Leopoldo Mendoza v. Fonseca McElroy Grinding Co. , 913 F.3d 911 ( 2019 )


Menu:
  •                        FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    LEOPOLDO PENA MENDOZA;                        No. 17-15221
    JOSE ARMANDO CORTES; ELVIZ
    SANCHEZ,                                        D.C. No.
    Plaintiffs-Appellants,           3:15-cv-05143-WHO
    v.
    ORDER
    FONSECA MCELROY GRINDING                    CERTIFYING
    CO., INC.; GRANITE ROCK                   QUESTION TO THE
    COMPANY,                                    CALIFORNIA
    Defendants-Appellees.            SUPREME COURT
    Filed January 15, 2019
    Before: RAYMOND C. FISHER and MILAN D. SMITH,
    JR., Circuit Judges, and ELAINE E. BUCKLO, * District
    Judge.
    Order
    *
    The Honorable Elaine E. Bucklo, United States District Judge for
    the Northern District of Illinois, sitting by designation.
    2     MENDOZA V. FONSECA MCELROY GRINDING CO.
    SUMMARY **
    Labor Law
    The panel certified the following question to the
    California Supreme Court:
    Is operating engineers’ offsite “mobilization
    work”—including the transportation to and
    from a public works site of roadwork
    grinding equipment—performed “in the
    execution of [a] contract for public work,”
    Cal. Lab. Code § 1772, such that it entitles
    workers to “not less than the general
    prevailing rate of per diem wages for work of
    a similar character in the locality in which the
    public work is performed” pursuant to
    section 1771 of the California Labor Code?
    ORDER
    This appeal requires us to resolve whether offsite
    mobilization work conducted in connection with a public
    works project is performed “in the execution of [a] contract
    for public work” such that it entitles workers to prevailing
    wages pursuant to the California Labor Code. Cal. Lab.
    Code §§ 1771–72. Whether the scope of the prevailing wage
    law is expanded or limited, the answer to this question could
    have a significant impact on California workers.
    **
    This summary constitutes no part of the opinion of the court. It
    has been prepared by court staff for the convenience of the reader.
    MENDOZA V. FONSECA MCELROY GRINDING CO.                    3
    We find no controlling precedent in the decisions of the
    California Supreme Court or Courts of Appeal, see Cal. R.
    Ct. 8.548(a)(2), and “considerations of comity and
    federalism suggest that the court of last resort in California,
    rather than our court, should have the opportunity to answer
    the question in the first instance.” Busker v. Wabtec Corp.,
    
    903 F.3d 881
    , 882 (9th Cir. 2018). We therefore respectfully
    ask the Supreme Court of California to exercise its discretion
    to decide the certified question set forth in Part I of this order.
    I. Certified Question
    Pursuant to Rule 8.548 of the California Rules of Court,
    we request that the California Supreme Court answer the
    following question of state law:
    Is operating engineers’ offsite “mobilization
    work”—including the transportation to and
    from a public works site of roadwork
    grinding equipment—performed “in the
    execution of [a] contract for public work,”
    Cal. Lab. Code § 1772, such that it entitles
    workers to “not less than the general
    prevailing rate of per diem wages for work of
    a similar character in the locality in which the
    public work is performed” pursuant to
    section 1771 of the California Labor Code?
    The Court may reformulate our question, and its exposition
    of the issues involved should not be limited by the question’s
    phrasing. Cal. R. Ct. 8.548(f)(5). We will accept and follow
    the Court’s decision. Cal. R. Ct. 8.548(b)(2).
    4    MENDOZA V. FONSECA MCELROY GRINDING CO.
    II. Background
    Plaintiffs-Appellants Leopoldo Pena Mendoza, Elviz
    Sanchez, and Jose Armando Cortes (Plaintiffs) are operating
    engineers and members of Operating Engineers Local No. 3.
    They worked on grinding crews, using milling equipment to
    break up and crush asphalt roadbeds so that new roads could
    be constructed. At times, their work duties included what
    they referred to as “mobilization” work, which
    entailed loading milling machines, which
    w[ere] stored at [a] permanent yard or in
    offsite storage locations, onto a lowbed
    trailer; tying down or otherwise securing the
    heavy equipment onto the lowbed trailer;
    performing a light, brake, and fluid level
    check of a semi-truck used to transport the
    heavy equipment; driving a transport truck
    transporting the milling machine to a
    construction jobsite; and driving the transport
    truck transporting the milling machine back
    to [the] permanent yard.
    As part of this mobilization process, Plaintiffs reported to a
    designated yard where the equipment was housed, and then
    performed the maintenance and transportation work.
    Neither the permanent yard nor the offsite storage locations
    depended on any public works project for their existence.
    Defendant-Appellee Fonseca McElroy Grinding Co. Inc.
    (FMG), a roadwork construction company, was acquired by
    Defendant-Appellee Granite Rock Company (Granite Rock,
    and together with FMG, Defendants) in 2014. FMG and
    Granite Rock were both signatory parties to the Operating
    Engineers Local No. 3 Master Agreement for Northern
    California (Master Agreement). In 2010, FMG entered into
    MENDOZA V. FONSECA MCELROY GRINDING CO.                          5
    an additional Memorandum of Agreement (MOA) with
    Local No. 3, which provided for a “Lowbed Transport” wage
    rate for mobilization work; this rate for offsite work was
    lower than the Master Agreement rates for onsite
    construction. Granite Rock was also a signatory to the
    MOA.
    Plaintiffs worked for FMG and then Granite Rock,
    including on public works construction projects, and
    received compensation based on the Master Agreement and
    MOA. Accordingly, although they received a prevailing
    wage for onsite construction on public works projects, they
    were not paid a prevailing wage for offsite mobilization
    work. Plaintiffs estimate that “[t]he ballpark difference
    between the two overtime rates in August [] 2012 was
    $67.72 (prevailing wage) and $23.89 (lowbed
    transportation) for an underpayment of $38.38 in the base
    pay.” Defendants note that “[t]he public works contracts
    under which Plaintiffs worked did not specify the daily
    schedule for Granite Rock’s workers,” and “[t]hus Granite
    Rock determined whether [they] would report directly to the
    construction jobsite or its yard” and “what tasks, if any,
    [they] would perform after completing their jobsite work.” 1
    On November 9, 2015, Mendoza brought claims under
    the Fair Labor Standards Act and California labor laws for
    nonpayment of wages. Three months later, he, along with
    Sanchez and Cortes, filed an amended complaint.
    The parties addressed the dispute that forms the basis of
    this appeal through cross-motions for partial summary
    judgment, which the district court heard on October 26,
    1
    The contracts for the specific work at issue in this case were not
    included in the record before us.
    6       MENDOZA V. FONSECA MCELROY GRINDING CO.
    2016. On November 28, 2016, the court entered an order in
    which it concluded that the offsite mobilization of equipment
    was not “in the execution” of a public works contract.
    Mendoza v. Fonseca McElroy Grinding Co., No. 15-cv-
    05143-WHO, 
    2016 WL 6947552
    , at *1 (N.D. Cal. Nov. 28,
    2016). Following this determination, the parties settled all
    remaining issues, except the dispute now before us.
    A timely appeal to this court followed, raising the
    question of California law posed in Part I.
    III.      Explanation of Request for Certification
    Under California law, “not less than the general
    prevailing rate of per diem wages for work of a similar
    character in the locality in which the public work is
    performed . . . shall be paid to all workers employed on
    public works.” Cal. Lab. Code § 1771. This prevailing
    wage requirement applies to “[w]orkers employed by
    contractors or subcontractors in the execution of any contract
    for public work.” 
    Id. § 1772
    (emphasis added).
    The California Supreme Court has explained that
    [t]he overall purpose of the prevailing wage
    law . . . is to benefit and protect employees on
    public works projects. This general objective
    subsumes within it a number of specific
    goals: to protect employees from substandard
    wages that might be paid if contractors could
    recruit labor from distant cheap-labor areas;
    to permit union contractors to compete with
    nonunion contractors; to benefit the public
    through the superior efficiency of well-paid
    employees; and to compensate nonpublic
    employees with higher wages for the absence
    MENDOZA V. FONSECA MCELROY GRINDING CO.                7
    of job security and employment benefits
    enjoyed by public employees.
    Lusardi Constr. Co. v. Aubry, 
    824 P.2d 643
    , 649 (Cal. 1992).
    It has also emphasized that the prevailing wage law should
    be construed liberally. City of Long Beach v. Dep’t of Indus.
    Relations, 
    102 P.3d 904
    , 908 (Cal. 2004).
    On appeal, we are asked to determine whether Plaintiffs
    were employed “in the execution of” a public works contract
    when they performed offsite mobilization work, including
    maintenance and transportation of equipment.
    A. Related Precedent
    We note, as did the district court, that California courts
    have not previously addressed the applicability of the
    prevailing wage statute to offsite mobilization work
    performed by workers employed on public works projects.
    See Mendoza, 
    2016 WL 6947552
    , at *1. However, the
    analytical framework developed in two California Court of
    Appeal decisions—Williams v. SnSands Corporation,
    
    67 Cal. Rptr. 3d 606
    (Ct. App. 2007), and Sheet Metal
    Workers’ International Association, Local 104 v. Duncan,
    
    176 Cal. Rptr. 3d 634
    , 650 (Ct. App. 2014)—might provide
    guidance.
    In Williams, the Court of Appeal addressed whether a
    material subcontractor’s truck drivers who hauled materials
    away from a public works site were employed “in the
    execution of” a public works contract or, like bona fide
    material suppliers, were exempt from the prevailing wage
    
    requirement. 67 Cal. Rptr. 3d at 610
    , 613–14. To resolve
    this issue, the court explained that it needed to determine
    “the role the transport of the materials plays in the
    8       MENDOZA V. FONSECA MCELROY GRINDING CO.
    performance or ‘execution’ of the public works contract.”
    
    Id. at 613.
    It noted that
    [t]he familiar meaning of “execution” is “the
    action of carrying into effect (a plan, design,
    purpose, command, decree, task, etc.);
    accomplishment”; “the act of carrying out or
    putting into effect”; “the act of carrying out
    fully or putting completely into effect, doing
    what is provided or required.” Therefore, the
    use of “execution” in the phrase “in the
    execution of any contract for public work,”
    plainly means the carrying out and
    completion of all provisions of the contract.
    
    Id. at 611
    (citations omitted) (first quoting 5 Oxford English
    Dictionary 521 (2d ed. 1989); then quoting Black’s Law
    Dictionary 405 (8th ed. 2004); and then quoting Webster’s
    10th New Collegiate Dictionary 405 (2001)). Borrowing
    from a previous material supplier exemption case, O. G.
    Sansone Co. v. Dep’t of Transp., 
    127 Cal. Rptr. 799
    (Ct.
    App. 1976), 2 the court distilled three factors to consider:
    (1) “whether the transport was required to carry out a term
    of the public works contract”; (2) “whether the work was
    2
    In O. G. Sansone, the Court of Appeal considered whether two
    companies that performed hauling work on a public works contract were
    required to pay prevailing 
    wages. 127 Cal. Rptr. at 801
    –02. The
    companies’ employees hauled materials to the public works site from
    locations adjacent to the site that were created to serve the project, and
    the materials they hauled were identified in the public works contract
    and had not been acquired from a “standard commercial supplier.” 
    Id. at 803.
    The court held that because the truckers hauled materials from a
    project-exclusive site under private agreements that were necessary to
    fulfill the terms of the contract, their employer was a subcontractor who
    needed to pay the prevailing wage. 
    Id. at 804.
         MENDOZA V. FONSECA MCELROY GRINDING CO.                9
    performed on the project site or another site integrally
    connected to the project site”; and (3) “whether work that
    was performed off the actual construction site was
    nevertheless necessary to accomplish or fulfill the contract.”
    
    Williams, 67 Cal. Rptr. 3d at 613
    . Applying these factors,
    the court concluded that the truckers’ off-hauling work was
    “unrelated” to the public works contracts and that the
    truckers, who were not otherwise employed on the public
    works project, fell within the material supplier exemption.
    
    Id. at 614.
    “In the absence of evidence that, either by
    contract or custom, the off-hauling . . . was ‘“an integrated
    aspect of the ‘flow’ process of construction,”’” the Williams
    court determined that the prevailing wage statute did not
    apply to the employees of a material supplier. 
    Id. (quoting O.
    G. 
    Sansone, 127 Cal. Rptr. at 804
    ).
    In Sheet Metal Workers, the Court of Appeal reviewed
    “whether the prevailing wage law applies to an employee of
    a subcontractor who fabricates materials for a public works
    project at a permanent offsite manufacturing facility that is
    not exclusively dedicated to the 
    project.” 176 Cal. Rptr. 3d at 637
    . The court recognized that “the prevailing wage law
    is ambiguous concerning its geographic scope. There is no
    clear indication the Legislature rejected some geographical
    restriction on its application, particularly in the face of
    statutes that refer to the site of the work.” 
    Id. at 650.
    The
    court distinguished a hauling case like Williams in light of
    this geographic consideration, noting that “hauling activities
    necessarily have at least a limited geographical connection
    to the public works site,” whereas “offsite fabrication could
    theoretically take place anywhere in the world.” 
    Id. at 646.
    It further noted that the Department of Industrial Relations
    10    MENDOZA V. FONSECA MCELROY GRINDING CO.
    (DIR) 3 had previously determined that “fabrication work
    performed at a permanent offsite facility not exclusively
    dedicated to the public works project is not covered by the
    prevailing wage law, whereas fabrication work performed at
    a temporary facility that is dedicated to the project is
    covered.” 
    Id. at 648.
    The DIR had explained that “extending
    coverage to offsite fabrication would not significantly
    protect local labor markets, because fabrication does not
    necessarily take place in the local labor market.” 
    Id. at 647.
    Applying the analysis from O. G. Sansone, the DIR
    concluded that “the sheet metal supplier was exempt from
    the prevailing wage requirements as a material supplier
    because it was a standard supplier of sheet metal products to
    the general public, its facility existed long before the public
    works contract, and the facility was not located on or near
    the site of the public work.” 
    Id. After considering
    these
    factors and the DIR’s determination, the Sheet Metal
    Workers court similarly concluded that “[w]ork performed
    at a permanent, offsite, nonexclusive manufacturing facility
    does not constitute an integral part of the process of
    construction at the site of the public work.” 
    Id. at 650.
    3
    The DIR is charged with “determin[ing] the general prevailing
    rate” based on “the applicable wage rates established by collective
    bargaining agreements and the rates that may have been predetermined
    for federal public works, within the locality and in the nearest labor
    market area,” and other factors. Cal. Lab. Code §§ 1770, 1773; see also
    State Bldg. & Constr. Trades Council of Cal. v. Duncan, 
    76 Cal. Rptr. 3d
    507, 511–12 (Ct. App. 2008) (reviewing the DIR’s role in wage
    determinations). Upon request, it also makes “determination[s] of
    whether a specific project or type of work awarded or undertaken by a
    political subdivision is a public work.” Cal. Lab. Code § 1773.5(b).
    MENDOZA V. FONSECA MCELROY GRINDING CO.                11
    B. Application to Plaintiffs’ Offsite Mobilization
    Work
    The outcome of this appeal might depend on whether
    Williams and Sheet Metal Workers properly apply in this
    context. Although neither case is directly on point, both
    might be sufficiently analogous to our case such that similar
    reasoning should be brought to bear.
    Plaintiffs’ offsite mobilization efforts are at least
    partially comparable to the hauling work in Williams and the
    fabrication work in Sheet Metal Workers. As with the
    latter’s fabrication shop, the offsite yards where Plaintiffs
    undertook their mobilization work “do not depend on any
    particular public works project for their existence.” Their
    work is therefore distinguishable from, for example, the
    hauling of materials from sites “located adjacent to and
    established exclusively to serve the [public works] project
    site.” O. G. 
    Sansone, 127 Cal. Rptr. at 801
    . The second
    Williams factor would thus militate against applying the
    prevailing wage law, as Plaintiffs’ mobilization work was
    not “performed on [a public works] project site or another
    site integrally connected to the project site.” 
    67 Cal. Rptr. 3d
    at 613.
    As to the first Williams factor—“whether the transport
    was required to carry out a term of the public works
    contract,” 
    id. at 613—the
    record does not provide any such
    terms from the contract, and, as the district court noted, there
    is “no evidence of the custom or practice of the industry
    regarding transportation of heavy equipment to public works
    project sites.” Mendoza, 
    2016 WL 6947552
    , at *7. Had
    Plaintiffs supplied evidence that the offsite mobilization
    work was “an integrated aspect of the ‘flow’ process of
    construction,” Williams, 
    67 Cal. Rptr. 3d
    at 612, then this
    case might be more easily resolved. However, no such
    12       MENDOZA V. FONSECA MCELROY GRINDING CO.
    evidence is presented, either from the terms of the public
    works contract or with regards to industry custom. The
    contract itself is not included in the record, and although
    Plaintiffs requested judicial notice of a variety of materials—
    mostly DIR wage determinations for other types of work—
    none of these documents relates to the offsite mobilization
    of grinding equipment, let alone provides evidence that these
    tools, or the work to prepare them, were essential
    components of the public works project. 4
    Finally, as to the third Williams factor—“whether work
    that was performed off the actual construction site was
    nevertheless necessary to accomplish or fulfill the contract,”
    
    id. at 613—the
    district court observed that California courts
    have considered transportation to be integral to public work
    in the context of materials, rather than tools. Mendoza, 
    2016 WL 6947552
    , at *7. 5 The court determined that a milling
    4
    Rather than rely on such evidence, Plaintiffs instead argue that it
    is self-evident that the milling machines were integral to the public works
    project because “one can safely say that without the [milling machine]
    on site, the job of grinding up the roadbed could not be performed and
    the contract executed.”
    5
    Drawing a bright line between materials and tools in this way is
    plausible, but not obvious. On the one hand, because materials are
    integrated into a jobsite and are not reusable, they are exclusively
    devoted to a public works project in a way that tools are not. This
    “exclusivity” is an ongoing theme in the relevant case law, as
    demonstrated, for example, by the focus on whether an offsite facility
    was created for a public works project, or whether a materialman also
    sold supplies to the general public. See, e.g., O. G. Sansone, 127 Cal.
    Rptr. at 803–04. Tools do not have this inherent characteristic of
    exclusivity: the reason for a tool to come and go from a jobsite may be
    for its protection or alternative use, which serves the contractor’s
    interest, not the interest of the public works project. On the other hand,
    the milling machines that Plaintiffs transported constituted a highly
    significant component of the public works project on which they were
    MENDOZA V. FONSECA MCELROY GRINDING CO.                          13
    machine is “more akin to a tool, not a building material,” and
    on that basis distinguished Plaintiffs’ mobilization efforts
    from other work that involved “a building material, like
    aggregate subbase or asphalt,” and therefore satisfied the
    third Williams factor. 
    Id. 6 The
    court also expressed concern
    about a potential slippery slope, pondering whether
    Plaintiffs’ “argument could be used to justify application of
    the prevailing wage law to the transportation of many things
    needed for a public works construction job, such as ‘tools,
    portable toilets, generators, potable water, lumber, asphalt,
    [and] steel,’” and noting that “[t]he California Court of
    Appeal has cautioned against an interpretation under which
    ‘nearly any activity related to the completion or fulfillment
    of a public works contract would be subject to the prevailing
    wage law, regardless of where it takes place or whether it
    plays a substantial role in the process of construction.’” 
    Id. at *8
    (quoting Sheet Metal Workers, 1
    76 Cal. Rptr. 3d
    at
    642).
    In short, application of the three Williams factors
    suggests—albeit not conclusively—that Plaintiffs did not
    employed. The heavy equipment was specifically tailored to perform the
    type of work required by the project, and unlike other construction tools,
    was not widely usable in other contexts. In this sense, the milling
    machines might have been “necessary to accomplish or fulfill the
    contract” to an even greater degree than common construction tools like
    portable toilets or generators, or generic materials like asphalt. 
    Williams, 67 Cal. Rptr. 3d at 613
    .
    6
    The court cited O. G. Sansone’s discussion of Green v. Jones,
    
    128 N.W.2d 1
    (Wis. 1964), in which the Wisconsin Supreme Court
    determined that haulers were covered by the prevailing wage law when
    they hauled materials that “were dumped or spread directly on the
    roadbed and were immediately used in the construction of the project.”
    O. G. 
    Sansone, 127 Cal. Rptr. at 804
    (citing 
    Green, 128 N.W.2d at 7
    ).
    14       MENDOZA V. FONSECA MCELROY GRINDING CO.
    perform the offsite mobilization work in the execution of a
    public works contract such that the prevailing wage law
    applied. 7
    However, other considerations suggest a contrary
    conclusion. To begin, the distinctions between Williams and
    Sheet Metal Workers and this case are significant. Unlike
    the workers in those cases, Plaintiffs performed work on the
    public works site that indisputably qualified for the
    prevailing wage, leaving us to determine whether work they
    performed offsite in connection with those efforts should be
    similarly compensated. Whether wage rates for workers
    employed on a public works project should vary based on
    the task performed is a different inquiry from whether a class
    7
    Additionally, although not controlling, the federal Davis-Bacon
    Act provides support for this result. “California courts have turned to
    the Davis-Bacon Act for guidance on issues not clearly answered by
    California authority.” Sheet Metal Workers, 1
    76 Cal. Rptr. 3d
    at 649–50
    (“[U]nless the Davis-Bacon Act is fundamentally inconsistent with the
    portions of the prevailing wage law that one seeks to interpret, the
    approach taken under the Davis-Bacon Act may provide useful
    guidance.”). The Davis-Bacon Act “plainly imposes a geographical
    limitation on the application of the federal prevailing wage law,” 
    id. at 642,
    as it applies to “mechanics and laborers employed directly on the
    site of the work.” 40 U.S.C. § 3142(c)(1). The “site of work” does not
    include “permanent home offices, branch plant establishments,
    fabrication plants, tool yards, etc., of a contractor or subcontractor whose
    location and continuance in operation are determined wholly without
    regard to a particular Federal or federally assisted contract or project.”
    29 C.F.R. § 5.2(l)(3). The same regulation also specifies that “the
    transportation of materials or supplies to or from the site of the work by
    employees of the construction contractor or a construction subcontractor
    is not ‘construction, prosecution, completion, or repair.’” 
    Id. § 5.2(j)(2).
    Accordingly, although the Davis-Bacon Act is not dispositive,
    interpreting Plaintiffs’ offsite mobilization work as outside “the
    execution of” a public works contract is consistent with the Act’s
    guidance.
    MENDOZA V. FONSECA MCELROY GRINDING CO.               15
    of employees is sufficiently involved in a public works
    project to be considered employed in the execution of a
    public works contract, and Williams and Sheet Metal
    Workers only addressed the latter issue. Furthermore, the
    Court of Appeal’s geographic concern in Sheet Metal
    Workers—specifically, that the manufacturing work at issue
    there could conceivably have been undertaken anywhere,
    and thus did not necessarily implicate the policy concern
    underlying the prevailing wage law—is not present here.
    Plaintiffs’ mobilization and transportation work was
    geographically confined to areas in reasonable proximity to
    the public works site. Lastly, whereas Williams involved a
    worker with “the status of a bona fide materials supplier,”
    
    67 Cal. Rptr. 3d
    at 613–14, Plaintiffs directly worked for a
    public works contractor, not a materials supplier. These
    notable distinctions suggest that Williams and Sheet Metal
    Workers might be of limited use in answering the question
    that forms the basis of this appeal.
    Additionally, Plaintiffs rely on the DIR’s interpretations
    of its Public Works Manual and prevailing wage
    determinations, which, they contend, “show that
    mobilization is part and parcel of a contractor’s prevailing
    wage obligations.” They acknowledge that “a published
    determination is not a legal opinion or a position
    statement”—a position echoed by the Public Works Manual,
    which asserts that it “is not intended as a comprehensive
    summary of existing law or duly promulgated regulations”
    and “should not be relied upon” to “establish rules of general
    application.”     However, “[a]lthough the [DIR] has
    determined that its coverage determinations do not have
    precedential value, the determinations nonetheless constitute
    administrative interpretations entitled to considerable
    deference.” Sheet Metal Workers, 1
    76 Cal. Rptr. 3d
    at 647.
    16   MENDOZA V. FONSECA MCELROY GRINDING CO.
    The relevant provision of the Public Works Manual reads
    as follows:
    Travel time related to a public works project
    constitutes “hours worked” on the project,
    which is payable at not less than the
    prevailing rate based on the worker’s
    classification, unless the Director’s wage
    determination      for that       classification
    specifically includes a lesser travel time rate.
    (See Director’s Decision in In the Matter of
    Kern Asphalt Paving & Sealing Co., Inc.
    (March 28, 2008), Case No. 04-0117-PWH.
    (See also Morillion v. Royal Packing Co.
    (2000) 
    22 Cal. 4th 575
    ).) Travel time required
    by an employer after a worker reports to the
    first place at which his or her presence is
    required by the employer is compensable
    travel time, and includes travel to a public
    work site, whether from the contractor’s
    yard, shop, another public work site, or a
    private job site. All such compensable travel
    time must be paid at the same prevailing
    wage rate required for the work actually
    performed by the worker at the public works
    site. No additional facts, such as whether
    tools or supplies are being delivered by the
    worker to the site, need be present.
    Given that DIR decisions, while not binding, are at the very
    least revealing, this provision seems to favor Plaintiffs’
    position. This is particularly true because the provision was
    undergirded by the DIR’s decision in In re Kern Asphalt
    Paving & Sealing Co., No. 04-0117-PWH, in which it
    concluded that travel time was compensable at the prevailing
    MENDOZA V. FONSECA MCELROY GRINDING CO.               17
    wage for employees’ work on a public jobsite. With regard
    to the prevailing wage, the DIR wrote:
    The relevant prevailing wage determinations
    contain no special rate for travel time. In the
    absence of any evidence to the contrary, the
    required travel time must be regarded as
    incidental to the workers’ regular duties and
    payable at the same prevailing rates that
    apply to the classification associated with
    those duties. [The employer] has presented
    no argument or evidence supporting a
    different rate outside of its contention that it
    was not obligated to pay for the travel time at
    all.
    (footnote omitted). Although this determination supports
    Plaintiffs’ position, DIR determinations must be designated
    as precedential in order “to be relied upon in subsequent
    determinations,” State Bldg. & Constr. Trades Council of
    Cal. v. Duncan, 
    76 Cal. Rptr. 3d
    507, 515 (Ct. App. 2008)
    (citing Cal. Gov’t Code § 11425.60), and Kern Asphalt was
    not so designated.        See Director’s Prevailing Wage
    Enforcement Decisions (Labor Code section 1742) (2007 to
    present), Dep’t of Indus. Relations, http://www.dir.ca.gov/o
    prl/PrevWageEncDecision.htm (last visited Jan. 7, 2019)
    (listing Kern Asphalt among decisions that “have not been
    designated precedential and, therefore, . . . cannot be relied
    on as authority in future cases”). Nevertheless, the reasoning
    and conclusion of Kern Asphalt are instructive, if not
    binding, even though the courts bear the ultimate
    responsibility for interpreting the statutory language of the
    prevailing wage law. See City of Long 
    Beach, 102 P.3d at 910
    (“When an administrative agency construes a statute in
    adopting a regulation or formulating a policy, the court will
    18     MENDOZA V. FONSECA MCELROY GRINDING CO.
    respect the agency interpretation as one of several
    interpretive tools that may be helpful. In the end, however,
    ‘[the court] must . . . independently judge the text of the
    statute.’” (alterations in original) (quoting Agnew v. State
    Bd. of Equalization, 
    981 P.2d 52
    , 60 (Cal. 1999))).
    C. Summation
    Ultimately, no California court has addressed whether
    offsite mobilization work, performed by workers who are
    otherwise employed on a public works project, entitles the
    workers to prevailing wages for those efforts. We note that
    the various possible outcomes to this question could yield
    wide-ranging results. For example, a broader application of
    Kern Asphalt might result in an extension of prevailing
    wages to a range of public works-adjacent activities,
    including mobilization and travel.               Alternatively,
    endorsement of the district court’s analysis might limit
    prevailing wages only to work that satisfies the factors set
    forth by the Court of Appeal in Williams, and thus limit
    wages for workers employed on public works projects when
    they perform offsite tasks, even when that work is closely
    related to their onsite employment. Resolution of this issue
    might also implicate, as the district court noted, workers who
    haul other equipment to public works sites, from generators
    and scaffolding to water and portable toilets.
    Given the potential scope of this decision, its impact on
    California workers, and the absence of guiding precedent,
    we conclude that certification to the California Supreme
    Court of the question presented in Part I is appropriate.
    IV.     Administrative Information
    We provide the following information as required by
    California Rule of Court 8.548(b)(1).
    MENDOZA V. FONSECA MCELROY GRINDING CO.                19
    The title of this case is: LEOPOLDO PENA
    MENDOZA, JOSE ARMANDO CORTES, and ELVIZ
    SANCHEZ,    Plaintiffs-Appellants v. FONSECA
    MCELROY GRINDING CO., INC and GRANITE ROCK
    COMPANY, Defendants-Appellees.
    The case number in our court is 17-15221.
    Plaintiffs-Appellants Leopoldo Pena Mendoza, Jose
    Armando Cortes, and Elviz Sanchez are represented by the
    following counsel:
    Tomas E. Margain and Huy Ngoc Tran
    Justice at Work Law Group
    84 West Santa Clara Street, Suite 790
    San Jose, California 95113
    Defendants-Appellees Fonseca McElroy Grinding Co.,
    Inc. and Granite Rock Company are represented by the
    following counsel:
    Paul V. Simpson
    Simpson, Garrity, Innes & Jacuzzi, PC
    601 Gateway Boulevard, Suite 950
    South San Francisco, California 94080
    We designate Leopoldo Pena Mendoza, Jose Armando
    Cortes, and Elviz Sanchez as the petitioners if our request
    for a decision is granted, as they are the appellants before our
    court.
    The clerk of this court shall submit to the California
    Supreme Court, under seal of the United States Court of
    Appeals for the Ninth Circuit, copies of all relevant briefs
    and excerpts of record, as well as an original and ten copies
    20    MENDOZA V. FONSECA MCELROY GRINDING CO.
    of this order, with a certificate of service on the parties. Cal.
    R. Ct. 8.548(c)–(d).
    This case is withdrawn from submission. Further
    proceedings before us are stayed pending the California
    Supreme Court’s decision. The parties shall notify the clerk
    of this court within seven days after the California Supreme
    Court accepts or declines this request, and again within
    seven days if the California Supreme Court issues a decision.
    The panel retains jurisdiction over further proceedings. The
    clerk is directed to administratively close this docket,
    pending further order.
    IT IS SO ORDERED.