Idaho Conservation League v. Bonneville Power Administration , 826 F.3d 1173 ( 2016 )


Menu:
  •                     FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    IDAHO CONSERVATION LEAGUE,                      No. 12-70338
    Petitioner,
    v.                            OPINION
    BONNEVILLE POWER
    ADMINISTRATION,
    Respondent.
    On Petition for Review of an Order of the
    Bonneville Power Administration
    Argued and Submitted October 6, 2014
    Portland, Oregon
    Filed June 21, 2016
    Before: Alex Kozinski, Ferdinand F. Fernandez
    and Andre M. Davis,* Circuit Judges.
    Opinion by Judge Kozinski
    *
    The Honorable Andre M. Davis, Senior Circuit Judge for the U.S.
    Court of Appeals for the Fourth Circuit, sitting by designation.
    2           IDAHO CONSERVATION LEAGUE V. BPA
    SUMMARY**
    Environmental Law
    The panel denied a petition for review of a decision of the
    Bonneville Power Administration to move forward with a
    proposal to change how the Albeni Falls Dam in the Pacific
    Northwest operates during winter months without first
    preparing an environmental impact statement under the
    National Environmental Policy Act.
    Lake Pend Oreille, which serves as the dam’s reservoir,
    is jointly managed by the Army Corps of Engineers, the
    Bonneville Power Administration, and the Bureau of
    Reclamation. In the initial winter months of the dam’s
    operation, starting in the late 1950s, the Corps fluctuated the
    level of the lake, but in some years the Corps held the lake’s
    level constant. From 1997 to 2011, the Corps held the lake’s
    level constant. In 2011, the agencies confirmed in an
    environmental assessment that they planned to return to a
    more flexible approach and allow the lake level to fluctuate.
    NEPA only requires the preparation of an environmental
    impact statement when a proposed federal action is major, but
    “where a proposed federal action would not change the status
    quo,” an environmental impact statement is not required.
    Upper Snake River Chapter of Trout Unlimited v. Hodel, 
    921 F.2d 232
    , 235 (9th Cir. 1990).
    **
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    IDAHO CONSERVATION LEAGUE V. BPA                   3
    The panel held that the agencies complied with NEPA
    when they finalized their 2011 decision without preparing an
    environmental impact statement. The panel held that holding
    lake levels constant from 1997 to 2011 did not change the
    status quo, and reverting to the previous regime of fluctuating
    the lake levels did not change the status quo either.
    The panel held that because the agencies’ decision
    adopting flexible winter operations did not trigger NEPA’s
    requirement to publish an environmental impact statement,
    petitioner’s challenges to the environmental assessment’s
    finding of no significant impact were moot. The panel held
    that petitioner did not properly raise a challenge to the
    Bonneville Power Administration’s failure to prepare a
    supplemental environmental impact statement addressing the
    effects of the flowering rush on the dam’s operation.
    COUNSEL
    Bryan Hurlbutt (argued), Advocates for the West, Boise,
    Idaho, for Petitioner.
    Hub V. Adams (argued), Attorney; Jacilyn R. Margeson,
    Assistant Attorney General; Randy A. Roach, General
    Counsel; Bonneville Power Administration, Portland,
    Oregon; David J. Adler, Special Assistant United States
    Attorney; S. Amanda Marshall, United States Attorney;
    Stephen J. Odell, Assistant United States Attorney; United
    States Attorney’s Office, Portland, Oregon; for Respondent.
    4         IDAHO CONSERVATION LEAGUE V. BPA
    OPINION
    KOZINSKI, Circuit Judge:
    Operated by the Army Corps of Engineers (Corps), the
    Albeni Falls Dam helps provide power to the Pacific
    Northwest. The Bonneville Power Administration (BPA) is
    charged with marketing the power generated from the dam.
    In 2011, the agencies decided to change how they operated
    the dam during the winter months. We consider whether they
    complied with the National Environmental Policy Act
    (NEPA) when they finalized this decision without preparing
    an environmental impact statement.
    FACTS
    The Albeni Falls Dam straddles the Pend Oreille River,
    which connects Lake Pend Oreille and the Columbia River.
    Completed in 1957 as part of the Federal Columbia River
    Power System, it is jointly managed by the Corps, BPA and
    the Bureau of Reclamation. Like other dams in the System,
    the Albeni Falls Dam is operated to balance a variety of
    competing objectives, such as flood control, power
    generation, navigation and wildlife conservation.
    Lake Pend Oreille serves as the dam’s reservoir. When
    water is released from the lake, it drives turbines that generate
    electricity. This decreases the reservoir’s depth and causes its
    shoreline to recede. For decades, the Corps maintained the
    flexibility to generate power during the winter months. In the
    initial winters of the dam’s operation, starting in the late
    1950s, the Corps fluctuated the level of the lake to generate
    power as needed. In some years, however, the Corps held the
    lake’s level constant, often near 2051 feet.
    IDAHO CONSERVATION LEAGUE V. BPA                   5
    In 1995, the Corps determined that allowing the lake’s
    elevation to drop during the winter months had adverse
    effects on the kokanee salmon population and so beginning
    in 1997 began holding the lake’s elevation constant. But in
    2009, BPA urged the Corps to return to a more flexible
    approach to winter dam management. After two years of
    discussions and a public comment period, the agencies
    confirmed in a 2011 environmental assessment (EA) that they
    planned to follow through with BPA’s proposal. The plan for
    “flexible winter power operations” gives the Corps the option
    each winter to store water in the reservoir and then release it
    through the dam according to power needs. Thus, instead of
    keeping the lake’s level constant, the Corps may allow it to
    rise and fall by as much as five feet during the winter.
    The EA concludes that the proposed winter fluctuations
    will have no significant environmental impact. Accordingly,
    the agencies decided to move forward with the proposal
    without preparing an environmental impact statement (EIS).
    See 
    40 C.F.R. §§ 1501.4
    (b)–(c), 1508.9.           Petitioner
    challenges this decision as a violation of NEPA and asks us
    to require BPA to prepare an EIS. We have original
    jurisdiction pursuant to the Northwest Power Act. 16 U.S.C.
    § 839f(e)(5).
    DISCUSSION
    NEPA, which applies to all federal agencies, 
    42 U.S.C. § 4332
    , doesn’t dictate particular policy outcomes; instead, it
    regulates the manner in which agencies arrive at them.
    Specifically, for all “major Federal actions significantly
    affecting the quality of the human environment,” the agency
    must prepare an EIS, which is a detailed study examining the
    environmental consequences of its decision.                
    Id.
    6          IDAHO CONSERVATION LEAGUE V. BPA
    § 4332(2)(C). An EA is meant to briefly document the
    reasons for the agency’s determination whether an EIS is
    required. 
    40 C.F.R. § 1508.9
    ; see Cascadia Wildlands v.
    Bureau of Indian Affairs, 
    801 F.3d 1105
    , 1111 (9th Cir.
    2015). The EA here concludes that no EIS is required
    because the proposed action will not “result in any new
    significant impacts to the human environment.”
    1. NEPA only requires the preparation of an EIS when a
    proposed federal action is major. See Upper Snake River
    Chapter of Trout Unlimited v. Hodel, 
    921 F.2d 232
    , 234–35
    (9th Cir. 1990). A federal action that may have significant
    environmental impacts need not “also be ‘major’ in an
    economic or some other nonenvironmental sense to trigger
    the EIS requirement.” City of Davis v. Coleman, 
    521 F.2d 661
    , 673 n.15 (9th Cir. 1975); see 
    40 C.F.R. § 1508.18
    (“Major reinforces but does not have a meaning independent
    of significantly.”). But when an agency, responding to
    changing conditions, makes a decision to operate a completed
    facility “within the range originally available” to it, the action
    is not major. Upper Snake River, 
    921 F.2d at 235
     (quoting
    Cty. of Trinity v. Andrus, 
    438 F. Supp. 1368
    , 1388 (E.D. Cal.
    1977)). In other words, “where a proposed federal action
    would not change the status quo, an EIS is not necessary.”
    Id.; accord San Luis & Delta-Mendota Water Auth. v. Jewell,
    
    747 F.3d 581
    , 646 (9th Cir. 2014).
    Upper Snake River involved a challenge to the Bureau of
    Reclamation’s management of the Palisades Dam. Upper
    Snake River, 
    921 F.2d at 233
    . Reclamation typically ensured
    that water flowed into the Snake River at a rate of at least
    1,000 cubic feet per second. 
    Id.
     In response to a drought, the
    agency reduced water flow below that rate in two consecutive
    years and wanted to do so a third time without preparing an
    IDAHO CONSERVATION LEAGUE V. BPA                  7
    EIS. 
    Id.
     at 233 & n.1, 234. We acknowledged that, “if an
    ongoing project undergoes changes which themselves amount
    to ‘major Federal actions,’ the operating agency must prepare
    an EIS.” 
    Id. at 234
    . But Reclamation was not effecting a
    substantial operational change or expanding the Palisades
    Dam’s original facilities. Instead, the agency was doing what
    it had always done: “from time to time and depending on the
    river’s flow level, adjust[ing] up or down the volume of water
    released from the Dam.” 
    Id. at 235
    . Accordingly, we found
    that Reclamation did not need to prepare an EIS. 
    Id. at 236
    .
    If the agencies in our case have consistently fluctuated
    winter lake levels, formalizing that approach would not be a
    major federal action because the agencies would be “doing
    nothing new, nor more extensive, nor other than that
    contemplated when the [Albeni Falls Dam] was first
    operational.” 
    Id. at 235
    . The Corps fluctuated the elevation
    of Lake Pend Oreille in many winters prior to 1997, and
    various dam management strategies considered in a 1995 EIS
    included elements of what is now the proposal for flexible
    winter operations. Accordingly, the question is whether
    holding lake levels constant from 1997 to 2011 changed the
    status quo. If not, then reverting to the previous regime
    doesn’t change the status quo either.
    The Corps discussed holding winter lake levels constant
    in an EA published in 1995. This document reviewed a
    proposal for a three-winter test to hold the lake at a high
    minimum and found that doing so would have no significant
    environmental impacts. BPA and the Corps subsequently
    published Records of Decision putting this plan into action.
    We have explained that the time for an EIS is when an agency
    undertakes a “significant shift of direction in operating
    policy.” Grand Canyon Trust v. U.S. Bureau of Reclamation,
    8         IDAHO CONSERVATION LEAGUE V. BPA
    
    691 F.3d 1008
    , 1022 (9th Cir. 2012) (as amended). And, for
    purposes of NEPA, the term “[m]ajor reinforces but does not
    have a meaning independent of significantly.” 
    40 C.F.R. § 1508.18
    . Thus, this short-term decision, which was found
    to have no significant environmental impact, could not have
    constituted a major federal action because it wasn’t a
    significant or long-term change in operating policy. In short,
    it did not change the status quo.
    Actions taken with respect to winter dam management
    since 1995 reinforce the conclusion that there was no change
    to the status quo. As mentioned, the plan to hold winter lake
    levels constant began as a three-year test. The agencies
    managing the dam twice decided to carry forward this
    management strategy at the urging of the U.S. Fish and
    Wildlife Service. It’s also notable that, since 2000, an
    interagency team has met each year to recommend the lake’s
    constant elevation for the coming winter. In four winters
    from 1996 to 2011, Lake Pend Oreille was held near 2051
    feet; the lake was also held near that elevation in eight
    winters between 1980 and 1995. See Upper Snake River,
    
    921 F.2d at 235
     (finding that even if an agency had only
    engaged in a proposed action sporadically in the past, that
    was enough to show that repeating that action did not change
    the status quo). As in Upper Snake River, the agencies here
    considered each year how to manage the Albeni Falls Dam
    based on that year’s conditions.           The Corps never
    relinquished its authority to fluctuate the lake’s elevation in
    response to power demands: The Corps’ 2002 Water Control
    Manual notes that Lake Pend Oreille “is usually operated”
    within a one-foot range above the winter minimum, but that
    “storage above [that minimum] may be used for . . .
    unscheduled hydropower operations.” Thus, from 1997 to
    2011, the agencies maintained the discretion they have
    IDAHO CONSERVATION LEAGUE V. BPA                  9
    always had to respond annually to changing conditions. See
    
    id.
     Continuing to do so did not change the status quo.
    Because the period when the agencies held winter lake
    levels constant did not change the operational status quo,
    neither does the decision to revert to flexible winter
    operations. Power generation has always been among the
    central concerns in operating the dam. For example, a 1948
    Army report on plans for the dam explained that, “[d]uring
    the fall and winter period when regional power supply is
    lowest and power loads are greatest, the stored water [at Lake
    Pend Oreille] will be drawn upon for power purposes.” The
    EA echoes that report, noting that “[t]he purpose of [flexible
    winter operations] is to more efficiently use the available
    water storage capabilities at AFD to generate power during
    the winter” and that “[s]toring water in the near term will
    provide power benefits at a future date when that water is
    released[,] . . . depend[ing] on power prices, load demand,
    and conditions at [another dam].” As the EA further
    explains: “Historically, winter power operations have been
    associated with [releasing] water for power. Water was
    stored for power operations during the winter in the 1980s
    and early 1990s.” Thus, in some winters the lake has
    fluctuated, and in others it hasn’t. Accordingly, the agencies
    will be doing “nothing new, nor more extensive, nor other
    than that contemplated when the project was first
    operational.” Upper Snake River, 
    921 F.2d at 235
    .
    Petitioner argues that Upper Snake River is
    distinguishable because “[u]nder existing operations, the
    Corps maintains steady lake levels throughout winter,” while
    under flexible winter operations, “lake levels would be raised
    and lowered over a five-foot range up to three times every
    winter for the life of the Dam.” But Petitioner’s view of
    10         IDAHO CONSERVATION LEAGUE V. BPA
    “existing operations” is incorrectly limited to operations since
    the publication of the 1995 EA. Moreover, Petitioner
    mischaracterizes the proposal. According to the current EA,
    it’s “unlikely” that lake levels would rise and fall over a five-
    foot range three times every winter—a variety of factors, such
    as power demand and weather conditions, will influence how
    the agencies operate the dam each year. Additionally, there
    may still be winters where the agencies hold the lake’s level
    constant in order to facilitate kokanee reproduction. Thus,
    the flexible winter operations proposal comprises elements of
    both earlier and more recent management strategies. These
    details support the conclusion that the agencies charged with
    operating the Albeni Falls Dam will do so in accordance with
    the status quo. Id.; see also Grand Canyon Trust, 691 F.3d at
    1022.
    Petitioner finally argues that implementing flexible winter
    operations requires an EIS because the continued operation of
    the Albeni Falls Dam is itself a major federal action that
    significantly affects the human environment. See 
    40 C.F.R. § 1508.18
    (a) (“Actions include new and continuing activities
    . . . .”). But decisions made as a part of the ongoing operation
    of a federal project must themselves “rise to the level of
    major federal actions to warrant preparation of an EIS.”
    Upper Snake River, 
    921 F.2d at
    235 n.3. Requiring an agency
    to prepare an EIS every time it takes an action consistent with
    past conduct would grind agency decisionmaking to a halt.
    Cf. Marsh v. Or. Nat. Res. Council, 
    490 U.S. 360
    , 373 (1989)
    (explaining that requiring a supplemental EIS every time new
    information is available “would render agency
    decisionmaking intractable”); Grand Canyon Trust, 691 F.3d
    at 1022 (noting it would be neither pragmatic nor realistic to
    require an agency to prepare an EIS when it engages in
    “routine and required annual reporting”).
    IDAHO CONSERVATION LEAGUE V. BPA                  11
    2. Petitioner claims the EA arbitrarily concludes that
    flexible winter operations will have only an incremental
    impact on the spread of the flowering rush, an invasive
    species that was discovered around Lake Pend Oreille in
    2008. Because the decision adopting flexible winter
    operations doesn’t trigger NEPA’s requirement to publish an
    EIS, this and Petitioner’s other challenges to the EA’s finding
    of no significant impact are moot. See Upper Snake River,
    
    921 F.2d at 234
    .
    Petitioner also argues in passing that, because the
    flowering rush has never been considered in a NEPA
    document, “BPA arbitrarily limited its analysis of flowering
    rush impacts to only the incremental impacts attributable to
    the new winter fluctuations; BPA never considered the
    significance of the spread of flowering rush in relation to the
    Dam’s year-round operation.” Agencies have a continuing
    duty to “prepare supplements to . . . final environmental
    impact statements” if there are “significant new
    circumstances or information relevant to environmental
    concerns” that were not considered in an earlier EIS.
    
    40 C.F.R. § 1502.9
    (c)(1); Marsh, 
    490 U.S. at
    372–74. The
    relevant EIS in this case is the 1995 Columbia River Power
    System Operation Review Environmental Impact Statement
    (SOR EIS), a programmatic EIS that evaluated a range of
    alternative management strategies for the 14 federal dams and
    reservoirs in the Columbia River Power System. The EA
    here acknowledges that the SOR EIS did not consider the
    effect of the dam’s operation on the flowering rush and
    characterizes the rush’s spread as “new information.” It
    nevertheless concludes that there are “no significant new
    circumstances or information” warranting preparation of a
    supplemental EIS.
    12        IDAHO CONSERVATION LEAGUE V. BPA
    Petitioner may well have a colorable claim that the
    agencies managing the Albeni Falls Dam must supplement
    the SOR EIS with an analysis of how year-round dam
    operations, as compared with flexible winter operations
    specifically, affect the “seemingly inevitable spread of this
    invasive species.” But this question is outside the scope of
    this case; Petitioner sought review of “the final decision . . .
    adopting the ‘Flexible Winter Power Operations’ at Albeni
    Falls Dam.” Petitioner’s opening brief similarly frames the
    issue as whether BPA violated NEPA by “approving the new
    winter operations without preparing an up-to-date EIS” and
    concludes by asking us to “reverse and remand the . . . EA
    approving the Flexible Winter Operations.” Petitioner only
    mentions in a footnote that BPA might need to prepare a
    supplemental EIS addressing the impact of year-round dam
    operations on the flowering rush. We do not “ordinarily
    consider matters on appeal that are not specifically and
    distinctly argued” in an opening brief, Laboa v. Calderon,
    
    224 F.3d 972
    , 985 (9th Cir. 2000), including those raised only
    in a footnote, see 
    id.
     at 985 n.8. A later agency decision or
    action may provide Petitioner occasion to challenge BPA’s
    failure to prepare a supplemental EIS addressing the
    flowering rush. But the time has passed to do so as part of a
    challenge to this EA.
    We address Petitioner’s remaining claims in a
    memorandum disposition filed concurrently herewith.
    DENIED.
    

Document Info

Docket Number: 12-70338

Citation Numbers: 826 F.3d 1173, 82 ERC (BNA) 1788, 2016 U.S. App. LEXIS 11175, 2016 WL 3430538

Judges: Kozinski, Fernandez, Davis

Filed Date: 6/21/2016

Precedential Status: Precedential

Modified Date: 11/5/2024