Kiewit Power Constructors Co. v. City of Los Angeles ( 2020 )


Menu:
  •                             NOT FOR PUBLICATION                          FILED
    UNITED STATES COURT OF APPEALS                        MAY 8 2020
    MOLLY C. DWYER, CLERK
    U.S. COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    KIEWIT POWER CONSTRUCTORS CO.,                  No.    18-56218
    a Delaware corporation,
    D.C. No.
    Plaintiff-counter-                        2:16-cv-02590-AB-GJS
    defendant-Appellee,
    v.                                             MEMORANDUM*
    CITY OF LOS ANGELES, acting by and
    through the Department of Water and
    Power,
    Defendant-counter-claimant-
    Appellant.
    KIEWIT POWER CONSTRUCTORS CO.,                  No.    18-56537
    a Delaware corporation,
    D.C. No.
    Plaintiff-counter-                        2:16-cv-02590-AB-GJS
    defendant-Appellant,
    v.
    CITY OF LOS ANGELES, acting by and
    through the Department of Water and
    Power,
    Defendant-counter-claimant-
    Appellee.
    *
    This disposition is not appropriate for publication and is not precedent
    except as provided by Ninth Circuit Rule 36-3.
    Appeal from the United States District Court
    for the Central District of California
    Andre Birotte, Jr., District Judge, Presiding
    Submitted May 4, 2020**
    Pasadena, California
    Before: OWENS and BADE, Circuit Judges, and MOSKOWITZ,*** District
    Judge.
    The City of Los Angeles, acting through the Department of Water and
    Power (“LADWP”), appeals from the judgment and award of damages for the
    breach of the implied covenant of good faith and fair dealing to Kiewit Power
    Constructors Co. (“Kiewit”), and the district court’s prior denial of LADWP’s
    motion for summary judgment. LADWP also appeals the denial of its motion for a
    judgment as a matter of law and post-judgment motions. Kiewit cross-appeals
    from post-trial rulings denying prejudgment interest and costs. We have
    jurisdiction pursuant to 
    28 U.S.C. § 1291
    , and we affirm.
    1.     LADWP contends that the jury’s verdict should be vacated as a matter
    of law because it is contrary to California law regarding public works contracts.
    Under California law, “public works contracts are the subject of intensive statutory
    **
    The panel unanimously concludes this case is suitable for decision
    without oral argument. See Fed. R. App. P. 34(a)(2).
    ***
    The Honorable Barry Ted Moskowitz, United States District Judge for
    the Southern District of California, sitting by designation.
    2
    regulation and lack the freedom of modification present in private party contracts.”
    P&D Consultants, Inc. v. City of Carlsbad, 
    119 Cal. Rptr. 3d 253
    , 262 (Ct. App.
    2010) (emphasis in original) (quoting Amelco Elec. v. City of Thousand Oaks, 
    38 P.3d 1120
    , 1129 (Cal. 2002)). Lower California courts have recognized that public
    contracts cannot be modified orally, enforced by estoppel, or enforced under quasi-
    contract theories or implied-in-fact contract theories. See, e.g., Green Valley
    Landowners Assoc. v. City of Vallejo, 
    194 Cal. Rptr. 3d 19
    , 29 (Ct. App. 2015);
    Katsura v. City of San Buenaventura, 
    65 Cal. Rptr. 3d 762
    , 765 (Ct. App. 2007).
    But the California Supreme Court recognizes that the implied covenant of good
    faith and fair dealing applies in all contracts. Cates Constr., Inc. v. Talbot
    Partners, 
    980 P.2d 407
    , 415 (Cal. 1999) (citing Foley v. Interactive Data Corp.,
    
    765 P.2d 373
    , 389 (Cal. 1988)). Here, both LADWP and Kiewit asserted and
    prevailed on claims of the implied covenant of good faith and fair dealing.1
    LADWP recognizes that the key issue on appeal is the scope of that covenant in
    this case. See Carma Developers, Inc. v. Marathon Dev. Cal., Inc., 
    826 P.2d 710
    ,
    727 (Cal. 1992) (“[T]he scope of conduct prohibited by the covenant of good faith
    is circumscribed by the purposes and express terms of the contract.”). Considering
    the California Supreme Court’s recognition that the implied covenant of good faith
    1
    LADWP did not object to the jury instructions or the special verdict form that
    included Kiewit’s breach of the implied covenant of good faith and fair dealing.
    3
    and fair dealing applies in all contracts, we decline to vacate the jury’s verdict in
    this case as a matter of law.
    2.     LADWP contends that if the implied covenant of good faith and fair
    dealing applies, the judgment awarding Kiewit damages should be vacated because
    application of that covenant circumvents the express language of the parties’
    contract and, thus, Kiewit did not have a reasonable expectation of payment. The
    implied covenant of good faith and fair dealing only protects “legitimate
    expectations of the parties which arise from the contract.” Brandt v. Lockheed
    Missiles & Space Co., 
    201 Cal. Rptr. 746
    , 749 (Ct. App. 1984) (citation omitted).
    Although Kiewit did not comply with the contract’s provision governing change
    orders, section 3.16, that provision was not the sole mechanism for Kiewit to seek
    additional compensation for costs it incurred to meet the original substantial
    completion date despite the delayed delivery of key equipment by LADWP’s
    original equipment manufacturer (“OEM”). Section 3.19 provided another means
    for Kiewit to protest and seek additional compensation if Kiewit considered
    LADWP’s demands “outside the requirements of” the contract. As the district
    court found, summary judgment was not appropriate because a genuine issue
    existed on whether LADWP made demands outside the requirements of the
    contract, thereby triggering section 3.19. See Fed. R. Civ. P. 56(a).
    The evidence supports a conclusion that Kiewit considered LADWP’s
    4
    demand that Kiewit meet the original substantial completion date despite the
    OEM’s late equipment delivery to be outside the requirements of the contract.
    Thus, applying the implied covenant of good faith and fair dealing does not create
    obligations that are inconsistent with the terms of the contract. Carma Developers,
    
    826 P.2d at 727
    .
    LADWP further argues that Kiewit did not comply with the requirements for
    submitting a claim under section 3.19 and, thus, still lacked a legitimate
    expectation of payment arising from the contract. See Brandt, 201 Cal. Rptr. at
    749. A genuine issue of fact on whether Kiewit’s communications with LADWP
    satisfied section 3.19’s requirements precluded summary judgment in favor of
    LADWP. See Fed. R. Civ. P. 56(a).
    Construing the evidence in favor of Kiewit, as we must on review of the
    denial of LADWP’s Rule 50 motions, does not lead to only one conclusion that is
    contrary to the jury’s verdict. See Pavao v. Pagay, 
    307 F.3d 915
    , 918 (9th Cir.
    2002). The evidence supports the conclusion that, on February 10, 2016,
    LADWP’s tone changed from its earlier communications indicating that it was
    considering Kiewit’s requests for additional compensation. Considering that shift,
    Kiewit’s March 2, 2016 letter taking issue with LADWP’s position that the
    “parties had agreed to a schedule without cost implications” was promptly
    delivered. The jury could have reasonably concluded the March 2, 2016 letter was
    5
    a protest for additional compensation under section 3.19(A). Section 3.19(A) did
    not specify the form of a “written statement of protest,” and the March 2, 2016
    letter expressed Kiewit’s dissent to LADWP’s position and thus, was a protest
    under that word’s plain meaning. See Protest, Black’s Law Dictionary (11th ed.
    2019) (A protest is “a formal statement or action expressing dissent or
    disapproval”); see also Valencia v. Smyth, 
    110 Cal. Rptr. 3d 180
    , 185-86 (Ct. App.
    2010) (recognizing the plain meaning rule).
    The jury could also have reasonably concluded that Kiewit certified that it
    believed the damages requested in its claim actually and accurately reflected
    LADWP’s liability. Section 3.19(C) of the contract required that “all claims” shall
    be so certified but did impose a certification requirement on the written statement
    of protest. While the March 2, 2016 letter did not use the word “certify” or the
    other language in section 3.19(C), it indicated that Kiewit was submitting its cost
    information pursuant to LADWP’s requests and attached supporting
    documentation regarding Kiewit’s costs. Considering the ambiguity in section
    3.19’s provisions, the jury reasonably could have concluded that, when considered
    as a whole, the March 2, 2016 letter and supporting documentation regarding
    Kiewit’s costs certified that Kiewit believed LADWP was liable for those costs in
    compliance with section 3.19(C).
    Because the contract provided a mechanism for Kiewit to seek additional
    6
    compensation, section 3.19, and because the jury could reasonably conclude that
    Kiewit satisfied section 3.19’s requirements for a protest, Kiewit had a reasonable
    expectation of payment and the implied covenant of good faith and fair dealing
    created a duty for LADWP to negotiate Kiewit’s protest and the amount of
    compensation. Therefore, we reject LADWP’s argument that the judgment
    awarding Kiewit damages should be vacated on the ground that the application of
    the implied covenant of good faith and fair dealing circumvents the express
    language of the parties’ contract. See Carma Developers, 
    826 P.2d at 727
    .
    3.     Prejudgment interest is a substantive matter governed by California
    law. See Sea Hawk Foods, Inc. v. Exxon Corp. & Exxon Shipping Co. (In re Exxon
    Valdez), 
    484 F.3d 1098
    , 1101 (9th Cir. 2007). Under California Civil Code section
    3287(a), a court must award prejudgment interest when a plaintiff is “entitled to
    recover damages certain, or capable of being made certain by calculation.” For
    purposes of section 3287(a), “[d]amages are deemed certain or capable of being
    made certain . . . where there is essentially no dispute between the parties
    concerning the basis of the computation of damages if any are recoverable but
    where their dispute centers on the issue of liability giving rise to damages.”
    Warren v. Kia Motors Am., Inc., 
    241 Cal. Rptr. 3d 263
    , 280-81 (Ct. App. 2018)
    (internal quotation omitted). But section 3287(a) does not “authorize prejudgment
    interest where the amount of damages . . . depends upon a judicial determination
    7
    based upon conflicting evidence [and] . . . cannot be resolved except by verdict or
    judgment.” 
    Id.
     (alteration and quotation omitted). We review the district court’s
    denial of prejudgment interest for abuse of discretion. Champion Produce, Inc. v.
    Ruby Robinson Co., Inc., 
    342 F.3d 1016
    , 1020 (9th Cir. 2003).
    The district court applied section 3287(a) and concluded that Kiewit was not
    entitled to prejudgment interest because the amount of damages was not certain until
    the jury’s verdict. The amount of damages Kiewit requested varied over time by
    over $2 million. This difference is not minor. See Chesapeake Indus., Inc. v. Togova
    Enters., Inc., 
    197 Cal. Rptr. 348
    , 354 (Ct. App. 1983) (finding that the “large
    discrepancy” between the amount claimed, $115,000.00, and the final judgment,
    $34,830.04, supported the conclusion that the amount was not calculable).
    Additionally, as the district court noted, productivity losses was the major category
    of Kiewit’s additional costs. Kiewit’s own expert testified that there are several
    bases for measuring productivity on a construction site and many different methods
    for determining what productivity loss is attributable to what cause. The parties
    disputed the methods for determining Kiewit’s costs, whether Kiewit had provided
    information sufficient to determine those costs, and the accuracy of Kiewit’s
    assumptions about those costs. Kiewit itself offered several different methods for
    calculating its costs and reduced its evaluation of damages during the litigation.
    Considering the foregoing, the district court did not abuse its discretion in denying
    8
    Kiewit prejudgment interest. See id.; Nicholson-Brown, Inc. v. City of San Jose, 
    133 Cal. Rptr. 159
    , 164-65 (Ct. App. 1976), disapproved of on other grounds by Bullis
    v. Sec. Pac. Nat’l Bank, 
    582 P.2d 109
     (Cal. 1978).
    4.     Federal Rule of Civil Procedure 54(d) governs the award of costs
    “even in diversity cases.” Champion Produce, 
    342 F.3d at 1022
    . Rule 54(d)
    creates a presumption in favor of awarding costs to the prevailing party. See Fed.
    R. Civ. P. 54(d). But when the judgment is mixed, the district court has the
    discretion to require “each party to bear its own costs.” Amarel v. Connell, 
    102 F.3d 1494
    , 1523 (9th Cir. 1996). This court reviews for an abuse of discretion a
    district court’s decision to award or deny costs. Ass’n of Mexican-Am. Educators
    v. California, 
    231 F.3d 572
    , 592 (9th Cir. 2000) (en banc).
    Here, the district court gave sufficient reasons for denying costs to Kiewit
    including that the judgment was mixed, the issues in the case were close and
    difficult, and the difficulty of allocating costs. These are appropriate reasons for
    denying costs. See Champion Produce, 
    342 F.3d at 1023
    ; Amarel, 102 F.3d at
    1523. Because the district court provided sufficient reasons to supports its
    decision, it did not abuse its discretion in denying Kiewit costs.
    AFFIRMED. Each party shall bear its own costs on appeal.
    9