Western Watersheds Project v. Bob Abbey , 719 F.3d 1035 ( 2013 )


Menu:
  •                  FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    WESTERN WATERSHEDS PROJECT , a            No. 11-35705
    nonprofit organization; GLENN
    MONAHAN , in his individual                  D.C. No.
    capacity and as a member of               4:10-cv-00004-
    Western Watersheds Project; NANCY              SEH
    SCHULTZ, in her individual capacity
    and as a member of Western
    Watersheds Project,                         OPINION
    Plaintiffs - Appellants,
    v.
    BOB ABBEY , in his official capacity
    as Director of the Bureau of Land
    Management, an agency of the
    United States; GARY SLAGEL, in his
    official capacity as Manager of the
    Upper Missouri River Breaks
    National Monument; GENE R.
    TERLAND , in his official capacity as
    BLM Montana State Director; GARY
    L. BENES, in his official capacity as
    Field Manager of BLM’s Lewistown
    Field Office; BUREAU OF LAND
    MANAGEMENT , an agency of the
    United States Department of Interior,
    Defendants - Appellees,
    2     WESTERN WATERSHEDS PROJECT V . ABBEY
    and
    BLAINE COUNTY ; CHOUTEAU
    COUNTY ; FERGUS COUNTY ;
    MISSOURI RIVER STEWARDS;
    PHILLIPS COUNTY ,
    Intervenor-Defendants -
    Appellees.
    Appeal from the United States District Court
    for the District of Montana
    Sam E. Haddon, District Judge, Presiding
    Argued and Submitted
    February 5, 2013—Seattle, Washington
    Filed June 7, 2013
    Before: Raymond C. Fisher, Ronald M. Gould,
    and Richard A. Paez, Circuit Judges.
    Opinion by Judge Gould
    WESTERN WATERSHEDS PROJECT V . ABBEY                         3
    SUMMARY*
    Environmental Law
    The panel affirmed in part and reversed in part the district
    court’s summary judgment in favor of United States agencies
    and officials in an action challenging the Bureau of Land
    Management’s management of grazing within the Upper
    Missouri River Breaks National Monument in Montana.
    The panel held that BLM reasonably interpreted
    Proclamation No. 7398, 
    3 C.F.R. § 7398
     (2002), to not
    require programmatic changes to grazing management
    policies in the Breaks Monument Resource Management
    Plan, and the Breaks Monument Environmental Impact
    Statement complied with the National Environmental Policy
    Act by taking a hard and careful look at grazing impacts.
    The panel also held that the Environmental Assessment
    for the Woodhawk Allotment, located within the Monument,
    violated the National Environmental Policy Act by not
    considering a reasonable range of alternatives that included
    a no- or reduced-grazing option. The panel remanded for the
    district court to enter an appropriate order requiring BLM to
    remedy the deficiencies in the Environmental Assessment for
    the Woodhawk Allotment or to prepare a more detailed
    Environmental Impact Statement.
    *
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    4       WESTERN WATERSHEDS PROJECT V . ABBEY
    COUNSEL
    Thomas J. Woodbury, Western Watersheds Project, Missoula,
    Montana, for Plaintiffs-Appellants.
    Robert Parke Stockman (argued), Ignacia S. Moreno,
    Assistant Attorney General, Tyler Welti, Rachel K. Bowen,
    and David C. Shilton, United States Department of Justice,
    Environment & Natural Resources Division, Washington
    D.C.; Sarah Shattuck and Karan Dunnigan, Of Counsel,
    Office of the Solicitor General, United States Department of
    the Interior, Washington D.C., for Defendants-Appellees.
    Hertha L. Lund (argued), Lund Law, Bozeman, Montana;
    Steven J. Lechner and Jeffrey Wilson McCoy, Mountain
    States Legal Foundation, Lakewood, Colorado, for
    Intervenors-Appellees.
    OPINION
    GOULD, Circuit Judge:
    More than two-hundred years ago, the Upper Missouri
    River Breaks enchanted Lewis and Clark as they traveled
    westward through what is now north-central Montana.
    Proclamation No.7398, 
    3 C.F.R. § 7398
     (2002). The
    explorers marveled at the area’s “most romantic appearance,”
    with white sandstone bluffs that seemed “to rival the human
    art of masonry.” 
    Id.
     They admired the abundant wildlife and
    observed big-horn sheep, mule deer, elk, and antelope. 
    Id.
     In
    2001, President Clinton recognized the biological, historical,
    and cultural significance of the Breaks country by designating
    the area as the Upper Missouri River Breaks National
    WESTERN WATERSHEDS PROJECT V . ABBEY                5
    Monument (“Breaks Monument” or “Monument”). The
    Bureau of Land Management (“BLM”), an agency of the
    United States Department of the Interior, manages the
    Monument, an area of unparalleled scenic beauty, great
    geological and biological import, and special historical
    significance.
    Appellants Western Watersheds Project, Glenn Monahan,
    and Nancy Shultz (collectively “Western Watersheds”) argue
    that BLM’s management of grazing within the Breaks
    Monument violates the Federal Land Policy and Management
    Act of 1976 (“FLPMA”), 
    43 U.S.C. §§ 1701
    –1787;
    Proclamation No. 7398, 
    3 C.F.R. § 7398
     (2002); and the
    National Environmental Policy Act of 1969 (“NEPA”),
    
    42 U.S.C. §§ 4321
    –4347. Western Watersheds contends that
    BLM improperly interpreted the Proclamation to exclude
    programmatic grazing changes from the Breaks Monument
    Resource Management Plan (“Breaks Resource Plan”). It
    further argues that the Breaks Monument Environmental
    Impact Statement (“Breaks EIS”) and the site-specific
    Environmental Assessment (“EA”) for the Woodhawk
    Allotment violated NEPA by not adequately assessing the
    impacts of livestock grazing within the Monument.
    The district court granted summary judgment in favor of
    Appellees United States Department of the Interior, BLM,
    and named employees in their official capacities (collectively
    “BLM”).       Western Watersheds appealed.         We have
    jurisdiction to review this appeal under 
    28 U.S.C. § 1291
    .
    We affirm in part and reverse in part. We conclude (1) that
    BLM reasonably interpreted the Proclamation in developing
    the Breaks Resource Plan, (2) that the Breaks EIS complied
    with NEPA, and (3) that the EA for the Woodhawk Allotment
    6       WESTERN WATERSHEDS PROJECT V . ABBEY
    violated NEPA. We remand for further proceedings on the
    Woodhawk Allotment permit renewal.
    I
    President Clinton established the Breaks Monument by
    presidential proclamation pursuant to his authority under the
    Antiquities Act, 
    16 U.S.C. § 431
    . See 
    3 C.F.R. § 7398
    . The
    Breaks Monument comprises more than 375,000 acres of
    federal land in north-central Montana intermingled with
    nearly 120,000 acres of state, county, and private land. The
    Proclamation’s purpose is to protect various “objects” in the
    Breaks country that have biological, geological, or historical
    significance. 
    Id.
    The Breaks country remains remote and largely
    undeveloped, so “[m]any of the biological objects described
    in Lewis’ and Clark’s journals continue to make the
    monument their home.” 
    Id.
     These biological objects include
    essential habitat for sage-grouse and waterfowl, the Judith
    River and its tributaries that provide habitat for forty-eight
    species of fish, and a fully functioning cottonwood gallery
    forest ecosystem—one of only a few remaining in the
    Northern Plains. 
    Id.
    The Proclamation directs BLM to manage the Breaks
    Monument pursuant to applicable legal authorities and the
    Proclamation’s purposes and terms. 
    Id.
     These terms include
    provisions that either direct BLM to take a specific action or
    limit the Proclamation’s impact. 
    Id.
     One of these provisions,
    and a key one affecting this lawsuit, states that the “[l]aws,
    regulations, and policies followed by the [BLM] in issuing
    and administering grazing permits or leases on all lands under
    its jurisdiction shall continue to apply with regard to the lands
    WESTERN WATERSHEDS PROJECT V . ABBEY                7
    in the monument.” 
    Id.
     Western Watersheds challenges
    BLM’s interpretation of that grazing provision.
    BLM concluded that the grazing provision authorized it
    to follow existing laws, regulations, and policies governing
    grazing to “protect the objects of the Monument and
    rangeland resources.” This interpretation limited the scope of
    both the Breaks Resource Plan, which BLM created to guide
    the agency’s management of the Breaks Monument, and the
    Breaks EIS, which assessed environmental impacts of the
    Breaks Resource Plan. The Breaks EIS considered six
    alternatives, but none proposed programmatic changes to
    grazing management because, importantly, BLM interpreted
    the Proclamation not to require such changes. The Breaks
    Resource Plan and Breaks EIS adopted BLM’s interpretation
    and explained that existing laws, regulations, and policies
    would continue to apply in the Monument. These laws and
    regulations include the Lewistown District Standards for
    Rangeland Health and Guidelines for Livestock Grazing
    Management (Lewistown Standards).
    Western Watersheds contends that the Lewiston
    Standards are inadequate to protect Monument objects and
    that BLM erred by relying on the Lewiston Standards in the
    Breaks Resource Plan, the Breaks EIS, and the EA for the
    Woodhawk Allotment. This contention moves us toward
    center stage in the drama of this dispute involving grazing
    within the Breaks area protected by the Proclamation. We
    must consider both BLM’s grazing policies, which may be
    continued under the Proclamation, and the needs of the
    Monument objects, some of which are in tension with BLM’s
    existing grazing policies.
    8       WESTERN WATERSHEDS PROJECT V . ABBEY
    The Lewistown Standards were created in 1997 as part of
    the regional Montana/Dakotas Standards for Rangeland
    Health and Guidelines for Livestock Grazing Management.
    BLM regulations mandate the creation of regional or
    statewide rangeland standards consistent with the
    fundamentals of rangeland health set forth in those
    regulations. See 
    43 C.F.R. §§ 4180.1
    , 4180.2. These
    regulations also allow for localized standards and guidelines,
    like those developed for the Lewistown District, “to address
    local ecosystems and management practices.” 
    43 C.F.R. § 4180.2
    (b). The Central Montana Resource Advisory
    Council participated in developing the Lewistown Standards.
    The Lewistown Standards set five standards and fourteen
    guidelines. The “[s]tandards are statements of physical and
    biological condition or degree of function required for healthy
    sustainable rangelands.” Standards one and two adopt a
    proper-functioning-condition model to determine upland,
    riparian, and wetland health. These standards require soil
    stabilization, adequate vegetation, and a rich biotic
    community. The guidelines “are preferred or advisable
    approaches to ensure that standards can be met or that
    significant progress can be made toward meeting the
    standard(s).” All BLM rangelands in the Lewistown District
    must achieve the standards or make measurable progress
    toward them. The Lewistown Standards are implemented
    through a watershed planning process that identifies
    watershed plan areas by grouping grazing allotments that
    have similar resource values and concerns. Generally, BLM
    issues ten-year grazing permits for these allotments, and each
    permit renewal must comply with NEPA.
    The Woodhawk Allotment, located within the Monument,
    is governed by the watershed planning process and the
    WESTERN WATERSHEDS PROJECT V . ABBEY                9
    Lewistown Standards. When the ten-year grazing permit for
    the Allotment expired on December 31, 2008, BLM proposed
    renewing the permit for another ten-year period. BLM then
    conducted an environmental assessment to determine the
    environmental impact of renewing the permit. With this
    assessment, BLM released a finding of no significant impact
    because (1) the permit renewal would facilitate management
    changes to improve riparian and water quality conditions and
    (2) it would not impact wildlife, air quality, or cultural
    resources. The EA considered four alternatives in detail: one
    no-action alternative, which would implement the same
    management practices as the previous permit, and three
    action alternatives that proposed different management
    practices for the Allotment. Also, the EA considered but did
    not analyze in detail alternatives that would reduce or
    eliminate grazing. These reduced-grazing alternatives were
    eliminated because BLM determined that they did not meet
    the purpose of the proposed permit renewal. Moreover,
    because it had considered a no-grazing alternative in the 1979
    Missouri Breaks Grazing Environmental Statement, BLM
    found it unnecessary to consider such an option for the
    Woodhawk Allotment. Western Watersheds challenges both
    the BLM’s finding of no significant impact and the range of
    alternatives considered in the Woodhawk Allotment EA.
    Western Watersheds’s underlying concern is that the
    Breaks Resource Plan, the Breaks EIS, and the EA for the
    Woodhawk Allotment ignore the detrimental impacts of
    livestock grazing on Monument objects, especially riparian
    areas, cottonwood gallery forest ecosystems, and sage-grouse
    habitat. Livestock have grazed in the Breaks Monument area
    since the late 1800s. BLM acknowledges that livestock
    grazing can significantly affect the protected biological
    objects of the Monument. Overgrazing reduces habitat
    10        WESTERN WATERSHEDS PROJECT V . ABBEY
    quality for the greater sage-grouse, which can cause increased
    predation on nests or nest desertion. In riparian areas, grazing
    degrades water quality, affecting fish and other aquatic
    species. BLM studies have found hot-season grazing to be a
    significant cause of the lack of cottonwood and willow
    regeneration along the Missouri River.
    On November 20, 2009, Western Watersheds filed suit in
    the U.S. District Court for the District of Montana
    challenging the Breaks Resource Plan, the Breaks EIS, and
    the EA for the Woodhawk Allotment. This case was
    consolidated with two other cases challenging the Breaks
    Resource Plan and EIS.1 On August 9, 2011, the district court
    denied Western Watersheds’s motion for summary judgment
    and granted BLM’s motion for summary judgment. In re
    Montana Wilderness Ass'n, 
    807 F. Supp. 2d 990
    , 1005 (D.
    Mont. 2011). The district court found reasonable BLM’s
    interpretation that the Proclamation let it manage the Breaks
    Monument for multiple-use so long as Monument objects
    were adequately protected. The district court also determined
    that the Breaks Resource Plan adequately protected
    Monument objects and did not violate FLPMA. Rejecting
    Western Watersheds’s NEPA claims, the district court
    concluded that BLM took a “hard look” at grazing impacts in
    the Breaks EIS and did not err by excluding from
    consideration programmatic changes to grazing management.
    The district court also determined that the EA complied with
    NEPA.
    1
    Although the district court issued one decision for all three cases, the
    parties appealed separately. The two other cases, Montana Wilderness
    Association v. Terland, 11-35818, and The Wilderness Society v. Bureau
    of Land Management, 11-35821, were consolidated on appeal and heard
    by this panel on the same day as this case.
    WESTERN WATERSHEDS PROJECT V . ABBEY                11
    II
    “We review de novo the district court’s grant of summary
    judgment.” Ocean Advocates v. U.S. Army Corps of Eng’rs,
    
    402 F.3d 846
    , 858 (9th Cir. 2004). The Administrative
    Procedure Act (“APA”) governs our review of BLM’s
    compliance with NEPA and FLPMA. See Ctr. for Biological
    Diversity v. U.S. Dep’t of Interior, 
    623 F.3d 633
    , 641 (9th
    Cir. 2010). Under the APA, we may set aside BLM’s
    decision only if it is “arbitrary, capricious, an abuse of
    discretion, or otherwise not in accordance with law.”
    Ecology Ctr. v. Castaneda, 
    574 F.3d 652
    , 656 (9th Cir. 2009)
    (quoting 
    5 U.S.C. § 706
    (2)(A)). This deferential standard
    requires us to “ensure that the agency considered the relevant
    factors and articulated a rational connection between the facts
    found and the choices made.” Greater Yellowstone Coal., Inc.
    v. Servheen, 
    665 F.3d 1015
    , 1023 (9th Cir. 2011) (quoting
    Nw. Ecosystem Alliance v. U.S. Fish & Wildlife Serv.,
    
    475 F.3d 1136
    , 1140 (9th Cir. 2007)). But it does not allow
    us “to substitute our judgment for that of the agency.” 
    Id.
    12        WESTERN WATERSHEDS PROJECT V . ABBEY
    III
    We proceed to the merits.2 Western Watersheds contends
    that BLM’s interpretation of the Proclamation is illogical and
    violates FLPMA and the Proclamation by unreasonably
    elevating multiple-use principles above protection of
    Monument objects. BLM responds that its interpretation is
    2
    On appeal, Intervenors-Appellees’ moved to strike portions of W estern
    W atersheds’s excerpts of record and references to those documents in the
    opening brief. The district court had refused to consider this evidence,
    first by denying W estern W atershed’s motion to compel supplementation
    of the administrative record and second by granting BLM’s motion to
    strike the extra-record evidence submitted by W estern W atersheds. W e
    review a district court’s ruling on a motion to strike for abuse of
    discretion. El Pollo Loco, Inc. v. Hashim, 
    316 F.3d 1032
    , 1038 (9th Cir.
    2003). W estern W atersheds raised the issue of the excluded evidence in
    a two-sentence footnote to the facts section of their opening brief. Parties
    must clearly articulate in their opening brief any issues that they intend to
    raise on appeal. Christian Legal Soc’y Chapter of U niv. of Cal. v. Wu,
    
    626 F.3d 483
    , 485 (9th Cir. 2010) (order). W estern Watershed’s minimal
    discussion of the district court’s orders in a footnote does not meet this
    standard. See 
    id.
     By not properly raising the issue in its opening brief,
    W estern W atersheds waived any challenge to these district court orders.
    See Smith v. Marsh, 
    194 F.3d 1045
    , 1052 (9th Cir. 1999). W e also agree
    with the district court that BLM did not consider the challenged evidence
    in developing the Breaks Resource Plan, the Breaks EIS, or the EA for the
    W oodhawk Allotment, and that the evidence did not meet any exception
    for supplementing the record. See Sw. Ctr. for Biological Diversity v. U.S.
    Forest Serv., 
    100 F.3d 1443
    , 1450 (9th Cir. 1996). W e therefore grant the
    motion to strike the extra-record evidence submitted by W estern
    W atersheds and any reference to this evidence in W estern W atersheds’s
    opening and reply briefs. Moreover, we decline to take judicial notice of
    these documents, as urged by W estern Watersheds, because the documents
    contain observations and conclusions that are not “generally known” or
    “accurately and readily determined from sources whose accuracy cannot
    reasonably be questioned.” Fed. R. Evid. 201(b).
    WESTERN WATERSHEDS PROJECT V . ABBEY                         13
    not unreasonable in light of the plain language and structure
    of the Proclamation. We agree.
    “FLPMA requires that BLM, under the Secretary of the
    Interior, ‘develop, maintain, and[,] when appropriate, revise
    land use plans’ to ensure that land management be conducted
    ‘on the basis of multiple use and sustained yield.’” Klamath
    Siskiyou Wildlands Ctr. v. Boody, 
    468 F.3d 549
    , 555 (9th Cir.
    2006) (quoting 
    43 U.S.C. §§ 1701
    (a)(7), 1712(a)). This
    multiple-use-and-sustainable-yield mandate guides BLM’s
    management of public lands “except that where a tract of
    such public land has been dedicated to specific uses
    according to any other provisions of law it shall be managed
    in accordance with such law.” 
    43 U.S.C. § 1732
    (a). Under
    this provision, BLM must manage the Breaks Monument in
    compliance with the terms of the Proclamation. Id.3
    We have previously applied “great deference” to an
    agency’s interpretation of an executive order charged to its
    administration. Kester v. Campbell, 
    652 F.2d 13
    , 15 (9th Cir.
    1981); see also Am. Fed’n of Gov’t Emps. v. Fed. Labor
    Relations Auth., 
    204 F.3d 1272
    , 1274–75 (9th Cir. 2000). We
    explained that an agency’s interpretation must be reasonable,
    but “need not be the only reasonable interpretation.” Kester,
    
    652 F.2d at 16
    . To determine reasonableness, we adopted the
    standard applied for reviewing an agency’s interpretation of
    its own regulations. 
    Id.
     at 15–16. Under that standard, an
    agency interpretation is reasonable “unless it is plainly
    3
    Because § 1732(a) incorporates the Proclamation’s terms, we need not
    consider whether the Proclamation itself is subject to judicial review. See
    City of Carmel-By-The-Sea v. U.S. Dep’t of Transp., 
    123 F.3d 1142
    , 1166
    (9th Cir. 1997) (determining whether Executive Orders were subject to
    judicial review).
    14      WESTERN WATERSHEDS PROJECT V . ABBEY
    erroneous or inconsistent with the (order).” Id. at 16 (quoting
    United States v. Larionoff, 
    431 U.S. 864
    , 872 (1977)). We
    similarly apply that deferential standard to an agency’s
    interpretation of a presidential proclamation it administers.
    We review the BLM’s interpretation to determine whether it
    is consistent with the Proclamation’s language and purpose.
    See 
    id.
    BLM’s interpretation is reasonable and consistent with
    the plain language of the Proclamation. The Proclamation
    recites that “[l]aws, regulations, and policies followed by the
    [BLM] in issuing and administering grazing permits or leases
    on all lands under its jurisdiction shall continue to apply with
    regard to the lands in the monument.” 
    3 C.F.R. § 7398
    .
    BLM interpreted this language to mean that the “Monument
    designation in itself d[id] not mandate a need for an
    adjustment of forage allocated to livestock.” Based on this
    interpretation, BLM concluded that livestock grazing would
    continue to be governed (1) by existing laws and regulations
    that apply to grazing on all BLM public lands and (2) by the
    Lewistown Standards.           BLM then incorporated the
    Lewistown Standards into the Breaks Resource Plan to
    control grazing on the Monument.
    It was reasonable for BLM to conclude that the plain
    language of the Proclamation allowed it to continue to apply
    the Lewistown Standards within the Monument. Nothing in
    the Proclamation suggests that those Standards should not be
    considered a “policy” for the purposes of implementing the
    Proclamation. They were adopted before the Proclamation
    and are the main policy followed by BLM in administering
    grazing on its land. Moreover, although it requires the
    protection of Monument objects, the Proclamation does not
    foreclose consideration of multiple-use-and-sustainable-yield
    WESTERN WATERSHEDS PROJECT V . ABBEY                15
    principles for grazing management. These principles are part
    of the existing law that guides the “[BLM] in issuing and
    administering grazing permits.” 
    3 C.F.R. § 7398
    .
    The Proclamation’s structure also supports the conclusion
    that BLM’s interpretation “sensibly conforms to the purpose
    and wording of the [Proclamation].” Lezama-Garcia v.
    Holder, 
    666 F.3d 518
    , 525 (9th Cir. 2011). After discussing
    the various objects protected by the designation, the
    Proclamation sets forth several directives and limitations.
    The directives require the Secretary of the Interior to prepare
    a transportation plan and prohibit off-road use of motorized
    vehicles. 
    3 C.F.R. § 7398
    . The limitations restrict the
    designation’s impact on tribal rights and state management of
    fish and wildlife. 
    Id.
     The provision discussing grazing
    management falls within these limiting provisions. That
    placement supports BLM’s conclusion that President Clinton
    intended this to be a restrictive term that did not mandate
    changes to BLM’s grazing management so long as Monument
    objects were protected.
    BLM’s interpretation also reasonably reflects the views
    of then-Secretary of the Interior Bruce Babbitt and the
    Central Montana Resource Advisory Council expressed while
    promoting the area for designation. In response to a request
    from the Secretary, the Resource Advisory Council
    recommended to Secretary Babbitt that livestock grazing
    continue to be managed in accordance with the Lewistown
    Standards.     Secretary Babbitt approved, stating that
    “[c]onsistent with the implementation of th[e] [Lewistown]
    Standards and Guidelines, as well as other applicable law,
    grazing should continue and BLM’s mandates regarding
    livestock grazing should not be affected.”              This
    correspondence is consistent with BLM’s conclusion that the
    16      WESTERN WATERSHEDS PROJECT V . ABBEY
    grazing provision in the Proclamation contemplated a
    continuing application of the Lewistown Standards.
    Western Watersheds argues that BLM’s reading of the
    Proclamation is illogical because it ignores other laws,
    regulations, and policies followed by BLM in administering
    grazing. Western Watersheds contends that BLM ignored the
    Taylor Grazing Act, 
    43 U.S.C. §§ 315
    –315n; § 302(b) of
    FLPMA, 
    42 U.S.C. § 1732
    (b); BLM’s own regulations; and
    other BLM policies. But Western Watersheds does not show
    that the Lewistown Standards conflict with what is required
    by these authorities. Upon review, the contrary proves true.
    The Lewistown Standards aim to “maintain or improve
    resource conditions in upland and riparian habitats” to
    achieve “healthy sustainable rangelands.” This goal does not
    conflict with the Taylor Grazing Act’s purpose of stopping
    injury to public lands by preventing overgrazing, see Public
    Lands Council v. Babbitt, 
    529 U.S. 728
    , 733 (2000), or
    FLPMA’s directive that the Secretary of the Interior “take
    any action necessary to prevent unnecessary or undue
    degradation of the lands,” 
    43 U.S.C. § 1732
    (b). Moreover,
    we have determined that the “undue degradation” provision
    of § 1732(b) does not mandate specific BLM action but
    instead gives BLM “discretion to choose appropriate
    measures to address the environmental degradation.”
    Gardner v. U.S. Bureau of Land Mgmt., 
    638 F.3d 1217
    , 1222
    (9th Cir. 2011). We also find no conflict between the
    Lewistown Standards’ purpose and the National Landscape
    Conservation System’s intent to “conserve, protect, and
    restore nationally significant landscapes.” See 16 U.S.C.
    WESTERN WATERSHEDS PROJECT V . ABBEY                         17
    § 7202(a).4 We recognize that the grazing provision of the
    Proclamation may reflect a political compromise between
    conservation values and public use, but any such political
    matters are beyond the purview of the courts.
    Western Watersheds also contends that BLM’s
    interpretation does not reasonably protect Monument objects.
    They argue that by adopting the Lewistown Standards, the
    Breaks Resource Plan applies the same failed management
    strategies employed by BLM for thirty years to the detriment
    of sage-grouse habitat, cottonwood gallery forest ecosystems,
    and riparian areas. Western Watersheds is concerned with the
    Lewistown Standards’ use of the properly-functioning-
    condition standard instead of the potential-natural-community
    standard.5 To the extent that Western Watersheds seeks to
    challenge the Lewistown Standards or BLM’s past
    management decisions, those matters are not properly before
    us. This case is not about the legitimacy of the Lewiston
    4
    W estern W atersheds also contends that BLM’s interpretation conflicts
    with agency guidance and a draft resource management plan
    implementing a similar presidential proclamation. W e decline to review
    these documents. The agency guidance was issued after the Breaks
    Resource Plan and “may not be advanced as a new rationalization” for
    attacking BLM ’s interpretation. Sw. Ctr. for Biological Diversity,
    
    100 F.3d at 1450
    . Likewise, the district court refused to take judicial
    notice of the draft resource management plan because it constituted extra-
    record evidence, and we decline to review that evidence when that issue
    was waived on appeal. See supra note 2.
    5
    A potential-natural-community standard would require BLM to
    manage the allotment to achieve plant communities “representing the
    latest successional stage attainable on a specific, hydrological included
    surface.” According to W estern Watersheds, this is a more stringent
    management standard than the properly-functioning-condition model
    adopted in the Lewiston Standards.
    18      WESTERN WATERSHEDS PROJECT V . ABBEY
    Standards. It is about the legitimacy of BLM’s decision to
    incorporate those Standards into the Breaks Resource Plan.
    And any challenges to past BLM management decisions are
    likely barred by the six-year statute of limitations. See
    
    28 U.S.C. § 2401
    .
    Moreover, the record does not support Western
    Watersheds’s argument that Monument objects are threatened
    by BLM’s reliance on the Lewistown Standards. For
    example, the Breaks Resource Plan sets forth specific
    restrictions on grazing near sage-grouse leks during the
    breeding season and provides the option to adjust grazing
    seasons to protect habitat. It provides that grazing may be
    adjusted to achieve healthy vegetation goals or other
    rangeland standards in accordance with 
    43 C.F.R. § 4180.2
    (c). BLM could make changes to grazing levels as
    needed to restore the ecosystem to its properly functioning
    condition. See id.; 
    43 C.F.R. § 4110.3
    . It may be true that
    BLM could adopt more stringent standards for rangeland
    health, but it does not follow that BLM’s decision not to do
    so violates the Proclamation and FLPMA. We will not
    substitute our judgment for that of the agency. Lands Council
    v. McNair, 
    537 F.3d 981
    , 987 (9th Cir. 2008) (en banc),
    abrogated on other grounds by Winter v. Natural Res. Def.
    Council, Inc., 
    555 U.S. 7
     (2008). Absent evidence that
    BLM’s protection efforts are inconsistent with the
    Proclamation or contrary to other applicable law, we
    conclude that there is no error in its interpretation. See
    Kester, 
    652 F.2d at 16
    . The record supports BLM’s
    conclusion that adopting the Lewistown Standards in the
    Breaks Resource Plan gives adequate protection for
    Monument objects.
    WESTERN WATERSHEDS PROJECT V . ABBEY               19
    We conclude that BLM’s interpretation is consistent with
    the Proclamation’s plain language, structure, and history.
    BLM’s interpretation of the Proclamation was reasonable and
    the Breaks Resource Plan adequately protects Monument
    objects and does not offend FLPMA. BLM’s interpretation
    of the Proclamation does not mean that BLM lacks authority
    to reconsider its grazing programs in future actions if
    necessary to protect Monument objects. We hold only that it
    was reasonable for BLM to interpret the Proclamation not to
    require programmatic changes to its grazing practices in the
    Breaks Resource Plan.
    IV
    We next review whether the Breaks EIS complied with
    NEPA. Western Watersheds contends that the Breaks EIS
    violates NEPA in several ways: (1) it improperly determined
    that programmatic changes to BLM’s grazing policies were
    outside the scope of the Breaks EIS; (2) it did not consider a
    no-grazing or reduced-grazing alternative; and (3) it did not
    take a “hard look” at grazing impacts. We conclude that the
    Breaks EIS did not violate NEPA.
    “NEPA is a procedural statute intended to ensure
    environmentally informed decision-making by federal
    agencies.” Tillamook Cnty. v. U.S. Army Corps of Eng’rs,
    
    288 F.3d 1140
    , 1143 (9th Cir. 2002). It requires federal
    agencies to take a “hard look” at a proposed project’s
    environmental impacts, but it does not mandate particular
    results. 
    Id.
     Under NEPA, federal agencies must prepare an
    EIS before “taking ‘major Federal actions significantly
    affecting the quality’ of the environment.” Kern v. U.S.
    Bureau of Land Mgmt., 
    284 F.3d 1062
    , 1067 (9th Cir. 2002)
    (quoting 
    42 U.S.C. § 4332
    (2)(C)).         “By definition,
    20       WESTERN WATERSHEDS PROJECT V . ABBEY
    preparation of an RMP6 is a ‘major Federal action
    significantly affecting the quality of the human environment,’
    and so categorically requires preparation of an EIS.” 
    Id.
    (quoting 
    43 C.F.R. § 1601.0-6
    )). Council on Environmental
    Quality regulations require an EIS to state the purpose and
    need of the project and to consider a reasonable range of
    alternatives. 
    40 C.F.R. §§ 1502.13
    , 1502.14.
    A
    Western Watersheds argues that BLM erred by defining
    the scope and purpose of the Breaks EIS to exclude
    programmatic changes to grazing and by not considering an
    alternative that provided for grazing reduction or elimination.
    These arguments are related: a project’s scope and purpose
    define the reasonable range of alternatives that must be
    analyzed. See Westlands Water Dist. v. U.S. Dep’t of
    Interior, 
    376 F.3d 853
    , 868 (9th Cir. 2004).
    “The ‘scope’ of an EIS is defined as ‘the range of action,
    alternatives, and impacts to be considered in an [EIS].” Nw.
    Res. Info. Ctr., Inc. v. Nat’l Marine Fisheries Serv., 
    56 F.3d 1060
    , 1067 (9th Cir. 1995) (quoting 
    40 C.F.R. § 1508.25
    ). To
    determine the proper scope of an EIS, agencies should
    consider (a) connected, cumulative, and similar actions; (b)
    a no-action alternative, other reasonable alternatives, and
    mitigation measures; and (c) direct, indirect, and cumulative
    impacts. 
    40 C.F.R. § 1508.25
    . An agency has “considerable
    discretion” to define the scope of an EIS. Nw. Res. Info. Ctr.,
    Inc., 
    56 F.3d at 1067
     (quoting Thomas v. Peterson, 
    753 F.2d 754
    , 758 (9th Cir. 1985)).
    6
    The court in this statement by “RMP” is referring to a resource
    management plan.
    WESTERN WATERSHEDS PROJECT V . ABBEY                   21
    The scoping process for the Breaks EIS expressly
    excluded changes to grazing management based on BLM’s
    interpretation of the Proclamation. The EIS defined the
    Breaks Resource Plan’s purpose as:
    provid[ing] a comprehensive plan for
    managing the Monument and site-specific,
    detailed plans for managing transportation,
    visitor use, and oil and gas leases in a manner
    that protects the objects identified in the
    Proclamation, while recognizing valid
    existing rights. The Proclamation requires
    that BLM manage the Monument in order to
    implement the purpose of the Proclamation.
    This statement highlights specific projects mandated by the
    Proclamation, none of which required broad changes to
    BLM’s grazing practices.
    BLM did not violate NEPA by excluding changes to its
    grazing practices from the scope and purpose of the Breaks
    Resource Plan. Because the Breaks Resource Plan was
    developed to implement the Proclamation’s objectives, those
    objectives guide our analysis of the reasonableness of the
    purpose outlined in the EIS. See Westlands Water Dist.,
    
    376 F.3d at 866
     (“Where an action is taken pursuant to a
    specific statute, the statutory objectives of the project serve as
    a guide by which to determine the reasonableness of
    objectives outlined in an EIS.”). We have already determined
    that BLM’s interpretation of the Proclamation to allow the
    continued use of its grazing management was reasonable
    under FLPMA and the Proclamation. Based on that analysis,
    BLM also reasonably defined the scope and purpose of the
    22      WESTERN WATERSHEDS PROJECT V . ABBEY
    Breaks Resource Plan in the EIS. Western Watersheds does
    not show that NEPA mandates a different conclusion.
    It was also reasonable for the Breaks EIS to exclude
    detailed consideration of a no-grazing or reduced-grazing
    alternative. An EIS need not consider in detail an alternative
    that does not meet the purpose of the project. See City of
    Angoon v. Hodel, 
    803 F.2d 1016
    , 1021 (9th Cir. 1986)
    (“When the purpose is to accomplish one thing, it makes no
    sense to consider the alternative ways by which another thing
    might be achieved.”). But if an alternative is eliminated from
    detailed study, the agency must “briefly discuss [its] reasons”
    for doing so. 
    40 C.F.R. § 1502.14
    (a). Here, the EIS
    explained why it excluded from detailed review two
    alternatives that would reduce or eliminate grazing. The EIS
    considered but eliminated two reduced-grazing alternatives:
    (1) an alternative to identify lands as not available for
    livestock grazing and (2) an alternative to reduce or phase out
    livestock grazing. BLM rejected the first alternative because
    the Proclamation did “not require nor suggest” the need to
    restrict grazing and the existing Lewistown Standards could
    be used “to mitigate conflicts with Monument uses and
    values.” Similarly, BLM excluded the second alternative
    because there was “no documented need to reduce or phase
    out livestock grazing based on the Proclamation and
    Standards for Rangeland Health.” Given the scope and
    purpose of the Breaks Resource Plan, these explanations
    satisfy NEPA’s brief discussion requirement. See League of
    Wilderness Defenders – Blue Mountains Biodiversity Project
    v. U.S. Forest Serv., 
    689 F.3d 1060
    , 1072–73 (9th Cir. 2012)
    (concluding that the Forest Service did not err by eliminating
    from detailed review two alternatives that would not meet the
    purpose of the proposed action). We conclude that at the
    programmatic level of NEPA review, it was reasonable for
    WESTERN WATERSHEDS PROJECT V . ABBEY                         23
    BLM to decline to analyze in detail an alternative that would
    change grazing management levels throughout the entire
    Monument.
    B
    Western Watersheds also contends that the Breaks EIS
    did not take a “hard look” at grazing impacts. They argue
    that the Breaks EIS did not adequately analyze these impacts
    and that it inappropriately tiered to other NEPA documents.7
    The record leads us to opposite conclusions.
    NEPA requires agencies “to take a ‘hard look’ at how the
    choices before them affect the environment, and then to place
    their data and conclusions before the public.” Or. Natural
    Desert Ass’n v. Bureau of Land Mgmt., 
    625 F.3d 1092
    , 1099
    (9th Cir. 2008). This “hard look” requires a “full and fair
    discussion of significant environmental impacts” in the EIS.
    
    40 C.F.R. § 1502.1
    . “General statements about possible
    effects and some risk do not constitute a hard look absent a
    justification regarding why more definitive information could
    not be provided.” W. Watersheds Project v. Kraayenbrink,
    
    632 F.3d 472
    , 491 (9th Cir. 2011) (citations and alterations
    7
    W estern W atersheds also argues that the B reaks EIS should have
    disclosed as a cumulative impact that BLM destroyed over two-thousand
    acres of sage-grouse habitat in 1979 through sagebrush spraying. We
    disagree. NEPA requires an agency to consider the cumulative impact of
    the current action “when added to other past, present, and reasonably
    foreseeable future actions.” Blue Mountains Biodiversity Project v.
    Blackwood, 
    161 F.3d 1208
    , 1214–15 (9th Cir. 1998). Although in some
    situations discussion of the environmental impact of a thirty-year-old
    project might be useful and relevant, we conclude that it is not here. The
    EIS took a “hard look” at environmental impacts on sage-grouse without
    discussing the 1979 spraying.
    24      WESTERN WATERSHEDS PROJECT V . ABBEY
    omitted). The requirements of NEPA are procedural and not
    substantive. Vt. Yankee Nuclear Power Corp. v. Natural Res.
    Def. Council, Inc., 
    435 U.S. 519
    , 558 (1978). They require a
    responsible federal agency to give a hard and careful look at
    environmental impacts. See Metcalf v. Daley, 
    214 F.3d 1135
    ,
    1141 (9th Cir. 2000). Rather than “mandating that agencies
    achieve particular substantive environmental results . . . ,
    NEPA promotes its sweeping commitment to ‘prevent or
    eliminate damage to the environment and biosphere’ by
    focusing Government and public attention on the
    environmental effects of proposed agency action.” Marsh v.
    Or. Natural Res. Council, 
    490 U.S. 360
    , 371 (1989) (quoting
    
    42 U.S.C. § 4321
    ).
    Western Watersheds first contends that BLM violated
    NEPA by not fully analyzing grazing impacts on Monument
    objects and by not considering management
    recommendations made in three scientific studies that
    assessed environmental impacts of grazing in the Breaks
    country.     These studies include: the 1989 Inventory
    Classification and Management of Riparian Sites Along the
    Upper Missouri National Wild and Scenic Review by Paul
    Hanson (“Hanson study”); the 2003 study on Flood
    Dependency of Cottonwood Establishment Along the
    Missouri River by Michael Scott, et al. (“Scott study”); and
    the 2004 study on Riparian Forests of the Wild and Scenic
    Missouri River: Ecology and Management by Greg Kudray
    et al. (“Kudray study”). We reject this argument.
    Our review of the record shows that BLM adequately
    considered riparian health and grazing impacts in the Breaks
    EIS. In more than one section, the EIS addressed grazing
    impacts on greater sage-grouse habitat, riparian vegetation,
    and fish and wildlife. It also discussed range improvements
    WESTERN WATERSHEDS PROJECT V . ABBEY              25
    that would be implemented for each alternative, including
    constructing new water developments to reduce
    livestock/wildlife conflicts and promoting adequate ground
    cover to reduce grazing impacts on soils. Given that the
    Breaks EIS discussed grazing impacts in detail, Western
    Watersheds seems to argue that BLM did not look hard
    enough at grazing. But the record is sufficient to satisfy us
    that BLM made an informed decision based on its objective,
    good-faith analysis of grazing’s adverse impacts. See
    Kraayenbrink, 
    632 F.3d at 491
    .
    Also, the record reveals that the Breaks EIS discussed
    each of the studies that Western Watersheds contends BLM
    did not consider. The Breaks EIS cited the studies performed
    by Hansen, Scott, and Kudray multiple times to define the
    riparian areas affected by the Breaks Resource Plan. That
    section further noted that the Hansen study and others “show
    a significant lack of regeneration of cottonwood, willow, and
    understory species on the Missouri River,” which is caused in
    part by “continuous hot season use by livestock.” BLM
    considered these studies. It simply did not draw the same
    conclusions about riparian habitat and grazing impacts as
    does Western Watersheds. In short, Western Watersheds asks
    us to perform our own scientific review of these studies to
    conclude that BLM ignored important scientific evidence.
    But our role is more precisely to “ensure that the agency has
    adequately considered and disclosed the environmental
    impact of its actions.” Hells Canyon Alliance v. U.S. Forest
    Serv., 
    227 F.3d 1170
    , 1177 (9th Cir. 2000) (quoting Morongo
    Band of Mission Indians v. Fed. Aviation Admin., 
    161 F.3d 569
    , 573 (9th Cir. 1998)). We decline to substitute our
    judgment for that of BLM, especially with “respect to
    scientific matters within the purview of the agency.”
    26      WESTERN WATERSHEDS PROJECT V . ABBEY
    Klamath-Siskiyou Wildlands Ctr. v. Bureau of Land Mgmt.,
    
    387 F.3d 989
    , 993 (9th Cir. 2004).
    We are not persuaded by Western Watersheds’s
    remaining argument that the Breaks EIS is deficient because
    it inappropriately tiered its analysis of grazing impacts to
    environmental assessments performed for site-specific
    watershed plans. “Tiering refers to the coverage of general
    matters in broader environmental impact statements (such as
    national program or policy statements) with subsequent
    narrower statements or environmental analyses (such as
    regional or basinwide program statements or ultimately
    site-specific statements) incorporating by reference the
    general discussions and concentrating solely on the issues
    specific to the statement subsequently prepared.” 
    40 C.F.R. § 1508.28
    . NEPA regulations encourage tiering to decrease
    repetition so that agencies can “concentrate on the issues
    specific to the subsequent action.” 
    40 C.F.R. § 1502.20
    .
    Western Watersheds explains that under these regulations it
    would be improper for BLM to tier the Breaks EIS to
    environmental assessments performed during the watershed
    process. See 
    40 C.F.R. § 1508.28
    (a).
    But Western Watersheds does not explain just how the
    Breaks EIS tiers to these site-specific environment
    assessments.      They contend that the Breaks EIS
    inappropriately tiers to both “existing and anticipated
    Watershed EAs.” We find no evidence of this in the record.
    Western Watersheds cites to sections of the EIS that
    explained how the watershed planning and permit renewal
    process assesses compliance with the Lewistown Standards.
    But these discussions merely show how the Lewistown
    Standards are implemented and do not impermissibly
    WESTERN WATERSHEDS PROJECT V . ABBEY                27
    incorporate environmental review conducted through the
    watershed planning process.
    Western Watersheds’s argument that the EIS defers to
    future environmental assessments of grazing impacts gets no
    further. It is unclear how an EIS can effectively tier to
    environmental analysis not yet performed. In effect, this
    argument restates Western Watersheds’s contention that the
    EIS did not adequately consider grazing impacts. But we
    have concluded that it did do so. BLM’s discussion of how
    it will conduct more in-depth review at the site-specific level
    does not indicate that the Breaks EIS improperly “tiered” to
    these future assessments but only that BLM plans to “fully
    evaluate[]” site-specific impacts of its future actions. See
    Friends of Yosemite Valley v. Norton, 
    348 F.3d 789
    , 800 (9th
    Cir. 2003).
    C
    In concluding that BLM complied with NEPA in
    developing the Breaks EIS, we distinguish between the two
    different levels of agency planning and management:
    programmatic and site-specific. See 
    id.
     When an agency
    develops an EIS for a programmatic plan like the Breaks
    Resource Plan, the EIS “must provide ‘sufficient detail to
    foster informed decision-making,’ but ‘site-specific impacts
    need not be fully evaluated until a critical decision has been
    made to act on site development.’” 
    Id.
     (quoting N. Alaska
    Envtl. Ctr. v. Lujan, 
    961 F.2d 886
    , 890–91 (9th Cir. 1992)).
    Our conclusion that the Breaks EIS contains sufficient
    analysis for informed decision-making at the programmatic
    level does not reduce or minimize BLM’s critical duty to
    “fully evaluate[]” site-specific impacts. See 
    id.
     Stated
    another way, BLM’s decision to exclude broad changes to its
    28      WESTERN WATERSHEDS PROJECT V . ABBEY
    grazing management throughout the Monument in the Breaks
    Resource Plan does not avoid its critical obligation to
    consider changes to grazing preferences at the site-specific
    stage. It is to that issue that we now turn.
    V
    We consider whether the EA for the Woodhawk
    Allotment complied with NEPA. Western Watersheds
    challenges BLM’s finding of no significant impact and argues
    that BLM should have prepared a full EIS before issuing the
    renewed permit. It also contends that BLM did not consider
    a reasonable range of alternatives because the EA did not
    consider (1) a no-grazing alternative or (2) an alternative that
    incorporated the potential-natural-community standard.
    Western Watersheds further expresses concern that the EA
    tiers to outdated NEPA documents.
    An agency may prepare an environmental assessment to
    determine whether an EIS is needed. 
    40 C.F.R. § 1501.4
    (b).
    If the environmental assessment shows that the agency action
    may significantly affect the environment, then the agency
    must prepare an EIS. Nat’l Parks & Conservation Ass’n v.
    Babbitt, 
    241 F.3d 722
    , 730 (9th Cir. 2001), abrogated on
    other grounds by Monsanto Co. v. Geerston Seed Farms, 
    130 S. Ct. 2743
    , 2756–57 (2010). If an agency concludes in its
    environmental assessment that the proposed action will not
    have a significant environmental impact, then it may issue a
    finding of no significant impact and proceed without further
    study. See Te-Moak Tribe of W. Shoshone of Nev. v. U.S.
    Dep’t of Interior, 
    608 F.3d 592
    , 599 (9th Cir. 2010). NEPA’s
    requirement that agencies “study, develop, and describe
    appropriate alternatives . . . applies whether an agency is
    preparing an [EIS] or an [EA].” N. Idaho Cmty. Action
    WESTERN WATERSHEDS PROJECT V . ABBEY                      29
    Network v. U.S. Dep’t of Transp., 
    545 F.3d 1147
    , 1153 (9th
    Cir. 2008) (per curiam) (citations omitted). Although an
    agency must still “give full and meaningful consideration to
    all reasonable alternatives” in an environmental assessment,
    the agency’s obligation to discuss alternatives is less than in
    an EIS. 
    Id.
     “The existence of a viable but unexamined
    alternative renders an [EA] inadequate.” Westlands Water
    Dist., 
    376 F.3d at 868
     (quoting Morongo, 
    161 F.3d at 575
    ).
    The Woodhawk Allotment EA considered three action
    alternatives and one no-action alternative. The action
    alternatives each considered issuing a new grazing permit at
    the same grazing level as the previous permit, 3,120 animal
    unit months (“AUMs”),8 but with changes to the terms and
    conditions of the permit, including range improvements such
    as installing or removing fencing. The no-action alternative
    that BLM considered in the EA “would issue a new grazing
    permit with 3,120 animal unit months” and have the same
    terms and conditions as the expiring permit. Also, the EA
    considered but did not analyze in detail a no-grazing
    alternative, a reduced-stocking-level alternative (“reduced-
    grazing alternative”), and an alternative that would manage
    the area for potential natural community. The no-grazing and
    reduced-grazing alternatives were both excluded for not
    meeting the purpose and need of the proposed action. The
    no-grazing alterative was also excluded because it was
    previously considered in the 1979 Missouri Breaks Grazing
    Environmental Statement. The potential-natural-community
    alterative was eliminated as unreasonable because it would be
    impossible to maintain given the project’s purpose and need.
    8
    Animal unit months are defined as “the right to obtain the forage
    needed to sustain one cow (or five sheep) for one month.” Public Lands
    Council, 
    529 U.S. at 735
    .
    30      WESTERN WATERSHEDS PROJECT V . ABBEY
    We are troubled by BLM’s decision not to consider a
    reduced- or no-grazing alternative at the site-specific level,
    having chosen not to perform that review at the programmatic
    level. Although we have held above that the decision not to
    consider these alternatives in the Breaks Resource Plan did
    not violate NEPA, this decision has deprived BLM of
    information on the environmental impacts of the
    unconsidered alternatives. At the site-specific level, then,
    BLM is operating with limited information on grazing
    impacts. It is at this stage, when the agency makes a critical
    decision to act, that the agency is obligated fully to evaluate
    the impacts of the proposed action. See ‘Ilio’ulaokalani
    Coal. v. Rumsfeld, 
    464 F.3d 1083
    , 1097 (9th Cir. 2006)
    (explaining that if an agency does not consider reasonable
    alternatives at the programmatic stage, then it has an
    “obligation” to consider such alternatives at the site-specific
    stage). The analysis in the Breaks EIS was sufficient for the
    proposed programmatic action, but the proposed permit
    renewal at the site-specific level demands more. Where
    modification of grazing practices is not considered at a
    programmatic level for the full Monument area, it is all the
    more important that agency actions on site-specific areas give
    a hard and careful look at grazing impacts on Monument
    objects.
    BLM’s analysis in the EA does not take this hard and
    careful look. Each of the four alternatives considered in
    detail, including the no-action alternative, would have
    reauthorized grazing at the exact same level—3,120 animal
    unit months. The distinguishing factors between the no-
    action alternative and the action alternatives that were voiced
    by BLM were the terms and conditions imposed on the
    grazing permit. For example, in Alternative 4, the proposed
    and selected action, the terms of the new grazing permit
    WESTERN WATERSHEDS PROJECT V . ABBEY                       31
    would require relocation of grazing boundaries, replacement
    of some fencing barriers, and adjustment to riparian
    objectives to increase water quality. We do not question the
    environmental soundness of these terms and conditions, as
    that is not the issue presented to us. But we do question how
    an agency can make an informed decision on a project’s
    environmental impacts when each alternative considered
    would authorize the same underlying action—permitting
    grazing at the level of 3,120 AUMs. There is no meaningful
    difference between the four alternatives considered in detail
    as to how much grazing they allow. See Muckleshoot Indian
    Tribe v. U.S. Forest Serv., 
    177 F.3d 800
    , 813 (9th Cir. 1998)
    (per curiam) (concluding that the EIS violated NEPA when
    the two action alternatives considered in detail were
    “virtually identical”). Given the varied objects of the
    Proclamation, and the ways in which grazing in a particular
    area might affect them, we do not think that readopting prior
    grazing levels in the Monument without assessment was
    precisely what the President had in mind in proclaiming that
    prior grazing policies could continue. True, the prior grazing
    practices can continue, but BLM must consider if they should
    be modified in any case where prior grazing practices would
    substantially harm the objects that the Proclamation declared
    to be preserved.
    The Proclamation’s grazing provision did not restrict
    BLM’s authority to change grazing levels; it maintained it.9
    9
    W e are persuaded by Judge W inmill’s analysis in Western Watersheds
    Project v. Salazar, which analyzed a similar grazing provision in
    Presidential Proclamation No. 7373. See 2011 W L 4526746, at *14 (D.
    Idaho. Sept. 28, 2001). President Clinton issued that Proclamation on
    November 9, 2000, to expand the Craters of the Moon National
    Monument. 
    Id. at *7
    .
    32      WESTERN WATERSHEDS PROJECT V . ABBEY
    The grazing provision says only that existing laws shall
    continue to apply with regard to grazing management. See 
    3 C.F.R. § 7398
    . Under those existing laws, BLM has the
    authority “under the Taylor Act and . . . FLPMA to reclassify
    and withdraw rangeland from grazing use.” Public Lands
    Council, 
    529 U.S. at 742
    . FLPMA authorizes BLM to issue
    ten-year grazing permits “subject to such terms and
    conditions the Secretary concerned deems appropriate and
    consistent with governing law.” 
    43 U.S.C. § 1752
    (a).
    Renewal of those permits depends, in part, on whether the
    land remains available for grazing in accordance with the
    applicable land use management plan. See 
    43 U.S.C. § 1752
    (c); Public Lands Council, 
    529 U.S. at 742
    . The
    Breaks Resource Plan, as the governing land use management
    plan, makes clear that “[t]he Proclamation requires that the
    BLM manage the Monument in order to implement the
    purpose of the Proclamation.” From these provisions, it is
    plain that existing laws permit BLM to make changes to the
    scope of grazing operations. To this end, the Proclamation
    and the Breaks Resource Plan both reiterate BLM’s authority
    to reduce or eliminate grazing as needed to protect Monument
    objects.
    Perhaps in recognition of this authority, BLM briefly
    considered both a no-grazing and a reduced-grazing
    alternative. This brief discussion, however, does not cure the
    inadequacies of the other alternatives analyzed in the EA.
    BLM considered and then dismissed without detailed analysis
    the no-grazing and reduced-grazing alternatives. The first
    reason given by BLM for rejecting these alternatives was that
    they were beyond the purpose and need of the project. But
    the record shows that these alternatives could feasibly meet
    the project’s goal. Feasible alternatives should be considered
    in detail. See Muckleshoot Indian Tribe, 177 F.3d at 814
    WESTERN WATERSHEDS PROJECT V . ABBEY               33
    (concluding that the Forest Service violated NEPA by
    considering but preliminary dismissing several feasible
    alternatives). The purpose and need of the Woodhawk
    Allotment permit renewal was “to evaluate rangeland health
    standards and modify current grazing practices on the
    allotment so that progress can be made toward meeting the
    standards.” Lewiston Standard number two sets forth the
    specific goal of achieving proper functioning condition in
    wetland areas, which is indicated in part by diverse
    composition of vegetation and adequate vegetative cover. It
    would be reasonable to analyze in detail the environmental
    impacts of an alternative that authorized something less than
    3,120 AUMs before a permit was renewed. Such an
    alternative could still reasonably meet the purpose of making
    progress toward meeting the Lewistown Standards, but it
    might operate in a more friendly way toward the protected
    objects of the Monument.
    The EA also explained that detailed review of a no-
    grazing alternative was not necessary because such an
    alternative had been analyzed in the 1979 Missouri Breaks
    Grazing Environmental Statement. But an agency errs when
    it relies on old data without showing that the data remain
    accurate. See N. Plains Res. Council, Inc. v. Surface Transp.
    Bd., 
    668 F.3d 1067
    , 1086–87 (9th Cir. 2011) (concluding that
    the Surface Transportation Board did not take a “hard look”
    at environmental impacts when it relied on ten-year-old aerial
    surveys). Here, BLM did not explain why its detailed
    consideration of an alternative in an analysis made thirty
    years before the 2009 Woodhawk Allotment EA for purposes
    of administering grazing over a broad area excuses its duty to
    fully analyze that alternative now, after decades have passed
    and after the Proclamation has added protection for the area.
    Even if the physical environment of the Woodhawk
    34      WESTERN WATERSHEDS PROJECT V . ABBEY
    Allotment is substantially the same, that does not “lead[] to
    the conclusion that the information regarding habitat and
    populations of numerous species remains the same as well.”
    
    Id. at 1086
    . A general assessment of a no-grazing alternative
    in the 1979 Missouri Breaks Grazing Environmental
    Statement, which was performed decades before President
    Clinton issued the Proclamation to protect objects of the
    Monument, does not avoid the need to consider with care
    impacts of grazing in the Woodhawk Allotment EA. See
    Klamath-Siskiyou Wildlands Ctr., 
    387 F.3d at
    997–98
    (concluding that it is improper to tier to an EIS that lacks
    information about specific impacts of a proposed project).
    The severely dated information in the 1979 Environmental
    Statement does not give adequate, accurate, and specific data
    on grazing impacts to Monument objects such as might
    facilitate an informed decision by BLM.
    The Proclamation changed the legal landscape of the
    permitting process for the Woodhawk Allotment, and BLM
    must consider this change in determining the reasonable
    range of alternatives that should be carefully analyzed in the
    Woodhawk Allotment. See Natural Res. Def. Council v. U.S.
    Forest Serv., 
    421 F.3d 797
    , 813 (9th Cir. 2005) (“[W]here
    changed circumstances affect the factors relevant to the
    development and evaluation of alternatives, the [agency] must
    account for such change in the alternatives it considers.”).
    BLM must consider both the terms of the Proclamation and
    the objects of the Proclamation to be preserved before taking
    actions that can affect Monument objects. It did not do so
    when it rejected without analysis the no-grazing alternative or
    the possibility of more limited grazing.
    BLM’s second reason for rejecting the reduced-grazing
    alternative is deficient for the same reason. The EA
    WESTERN WATERSHEDS PROJECT V . ABBEY              35
    explained that in addition to not meeting the purpose and
    need of the project, the reduced-grazing alternative was
    contrary to the stocking levels that had been established for
    the Woodhawk Watershed before the 1998 watershed plan.
    Again, this explanation does not account for the changed
    circumstances of the Proclamation. See 
    id.
     These grazing
    levels may have been sufficient to meet the area’s
    environmental needs before the land was designated as a
    National Monument, but BLM did not show how maintaining
    the same grazing levels thereafter is adequate to protect the
    objects preserved by the Proclamation. BLM’s failure to
    consider the changed circumstances brought by the
    Proclamation, and the impacts of grazing on protected objects
    in the Monument within the Woodhawk Allotment, renders
    the EA inadequate.
    BLM responds that the Woodhawk Allotment EA is
    sufficient because it meets the goals of the Breaks Resource
    Plan. BLM identifies agency responses to public comments
    that asked BLM to consider in detail reduced-grazing
    alternatives. These responses stated that the goals of the EA
    were in line with those of the Breaks Resource Plan to
    manage riparian and wetland areas with the aim of making
    progress toward a “proper functioning condition,” to borrow
    a phrase from the Lewiston Standards, of the ecosystem. The
    response that mentions protection of Monument objects states
    simply that Alternative 4 in the EA should protect Monument
    objects. This may be true, but even so it does not excuse
    BLM from its heightened obligation to analyze fully other
    reasonable grazing alternatives that may better protect
    Monument objects. An alternative to authorizing grazing at
    3,120 AUMs could feasibly meet the goals of both the Breaks
    Resource Plan and the Woodhawk Allotment permit renewal,
    while better preserving Monument objects. But BLM’s
    36      WESTERN WATERSHEDS PROJECT V . ABBEY
    decision not to consider such an alternative, without adequate
    explanation, shows that it did not take the hard and careful
    look at impacts of the permit renewal that is required by
    NEPA.
    In conclusion, the EA process for the Woodhawk
    Allotment was deficient in its consideration of alternatives
    insofar as it did not consider in detail any alternative that
    would have reduced grazing levels on the Allotment in light
    of the Monument’s protected objects. BLM cannot ignore the
    Proclamation’s goal of protecting Monument objects when it
    determines the reasonable range of alternatives for NEPA
    review of site-specific actions. We make no decision of
    substance on how a balance should be struck by BLM, but we
    conclude that the agency’s procedural efforts to explore
    alternatives in the EA did not satisfy NEPA. Because we
    reverse on this issue, we do not reach Western Watersheds’s
    arguments that BLM should have considered a potential-
    natural-community standard or that BLM should have
    prepared an EIS for the Woodhawk Allotment.
    VI
    Western Watersheds seeks injunctive relief to limit
    grazing in riparian areas until the BLM complies with NEPA
    for the Woodhawk Allotment. Before a court may issue a
    permanent injunction, a party must show “(1) that it has
    suffered an irreparable injury; (2) that remedies available at
    law, such as monetary damages, are inadequate to
    compensate for that injury; (3) that, considering the balance
    of hardships between the plaintiff and defendant, a remedy in
    equity is warranted; and (4) that the public interest would not
    be disserved by a permanent injunction.” Monsanto Co., 
    130 S. Ct. at 2756
    ; Sierra Forest Legacy v. Sherman, 646 F.3d
    WESTERN WATERSHEDS PROJECT V . ABBEY                37
    1161, 1184 (9th Cir. 2011); see also Winter, 
    555 U.S. at 32
    (stating that the standard for issuing a permanent injunction
    is essentially the same as for a preliminary one except for the
    need to succeed on the merits). This standard applies equally
    in NEPA cases—we put no thumb on the scale in favor of an
    injunction. Monsanto Co., 
    130 S. Ct. at 2757
    .
    Because the district court concluded that the EA complied
    with NEPA, it did not consider injunctive relief. We have
    reached a conclusion on the EA different from that of the
    district court, but we decline to reach a decision in the first
    instance on the appropriate remedy and, specifically, whether
    injunctive relief is proper. We remand to the district court to
    determine on an appropriate record whether injunctive relief
    is warranted under the traditional four-factor test. See Ocean
    Advocates, 402 F.3d at 871 (remanding to the district court to
    consider injunctive relief in the first instance); see also
    Natural Res. Def. Council, 
    421 F.3d at
    816–17 (remanding to
    the district court to consider a permanent injunction when a
    Forest Service EIS violated NEPA).
    VII
    We hold that BLM reasonably interpreted the
    Proclamation to not require programmatic changes to grazing
    management policies in the Breaks Resource Plan and that
    the Breaks EIS complied with NEPA by taking a hard and
    careful look at grazing impacts. By contrast, we hold that the
    EA for the Woodhawk Allotment violated NEPA by not
    considering a reasonable range of alternatives that included
    a no- or reduced-grazing option. We reverse and remand for
    the district court to enter an appropriate order requiring BLM
    to remedy the deficiencies in the EA for the Woodhawk
    38      WESTERN WATERSHEDS PROJECT V . ABBEY
    Allotment or to prepare a more detailed EIS, whichever is
    considered appropriate, in a timely matter.
    Because this is a mixed judgment, each party shall bear its
    own costs.
    AFFIRMED IN PART; REVERSED IN PART;
    REMANDED.
    

Document Info

Docket Number: 11-35705

Citation Numbers: 719 F.3d 1035

Filed Date: 6/7/2013

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (37)

Northern Plains Resource v. Surface Transp. Bd. , 668 F.3d 1067 ( 2011 )

northwest-ecosystem-alliance-center-for-biological-diversity-tahoma-audubon , 475 F.3d 1136 ( 2007 )

natural-resources-defense-council-southeast-alaska-conservation-council , 421 F.3d 797 ( 2005 )

klamath-siskiyou-wildlands-center-umpqua-watersheds-cascadia-wildlands , 468 F.3d 549 ( 2006 )

westlands-water-district-san-luis-delta-mendota-water-authority-v-united , 376 F.3d 853 ( 2004 )

klamath-siskiyou-wildlands-center-an-oregon-non-profit-organization-v , 387 F.3d 989 ( 2004 )

Western Watersheds Project v. Kraayenbrink , 632 F.3d 472 ( 2011 )

northern-alaska-environmental-center-sierra-club-inc-denali-citizens , 961 F.2d 886 ( 1992 )

katuria-e-smith-angela-rock-michael-pyle-for-themselves-and-all-others , 194 F.3d 1045 ( 1999 )

city-of-angoon-the-sierra-club-the-wilderness-society-plaintiffs-v , 803 F.2d 1016 ( 1986 )

jack-metcalf-australians-for-animals-beach-marine-protection-stassawood-of , 214 F.3d 1135 ( 2000 )

northwest-resource-information-center-inc-oregon-natural-resources , 56 F.3d 1060 ( 1995 )

The Lands Council v. McNair , 537 F.3d 981 ( 2008 )

ilioulaokalani-coalition-a-hawaii-nonprofit-corporation-na-imi-pono-a , 464 F.3d 1083 ( 2006 )

Ecology Center v. Castaneda , 574 F.3d 652 ( 2009 )

Te-Moak Tribe of Western Shoshone v. United States ... , 608 F.3d 592 ( 2010 )

blue-mountains-biodiversity-project-blue-mountain-native-forest-alliance , 161 F.3d 1208 ( 1998 )

hugh-r-kern-leigh-ann-lipscomb-oregon-natural-resources-council-v-united , 284 F.3d 1062 ( 2002 )

hells-canyon-alliance-v-united-states-forest-service-michael-dombeck , 227 F.3d 1170 ( 2000 )

national-parks-conservation-association , 241 F.3d 722 ( 2001 )

View All Authorities »