North Idaho Community Action Network v. United States Department of Transportation ( 2008 )


Menu:
  •                      FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    NORTH IDAHO COMMUNITY ACTION                
    NETWORK,
    Plaintiff-Appellant,
    v.
    UNITED STATES DEPARTMENT OF
    TRANSPORTATION; MARY E.
    PETERS,* U.S. Secretary of
    Transportation; UNITED STATES
    FEDERAL HIGHWAY ADMINISTRATION;                    No. 08-35283
    THOMAS J. MADISON, JR.,**
    Administrator, U.S. Federal                         D.C. No.
    2:05-CV-00273-EJL
    Highway Administration; PETER
    OPINION
    HARTMAN,*** Division
    Administrator, Idaho Division,
    U.S. Federal Highway
    Administration; EDWIN B. JOHNSON,
    Field Operations Engineer, Idaho
    Division, U.S. Federal Highway
    Administration; UNITED STATES
    FISH & WILDLIFE SERVICE; IDAHO
    TRANSPORTATION DEPARTMENT;
    
    *Mary E. Peters is substituted for her predecessor, Norman Mineta, as
    U.S. Secretary of Transportation, pursuant to Fed. R. App. P. 43(c)(2).
    **Thomas J. Madison, Jr., is substituted for his predecessor, Mary E.
    Peters, as Administrator of the U.S. Federal Highway Administration, pur-
    suant to Fed. R. App. P. 43(c)(2).
    ***Peter Hartman is substituted for his predecessor, Steve Mareno, as
    Division Administrator, Idaho Division, U.S. Federal Highway Adminis-
    tration, pursuant to Fed. R. App. P. 43(c)(2).
    14099
    14100        NORTH IDAHO COMMUNITY ACTION v. DOT
    PAMELA LOWE,**** Director, Idaho            
    Transportation Department,                  
    Defendants-Appellees.
    
    Appeal from the United States District Court
    for the District of Idaho
    Edward J. Lodge, District Judge, Presiding
    Argued and Submitted
    August 25, 2008—Seattle, Washington
    Filed October 6, 2008
    Before: Thomas G. Nelson, Michael Daly Hawkins, and
    Jay S. Bybee, Circuit Judges.
    Per Curiam Opinion
    ****Pamela Lowe is substituted for her predecessor, David S. Ekern,
    as Director, Idaho Transportation Department, pursuant to Fed. R. App. P.
    43(c)(2).
    NORTH IDAHO COMMUNITY ACTION v. DOT   14103
    COUNSEL
    Matthew K. Bishop, Western Environmental Law Center,
    Helena, Montana, for the plaintiff-appellant.
    14104      NORTH IDAHO COMMUNITY ACTION v. DOT
    Deborah A. Ferguson, Assistant United States Attorney,
    Office of the United States Attorney for the District of Idaho,
    Boise, Idaho, for appellee United States of America; Murray
    D. Feldman, Holland & Hart, LLP, Boise, Idaho, for appellees
    Idaho Transportation Department, et al.
    OPINION
    PER CURIAM:
    Plaintiff North Idaho Community Action Network
    (“NICAN”) appeals the district court’s grant of summary
    judgment in favor of defendants United States Department of
    Transportation (the “DOT”), Federal Highway Administra-
    tion, and Idaho Transportation Department (collectively, the
    “Agencies”). NICAN challenges a proposed highway con-
    struction project on a portion of U.S. Highway 95 located in
    northern Idaho. NICAN claims that the Agencies violated the
    National Environmental Policy Act (“NEPA”), 
    42 U.S.C. § 4321
     et seq., and Section 4(f) of the Department of Trans-
    portation Act, 
    49 U.S.C. § 303
    (c). We affirm in part, reverse
    in part, and remand with instructions.
    FACTS AND PROCEDURAL HISTORY
    U.S. Highway 95 (“US-95”) currently runs through the
    heart of downtown Sandpoint, Idaho, and is the only highway
    that ties northern Idaho to southern Idaho. The proposed high-
    way construction project (the “Project”) will improve US-95
    in and around Sandpoint.
    The Project will be funded and constructed in four separate
    phases. The first, second, and fourth phases involve widening
    the existing highway to four lanes. The third phase involves
    realigning an approximate two-mile stretch of US-95 to create
    a byway that will route the highway to the east of Sandpoint
    NORTH IDAHO COMMUNITY ACTION v. DOT          14105
    and remove through-traffic from the downtown Sandpoint
    area. Because the Agencies deem the third phase to be the
    most important phase of the Project, the Agencies have pro-
    ceeded with that phase first.
    In September 1999, the Agencies approved a final environ-
    mental impact statement (the “1999 EIS”) for the Project. In
    May 2000, the Agencies issued a record of decision (the
    “ROD”) for the Project. In the ROD, the Agencies selected
    the “Sand Creek Byway” as the preferred alternative for the
    third phase of the Project. As initially planned in the 1999
    EIS, the Sand Creek Byway involved constructing two miles
    of new two-lane highway along the east side of Sand Creek,
    building a partial interchange/bridge structure over Sand
    Creek and Bridge Street, and building a full diamond inter-
    change at the junction of US-95 and State Highway 200.
    In April 2005, the Agencies released an environmental
    assessment (the “2005 EA”) that included various changes to
    the Project design described in the 1999 EIS. These changes
    all relate to the third phase of the Project, the Sand Creek
    Byway, and were made in response to input from various
    members of the local community. The changes include traffic
    design modifications—such as building additional off-ramps
    and adding a third lane for safer merging—as well as aesthetic
    improvements and mitigation measures—such as constructing
    a pedestrian and bicycle pathway along Sand Creek and build-
    ing three artificial habitat enhancement areas in Sand Creek.
    The 2005 EA concluded that the changes to the Project design
    would not have significant impacts beyond those already con-
    sidered in the 1999 EIS. Based on this conclusion, the Agen-
    cies issued a Finding of No Significant Impact (“FONSI”).
    In August 2006, the Agencies prepared an environmental
    reevaluation (the “2006 Reevaluation”) covering the Project.
    The 2006 Reevaluation set forth additional changes to the
    Project design and assessed possible environmental effects of
    those changes. The majority of the changes involve dredging
    14106      NORTH IDAHO COMMUNITY ACTION v. DOT
    Sand Creek and will result in the removal of approximately
    17,035 cubic yards of material from Sand Creek. The 2006
    Reevaluation concluded that there was no additional signifi-
    cant impact and that neither a supplemental environmental
    impact statement (“SEIS”) nor an environmental assessment
    (“EA”) was required.
    In July 2005, after the Agencies released the 2005 EA and
    issued its FONSI determination, but before the Agencies pre-
    pared the 2006 Reevaluation, NICAN filed suit in the district
    court challenging the Agencies’ approval of the Project. On
    the parties’ cross-motions for summary judgment, the district
    court granted summary judgment in favor of the Agencies and
    against NICAN.
    NICAN moved for an injunction pending appeal, which the
    district court denied. NICAN then sought and obtained an
    injunction pending appeal from a motions panel of this court.
    After oral argument in this expedited appeal, we lifted the
    injunction and allowed construction of the Sand Creek Byway
    to commence. This Opinion sets forth the explanation for our
    decision.
    STANDARD OF REVIEW
    We review a district court’s grant of summary judgment de
    novo. Nw. Ecosystem Alliance v. U.S. Fish & Wildlife Serv.,
    
    475 F.3d 1136
    , 1140 (9th Cir. 2007). The Administrative Pro-
    cedure Act (“APA”) provides authority for the court’s review
    of decisions under NEPA and Section 4(f) of the Department
    of Transportation Act, 
    49 U.S.C. § 303
    (c). See Pit River Tribe
    v. U.S. Forest Serv., 
    469 F.3d 768
    , 778 (9th Cir. 2006);
    Alaska Ctr. for the Env’t v. Armbrister, 
    131 F.3d 1285
    , 1288
    (9th Cir. 1997). Under the APA, a reviewing court may set
    aside agency actions that are “arbitrary, capricious, an abuse
    of discretion, or otherwise not in accordance with law.” 
    5 U.S.C. § 706
    (2)(A). As this court recently explained:
    NORTH IDAHO COMMUNITY ACTION v. DOT           14107
    Review under the arbitrary and capricious standard
    is narrow, and we do not substitute our judgment for
    that of the agency. Rather we will reverse a decision
    as arbitrary and capricious only if the agency relied
    on factors Congress did not intend it to consider,
    entirely failed to consider an important aspect of the
    problem, or offered an explanation that runs counter
    to the evidence before the agency or is so implausi-
    ble that it could not be ascribed to a difference in
    view or the product of agency expertise.
    Lands Council v. McNair, 
    537 F.3d 981
    , 987 (9th Cir. 2008)
    (en banc) (internal quotations and citations omitted).
    DISCUSSION
    I.   NEPA
    “NEPA ‘is our basic national charter for protection of the
    environment.’ ” Ctr. for Biological Diversity v. Nat’l High-
    way Traffic Safety Admin., 
    538 F.3d 1172
    , 1185 (9th Cir.
    2008). Although NEPA does not impose any substantive
    requirements on federal agencies, it does impose procedural
    requirements. See Lands Council, 
    537 F.3d at 1000
    . Through
    these procedural requirements, NEPA seeks to make certain
    that agencies “ ‘will have available, and will carefully con-
    sider, detailed information concerning significant environ-
    mental impacts,’ and ‘that the relevant information will be
    made available to the larger [public] audience.’ ” 
    Id.
     (quoting
    Robertson v. Methow Valley Citizens Council, 
    490 U.S. 332
    ,
    349 (1989)).
    NICAN argues that the Agencies violated NEPA’s proce-
    dural requirements by (a) failing to consider alternatives to
    changes to the Project set forth in the 2005 EA, (b) failing to
    disclose and assess in the 2005 EA the impacts of dredging
    Sand Creek, (c) failing to consider a tunnel alternative for the
    Project, (d) failing to consider the impacts the Project will
    14108       NORTH IDAHO COMMUNITY ACTION v. DOT
    have on historical properties, and (e) failing to prepare a sup-
    plemental environmental impact statement. We address each
    of these claims in turn.
    A.    Failure to Consider Alternatives
    NICAN argues that the Agencies violated NEPA by failing
    to consider alternatives to the various changes to the Project
    design set forth in the 2005 EA. We disagree.
    [1] NEPA requires the agencies to “study, develop, and
    describe appropriate alternatives to recommended courses of
    action in any proposal which involves unresolved conflicts
    concerning alternative uses of available resources.” 
    42 U.S.C. § 4332
    (2)(E). This “alternatives provision” applies whether an
    agency is preparing an environmental impact statement
    (“EIS”) or an environmental assessment (“EA”), and requires
    the agency to give full and meaningful consideration to all
    reasonable alternatives. Native Ecosystems Council v. U.S.
    Forest Serv., 
    428 F.3d 1233
    , 1245 (9th Cir. 2005). However,
    “an agency’s obligation to consider alternatives under an EA
    is a lesser one than under an EIS.” 
    Id. at 1246
    . Thus, whereas
    with an EIS, an agency is required to “[r]igorously explore
    and objectively evaluate all reasonable alternatives,” see 
    40 C.F.R. § 1502.14
    (a), with an EA, an agency only is required
    to include a brief discussion of reasonable alternatives. See 
    40 C.F.R. § 1508.9
    (b).
    NICAN does not dispute that the Agencies adequately
    explored and evaluated reasonable alternatives to the Project
    in preparing the 1999 EIS. NICAN also does not challenge
    the Agencies’ selection, in the ROD, of the Sand Creek
    Byway as the preferred alternative. Rather, NICAN argues
    that the Agencies violated NEPA because they failed to con-
    sider alternatives to the various changes to the Project design
    set forth in the 2005 EA.
    [2] In the 2005 EA, the Agencies considered and briefly
    discussed two alternatives: the Project with the changes pro-
    NORTH IDAHO COMMUNITY ACTION v. DOT            14109
    posed in the 2005 EA, and the Project without the proposed
    changes (i.e., proceeding with the Project as previously
    described in the 1999 EIS). As discussed in Section I.E.
    below, the changes to the Project proposed in the 2005 EA
    will not result in significant environmental effects that were
    not previously evaluated in the 1999 EIS. Under these circum-
    stances, we hold that the Agencies fulfilled their obligations
    under NEPA’s alternatives provision when they considered
    and discussed only two alternatives in the 2005 EA. See
    Native Ecosystems, 
    428 F.3d at 1245-49
     (holding that the
    agency complied with NEPA’s alternatives provision in pre-
    paring an EA where the agency considered only two
    alternatives—a no action alternative and a preferred alterna-
    tive); 
    40 C.F.R. § 1508.9
    (b) (requiring only a brief discussion
    of reasonable alternatives in an EA).
    B.   Failure to Disclose/Analyze Dredging
    NICAN argues that the Agencies violated NEPA by failing
    to disclose and assess in the 2005 EA, or a supplemental EA,
    the impacts of dredging Sand Creek. We disagree.
    Prior to issuance of the 2005 EA, there were internal dis-
    cussions within the Agencies regarding the possible need for
    the excavation or dredging of Sand Creek. There also was,
    however, a good deal of uncertainty within the Agencies
    about whether dredging would be required and, if so, the
    extent of that dredging. For example, the initial application to
    the Army Corps of Engineers indicated a belief that no dredg-
    ing would be required. And shortly before the 2005 EA was
    issued, hydraulics engineers were still examining at least three
    dredging alternatives, and the design remained “subject to
    change.”
    The Agencies could not adequately or meaningfully evalu-
    ate the environmental impacts of any potential dredging until
    they had more information, which depended at least in part on
    ongoing discussions with the Army Corps of Engineers and
    14110      NORTH IDAHO COMMUNITY ACTION v. DOT
    the Clean Water Act permitting process. Once additional
    information regarding the proposed dredging was available,
    the Agencies performed the 2006 Reevaluation to analyze the
    dredging and its projected impacts, and to determine whether
    the new information required the preparation of a SEIS or a
    supplemental EA. See Idaho Sporting Cong. Inc. v. Alexan-
    der, 
    222 F.3d 562
    , 566 (9th Cir. 2000); Price Road Neighbor-
    hood Ass’n v. U.S. Dep’t of Transp., 
    113 F.3d 1505
    , 1510 (9th
    Cir. 1997); 
    23 C.F.R. § 771.129
    (a) (1988). The Agencies con-
    cluded that the dredging would not have significant environ-
    mental impacts beyond those already considered, and thus
    that neither a SEIS nor a supplemental EA was required.
    The Agencies’ use of the reevaluation process is substan-
    tially similar to that approved in Price Road, 
    113 F.3d at 1510
    , and we find no fault with the Agencies’ use of that pro-
    cess here.
    In Price Road, a freeway project initially contemplated two
    below-ground enclosed tunnels but was revised to include two
    fully-directional loop ramps instead of the tunnels. 
    Id. at 1507-08
    . The Agencies considered, in an environmental
    reevaluation, the environmental effects of the changes and
    determined there were no discernible differences in the level
    of environmental impacts beyond those previously consid-
    ered. 
    Id. at 1508
    . The agency thus did not prepare an EA or
    EIS for the changes. 
    Id.
    [3] We noted that, while NEPA does not specifically
    address how an agency should decide when changes require
    a more formal EA or EIS, the Federal Highway Administra-
    tion had specifically provided for reevaluations as a means to
    determine whether or not the approved environmental docu-
    ment remains valid. 
    Id.
     at 1509-10 (citing 
    23 C.F.R. § 771.129
    (c)). We thus concluded that if the agency, after the
    requisite “hard look” in a reevaluation, determines that the
    new impacts will not be significant (or not significantly dif-
    ferent from those already considered), then the agency is in
    NORTH IDAHO COMMUNITY ACTION v. DOT                    14111
    full compliance with NEPA and is not required to conduct a
    supplemental EA. 
    Id. at 1510
    ; see also Highway J Citizens
    Group v. Mineta, 
    349 F.3d 938
    , 959-60 (7th Cir. 2003) (hold-
    ing that when a “known issue came into sharper focus after
    the formal environmental documents were issued,” it was not
    improper to use internal reevaluation to analyze the issue).
    [4] In the present case, the Agencies took the requisite
    “hard look” at the impacts of dredging Sand Creek in the
    2006 Reevaluation, and determined that there were no new
    impacts that were significantly different than those already
    considered and that neither a SEIS nor a supplemental EA
    was therefore required. We hold that the Agencies did not act
    arbitrarily or capriciously in making those determinations, and
    that they complied with NEPA in their evaluation of the pro-
    posed dredging.1
    C.    Tunnel Alternative
    NICAN argues that the Agencies violated NEPA by failing
    to consider a new tunnel alternative for the Project. Again, we
    disagree.
    [5] Agencies have a continuing obligation to consider new
    information that comes to light, even after the issuance of an
    EIS. See 
    40 C.F.R. § 1502.9
     (c)(1)(ii) (requiring the agency to
    prepare supplements to either draft or final environmental
    impact statements if “[t]here are significant new circum-
    stances or information relevant to environmental concerns and
    1
    NICAN’s reliance on Idaho Sporting Cong., 
    222 F.3d at 566-67
    , is
    misplaced. In that case, this court already had determined there were defi-
    ciencies in the agency’s EA and EIS. Rather than issue a revised EA and
    EIS to address those deficiencies, the agency improperly attempted to
    address the deficiencies through issuance of a supplemental information
    report (“SIR”). In contrast, in the present case, as in Price Road, the
    reevaluation process was used not in an attempt to correct deficiencies in
    an EA or EIS, but instead to make an ex-ante decision about the need for
    a SEIS or supplemental EA.
    14112      NORTH IDAHO COMMUNITY ACTION v. DOT
    bearing on the proposed action or its impacts”); see also
    Marsh v. Oregon Natural Res. Council, 
    490 U.S. 360
    , 373-74
    (1989) (“[A]n agency need not supplement an EIS every time
    new information comes to light after the EIS is finalized. . . .
    On the other hand, . . . NEPA does require that agencies take
    a ‘hard look’ at the environmental effects of their planned
    action, even after a proposal has received initial approval.”);
    Friends of the Clearwater v. Dombeck, 
    222 F.3d 552
    , 558
    (9th Cir. 2000) (“When new information comes to light the
    agency must consider it, evaluate it, and make a reasoned
    determination whether it is of such significance as to require
    [a supplemental EIS].”) (internal quotation marks and citation
    omitted); Hughes River Watershed Conservancy v. Glickman,
    
    81 F.3d 437
    , 444-45 (4th Cir. 1996) (holding that the agency
    violated NEPA by failing to take a “hard look” at new infor-
    mation regarding zebra mussel infestation).
    [6] This continuing obligation, however, extends only to
    new information or circumstances regarding environmental
    impacts that may not have been appreciated or considered
    when the EIS was prepared. An agency is not required by
    NEPA to consider new alternatives that come to light after
    issuance of the EIS absent “substantial changes in the pro-
    posed action relevant to environmental concerns,” or “signifi-
    cant new circumstances or information relevant to
    environmental concerns and bearing on the proposed action or
    its impacts.” 
    40 C.F.R. § 1502.9
     (c)(1); see 
    40 C.F.R. § 1502.14
    .
    [7] Here, the tunnel alternative is not new “information” or
    a new “circumstance” regarding environmental impacts that
    may not have been appreciated or considered when the 1999
    EIS was prepared, and there is no substantial change in the
    Project that is “relevant to environmental concerns.” Accord-
    ingly, we hold that the Agencies did not violate NEPA by fail-
    NORTH IDAHO COMMUNITY ACTION v. DOT                    14113
    ing to consider the tunnel alternative when it was brought to
    their attention in 2006.2
    D.    Impacts to Historic Properties
    NICAN argues that the Agencies violated NEPA by: (1)
    taking a “phased approach” to how the Project will impact
    historic properties, and (2) failing to take a “hard look” at how
    the construction and operation of the Project will impact the
    Burlington Northern Railroad Depot (the “Depot”). We dis-
    agree and hold that the Agencies fully complied with NEPA
    on this issue.
    [8] NEPA requires federal agencies to consider the environ-
    mental impact of major federal action. See San Carlos Apache
    Tribe v. United States, 
    417 F.3d 1091
    , 1097 (9th Cir. 2005)
    (citing 
    42 U.S.C. § 4332
    (2)(C)); see also Coliseum Square
    Ass’n, Inc. v. Jackson, 
    465 F.3d 215
    , 223-25 (5th Cir. 2006).
    NEPA has no independent requirement that an agency exam-
    ine, separate and apart from any environmental impacts, the
    impact that a federal action will have on historic properties.
    NICAN’s reliance on NEPA regulations requiring consider-
    ation of environmental impacts to support its historic-
    property-impact argument is therefore misplaced.
    [9] Moreover, although an EIS is required to include “dis-
    cussions” of “historic and cultural resources,” see 
    40 C.F.R. § 1502.16
    (g), the Agencies’ 1999 EIS complied with this
    requirement. The 1999 EIS considered the impacts the Project
    is anticipated to have on historic properties, primarily focus-
    ing on the impacts of the Sand Creek Byway alternative ver-
    2
    Moreover, because the tunnel alternative was not raised and identified
    until June 2006, well after the notice and comment periods for the 1999
    EIS and the 2005 EA closed, any objection to the failure to consider that
    alternative has been waived. See Dep’t of Transp. v. Pub. Citizen, 
    541 U.S. 752
    , 764-65 (2004) (holding that objections to the failure to consider
    alternatives beyond those evaluated in the EA were forfeited by failure to
    identify additional alternatives during notice and comment period).
    14114        NORTH IDAHO COMMUNITY ACTION v. DOT
    sus a through-town couplet alternative. The Agencies
    ultimately chose the Sand Creek Byway alternative, in part
    because the through-town couplet alternative potentially
    would have impacted numerous historic sites, whereas the
    Sand Creek Byway alternative only would potentially impact
    the Depot and some underground sites.3
    The 1999 EIS recognized possible noise and vibration
    impacts, noted general steps that would be taken to minimize
    impacts, and indicated that additional surveys and mitigation
    measures would be undertaken after selection of the preferred
    route. The 2005 EA included a more detailed noise analysis
    following testing and modeling, which concluded that there
    were no significant adverse effects from the Project.4 The
    2005 EA also described various mitigation procedures to pro-
    tect the Depot from other construction activities, including the
    changes to the Project and ongoing monitoring, developed in
    consultation with the State Historic Preservation Officer
    (“SHPO”).5
    [10] We hold that the broad overview in the 1999 EIS of
    the Project’s impacts on historic properties, coupled with the
    specific, detailed analysis of the impacts of the Sand Creek
    Byway, and mitigation measures to minimize those impacts,
    was more than sufficient to meet NEPA’s requirements in
    relation to historic properties.6
    3
    These underground sites could be protected by simply preserving any-
    thing unearthed off-site.
    4
    We defer to the Agencies’ interpretation of these data. Lands Council,
    
    537 F.3d at 993-94
    .
    5
    In determining whether the potential construction effects would likely
    be significant, the Agencies are permitted to take into account mitigation
    measures which reduce the impact of construction. See Wetlands Action
    Network v. U.S. Army Corps of Eng’rs, 
    222 F.3d 1105
    , 1121 (9th Cir.
    2000).
    6
    The sufficiency of the Agencies’ analysis under Section 4(f) of the
    Department of Transportation Act, 
    49 U.S.C. § 303
    (c), is discussed sepa-
    rately in Section II.A. below.
    NORTH IDAHO COMMUNITY ACTION v. DOT            14115
    E.   Failure to Prepare a SEIS
    [11] An agency is not required to prepare a SEIS every
    time new information comes to light. See Marsh, 
    490 U.S. at 373
    . Rather, a SEIS is required only if changes, new informa-
    tion, or circumstances may result in significant environmental
    impacts “in a manner not previously evaluated and consid-
    ered.” Westlands Water Dist. v. Dep’t of Interior, 
    376 F.3d 853
    , 873 (9th Cir. 2004) (citation omitted). To assist the
    agency in determining whether a SEIS is required, an agency
    may prepare an environmental report (such as a reevaluation)
    or an EA. See 
    23 C.F.R. §§ 771.119
    (a), 771.129, 771.130(c).
    [12] Here the agencies prepared both an EA and a reevalua-
    tion. In these documents, the Agencies considered the changes
    to the Project and the impacts of those changes. Although the
    changes would have somewhat different impacts from those
    previously analyzed in the 1999 EIS, the Agencies determined
    that those impacts were not significant or adverse enough to
    require a SEIS.
    NICAN argues that the Agencies acted arbitrarily and
    capriciously by failing to prepare a SEIS regarding the
    changes to the Project discussed in the 2005 EA and the 2006
    Reevaluation. NICAN contends that a SEIS was required
    because of impacts to wetlands, cumulatively significant
    impacts, controversial or uncertain impacts, and adverse
    impact on historic sites. See 
    40 C.F.R. § 1508.27
    (b) (discuss-
    ing factors which should be considered in evaluating intensity
    of impact). We disagree and hold that a SEIS was not
    required.
    As modified, the Project affected only an additional 0.32
    acres of wetlands, which was also mitigated by construction
    of 1.1 acres of additional wetland area in a different location.
    See Wetlands Action Network, 
    222 F.3d at 1121
     (holding that
    an agency can consider mitigation effects that minimize the
    impacts of a project in determining the significance of the
    14116      NORTH IDAHO COMMUNITY ACTION v. DOT
    project’s environmental impact). Further, the changes to the
    Project relating to the Depot were in response to requests by
    the SHPO to mitigate and protect the Depot from adverse
    effects, and were not adverse consequences in and of them-
    selves. Cf. Enos v. Marsh, 
    769 F.2d 1263
    , 1373-74 (9th Cir.
    1985) (holding that it was not arbitrary and capricious for the
    agency to find no adverse effect on archeological sites when
    that finding was consistent with the opinion of a SHPO).
    Moreover, the uncertainty and controversy relied on by
    NICAN are not directed to the changes in the Project, but to
    the Sand Creek Bypass alternative itself. That alternative was
    discussed and evaluated in the 1999 EIS, and any challenge
    to the selection of that alternative has been waived. Cf. Dep’t
    of Transp., 
    541 U.S. at 764-65
     (holding that objections to the
    failure to consider alternatives beyond those evaluated in the
    EA were forfeited by failure to identify additional alternatives
    during notice and comment period).
    Finally, the Agencies sufficiently considered the cumula-
    tive impacts of the Project. In the 1999 EIS, the Agencies dis-
    cussed and analyzed the environmental impacts of the Project
    as initially proposed. In the 2005 EA and 2006 Reevaluation,
    the Agencies determined that the changes to the Project did
    not significantly impact the environment in a way not previ-
    ously considered. NICAN has pointed to nothing that con-
    vinces us that these determinations by the Agencies were
    inaccurate, let alone arbitrary or capricious.
    [13] We hold that the Agencies’ determination that the
    changes to the Project would not significantly impact the
    environment in a way not previously considered, and that a
    SEIS therefore was not required, was not arbitrary or capri-
    cious. See Marsh, 
    490 U.S. at 373-74
    ; see also Westlands
    Water Dist., 
    376 F.3d at 873
    .
    NORTH IDAHO COMMUNITY ACTION v. DOT            14117
    II.    Alleged Violations of Section 4(f) of the Department
    of Transportation Act
    All federally funded highway projects must comply with
    not only federal environmental protection laws, such as
    NEPA, but also with historic preservation laws, including
    Section 106 of the National Historic Preservation Act, 16
    U.S.C. § 470f (“§ 106”), and Section 4(f) of the Department
    of Transportation Act of 1966, 
    49 U.S.C. § 303
    (c) (“§ 4(f)”).
    Section 106 is a procedural statute that describes the pro-
    cess by which a project’s impacts to historical sites are identi-
    fied. It provides that before a federal agency may authorize
    the expenditure of funds for a federal or federally assisted
    project, the agency must first consider the effects of the proj-
    ect on “any district, site, building, structure, or object that is
    included in or eligible for inclusion in the National Register.”
    16 U.S.C. § 470f.
    Section 4(f), in contrast, imposes a substantive mandate.
    See 
    49 U.S.C. § 303
    (c). It allows a federal project “requiring
    the use of land of an historic site” to be approved only if “(1)
    there is no prudent and feasible alternative to using that land;
    and (2) the program or project includes all possible planning
    to minimize harm to the park, recreation area, wildlife and
    waterfowl refuge, or historic site resulting from the use.” 
    49 U.S.C. § 303
    (c) (emphasis added).
    NICAN argues that the Agencies violated § 4(f) by (a) fail-
    ing to survey, identify, and evaluate § 4(f) properties for all
    four phases of the Project, and (b) determining that a § 4(f)
    analysis was not required because the construction and opera-
    tion of the Project would not result in “use” of the Depot. We
    examine each of these claims in turn.
    A.    Failure to Evaluate § 4(f) Properties for all Four
    Phases of the Project
    NICAN argues that the Agencies violated § 4(f) by failing
    to survey for, identify, and evaluate the impacts on historic
    14118        NORTH IDAHO COMMUNITY ACTION v. DOT
    properties for all four phases of the Project as required by
    § 106 and § 4(f).
    The Agencies concede that they have taken a phased
    approach and have conducted a detailed § 106 identification
    process and § 4(f) evaluation only with respect to the Sand
    Creek Byway phase of the Project, and have not done so with
    respect to the remaining three phases of the Project. Further,
    the Agencies correctly point out that the regulations govern-
    ing the § 106 process allow a phased approach to identifying
    historic properties in some circumstances. See 
    36 C.F.R. § 800.4
    (b)(2); 
    36 C.F.R. § 800.8
    (a)(1).
    [14] However, § 4(f) and its regulations require that the
    § 4(f) evaluation be completed before an agency issues its
    ROD. See 
    23 C.F.R. § 771.135
    (b) (“Any use of lands from a
    section 4(f) property shall be evaluated early in the develop-
    ment of the action when alternatives to the proposed action
    are under study.”) (emphasis added); 
    23 C.F.R. § 771.135
    (i)
    (2007) (stating that evaluation of alternatives to using § 4(f)
    property should be presented in an EIS or EA); 
    23 C.F.R. § 771.135
    (l) (stating that if an EIS is required for a project,
    the agency should conduct the § 4(f) analysis in the EIS or
    ROD).7 And because the § 4(f) evaluation cannot occur until
    after the § 106 identification process has been completed, the
    § 106 process necessarily must be complete by the time the
    ROD is issued. See, e.g., 
    49 U.S.C. § 303
    (d)(2) (allowing the
    Secretary to find § 4(f) de minimis impact only if that deter-
    mination has been developed in the consultation process
    required under § 106).
    The District of Columbia Circuit reached the same conclu-
    7
    These regulations were in effect at the time of the Agencies’ decision
    in this case. They have been removed and replaced with similar ones as
    of April 11, 2008. 
    23 C.F.R. § 774.9
     (a) & (b) still provide that § 4(f)
    properties must be evaluated early while alternatives are under study, and
    that the § 4(f) approval should appear in the EIS or ROD.
    NORTH IDAHO COMMUNITY ACTION v. DOT                    14119
    sion in a markedly similar case, Corridor H Alternatives, Inc.
    v. Slater, 
    166 F.3d 368
     (D.C. Cir. 1999). In Corrider H, the
    agency approved a plan for building a lengthy highway corri-
    dor, which was divided into fourteen segments. 
    Id. at 371
    .
    The EIS selected an alternative that required the agency to
    identify historic properties in each segment in sequence and
    provided that no work would proceed where the treatment of
    historic properties had not been finalized. 
    Id.
     The ROD,
    approving the selected alternative, recognized that the § 4(f)
    evaluation could not be conducted until the § 106 identifica-
    tion process was completed. Id. at 371-72.
    The District of Columbia Circuit held that the agency was
    required to complete the § 4(f) process for the entire corridor
    project before issuing the ROD. See id. at 372-74 (citing 
    23 C.F.R. § 771.135
    ); see also Valley Cmty. Pres. Comm’n v.
    Mineta, 
    373 F.3d 1078
    , 1087-88 (10th Cir. 2004) (“Section
    4(f) regulations clearly require the FHWA to make the requi-
    site Section 4(f) evaluations prior to issuing an ROD approv-
    ing a proposed construction project.”); Benton Franklin
    Riverfront Trailway & Bridge Comm. v. Lewis, 
    701 F.2d 784
    ,
    788-89 (9th Cir. 1983) (criticizing agency for failing to com-
    plete Section 4(f) analysis earlier).8
    [15] We hold, consistently with the District of Columbia
    Circuit’s decision in Corrider H, that an agency is required to
    complete the § 4(f) evaluation for the entire Project prior to
    issuing its ROD.
    8
    The Agencies’ reliance on City of Alexandria v. Slater, 
    198 F.3d 862
    (D.C. Cir. 1999), is misplaced. In Slater, the agency identified historic
    properties along the entire project corridor, and documented its findings
    in a Memorandum of Agreement and a § 4(f) evaluation; the agency
    deferred only the determination of whether some ancillary construction
    activities might also impact § 4(f) properties. Id. at 873. In contrast, here
    the Agencies concede that they have conducted the § 106 identification
    process and § 4(f) evaluation only as to the Sand Creek Byway phase of
    the project, and have not conducted the necessary identification and evalu-
    ation for the other phases of the Project.
    14120      NORTH IDAHO COMMUNITY ACTION v. DOT
    [16] The Agencies concede that they have taken a phase-
    by-phase approach, that they have not completed the § 4(f)
    evaluation for the entire Project, and that they already have
    issued the ROD. The Agencies have accordingly violated
    § 4(f). We therefore reverse the district court’s grant of sum-
    mary judgment on this issue.
    B.    “Use” of the Depot
    In the 1999 EIS, the Agencies performed a § 4(f) evalua-
    tion with respect to the Depot. The Agencies concluded that
    there was no feasible and prudent alternative to the use of the
    Depot and that the proposed action included all possible plan-
    ning to minimize harm to the Depot, thus allowing the Project
    to proceed. See 
    49 U.S.C. § 303
    (c)(1).
    NICAN does not challenge the Agencies’ § 4(f) evaluation
    contained in the 1999 EIS. Instead, NICAN argues that the
    Agencies acted arbitrarily and capriciously when they deter-
    mined that modifications to the Project set forth in the 2005
    EA will not “use” the Depot for purposes of § 4(f), and that
    a formal § 4(f) evaluation was therefore not required in rela-
    tion to those modifications.
    The modifications at issue came about as a result of the
    Agencies’ agreement with the SHPO to perform certain
    repairs and make certain improvements to the Depot. The
    agreed-to repairs include removing the sandstone water table
    course, replacing missing bricks, repointing all masonry
    joints, and reconstructing a concrete curb and walkway at the
    west side. The agreed-to improvements include paving the
    Depot access road and parking areas, adding lighting to the
    pedestrian parking area, and building a handicap access ramp
    and brick pathway connecting the parking area to the Depot.
    These “modifications” will not have an “adverse effect” on
    the Depot, but are instead improvements that inure to the ben-
    efit of the Depot. See 
    49 U.S.C. § 303
    (c), (d)(2). And,
    although occurring on Depot property, these improvements do
    NORTH IDAHO COMMUNITY ACTION v. DOT                    14121
    not “permanently incorporate[ ] [the land] into a transporta-
    tion facility” to bring it within the parameters of § 4(f). See
    
    23 C.F.R. § 771.135
    (p)(1) (2000);9 see also Laguna Green-
    belt, Inc. v. U.S. Dept. of Transp., 
    42 F.3d 517
    , 533 (9th Cir.
    1994) (holding that properties were not actually or construc-
    tively used in a proposed project where the project would
    not “substantially impair the current features, activities and
    attributes” of parklands and bike paths). These improve-
    ments do not, therefore, involve a “use” of the Depot property
    under § 4(f). See 
    49 U.S.C. § 303
    (c), (d)(2); 
    23 C.F.R. § 771.135
    (p)(1) (2000).
    Other modifications to the Project—such as installing a
    construction fence and mesh grating, and excavating a trench
    —involve activities that are temporary and minor, that have
    been approved by the SHPO, and from which the land will be
    fully restored. These activities also do not, therefore, involve
    a “use” of the Depot property under § 4(f). See 
    23 C.F.R. § 771.135
    (p)(7) (describing when a temporary occupancy is
    so minimal it does not constitute a “use”).
    [17] We hold that the Agencies did not act arbitrarily or
    capriciously in determining that the modifications to the Proj-
    ect discussed in the 2005 EA would not “use” the Depot prop-
    erty within the meaning of § 4(f).
    III.   Remedy
    Although we conclude the Agencies violated § 4(f) by fail-
    ing to conduct the § 4(f) evaluation for the entire Project prior
    to issuing the ROD, we find it unnecessary to enjoin the entire
    Project while the Agencies complete the necessary evaluation.
    All parties agree that the § 4(f) evaluation has been completed
    with respect to the Sand Creek Byway phase of the Project.
    9
    This was the regulation in effect at the time of the Agencies’ decision;
    it has now been removed and repromulgated in substantially the same
    form at 
    23 C.F.R. § 774.17
     (2008).
    14122        NORTH IDAHO COMMUNITY ACTION v. DOT
    The Sand Creek Byway has independent viability, beginning
    and ending at points on existing US-95, and the Sand Creek
    Byway will accomplish many goals of the overall Project.
    [18] On the unique facts of this case, we conclude that the
    scope of injunctive relief should be limited to precluding the
    Agencies from commencing construction of the remaining
    three phases of the Project until the § 4(f) evaluation has been
    fully completed. See, e.g., Sierra Club v. Bosworth, 
    510 F.3d 1016
    , 1034 (9th Cir. 2007) (after noting that some projects
    were already approved and in operational stages, limiting
    injunctive relief to projects that were approved after initiation
    of the lawsuit and giving the district court discretion to also
    exclude some projects that were approved later but already at
    or near completion); Nat’l Parks & Conservation Ass’n v.
    Babbitt, 
    241 F.3d 722
    , 739 (9th Cir. 2001) (limiting the scope
    of injunctive relief to two components of vessel management
    plan). We therefore remand to the district court with instruc-
    tions to enter an appropriate injunction in accordance with our
    decision. See Nat’l Parks, 
    241 F.3d at 740
    .10
    AFFIRMED IN PART, REVERSED IN PART, AND
    REMANDED WITH INSTRUCTIONS. Each party to bear
    its own costs on appeal.
    10
    Nothing in this decision shall be deemed to preclude NICAN or any
    other interested party from challenging the Agencies’ § 106 identification
    process and § 4(f) evaluation, once completed, with respect to the remain-
    ing phases of the Project.
    

Document Info

Docket Number: 08-35283

Judges: Nelson, Hawkins, Bybee

Filed Date: 10/6/2008

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (24)

pit-river-tribe-native-coalition-for-medicine-lake-highlands-defense-mount ( 2006 )

wetlands-action-network-a-california-non-profit-organization-ballona ( 2000 )

idaho-sporting-congress-inc-the-ecology-center-v-david-alexander ( 2000 )

the-laguna-greenbelt-inc-a-california-non-profit-corporation-the-laguna ( 1994 )

the-benton-franklin-riverfront-trailway-and-bridge-committee-v-drew-lewis ( 1983 )

alaska-center-for-the-environment-alaska-wilderness-recreation-and-tourism ( 1997 )

northwest-ecosystem-alliance-center-for-biological-diversity-tahoma-audubon ( 2007 )

Corridor H Alternatives, Inc. v. Slater ( 1999 )

City of Alexandria, Virginia,appellees v. Rodney E. Slater, ... ( 1999 )

Valley Community Preservation Commission v. Mineta ( 2004 )

national-parks-conservation-association ( 2001 )

friends-of-the-clearwater-idaho-sporting-congress-inc-the-northern ( 2000 )

Marsh v. Oregon Natural Resources Council ( 1989 )

The Lands Council v. McNair ( 2008 )

Sierra Club v. Bosworth ( 2007 )

native-ecosystems-council-v-united-states-forest-service-an-agency-of-the ( 2005 )

coliseum-square-association-inc-smart-growth-for-louisiana-louisiana ( 2006 )

westlands-water-district-san-luis-delta-mendota-water-authority-v-united ( 2004 )

highway-j-citizens-group-v-norman-mineta-in-his-official-capacity-as ( 2003 )

hughes-river-watershed-conservancy-an-unincorporated-association-sierra ( 1996 )

View All Authorities »