Friends of the Santa Clara v. US Army Corps of Engineers , 887 F.3d 906 ( 2018 )


Menu:
  •                  FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    FRIENDS OF THE SANTA CLARA                 No. 15-56337
    RIVER; SANTA CLARITA
    ORGANIZATION FOR PLANNING THE                D.C. No.
    ENVIRONMENT,                              2:14-cv-01667-
    Plaintiffs-Appellants,         PSG-CW
    v.
    OPINION
    UNITED STATES ARMY CORPS OF
    ENGINEERS; KIMBERLY COLLOTON,
    in her official capacity as
    Commander and District Engineer of
    the Los Angeles District of the U.S.
    Army Corps of Engineers,
    Defendants-Appellees,
    and
    THE NEWHALL LAND AND FARMING
    COMPANY, a California limited
    partnership,
    Intervenor-Defendant-Appellee.
    Appeal from the United States District Court
    for the Central District of California
    Philip S. Gutierrez, District Judge, Presiding
    2     FRIENDS OF THE SANTA CLARA RIVER V. USACE
    Argued and Submitted February 10, 2017
    Submission Vacated June 23, 2017
    Resubmitted April 2, 2018
    Pasadena, California
    Filed April 9, 2018
    Before: Andrew J. Kleinfeld, Sandra S. Ikuta,
    and Jacqueline H. Nguyen, Circuit Judges.
    Opinion by Judge Ikuta
    SUMMARY*
    Environmental Law
    The panel affirmed the district court’s summary judgment
    in favor of the U.S. Army Corps of Engineers and intervenor
    Newhall Land and Farming in an action challenging the
    Corps’ issuance of a permit, pursuant to Section 404 of the
    Clean Water Act, to Newhall Land, authorizing the discharge
    of materials into the Santa Clara River as part of the Newhall
    Ranch project in Los Angeles County near Santa Clarita,
    California.
    After this case was argued on appeal, the Corps and
    Newhall Land settled with four of the six plaintiffs, and
    stipulated to their voluntary dismissal.     The Corps
    acknowledged that the remaining plaintiffs, Santa Clarita
    *
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    FRIENDS OF THE SANTA CLARA RIVER V. USACE               3
    Organization for Planning the Environment and Friends of the
    Santa Clara River, had standing to pursue their Clean Water
    Act claim. The panel held that the plaintiffs also had standing
    for their National Environmental Policy Act (“NEPA”) and
    Endangered Species Act (“ESA”) claims.
    The panel rejected challenges under the Clean Water Act
    to the Corp’s permit issuance. The panel concluded that the
    Corps complied with its obligations under the Clean Water
    Act because the Corps properly considered practicability as
    required under the Section 404(b) Guidelines.
    The panel further concluded that the Corps complied with
    the ESA because its determination that Southern California
    steelhead would not be affected by the Project, and its
    corresponding decision not to consult with the National
    Marine Fisheries Service, were not arbitrary and capricious.
    For similar reasons, the panel concluded that the Corps
    reasonably assessed the Project’s potential impacts to the
    steelhead and provided sufficient discussion to satisfy its
    NEPA obligations.
    COUNSEL
    John Buse (argued) and Aruna Prabhala, Center for
    Biological Diversity, Oakland, California; Dean Wallraff,
    Advocates for the Environment, Shadow Hills, California; for
    Plaintiffs-Appellants.
    Anna Katselas (argued), Lesley Lawrence-Hammer, Norman
    L. Rave, Devon Lehman McCune, Jennifer Scheller
    Neumann, and Andrew C. Mergen, Attorneys; Eric Grant,
    4       FRIENDS OF THE SANTA CLARA RIVER V. USACE
    Deputy Assistant Attorney General; Jeffrey H. Wood, Acting
    Assistant Attorney General; Environment & Natural
    Resources Division, United States Department of Justice,
    Washington, D.C., for Defendants-Appellees.
    James F. Rusk (argued) and Robert J. Uram, Sheppard Mullin
    Richter & Hampton LLP, San Francisco, California; David P.
    Hubbard v. Mark J. Dillon, Gatzke Dillon & Ballance LLP,
    Carlsbad, California; Miriam A. Vogel, Morrison and
    Foerster LLP, Los Angeles, California; for Intervenor-
    Defendant-Appellee.
    OPINION
    IKUTA, Circuit Judge:
    Under Section 404 of the Clean Water Act, 33 U.S.C.
    § 1344, the U.S. Army Corps of Engineers (Corps) may issue
    permits authorizing the discharge of dredged or fill material
    into the navigable waters of the United States. In this case,
    we consider challenges to the Corps’s issuance of a Section
    404 permit to Newhall Land and Farming (Newhall Land),
    authorizing the discharge of materials into the Santa Clara
    River as part of the Newhall Ranch project in northwestern
    Los Angeles County near Santa Clarita, California.
    The Santa Clarita Organization for Planning the
    Environment (SCOPE) and the Friends of the Santa Clara
    River (Friends)1 challenge the permit issuance under the
    1
    We refer to the organizations collectively as “SCOPE” where
    appropriate, or otherwise refer to them by their respective names. After
    oral argument, four other plaintiffs in this litigation, the Center for
    FRIENDS OF THE SANTA CLARA RIVER V. USACE                         5
    Clean Water Act (CWA), the National Environmental
    Policy Act (NEPA), and the Endangered Species Act (ESA).2
    We conclude that the Corps complied with the numerous
    requirements prescribed by each of these statutes, and we
    affirm.
    I
    We begin by reviewing the legal framework.
    A
    Under the CWA, the discharge of any pollutant
    (including dredged or fill material) to navigable waters is
    unlawful unless the discharge complies with various statutory
    requirements, including obtaining a permit issued by the
    Corps under Section 404 of the CWA, 33 U.S.C. § 1344 (a
    Section 404 Permit). 33 U.S.C. §§ 1311(a), 1362(6), (12);
    see also United States v. Riverside Bayview Homes, Inc.,
    
    474 U.S. 121
    , 123 (1985). Section 404 of the CWA
    authorizes the Corps to “issue permits, after notice and
    opportunity for public hearings[,] for the discharge of
    Biological Diversity, the Wishtoyo Foundation, Ventura Coastkeeper, and
    the Santa Ynez Band of Chumash Mission Indians of the Santa Ynez
    Reservation (the Santa Ynez Band) reached a settlement with the Corps
    and Newhall Land and were voluntarily dismissed from the case.
    2
    The Santa Ynez Band also advanced a challenge under the National
    Historic Preservation Act (NHPA). Because neither of the remaining
    plaintiffs has standing to pursue the NHPA claim, we GRANT the Corps
    and Newhall Land’s unopposed motion to dismiss the NHPA claim. We
    also GRANT their unopposed motion for a limited remand to the district
    court to seek partial vacatur of the NHPA portion of its decision as part of
    the settlement agreement.
    6       FRIENDS OF THE SANTA CLARA RIVER V. USACE
    dredged or fill material into the navigable waters at specified
    disposal sites.” 33 U.S.C. § 1344(a); see also 33 C.F.R.
    § 325.2 (processing of applications). The term “navigable
    waters” means “the waters of the United States, including the
    territorial seas,” 33 U.S.C. § 1362(7), which is further defined
    by regulation to include wetlands, 33 C.F.R. § 328.3(a)(3)
    (2014).3
    When an applicant applies for a permit for a discharge to
    wetlands, the Corps evaluates whether to grant or deny the
    application under guidelines developed by the Environmental
    Protection Agency (EPA) in conjunction with the Secretary
    of the Army and published in 40 C.F.R. part 230. See
    33 C.F.R. § 320.2(f); see also 33 U.S.C. § 1344(b). These
    regulations, referred to as the Section 404(b)(1) Guidelines,
    or simply the Guidelines, provide that “no discharge of
    dredged or fill material shall be permitted if there is a
    practicable alternative to the proposed discharge which would
    have less adverse impact on the aquatic ecosystem, so long as
    3
    The 2015 regulations setting forth a new definition of “waters of the
    United States” had been stayed by the U.S. Court of Appeals for the Sixth
    Circuit. In re EPA and Dep’t of Def. Final Rule, 
    803 F.3d 804
    , 809 (6th
    Cir. 2015). On January 22, 2018, the Supreme Court held that the courts
    of appeals do not have original jurisdiction to review challenges to the
    2015 Rule. Nat’l Ass’n of Mfrs. v. Dep’t of Def., 
    138 S. Ct. 617
    , 623
    (2018). Pursuant to an Executive Order, the Environmental Protection
    Agency, Department of Army, and the Corps published a final rule
    delaying the applicability of the 2015 regulations until February 6, 2020.
    Definition of “Waters of the United States”—Addition of an Applicability
    Date to 2015 Clean Water Rule, 83 Fed. Reg. 5200 (Feb. 6, 2018). Until
    that applicability date, “the agencies will administer the regulations in
    place prior to the 2015 Rule, and will continue to interpret the statutory
    term ‘waters of the United States’ to mean the waters covered by those
    regulations.” 
    Id. at 5201.
    We therefore rely on the definition set forth in
    the prior regulations.
    FRIENDS OF THE SANTA CLARA RIVER V. USACE               7
    the alternative does not have other significant adverse
    environmental consequences” except as otherwise specified.
    40 C.F.R. § 230.10(a). That is, the Corps must analyze
    alternatives to the proposed discharge and “select the least
    environmentally damaging practicable alternative.” Bering
    Strait Citizens for Responsible Res. Dev. v. U.S. Army Corps
    of Eng’rs, 
    524 F.3d 938
    , 955 (9th Cir. 2008).
    The Guidelines further provide that “[a]n alternative is
    practicable if it is available and capable of being done after
    taking into consideration cost, existing technology, and
    logistics in light of overall project purposes.” 40 C.F.R.
    § 230.10(a)(2). The term “practicable alternatives” includes
    “[a]ctivities which do not involve a discharge of dredged or
    fill material into the waters of the United States or ocean
    waters” and “[d]ischarges of dredged or fill material at other
    locations in waters of the United States or ocean waters.”
    40 C.F.R. § 230.10(a)(1).
    In order to determine whether an alternative is
    practicable, “the Corps must first determine the ‘overall
    project purpose.’” Jones v. Nat’l Marine Fisheries Serv.,
    
    741 F.3d 989
    , 1002 (9th Cir. 2013) (quoting 40 C.F.R.
    § 230.10(a)(2)). In defining the overall project purpose, “the
    Corps has a duty to consider the applicant’s purpose,”
    Sylvester v. U.S. Army Corps of Eng’rs, 
    882 F.2d 407
    , 409
    (9th Cir. 1989), and “the objectives of the applicant’s
    project,” 
    id. (quoting La.
    Wildlife Fed’n, Inc. v. York,
    
    761 F.2d 1044
    , 1048 (5th Cir. 1985) (per curiam)). “Indeed,
    it would be bizarre if the Corps were to ignore the purpose for
    which the applicant seeks a permit and to substitute a purpose
    it deems more suitable.” 
    Id. (quoting La.
    Wildlife 
    Fed’n, 761 F.2d at 1048
    ). The permit applicant may not define the
    project purpose narrowly “in order to preclude the existence
    8    FRIENDS OF THE SANTA CLARA RIVER V. USACE
    of any alternative sites and thus make what is practicable
    appear impracticable.” 
    Id. But when
    the applicant’s stated
    purpose is “genuine and legitimate,” the Corps may not reject
    it. 
    Id. In determining
    the overall project purpose, the Corps will
    “normally accept decisions” by state, local, and tribal
    governments with respect to “zoning and land use matters,”
    unless “there are significant issues of overriding national
    importance.” 33 C.F.R. § 320.4(j)(2). Likewise, when the
    Corps approves or undertakes projects requiring the discharge
    of material into the waters of the United States, it must
    consider “officially adopted state, regional, or local land use
    classifications, determinations, or policies.” 33 C.F.R.
    § 336.1(c)(11)(ii).
    In analyzing “practicable alternatives,” the Corps must
    determine whether a project is “water dependent.” A project
    that “does not require access or proximity to or siting within
    the special aquatic site in question to fulfill its basic purpose”
    is “not ‘water dependent.’” 40 C.F.R. § 230.10(a)(3). A
    project’s “basic purpose (for determining water dependency)
    is distinct from the overall purpose (for determining
    practicable alternatives).” Del. Riverkeeper Network v. U.S.
    Army Corps of Eng’rs, 
    869 F.3d 148
    , 157 (3d Cir. 2017)
    (emphasis omitted). When a project’s basic purpose is not
    water dependent, “practicable alternatives that do not involve
    special aquatic sites are presumed to be available, unless
    clearly demonstrated otherwise.” 40 C.F.R. § 230.10(a)(3).
    “[C]lassification of an activity as ‘non-water dependent’ does
    not serve as an automatic bar to issuance of a permit . . . [it]
    simply necessitates a more persuasive showing than
    otherwise concerning the lack of alternatives.” 
    Sylvester, 882 F.2d at 409
    (quoting La. Wildlife Fed’n, Inc. v. York,
    FRIENDS OF THE SANTA CLARA RIVER V. USACE                9
    
    603 F. Supp. 518
    , 527 (W.D. La. 1984), aff’d in part and
    vacated in part, 
    761 F.2d 1044
    (5th Cir. 1985)) (alterations in
    original). When the Corps recognizes that a project is not
    water dependent, considers a range of alternative sites for the
    project, and concludes that there are no practicable alternative
    sites available, the presumption is rebutted. Bering Strait
    
    Citizens, 524 F.3d at 947
    ; see also Butte Envtl. Council v.
    U.S. Army Corps of Eng’rs, 
    620 F.3d 936
    , 945 (9th Cir. 2010)
    (holding that “the Corps applied the proper presumption and
    found that it had been rebutted” because “the Corps
    acknowledged that the proposed project was not water
    dependent” and reviewed “over a dozen alternative sites”).
    We then defer to the Corps’s approval of an alternative.
    Bering Strait 
    Citizens, 524 F.3d at 947
    .
    B
    Before issuing a permit allowing the discharge of dredge
    or fill materials into wetlands, the Corps must comply with
    NEPA, 42 U.S.C. §§ 4321–4370m-12; see 33 C.F.R.
    § 325.2(a)(4) and Appendix B. NEPA requires all federal
    agencies to consider the environmental impact of any “major
    Federal actions significantly affecting the quality of the
    human environment,” and provide a detailed statement on
    “the environmental impact of the proposed action,” “any
    adverse environmental effects which cannot be avoided
    should the proposal be implemented,” and any “alternatives
    to the proposed action.” 42 U.S.C. § 4332(C).
    The Corps’s procedures for implementing NEPA include
    directions for preparing an environmental impact statement
    (EIS) for a decision on a permit application. See 33 C.F.R.
    §§ 230.13, 325.2(a)(4). If the Corps is the lead agency,
    33 C.F.R. § 230.16(a); 40 C.F.R. § 1501.5, it must address the
    10   FRIENDS OF THE SANTA CLARA RIVER V. USACE
    purpose and need of the project and consider reasonable
    alternatives, among other requirements. 33 C.F.R. § 325 app.
    B (9)(b)(4), (5). Because “NEPA does not provide
    substantive protections, only procedural ones,” Conservation
    Cong. v. Finley, 
    774 F.3d 611
    , 615 (9th Cir. 2014), “our
    review is limited to whether the EIS contains ‘a reasonably
    thorough discussion of the significant aspects of the probable
    environmental consequences,’” Nat. Res. Def. Council v.
    U.S. Dep’t of Transp., 
    770 F.3d 1260
    , 1271 (9th Cir. 2014)
    (quoting City of Carmel-by-the-Sea v. U.S. Dep’t of Transp.,
    
    123 F.3d 1142
    , 1150 (9th Cir. 1997)). Although a court must
    “insure that the agency has taken a hard look at
    environmental consequences,” a court cannot “interject itself
    within the area of discretion of the executive as to the choice
    of the action to be taken.” Kleppe v. Sierra Club, 
    427 U.S. 390
    , 410 n.21 (1976) (quoting Nat. Res. Def. Council v.
    Morton, 
    458 F.2d 827
    , 838 (D.C. Cir. 1972)) (internal
    quotation marks omitted).
    C
    The Corps must also comply with the ESA, 16 U.S.C.
    §§ 1531–44. Under the ESA, each federal agency must
    “insure that any action authorized, funded, or carried out by
    such agency . . . is not likely to jeopardize the continued
    existence of any endangered species or threatened species or
    result in the destruction or adverse modification of habitat” of
    endangered or threatened species. 16 U.S.C. § 1536(a)(2).
    Therefore, the Corps must review the permit application “for
    the potential impact on threatened or endangered species
    pursuant to section 7 of the Endangered Species Act.”
    33 C.F.R. § 325.2(b)(5). If the Corps determines that “the
    proposed activity may affect an endangered or threatened
    species or their critical habitat,” it must “initiate formal
    FRIENDS OF THE SANTA CLARA RIVER V. USACE                      11
    consultation procedures with the U.S. Fish and Wildlife
    Service [(FWS)] or National Marine Fisheries Service”
    (NMFS). Id.4 Conversely, if the Corps “determines that the
    proposed activity would not affect listed species or their
    critical habitat, [it] will include a statement to this effect” in
    the public notice regarding the application for a permit, 
    id., and “the
    consultation requirements are not triggered,” Pac.
    Rivers Council v. Thomas, 
    30 F.3d 1050
    , 1054 n.8 (9th Cir.
    1994).
    After the Corps has completed its review, it will
    determine whether a permit should be issued and (if an EIS
    has been prepared) issue a record of decision (ROD).
    33 C.F.R. § 325.2(a)(6).
    II
    We next turn to the lengthy history of the Newhall Ranch
    Project and the activities preceding the Corps’s issuance of
    the Section 404 Permit.
    Starting in the early 1990s, Newhall Land, a land
    management company, and Los Angeles County (the County)
    began developing a land use plan (the Newhall Ranch
    Specific Plan) to guide the development of the Newhall
    4
    FWS and NMFS apportion listing and consultation responsibilities
    by species. See 50 C.F.R. § 402.01(b). FWS is responsible for land-based
    and freshwater species, and NMFS is responsible for marine and
    anadromous species. See Conservation Cong. v. U.S. Forest Serv.,
    
    720 F.3d 1048
    , 1051 (9th Cir. 2013); Gifford Pinchot Task Force v. U.S.
    Fish & Wildlife Serv., 
    378 F.3d 1059
    , 1063 n.1 (9th Cir. 2004),
    superseded on other grounds by Definition of Destruction or Adverse
    Modification of Critical Habitat, 81 Fed. Reg. 7214 (Feb. 11, 2016)
    (codified at 50 C.F.R. § 402.02 (2016)).
    12    FRIENDS OF THE SANTA CLARA RIVER V. USACE
    Ranch Project. As envisioned in the Specific Plan, the
    Project would be a large-scale residential, commercial, and
    industrial development in northwestern Los Angeles County
    near the city of Santa Clarita. It would encompass
    approximately 12,000 acres, including 5.5 linear miles of the
    Santa Clara River and its tributaries. In compliance with the
    California Environmental Quality Act (CEQA), Cal. Pub.
    Res. Code §§ 21000–21189.57,5 the County held public
    hearings and published an environmental impact report (EIR)
    for the Specific Plan. The County ultimately approved the
    Specific Plan, as revised in response to public comments, and
    issued various project approvals, including zoning changes.
    Environmental groups immediately brought actions in
    state court to challenge the County’s approval of the Specific
    Plan. In August 2000, the state court ordered the County to
    vacate the project approval and conduct further
    environmental analyses. See Ctr. for Biological Diversity v.
    Dep’t of Fish & Wildlife, 
    224 Cal. App. 4th 1105
    , 1112
    (2014), rev’d on other grounds, 
    62 Cal. 4th 204
    (2015).
    Following numerous additional hearings and further analyses,
    the County adopted a revised Specific Plan for the Newhall
    Ranch Project in May 2003. As revised, the Specific Plan
    provided for the development of more than 21,000 residential
    units and 5.5 million square feet of commercial, office, and
    5
    CEQA is similar to NEPA, and requires the preparation of an
    “environmental impact report” (EIR) by the lead state agency. See Cal.
    Pub. Res. Code § 21100; see also City of Los Angeles v. FAA, 
    138 F.3d 806
    , 807 (9th Cir. 1998). While both NEPA and CEQA impose
    procedural requirements, see City of 
    Carmel-By-The-Sea, 123 F.3d at 1150
    , CEQA also contains a “substantive mandate that public agencies
    refrain from approving projects for which there are feasible alternatives or
    mitigation measures,” Mountain Lion Found. v. Fish & Game Comm’n,
    
    16 Cal. 4th 105
    , 134 (1997).
    FRIENDS OF THE SANTA CLARA RIVER V. USACE               13
    retail uses in a series of “interrelated villages.” 
    Id. at 1113.
    The state court approved the amended Specific Plan, and
    dismissed the environmental plaintiffs pursuant to a
    settlement agreement. 
    Id. In December
    2003, Newhall Land applied to the Corps for
    a Section 404 Permit that would allow the construction of the
    infrastructure necessary for the development authorized by
    the Specific Plan. Pursuant to its permitting regulations, the
    Corps determined it was the lead agency for purposes of
    NEPA compliance. See 33 C.F.R. § 325.2(a)(4), app. B
    § 325(8). After deciding to prepare an EIS, the Corps
    coordinated with the California Department of Fish and
    Wildlife (CDFW) to prepare a combined EIS/EIR.
    The Corps published a notice of intent to prepare an
    EIS/EIR in the Federal Register in 2004 and a second one in
    2005, and held two public scoping meetings to determine the
    scope of the issues to be addressed and to identify the
    significant issues relating to the action. See 40 C.F.R.
    § 1501.7. The Corps circulated the Draft EIS/EIR in May
    2009 for public comment. After receiving and considering
    public comments on the Draft EIS/EIR, the Corps prepared a
    Final EIS/EIR, which included the Corps’s Draft Section
    404(b)(1) Guidelines Evaluation.
    As part of its analysis of the Project’s water quality,
    biological resources, and cumulative impacts, the Final
    EIS/EIR discussed the Project’s water discharges into the
    Santa Clara River and the potential impacts on the Southern
    California steelhead, an endangered species. The Corps
    determined that the Project area was not part of the
    steelhead’s critical habitat, but considered the Project’s
    potential to affect steelhead and its habitat downstream of the
    14       FRIENDS OF THE SANTA CLARA RIVER V. USACE
    Project area through increased stormwater discharges. While
    the Santa Clara River generally contains water on a year-
    round basis, a portion of the river between the Project area
    and the downstream steelhead areas is dry most of the year,
    so Project discharges would generally not impact steelhead.
    (This dry reach of the river is informally known as the “Dry
    Gap.”) In months when there is sufficient rainfall, however,
    stormwater runoff may flow through the Dry Gap, and during
    those periods Project discharge might reach steelhead
    populations. The Corps nonetheless determined that these
    changes would not have a substantial adverse effect on the
    southern steelhead.
    In reaching this conclusion, the Corps analyzed the
    combination of wastewater and stormwater discharges from
    the Project, and concluded that the Project’s total discharges
    would have a dissolved-copper concentration of 9.0
    micrograms-per-liter. This concentration is less than the
    existing dissolved-copper concentration in the Santa Clara
    River that occurs during storm events large enough to flow
    through the Dry Gap. In addition, this concentration would
    be less than the limit of 32 micrograms-per-liter of dissolved
    copper that the California Toxics Rule (CTR), an EPA-
    promulgated regulation establishing water quality standards
    in California, set for the Santa Clara River.6 Accordingly, the
    Corps concluded in the Final EIS/EIR that the Project would
    6
    The CTR “promulgates criteria for priority toxic pollutants in the
    State of California for inland surface waters and enclosed bays and
    estuaries,” including for aquatic life, 40 C.F.R. § 131.38(a), and is “legally
    applicable in the State of California for inland surface waters, enclosed
    bays and estuaries for all purposes and programs under the Clean Water
    Act.” Water Quality Standards; Establishment of Numeric Criteria for
    Priority Toxic Pollutants for the State of California, 65 Fed. Reg. 31,682,
    31,682 (May 18, 2000) (codified at 40 C.F.R. pt. 131).
    FRIENDS OF THE SANTA CLARA RIVER V. USACE             15
    not affect the steelhead, and therefore it was not required to
    consult with NMFS to discharge its responsibilities under the
    ESA. See 16 U.S.C. § 1536(a)(3); 33 C.F.R. § 325.2(b)(5).
    The Corps solicited additional comments that would be
    considered “before the Corps . . . finalizes the Record of
    Decision (ROD) for the Federal action associated with the
    proposed project.” Among other letters, it received a
    comment letter from Ventura Coastkeeper expressing its
    concern that the Project’s discharges would contain dissolved
    copper at a concentration that would harm Southern
    California steelhead. In August 2010, the Corps also received
    a letter from the EPA, offering comments on the Final
    EIS/EIR and suggesting, among other things, that the Corps’s
    practicability analysis for different alternatives should
    consider the expected revenues from the Project. The EPA
    subsequently sent a letter in August 2011, indicating that it
    would not seek review of the Corps’s permit decision, citing
    significant improvements to the Project design and additional
    mitigation measures that had resulted from collaboration
    among the EPA, the Corps, and Newhall Land.
    On August 31, 2011, the Corps issued a ROD and a
    provisional Section 404(b) permit to Newhall Land. The
    ROD addressed the comments the Corps had received on the
    Final EIS/EIR. In responding to Ventura Coastkeeper’s
    comment letter, the Corps summarized the results of a
    Supplemental Water Quality Analysis conducted by a third-
    party consultant in May 2011, which showed that the
    additional stormwater retention measures incorporated into
    the Project would further reduce the dissolved-copper
    concentration in the Project’s stormwater discharges.
    16   FRIENDS OF THE SANTA CLARA RIVER V. USACE
    The Corps also appended its Final Section 404(b)(1)
    Guidelines Evaluation (Final Evaluation) to the ROD. The
    Final Evaluation stated that it was not a stand-alone
    document, but relied heavily on the information provided in
    the Draft EIS/EIR and the Final EIS/EIR. Like the Final
    EIS/EIR, the Final Evaluation concluded that the Project
    would not affect the steelhead and therefore consultation with
    NMFS pursuant to the ESA was not required.
    The Final Evaluation defined the “overall project
    purpose” for purposes of analyzing the practicability of
    alternatives as follows:
    [T]he development of a master planned
    community with interrelated villages in the
    vicinity of the Santa Clarita Valley in
    northwestern Los Angeles County that
    achieves the basic objectives of the Specific
    Plan by providing a broad range of land uses
    of approximately the same size and
    proportions as approved in the Specific Plan,
    including residential, mixed-use, commercial
    and industrial uses, public services (schools,
    parks, etc.), and a water reclamation plant.
    The Corps determined that the overall project purpose also
    included 15 of the 37 basic objectives of the Specific Plan.
    The Corps stated that the “basic project purpose,” which is
    used to determine whether the project is water dependent, was
    “to provide housing and commercial/industrial/mixed-use
    development.” Because the basic project purpose was not
    water dependent, the Corps determined that the rebuttable
    presumption that practicable alternatives were available
    applied, but was rebutted because the Corps had analyzed
    FRIENDS OF THE SANTA CLARA RIVER V. USACE                     17
    23 alternative sites and concluded that they were
    impracticable.
    The Final Evaluation considered the eight on-site
    alternatives described and analyzed in the Final EIS/EIR, in
    order to determine which one was the “least environmentally
    damaging practicable alternative.” Bering Strait 
    Citizens, 524 F.3d at 955
    . These alternatives included a no-build
    alternative (Alternative 1), Newhall Land’s preferred
    alternative (Alternative 2), and six other alternatives
    (Alternatives 3 through 7 and Modified Alternative 3), each
    with varying project sizes and resulting impacts on waters of
    the United States. Alternative 2, Newhall Land’s alternative,
    proposed developing 2,864.2 acres, which would include
    20,885 residential units7 and 5.5 million square feet of
    commercial space. It would have permanently filled 93.3
    acres of waters of the United States, including 20.5 acres of
    wetlands, and would have temporarily filled 33.3 acres of
    waters of the United States, including 11.2 acres of wetlands.
    The Corps selected Modified Alternative 3 as the least
    environmentally damaging practicable alternative. Compared
    to Newhall Land’s preferred alternative (Alternative 2),
    Modified Alternative 3 reduced permanent impacts to waters
    of the United States by 29 percent and temporary impacts by
    3 percent. It also reduced the acreage that could be developed
    for residential units by 10 percent and likewise reduced the
    7
    The Specific Plan allowed an additional 423 residential “second
    units” as part of the Project, see Ctr. for Biological Diversity, 224 Cal.
    App. 4th at 1113, but the Corps did not consider those units separately in
    its analysis because the Corps determined that they would not impact the
    Project’s development footprint or secondary environmental effects.
    SCOPE does not challenge this decision.
    18       FRIENDS OF THE SANTA CLARA RIVER V. USACE
    developable commercial acreage by 14 percent, increasing the
    Project’s cost per developable acre by 5.7 percent. The Corps
    concluded that further modifications to the Project would be
    impracticably expensive, noting that Modified Alternative 3
    would be more costly than the most expensive comparable
    development project in the region. Accordingly, the ROD
    adopted Modified Alternative 3 as the basis for the Section
    404 permit.
    In March 2014, SCOPE sued the EPA, the Corps, and
    their respective agency officials in district court, alleging
    violations of the CWA, NEPA, and the NHPA.8 Newhall
    Land successfully moved to intervene as a defendant. In
    January 2015, SCOPE amended its complaint to assert an
    additional claim under the ESA. On cross-motions for
    summary judgment, the district court granted summary
    judgment in favor of the Corps and Newhall Land on June 30,
    2015, the judgment that SCOPE now appeals.
    III
    Before reaching the merits of SCOPE’s claims, we
    consider whether the plaintiffs have standing to bring their
    NEPA and ESA claims. After this case was argued on appeal,
    the Corps and Newhall Land settled with four of the six
    plaintiffs, and stipulated to voluntary dismissal of those
    plaintiffs. In supplemental briefing on the effect of these
    dismissals, the Corps and Newhall Land argue that while both
    of the remaining plaintiffs, SCOPE and Friends, have
    8
    The district court dismissed the EPA and its officials as defendants
    for lack of subject matter jurisdiction. The propriety of this dismissal is
    not before us on appeal. As explained 
    above, supra
    5 n.2, we grant the
    Corps and Newhall Land’s unopposed motion to dismiss the NHPA claim.
    FRIENDS OF THE SANTA CLARA RIVER V. USACE                 19
    standing to pursue their CWA claim, they lack standing to
    pursue their NEPA and ESA claims. We may consider the
    jurisdictional question of Article III standing for the first time
    on appeal. See Wash. Envtl. Council v. Bellon, 
    732 F.3d 1131
    , 1139 (9th Cir. 2013). Because “[t]he need to satisfy
    [Article III standing] requirements persists throughout the life
    of the lawsuit,” if circumstances change such that the
    plaintiffs before us no longer possess standing, we must
    dismiss the affected claims. Wittman v. Personhuballah,
    
    136 S. Ct. 1732
    , 1736–37 (2016). We conclude, however,
    that SCOPE and Friends possess standing for their NEPA and
    ESA claims.
    A
    “[A] plaintiff must demonstrate standing for each claim
    he seeks to press and for each form of relief that is sought.”
    Town of Chester v. Laroe Estates, Inc., 
    137 S. Ct. 1645
    , 1650
    (2017) (quoting Davis v. Fed. Election Comm’n, 
    554 U.S. 724
    , 734 (2008)). When there are multiple plaintiffs, “[a]t
    least one plaintiff must have standing to seek each form of
    relief requested in the complaint.” 
    Id. at 1651.
    In order for
    an organizational plaintiff such as SCOPE or Friends to have
    standing, it must demonstrate that at least one of its
    “members would otherwise have standing to sue in [the
    member’s] own right, the interests at stake are germane to the
    organization’s purpose, and neither the claim asserted nor the
    relief requested requires the participation of individual
    members in the lawsuit.” Wash. Envtl. 
    Council, 732 F.3d at 1139
    (quoting Friends of the Earth, Inc. v. Laidlaw Envtl.
    Servs. (TOC), Inc., 
    528 U.S. 167
    , 181 (2000)).
    A plaintiff seeking relief in federal court must establish
    the three elements that constitute the “irreducible
    20   FRIENDS OF THE SANTA CLARA RIVER V. USACE
    constitutional minimum” of Article III standing, Lujan v.
    Defs. of Wildlife, 
    504 U.S. 555
    , 560 (1992), namely, that the
    plaintiff has “(1) suffered an injury in fact, (2) that is fairly
    traceable to the challenged conduct of the defendant, and
    (3) that is likely to be redressed by a favorable judicial
    decision,” Spokeo, Inc. v. Robins, 
    136 S. Ct. 1540
    , 1547
    (2016).
    This standard “is softened when a plaintiff asserts a
    violation of a procedural right” conferred by a federal statute,
    San Luis & Delta-Mendota Water Auth. v. Haugrud, 
    848 F.3d 1216
    , 1232 (9th Cir. 2017) (internal quotation marks and
    citation omitted), because “the causation and redressability
    requirements [for standing] are relaxed,”           WildEarth
    Guardians v. U.S. Dep’t of Agric., 
    795 F.3d 1148
    , 1154 (9th
    Cir. 2015) (citation omitted). In order to establish an injury
    in fact in the context of a claimed procedural error in an
    agency’s decisionmaking process, a plaintiff must show that
    “(1) the [agency] violated certain procedural rules; (2) these
    rules protect [a plaintiff’s] concrete interests; and (3) it is
    reasonably probable that the challenged action will threaten
    their concrete interests.” 
    Haugrud, 848 F.3d at 1232
    (alterations in original) (quoting Nuclear Info. & Res. Serv. v.
    Nuclear Regulatory Comm’n, 
    457 F.3d 941
    , 949 (9th Cir.
    2006)).
    To establish causation and redressability, the plaintiff
    must show that “the relief requested—that the agency follow
    the correct procedures—may influence the agency’s ultimate
    decision.” WildEarth 
    Guardians, 795 F.3d at 1156
    (quoting
    Salmon Spawning & Recovery All. v. Gutierrez, 
    545 F.3d 1220
    , 1226 (9th Cir. 2008)). In the NEPA context, plaintiffs
    may demonstrate redressability with a showing that the
    agency’s decision could “could be influenced by the
    FRIENDS OF THE SANTA CLARA RIVER V. USACE             21
    environmental considerations that NEPA requires an agency
    to study.” Laub v. U.S. Dep’t of Interior, 
    342 F.3d 1080
    ,
    1087 (9th Cir. 2003). A plaintiff does not need to show that
    the correction of the alleged procedural error would lead to a
    decision more favorable to plaintiffs’ interests. See 
    id. (“In order
    to establish redressability, plaintiffs asserting the
    inadequacy of an agency’s EIS . . . need not show that further
    analysis by the government would result in a different
    conclusion.”); Cantrell v. City of Long Beach, 
    241 F.3d 674
    ,
    682 (9th Cir. 2001) (“[P]laintiffs asserting procedural
    standing need not demonstrate that the ultimate outcome
    following proper procedures will benefit them.”). Similarly,
    plaintiffs asserting violations of the ESA’s consultation
    requirements are “not required to establish what a Section 7
    consultation would reveal, or what standards would be set.”
    Cottonwood Envtl. Law Ctr. v. U.S. Forest Serv., 
    789 F.3d 1075
    , 1082 (9th Cir. 2015).
    While “[t]his is not a high bar to meet . . . . the
    redress[a]bility requirement is not toothless in procedural
    injury cases.” Salmon 
    Spawning, 545 F.3d at 1227
    .
    Procedural rights “can loosen . . . the redressability prong,”
    not eliminate it. Summers v. Earth Island Inst., 
    555 U.S. 488
    ,
    497 (2009). For instance, we have found redressability
    lacking where an agency’s correction of a procedural error
    could not lead to a decision more favorable to plaintiffs, as
    where a project had already been completed, see Rattlesnake
    Coal. v. EPA, 
    509 F.3d 1095
    , 1102–03 (9th Cir. 2007), where
    a different agency had already made the same decision, see
    Nuclear Info. & Res. 
    Serv., 457 F.3d at 955
    , or where the
    agency could not reverse the United States’ entrance into an
    international treaty, see Salmon 
    Spawning, 545 F.3d at 1227
    .
    22       FRIENDS OF THE SANTA CLARA RIVER V. USACE
    In this case, SCOPE and Friends assert procedural
    violations of NEPA and ESA. See WildEarth 
    Guardians, 795 F.3d at 1154
    (noting that a claim “alleging a NEPA
    violation” is procedural); Nat. Res. Def. Council v. Jewell,
    
    749 F.3d 776
    , 783 (9th Cir. 2014) (en banc) (“[A]lleged
    violations of Section 7(a)(2)’s consultation requirement
    constitute a procedural injury for standing purposes.”).
    B
    Newhall Land argues that the plaintiffs have failed to
    show standing even under our relaxed standards. According
    to Newhall Land, the plaintiffs have not shown that the
    Corps’s alleged procedural deficiencies under NEPA and
    ESA affected their concrete interests, because plaintiffs allege
    only that the Corps conducted an inadequate analysis of the
    Project’s impacts on Southern California steelhead under
    NEPA, and that the Corps failed to engage in consultation
    with the NMFS regarding those impacts as required under the
    ESA.9 But, Newhall Land argues, the plaintiffs’ interests are
    limited to recreation and natural resources within the Project
    area, where steelhead are not present.
    This argument fails, however, because under our relaxed
    standard, the plaintiffs need show only that “the challenged
    [agency] action will threaten their concrete interests,” Ctr. for
    Food Safety v. Vilsack, 
    636 F.3d 1166
    , 1171 (9th Cir. 2011)
    (emphasis added), not that the alleged procedural deficiency
    will threaten such interests. Here the challenged agency
    action is the Corps’s issuance of the Section 404 permit, and
    9
    Before the district court, SCOPE also challenged the Final
    EIS/EIR’s traffic and cultural resource analysis, but does not do so on
    appeal.
    FRIENDS OF THE SANTA CLARA RIVER V. USACE                23
    so the plaintiffs need show only that the issuance of the
    permit will affect their interest in recreation and aesthetics in
    the Project area; they do not need to show that the alleged
    inadequacies in the Corps’s analysis of the Project’s impact
    on steelhead will have such an effect. See, e.g., 
    id. at 1172;
    Nuclear Info. & Res. 
    Serv., 457 F.3d at 952
    ; City of Sausalito
    v. O’Neill, 
    386 F.3d 1186
    , 1197 (9th Cir. 2004). Two other
    circuits have likewise rejected Newhall Land’s argument that
    the plaintiffs’ injury must be tied to the particular procedural
    deficiency alleged. See WildEarth Guardians v. U.S. Bureau
    of Land Mgmt., 
    870 F.3d 1222
    , 1231 (10th Cir. 2017);
    WildEarth Guardians v. Jewell, 
    738 F.3d 298
    , 307 (D.C. Cir.
    2013) (“The Appellants’ aesthetic injury follows from an
    inadequate FEIS whether or not the inadequacy concerns the
    same environmental issue that causes their injury.”). SCOPE
    and Friends have concrete interests at stake, see 
    Laidlaw, 528 U.S. at 183
    , and it is reasonably probable that those
    interests will be threatened by the “challenged action,” Ctr.
    for Food 
    Safety, 636 F.3d at 1171
    , the issuance of the Section
    404 permit.
    We also reject the argument that plaintiffs failed to show
    causation and redressability. Contrary to Newhall Land’s
    argument, SCOPE and Friends do not need to show that the
    Corps’s correction of the alleged procedural error would lead
    to a favorable decision such as a decision not to issue a
    Section 404 permit. See 
    Laub, 342 F.3d at 1087
    . Rather,
    plaintiffs need only show a reasonable probability that the
    Corps’ decision “could be influenced by the environmental
    considerations that NEPA requires an agency to study.” 
    Id. Here, such
    a reasonable probability exists. Plaintiffs
    suggest that if the Corps conducted further analysis, it would
    become aware of more significant impacts to steelhead.
    24        FRIENDS OF THE SANTA CLARA RIVER V. USACE
    Because the Project’s stormwater discharge results from
    paving over surfaces that would otherwise absorb rainfall, it
    is plausible that mitigating those impacts would result in
    alterations or reductions to the Project’s footprint. Moreover,
    if the analysis revealed that the Project would “affect”
    steelhead, 50 C.F.R. § 402.14(a), the Corps would then have
    to engage in ESA consultation, possibly leading to further
    Project modifications. See 16 U.S.C. § 1536(b)(3).10
    Accordingly, we conclude that Plaintiffs have standing for
    their NEPA and ESA claims.11
    IV
    Because this case involves review of a final agency
    determination under the Administrative Procedure Act,
    5 U.S.C. § 706, the district court limited its review to the
    administrative record, and resolved it on summary judgment.
    10
    Indeed, given that the Corps concluded that requiring the Project to
    incur the cost of further mitigation would make it impracticably
    expensive, it is conceivable that significant new modifications or delay
    would block the Project entirely. See generally, Amanda Covarrubias &
    Catherine Saillant, Longtime Foes of Ahmanson Project Rejoice, Los
    Angeles Times (Sept. 24, 2003), http://articles.latimes.com/2003/sep/24
    /local/me-ahmanson24/.
    11
    SCOPE and Friends also satisfy the other organizational standing
    requirements. The protection of the Project area’s natural resources is
    “germane to the organization’s purpose,” and “neither the claim asserted
    nor the relief requested requires the participation of individual members
    in the lawsuit.” Wash. Envtl. 
    Council, 732 F.3d at 1139
    (quoting 
    Laidlaw, 528 U.S. at 181
    ). Moreover, SCOPE and Friends satisfy prudential
    standing requirements, as “[i]t is well settled that the zone of interests
    protected by NEPA is environmental,” Nuclear Info. & Res. 
    Serv., 457 F.3d at 950
    , and the zone-of-interests test does not apply to their claim
    under the ESA’s citizen suit provision, see Bennett v. Spear, 
    520 U.S. 154
    ,
    164 (1997); 16 U.S.C. § 1540(g).
    FRIENDS OF THE SANTA CLARA RIVER V. USACE                    25
    We review a grant of summary judgment de novo, and must
    determine whether the Corps’s action was arbitrary or
    capricious under the APA.12 See Gifford Pinchot Task Force
    v. U.S. Fish & Wildlife Serv., 
    378 F.3d 1059
    , 1065 (9th Cir.
    2004) (citing 5 U.S.C. § 706(2)(A)), superseded on other
    grounds by Definition of Destruction or Adverse
    Modification of Critical Habitat, 81 Fed. Reg. 7214.
    “Review under the arbitrary and capricious standard is
    deferential . . . .” Nat’l Ass’n of Home Builders v. Defs. of
    Wildlife, 
    551 U.S. 644
    , 658 (2007). “[O]ur proper role is
    simply to ensure that the [agency] made no ‘clear error of
    judgment’ that would render its action ‘arbitrary and
    capricious,’” Lands Council v. McNair, 
    537 F.3d 981
    , 993
    (9th Cir. 2008) (en banc), overruled on other grounds by
    Winter v. Nat. Res. Def. Council, 
    555 U.S. 7
    (2008), and we
    require only “‘a rational connection between facts found and
    conclusions made’ by the defendant agencies.” 
    Finley, 774 F.3d at 617
    (quoting League of Wilderness Defs./Blue
    Mountains Biodiversity Project v. Connaughton, 
    752 F.3d 755
    , 760 (9th Cir. 2014)). Accordingly, “we will not vacate
    an agency’s decision unless [the agency] ‘has relied on
    factors which Congress has not intended it to consider,
    entirely failed to consider an important aspect of the problem,
    offered an explanation for its decision that runs counter to the
    evidence before the agency, or is so implausible that it could
    not be ascribed to a difference in view or the product of
    agency expertise.’” Nat’l Ass’n of Home Builders, 
    551 U.S. 12
           Even though SCOPE brings its ESA claim under the ESA’s citizen
    suit provision, 16 U.S.C. § 1540(g), “the APA’s ‘arbitrary and capricious’
    standard applies; and, an agency’s ‘no effect’ determination under the
    ESA must be upheld unless arbitrary and capricious.” W. Watersheds
    Project v. Kraayenbrink, 
    632 F.3d 472
    , 481 (9th Cir. 2011).
    26   FRIENDS OF THE SANTA CLARA RIVER V. USACE
    at 658 (quoting Motor Vehicle Mfrs. Ass’n of U.S., Inc. v.
    State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983)).
    “This approach . . . requires us to defer to an agency’s
    determination in an area involving a ‘high level of technical
    expertise.’” Lands 
    Council, 537 F.3d at 993
    (citation
    omitted). That is, “[w]e are to be ‘most deferential’ when the
    agency is ‘making predictions, within its [area of] special
    expertise, at the frontiers of science.’” 
    Id. (alteration in
    original) (quoting Forest Guardians v. U.S. Forest Serv.,
    
    329 F.3d 1089
    , 1099 (9th Cir. 2003)). We cannot “substitute
    our judgment for the agency’s in determining which scientific
    data to credit, so long as the conclusion is supported by
    adequate and reliable data.” 
    Finley, 774 F.3d at 620
    .
    V
    A
    We first consider SCOPE’s CWA claim. SCOPE argues
    that the Corps failed to select the least environmentally
    damaging practicable alternative in issuing a Section 404(b)
    permit. SCOPE claims that in determining the overall project
    purpose, the Corps incorporated Newhall Land’s project
    objectives and the County’s Specific Plan objectives and
    therefore relied on an overly specific purpose that unduly
    narrowed the range of available alternatives.
    We disagree. As explained above, the Corps not only
    may, but must, consider Newhall Land’s project objectives,
    provided that those project objectives are not so narrowly
    defined as to preclude alternatives, see 
    Jones, 741 F.3d at 1002
    ; 
    Sylvester, 882 F.2d at 409
    , and must also consider the
    Specific Plan objectives, 33 C.F.R. §§ 320.4(j)(2),
    FRIENDS OF THE SANTA CLARA RIVER V. USACE                     27
    336.1(c)(11)(ii). Therefore, the Corps was not arbitrary or
    capricious in rejecting certain alternatives on the ground that
    they failed to meet Newhall Land’s objectives or the Specific
    Plan objectives.
    The Corps could reasonably reject Alternatives 7 and 8
    because their substantial reductions in the extent of
    developable land (44 percent and 25 percent, respectively)
    would prevent the Project from meeting elements of the
    overall project purpose and their substantial increase in costs
    (51 percent and 28 percent, respectively) would render them
    impracticable. Nor was the Corps arbitrary or capricious in
    rejecting Alternative 6 on the ground that it reduced
    developable space in a manner that would preclude village-
    style development, its 13 percent increase in cost would make
    it impracticable, and other practicable alternatives would be
    less environmentally damaging.13
    SCOPE next attacks the manner in which the Corps
    assessed the cost of the alternatives under consideration.
    First, SCOPE contends that the Corps failed to select the least
    environmentally damaging practicable alternative because
    further avoidance and minimization of impacts to waters of
    the United States were theoretically possible, and the Corps
    erred in considering the financial impact of further avoidance.
    We disagree. The regulations require the Corps to take into
    13
    SCOPE argues that the Corps should have followed its 1989 intra-
    agency review decision in the Hartz Mountain project in New Jersey,
    where the Corps acknowledged that “federal concerns over the
    environment, health and/or safety will often result in decisions that are
    inconsistent with local land use approvals.” However, the Corps’s 1989
    decision pertained to a different project in an entirely different context.
    Nothing in that decision shows that the Corps erred in its consideration of
    the Specific Plan objectives here.
    28   FRIENDS OF THE SANTA CLARA RIVER V. USACE
    consideration the cost of an alternative in making the
    determination that there is no practicable alternative. See
    40 C.F.R. § 230.10(a)(2) (“An alternative is practicable if it
    is available and capable of being done after taking into
    consideration cost, existing technology, and logistics in light
    of overall project purposes.”). The Corps followed this
    regulatory requirement in determining that it would be
    impracticably expensive to adopt an alternative more
    restrictive than the selected alternative, Modified Alternative
    3, to avoid further impacts to waters of the United States.
    The Corps’s determination was reasonably based on its
    findings that Modified Alternative 3 would be more
    expensive than any previous comparable development project
    in southern California, and would also exceed the average and
    median costs for such projects by at least 56 percent. The
    alternative was 5.7 percent more costly than Newhall Land’s
    preferred alternative, and significantly shrank the Project’s
    footprint. The Corps’s decision that Modified Alternative 3
    was at the outer limit of cost practicability was thus based on
    a “rational connection between facts found and the
    conclusion” made and we defer to its determination under
    40 C.F.R. § 230.10(a)(2). Butte Envtl. 
    Council, 620 F.3d at 947
    ; see also Bering Strait 
    Citizens, 524 F.3d at 948
    .
    SCOPE further criticizes three different aspects of the
    Corps’s cost methodology. It claims that: (1) the Corps
    should have considered costs on a per-residential unit or per-
    commercial floor space basis rather than a per-acre basis;
    (2) the Corps was required to consider the Project’s revenues;
    and (3) the Corps should have excluded land acquisition costs
    because those costs are sunk costs. We disagree. The
    Section 404(b) Guidelines do not require the Corps to use any
    particular metric for analyzing costs; rather, they merely
    instruct the Corps to assess alternatives in light of their “cost,
    FRIENDS OF THE SANTA CLARA RIVER V. USACE                        29
    existing technology, and logistics,” 40 C.F.R. § 230.10(a)(2).
    Therefore, so long as the Corps’s evaluation of costs is
    reasonable, we must defer to it. See Nat’l Ass’n of Home
    
    Builders, 551 U.S. at 658
    . Here, the Corps adopted a
    reasonable methodology for calculating and evaluating costs,
    and therefore it is entitled to deference.
    The Corps’s evaluation of costs on a per-acre basis was
    reasonable. As the Corps explained, Newhall Land intended
    to sell developable land by the acre, rather than developing
    the land itself and selling units or floor space. Accordingly,
    the Corps could reasonably conclude that determining
    Newhall Land’s costs per acre made more sense than
    speculating about the type and density of units that might
    ultimately be built on that land. The Corps also noted that the
    per-acre cost metric was “more widely used in the industry.”
    The Corps also reasonably declined to consider revenues
    as part of an alternative’s costs. The regulations direct the
    Corps to assess practicability based on “cost, existing
    technology, and logistics.” 40 C.F.R. § 230.10(a)(2). “Cost”
    means an “expenditure or outlay,” see Webster’s Third New
    Intl. Dictionary 515 (2002), and does not include “revenues,”
    which are items of income, see 
    id. at 1942.14
    Although
    14
    We additionally reject SCOPE’s suggestion that the EPA has
    authoritatively interpreted “cost” in 40 C.F.R. § 230.10(a)(2) to include
    revenues. Neither of the authorities on which SCOPE relies, a 2008
    comment made by the EPA in response to a Section 404 permit sought by
    the Potash Corporation of Saskatchewan, and the EPA’s comment in
    response to the Draft EIS/EIR in this case, purports to be an authoritative
    interpretation of the Section 404(b) Guidelines. Of course, even if those
    documents did purport to offer an authoritative interpretation, such an
    interpretation could not supersede the unambiguous plain language of
    30        FRIENDS OF THE SANTA CLARA RIVER V. USACE
    revenues are not part of “costs,” the Corps nevertheless stated
    that it took revenues into account “by looking at how each
    alternative affects developable acreage, which is the source
    of revenue for the project.” Given the close relationship
    between the developable acreage resulting from the Project
    and revenues to Newhall Land, the Corps did not fail to
    consider an important aspect of the problem.15
    Finally, the Corps did not err by including the acquisition
    costs of the property proposed for the Project site. The
    Section 404(b) Guidelines do not require a specified
    treatment of land acquisition costs, so we defer to the Corps’s
    judgment unless its decision was arbitrary or capricious. See
    
    Jones, 741 F.3d at 996
    . Here, the Corps reasonably included
    the acquisition costs as part of its determination of whether an
    alternative is practicable. Because Newhall Land is investing
    (or contributing) its valuable site to the Project, the costs of
    the Project include the value of the property. Accordingly,
    the exclusion of the value of the property would have led to
    inaccurate comparisons between the costs for the Newhall
    Ranch project and the costs for comparable projects, which
    would require property acquisition. Indeed, the Corps would
    have arguably “entirely failed to consider an important aspect
    of the problem” had the Corps excluded land costs in its
    practicability analysis rather than included it. Nat’l Ass’n of
    40 C.F.R. § 230.10(a)(2). See Siskiyou Reg’l Educ. Project v. U.S. Forest
    Serv., 
    565 F.3d 545
    , 555 (9th Cir. 2009).
    15
    SCOPE’s characterization of the land cost to Newhall Land as a
    “sunk cost” is similarly incorrect. A sunk cost is “[a] cost that has already
    been incurred and that cannot be recovered.” See Black’s Law Dictionary
    398 (9th ed. 2009) (emphasis added). Newhall Land could recover the
    costs of acquiring the Project site (however long ago those costs were
    incurred) by selling the site.
    FRIENDS OF THE SANTA CLARA RIVER V. USACE               31
    Home 
    Builders, 551 U.S. at 658
    (quoting Motor Vehicle Mfrs.
    
    Ass’n, 463 U.S. at 43
    ).
    We therefore find no merit in SCOPE’s CWA challenges
    to the Corps’s permit issuance.
    B
    We next turn to SCOPE’s claim that the Corps violated
    the ESA. SCOPE argues that the Corps erred in determining
    that the Project “will have no effect” on Southern California
    steelhead in the Santa Clara River, and so was required to
    consult with NMFS on the Project’s potential impact. See
    Pac. Rivers 
    Council, 30 F.3d at 1054
    n.8; 50 C.F.R.
    § 402.14(a). SCOPE argues that the Project may affect
    steelhead because, during storm events where the volume of
    the Project’s discharges is sufficient to flow into the reach of
    the Santa Clara River downstream of the Dry Gap, those
    discharges will contain concentrations of dissolved copper
    that cause sublethal impacts to juvenile steelhead smolt.
    We disagree. The data and analysis set forth in the Draft
    EIS/EIR and Final EIS/EIR consistently establish that
    concentrations of dissolved copper in discharges from the
    Project would be within the background range already
    observed in the Santa Clara River and well below the CTR’s
    dissolved-copper criterion for the Santa Clara River. During
    storm events large enough to cause discharges from the
    Project to flow into the reach of the Santa Clara River
    downstream of the Dry Gap, the background concentration of
    dissolved copper in the relevant portion of the Santa Clara
    River averages 9.9 micrograms-per-liter. The Final EIS/EIR
    estimated that the combined discharge from the Project’s
    stormwater runoff and its wastewater treatment plant would
    32        FRIENDS OF THE SANTA CLARA RIVER V. USACE
    contain only 9.0 micrograms of dissolved copper per liter,
    which would be lower than that background concentration.16
    The 2011 Supplemental Water Quality Analysis (incorporated
    by reference into the ROD) found that the additional
    stormwater retention measures required by the Corps would
    reduce the dissolved-copper concentration of the Project’s
    stormwater discharges from the 8.3 micrograms-per-liter
    referenced in the Final EIS, to 6.5 micrograms-per-liter, again
    well below background. Given this information, the Corps
    reasonably concluded that the Project’s discharges of
    dissolved copper would not affect steelhead downstream of
    Dry Gap. The Corps also noted that because the Project
    discharges would flow into the Santa Clara River downstream
    of the Dry Gap only when water flows were already high, the
    Project discharges would constitute less than one percent of
    the River’s flow and “water quality in the Santa Clara River
    would not be significantly affected by the discharges.”
    Because the Corps’s determination that the Project would not
    affect steelhead was not arbitrary or capricious, we reject
    SCOPE’s ESA claim. See 
    Kraayenbrink, 632 F.3d at 481
    .
    SCOPE’s argument to the contrary hinges on its
    contention that the Corps erred by failing to consider a 2007
    Technical Memorandum published by NMFS, An Overview
    of Sensory Effects on Juvenile Salmonids Exposed to
    Dissolved Copper (the “NMFS Memorandum”) which
    Ventura Coastkeeper submitted with its comments on the
    Final EIS/EIR.       According to SCOPE, the NMFS
    16
    SCOPE argues in its reply brief that the Corps erred by relying in
    part on average concentrations, but the district court rejected this
    argument, and SCOPE abandoned it on appeal by failing to raise it in its
    opening brief, see TAAG Linhas Aereas de Angola v. Transamerica
    Airlines, Inc., 
    915 F.2d 1351
    , 1353 n.1 (9th Cir. 1990).
    FRIENDS OF THE SANTA CLARA RIVER V. USACE               33
    Memorandum establishes that the levels of dissolved copper
    in discharges from the Project will have “sublethal impacts”
    on steelhead smolt, which are not adequately accounted for in
    the CTR criteria. SCOPE argues that the Corps failed to use
    “the best scientific and commercial data available,” 16 U.S.C.
    § 1536(a)(2), because it did not adequately consider the
    thresholds set out in the NMFS Memorandum.
    We reject this argument. As a threshold matter, we may
    not substitute our scientific judgment for that of the agency.
    “The determination of what constitutes the ‘best scientific
    data available’ belongs to the agency’s ‘special expertise[’]”
    and warrants substantial deference. San Luis & Delta-
    Mendota Water Auth. v. Jewell, 
    747 F.3d 581
    , 602 (9th Cir.
    2014) (emphasis omitted) (quoting Baltimore Gas & Elec.
    Co. v. Nat. Res. Def. Council, 
    462 U.S. 87
    , 103 (1983)).
    Accordingly, “[t]he best available data requirement ‘merely
    prohibits [the Corps] from disregarding available scientific
    evidence that is in some way better than the evidence [it]
    relies on.’” Kern Cty. Farm Bureau v. Allen, 
    450 F.3d 1072
    ,
    1080 (9th Cir. 2006) (third alteration in original) (quoting Sw.
    Ctr. for Biological Diversity v. Babbitt, 
    215 F.3d 58
    , 60 (D.C.
    Cir. 2000)). In this case, the Corps could reasonably
    conclude that the NMFS Memorandum does not contain the
    best scientific data available for the Project. The NMFS
    Memorandum summarizes and analyzes laboratory studies
    regarding the effects of concentrations of copper on coho
    salmon in municipal water. It did not consider steelhead
    populations or the effect of copper concentrations in natural
    34    FRIENDS OF THE SANTA CLARA RIVER V. USACE
    conditions. Moreover, it did not consider any data specific to
    the Project or the Santa Clara River.17
    Nor was it arbitrary or capricious for the Corps to
    consider the CTR criteria as “a useful benchmark” to assess
    the possible water-quality impacts of the Project’s discharges.
    The Corps could reasonably consider the CTR criteria as one
    source of information, given that the EPA promulgated the
    CTR to establish water-quality criteria “legally applicable in
    the State of California for inland surface waters, enclosed
    bays and estuaries for all purposes and programs under the
    Clean Water Act.” 65 Fed. Reg. at 31,682; see also 40 C.F.R.
    § 131.38. As applied here, the CTR provides “an estimate of
    the highest concentration of a substance in water which does
    not present a significant risk to the aquatic organisms in the
    water and their uses,” 65 Fed. Reg. at 31,689, and which
    California and the EPA must consider in implementing
    various water quality programs under the CWA, 
    id. at 31,683–84.18
    Because the effects of dissolved copper and
    other dissolved metals depend on water “hardness” and other
    factors that vary among bodies of water, the CTR provides a
    method for calculating a site-specific dissolved-copper
    criterion. 
    Id. at 31,690,
    31,692; see also 40 C.F.R. § 131.38,
    gen. note 3 to table in paragraph (b)(1). The Corps could thus
    17
    Although SCOPE faults the Corps for not expressly rejecting the
    use of the NMFS Memorandum, the Corps responded to the letter
    attaching the Memorandum, reiterated its reasoning, and explained that it
    had concluded that the Project would not affect steelhead. We can thus
    reasonably discern that the Corps concluded that the NMFS Memorandum
    was inapplicable. See Alaska Dep’t of Envtl. Conservation v. EPA,
    
    540 U.S. 461
    , 497 (2004).
    18
    SCOPE does not point to any public comment disputing the use of
    the CTR.
    FRIENDS OF THE SANTA CLARA RIVER V. USACE                   35
    reasonably consider the CTR as part of its analysis.
    Moreover, because the Corps considered other sources of
    data, including project-specific modeling, in determining that
    issuance of the Section 404 Permit would have no effect on
    downstream steelhead, SCOPE’s arguments regarding
    limitations in the applicability of the CTR are not material.19
    SCOPE next argues that because the Corps published its
    determination that the Project would not affect steelhead in its
    June 2010 Final EIS/EIR, it could not rely on the
    Supplemental Analysis, which had been issued almost a year
    later in May 2011, to support its determination. We reject
    this argument, because the Corps did not need to rely on the
    Supplemental Analysis in order to reach its conclusion. The
    Final EIS/EIR explains the Corps’s determination that the
    Project’s stormwater and wastewater discharges would not
    affect steelhead because the dissolved-copper concentrations
    of the combined discharge would be within background
    ranges and lower than the average concentration during large
    storm events, as well as substantially below the CTR’s
    threshold. This conclusion was not arbitrary or capricious.
    The Supplemental Analysis merely confirmed the Corps’s
    initial conclusion that there would be no effect because it
    established that the Project’s stormwater retention measures
    would further lower the dissolved-copper concentrations in
    the Project’s runoff. Because the Final EIS/EIR’s analysis of
    combined stormwater and wastewater discharges was
    19
    Although SCOPE contends that the CTR criteria were inapplicable
    because “unacceptable adverse effects” as defined in the CTR do not
    include the kind of sublethal impacts considered in the NMFS
    Memorandum, the Corps could reasonably conclude that the CTR’s site-
    specific calculations were more applicable to the steelhead population at
    issue in the Santa Clara River.
    36        FRIENDS OF THE SANTA CLARA RIVER V. USACE
    sufficient to support the Corps’s determination that Southern
    California steelhead would not be affected by the Project, we
    also reject SCOPE’s argument that the Corps erred by relying
    on the Supplemental Analysis, which did not include the
    effects of wastewater discharges.20
    We therefore conclude that the Corps reasonably
    determined that the Project would have no effect on
    steelhead, and in the absence of a consultation request from
    NMFS, see 50 C.F.R. § 402.14(a), the Corps’s decision not to
    consult with NMFS was not arbitrary and capricious.21
    C
    In its NEPA claim, SCOPE argues that the Corps’s Final
    EIS/EIR provided an inadequate analysis of the cumulative
    impacts of the Project’s dissolved-copper discharges on
    steelhead in the reach of the Santa Clara River downstream of
    20
    Similarly, because the Supplemental Analysis was not necessary to
    support the Corps’s determination that the Project would not affect the
    steelhead, we do not consider SCOPE’s argument that the Supplemental
    Analysis’s projections were substantively flawed.
    21
    NMFS did not request formal consultation with the Corps regarding
    the Southern California steelhead. Rather, NMFS responded to an inquiry
    from the Corps regarding the status of Southern California steelhead and
    its critical habitats, informing the Corps “the Santa Clara River basin
    upstream from its confluence with Piru Creek . . . is not currently
    considered by NMFS to be part of the critical habitat designation” for
    Southern California steelhead and stating that “[f]or those projects the
    Corps determines will have no effect, there is no need to seek concurrence
    from, or consult further with, NMFS.” SCOPE emphasizes that the Corps
    received numerous comments stating it had an obligation to consult with
    NMFS, but such requests made to the Corps do not trigger the Corps’s
    obligation to consult under the ESA. See 50 C.F.R. § 402.14(a).
    FRIENDS OF THE SANTA CLARA RIVER V. USACE               37
    the Dry Gap. Because SCOPE raises essentially the same
    arguments that it advanced under its ESA claim, they fail for
    largely the same reasons.
    First, SCOPE again contends that the NMFS
    Memorandum demonstrates that the Project’s dissolved-
    copper discharges may cause sublethal impacts to steelhead,
    and the Final EIS/EIR failed to consider those impacts. As
    explained above, the Corps did not err in declining to rely on
    the NMFS Memorandum. See Or. Nat. Res. Council Fund v.
    Goodman, 
    505 F.3d 884
    , 897 (9th Cir. 2007) (“NEPA does
    not require the reviewing court to ‘decide whether an [EIS] is
    based on the best scientific methodology available.’”)
    (quoting Or. Envtl. Council v. Kunzman, 
    817 F.2d 484
    , 496
    (9th Cir. 1987) (alteration in original)). Furthermore, because
    the Corps reasonably determined that the Project was not
    likely to affect steelhead populations in the Santa Clara River,
    it was also not arbitrary or capricious to conclude that the
    Project would not result in significant cumulative water
    quality impacts to steelhead. See Sw. Ctr. for Biological
    Diversity v. U.S. Forest Serv., 
    100 F.3d 1443
    , 1448 (9th Cir.
    1996) (explaining that an agency’s “no effect” determination
    under the ESA supported its conclusion that the action would
    “not individually or cumulatively have a significant effect on
    the human environment” under NEPA) (quoting 40 C.F.R.
    § 1508.4). For this reason, the Final EIS/EIR provided a
    sufficient discussion “to show why more study is not
    warranted,” 40 C.F.R. § 1502.2(b), and therefore satisfied
    NEPA’s requirements. See Protect Our Communities Found.
    v. Jewell, 
    825 F.3d 571
    , 583 (9th Cir. 2016).
    Second, SCOPE challenges the Corps’s reference to the
    May 2011 Supplemental Analysis in its response to
    comments on the Final EIS/EIR. SCOPE argues that the
    38   FRIENDS OF THE SANTA CLARA RIVER V. USACE
    Corps was required to recirculate a revised EIS/EIR
    containing the Supplemental Analysis or alternatively,
    include the full document as an appendix. As explained
    above, the Supplemental Analysis merely confirmed the
    Corps’s conclusion, but was not its basis; accordingly, it did
    not contain “significant new information” that would require
    the Corps to recirculate the EIS/EIR for further comment.
    California ex rel. Imperial Cty. Air Pollution Control Dist. v.
    U.S. Dep’t of the Interior, 
    767 F.3d 781
    , 794 (9th Cir. 2014);
    see also 40 C.F.R. § 1502.9(c)(1)(ii). Moreover, contrary to
    SCOPE’s assertions, the Corps did not violate NEPA by
    incorporating the Supplemental Analysis by reference and
    informing the public that it was available upon request, rather
    than providing the document in an appendix. See California
    ex rel. Imperial Cty. Air Pollution Control 
    Dist., 767 F.3d at 794
    –95; 40 C.F.R. § 1502.21.
    Because the Final EIS/EIR provided an adequate analysis
    of the cumulative impacts of the Project’s dissolved copper
    discharges, SCOPE’s NEPA claim also fails.
    VI
    We conclude that the Corps complied with its obligations
    under the CWA, having properly considered practicability as
    required under the Section 404(b) Guidelines. We further
    conclude that the Corps complied with the ESA, as its
    determination that Southern California steelhead would not
    be affected by the Project and its corresponding decision not
    to consult with NMFS were not arbitrary and capricious. For
    similar reasons, we conclude that the Corps reasonably
    assessed the Project’s potential impacts to the steelhead and
    provided sufficient discussion to satisfy its NEPA obligations.
    FRIENDS OF THE SANTA CLARA RIVER V. USACE       39
    Accordingly, the district court properly granted summary
    judgment in the Corps’s favor.
    AFFIRMED.
    

Document Info

Docket Number: 15-56337

Citation Numbers: 887 F.3d 906

Filed Date: 4/9/2018

Precedential Status: Precedential

Modified Date: 4/9/2018

Authorities (33)

anne-cantrell-an-individual-lou-anna-denison-an-individual-kenneth-n , 241 F.3d 674 ( 2001 )

Spokeo, Inc. v. Robins , 136 S. Ct. 1540 ( 2016 )

Center for Food Safety v. Vilsack , 636 F.3d 1166 ( 2011 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

Winter v. Natural Resources Defense Council, Inc. , 129 S. Ct. 365 ( 2008 )

Baltimore Gas & Electric Co. v. Natural Resources Defense ... , 103 S. Ct. 2246 ( 1983 )

Oregon Natural Resources Council Fund v. Goodman , 505 F.3d 884 ( 2007 )

frederic-d-sylvester-v-us-army-corps-of-engineers-wayne-j-scholl-in , 882 F.2d 407 ( 1989 )

Natural Resources Defense Council, Inc. v. Rogers C. B. ... , 458 F.2d 827 ( 1972 )

SW Ctr Bio Divrsty v. Babbitt, Bruce , 215 F.3d 58 ( 2000 )

Western Watersheds Project v. Kraayenbrink , 632 F.3d 472 ( 2011 )

Lujan v. Defenders of Wildlife , 112 S. Ct. 2130 ( 1992 )

Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )

The Lands Council v. McNair , 537 F.3d 981 ( 2008 )

city-of-sausalito-a-municipal-corporation-v-brian-oneill-john-reynolds , 386 F.3d 1186 ( 2004 )

Rattlesnake Coalition v. U.S. Environmental Protection ... , 53 A.L.R. Fed. 2d 723 ( 2007 )

forest-guardians-a-nonprofit-corporation-white-mountain-conservation , 329 F.3d 1089 ( 2003 )

Butte Environmental Council v. United States Army Corps of ... , 620 F.3d 936 ( 2010 )

city-of-los-angeles-v-federal-aviation-administration-burbank-glendale , 138 F.3d 806 ( 1998 )

Louisiana Wildlife Federation, Inc. v. York , 603 F. Supp. 518 ( 1984 )

View All Authorities »