Technica LLC Ex Rel. United States v. Carolina Casualty Insurance , 749 F.3d 1149 ( 2014 )


Menu:
  •                      FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    TECHNICA LLC, for the use and                      No. 12-56539
    benefit of: United States of America,
    Plaintiff-Appellant,               D.C. No.
    3:08-cv-01673-
    v.                               H-KSC
    CAROLINA CASUALTY INSURANCE
    COMPANY; CANDELARIA                                  OPINION
    CORPORATION; OTAY GROUP, INC.;
    DOES 1 THROUGH 10, INCLUSIVE,
    Defendants-Appellees.
    Appeal from the United States District Court
    for the Southern District of California
    Marilyn L. Huff, District Judge, Presiding
    Argued and Submitted
    October 11, 2013—Pasadena, California
    Filed April 29, 2014
    Before: Richard A. Paez and Andrew D. Hurwitz, Circuit
    Judges, and Ralph R. Erickson, Chief District Judge.*
    Opinion by Judge Paez
    *
    The Honorable Ralph R. Erickson, Chief District Judge for the U.S.
    District Court for the District of North Dakota, sitting by designation.
    2         TECHNICA LLC V. CAROLINA CAS. INS. CO.
    SUMMARY**
    Miller Act
    Reversing the district court’s summary judgment, the
    panel held that a subcontractor’s lack of a California
    contractor’s license did not bar it from pursuing a Miller Act
    claim for payments due on a subcontract for work on a
    federal construction project in California.
    Agreeing with the Eighth and Tenth Circuits, and
    distinguishing cases dealing with the substantive law of
    contracts, the panel held that rights and remedies under the
    Miller Act may not be conditioned by state law. Therefore,
    the limitation in California Business and Professions Code
    § 7031(a) on the right of a non-licensed contractor to
    maintain an action for collection of unpaid services does not
    apply to an action under the Miller Act.
    COUNSEL
    J. Scott Scheper (argued), Jack R. Leer; Seltzer Caplan
    McMahon Vitek, San Diego, California, for Plaintiff-
    Appellant Technica, LLC.
    Robert J. Berens (argued), Adam D. Melton; Lewis Brisbois
    Bisgaard & Smith, LLP, Phoenix, Arizona, for Defendants-
    Appellees Carolina Casualty Insurance Company, Candelaria
    Corporation and Otay Group, Inc.
    **
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    TECHNICA LLC V. CAROLINA CAS. INS. CO.              3
    OPINION
    PAEZ, Circuit Judge:
    In this Miller Act case, Technica, Inc. (“Technica”), a
    subcontractor on a federal construction project in California,
    appeals the grant of summary judgment to Candelaria
    Corporation (“Candelaria”), the prime contractor, and its
    surety Carolina Casualty Insurance Company (“CCIC”). See
    
    40 U.S.C. §§ 3131
    –3134. At issue is whether the district
    court erred in concluding that because Technica was not a
    licensed California contractor as required by California law,
    it is precluded from pursuing its Miller Act claim for
    payments due under the subcontract. Reviewing the grant of
    summary judgment de novo, we conclude that the absence of
    California licensure does not bar this suit, and therefore
    reverse. See McDonald v. Sun Oil Co., 
    548 F.3d 774
    , 778
    (9th Cir. 2008).
    I.
    This dispute stems from work performed in California
    on the ICE El Centro SPC - Perimeter Fence
    Replacement/Internal Devising Fence Replacement federal
    project (“Project”). Candelaria, the prime government
    contractor on the Project, provided a payment bond as
    required by the terms of the government contract and the
    Miller Act, and enlisted CCIC as its surety. In December
    2007, Candelaria entered into a subcontract with Otay Group,
    Inc. (“Otay”) to perform a portion of the work required under
    the prime contract. Shortly thereafter, Otay contracted with
    Technica to act as a sub-subcontractor on the Project.
    4         TECHNICA LLC V. CAROLINA CAS. INS. CO.
    Between late 2007 and June 2008, Technica provided
    $893,697.77 worth of labor, material and services to the
    Project. Technica submitted invoices to Otay and Candelaria
    for this work, but received only partial payments totaling
    $287,861.81. In June 2008, Candelaria terminated Otay’s
    subcontract. In September 2008, Technica filed a complaint
    in district court invoking its rights under the Miller Act to
    recover outstanding amounts owed on the subcontract against
    the payment bond.
    Candelaria and CCIC filed a motion for summary
    judgment, arguing that California’s contractor licensing
    statute, California Business and Professions Code § 7031(a),1
    provided a complete defense to Technica’s Miller Act claim.
    Section 7031(a) precludes any contractor from maintaining an
    action for collection of compensation for services if the
    contractor was not a licensed contractor during the
    performance of the contract. Candelaria and CCIC asserted
    that because Technica did not hold a California contractor’s
    license and did not fit within the “labor provider” exception
    to the licensing requirement it could not maintain its Miller
    1
    Section 7031(a) provides: “Except as provided in subdivision (e), no
    person engaged in the business or acting in the capacity of a contractor,
    may bring or maintain any action, or recover in law or equity in any
    action, in any court of this state for the collection of compensation for the
    performance of any act or contract where a license is required by this
    chapter without alleging that he or she was a duly licensed contractor at
    all times during the performance of that act or contract, regardless of the
    merits of the cause of action brought by the person . . . .” See also
    Hydrotech Sys, Ltd. v. Oasis Waterpark, 
    803 P.2d 370
     (Cal. 1991) (en
    banc).
    TECHNICA LLC V. CAROLINA CAS. INS. CO.                       5
    Act claim.2 See Cal. Labor Pool, Inc. v. Westway
    Contractors, Inc., 
    61 Cal. Rptr. 2d 715
     (Ct. App. 1997). The
    district court, finding there was no dispute that Technica
    lacked a California contractor’s license, concluded that
    California’s contractor licensing law applied and that,
    because the labor provider exception did not apply, Technica
    could not pursue its Miller Act claim.
    This appeal timely followed.3
    II.
    The Miller Act is the modern-day remedy to the historical
    dilemma faced by contractors and materialmen denied
    compensation in federal construction projects. The common
    law doctrine of sovereign immunity prevented liens against
    property of the federal government, and federal statutes only
    allowed those in privity of contract with the government to
    sue to enforce contractual rights. See 
    28 U.S.C. § 1491
    ;
    United States v. Munsey Trust Co., 
    332 U.S. 234
    , 241 (1947).
    Recognizing that other parties who contribute to the
    performance of a federal construction contract, including
    subcontractors, should in some way be assured payment of
    their claims, Congress enacted the Heard Act in 1894. See
    Act of August 13, 1894, ch. 280, 
    28 Stat. 278
    , amended by
    2
    Candelaria and CCIC also alleged that Technica’s Miller Act claim
    was barred because Technica acted as a financer of Otay’s labor costs and
    financers of labor may not pursue Miller Act claims. The district court did
    not address this argument in its summary judgment ruling and it was not
    raised by the parties on appeal. Accordingly, it is waived. See Brookfield
    Commc’ns Inc. v. W. Coast Entm’t Corp., 
    174 F.3d 1036
    , 1046 n.7 (9th
    Cir. 1999).
    3
    We have jurisdiction pursuant to 
    28 U.S.C. § 1291
    .
    6       TECHNICA LLC V. CAROLINA CAS. INS. CO.
    Pub. L. No. 58-100, ch. 778, 
    33 Stat. 811
    , and Pub. L. No.
    61-476, ch. 238, 
    36 Stat. 1167
    . In 1935, the Heard Act was
    repealed and the Miller Act enacted in its place. See Pub. L.
    No. 74-321, ch. 642, 
    49 Stat. 793
     (codified as amended at
    
    40 U.S.C. §§ 3131
    –3134).
    The Miller Act requires a general contractor on a federal
    construction project to furnish a payment bond “for the
    protection of all persons supplying labor and material in
    carrying out the work provided for in the contract.”
    
    40 U.S.C. § 3133
    (b)(2). It “represents a congressional effort
    to protect persons supplying labor and material for the
    construction of federal public buildings in lieu of the
    protections they might receive under state statutes with
    respect to the construction of nonfederal buildings.” Mai
    Steel Serv. Inc. v. Blake Constr. Co., 
    981 F.2d 414
    , 416–17
    (9th Cir. 1992) (quoting United States ex rel. Sherman v.
    Carter, 
    353 U.S. 210
    , 216 (1957)) (internal quotation marks
    omitted). Under the Miller Act, any person who has
    furnished labor or material in carrying out work on a federal
    construction project and
    [who] has not been paid in full within 90 days
    after the day on which the person did perform
    the last of labor . . . may bring a civil action
    on the payment bond for the amount unpaid at
    the time the civil action is brought and may
    prosecute the action to final execution and
    judgment for the amount due.
    
    40 U.S.C. § 3133
    (b)(1). The Miller Act explicitly extends to
    sub-subcontractors, like Technica, the right to file and
    prosecute an action against a prime contractor’s payment
    bond. See § 3133(b)(2) (“A person having a direct
    TECHNICA LLC V. CAROLINA CAS. INS. CO.                        7
    contractual relationship with a subcontractor but no
    contractual relationship, express or implied, with the
    contractor furnishing the payment bond may bring a civil
    action on the payment bond . . . .”). Because, the Miller Act
    provides Technica a federal cause of action, “the scope of the
    remedy as well as the substance of the rights created thereby
    is a matter of federal not state law.” F.D. Rich Co., Inc., v.
    United States ex rel. Indus. Lumber Co., 
    417 U.S. 116
    , 127
    (1974). The Miller Act is highly remedial in nature, and “is
    entitled to a liberal construction and application in order
    properly to effectuate the Congressional intent to protect
    those whose labor and materials go into public projects.”
    Sherman, 
    353 U.S. at 216
     (quoting Clifford F. MacEvoy Co.
    v. Calvin Tomkins Co., 
    322 U.S. 102
    , 107 (1944)) (internal
    quotation marks omitted).
    III.
    The question before us is whether California’s
    contractor’s licensing law restricts “the substance of the
    rights” afforded to Technica under the Miller Act. Although
    this is a matter of first impression for our circuit, the Supreme
    Court, and the Eighth and Tenth Circuits, have held that
    rights and remedies under the Miller Act may not be
    conditioned by state law. We conclude that their reasoning
    applies with equal force to this case.4
    4
    Because we conclude the text of the Miller Act forecloses any
    argument that complying with state contractor licensing requirements is
    a condition to maintaining a Miller Act claim, we find it unnecessary to
    conduct a preemption analysis. Accordingly, Candelaria and CCIC’s
    argument that California’s contractor licensing requirements are not
    preempted by the Federal Acquisition Regulations (“FARs”), 48 C.F.R.
    ch. 1, is irrelevant to the issue before us. Whether Technica’s right to
    recover against the payment bond is barred by section 7031(a) turns on the
    8        TECHNICA LLC V. CAROLINA CAS. INS. CO.
    In F.D. Rich, the Supreme Court relied upon the federal
    interest in the uniform application of law in determining that
    state laws cannot be used to provide an award of attorneys’
    fees to a Miller Act claimant where such a right is not
    provided by federal law. 
    417 U.S. at
    127–28. Reversing a
    ruling of this circuit, the Supreme Court held that, where
    there was no evidence of congressional intent to incorporate
    state law, the application of uniform federal law better served
    “[t]he reasonable expectations of [] potential litigants” under
    the Miller Act. 
    Id. at 127
    . In particular, the Court noted
    “[m]any federal contracts involve construction in more than
    one State, and often, as here, the parties to Miller Act
    litigation have little or no contact, other than the contract
    itself, with the State in which the federal project is located.”
    
    Id.
    Following F.D. Rich, the Tenth Circuit concluded that
    state statutes cannot condition the rights available to a
    subcontractor under the Miller Act because state laws “do not
    condition or otherwise proscribe in any manner the right of
    the United States to institute and maintain in the United
    States Court for the use and benefit of a subcontractor an
    action against the prime contractor . . . .” Hoeppner Constr.
    Co. v. United States ex rel. E.L. Mangum, 
    287 F.2d 108
    , 110
    (10th Cir. 1960). In Hoeppner, the Tenth Circuit considered
    a proffered defense to a Miller Act claim based on Colorado’s
    requirement that a partnership record an affidavit with a
    county recorder’s office identifying the names of the
    individual partners. 
    Id.
     State law further provided that where
    the partnership failed to file such an affidavit, it could not
    maintain an action to collect debts. 
    Id.
     Invoking this
    rights afforded under the Miller Act and not whether the licensing
    requirements are preempted by the FARs.
    TECHNICA LLC V. CAROLINA CAS. INS. CO.                 9
    procedural requirement, the surety argued that the United
    States could not maintain an action under the Miller Act on
    behalf of a subcontractor who had failed to file the affidavit.
    
    Id.
     The court rejected this defense, holding that the right to
    maintain an action under the Miller Act “does not have its
    source in the law of Colorado.” 
    Id.
     Accordingly, the state
    law filing requirements could not be used to limit
    subcontractor rights under the Miller Act. 
    Id.
    Similarly, in Aetna Casualty & Surety Co. v. United
    States ex rel. R.J. Studer & Sons, the Eighth Circuit held that
    a South Dakota statute forbidding enforcement of a contract
    on behalf of a foreign corporation could not be used to defeat
    a Miller Act claim by a joint venture that included a Montana
    corporation. 
    365 F.2d 997
    , 999–1000 (8th Cir. 1966).
    Acknowledging that the Miller Act “is highly remedial in
    nature,” the court held that state statutes which restrict the
    rights of noncomplying parties “should not and will not be
    enforced by the federal courts in Miller Act cases.” 
    Id. at 1000
    ; see also United States ex rel. James F. O’Neil Co. v.
    Malan Constr. Corp., 
    168 F. Supp. 255
    , 258–59 (E.D. Tenn.
    1958) (holding that application of a state law defense
    requiring a corporation to qualify itself in Tennessee “would
    be futile, and would defeat the purpose of the [Miller] Act, if,
    having created the right to a surety bond . . . the right so given
    were simultaneously nullified by application of the state
    law”).
    Although Candelaria and CCIC urge us to consider case
    law in this circuit that applies state law in Miller Act claims,
    these cases are distinguishable because they deal with the
    application of the substantive law of contracts and not the
    rights established by the Miller Act. For instance, in
    Continental Casualty Co. v. Schaefer, we held that
    10      TECHNICA LLC V. CAROLINA CAS. INS. CO.
    Washington’s substantive law of contracts applied to an issue
    that “does not involve construction o[r] application of a
    federal statute,” such as whether the parties had created an
    implied agreement in their contract to cover payment for
    additional work. 
    173 F.2d 5
    , 7 (9th Cir. 1949); see also
    United States ex rel. Palmer Constr., Inc. v. Cal State Elec.,
    Inc., 
    940 F.2d 1260
    , 1261 (9th Cir. 1991) (explaining that
    state law controls the interpretation of subcontracts in a
    Miller Act case); United States ex rel. Leno v. Summit Constr.
    Co., 
    892 F.2d 788
    , 791–92 (9th Cir. 1989) (holding that while
    state law controls the calculation of damages under a Miller
    Act subcontract, claims arising under the Miller Act are not
    entitled to attorneys’ fees under state law).
    We therefore hold that the limitation in California
    Business and Professions Code § 7031(a) on the right of a
    non-licensed contractor to maintain an action for collection of
    unpaid services does not apply to an action under the Miller
    Act. “Manifestly the federal rights affording relief . . . under
    a federally declared standard could be defeated if states were
    permitted to have the final say as to what defenses could and
    could not be properly interposed to suits under the Act.” Dice
    v. Akron, Canton & Youngstown R.R. Co., 
    342 U.S. 359
    , 361
    (1952) (addressing state law defenses to claims under the
    Federal Employers’ Liability Act). Like the state restrictions
    on a foreign corporation’s right to maintain a suit at issue in
    Aetna Casualty & Surety Co., application of California’s
    licensing statute as a defense to a Miller Act claim would, at
    best, condition the rights of a subcontractor on the procedural
    requirements of state law, and, at worst, result in the
    nullification of those rights entirely. Neither result is in
    accordance with the remedial purposes of the Miller Act.
    TECHNICA LLC V. CAROLINA CAS. INS. CO.               11
    Moreover, as the Supreme Court has held, enforcement of
    state licensing requirements against Miller Act claims would
    wreak havoc on the uniform application of the Miller Act.
    See F.D. Rich, 
    417 U.S. at 127
    . Federal subcontractors
    routinely bid on projects throughout the country and often
    perform contracts that span multiple states. Requiring them
    to comply with contractor licensing requirements in any given
    state in which they may work is contrary to the intent of
    Congress in enacting the Miller Act, which was meant to
    reduce the substantive and procedural hurdles placed on
    federal subcontractors, labor providers and materialmen in
    seeking payment or wages denied to them. See Sherman,
    
    353 U.S. at 216
    .
    IV.
    For the above reasons, we reverse the district court’s grant
    of summary judgment to Candelaria and CCIC. Because the
    California licensing requirement is not a defense to a claim
    under the Miller Act, we need not address whether Technica
    falls within the labor provider exception to the statute. See
    Cal. Labor Pool, Inc., 
    61 Cal. Rptr. 2d 751
    .
    REVERSED AND REMANDED.