona McCracken and Raymond W.
    Myers, Citizens’ Utility Board of Oregon, Portland, Oregon,
    for Intervenors Idaho Public Utilities Commission, et al.
    APAC V. BPA                                  5
    OPINION
    PAEZ, Circuit Judge:
    In this opinion, we consider whether a settlement
    agreement between the Bonneville Power Administration
    (“BPA”) and a large number of its customers is lawful. We
    invalidated a previous settlement between BPA and a class of
    customers because it did not comply with the Pacific
    Northwest Electric Power Planning and Conservation Act
    (“NWPA”). See Portland Gen. Elec. Co. v. BPA, 
    501 F.3d 1009
    , 1036–37 (9th Cir. 2007) (“PGE”); Golden Nw.
    Aluminum, Inc. v. BPA, 
    501 F.3d 1037
    , 1048 (9th Cir. 2007)
    (“Golden Nw.”). On remand, BPA initiated a complex rate-
    making process, under which it calculated both (1)
    overcharges resulting from the unlawful settlement, and (2)
    new rates, intended to comply with PGE and Golden
    Northwest. Its customers, in turn, filed numerous petitions
    for review in this court, challenging various aspects of BPA’s
    rate-making.1
    In the face of potentially unending litigation, BPA and a
    large number of its customers entered into the Residential
    Exchange Program Settlement Agreement (“REP-12
    Settlement Agreement” or “Settlement”). Record of Decision
    (“ROD”) 14.2 The Settlement sets terms for refunding
    1
    At the time of the BPA Administrator’s final decision in this case,
    there were 56 petitions pending before the Ninth Circuit “on issues related
    to BPA’s establishment of its power rates.” Record of Decision 13.
    2
    The REP-12 Record of Decision is contained in BPA’s supplemental
    excerpts of record, filed with the court. It is also available at
    6                          APAC V. BPA
    customers who were previously over-charged, as well as
    setting terms—including a new rate-making methodology—
    for the next seventeen years. After a thorough evaluation, the
    BPA Administrator issued the REP-12 Record of Decision, a
    final agency action, in which he adopted the Settlement and
    committed BPA to abide by its terms.
    In its petition for review, the Association of Public
    Agency Customers (“APAC”) challenges the Settlement,
    alleging that it violates several provisions of the NWPA,
    16 U.S.C. §§ 839c(c), 839e(b), the Bonneville Project Act,
    16 U.S.C. § 832d(a), regulations of the Federal Energy
    Regulatory Commission, 
    18 C.F.R. §§ 300.1
    (b)(6),
    300.21(e)(1), and this court’s decisions in PGE and Golden
    Northwest.3 In response, BPA and the intervening parties
    argue, in part, that APAC’s members lack standing to bring
    this challenge, because they are merely the customers of
    BPA’s customers, not direct customers themselves.4 We
    conclude that APAC has standing to challenge the Settlement,
    due to the “pass-through” contracts under which its members
    pay rates that directly reflect the rates BPA charges its direct
    http://www.bpa.gov/Finance/ResidentialExchangeProgram/Pages/defau
    lt.aspx. We cite to the page numbers of the Record of Decision, rather
    than to the parties’ supplemental excerpts of record.
    3
    APAC’s petition was initially consolidated with Alcoa Inc. v. BPA, No.
    11-73161. However, BPA and Alcoa later reached a settlement of their
    dispute and agreed to dismiss that action under Rule 42(b) of the Federal
    Rules of Appellate Procedure. We dismissed Alcoa’s petition with
    prejudice on December 18, 2012.
    4
    The intervening parties are: a group of investor-owned utilities
    (“IOUs”), a group of consumer-owned utilities (“COUs”), and the
    Citizens’ Utility Board of Oregon. All intervening parties urge the court
    to dismiss or deny APAC’s petition.
    APAC V. BPA                                7
    customers. With respect to the merits, however, we conclude
    that the Settlement complies with the relevant statutory
    requirements and with our prior decisions, and we therefore
    deny APAC’s petition for review.
    I. BACKGROUND
    We have previously chronicled the history of BPA, a
    federal agency that markets power generated by federal
    hydroelectric projects in the Columbia River Basin. See, e.g.,
    Alcoa, Inc. v. Bonneville Power Admin., 
    698 F.3d 774
    , 779
    (9th Cir. 2012); Pac. Nw. Generating Co-op. v. Dep’t of
    Energy, 
    580 F.3d 792
    , 797–800 (9th Cir. 2009); Golden Nw.,
    501 F.3d at 1041; PGE, 501 F.3d at 1013–16; Pub. Power
    Council, Inc. v. Bonneville Power Admin., 
    442 F.3d 1204
    ,
    1206 (9th Cir. 2006); M-S-R Pub. Power Agency v.
    Bonneville Power Admin., 
    297 F.3d 833
    , 836–37 (9th Cir.
    2002) (as amended); Ass’n of Pub. Agency Customers, Inc. v.
    Bonneville Power Admin., 
    126 F.3d 1158
    , 1163–65 (9th Cir.
    1997) (“APAC”). Nevertheless, because of the complexity of
    the case, we begin with a brief review of the relevant history
    of the agency and provisions of the NWPA, one of “the tangle
    of statutes that govern [BPA’s] operations.” Golden Nw.,
    501 F.3d at 1042.5 We then discuss the specific facts relevant
    to this appeal.
    5
    “BPA’s authority to market power is derived from four separate acts:
    the Bonneville Project Act; the Regional Preference Act of 1964,
    
    16 U.S.C. §§ 837
    –837k (2000); the Federal Columbia River Transmission
    System Act, 
    16 U.S.C. §§ 838
    –838k (2000); and the [NWPA], 
    16 U.S.C. §§ 839
    –839h (2000).” PGE, 501 F.3d at 1014 n.2. BPA “originally
    operated under an annual congressional appropriation, but was
    restructured as a self-financed agency in 1974.” Id. at 1014.
    8                      APAC V. BPA
    A.
    Congress created BPA, an agency within the Department
    of Energy, in 1937. PGE, 501 F.3d at 1013. The agency was
    initially “tasked with marketing the power generated by
    federally owned dams on the Columbia River.” Id. For the
    first thirty years of its existence—from the 1930s through the
    1960s—BPA had sufficient resources to meet the power
    demands of two classes of customers. Id. at 1014. First, BPA
    provided power to “preference utilities,” also known as
    “consumer-owned utilities” or “COUs.” This class consists
    of publicly-owned utilities, cooperatives, and federal
    agencies, who are accorded priority to federal power under
    the Bonneville Project Act. Id.; see also 16 U.S.C. § 832c(a),
    (d). Second, BPA provided power to “non-preference
    utilities.” PGE, 501 F.3d at 1014. This class of customers is
    made up of two sub-classes: (1) investor-owned utilities
    (“IOUs”), who purchase power for re-sale, and (2) direct
    service industrial customers (“DSIs”), who purchase power
    for direct consumption. Id.; see also APAC, 
    126 F.3d at 1164
    .
    As demand for low-cost federal power rose in the 1970s,
    BPA forecast that it would be unable to meet all of its
    customers’ power needs by the end of the decade. PGE,
    501 F.3d at 1014. An “uncertain and unstable” period
    followed, during which BPA advised non-preference
    customers—and, later, preference customers—of its looming
    inability to provide them with power. APAC, 
    126 F.3d at 1165
    ; see also PGE, 501 F.3d at 1014. As a result, many
    non-preference customers were forced to purchase power
    elsewhere, “at a severe cost disadvantage in the marketplace.”
    Id.
    APAC V. BPA                          9
    B.
    In response to the pending energy crisis, Congress
    enacted the NWPA in 1980. The NWPA “transformed BPA
    from an agency that merely sold whatever power was
    available from generating facilities in the Federal Columbia
    River Power System to one charged with the responsibility of
    meeting the region’s future power needs.” APAC, 
    126 F.3d at 1165
    . Of particular importance here, the statute authorizes
    BPA to “exercise greater control over its power supply and to
    augment that supply by purchasing electric power in the
    market.” PGE, 501 F.3d at 1014. It also authorizes the BPA
    Administrator to “establish and revise the rates at which
    BPA’s power is sold,” and—subject to certain limitations—to
    “enter into contracts, agreements, and settlements of claims
    and contractual obligations.” Id. Two of the provisions
    granting BPA such authority, section 5, 16 U.S.C. § 839c, and
    section 7, 16 U.S.C. § 839e, are at issue in this appeal.
    1.
    Section 5(c) of the NWPA makes low-cost power
    available to IOUs, one of the classes of non-preference
    customers. Under this provision, IOUs are entitled to
    “exchange power they have purchased or generated for lower-
    cost power generated by BPA.” PGE, 501 F.3d at 1015; see
    also 16 U.S.C. § 839c(c)(1); Golden Nw., 501 F.3d at 1047.
    This process, known as the Residential Exchange Program
    (“REP”), “essentially acts as a cash rebate to the IOUs,”
    allowing the IOUs to benefit from BPA’s low rates even
    when BPA cannot itself provide them with power. PGE,
    501 F.3d at 1015 (explaining that the “‘exchange’ is a paper
    10                           APAC V. BPA
    transaction”).6 The IOUs, in turn, are required to pass on this
    financial benefit to their customers. 16 U.S.C. § 839c(c)(3);
    see also Cal. Energy Res. Conservation & Dev. Comm’n v.
    Johnson, 
    807 F.2d 1456
    , 1460 (9th Cir. 1986) (explaining
    that without the REP, “consumers living in areas served by
    private utilities faced higher power prices than consumers
    living in areas served by public utilities”).
    The traditional formula for deciding if an IOU is entitled
    to a “REP Benefit” is as follows: first, the IOU offers to sell
    power to BPA at its “average system cost” (“ASC”) for
    producing power.7 Second, BPA calculates the “PF Exchange
    rate,” which is the sum of a base rate for power, see 16 U.S.C.
    § 839e(b)(1), plus any supplemental charges triggered by the
    “rate ceiling,” see id. at (b)(3), discussed infra. If the PF
    Exchange rate is lower than the ASC, the IOU is entitled to a
    REP Benefit, which will be the difference between those two
    6
    Section 5(c) technically makes REP benefits available to any qualified
    utility, including COUs. See 16 U.S.C. § 839c(c)(1). But it was intended
    primarily to benefit the IOUs, and the Settlement guarantees REP benefits
    only to IOUs. See Washington Utilities & Transp. Comm’n (WUTC) v.
    F.E.R.C., 
    26 F.3d 935
    , 936–37 (9th Cir. 1994) (“The exchange program
    is designed to eliminate the disparities between electric rates paid by
    residential customers of IOUs and the lower rates paid by customers of
    publicly-owned utilities”). For these reasons, and for the sake of clarity,
    we refer to “IOUs,” rather than “utilities,” as the relevant beneficiaries of
    section 5(c).
    7
    BPA determines an IOU’s ASC “on the basis of methodology
    developed for this purpose in consultation with the [Pacific Northwest
    Electric Power and Conservation Planning] Council, the Administrator’s
    customers, and appropriate State regulatory bodies in the region.”
    16 U.S.C. § 839c(c)(7). The ASC methodology is subject to review and
    approval by the Federal Energy Regulatory Commission (“FERC”).
    BPA’s current methodology was developed in 2008 and approved by
    FERC in 2009. ROD 3.
    APAC V. BPA                                11
    amounts, multiplied by the IOU’s residential load. See
    16 U.S.C. § 839c(c)(1) (stating that the Administrator “shall
    acquire by purchase such power and shall offer, in exchange,
    to sell an equivalent amount of electric power” (emphasis
    added)); ROD 2.
    2.
    While section 5 provides low-cost power to the IOUs,
    section 7 ensures that the preference customers—i.e., the
    COUs—will not bear the cost of this benefit. See PGE,
    501 F.3d at 1015 (“The legislative history of the NWPA
    suggests that Congress viewed the NWPA as a compromise
    between the preference and non-preference utilities”).
    Section 7 governs the rates that BPA charges its customers,
    Golden Nw., 501 F.3d at 1041, and it contains two relevant
    restrictions.
    First, BPA may not charge its preference customers
    higher rates than it would in the absence of the REP.
    16 U.S.C. § 839e(b)(2)(C).8 In order to ensure this does not
    happen, BPA is required to perform a “rate test,” through
    which it compares the “PF Public rate”—i.e. the projected
    rate for the COUs—to a hypothetical rate based on five
    assumptions, including the assumption that no exchanges
    were made through the REP. Id. at (A)–(E). If the “rate test”
    shows that the PF Public rate is higher than the hypothetical
    rate, BPA must adjust the PF Public rate downward by the
    8
    The rate that BPA charges its preference customers is the “Priority
    Firm Public rate,” or “PF Public rate.” See ROD xi, 180, 185, 330; see
    also 16 U.S.C. §§ 839c(b), 839e(b); Pac. Nw. Generating Co-op.,
    
    580 F.3d at 802
    . This rate is also referred to as the “PF Preference rate.”
    ROD 7; see also ROD 203.
    12                     APAC V. BPA
    amount of the difference. This is called the “rate ceiling”
    trigger.
    The triggering of the “rate ceiling” leads to the second
    restriction: if the PF Public rate is adjusted downward, the
    cost of making such an adjustment must be recovered from all
    of the other rates BPA charges for power, including the PF
    Exchange rate that BPA sets for the IOUs. 
    Id.
     at (b)(3). This
    brings us somewhat full circle: the practical effect of adding
    a supplemental charge to the PF Exchange rate charged to
    IOUs is simply a reduction in REP Benefits for the IOUs.
    See PGE, 501 F.3d at 1015.
    C.
    Put simply, the REP is complicated. It was the source of
    “almost continuous litigation” in the 1980s, during which
    period many IOUs chose to settle with BPA rather than
    actively participate in the program. ROD 5; see also Cal.
    Energy Res. Cons. & Dec. Comm’n v. Johnson, 
    807 F.2d 1456
    , 1458 (9th Cir. 1986). And it was at the heart of the
    2000 REP Settlement Agreement, which this court struck
    down in PGE and Golden Northwest.
    In the 2000 REP Settlement Agreement, BPA attempted
    to settle its REP obligations to the IOUs for fiscal years
    2002–2011. Golden Nw., 501 F.3d at 1047. It then adjusted
    the rates for the COUs upward, in order to recover the costs
    associated with the settlement. Id. at 1048. We held that
    BPA’s actions were contrary to the NWPA. In PGE, we
    held—contrary to BPA’s argument—that BPA must comply
    with sections 5 and 7 “whenever [it] engages in a purchase
    and exchange of power,” including in settlement agreements.
    501 F.3d at 1032 (emphasis added). We concluded that BPA
    APAC V. BPA                                 13
    had failed to do so, because the settlement did not rely on the
    IOUs’ current ASCs—that is, the rates at which the IOUs
    offer to sell power to BPA—when calculating their REP
    settlement benefits. Id. at 1033; see also id. at 1037
    (concluding that the settlement did not “resemble the REP
    program created in §§ 5(c) and 7(b) that it purports to be
    settling”).9 And in PGE’s companion case, Golden
    Northwest, we further held that it was a violation of
    section 7(b) for BPA to distribute the costs of the settlement
    to its preference customers. 501 F.3d at 1048. We remanded
    both cases to BPA to set rates in accordance with our
    opinions.
    On remand, BPA initiated proceedings to set new rates in
    compliance with PGE and Golden Northwest. This resulted
    in several final decisions: (1) the “WP-07 Supplemental
    Record of Decision,” which set a refund schedule for past
    over-charges from the unlawful 2000 settlement, (2) the
    “2008 Residential Purchase and Sale Agreement Record of
    Decision,” which applied specifically to IOUs, and (3) the
    “WP-10 Record of Decision,” which established future rates
    for 2010–2011. The details of these decisions do not matter
    here. What does matter is that each of these decisions
    resulted in an onslaught of appeals to this court, which have
    been stayed pending the outcome of this case. ROD 29.
    9
    We explained that BPA had erroneously relied on a “set of
    assumptions . . . [that] served to enlarge the group of IOUs eligible for the
    settlement and to increase the benefits of those already qualified for the
    REP,” including (1) the possibility of a legal challenge to the methodology
    for rate-making, despite the lack of any such existing challenge, (2) the
    possibility of a challenge to the PF Exchange rate, and (3) future
    fluctuations in the energy market. PGE, 501 F.3d at 1033.
    14                           APAC V. BPA
    D.
    Against this backdrop, we turn to the subject of this
    appeal: the REP-12 Record of Decision. In the face of
    “seemingly endless litigation” over the REP, a large number
    of BPA’s customers entered into settlement negotiations.10
    This resulted in the REP-12 Settlement Agreement, which
    was signed by parties representing 94 percent of the total load
    that BPA serves.11 The Settlement was then submitted to the
    BPA Administrator, who conducted a seven-month
    evaluation to determine if it was reasonable and if it complied
    with BPA’s statutory mandates, as well as with PGE and
    Golden Northwest. After concluding that the Settlement was
    lawful and reasonable, the BPA Administrator adopted it and
    committed BPA to abide by its terms. ROD 419. The REP-
    12 Record of Decision replaces the Administrator’s previous
    REP-related decisions. See ROD 20; 29.
    Although the Settlement includes “many complicated
    formulas and terms,” ROD 29, its three key elements can be
    described succinctly. First, the Settlement sets a lump sum of
    REP benefits to be paid to the IOUs as a class over the
    seventeen-year term of the settlement.12 These lump sums are
    10
    The BPA Administrator publicly urged customers to work toward a
    settlement that would “provide greater long-term certainty” and “greater
    political equity” than what BPA could provide on its own. ROD xvii.
    11
    The settling parties consist of all six regional IOUs, three public utility
    commissions, several customer representative groups, the Citizens’ Utility
    Board of Oregon, and 89.1 percent (by load) of the COUs.
    12
    The lump sum allocated to the IOUs reflects the resolution of all
    disputed claims arising from fiscal years 2002–2011, as well as the IOUs’
    entitlement to REP benefits for fiscal years 2012–2028. Id.
    APAC V. BPA                               15
    broken down by year—for example, in FY 2012, the IOUs
    will collectively be paid $182.1 million, and in FY 2028, they
    will collectively be paid $286.1 million. ROD 30. Although
    the yearly lump sums are fixed, the payments to any
    particular IOU are not. Rather, the individual IOUs will still
    be required to file their ASCs with BPA every two years.
    Pursuant to section 5(c), if an IOU’s ASC does not exceed the
    applicable exchange rate for a particular period, that IOU will
    not receive REP benefits for that period.13 The BPA
    Administrator, in his analysis of the Settlement, concluded
    that the net present value of the REP benefits under the
    Settlement—$2.05 billion—is approximately $1 billion less
    than the net present value of the projected REP benefits over
    the same period of time, should BPA continue to pay out REP
    benefits without the Settlement. ROD 59.
    Second, the Settlement sets a new “rate test” methodology
    to meet the requirements of section 7(b). Under its traditional
    approach, BPA conducts a “rate test” every two years to
    determine the rate ceiling (i.e. the maximum rate that can be
    charged to COUs) and the PF Exchange rate. See 16 U.S.C.
    § 839e(b)(2). But under the Settlement, BPA prospectively
    conducted the rate test for each year of the Settlement. Thus,
    it ran seventeen separate rate tests, under which it determined
    the prospective cost of REP benefits (and the rate ceiling) for
    fiscal years 2012–2028, should the Settlement not take effect.
    In addition, it ran these tests using twenty-six different
    scenarios, to account for a range of different rate levels and
    litigation outcomes in the absence of the Settlement. BPA
    13
    The Settlement sets forth a specific formula for determining whether
    an individual IOU qualifies for REP benefits, and if so, what amount of
    REP benefits it should receive. See ROD Appendix A 19–20. We discuss
    this formula infra, in Part III.A.1.b.
    16                         APAC V. BPA
    then compared the projected cost of REP benefits under these
    rate tests to the cost of REP benefits under the Settlement. It
    concluded that the COUs’ interests were adequately
    protected, because in twenty-three of the twenty-six
    scenarios, the Settlement results in lower rates for the
    preference customers than would be allowed by the section
    7(b)(2) rate ceiling absent the Settlement.14
    Third, the Settlement provides a schedule of refunds to
    the COUs, who were overcharged under the terms of the 2000
    REP Settlement Agreement. See Golden Nw., 501 F.3d at
    1048. The Settlement provides that the COUs can retain the
    refunds they have already received from BPA—which total
    $587 million, for the period fiscal years 2008–2011—without
    further dispute.15 It also provides that BPA will continue to
    refund the COUs during fiscal years 2012–2019, paying a
    total of $612 million over the course of eight years. ROD
    253. The mechanism for making these refunds is to withhold
    a certain amount of the IOUs’ REP benefits, which the IOUs
    have agreed can be used to “pay for” the refunds to which the
    COUs are entitled.
    E.
    APAC is an “unincorporated ad hoc organization.” It is
    composed of six member groups, all of whom own and
    14
    The three scenarios in which the COUs’ rates were higher under the
    Settlement were scenarios that presumed the COUs would prevail on all
    their major contested legal issues and the IOUs would prevail on none;
    BPA deemed this unlikely. ROD 80–81.
    15
    These refunds are referred to by the parties as “Lookback Amounts,”
    and are the subject of numerous pending petitions before this court. See
    ROD 13–15.
    APAC V. BPA                                 17
    operate industrial facilities in the Pacific Northwest.16 The
    member groups are not customers of BPA; rather, they
    purchase electricity from BPA’s preference customers, the
    COUs. On appeal, APAC submitted an affidavit from the
    director of energy procurement at Georgia-Pacific LLP
    (“GP”), stating that GP contracts to buy power from two
    different COUs, the Clatskanie Public Utility District
    (“CPUD”) and the Central Lincoln Public Utility District
    (“CLPUD”).17 The affidavit describes the contractual
    relationship between GP and CPUD as follows:
    The electrical contract between BP and CPUD
    is a cost-based pass-through contract
    according to which GP buys power from
    CPUD at CPUD’s cost to purchase the power
    16
    These groups are Georgia-Pacific LLC, Grays Harbor Paper LP, JR
    Simplot Co., Longview Fibre Paper and Packaging, Inc., Ponderay
    Newsprint Company, and Weyerhaeuser Company.
    17
    APAC filed this affidavit with our court in order to establish standing.
    “Because Article III’s standing requirement does not apply to agency
    proceedings, petitioners had no reason to include facts sufficient to
    establish standing as a part of the administrative record. We therefore
    consider the affidavit[] not in order to supplement the administrative
    record on the merits, but rather to determine whether petitioners can
    satisfy a prerequisite to this court’s jurisdiction.” Nw. Envtl. Def. Ctr. v.
    Bonneville Power Admin., 
    117 F.3d 1520
    , 1527–28 (9th Cir. 1997).
    APAC also submitted an affidavit from the general manager of a
    group called “Grays Harbor PUD.” This affidavit addresses the former
    contractual relationship between “Grays Harbor Paper Company” and a
    COU, but suggests that Grays Harbor Paper Company no longer exists.
    It also fails to state whether Grays Harbor Paper Company is or was a
    member of APAC. Because we can resolve the question of standing on
    the basis of the affidavit from Georgia-Pacific LLP, we do not rely on the
    affidavit from Grays Harbor PUD.
    18                         APAC V. BPA
    from BPA and other sources, plus additional
    charges for overhead. Thus the rates and
    charges incurred by CPUD to purchase power
    from BPA for the Wauna mill are recovered
    by GP.
    The affidavit describes GP’s contractual relationship with
    CLPUD in nearly identical terms.18 As a result of these “pass
    through” contracts, GP claims to be “directly impacted
    financially by any rate increases or decreases adopted by
    BPA.”
    II. JURISDICTION AND STANDARD OF REVIEW
    A. Standing
    We have jurisdiction to review the REP-12 Record of
    Decision, because it is a final agency action. See 16 U.S.C.
    § 839f(e)(5); PGE, 501 F.3d at 1023. At the outset, however,
    we must address an important threshold question: does
    APAC, a group whose members are not direct customers of
    BPA, have standing to challenge the Settlement? Our answer
    to this question requires two separate inquiries. First, we ask
    if at least one of APAC’s members has “suffered sufficient
    injury to satisfy the ‘case or controversy’ requirement of
    Article III.” Cetacean Cmty. v. Bush, 
    386 F.3d 1169
    , 1174
    (9th Cir. 2004). Second, if APAC has established Article III
    standing, we “ask whether a statute has conferred ‘standing’
    on [at least one of APAC’s members],” 
    id. at 1175
    , such that
    the member is “within [its] zone of interests,” thereby
    18
    In its description of GP’s contractual relationship with CLPUD, the
    affidavit replaces “CPUD” with “CLPUD,” deletes the phrase “and other
    sources,” and replaces “Wauna mill” with “Toledo plant.”
    APAC V. BPA                               19
    meeting the requirements for prudential standing, Cent. Ariz.
    Water Conservation Dist. v. U.S. E.P.A., 
    990 F.2d 1531
    , 1538
    (9th Cir. 1993).19 We conclude that APAC has met the
    requirements for both constitutional and prudential standing,
    for the reasons explained below.
    1. Constitutional Standing
    The requirements for Article III standing are familiar.
    First, the petitioner must show that it has suffered “an injury
    in fact,” i.e., “an invasion of a legally protected interest which
    is (a) concrete and particularized, and (b) actual or imminent,
    not conjectural or hypothetical.” Lujan v. Defenders of
    Wildlife, 
    504 U.S. 555
    , 560 (1992) (quotation marks and
    citations omitted). Second, it must show that the injury is
    “fairly traceable to the challenged action of the defendant,”
    and is not “the result of the independent action of some third
    party not before the court.” 
    Id.
     (quotation marks and
    alternations omitted). Finally, “it must be likely, as opposed
    to merely speculative, that the injury will be redressed by a
    favorable decision.” 
    Id. at 561
     (quotation marks omitted).
    19
    We consider the standing of APAC’s individual members because an
    organization has standing to sue on behalf of its members if “‘(a) its
    members would otherwise have standing to sue in their own right; (b) the
    interests it seeks to vindicate are germane to the organization’s purpose;
    and (c) neither the claim asserted nor the relief requested requires the
    participation of individual members in the lawsuit.’” Smith v. Pac.
    Properties & Dev. Corp., 
    358 F.3d 1097
    , 1101–02 (9th Cir. 2004)
    (quoting Hunt v. Wash. State Apple Advert. Comm’n, 
    432 U.S. 333
    , 343
    (1977)); see also Ocean Advocates v. U.S. Army Corps of Engineers,
    
    402 F.3d 846
    , 859–61 (9th Cir. 2005) (concluding that organization had
    standing because one of its members had standing). BPA and the
    intervenors do not contend—nor do we have any reason to believe—that
    the latter two requirements are not satisfied.
    20                           APAC V. BPA
    We address each requirement in turn, focusing on whether it
    has been satisfied by one of APAC’s members, GP.
    a. Injury in Fact
    The alleged injury in this case is economic: according to
    APAC, its members will “suffer the burden” of over-inflated
    power rates, which BPA will set in order to ensure it can
    make the required REP payments to the IOUs.20 Put another
    way, the Settlement will cause BPA to set higher rates for the
    COUs, who will in turn set higher rates for members of
    APAC. The intervening IOUs counter that “because APAC’s
    members’ rates are set by COUs, not BPA, they have no legal
    right to any particular rate under the NWPA,” and thus do not
    have a legally protected interest in non-inflated rates.21 We
    disagree.
    First, we must clarify that a petitioner’s “legally protected
    interest” need not be a statutorily created interest.22 Thus, to
    20
    APAC also argues that the Settlement fails to reimburse the COUs for
    illegal overcharges resulting from the 2000 REP Settlement Agreement,
    which we struck down in PGE and Golden Northwest.
    21
    BPA does not dispute that APAC’s members may suffer an injury in
    fact; it instead focuses on the second and third requirements for
    constitutional standing, arguing that “any burden imposed on APAC’s
    members comes from the COUs that sell power to them,” and any remedy
    must also come from the COUs. See infra, at Part III.A.1.b–c.
    22
    The intervening IOUs confuse two separate inquiries: (1) the Article
    III “legally protected interest” inquiry, which is a part of establishing
    “injury-in-fact,” and (2) the prudential standing inquiry, which looks to
    whether a relevant statute confers a right to sue upon a particular plaintiff.
    But it is only after determining that “a plaintiff has suffered sufficient
    injury to satisfy Article III” that the court “ask[s] whether a statute has
    APAC V. BPA                                  21
    the extent the parties and the dissent focus on whether
    APAC’s members have a “right to any particular rate under
    the [NWPA],” Dissent at 67, their focus is too narrow.23 We
    have previously held that “economic injury is generally a
    legally protected interest.” Cent. Ariz., 
    990 F.2d at 1537
    ; see
    also Montana Shooting Sports Ass’n v. Holder, 
    727 F.3d 975
    ,
    980 (9th Cir. 2013) (“The economic costs of complying with
    a licensing scheme can be sufficient for standing.”); San
    Diego Cnty. Gun Rights Comm. v. Reno, 
    98 F.3d 1121
    , 1130
    (9th Cir. 1996) (“Economic injury is clearly a sufficient basis
    for standing.”); Aluminum Co. of Am. v. Bonneville Power
    Admin., 
    903 F.2d 585
    , 590 (9th Cir. 1989) (“There is harm in
    paying rates that may be excessive . . . .”). And we have
    found standing where the petitioners’ economic interest in an
    agency’s action was created by contract, rather than by
    statute.24 Cent. Ariz., 990 F.3d at 1537–38.
    conferred ‘standing’ on that plaintiff” as part of the prudential standing
    inquiry. Cetacean Cmty., 
    386 F.3d at 1175
     (emphasis added); see also
    Salmon Spawning & Recovery Alliance v. Gutierrez, 
    545 F.3d 1220
    ,
    1224–25 (9th Cir. 2008).
    23
    The exact requirements for a “legally protected interest” are far from
    clear. See, e.g., In re Special Grand Jury 89-2, 
    450 F.3d 1159
    , 1172 (10th
    Cir. 2006) (explaining that the term has “generated some confusion,” but
    concluding that the interest need not be “protected by law . . . so long as
    it is the sort of interest that courts think to be of sufficient moment to
    justify judicial intervention); Judicial Watch, Inc. v. U.S. Senate, 
    432 F.3d 359
    , 363 (D.C. Cir. 2005) (Williams, Senior J., concurring) (expressing
    “puzzlement” over the requirement and discussing the “powerful reasons”
    it should be interpreted to “simply reformulate[] pre-existing
    requirements, particularly that the interest affected be a cognizable one”).
    24
    The dissent misconstrues our explanation here that a legally protected
    interest need not be a statutorily created interest as a suggestion that it is
    “inappropriate to examine the statute in the context of a legally cognizable
    interest.” See Dissent at 66, n.9. We make no such suggestion. Our
    22                          APAC V. BPA
    For example, in Central Arizona—a case with strikingly
    similar facts—the EPA had promulgated a rule requiring the
    owners of a power generating system to take steps to reduce
    its SO2 emissions. 
    Id.
     at 1533–34. The petitioners, who
    purchased electricity from those owners, claimed “an
    economic interest in the Final Rule,” arguing that they
    “[would] be required, due to [their] contractual relationship
    with the [owners], to repay a major portion of . . . the costs of
    installing and maintaining the emission controls required by
    the Final Rule.” Id. at 1534. We held that the petitioners had
    standing to sue EPA, concluding, in part, that their pecuniary
    injury was “clearly a sufficient basis” upon which to establish
    an “injury in fact,” as required by Lujan.25 Id. at 1537
    (quotation marks omitted).
    Likewise, in Maricopa-Stanfield Irrigation and Drainage
    District v. United States, we held that the plaintiffs had
    point is only that a legally protected interest can derive from a source
    other than a statute.
    25
    The dissent asserts that Central Arizona is distinguishable because in
    that case EPA was acting in its regulatory capacity while in this case BPA
    acted “within its power to contract [with the COUs] by adopting the REP-
    12 Settlement Agreement.” Dissent at 71. This distinction makes no
    difference. Central Arizona is analogous because, just as the pecuniary
    impact of EPA’s regulations passed through to the purchasers of power
    from the generating system, the pecuniary impact of BPA’s actions passed
    through to GP. The pass-through contracts that GP has with the two
    COUs discussed in GP’s affidavit forms the basis for APAC’s Article III
    standing. BPA’s own authority to enter into a contractual relationship
    with the COUs does not somehow render GP a mere downstream
    customer without standing, as the dissent argues. Nor does it mean that
    GP seeks to establish standing by asserting the rights of a third party. See
    Dissent at 72–73. There is a direct correlation between the REP-12
    Settlement and the costs that GP will shoulder. The alleged injury is GP’s
    own, not that of the COUs or any other third party.
    APAC V. BPA                           23
    established “injury in fact” when the alleged unlawful act
    deprived them of rights they held under contract, not by
    statute. 
    158 F.3d 428
    , 435 (9th Cir. 1998). There, the
    plaintiffs were irrigation districts who claimed that the San
    Carlos Apache Tribe Water Rights Settlement Act of 1992
    (the “SCAT Act”) had resulted in the government taking their
    rights to certain water without just compensation. 
    Id. at 433
    .
    We concluded that the plaintiffs had standing to bring the
    lawsuit, explaining in part:
    The Districts allege that, by reallocating the
    excess Ak-Chin water to the [Central Arizona
    Project], the Ak-Chin Settlement Act
    automatically reallocated that water to the
    non-Indian agricultural pool, which water the
    Districts had purchased under their 1984
    subcontracts. If the Districts are correct in
    their assertion that the excess Ak-Chin water
    [should have] defaulted to them, then the
    SCAT Act’s reallocation of the excess Ak-Chin
    water . . . indirectly deprived the Districts of
    water due to them in their subcontracts.
    Because a higher-priority right to a CAP
    water allocation is more valuable than a
    lower-priority right to the same water, the
    Districts adequately have alleged that the
    SCAT Act deprived them of their legal rights
    to the excess Ak-Chin water allocation.
    
    Id. at 434
     (emphasis added). Here, as in Central Arizona and
    Maricopa-Stanfield, GP has an interest in receiving whatever
    it is guaranteed under its contracts with the COUs. By
    alleging that the Settlement will directly affect the rates it is
    24                         APAC V. BPA
    charged, resulting in economic harm, GP has sufficiently
    established an invasion of a legally protected interest.26
    But our inquiry does not end there. GP still must show
    that its harm is “concrete and particularized” and “actual or
    imminent, not conjectural or hypothetical.” Lujan, 
    504 U.S. at 560
     (quotation marks omitted). The COUs argue that GP
    cannot meet these requirements, because APAC’s members
    are not entitled to “any particular rate under the NWPA.” We
    disagree.
    The record shows that the “pass-through” contracts are
    just what their name suggests: under these contracts, GP’s
    affidavit explains, GP “buys power from [the COUs] at [the
    COUs’] cost to purchase the power from BPA,” such that
    “the rates and charges incurred by [the COUs] to purchase
    power from BPA . . . are recovered from” GP. Thus, BPA’s
    argument that “any burden imposed on APAC’s members
    comes from the COUs that sell power to them,” and not from
    BPA, relies on technicalities at the expense of common sense.
    Under the terms of the Settlement, GP will almost certainly
    be charged a rate that directly reflects the rates BPA charges
    the COUs. See Clapper v. Amnesty Int’l USA, 
    133 S. Ct. 1138
    , 1150 n.5 (2013) (“Our cases do not uniformly require
    26
    The dissent devotes an extensive part of its discussion to confronting
    arguments on which we do not rely to hold that APAC has standing. For
    instance, we do not hold that APAC has standing because its members are
    “significant purchasers” of BPA power. See Dissent at 69. Nor do we
    hold that all downstream consumers of energy, including residential
    customers, have standing to challenge the Settlement or any other action
    by BPA. See Dissent at 67–68. Our holding is limited to the unique facts
    of this case. Further, because APAC filed an affidavit on behalf of GP,
    which is uncontested, we do not need to address the “burden of
    production” issue raised by the dissent. See Dissent at 62, n. 7.
    APAC V. BPA                          25
    plaintiffs to demonstrate that it is literally certain that the
    harms they identify will come about.”). Although “the extent
    of [GP’s] economic harm is not readily determinable,” Cent.
    Ariz., 
    990 F.2d at 1538
     (emphasis added), the record reveals
    that if APAC prevails on the merits of its claims, “the
    [Settlement] will likely cause [GP] some amount of pecuniary
    harm,” 
    id.,
     due to the pass-through provisions in its contracts.
    See Maricopa-Stanfield, 
    158 F.3d at 434
     (“If the SCAT Act
    reallocated water that became the Districts’ property under
    the Ak-Chin Settlement Act, then the harm is certain even
    though its precise valuation may not be.”); see also Bennett
    v. Spear, 
    520 U.S. 154
    , 168 (1997) (“Given petitioners’
    allegation that the amount of available water will be reduced
    and that they will be adversely affected thereby, it is easy to
    presume specific facts under which petitioners will be injured
    . . . .”). We therefore conclude that the evidentiary showing
    by APAC is sufficient to establish an actual, concrete harm
    that is neither conjectural nor hypothetical. See Lujan,
    
    504 U.S. at 560
    .
    b. Fairly Traceable to Actions of BPA
    We next turn to the second requirement for constitutional
    standing: that the alleged injury be “fairly traceable to the
    challenged action of the defendant,” rather than to “the
    independent actions of some third party not before the court.”
    
    Id.
     (alterations and quotation marks omitted). To satisfy this
    requirement, APAC need not show that BPA’s actions are
    “the very last step in the chain of causation.” Bennett,
    
    520 U.S. at 169
    . Rather, APAC must show only that there are
    no independent actions of third parties that break the causal
    link between BPA’s allegedly unlawful act—i.e., its adoption
    of the Settlement—and GP’s economic harm. If there are no
    such independent actions, BPA’s challenged actions may be
    26                      APAC V. BPA
    understood to have had a “determinative . . . effect upon the
    action” of the third party, which in turn will cause harm to
    GP. Id.; see also Maya v. Centex Corp., 
    658 F.3d 1060
    , 1070
    (9th Cir. 2011) (“A causal chain does not fail simply because
    it has several ‘links,’ provided those links are ‘not
    hypothetical or tenuous’ and remain ‘plausible.’” (quoting
    Nat’l Audubon Soc., Inc. v. Davis, 
    307 F.3d 835
    , 849 (9th Cir.
    2002)) (internal alteration omitted)).
    Here, again, we find guidance in Central Arizona. As we
    explained there, the fact that the petitioners’ “contractual
    obligations may provide the basis for its economic liability
    for the increased costs imposed by the Final Rule . . . hardly
    means that the Final Rule itself is not the direct cause of that
    liability.” 
    990 F.2d at 1538
    . This statement rings even more
    true here, where the pass-through contracts directly pass on
    to GP whatever rates BPA charges the COUs. Indeed, it is
    difficult to imagine a causal chain in which the defendant’s
    actions are more “determinative” of the actions of a third
    party—and, in turn, of the alleged harm done to GP. See
    Bennett, 
    520 U.S. at 169
    . To consider the COUs’ rate-setting
    an “independent action,” separate from BPA’s rate-setting,
    simply “misses the point.” Cent. Ariz., 
    990 F.2d at 1538
    .
    Nor does it matter, as the dissent suggests, that the COUs
    may be able to depart from their contractual arrangements
    with APAC members. See Dissent at 74–75. This does not
    change the fact that the contractual rates GP will pay are
    directly correlated to the Settlement Agreement. We
    therefore conclude that APAC has shown that GP’s alleged
    economic injury is “fairly traceable” to the challenged action
    of BPA—i.e., the adoption of the Settlement —such that its
    has satisfied the second requirement for Article III standing.
    APAC V. BPA                               27
    c. Redressability
    Finally, we consider the third requirement for Article III
    standing: “it must be likely, as opposed to merely
    speculative, that the injury will be redressed by a favorable
    decision.” Lujan, 
    504 U.S. at 561
     (quotation marks omitted).
    We conclude that GP has satisfied this requirement for the
    same reasons it has satisfied the “fairly traceable” causation
    requirement. If the Settlement turned out to be unlawful, we
    would invalidate the REP-12 Record of Decision; as a result,
    it could no longer be the source of any economic harm to GP.
    GP has therefore satisfied the third requirement for Article III
    standing, and as a result, we conclude that APAC has
    constitutional standing to challenge the Settlement.
    2. Prudential Standing
    We turn to the second standing inquiry: the “judicially
    self-imposed” requirement of prudential standing.27 “For a
    27
    APAC argues that BPA has waived any challenge to APAC’s
    prudential standing by failing to raise it during the REP-12 proceedings
    before the agency. Unlike Article III standing, the issue of a party’s
    prudential standing can be waived if not raised in a timely manner. See
    Pershing Park Villas Homeowners Ass’n v. United Pac. Ins. Co., 
    219 F.3d 895
    , 899 (9th Cir. 2000). But here, BPA had no reason to challenge
    APAC’s prudential standing before filing its answering brief, since REP
    proceedings are not subject to standing requirements. See Overton Power
    Dist. No. 5 v. O’Leary, 
    73 F.3d 253
    , 257 (9th Cir. 1996) (“[I]t does not
    necessarily follow that a party able to participate in administrative
    proceedings therefore has standing to challenge agency decisions.”); see
    also 
    16 U.S.C. § 839
    (3)(B) (stating that one of the purposes of the NWPA
    is “to provide for the participation and consultation of the Pacific
    Northwest States, local governments, consumers, customers, users of the
    28                          APAC V. BPA
    plaintiff to have prudential standing under the APA, the
    interest sought to be protected by the complainant must be
    arguably within the zone of interests to be protected or
    regulated by the statute in question.” Nat’l Credit Union
    Admin. v. First Nat. Bank & Trust Co., 
    522 U.S. 479
    , 488
    (1998) (internal quotation marks and alteration omitted); see
    also Cetacean Cmty., 
    386 F.3d at 1176
     (“When a plaintiff
    seeks to challenge federal administrative action, section 10(a)
    [of the Administrative Procedure Act (‘APA’)] provides a
    mechanism to enforce the underlying substantive statute.”).28
    To satisfy this requirement, “all that is required is a rough
    correspondence of the plaintiff’s interests with the statutory
    purpose.” Bernhardt v. Cnty. of Los Angeles, 
    279 F.3d 862
    ,
    870 (9th Cir. 2002). The test “‘is not meant to be especially
    demanding’ . . . keeping with Congress’s ‘evident intent’
    when enacting the APA ‘to make agency action
    presumptively reviewable.’” Match-E-Be-Nash-She-Wish
    Band of Pottawatomi Indians v. Patchak, 
    132 S. Ct. 2199
    ,
    2210 (2012) (quoting Clarke v. Securities Industry Assn.,
    
    479 U.S. 388
    , 399 (1987)); see also 
    id.
     (noting that “the
    benefit of any doubt goes to the plaintiff”).
    Columbia River System . . . and the public at large within the region” in
    “facilitating the orderly planning of the region’s power system”). Thus,
    BPA has not waived this challenge.
    28
    The “zone of interest” requirement derives from section 10 of the
    APA, which provides that “[a] person suffering legal wrong because of
    agency action, or adversely affected or aggrieved by agency action within
    the meaning of a relevant statute, is entitled to judicial review thereof.”
    
    5 U.S.C. § 702
    . The Supreme Court has “interpreted § 10(a) of the APA
    to impose a prudential standing requirement in addition to the
    requirement, imposed by Article III of the Constitution, that a plaintiff
    have suffered a sufficient injury in fact.” Nat’l Credit Union Admin.,
    
    522 U.S. at 488
    .
    APAC V. BPA                               29
    Here, the interests of APAC’s members clearly line up
    with the statutory purposes of the NWPA.29 APAC’s
    members have an interest in purchasing low-cost power,
    which allows them to operate their businesses. The statute,
    in turn, states that one of its purposes is “to provide that the
    customers of the [BPA] and their consumers continue to pay
    all costs necessary to produce, transmit, and conserve
    resources to meet the region’s electric power requirements.”
    
    16 U.S.C. § 839
    (4) (emphasis added); see also 16 U.S.C.
    § 838g (explaining that “rate schedules . . . shall be fixed and
    established . . . with a view to encouraging the widest
    possible diversified use of electric power at the lowest
    possible rates to consumers consistent with sound business
    principles” (emphasis added)); § 839a(5) (defining
    “consumer” as “any end user of electric power”). The
    legislative history of the NWPA also shows that Congress
    intended for the customers of COUs to benefit from its
    protections. See H.R. Rep. No. 96-976, pt. 2, at 36 (1980),
    reprinted in 1980 U.S.C.C.A.N. 6023, 6034 (“As an added
    protection against preference utilities and their customers
    suffering adverse economic consequences as a result of this
    legislation, section 7(b)(2) establishes a ‘rate ceiling.’”
    29
    In addition to arguing that the Settlement is unlawful because it
    violates the NWPA, APAC also argues that the Settlement is unlawful
    because it violates the Bonneville Power Act and related FERC
    regulations. However, this argument is wrapped into APAC’s argument
    that the Settlement violates the NWPA, insofar as the NWPA incorporates
    the relevant provisions of Bonneville Project Act. 16 U.S.C. § 839c(a)
    (stating that all power sales conducted pursuant to section 5 of the NWPA
    are “subject at all times to the preference and priority provisions of the
    Bonneville Project Act of 1937 (
    16 U.S.C. § 832
     and following) and, in
    particular, sections 4 and 5 thereof [16 U.S.C. §§ 832c, 832d]”). We
    therefore need not separately consider whether APAC’s interests line up
    with the statutory purposes of the Bonneville Power Act.
    30                      APAC V. BPA
    (emphasis added)). On this basis, we conclude that the
    interests of APAC’s members are more than “marginally
    related” to the purposes of the NWPA, and therefore they
    have satisfied the requirements for prudential standing. See
    Match-E-Be-Nash-She-Wish, 
    132 S. Ct. at 2210
    .
    In sum, we conclude that APAC has constitutional and
    prudential standing to challenge the Settlement. We therefore
    turn to the merits of the petition for review.
    B. Standard of Review
    “Our review of BPA’s actions is governed by the [APA].”
    PGE, 501 F.3d at 1023; see also 16 U.S.C. § 839f(e)(2).
    Thus, we will set aside the Record of Decision only if it is
    “arbitrary, capricious, an abuse of discretion, or otherwise not
    in accordance with law.” 
    5 U.S.C. § 706
    (2)(a). “In
    determining whether BPA has acted in accordance with law,
    we defer to BPA’s reasonable interpretations of its governing
    statutes.” Golden Nw., 501 F.3d at 1045; see also
    Confederated Tribes of Umatilla Indian Reservation v.
    Bonneville Power Admin., 
    342 F.3d 924
    , 928 (9th Cir. 2003)
    (“Due to the complex subject matter and BPA’s factual and
    legal expertise, we give special, substantial deference to
    BPA’s interpretation of the [NWPA].”).
    III. ANALYSIS
    A. NWPA Section 5(c)
    One of APAC’s main arguments is that the Settlement
    does not comply with section 5(c) of the NWPA, which
    governs the process by which BPA implements the REP. See
    16 U.S.C. § 839c(c). First, APAC argues that setting a lump
    APAC V. BPA                          31
    sum of REP benefits, rather than calculating REP benefits “on
    an individual IOU-by-IOU basis,” violates section 5(c)(1).
    Second, APAC argues that BPA’s waiver of the “in lieu”
    provision of section 5(c), 16 U.S.C. § 839c(c)(5), is unlawful.
    We conclude that the Settlement does not violate section 5(c)
    on either ground.
    1. Section 5(c)(1)
    We begin by clarifying the process for setting REP
    benefits. This is a three-step process: first, BPA estimates
    the aggregate amount of REP benefits to be paid to the IOUs
    for a given year, pursuant to section 7(b)(2); second, BPA
    uses that estimate to set the PF Exchange rate for a given
    year; third, BPA uses the PF Exchange rate to determine an
    individual IOU’s REP Benefit, pursuant to section 5(c)(1).
    Thus, contrary to APAC’s characterization of the process,
    BPA must always calculate the aggregate amount of REP
    benefits to be paid out in a given year prior to setting the PF
    Exchange rate for that year. See 16 U.S.C. § 839e(b)(2)(C).
    This is not a novel concept invented by the Settlement. As
    the BPA Administrator explained, “[i]f BPA does not know
    the total permissible cost of the REP after running the 7(b)(2)
    rate test, then BPA has no way of setting the PF Exchange
    rate.” ROD 93.
    What is a novel concept is that the Settlement obligates
    BPA to actually pay out the total amount of REP benefits it
    estimates under section 7(b). Put another way, estimating the
    aggregate amount of REP benefits to be paid is fundamentally
    different from actually setting that amount. We acknowledge
    that this is an important difference. But we fail to see how
    setting an aggregate amount of REP benefits is a violation of
    section 5(c), so long as the amount that is set is less than the
    32                      APAC V. BPA
    maximum possible REP benefits that could be distributed
    pursuant to section 7. As the BPA Administrator explained,
    “it is section 7(b) that ultimately establishes the amount of the
    REP costs that BPA may recover in rates, while section 5(c)
    . . . establishes how the REP benefits are distributed among
    the REP participants.” ROD 93 (emphasis added). We find
    this explanation helpful, as it clearly isolates what we must
    decide here: so long as the amount of REP benefits under the
    Settlement is lawful—a question we address infra in Part
    III.B—all that we must decide is whether the process for
    setting and distributing those benefits among the individual
    IOUs complies with section 5(c).
    a. Setting REP Benefits for Individual IOUs
    We therefore turn to section 5(c). Under this provision,
    there are two requirements that BPA must follow when
    setting REP benefits for any given IOU. First, “the
    Administrator shall acquire by purchase” the power that a
    utility “offers to sell . . . at [its] average system cost [ASC].”
    16 U.S.C. § 839c(c)(1). Second, “the Administrator shall . . .
    sell an equivalent amount of power to such utility” in return.
    Id. As APAC reads section 5(c), these two directives
    necessarily require BPA to calculate an individual IOU’s REP
    Benefit using the following formula, which we will call the
    “traditional section 5 formula”:
    [(ASC - PF Exchange Rate) x (load)] = REP Benefit
    Thus, according to APAC, section 5(c) requires BPA to first
    calculate the PF Exchange rate, and then—on the basis of that
    rate, together with an IOU’s ASC and load—calculate the
    APAC V. BPA                               33
    IOU’s REP Benefit.30 But by setting a lump sum of REP
    benefits, APAC argues, the Settlement allows BPA to “back[]
    into the rate[] to produce [the] guaranteed REP benefits.”
    APAC claims that this is a violation of section 5(c).
    We disagree. Although the traditional section 5 formula
    satisfies the requirements of section 5(c), it is not the only
    formula that would do so. Of critical importance here,
    section 5(c) does not specify the rate at which BPA must sell
    power back to qualifying utilities; as the Administrator noted,
    “[s]ection 5(c) is notably silent on what rate BPA must use to
    sell its power to the utility.” ROD 93. Thus, although BPA
    has traditionally calculated the REP Benefit using the PF
    Exchange rate, all that section 5 actually requires is for BPA
    to make the following calculation, where both italicized terms
    are variables:
    [(ASC - Rate Charged by BPA) x (load)] = REP Benefit
    If BPA uses this basic formula with the goal of calculating
    the maximum REP benefit for any given IOU, it will
    effectively use the traditional section 5 formula—that is, it
    will figure out the PF Exchange rate, and it will base the REP
    Benefit on that rate. How do we know this? We know
    because the PF Exchange rate is the sum of BPA’s base rate
    for power, 16 U.S.C. § 839e(b)(1), plus any supplemental
    charges triggered by the “rate ceiling,” id. at (b)(3). Thus, the
    PF Exchange rate is the lowest rate that BPA can charge the
    IOUs. And, as the lowest rate possible, it necessarily creates
    30
    Put in more mathematical terms, APAC argues that the value of the
    “REP Benefit” must be the dependent variable in the formula derived from
    section 5(c).
    34                        APAC V. BPA
    the largest possible difference with the ASC—which, in turn,
    results in the maximum possible REP Benefit.
    But an IOU does not have to accept the maximum
    possible REP Benefit. See, e.g., United States v. Mezzanatto,
    
    513 U.S. 196
    , 201 (1995) (“[A]bsent some affirmative
    indication of Congress’ intent to preclude waiver, we have
    presumed that statutory provisions are subject to waiver by
    voluntary agreement of the parties.”). We agree with the
    Administrator that the IOUs are not prohibited from “taking
    fewer REP benefits than any otherwise would be entitled to
    under the law.” ROD 91. And if an IOU accepts less than
    the maximum REP Benefit, the effect is simply that BPA will
    charge a higher rate to that IOU, in order to create a smaller
    difference between the ASC and the rate charged. Nothing in
    section 5 suggests that this is unlawful. See ROD 119
    (concluding that “allowing the IOUs to waive their statutory
    rights to full REP benefits . . . results in lower rates for all
    COU ratepayers”). We therefore conclude that setting a pre-
    determined REP Benefit, as required by the Settlement, is not
    a violation of section 5 so long as the pre-determined benefit
    is lower than the maximum REP Benefit that would result
    from using the PF Exchange rate.31 See 16 U.S.C.
    § 839e(b)(2) (stating that the rates charged to the COUs “may
    not exceed” a certain rate, but not setting a minimum rate);
    see also ROD 94 (“Section 7(b)(2) creates only a cap—not a
    floor—on the aggregate amount of REP benefits that BPA
    31
    This, of course, raises the “critical question” of “whether the
    aggregate REP benefits provided under the Settlement exceed what the
    [NWPA] permits.” ROD 116. We address that question infra in Part
    III.B.
    APAC V. BPA                                 35
    must pay to the exchanging utilities and include in rates.”).32
    Here, the BPA Administrator concluded that the pre-
    determined REP benefits under the Settlement amount to
    approximately $1 billion less than what the IOUs would be
    entitled to without the Settlement, and therefore setting such
    a lump sum is not a violation of section 5(c)(1).
    b. Distributing REP Benefits Among the IOUs
    Our inquiry could end there if we knew that every IOU
    would qualify for REP benefits for each of the seventeen
    years covered by the Settlement. If so, it would logically
    follow that no IOU could receive REP benefits beyond what
    they would be entitled to in the absence of the Settlement.33
    But here, it is not a foregone conclusion that every settling
    IOU will qualify for REP benefits in a given year. Rather,
    under the Settlement, each IOU is required to file its ASC
    32
    We also reject APAC’s argument that reference to “a Pacific
    Northwest electric utility,” 16 U.S.C. § 839c(c)(1) (emphasis added), is
    evidence of “Congress’ intent to provide benefits only on an IOU-specific
    basis.” First, section 5(c)(1) is silent with respect to “calculating the
    exchange benefits for the IOUs as a class.” ROD 92. We therefore defer
    to the Administrator’s reasonable interpretation of section 5(c)(1), which
    allows BPA to settle its REP obligations. Id.; see also ROD 98
    (explaining that under APAC’s interpretation of section 5(c), “BPA has no
    choice but to implement the traditional REP,” and in that case “there could
    be no settlement of the REP”); PGE, 501 F.3d at 1037 (“BPA has broad
    authority to settle claims under the NWPA.”). Second, even under the
    Administrator’s interpretation of section 5(c), BPA still must provide
    benefits on an IOU-specific basis, for the reasons discussed in this section.
    33
    Put another way, if we start from two premises—first, that the total
    amount of aggregate REP benefits is lawful, and second, that the REP
    benefits are distributed proportionately among all IOUs—we must
    necessarily conclude that the total amount of REP benefits distributed to
    any particular IOU is lawful.
    36                          APAC V. BPA
    with BPA every two years, consistent with BPA’s current
    methodology. ROD 111. BPA will then determine if the
    IOU qualifies for REP benefits by comparing the IOU’s ASC
    to the “utility-specific exchange rate” established for that
    IOU. ROD 112. If the ASC is higher than the “utility
    specific exchange rate,” BPA will calculate the IOU’s REP
    benefits using the following formula, set forth in section 6 of
    the Settlement:
    ([(ASC - Base Rate) x (load)] X [(Total REP Settlement Benefits) /
    (3((ASC - Base Rate) x Load))]) + 6.2 Adjustment = REP Benefit
    ROD Appendix A 19–20; see also ROD 376–77. Although
    complicated, this formula essentially serves one main
    purpose: it ensures that each qualifying IOU will receive an
    amount of REP benefits proportional to the difference
    between its ASC and the base rate for power.34
    34
    The formula is best understood when broken into sub-parts. First,
    BPA will calculate the difference between an individual IOU’s ASC and
    the base rate for power in that fiscal year, and multiply that amount by the
    IOU’s power load:
    (ASC - Base Rate) x (Load) = A
    The value of “A” will be different for each IOU, since it is dependent on
    that IOU’s particular ASC and load.
    Second, BPA will divide the total amount of REP settlement benefits
    in a given year—that is, the lump sum provided for all IOUs in that
    year—by the total sum of all of the “A” values, as calculated for each IOU
    using the formula above:
    APAC V. BPA                                 37
    APAC argues that it is unlawful for BPA to use a
    “formula not specified in the statute,” for two reasons: first
    “BPA cannot assure that it will pay REP benefits only to
    those qualified IOU’s that qualify for such a benefit,” and
    second, it cannot assure that it will pay REP benefits “only in
    (Total REP Settlement Benefits) = B
    3((ASC - Base Rate) x Load))
    This creates a scaled value that will be the same for all IOUs, since it does
    not rely on any IOU-specific values.
    Third, BPA will multiply A times B:
    ([(ASC - Base Rate) x (Load)] X [(Total REP Settlement
    Benefits)/( 3((ASC - Base Rate) x Load))]) = C
    This third step serves to divide the aggregate REP benefits among the
    IOUs in a way that is proportional to their ASCs: a higher ASC results in
    a greater difference between the ASC and the base rate, which results in
    a greater value for “A,” which in turns results in a greater value for “C.”
    Finally, BPA will add the amount of any “6.2 adjustment,” resulting
    in the final REP Benefit for that IOU:
    C + [Section 6.2 adjustment] = REP Benefit
    This final step involves a “reallocation” of REP benefits among the IOUs,
    which reflects the fact that the IOUs have not received equal refund
    payments from BPA thus far. ROD 120. Thus, “some [IOUs] have
    agreed to take a larger amount of rate protection in the calculation of their
    PF Exchange rate, while others have agreed to take less.” ROD 121. This
    internal reallocation of benefits among the IOUs does not affect any other
    class of BPA ratepayers. See id. (concluding that “[n]othing in section
    5(c), section 7(b)(2), or section 7(b)(3) prohibits the IOUs from waiving
    their rights to have rate protection dollars allocated on a pro rata basis
    among the PF Exchange rates”).
    38                            APAC V. BPA
    the amount to which each qualified IOU is entitled under § 5(c).”
    With respect to APAC’s first argument, we agree that
    some IOUs could qualify for REP benefits under the
    Settlement even though they would not qualify for benefits
    absent the Settlement. The formula used in the Settlement
    requires BPA to calculate only “(ASC - Base Rate) x (Load),”
    as opposed to “(ASC - PF Exchange Rate) x (Load),” when
    deciding if an IOU qualifies for benefits. Because the base
    rate for power is necessarily lower than the PF Exchange rate,
    the former formula will allow more IOUs to qualify for REP
    benefits than the latter formula.35
    But this is not unlawful. Although BPA has traditionally
    calculated REP benefits using the PF Exchange rate, section
    5(c) does not prohibit BPA from selling power to the IOUs at
    rates lower than the PF Exchange rate. See ROD 94
    (“Section 7(b)(2) does not require BPA to either pay the IOUs
    or charge the COUs in rates the exact amount of REP benefits
    established by a comparison of the utilities’ ASCs and BPA’s
    PF Exchange rate.”). Rather, under its traditional approach,
    BPA has done so in order to ensure that the COUs’ interests
    are protected under section 7. But once BPA has fulfilled its
    obligations under section 7, as it has under the Settlement,36
    section 5 does not impose any additional restrictions on the
    rate at which BPA must sell power to the IOUs. See ROD
    35
    Consider, for example, a scenario where an IOU’s ASC is 40.00, the
    base rate for power is 30.00, and the PF Exchange rate is 50.00. Under the
    formula used in the Settlement, the IOU would qualify for some portion
    of the REP benefits. Under the formula traditionally used, however the
    IOU would not qualify for any REP benefits, because 40 - 50 = -10.
    36
    See discussion infra Part III.B.
    APAC V. BPA                               39
    115 (“Aggregate REP costs are determined pursuant to
    sections 7(b)(1) and 7(b)(2) of the Northwest Power Act.
    Once the size of the aggregate REP is determined, BPA will
    use ASCs, PF Exchange rates, and qualifying exchange load
    to determine each utility’s REP benefits, whether under the
    Settlement or under no settlement.”). Thus, even though
    more IOUs may qualify for REP Benefits under the
    Settlement than otherwise would qualify, the formula that
    BPA uses to determine eligibility still complies with section
    5.
    The same reasoning leads us to reject APAC’s second
    argument, that some IOUs may receive a greater share of
    REP benefits than they are “entitled” to under section 5(c).
    Yet again, we agree with the factual premise of APAC’s
    argument: if the total amount of REP benefits is a pie, and
    not every IOU gets a slice of the pie, the other IOUs will
    simply get corresponding bigger slices of pie.37 Or, as APAC
    frames it, “each qualifying IOU will receive its proportional
    share of the fixed total annual amount of REP benefits
    provided in the Settlement regardless of the actual difference
    between its ASC and Exchange Rate.” And we understand
    the intuitive concern that a particular IOU should not receive
    greater benefits under the Settlement than it would otherwise.
    But here, again, we conclude that so long as the total
    amount of REP benefits distributed does not violate section
    7, there is no statutory restriction on what share of those
    benefits any particular IOU may receive.           As the
    Administrator explained, if “the IOUs wish to share among
    themselves a smaller amount of REP benefits through a fixed
    37
    This would occur if one or more of the IOUs did not qualify for REP
    benefits under the formula set forth in the Settlement.
    40                          APAC V. BPA
    payment stream that settles future uncertainties . . . there is
    nothing in section 5(c) . . . that prohibits BPA from honoring
    such a decision.” ROD 94. Thus, so long as “the aggregate
    level of REP benefits provided under the Settlement”
    comports with section 7, and “the distribution of those
    payments is being administered in a manner that closely
    resembles the REP envisioned by Congress in section 5(c),”
    the Settlement is “consistent with BPA’s statutory authority
    and is consistent with law.” ROD 115; see also PGE,
    501 F.3d at 1037 (striking down the 2000 Settlement because
    it did not “resemble” the REP program created in section 5).
    And given the meticulous calculations that BPA will use to
    distribute the REP benefits proportionately among the IOUs,
    we too are “frankly at a loss as to how the Settlement . . .
    could be closer to the[] statutory requirements” of section
    5(c).38 ROD 115. We therefore agree with the Administrator
    that the Settlement’s lump sum of REP benefits does not
    violate section 5(c)(1). See Chevron, U.S.A., Inc. v. Natural
    Res. Def. Council, Inc., 
    467 U.S. 837
    , 843 (1984).
    2. Section 5(c)(5) (“in lieu” powers)
    We also reject APAC’s argument that BPA violated
    section 5(c) by waiving its ability to make in lieu purchases
    pursuant to section 5(c)(5). See 16 U.S.C. § 839c(c)(5).39
    38
    We further note that BPA staff “worked with the parties to test the
    formulas in the Settlement to ensure they would function over time,”
    which included identifying a potential “anomalous scenario” that could
    occur if “BPA’s cost of power was higher than all of the IOUs’ cost of
    power.” ROD 116–17.
    39
    The in-lieu provision of section 5 provides: “Subject to the provisions
    of sections 839b and 839d of this title, in lieu of purchasing any amount
    of electric power offered by a utility under paragraph (1) of this
    APAC V. BPA                                  41
    The in lieu provision of section 5 permits BPA, “in its
    discretion, [to] sell the IOUs actual power purchased from
    other sources in lieu of participating in the REP so long as
    BPA’s cost for purchasing such power is less than the IOUs’
    cost to produce or secure their own power.” PGE, 501 F.3d
    at 1022. Thus, in theory, BPA can reduce the costs of the
    REP by engaging in in lieu transactions, which involve the
    actual sale of power, rather than paper transactions.40 We
    agree with the BPA Administrator’s conclusion that BPA did
    not violate section 5(c) by waiving this authority. See ROD
    129–34.
    First, we agree with the Administrator that BPA’s
    decision to engage, or not engage, in in-lieu transactions is
    entirely discretionary. See ROD 133. Indeed, the statute
    itself says only that BPA “may” engage in in-lieu
    transactions. 16 U.S.C. § 839c(c)(5) (emphasis added). “The
    permissive language and the absence of any legislative
    history lead us to conclude that the implementation of section
    5(c)(5) is completely within the discretion of the BPA.” Cal.
    Energy, 807 F.2d at 1462. Thus, the Administrator has
    interpreted section 5 as presenting “no statutory impediment”
    to BPA’s waiving its in-lieu authority, so long as BPA
    provides “a reasoned decision for withholding [its] discretion
    subsection, the Administrator may acquire an equivalent amount of
    electric power from other sources to replace power sold to such utility as
    part of an exchange sale if the cost of such acquisition is less than the cost
    of purchasing the electric power offered by such utility.” 16 U.S.C.
    § 839c(c)(5).
    40
    In practice, however, BPA has never actually exercised this power.
    ROD 132; see also Cal. Energy, 807 F.2d at 1461 (explaining that in-lieu
    purchases are “but a minor feature of the exchange program created in
    section 5,” with “only a very limited usefulness”).
    42                      APAC V. BPA
    under the Settlement.” ROD 131; see also ROD 133
    (explaining that the “discretionary decision to engage in in-
    lieu transactions,” pursuant to section 5(c)(5), is not “part of
    BPA’s obligation to protect the rates of COUs under section
    7(b)(2)”).
    This is not to say that it is always permissible for BPA to
    waive its in-lieu authority. As APAC points out, we have
    previously held—albeit under markedly different facts—that
    BPA would have “abused its discretion under 5(c)(5)” if it
    had “completely precluded itself from ever making in-lieu
    purchases.” Cal. Energy, 897 F.2d at 1462 (concluding that
    the petitioner had not shown that the contract actually
    contained such a “complete ban on in-lieu sales of power”).
    In California Energy, however, the contracts at issue did not
    contain any limit on the amount of REP benefits that utilities
    might receive, meaning that the risk of waiving the in-lieu
    power—which is a means of keeping REP benefits in
    check—were much higher than in this case. This is
    consistent with the Administrator’s observation that “[i]n a
    world where the IOUs’ REP payments are determined rate
    case by rate case, it makes sense for the Administrator to
    retain his rights to engage in in lieu transactions to damper
    otherwise unknown REP costs.” ROD 130.
    Here, unlike in California Energy, there is a cap on the
    total amount of REP benefits the IOUs can receive under the
    Settlement, meaning that the cost of REP benefits will not
    suddenly spike in an unexpected way, as it could absent the
    Settlement. And BPA has provided a reasoned decision for
    waiving its in-lieu authority, taking into account the costs and
    benefits of doing so. Its primary reason for waiving this
    authority is “to achieve the substantial cost protections
    afforded by the Settlement,” ROD 130, the certainty of which
    APAC V. BPA                          43
    would be undermined if BPA retained the power to add
    another variable to its rate calculations. Essentially, BPA has
    waived one way of controlling REP costs—the ability to
    engage in in-lieu transactions—for another, greater way of
    controlling REP costs, i.e., the Settlement. ROD 132–33.
    We agree with the BPA Administrator that this is a
    reasonable trade-off. Furthermore, we note that because the
    amount of REP benefits is set under the Settlement, the only
    effect of an in-lieu transaction would be to “adjust the
    amounts paid to each IOU,” as opposed to creating “cost
    savings to BPA or any other ratepayers.” ROD 131. This
    further supports BPA’s decision to waive its in-lieu authority,
    because doing so does not deprive other ratepayers of a
    benefit they might otherwise receive. We therefore conclude
    that, under these facts, it was reasonable, and not unlawful,
    for BPA to waive its authority to engage in in-lieu
    transactions.
    We likewise reject APAC’s second argument, that “BPA,
    as a member of the executive branch,” cannot contract away
    the powers given to it by Congress. Here, BPA is “acting as
    a private contracting party,” and as a result, its “rights and
    duties are governed by law applicable to private parties
    unaltered by the government’s sovereign status.” Kimberly
    Assocs. v. United States, 
    261 F.3d 864
    , 869 (9th Cir. 2001);
    see also PGE, 501 F.3d at 1029 n.17 (“Unlike many
    regulatory agencies, ‘Congress endowed the Administrator
    with broad-based powers to act in accordance with BPA’s
    best business interests,’ allowing BPA ‘to function more like
    a business than a governmental regulatory agency.’” (quoting
    APAC, 
    126 F.3d at 1170
    )). BPA therefore did not err by
    waiving its ability to exercise one of its discretionary powers.
    44                      APAC V. BPA
    B. NWPA Section 7(b)
    APAC also argues that the Settlement does not comply
    with section 7(b) of the NWPA, under which BPA must
    calculate a “rate ceiling” to protect the COUs. See 16 U.S.C.
    § 839e(b)(2)–(3). Here, rather than challenging the “lump
    sum” term of the Settlement, APAC challenges the new
    methodology for running the “rate test” under section 7(b).
    As explained supra, under the Settlement, BPA ran the “rate
    test” prospectively for each year of the Settlement.
    APAC argues that under section 7(b), BPA cannot use
    rate projections “that extend beyond five years,” and
    therefore it cannot rely on its prospective rate tests for the
    entire term of the seventeen-year settlement. In support of
    this argument, APAC cites to the requirement that BPA must
    calculate the rate ceiling for any given year using projected
    power costs for that year, “plus the ensuing four years.”
    16 U.S.C. § 839e(b)(2); see also id. at (C) (explaining that
    BPA must calculate the rate ceiling by assuming that no REP
    benefits are paid out “during such five-year period”). This
    requirement, according to APAC, imposes “time constraints
    . . . which were designed to ensure that REP benefits must be
    based on current cost and load data.” We disagree.
    As APAC concedes, section 7(b) is silent with respect to
    how far in advance BPA can run the rate test for any given
    year. And the language APAC cites requires only that BPA
    use information from five separate years—the year in
    question, plus the following four years—to set rates for a
    single year. This requirement does not impose a restriction
    on running the section 7(b)(2) rate test in advance of a
    particular year; to the contrary, it supports the conclusion that
    BPA can rely on projected rates when running its rate tests.
    APAC V. BPA                          45
    In the absence of clear statutory language regarding how
    far in advance BPA can run its rate tests, we accord
    substantial deference to BPA’s interpretation of section 7.
    See PGE, 501 F.3d at 1025. Here, the Administrator
    concluded that since BPA unquestionably has the legal
    authority to settle REP disputes, see id. at 1030, it must also
    be able to satisfy its section 7(b)(2) obligations by running
    the rate test for the term of the settlement. ROD 173–74.
    Otherwise, “there could never be a meaningful REP
    settlement,” or at least not one that settled the dispute for
    longer than a five-year period. ROD 174. The Administrator
    thus explained:
    In a normal ratemaking context, where BPA
    revises its rates every two years in a contested
    environment, BPA conducts the 7(b)(2) rate
    test for the rate period plus four years to
    determine two-year rates. A REP settlement,
    however, resolves REP disputes for a longer
    term than a single rate period . . . . Therefore
    a REP settlement must satisfy section 7(b)(2)
    in a different manner from the rate test used to
    establish rates for a single rate period.
    ROD 173.         We conclude that this is a reasonable
    interpretation of section 7(b)(2). See Chevron, 
    467 U.S. at
    843 & n.11 (“[I]f the statute is silent or ambiguous with
    respect to the specific issue, the question for the court is
    whether the agency’s answer is based on a permissible
    construction of the statute. The court need not conclude that
    the agency construction was the only one it permissibly could
    have adopted to uphold the construction . . . .”). As BPA
    argues in its answering brief, section 7(b)(2) is not “a
    straitjacket that effectively prohibits settlement of the REP.”
    46                          APAC V. BPA
    And the mere fact that BPA has traditionally calculated the
    rate ceiling on a two-year cycle does not mean that is the only
    legal method for running the test.41 Rather, it makes sense
    that BPA would run the rate test for a two-year period when
    setting rates for the upcoming two years, and for a seventeen-
    year period when setting rates for the upcoming seventeen
    years.
    Nor does BPA’s method of running the section 7(b)(2)
    rate test under the Settlement render the test “superfluous,” as
    APAC argues. The purpose of the rate test is not to ensure
    that BPA charges the COUs the exact amount at which the
    rate ceiling is set; the purpose is to ensure they are charged an
    amount no higher than the rate ceiling. See 16 U.S.C.
    § 839e(b)(2). Thus, contrary to APAC’s argument, it does
    not matter if “the result of the § 7(b)(2) rate test can be
    directly, arithmetically linked” to the COUs’ rates, so long as
    those rates to do not exceed the rate ceiling. The section
    7(b)(2) rate test plays an important role in the Settlement,
    insofar as it requires BPA to compare the lump sum of REP
    benefits to the projected rate ceilings, in order to ensure that
    the COUs would not be charged rates higher than the rate
    ceiling. And to the extent the Settlement “pre-determine[s]
    the rate ceiling” by setting a lump sum of REP benefits, as
    APAC argues, it pre-determines a lower rate ceiling than
    would otherwise be set under section 7(b)(2). This is not a
    violation of section 7(b)(2).
    41
    Furthermore, as the BPA Administrator explained, the argument that
    “the duration of the 2012 Settlement . . . is unprecedented” not only fails
    to show that the Settlement is unlawful, it is also “simply wrong . . . .
    During the 1980s and 1990s, BPA negotiated REP settlement agreements
    and paid benefits under such agreements to 33 exchanging utilities,
    including all of BPA’s exchanging preference customers, for terms up to
    15 years.” ROD 201.
    APAC V. BPA                               47
    In addition to challenging the method of applying the
    section 7(b)(2) rate test, APAC also challenges its result.
    Thus, it argues that the Settlement violates section 7 because
    “the projected costs under some of the various scenarios in
    [BPA’s] analysis did, in fact, exceed the § 7(b)(2) rate test.”
    It is true that in three of the twenty-six scenarios, the COUs
    would not receive greater rate protection under the Settlement
    than they would without the Settlement.42 But these three
    scenarios involved “extreme instance[s] where the COUs
    prevail on multiple major contested issues and the IOUs
    succeed in virtually none of their issues.” ROD 59; 198.
    Although we recognize the narrow possibility that a violation
    of section 7(b)(3) could occur if one of these scenarios
    presented itself, we are satisfied with the Administrator’s
    conclusion that these “extreme” scenarios are unlikely to
    occur. ROD 80–81. “This is not to say that BPA could act
    contrary to a clear statutory directive in settling, but if there
    is room for doubt, we ought not to resolve it in a manner that
    sends the parties back to litigation.” Util. Reform Project v.
    Bonneville Power Admin., 
    869 F.2d 437
    , 443 (9th Cir. 1989).
    Such is the case here.
    42
    These twenty-six scenarios consisted of “four scenarios to analyze
    uncertainty in BPA’s costs and [twenty-two] scenarios to analyze the
    possible impact of the litigation outcomes.” ROD 56–58. As the
    Administrator noted, “the lower projected costs of the REP . . . are not
    mere ethereal guesswork.” ROD 60. In making these projections, BPA
    considered “multiple variations on the key drivers of future REP benefits,
    i.e., ASCs, exchange loads, BPA’s costs, litigation risks, and market
    variations.” ROD 64. Thus, although the very nature of forecasting
    implies some uncertainty, the rates that BPA forecast cannot fairly be
    characterized as, in APAC’s words, “pure speculation and conjecture.”
    48                      APAC V. BPA
    C. Cost Recovery Adjustment Clause
    APAC next argues that the Settlement is unlawful because
    it does not permit BPA to apply a Cost Recovery Adjustment
    Clause (“CRAC”) to the REP benefit levels. The CRAC is a
    rate mechanism by which BPA can adjust customers’ rates
    when “changes in costs and revenues vary substantially from
    what BPA was projecting when setting rates,” so that BPA is
    able to recover all of its costs. ROD 138; see also Indus.
    Customers of Nw. Utilities v. Bonneville Power Admin.,
    
    408 F.3d 638
    , 642 (9th Cir. 2005) (“The CRACs were created
    to allow the BPA to address any financial shortfalls without
    having to raise base rates.”). APAC argues that by
    “guaranteeing the IOUs a fixed amount of REP benefits that
    BPA cannot adjust,” the Settlement “excuses IOU customers
    from the CRAC,” which means that other customers will bear
    the burden of assuring that BPA recovers its costs. We agree
    with the factual premise that BPA cannot apply a CRAC to
    the IOUs’ REP benefit levels under the Settlement, even if
    BPA’s costs are higher than expected. See ROD 134. We
    nevertheless reject APAC’s argument, for two reasons.
    First, as the BPA Administrator explained “CRACs are
    not required by the [NWPA].” Rather, they are a mechanism
    by which BPA exercises its statutory authority to “recover . . .
    the cost associated with the acquisition, conservation, and
    transmission of electric power.” 16 U.S.C. § 839e(a)(1); see
    also Cal. Energy Comm’n, 909 F.2d at 1303 (explaining that
    section 7 “requires BPA, in marketing federal power, to
    establish rates that will produce sufficient revenues to ensure
    BPA’s fiscal independence”). BPA thus has broad authority
    to determine if and how to apply a CRAC. See, e.g., Pub.
    Power Council, 
    442 F.3d at 1211
     (explaining that a CRAC is
    APAC V. BPA                          49
    “entirely bound up with BPA’s rate making responsibilities,
    and we owe deference to the BPA in that area”).
    Second, to the extent APAC challenges BPA’s exercise of
    this discretion, we reject this challenge. The BPA
    Administrator concluded that it was reasonable to insulate the
    IOUs from a potential CRAC for two reasons: first, the IOUs
    “will not receive any upside benefits during a rate period” if,
    for example, BPA is unexpectedly able to charge lower rates
    than expected; and second, “because the REP benefits are
    fixed, the IOUs’ REP benefits payments would never be a
    contributing factor” to any unexpected costs that might
    trigger a CRAC. ROD 135; see also ROD 137. Thus, “the
    lack of a CRAC mechanism in the Settlement . . . [is] simply
    one of the trade-offs” of the Settlement, counter-balanced by
    other terms that are less beneficial to the IOUs. ROD 136.
    And while “COU customers may feel the brunt of a CRAC in
    a future rate case,” the BPA Administrator concluded that
    “the discount the IOUs are taking in their REP benefits under
    the Settlement would . . . more than make-up for the small
    amount of CRAC contributions the IOUs would have
    provided under a no-settlement alternative.” ROD 139. This
    was a reasonable conclusion. See Pac. Nw. Generating Co-
    op., 
    580 F.3d at 806
     (“[W]e have identified the question of
    how best to further BPA’s business interests consistent with
    its public mission as a statutory gap that Congress has left to
    BPA to fill.” (quotation marks omitted)); Pub. Power
    Council, 
    442 F.3d at 1209
     (“[W]e may not substitute our own
    judgment for that of BPA; we must simply assess whether
    BPA relied on improper factors, failed to consider an
    important aspect of the question, offered an explanation for
    its decision that runs counter to the evidence before it, or
    rendered a decision that is so implausible that it could not be
    ascribed to a difference in view or the product of agency
    50                          APAC V. BPA
    expertise.” (quotation marks and alterations omitted)). We
    therefore conclude that the Administrator’s decision to
    approve the Settlement without including a CRAC
    mechanism was neither unlawful nor unreasonable.
    D. Bonneville Power Act and FERC Regulations
    1.
    In addition to arguing that the Settlement violates the
    NWPA, APAC also argues that the Settlement violates the
    Bonneville Project Act, 16 U.S.C. § 832d, and applicable
    FERC regulations, 
    18 C.F.R. §§ 300.1
    (b)(6), 300.21(e)(1), by
    setting rates for a period that exceeds five years.43
    These sources require that contractual rates be equitably
    adjusted no less than once every five years. See 16. U.S.C.
    § 832d(a) (“Contracts entered into under this subsection shall
    contain . . . such provisions as the administrator and
    purchaser agree upon for the equitable adjustment of rates at
    appropriate intervals, not less frequently than once in every
    five years . . . .” (emphasis added)); 
    18 C.F.R. § 300.1
    (b)(6)
    (“Proposed rate approval period means the period for which
    confirmation and approval of the rate schedules is requested.
    This period must not exceed five years.”); § 300.21(e)(1)
    (stating that rate-approval periods are “not to exceed a five-
    year period” unless FERC deems it appropriate). But, as
    BPA argues, “establishing costs is not the same as setting
    43
    All power sales conducted pursuant to section 5 of the NWPA are
    “subject at all times to the preference and priority provisions of the
    Bonneville Project Act of 1937 (16 U.S.C. 832 and following) and, in
    particular, sections 4 and 5 thereof [16 U.S.C. §§ 832c, 832d].” 16 U.S.C.
    § 839c(a).
    APAC V. BPA                          51
    rates.” Here, the Settlement sets a fixed amount of REP
    benefits that BPA will be required to pay over the term of the
    Settlement, but it does not set any rates, meaning the five-
    year limit on rate-setting is inapplicable. As the BPA
    Administrator explained,
    Establishing rates and establishing costs are
    two substantively different things. The
    Settlement establishes the amount of REP
    benefits provided to the IOUs over the
    Settlement term and thus the amount of REP
    costs included in preference customers’ rates
    during that term. The Settlement does not
    establish rates.
    ROD 203. Rather, the Settlement resolves disputes about
    REP costs and rate-making methodology, neither of which
    “must be revised every five years” by statute or regulation.
    ROD 202.
    Furthermore, although the Settlement “pre-determines”
    REP benefits, that does not mean that it also pre-determines
    rates. As the Administrator explained, “ratemaking involves
    many steps, including a forecast of loads and resources; a
    determination of BPA’s total revenue requirement; a forecast
    of market prices; an analysis of risk and its mitigation; a cost
    of service analysis; a rate design analysis; and additional
    steps.” ROD 202. The Settlement itself likewise makes clear
    that BPA will continue to engage in ongoing rate-setting
    throughout the term of the Settlement. See, e.g., ROD
    Appendix A 19 (“For each Fiscal Year, BPA will develop
    rates, in the Rate Proceeding for the applicable Rate Period,
    such that each IOU will be paid its IOU-Specific REP
    Settlement Benefit Amount as calculated for such Fiscal Year
    52                      APAC V. BPA
    pursuant to this section 6.”). Indeed, after the Administrator
    approved the Settlement, BPA conducted the “BP-12” rate
    proceeding to “establish[] power and transmission rates for
    FY 2012–2013.” ROD 25. We thus conclude that the
    Settlement sets only costs, not rates, and therefore does not
    violate the five-year rate-setting limitations established by the
    Bonneville Power Act and FERC regulations.
    2.
    Next, APAC argues that the Settlement violates the
    Bonneville Power Act, 16 U.S.C. § 832d(a), because it does
    not permit BPA to cancel any contract with five years’ notice.
    The Bonneville Power Act provides the following
    cancellation requirements for contracts:
    [I]n the case of a contract with any purchaser
    engaged in the business of selling electric
    energy to the general public, the contract shall
    provide that the administrator may cancel
    such contract upon five years’ notice in
    writing if in the judgment of the administrator
    any part of the electric energy purchased
    under such contract is likely to be needed to
    satisfy the requirements of the said public
    bodies or cooperatives referred to in this
    chapter, and that such cancelation [sic] may
    be with respect to all or any part of the
    electric energy so purchased under said
    contract to the end that the preferential rights
    and priorities accorded public bodies and
    cooperatives under this chapter shall at all
    times be preserved.
    APAC V. BPA                               53
    16 U.S.C. § 832d(a) (emphasis added). We conclude that
    APAC’s argument fails because such cancellation can occur
    only if “any part of the electric energy purchased under [the]
    contract is likely to be needed.” But the Settlement does not
    deny the COUs’ access to power, because the Settlement
    guarantees only REP benefits, not actual power, for the IOUs.
    See generally Util. Reform Project, 
    869 F.2d at
    443–44
    (concluding that a particular power exchange between BPA
    and certain IOUs was “properly viewed as an exchange,
    rather than a sale, of power,” such that the five-year
    cancellation clause did not apply, because “BPA’s right to
    obtain exchange energy” meant there would be “no net
    diminution to the federal system” and BPA would “therefore
    continue to have the ability to meet its preference customers’
    needs”). Thus, there is no possibility that, under the terms of
    the Settlement, BPA will be required to provide power to the
    IOUs, much less power that is needed elsewhere.
    E. Compliance with PGE and Golden Northwest
    In addition to challenging the Settlement terms that
    provide benefits to the IOUs, APAC also raises a challenge to
    the terms that provide refunds to the COUs. APAC argues
    that the Settlement “fails to fulfill the mandate” of PGE and
    Golden Northwest because it “neither calculates the past
    overcharges nor provides for refunds with interest.”44 We
    find no merit to this argument. First, the Settlement
    addresses the overcharges by providing refunds for the
    COUs, in an amount totaling $612 million over eight years.
    44
    APAC also argues that the Settlement does not comply with PGE and
    Golden Northwest. because it violates section 5 and section 7 of the
    NWPA. We reject this argument for the reasons explained in our analysis
    of those provisions, supra.
    54                        APAC V. BPA
    As the Administrator explained, this amount “reflects BPA’s
    calculation of the outstanding Lookback Amount payments
    ($511 million), adjusted for interest earned over eights
    years.” ROD 253.45 Second, the very nature of a settlement
    is that the parties forego certain benefits or rights to which
    they may have a cognizable legal claim, in exchange for
    something else—here, guaranteed refunds, future certainty,
    and the end to ongoing litigation. Short of arguing that the
    parties to the Settlement have no right to settle, APAC cannot
    plausibly claim that the Settlement is invalid because it does
    not provide for the full amount of refunds to which the COUs
    may have been entitled, absent the Settlement. “An agency’s
    discretion is at its zenith when it is fashioning policies,
    remedies and sanctions . . . .” Pub. Utils. Comm’n of State of
    Cal. v. F.E.R.C., 
    462 F.3d 1027
    , 1053 (9th Cir. 2006)
    (emphasis added) (internal quotation marks and alteration
    omitted). We therefore will not disturb the Settlement’s
    refund schedule for the COUs, which all settling parties
    agreed to and which the BPA Administrator approved.
    F. Enforcement of Settlement on Non-Binding Parties
    APAC next argues that the Settlement is only a “partial
    settlement,” which “does not resolve all claims between all
    adverse parties” and cannot bind the non-signatories. This is
    true: the Settlement cannot, and does not, bind any parties
    that have not signed it. But this does not mean that BPA is
    45
    After our decisions in PGE and Golden Northwest, but before the
    Administrator approved the Settlement, BPA provided partial refunds to
    the COUs for over-charges under the 2000 Settlement. Adding these
    refunds to the $612 million guaranteed under the Settlement, “the total
    refund payments BPA will have made to the COUs will be approximately
    $1.2 billion.” ROD 253.
    APAC V. BPA                          55
    prohibited from setting the same rates for signing and non-
    signing parties. As BPA argues, it has the statutory authority
    to set rates and to recover costs through those rates, pursuant
    to section 7 of the NWPA. See 16 U.S.C. § 839e. So long as
    the Settlement complies with the relevant statutory
    authority—as we have concluded that it does—BPA does not
    need its customers to unanimously agree to the rates it sets in
    accordance with the Settlement. We agree with the
    Administrator’s explanation of the Settlement:
    Non-signers are bound only in the sense that
    they will pay in rates the REP benefits
    provided under the Settlement, but only after
    BPA has independently found that the
    Settlement satisfies the requirements and
    protections set forth in the [NWPA]. This is
    not the same thing, though, as treating non-
    signers as if they have executed the
    Settlement. For example, pursuant to section
    7.10 of the Settlement, signers may not
    “directly or indirectly challenge, either in
    whole or in part, the legality of the Settlement
    Agreement or any REP Settlement
    Implementation Agreement.” Non-signers are
    not so limited.
    56                           APAC V. BPA
    ROD 348.46 In other words, our conclusion that BPA can
    lawfully set the same rates for signing and non-signing parties
    does not necessarily preclude non-signing parties from
    challenging those rates going forward. Cf. ROD 325 (“[A]s
    a legal matter, BPA’s decision to execute the Settlement (and
    therefore become a ‘Party’), and BPA’s decision to replace its
    previous disputed decisions with the Settlement and this
    ROD, may have an effect on [parties’] pending claims.”). We
    therefore conclude that the Settlement does not improperly
    bind non-settling parties to the Settlement.
    G. Fairness and Reasonableness of the Settlement
    Finally, APAC argues that the Settlement is neither fair
    nor reasonable, and that the Administrator’s conclusion to the
    contrary is “arbitrary and capricious.” See 
    5 U.S.C. § 706
    (2)
    (providing that a court shall “hold unlawful and set aside
    agency actions, findings, and conclusions” that are “arbitrary,
    capricious, an abuse of discretion, or otherwise not in
    accordance with law”). APAC essentially re-caps the same
    arguments we have rejected supra, arguing, inter alia, that the
    COUs have “forfeited” the protections of the section 7(b)(2)
    rate test, that several of the tested scenarios did not result in
    46
    See also ROD 322 (“In terms of whether the Settlement provides
    equity to non-settling parties, BPA believes the non-settling parties are
    being treated equitably under the Settlement because they will benefit
    from the return of the Refund Amounts and resolution of the past refund
    payments.”); ROD 361 (“The conclusion is that under most possible future
    results of the rate test, rates for COUs would be higher than the rates under
    the Settlement . . . . Thus, BPA is not imposing rates on non-signing
    customers that would deny such customers their statutory 7(b)(2)
    protection.”); ROD 372 (“Because the Settlement is consistent with BPA’s
    ratesetting directives, the statutory protections of non-settling entities are
    not being violated by the Settlement.”).
    APAC V. BPA                        57
    lower REP benefits under the Settlement than would be
    distributed without the Settlement, that the Settlement
    improperly projects costs over a seventeen year period, that
    the Settlement improperly waives BPA’s in-lieu power and
    prevents it from allocating CRAC costs to the IOUs, and that
    the Settlement’s value to the COUs is “overstated,” since the
    COUs are entitled to greater refunds pursuant to PGE and
    Golden Northwest. We reject these arguments for the reasons
    provided supra. The Settlement is lawful. Furthermore, the
    BPA Administrator engaged in an exhaustive evaluation of
    the Settlement, providing thorough analyses and conclusions
    for countless challenges raised during the administrative
    proceedings.     We therefore conclude that the BPA
    Administrator’s adoption of the REP-12 Settlement in the
    REP-12 Record of Decision was not arbitrary or capricious.
    IV. CONCLUSION
    For the foregoing reasons, APAC’s petition for review is
    DENIED.
    58                           APAC V. BPA
    ALARCÓN, Circuit Judge, dissenting:
    I respectfully dissent.
    In this matter, we must initially determine whether
    APAC,1 a group whose members are not direct customers of
    BPA, has standing to challenge the REP-12 Settlement
    Agreement. BPA and the intervening parties,2 some of whom
    supply electricity to APAC’s members, contend that APAC’s
    members lack standing to bring this challenge because they
    are not direct customers of BPA. APAC counters that it has
    standing on account of its members’ cost-based pass-through
    contracts with the COUs.3 I would deny the petition because
    1
    APAC is the only party challenging the REP-12 Settlement Agreement.
    APAC’s petition initially was consolidated with Alcoa Inc. v. Bonneville
    Power Administration, No. 11-73161. BPA and Alcoa later settled their
    dispute and agreed to dismiss that action under Rule 42(b) of the Federal
    Rules of Appellate Procedure. This Court dismissed Alcoa’s petition with
    prejudice on December 18, 2012.
    2
    Three groups of intervenors sought and were granted permission to
    intervene and file answering briefs: (1) Joint COUs; (2) Joint IOUs; and
    (3) State Commissions. These parties joined in BPA’s arguments. The
    Joint IOUs separately challenge APAC’s standing in their answering brief.
    APAC filed a motion to supplement the record with affidavits, which the
    court granted. BPA filed a response to APAC’s motion to supplement the
    record with affidavits, contending that although it did not oppose APAC’s
    motion, APAC’s evidence failed to establish standing.
    3
    APAC has previously challenged BPA’s determinations in this Court.
    See, e.g., Ass’n of Pub. Agency Customers, Inc. v. Bonneville Power
    Admin. (APAC), 
    126 F.3d 1158
    , 1163 (9th Cir. 1997); Pub. Utils. Comm’n
    of Cal. v. FERC, 
    814 F.2d 560
     (9th Cir. 1987); Aluminum Co. of Am. v.
    Bonneville Power Admin. (Alcoa), 
    903 F.2d 585
    , 587 (9th Cir. 1989). Of
    those cases, BPA disputed APAC’s standing only in APAC. 
    126 F.3d at
    1183 n.9. There, the Ninth Circuit declined to decide whether APAC had
    APAC V. BPA                                59
    it is my view that we lack the power to review its merits
    because APAC has failed to demonstrate that it has Article III
    standing. Accordingly, I am persuaded I lack the power to
    comment on the majority’s opinion regarding the merits of
    APAC’s petition.
    I
    Because standing was not at issue in the agency
    proceeding below, we must consider the question in the first
    instance. Stormans, Inc. v. Selecky, 
    586 F.3d 1109
    , 1119 (9th
    Cir. 2009) (“Questions of standing . . . may be raised and
    considered for the first time on appeal, including sua sponte.”
    (citations omitted)). We must first consider whether at least
    one of APAC’s members “suffered sufficient injury to satisfy
    the ‘case or controversy’ requirement of Article III.”4
    Cetacean Cmty. v. Bush, 
    386 F.3d 1169
    , 1174 (9th Cir. 2004).
    If APAC establishes Article III standing, we next would be
    required to determine whether one of its members has
    standing to challenge BPA’s final actions because it was uncontested that
    two other petitioners raising the same challenges in the proceeding had
    standing. See 
    id.
     A ruling on APAC’s standing is necessary here,
    however, because APAC is the only party challenging the REP-12
    Settlement Agreement.
    4
    An association like APAC has standing to bring suit on behalf of its
    members if: (1) at least one of its members had standing to bring this
    petition on its own; (2) by bringing this petition APAC sought to protect
    interests germane to its purpose; and (3) neither the claim brought nor
    relief sought by APAC requires individual members to participate in the
    lawsuit. See Hunt v. Wash. State Apple Advert. Comm’n, 
    432 U.S. 333
    ,
    343 (1977). Neither BPA nor the intervenors argue, nor is there any
    reason to believe, that APAC fails to satisfy the second and third elements
    of this test. The only inquiry, then, is whether at least one of APAC’s
    individual members has standing under Article III.
    60                       APAC V. BPA
    prudential standing—“whether a statute has conferred
    ‘standing’” on at least one of APAC’s members, id. at 1175,
    such that the member falls “within [the statute’s] zone of
    interests,” Cent. Ariz. Water Conservation Dist. v. EPA,
    
    990 F.2d 1531
    , 1538 (9th Cir. 1993) (internal quotation marks
    omitted).
    A
    Article III of the United States Constitution limits the
    power of the courts to the resolution of actual “Cases” and
    “Controversies.” U.S. Const., art. III, § 2; Valley Forge
    Christian Coll. v. Ams. United for Separation of Church &
    State, Inc., 
    454 U.S. 464
    , 471 (1982). “[T]he irreducible
    constitutional minimum of standing contains three elements”:
    (1) injury in fact, (2) causation, and (3) redressability. Lujan
    v. Defenders of Wildlife, 
    504 U.S. 555
    , 560–61 (1992). Thus,
    the party seeking to establish standing must show the “actual
    or imminent” “invasion of a legally protected interest” that
    is “fairly traceable to the challenged action” and is “likely . . .
    to be redressed by a favorable decision.” 
    Id.
     at 560–61
    (emphasis added) (alterations, citations, and quotation marks
    omitted). The party seeking to establish jurisdiction—here,
    APAC—bears the burden of demonstrating standing.
    DaimlerChrysler Corp. v. Cuno, 
    547 U.S. 332
    , 342 & n.3
    (2006); Lujan, 
    504 U.S. at 561
    . When, as here, the party
    seeking to establish standing “is not himself the object of the
    government action or inaction he challenges, standing is not
    precluded, but is ordinarily ‘substantially more difficult’ to
    establish.” Lujan, 
    504 U.S. at 562
     (quoting Allen v. Wright,
    
    468 U.S. 737
    , 758 (1984)).
    APAC V. BPA                               61
    1
    Both BPA and APAC rely on the NWPA’s language and
    legislative history in making their respective standing
    arguments. Additionally, APAC supplemented the record on
    appeal with two affidavits.5 Though slightly different, the
    affidavits establish that two of APAC’s members purchase
    electricity from BPA’s COU customers, which purchase
    power from BPA directly. Two of APAC’s members have
    operated in the past6 or currently operate facilities in the
    Pacific Northwest that manufacture goods from forest
    products. Georgia-Pacific LLC’s (“GP”) paper mill in
    Wauna, Washington accounts for approximately 70% of the
    total load served by its COU supplier, and its Toledo
    packaging and container-board mill accounts for
    approximately 40% of the load served by its COU supplier.
    APAC’s members’ agreements with the COUs are “cost-
    based pass-through” contracts by which members purchase
    power from the COUs at the COUs’ cost of purchasing power
    from BPA—and, in some cases, other sources—plus any
    additional charges for overhead. As a result of these pass-
    5
    We consider APAC’s affidavits solely to determine whether APAC has
    standing. While a party may not supplement the record on appeal from an
    agency decision, this rule does not apply when a party attempts to
    establish standing. See Nw. Envtl. Def. Ctr. v. Bonneville Power Admin.,
    
    117 F.3d 1520
    , 1527–28 (9th Cir. 1997) (“Because Article III’s standing
    requirement does not apply to agency proceedings, petitioners had no
    reason to include facts sufficient to establish standing as a part of the
    administrative record.”). Standing was not at issue in the earlier
    proceedings. Accordingly, APAC may establish standing during the
    briefing phase. 
    Id. at 1528
    .
    6
    The Lovely Affidavit repeatedly uses the past tense when describing
    APAC’s member. I accordingly assume this member is no longer in
    operation and no longer has a contract with the COU.
    62                          APAC V. BPA
    through contracts, “the rates and charges incurred by [the
    COUs] to purchase power from BPA . . . are recovered from
    [APAC’s members].” And, while at least one member’s
    supplier had the “right to depart from this arrangement upon
    giving the contractually required notice,” the COU supplier
    “did not do so during the contract term.” The affidavits state
    that APAC’s members consequently “are directly impacted
    financially by any rate increases and decreases adopted by
    BPA.”
    BPA has not refuted or submitted supplemental evidence
    controverting these facts, though it argues they are
    insufficient to confer standing on APAC. Thus, the only
    question regarding APAC’s standing is whether it submitted
    sufficient admissible evidence to support each element of
    standing by a substantial probability.7
    7
    The Ninth Circuit has not explicitly articulated the appropriate burden
    of production that a petitioner bears when directly appealing an agency
    decision, but suggested in Northwest Environmental Defense Center that
    the appropriate standard is a summary judgment standard. 
    117 F.3d at
    1528–29; Lujan, 
    504 U.S. at 561
     (“[F]acts that must be averred (at the
    summary judgment stage) [and] proved (at the trial stage) in order to
    establish standing . . . .”); cf. Didrickson v. U.S. Dep’t of Interior,
    
    982 F.2d 1332
    , 1340 (9th Cir. 1992) (applying a summary judgment
    burden of production to an intervenor’s evidence of standing submitted for
    the first time on appeal, where the challenged decision was resolved at
    summary judgment). The Court of Appeals for the District of Columbia,
    which handles a large docket of direct agency appeals, has adopted a
    summary judgment burden of production for petitioners seeking review of
    administrative actions. See Sierra Club v. EPA, 
    292 F.3d 895
    , 899 (D.C.
    Cir. 2002). Under this standard, the petitioner must demonstrate each
    element of standing “by a substantial probability” and “may carry its
    burden of production by citing any record evidence relevant to its claim
    of standing and, if necessary, appending to its filing additional affidavits
    or other evidence sufficient to support its claim.” 
    Id. at 899
    , 900–01; see
    also Lujan, 
    504 U.S. at 561
     (stating that a plaintiff “must set forth by
    APAC V. BPA                                 63
    2
    To establish Article III standing, APAC must first
    demonstrate by a substantial probability that at least one of its
    members suffered or will suffer a injury in fact—the invasion
    of a legally protected interest that is concrete and
    particularized, and actual or imminent. Lujan, 
    504 U.S. at
    560–61. APAC has not satisfied this burden.8
    affidavit or other evidence specific facts” to support standing to survive
    a motion for summary judgment).
    8
    I note that APAC’s participation in the underlying agency proceeding
    does not confer standing because Article III’s standing requirements do
    not apply to agency proceedings. See Summers v. Earth Land Inst.,
    
    555 U.S. 488
    , 496 (2009); Nw. Envtl. Def. Ctr., 
    117 F.3d at 1528
    . The
    rules governing standing to participate in agency proceedings are almost
    universally more permissive than the requirements for constitutional
    standing. See, e.g., Office of Commc’n of the United Church of Christ v.
    FCC, 
    359 F.2d 994
     (D.C. Cir. 1966) (holding listening public’s interest in
    programming content was sufficient to confer standing to intervene in
    FCC adjudicatory proceeding involving license renewal); Scenic Hudson
    Preservation Conference v. Fed. Power Comm’n, 
    354 F.2d 608
     (2d Cir.
    1965) (holding the “private attorney general” concept justifies intervention
    in agency hearing by those without a direct personal or economic interest
    in agency decision). Historically, courts and agencies have broadened
    public participation in agency proceedings on the theory that broad public
    participation allows interested persons and groups to express their views
    before agency policies are announced and implemented, eases the
    enforcement of administrative programs relying upon public cooperation,
    satisfies judicial demands that agencies observe the highest procedural
    standards, and increases public confidence in the fairness of administrative
    hearings. See Barry B. Boyer, Funding Public Participation in Agency
    Proceedings: The Federal Trade Commission Experience, 
    70 Geo. L.J. 51
    , 52 & n.6 (1981) (“[N]umerous legal and administrative victories . . .
    established broad rights of public participation in agency proceedings.”);
    Roger C. Cramton, The Why, Where and How of Broadened Public
    Participation in the Administrative Process, 
    60 Geo. L.J. 525
    , 530–33
    64                          APAC V. BPA
    APAC claims the REP-12 Settlement harms its “concrete
    economic interests” in two ways: (1) it creates future harm by
    providing “unlawfully inflated” REP benefits to the IOUs;
    and (2) it perpetuates past harm by failing to redress the
    overcharges the COUs incurred (and in turn passed on to
    APAC’s members) as a result of the 2000 REP Settlement.
    As to the former, APAC contends BPA recovers the cost of
    the REP benefits in the Settlement by increasing the COUs’
    rates, which pass through to APAC’s members pursuant to
    their contracts with certain COUs. As to the latter, APAC
    notes that the REP-12 Settlement Agreement reimburses the
    COUs for overpayments by providing billing credits, or
    “Refund Amounts,” in an attempt to cure the overcharges the
    Ninth Circuit declared improper in Golden Northwest
    Aluminum, Inc. v. Bonneville Power Administration, 
    501 F.3d 1037
     (9th Cir. 2007), and Portland General Electric Co. v.
    Bonneville Power Administration (PGE), 
    501 F.3d 1009
     (9th
    Cir. 2007). APAC asserts these Refund Amounts are an
    “illusory fiction” and consequently fail to redress its
    members’ past harm. APAC contends that if it cannot
    challenge the REP-12 Settlement Agreement, its members
    will never have an opportunity “to remedy those past
    wrongs.”
    It is undisputed that APAC’s members do not contract
    with BPA for their power but instead contract with third-
    parties that in turn contract with BPA—here, some of BPA’s
    (1972); Reuel E. Schiller, Enlarging the Administrative Polity:
    Administrative Law and the Changing Definition of Pluralism,
    1945–1970, 
    53 Vand. L. Rev. 1389
    , 1417 (2000) (starting in the 1940s,
    federal courts “chang[ed] a variety of administrative law doctrines in ways
    that increased judicial scrutiny of the administrative process and opened
    that process up to parties that it believed were systematically excluded”).
    APAC V. BPA                          65
    COU customers. APAC contends that it has demonstrated
    that its members’ rates directly rise and fall with the COUs’
    rates as a result of the “cost-based pass-through contracts”
    they have with the COUs, under which “[APAC] buys power
    from [a COU] at [the COU]’s cost to purchase the power
    from BPA, plus additional charges for overhead.” BPA and
    the Joint IOUs argue these pass-through contracts are
    insufficient to confer standing. Specifically, BPA contends
    that APAC “has no relationship with BPA to support standing
    in this case” because its members are not BPA customers and
    do not have a direct relationship with BPA. As a result, BPA
    is not the party that sets the rates APAC’s members pay,
    rather, the COUs do.
    The general harm APAC claims—economic—has been
    recognized as a type of legally cognizable harm because
    paying excessive rates, either in the past or the future, is a
    concrete injury. See Alcoa, 903 F.2d at 590 (“There is harm
    in paying rates that may be excessive . . . .”); see also Sierra
    Club, 405 U.S. at 733–34 (“[E]conomic injuries have long
    been recognized as sufficient to lay the basis for standing
    . . . .”). While APAC identifies a legally cognizable type of
    harm, it nevertheless has failed to establish a legally
    cognizable interest because it cannot point to any right that
    would entitle its members to a particular rate. APAC
    maintains that its members’ pass-through contracts with the
    COUs confer statutory and contractual rights. APAC asserts
    that its members’ contracts with the COUs entitle those
    members to the rights the COUs enjoy pursuant to the NWPA
    and their direct contracts with BPA.
    66                          APAC V. BPA
    I first consider APAC’s claimed statutory rights9 under
    the NWPA. The NWPA identifies the three customer
    groups—COUs, IOUs, and DSIs—that fall within its purview
    and establishes guidelines and methodologies for calculating
    those customers’ rates.10 The NWPA requires BPA to
    promulgate these three groups’ rates in compliance with
    certain statutory obligations. 16 U.S.C. §§ 839c(c)(5),
    e(b)(2). These statutory mandates do not, however, constrain
    the rates of downstream end users like APAC’s members.
    See id. § 839e(b)(2) (providing guidelines for ratesetting
    relating to BPA’s three direct customer groups).
    Furthermore, the NWPA distinguishes between a “customer,”
    which it defines as “anyone who contracts for the purchase of
    power from the Administrator,” id. § 839a(7) (emphasis
    added), and a “consumer,” which it defines as “any end user
    9
    The majority suggests that it is inappropriate to examine the statute in
    the context of a legally cognizable interest, and that instead we should
    look to the statute only when analyzing prudential standing. This Court’s
    and the Supreme Court’s jurisprudence suggest otherwise. See, e.g., Linda
    R.S. v. Richard D., 
    410 U.S. 614
    , 617 n.3 (1973) (“It is, of course, true
    that Congress may not confer jurisdiction on Article III federal courts to
    render advisory opinions. But Congress may enact statutes creating legal
    rights, the invasion of which creates standing, even though no injury
    would exist without the statute.” (citation and internal quotation marks
    omitted)); Fulfillment Servs. Inc. v. United Parcel Serv., Inc., 
    528 F.3d 614
    , 618–19 (9th Cir. 2008) (same); Maricopa-Stanfield Irrigation &
    Drainage Dist. v. United States, 
    158 F.3d 428
    , 435 (9th Cir. 1998) (stating
    that in construing a water district’s subcontracts with the United States,
    this Court “must interpret them ‘against the backdrop of the legislative
    scheme that authorized them, and . . . in light of the policies underlying
    the controlling legislation.’” (quoting Peterson v. U.S. Dep’t of Interior,
    
    899 F.2d 799
    , 807 (9th Cir. 1990))).
    10
    While BPA may make sales to other parties under limited
    circumstances, APAC does not allege it purchased power from BPA under
    any of these circumstances.
    APAC V. BPA                              67
    of electric power,” 
    id.
     § 839a(5). Customers are entitled to
    specified rate protections, while “consumers” under the Act,
    like APAC’s members and residential customers, are not.
    The NWPA refers to “consumers” in the “Congressional
    declaration of purpose,” but one reference merely describes
    BPA’s general policy of including an array of parties in its
    administrative proceedings,11 including the “public at large,”
    id. § 839(3), and a second states only that BPA’s customers
    and their consumers should continue to bear the costs of
    administering the region’s electric power requirements, id.
    § 839(4). Because the NWPA groups all “end users” into the
    broad “consumers” category—including end users like
    residential consumers—these brief references do not establish
    that APAC’s members have the right to any particular rate
    under the Act.
    Additionally, while the NWPA contemplates the
    involvement of consumers of BPA power in its administrative
    proceedings and recognizes that the NWPA may benefit
    many parties (including the general public), it does not
    provide protections to these indirect consumers in its rate-
    setting provisions. For example, the NWPA requires that the
    IOUs pass through their REP benefits to their residential
    customers. 16 U.S.C. § 839c(c)(3); see PGE, 501 F.3d at
    1015. Thus, individual residential consumers of BPA power
    enjoy pass-through benefits from the IOUs, much as APAC’s
    members enjoy pass-through rates from the COUs through
    their contracts. Thus, to the extent the majority would rest
    APAC’s standing on the pass-through nature of its members’
    contracts, individual residential purchasers of BPA power
    11
    As noted above, the underlying policy favoring the inclusion of a
    broad range of parties in administrative proceedings does not apply to
    Article III courts. See supra note 8.
    68                         APAC V. BPA
    would also have standing based on the same pass-through
    nature of their rates.
    In addition, nothing in the NWPA’s legislative history
    suggests that Congress, in insuring that the benefits flowing
    from BPA’s direct customers’ rates would pass to end users,
    intended to confer a right on the end users of BPA power,
    including all residential customers. For example, while
    Congress expressed a desire to protect “the customers of
    preference utilities” by implementing the Rate Ceiling,12
    Congress also stated repeatedly that it intended to benefit the
    IOUs’ residential customers by implementing the REP.13
    Like the NWPA’s statutory language, the Act’s legislative
    history—which also recognizes the NWPA’s benefit to
    indirect consumers—does not establish that indirect
    consumers have the right to any particular rate under the
    NWPA. Put differently, Congress’s placement of restrictions
    on the rates that BPA’s direct customers charge their
    12
    See H.R. Rep. No. 96-976(II), at 35–36 (1980), reprinted in
    1980 U.S.C.C.A.N. 6023, 6033.
    13
    Id. at 36 (noting that while the REP program broadened residential
    customers’ access to less expensive BPA power, the concurrent
    implementation of the rate ceiling “added protection against preference
    utilities and their customers suffering the adverse and economic
    consequences as a result of [the NWPA]) (emphasis added); see also PGE,
    501 F.3d at 1016; Pub. Util. Comm’n of Or. v. Bonneville Power Admin.,
    
    767 F.2d 622
    , 624 (9th Cir. 1985) (“One of the goals of the Act is to
    ensure that residential customers served by the Northwest IOU’s have
    wholesale rate parity with residential customers served by publicly owned
    utilities and public cooperatives, BPA’s preference customers.” (emphasis
    added)).
    APAC V. BPA                             69
    customers does not confer a right on those indirect customers
    to challenge BPA’s contracts with its direct customers.14
    APAC responds that it is not just another downstream
    consumer of BPA power, but rather a “significant purchaser”
    of BPA power. To support this argument, APAC submits
    evidence, inter alia, that one of its members, GP, purchases
    70% of the total load served by one of BPA’s COUs, which
    in turn purchases 80% of its power from BPA. APAC’s
    evidence, though scant, likely establishes that it is a
    “significant purchaser” of BPA power. But being a
    “significant purchaser” of BPA power does not itself establish
    that at least one of APAC’s members has suffered a legally
    cognizable injury. This Court used the term “significant
    purchaser” of power in Public Utility District No. 1 of
    Douglas County v. Bonneville Power Administration (PUD),
    
    947 F.2d 386
    , 390 n.1 (9th Cir. 1991). There, in a footnote,
    we found that the intervenors–customers of certain public
    utilities alleged a sufficient injury where uncompensated
    losses to public utilities directly affected the customers’ rates.
    
    Id.
     In reaching that conclusion, we noted that the entities
    were “significant purchasers of [BPA] power,” but also relied
    on the intervenors–customers’ statutory right,15 under certain
    circumstances, to obtain compensation for monetary costs and
    power losses. 
    Id.
     APAC similarly argues that BPA’s
    adoption of the REP-12 Settlement Agreement will increase
    the COUs’ rates, which in turn will increase the rates of
    APAC’s members who are “significant purchasers” of BPA
    14
    See infra note 19 and accompanying text.
    15
    This case and others belie the majority’s suggestion that this Court
    does not examine statutory rights when analyzing the injury-in-fact
    element. See also supra note 9.
    70                     APAC V. BPA
    power. Unlike the customers in PUD, however, APAC does
    not (and cannot) point to a statutory guarantee that its
    members will be charged a certain rate or a statutory mandate
    that the COUs pass on credits or refunds to APAC’s
    members. Having pass-through contracts and being a
    “significant purchaser” without more, does not establish a
    legally cognizable injury.
    APAC similarly cites In re California Power Exchange
    Corp., 
    245 F.3d 1110
     (9th Cir. 2001), for the proposition that
    “end-use (or retail) customers have standing when their
    serving utility’s costs are increased.” However, the holding
    in California Power Exchange was not so broad. There, the
    intervenor–city petitioned for mandamus to compel the FERC
    to take action on California wholesale power purchasers’
    requests for refunds. In re Cal. Power Exch. Corp., 
    245 F.3d at 1119
    . This Court addressed the city’s standing in a
    footnote, holding that the city—a public utility
    customer—had standing because it had been injured by
    “unjust and unreasonable short-term rate conditions in
    California (in the form of higher electricity bills), and any
    refunds owed to [the utility] would redress the City’s injury,
    insofar as such refunds would flow through to [the utility’s]
    customers in the form of rate reductions.” 
    Id.
     at 1124 n.14.
    The injury there was not speculative—we could conclude
    with certainty that any refunds to the utilities “would flow
    through” to the city because a state statute so provided. See
    
    id.
     (quoting and citing 
    Cal. Pub. Util. Code § 332.1
    (2)).
    Thus, like the holding in PUD, the California Energy court’s
    holding was narrow and relied on the petitioners’ statutory
    right to compensation to establish certainty of injury and
    APAC V. BPA                               71
    redressability.16 APAC has pointed to no such statutory right
    here.
    Nor does APAC allege a legally cognizable injury arising
    from a contractual right. The majority’s reliance on Central
    Arizona Water Conservation District v. EPA, 
    990 F.3d 1531
    (9th Cir. 1993) is misplaced. In Central Arizona, this Court
    held that the petitioners—a water district and four related
    irrigation districts—had standing to challenge an EPA
    regulation that required a generating station to reduce sulfur
    dioxide emissions by 90%. 
    Id.
     at 1537–38. We held the
    petitioners, as direct customers of the generating station,
    established an injury in fact where they were “contractually
    required” to repay the generating station “the major portion
    of” costs relating to the station’s compliance with the EPA
    order. 
    Id. at 1534
    , 1537–38. APAC argues, and the majority
    opinion suggests, that EPA and BPA are analogous in that
    both engaged in agency determinations that affected indirect
    parties and consequently that these indirect parties both have
    standing to challenge the agency determination. However,
    this comparison ignores that in this instance BPA occupies a
    role that is distinct from the EPA’s regulatory role, in that
    BPA was acting within its power to contract by adopting the
    REP-12 Settlement Agreement. Accordingly, BPA is
    analogous to the generating station that directly contracted
    with the water and irrigation districts. In contrast to those
    directly contracting customers, APAC’s members are merely
    downstream retail customers.
    16
    While APAC cites to the Rate Ceiling Test and provisions of the
    NWPA to demonstrate that its members enjoy various protections under
    the NWPA, for the reasons set forth above, these provisions do not confer
    rights on consumers like APAC, but rather only on BPA’s direct
    customers.
    72                       APAC V. BPA
    The facts here are also distinguishable from the second
    contractual case on which the majority relies, Maricopa-
    Stanfield, where the Ninth Circuit held that the plaintiffs
    established “injury in fact.” 
    158 F.3d at 435
    . There, the
    plaintiffs were irrigation districts who claimed that adoption
    of the San Carlos Apache Tribe Water Rights Settlement Act
    of 1992 (“SCAT Act”) resulted in the government taking
    their rights to certain water without just compensation. 
    Id. at 433
    . There, we concluded that irrigation district alleged a
    legally cognizable injury. However, the irrigation districts’
    legal rights arose from their direct contracts with the United
    States. See 
    id. at 431
     (“Each of the Districts entered into a
    subcontract with the United States Department of the Interior
    . . . .” (emphasis added)), 434 (noting that the districts
    demonstrated a legally cognizable injury because they alleged
    that “the SCAT Act’s reallocation . . . indirectly deprived the
    Districts of water due to them in their subcontracts”
    (emphasis added)). Unlike the irrigation districts in
    Maricopa-Stanfield, APAC’s members cannot point to an
    entitlement in a direct contract with an agency of the United
    States. And, contrary to the majority’s suggestion otherwise,
    neither Central Arizona nor Maricopa-Stanfield stand for the
    proposition that a downstream retail customer can establish
    an injury in fact.
    “It is . . . a fundamental restriction on our authority that in
    the ordinary course, a litigant must assert his or her own legal
    rights and interests, and cannot rest a claim to relief on the
    legal rights or interests of third parties.” Hollingsworth v.
    Perry, 570 U.S. ___, ___, 
    133 S. Ct. 2653
    , 2663 (2013)
    (emphasis added) (internal quotation marks and alteration
    omitted). APAC attempts here to assert the COUs’ statutory
    and contractual rights, where APAC’s members lack their
    own. This Court has never found standing under such
    APAC V. BPA                          73
    circumstances. I would not extend standing here and would
    hold that APAC has failed to demonstrate that its members
    suffered a legally cognizable injury.
    3
    Similarly, I would conclude that APAC also has failed to
    demonstrate causation and redressability by a substantial
    probability. “Traceability and redressability are linked
    causation requirements that look in different directions.”
    Donald Doernberg & C. Keith Wingate, Federal Courts,
    Federalism and Separation of Powers: Cases and Materials
    54 (2d ed. 2000). “Traceability” or causation is backward-
    looking and refers to whether a party’s injury arises from the
    alleged wrongful conduct. Id.; see also M-S-R Pub. Power
    Agency v. Bonneville Power Admin., 
    297 F.3d 833
    , 843 (9th
    Cir. 2002) (stating that to demonstrate causation, a party must
    establish that its injury is “fairly traceable to the challenged
    action of the [agency], and not the result of the independent
    action of some third party not before the court” (quoting
    Bennett v. Spear, 
    520 U.S. 154
    , 167 (1997)).
    “Redressability,” on the other hand, is forward-looking and
    considers whether the relief requested is likely to improve the
    situation for the party requesting it. Doernberg & Wingate,
    supra, at 54. Thus, APAC must demonstrate that a favorable
    decision here would create “a significant increase in the
    likelihood that [APAC’s members] would obtain relief that
    directly redresses the injury suffered.” Utah v. Evans,
    
    536 U.S. 452
    , 464 (2002). APAC fails to establish causation
    and redressability because of a fatal flaw common to both
    queries—the COUs independent decisions have a significant
    effect on APAC’s members’ alleged harm and prevent this
    Court from redressing that alleged harm.
    74                      APAC V. BPA
    When an alleged injury arises from government action
    relating to a third party, as here, “standing is not precluded,
    but it is ordinarily substantially more difficult to establish.”
    Lujan, 
    504 U.S. at 562
     (internal quotation marks omitted);
    Clapper v. Amnesty Int’l USA, 568 U.S. ___, ___, 
    133 S. Ct. 1138
    , 1150 (2013) (“We decline to abandon our usual
    reluctance to endorse standing theories that rest on
    speculation about the decisions of independent actors.”).
    Indeed, “it becomes the burden of the plaintiff to adduce facts
    showing that those choices have been or will be made in such
    manner as to produce causation and permit redressability of
    injury.” Lujan, 
    504 U.S. at 562
    . APAC has not met its
    burden here.
    BPA and the Joint IOUs contend that the lack of a direct
    contractual relationship between APAC and BPA renders
    APAC unable to establish causation and redressability. BPA
    argues that “any burden imposed on APAC’s members comes
    from the COUs that sell power to them,” rather than from
    BPA. Similarly, the Joint IOUs assert that APAC’s alleged
    injury will not be redressed by a favorable decision here
    because such redress would depend on the actions of third
    parties—the COUs with whom APAC contracts. In response,
    APAC argues, and the majority agrees, that the “pass-through
    nature” of its members’ contracts with the COUs prevents the
    COUs from acting as “independent” third parties. As such,
    APAC claims a favorable ruling here would redress its
    members’ harm by restoring their pre-Settlement rates.
    Contrary to the majority’s conclusion, the COUs’
    “independent decisions” do have a “significant effect” on
    APAC’s members’ alleged harm. See Allen, 
    468 U.S. at 759
    .
    As noted above, at least one member’s contract with its COU
    supplier allowed the COU to depart from the parties’
    APAC V. BPA                               75
    contractual arrangement by providing notice. Furthermore,
    as direct BPA customers, the COUs are statutorily entitled to
    enter into contracts with BPA, including contracts that settle
    rate disputes with BPA and waive their rights to BPA benefits
    to which they otherwise would be entitled under the NWPA.
    See PUD, 
    947 F.2d at 396
     (“[N]othing in the statute suggests
    that a non-Federal project cannot waive its right to
    compensation.”); Avista Corp. v. Bonneville Power Admin.,
    380 F. App’x 652, 654–55 (9th Cir. 2010) (holding that IOUs
    can waive their REP benefits because nothing in § 5
    “preclude[s] waiver of benefits”). It makes little sense that
    the statute would allow the COUs to waive such rights, but
    also allow the COUs’ customers to challenge such waivers.
    When entering into settlement agreements, parties often give
    up rights to which they otherwise would be entitled in
    exchange for predictability. This Settlement is a compromise
    by which the contracting parties agreed to give up the
    possibility, inter alia, of more REP benefits, lower rates, or
    more refunds—in exchange for greater certainty and lower
    litigation costs. That is precisely what APAC’s COU
    suppliers17 did here—they waived their rights to potentially
    higher reimbursements of past overcharges.18 The rights the
    17
    All of the Joint COUs entered into the REP-12 Settlement Agreement.
    “[S]ome of the Joint COUs” supply power to APAC. Thus, at least
    “some” of APAC’s COU suppliers agreed to the REP-12 Settlement
    Agreement and also intervened in this action to oppose APAC’s petition.
    18
    In their brief, the Joint COUs explain why they joined the REP-12
    Settlement and gave up potential rights in exchange for certainty:
    APAC also claims [the REP-12 Settlement] is
    unreasonable because all the risk is on the side of the
    COUs.     This assertion is not credible.          The
    COUs—who, unlike APAC, have a direct stake in the
    settlement—overwhelmingly supported and joined the
    76                           APAC V. BPA
    COUs gave up are valuable, but so is predictability. APAC’s
    members cannot now step into the COUs’ shoes to challenge
    the Settlement.19
    Settlement. No COU has challenged the Settlement
    here as being unreasonable or inconsistent with its
    statutory rights. In supporting the Settlement before
    BPA, the COUs explained the serious risks they faced
    in the absence of the Settlement and their belief that
    settlement was the only reasonable way for them to
    achieve, within a reasonable time frame, the certainty
    regarding the REP they need to conduct their business.
    19
    The parties rely on principles of contract law in their briefs. Although
    not explicitly adopting the term “intended beneficiary,” the parties appear
    to present differing views regarding whether APAC, on account of its
    pass-through contracts, is an intended third-party beneficiary of BPA’s
    agreements with the COUs. Since the parties rely on principles of contract
    law in making their arguments, contract law relating to third-party
    beneficiaries is instructive here. First, state law applies to a determination
    of whether APAC is a third-party beneficiary of the COUs’ contracts with
    BPA. See Snohomish Cnty. Pub. Util. Dist. No. 1 v. Pacificorp (SCPUD),
    
    745 F. Supp. 1581
    , 1584 (D. Or. 1990). In Oregon and Washington,
    courts have held that intent to include a third-party beneficiary in a
    contract must appear from the terms of the contract construed as a whole
    and in light of the circumstances in existence at the time the contract was
    entered into. See Aetna Cas. & Surety Co. v. Or. Health Scis. Univ.,
    
    773 P.2d 1320
    , rev. allowed 
    781 P.2d 1214
     (Or. Ct. App. 1989);
    Postlewait Constr., Inc. v. Great Am. Ins. Co., 
    720 P.2d 805
    , 806–07
    (Wash. 1986). The parties to a contract must intend that the promisor
    assume a direct obligation to the intended beneficiary. Postlewait,
    720 P.2d at 806. In the absence of this direct benefit, the third-party
    beneficiary is merely an “incidental” beneficiary that acquires no rights
    under the contract. Id. Failure to name the third-party beneficiary, while
    not dispositive, is a strong indication that the promisee did not intend to
    confer a benefit on that party. Nw. Airlines v. Crosetti Bros., 
    483 P.2d 70
    ,
    73 (Or. 1971).
    APAC V. BPA                                  77
    APAC is not the correct party to adjudicate the claims in
    this petition. “[T]he standing inquiry requires careful judicial
    examination of [the facts supporting standing] to ascertain
    whether the particular plaintiff is entitled to an adjudication
    of the particular claims asserted.” Allen, 
    468 U.S. at 752
    (emphasis added); see Hollingsworth, 570 U.S. at ___,
    
    133 S. Ct. at 2663
     (“It is . . . a fundamental restriction on our
    authority that in the ordinary course, a litigant must assert his
    or her own legal rights and interests, and cannot rest a claim
    to relief on the legal rights or interests of third parties.”
    (emphasis added) (internal quotation marks and alterations
    omitted)). APAC’s remedy, if any, lies with the COUs with
    which its members contract. APAC’s statement that “BPA’s
    preference customer utilities are fiduciaries for their
    customers who actually incurred costs resulting from BPA’s
    unlawful treatment of the REP costs pursuant to the 2007
    Decisions” only supports the conclusion that APAC’s remedy
    is not against BPA—which has no duty to APAC—but rather
    against the COUs, which (according to APAC) owe fiduciary
    duties to its members.
    Here, APAC has not argued or offered evidence that the COUs’
    contracts with BPA name APAC’s members as beneficiaries, nor is there
    any indication from the contract terms or circumstances that BPA and the
    COUs intended to confer rights on the COUs’ customers. At most, the
    statutory language indicates APAC members could be construed as
    incidental beneficiaries that acquire no enforceable rights. See SCPUD,
    745 F. Supp. at 1584 (holding a local utility district lacked standing to
    bring a declaratory relief action in a contract dispute between an IOU and
    a joint operating agency because the utility failed to demonstrate a
    cognizable injury or a personal stake in the contracts at issue; the fact that
    the local utility districts might “receive the benefit of lower rates due to
    [the IOUs] participation” in the contracts was not sufficient to confer
    third-party standing or to establish an injury in fact).
    78                     APAC V. BPA
    Moreover, APAC has not established that the perpetuation
    of APAC’s past harm is fairly traceable to BPA. APAC’s
    evidence demonstrates that the rates BPA charges its utilities
    pass through to the utilities’ customers, but does not
    demonstrate that any credits or refunds for past overcharges
    also pass from the utilities to APAC’s members. This is
    important because APAC’s alleged past harm arises from
    these overcharges and the perpetuation of this harm arises
    from the Settlement’s alleged failure to remedy this harm.
    Unlike the indirect customers in California Power Energy
    and PUD, APAC does not point to a statute that would entitle
    its members to such refunds. And, unlike the direct
    customers in Maricopa-Stanfield, it cannot rely on a
    contractual right with BPA that would entitle its members to
    such refunds. If the COUs are able to amend their contracts,
    retain these refunds, or account for them in a manner that
    would not directly lower APAC’s members’ rates, any action
    by this Court would not redress APAC’s harm. Given that at
    least one of APAC’s member’s supplier was able to alter the
    terms of the pass-through contract upon notice, APAC has not
    established by a substantial certainty that a favorable ruling
    here would provide its members with the relief they seek.
    APAC carries the burden of supporting each element of
    standing with admissible evidence and has failed to do so.
    I conclude that APAC has failed to establish standing
    under Article III of the United States Constitution because it
    has not demonstrated by a substantial probability that at least
    one of its members has a legally cognizable injury that is
    fairly traceable to BPA’s adoption of the REP-12 Settlement,
    or that granting this petition would redress its harms. For
    these reasons, I would hold that this Court lacks jurisdiction
    to reach the merits of APAC’s contentions.
    APAC V. BPA                     79
    CONCLUSION
    As I would conclude that APAC lacks standing, I would
    deny APAC’s petition for review.
    

Document Info

Docket Number: 17-56607

Filed Date: 10/28/2013

Precedential Status: Precedential

Modified Date: 10/30/2014

Authorities (50)

Utah v. Evans , 122 S. Ct. 2191 ( 2002 )

boyd-didrickson-and-marina-katelnikoff-beck-plaintiff-intervenors-v , 982 F.2d 1332 ( 1992 )

ronald-ray-smith-and-disabled-rights-action-committee-a-utah-non-profit , 358 F.3d 1097 ( 2004 )

Stormans, Inc. v. Selecky , 586 F.3d 1109 ( 2009 )

Valley Forge Christian College v. Americans United for ... , 102 S. Ct. 752 ( 1982 )

United States v. Mezzanatto , 115 S. Ct. 797 ( 1995 )

Portland General Electric Co. v. Bonneville Power ... , 501 F.3d 1009 ( 2007 )

Golden Northwest Aluminum, Inc. v. Bonneville Power ... , 501 F.3d 1037 ( 2007 )

peter-d-peterson-v-united-states-department-of-the-interior-four-cases , 899 F.2d 799 ( 1990 )

public-power-council-inc-v-bonneville-power-administration-portland , 442 F.3d 1204 ( 2006 )

public-utility-district-no-1-of-douglas-county-public-utility-district-no , 947 F.2d 386 ( 1991 )

util-l-rep-p-14081-96-cal-daily-op-serv-129-96-daily-journal , 73 F.3d 253 ( 1996 )

the-washington-utilities-and-transportation-commission-wutc-v-federal , 26 F.3d 935 ( 1994 )

m-s-r-public-power-agency-v-bonneville-power-administration-an-agency-of , 297 F.3d 833 ( 2002 )

confederated-tribes-of-the-umatilla-indian-reservation-nez-perce-tribe , 342 F.3d 924 ( 2003 )

pershing-park-villas-homeowners-association-an-unincorporated-and , 219 F.3d 895 ( 2000 )

Chevron U. S. A. Inc. v. Natural Resources Defense Council, ... , 104 S. Ct. 2778 ( 1984 )

DaimlerChrysler Corp. v. Cuno , 126 S. Ct. 1854 ( 2006 )

Hunt v. Washington State Apple Advertising Commission , 97 S. Ct. 2434 ( 1977 )

The Cetacean Community v. George W. Bush, President of the ... , 386 F.3d 1169 ( 2004 )

View All Authorities »