City of Los Angeles v. Faa ( 2023 )


Menu:
  •                  FOR PUBLICATION
    UNITED STATES COURT OF APPEALS
    FOR THE NINTH CIRCUIT
    CITY OF LOS ANGELES, California,         No. 21-71170
    Petitioner,
    v.
    OPINION
    FEDERAL AVIATION
    ADMINISTRATION; STEPHEN M.
    DICKSON, in his official capacity as
    Administrator; U.S. DEPARTMENT
    OF TRANSPORTATION; PETE
    BUTTIGIEG, in his official capacity
    as Secretary,
    Respondents,
    BURBANK-GLENDALE-
    PASADENA AIRPORT
    AUTHORITY,
    Respondent-
    Real Party in Interest.
    On Petition for Review of an Order of the
    Federal Aviation Administration
    Argued and Submitted October 18, 2022
    Pasadena, California
    Filed March 29, 2023
    2                   CITY OF LOS ANGELES V. FAA
    Before: Stephen A. Higginson, * Morgan Christen, and
    Patrick J. Bumatay, Circuit Judges.
    Opinion by Judge Higginson;
    Dissent by Judge Bumatay
    SUMMARY **
    Federal Aviation Administration
    The panel granted in part the City of Los Angeles’s
    petition for review challenging the Federal Aviation
    Administration (“FAA”)’s issuance of a Final
    Environmental Impact Statement (EIS) and Record of
    Decision (ROD) that let the Burbank-Glendale-Pasadena
    Airport Authority start constructing a replacement terminal
    at the Bob Hope “Hollywood Burbank” Airport (the
    “Project”).
    The Airport Authority, which owns and operates the
    Airport, reached an agreement with the City of Burbank to
    build a new terminal. In 2016, Burbank voters approved that
    agreement as required by local law (“Measure B”). Before
    the FAA could sign off on the Project, the National
    Environmental Policy Act (“NEPA”) required the agency to
    prepare an EIS. In 2021, the FAA issued the Final EIS and
    ROD.
    *
    The Honorable Stephen A. Higginson, United States Circuit Judge for
    the U.S. Court of Appeals for the Fifth Circuit, sitting by designation.
    **
    This summary constitutes no part of the opinion of the court. It has
    been prepared by court staff for the convenience of the reader.
    CITY OF LOS ANGELES V. FAA                3
    Los Angeles first challenged FAA’s compliance with
    NEPA’s requirement that an EIS include a “detailed
    statement” of “alternatives to the proposed action.” 
    42 U.S.C. § 4332
    (2)(C)(iii). The panel denied the petition on
    this ground because the FAA considered a reasonable range
    of alternatives in the Final EIS. Here, the FAA drafted an
    adequate purpose and need statement and then narrowed the
    range of alternatives for detailed study based on rational
    considerations. Los Angeles failed to identify any
    reasonable alternative that FAA should have studied given
    the FAA’s analysis of the relevant technical and economic
    constraints. The panel held that contrary to Los Angeles’s
    argument—that the FAA improperly eliminated certain
    alternatives because they were not approved pursuant to
    Measure B—the FAA properly eliminated the new airport,
    remote landside facility, and southeast terminal alternatives
    based on rational considerations that were independent of
    Measure B. In addition, the panel held that even if the
    Measure B criteria foreclosed consideration of alternatives
    other than the Project, that would not be enough to establish
    an irreversible commitment to the Project. Here, the FAA
    could have picked the no action alternative after reviewing
    the Project’s environmental impacts. Accordingly, the
    FAA’s inclusion of the Measure B criteria did not
    predetermine the outcome of the FAA’s NEPA review.
    Next, Los Angeles challenged the FAA’s analysis of
    construction-related impacts. The panel held that the FAA
    did not take a hard look at noise impacts from the Project
    because its analysis rested on an unsupported and irrational
    assumption that construction equipment would not be
    operated simultaneously. Because the FAA failed to take a
    hard look at construction noise impacts and based its
    cumulative impacts analysis on its inadequately considered
    4                 CITY OF LOS ANGELES V. FAA
    conclusions about construction noise, the panel granted the
    petition on these limited grounds.
    The panel considered the rest of Los Angeles’s
    objections to the FAA’s impact analysis and found them
    meritless. On remand, the panel directed the FAA to address
    the deficiency in its construction noise analysis, the resulting
    deficiency in its cumulative impacts analysis, and the
    resulting deficiency in its environmental impacts analysis.
    Dissenting, Judge Bumatay wrote that the majority
    ignored the FAA’s reasonable assumptions about noise
    effects and should have deferred to the FAA’s reasonable
    analysis. He would hold that the FAA’s construction noise
    analysis was not arbitrary or capricious, and deny the City’s
    petition challenging the FAA’s construction noise
    analysis. Judge Bumatay agreed with those parts of the
    majority’s opinion that rejected the bulk of the City’s
    petition.
    COUNSEL
    Andrea K. Leisy (argued), Laura M. Harris, and Casey A.
    Shorrock, Remy Moose Manley LLP, Sacramento,
    California; David J. Michaelson, Attorney; Robert M.
    Mahlowitz, Deputy City Attorney, Michael N. Feuer, City
    Attorney; Office of the City Attorney, Los Angeles,
    California; for Petitioner.
    Justin D. Heminger (argued), Senior Litigation Counsel;
    Anna T. Katselas, Attorney; Todd Kim, Assistant Attorney
    General; Environment and Natural Resources Division,
    United States Department of Justice, Washington, D.C.;
    Joseph Manalili and Catherine M. Basic, Attorneys; Office
    CITY OF LOS ANGELES V. FAA              5
    of the Chief Counsel, Federal Aviation Administration,
    Washington, D.C.; for Respondent.
    Thomas A. Ryan (argued), McDermott Will & Emery LLP,
    Los Angeles, California; Jessica J. Thomas, McDermott
    Will & Emery LLP, San Francisco, California; Terence R.
    Boga, Ginetta L. Giovinco, and Chelsea O’Sullivan,
    Richards Watson & Gershon APC, Los Angeles, California;
    for Intervenor.
    OPINION
    HIGGINSON, Circuit Judge:
    The passenger terminal at the Bob Hope “Hollywood
    Burbank” Airport is more than fifty years old and violates
    safety standards set by the Federal Aviation Administration
    (FAA).       So the Burbank-Glendale-Pasadena Airport
    Authority, which owns and operates the Airport, reached an
    agreement with the City of Burbank to build a new terminal.
    In 2016, Burbank voters approved that agreement as
    required by local law. But before FAA could sign off on the
    project, the National Environmental Policy Act (NEPA), 
    42 U.S.C. §§ 4321
     et seq., required the agency to prepare an
    Environmental Impact Statement (EIS). In May 2021, the
    FAA issued a Final EIS (FEIS) and Record of Decision
    (ROD) that let the Authority start constructing the
    replacement terminal, and shortly after, the City of Los
    Angeles petitioned for review. Because FAA failed to
    comply with NEPA, we GRANT the petition in part and
    REMAND for FAA to redo the deficient parts of its analysis
    as specified in this opinion.
    6                    CITY OF LOS ANGELES V. FAA
    I.
    A.
    The Hollywood Burbank Airport spans 555 acres about
    twelve miles northwest of downtown Los Angeles.
    Approximately 455 of those acres are within Burbank, and
    the remaining 100 acres fall within Los Angeles.
    The Airport opened in 1930 and was purchased by the
    Lockheed Aircraft Company a decade later. During World
    War II, the Airport was one of the largest commercial
    airports in the region. In 1978, Lockheed sold the airport to
    the Burbank-Glendale-Pasadena Airport Authority. The
    Authority was created by a Joint Powers Agreement between
    Burbank, Glendale, and Pasadena. Los Angeles is not
    represented by the Authority. Since 1978, the Authority has
    owned and operated the Airport.
    Two intersecting runways divide the Airport into
    quadrants. The Airport’s 14-gate passenger terminal is in
    the southeast quadrant. The southwest and northwest
    quadrants contain aircraft hangars, parking areas, and other
    facilities for airport operations. Only the northeast quadrant
    is undeveloped.
    The existing terminal building occupies the site of the
    original 1930 terminal. After a fire in 1966, Lockheed
    rebuilt the terminal in the same spot. However, by 1980, the
    reconstructed terminal no longer complied with FAA
    standards. 1 In January of that year, FAA and the Authority
    1
    Although FAA has determined that the existing terminal is safe to use,
    the building is located within certain object-free areas that are designated
    as such to reduce the risk of collisions between aircraft and vehicles,
    CITY OF LOS ANGELES V. FAA                      7
    began discussing how to replace the terminal building. It
    took FAA and the Authority more than three decades to find
    a solution.
    Between 1981 and 1995, FAA and the Authority
    proposed three terminal concepts, none of which got off the
    ground. The first proposal failed when the Authority could
    not acquire the necessary land from Lockheed, and the
    second was abandoned when Lockheed announced that it
    planned to leave Burbank. In 1995, FAA issued an FEIS for
    a third proposal. Los Angeles and Burbank challenged that
    FEIS in this court and lost. See City of Los Angeles v. FAA,
    
    138 F.3d 806
     (9th Cir. 1998). But in 1999, a state court
    decision required the Authority to get approval for the
    project from Burbank. City of Burbank v. Burbank-
    Glendale-Pasadena Airport Auth., 
    85 Cal. Rptr. 2d 28
     (Cal.
    Ct. App. 1999). Instead of approving the project, Burbank
    residents adopted a ballot measure, “Measure B,” that
    required voter approval before the City of Burbank agreed to
    any relocation or expansion of the terminal. As a result of
    these decisions, any relocation or expansion of the terminal
    requires Burbank voter approval.
    In 2015, Burbank and the Authority agreed to a term
    sheet for a replacement terminal that would let the Authority
    build a new 14-gate terminal between 232,000 and 355,000
    square feet in size. The term sheet also specified that the
    project would be subject to review under the California
    Environmental Quality Act (CEQA). Burbank and the
    Authority subsequently entered into a development
    agreement that included 241 conditions of approval for the
    objects, and buildings. In addition, the terminal violates current FAA
    standards that protect navigable airspace around the runways.
    8                    CITY OF LOS ANGELES V. FAA
    project. The Authority finished its CEQA analysis in July
    2016.
    Pursuant to Measure B, Burbank residents voted on and
    approved the project in the November 2016 election. The
    text of the 2016 ballot measure asked voters whether an
    ordinance should “be approved allowing no more than a 14-
    gate, 355,000 square foot replacement terminal and ancillary
    improvements to be built at the Bob Hope Airport . . . in
    exchange for governance changes that provide Burbank a
    greater voice in the future of the airport.”
    Following passage of the ballot measure, the Authority
    submitted an Airport Layout Plan (ALP) for the proposed
    project to FAA. Because FAA approval of an ALP requires
    compliance with NEPA, FAA began to prepare an EIS in
    2018.
    B.
    NEPA requires federal agencies to prepare an EIS for
    “major [f]ederal actions significantly affecting the quality of
    the human environment.” 
    42 U.S.C. § 4332
    (C). An EIS
    must consider direct, indirect, and cumulative impacts from
    the proposed action. 
    40 C.F.R. § 1508.25
    (c). 2 The agency
    must also analyze a range of reasonable alternatives to the
    proposed action, including the alternative of taking no
    2
    The Council on Environmental Quality (CEQ) promulgates regulations
    implementing NEPA. 
    42 U.S.C. § 4342
    . In 2020, CEQ made substantial
    amendments to those regulations. See 
    85 Fed. Reg. 43,304
     (July 16,
    2020). But at the time that FAA started preparing the EIS for the Project,
    the updated regulations had not yet gone into effect, and so FAA
    followed the pre-2020 regulations. Because the parties do not dispute
    that the pre-2020 regulations govern the EIS, this opinion cites to and
    applies the pre-2020 regulations.
    CITY OF LOS ANGELES V. FAA                     9
    action. See 
    id.
     § 1502.14. These requirements are
    procedural, not substantive. In other words, “NEPA itself
    does not mandate particular results, but simply prescribes the
    necessary process,” Robertson v. Methow Valley Citizens
    Council, 
    490 U.S. 332
    , 350 (1989) (citations omitted), for an
    agency to “take[] a ‘hard look’ at [the] environmental
    consequences” of a proposed action, Kleppe v. Sierra Club,
    
    427 U.S. 390
    , 410 n.21 (1976) (citation omitted).
    On December 18, 2018, FAA announced its intent to
    prepare an EIS for the Replacement Passenger Terminal
    Building Project (the “Project”). In early 2019, FAA held
    two scoping meetings to identify potentially significant
    environmental impacts from the project. FAA released a
    Draft EIS (DEIS) on August 21, 2020. A forty-five-day
    comment period started running on that day. Following
    multiple requests for extensions, FAA added twenty-two
    days to the comment period. FAA received hundreds of
    comments by the deadline.
    On May 21, 2021, FAA issued a combined FEIS and
    ROD for the Project. FAA also responded to the comments
    on the DEIS, including those submitted by Los Angeles.
    C.
    On July 12, 2021, Los Angeles filed a petition for review
    of the ROD in this court pursuant to the FAA Authorization
    Act of 1994, 
    49 U.S.C. § 46110.3
     In relevant part, that
    statute provides for exclusive jurisdiction over petitions for
    review of certain FAA orders in the Court of Appeals for the
    District of Columbia Circuit or in the court of appeals for the
    3
    Los Angeles initially named the Authority as a respondent along with
    FAA. On the joint motion of the parties, the court redesignated the
    Authority as an intervenor.
    10               CITY OF LOS ANGELES V. FAA
    circuit in which the petitioner resides or has its principal
    place of business. 
    49 U.S.C. § 46110
    (a), (c). The parties
    agree that the ROD is an FAA order reviewable under
    Section 46110 and that this court has jurisdiction over the
    petition. See Ctr. for Cmty. Action & Env’t Just. v. FAA, 
    18 F.4th 592
    , 598 (2021).
    II.
    The Administrative Procedure Act (APA), 
    5 U.S.C. § 706
    (2)(A), controls judicial review of an agency’s
    compliance with NEPA. Bark v. U.S. Forest Serv., 
    958 F.3d 865
    , 869 (9th Cir. 2020). Under the APA, we may overturn
    agency action when it is “arbitrary, capricious, an abuse of
    discretion, or otherwise not in accordance with law.” 
    5 U.S.C. § 706
    (2)(A). As the party challenging the agency’s
    action, Los Angeles has the burden of persuasion. Ctr. for
    Cmty. Action, 18 F.4th at 599.
    Agency action is arbitrary and capricious if the agency
    “relied on factors which Congress has not intended it to
    consider, entirely failed to consider an important aspect of
    the problem, offered an explanation for its decision that runs
    counter to the evidence before the agency, or is so
    implausible that it could not be ascribed to a difference in
    view or the product of agency expertise.” WildEarth
    Guardians v. EPA., 
    759 F.3d 1064
    , 1069-70 (9th Cir. 2014)
    (citation omitted). In reviewing agency action under the
    arbitrary and capricious standard, we may not substitute our
    judgment for the agency’s. Lands Council v. McNair, 
    537 F.3d 981
    , 987 (9th Cir. 2008) (en banc), overruled in part on
    other grounds by Winter v. Nat. Res. Def. Council, 
    555 U.S. 7
     (2008). An agency decision will be upheld if there is a
    rational connection between the facts that the agency found
    and its conclusions. Barnes v. U.S. Dep’t of Transp., 655
    CITY OF LOS ANGELES V. FAA                         
    11 F.3d 1124
    , 1132 (9th Cir. 2011). But “[p]ost hoc
    explanations of agency action by appellate counsel cannot
    substitute for the agency’s own articulation of the basis for
    its decision.” Arrington v. Daniels, 
    516 F.3d 1106
    , 1113
    (9th Cir. 2008).
    We use the “rule of reason” standard to decide whether
    the agency’s discussion of environmental impacts is
    sufficiently thorough. Audubon Soc’y of Portland v.
    Haaland, 
    40 F.4th 967
    , 980 (9th Cir. 2022). The rule of
    reason “is essentially the same as an abuse of discretion
    analysis.” 
    Id.
     (cleaned up). In other words, under the rule
    of reason, an agency acts arbitrarily and capriciously “only
    when the record plainly demonstrates that the agency made
    a clear error in judgment in concluding that a project meets
    the requirements of NEPA.” 
    Id.
     (cleaned up).
    III.
    Los Angeles first challenges FAA’s compliance with
    NEPA’s requirement that an EIS include a “detailed
    statement” of “alternatives to the proposed action.” 4 42
    4
    FAA challenges Los Angeles’s standing to bring this suit, arguing that
    Los Angeles neither identifies any injury it would suffer from the Project
    nor offers any supporting evidence. But Los Angeles has pointed to
    sufficient evidence in the administrative record that the noise impacts
    from the Project could affect its neighborhoods and that the Project could
    increase the use of its roads and streets. See City of Sausalito v. O’Neill,
    
    386 F.3d 1186
    , 1197 (9th Cir. 2004) (holding that a municipality must
    allege injuries to “its own ‘proprietary interests,’” including the
    “municipality’s responsibilities, powers, and assets”); Cal. ex rel.
    Imperial Cnty. Air Pollution Control Dist. v. U.S. Dep’t of the Interior,
    
    767 F.3d 781
    , 790-91 (9th Cir. 2014) (allegations that federal action
    would undermine land management sufficient to establish standing);
    City of Las Vegas v. FAA, 
    570 F.3d 1109
    , 1114 (9th Cir. 2009) (similar).
    These threats to Los Angeles’s interests make this a “real controversy
    12                 CITY OF LOS ANGELES V. FAA
    U.S.C. § 4332(2)(C)(iii); see id. § 4332(2)(E); 
    40 C.F.R. § 1502.14
    . Since FAA considered a reasonable range of
    alternatives in the FEIS, the petition is denied on this ground.
    A.
    An EIS must “describe and analyze every reasonable
    alternative within the range dictated by the nature and scope
    of the proposal.” Audubon Soc’y of Portland, 40 F.4th at
    981 (citation omitted). Consideration of alternatives “is the
    heart of the [EIS]” and agencies should “[r]igorously explore
    and objectively evaluate all reasonable alternatives.” 
    40 C.F.R. § 1502.14
    . But NEPA does not force agencies to
    “review remote and speculative alternatives,” Protect Our
    Cmtys. Found. v. Jewell, 
    825 F.3d 571
    , 580 (9th Cir. 2016)
    (internal quotation marks omitted), “only reasonable or
    feasible ones,” City of Sausalito, 386 F.3d at 1207 (citation
    omitted). “[T]he EIS need only ‘briefly discuss’ the reasons
    for eliminating an alternative not selected for detailed
    examination.” Protect Our Cmtys. Found., 
    825 F.3d at 580
    (quoting 
    40 C.F.R. § 1502.14
    (a)). “The rule of reason guides
    both the [agency’s] choice of alternatives as well as the
    extent to which the EIS needs to discuss each alternative.”
    Audubon Soc’y of Portland, 40 F.4th at 980 (cleaned up).
    Because “[t]he range of alternatives that an agency must
    consider . . . is based on the purpose and need of the proposed
    agency action[,] . . . we begin by determining whether or not
    the purpose and need statement was reasonable.” Id. at 981
    (cleaned up). Then, we determine whether the agency
    with real impact.” TransUnion LLC v. Ramirez, 
    141 S. Ct. 2190
    , 2203
    (2021) (citation omitted). The Constitution does not require more.
    CITY OF LOS ANGELES V. FAA               13
    considered a reasonable range of alternatives based on its
    purpose and need. 
    Id. at 982
    .
    Here, FAA drafted an adequate purpose and need
    statement and then narrowed the range of alternatives for
    detailed study based on rational considerations. Indeed, Los
    Angeles failed to identify any reasonable alternative that
    FAA should have studied given FAA’s analysis of the
    relevant technical and economic constraints.
    B.
    NEPA requires that an agency’s purpose and need
    statement “briefly specify the underlying purpose and need
    to which the agency is responding in proposing the
    alternatives including the proposed action.” 
    40 C.F.R. § 1502.13
    . Agencies have discretion in drafting the purpose
    and need statement, Env’t Def. Ctr. v. Bureau of Ocean
    Energy Mgmt., 
    36 F.4th 850
    , 876 (9th Cir. 2022), but the
    statement must not “unreasonably narrow[] the agency’s
    consideration of alternatives so that the outcome is
    preordained,” Alaska Survival v. Surface Transp. Bd., 
    705 F.3d 1073
    , 1084 (9th Cir. 2013); see Nat’l Parks &
    Conservation Ass’n v. Bureau of Land Mgmt., 
    606 F.3d 1058
    , 1070 (9th Cir. 2010) (similar).
    In the FEIS, FAA stated that its purpose and need were
    “to provide a passenger terminal building that meets current
    FAA Airport Design Standards, passenger demand, and
    building requirements as well as improve utilization and
    operational efficiency of the passenger terminal building,”
    and “to ensure that the Airport operates in a safe manner” as
    required by the Airport and Airway Improvement Act of
    1982 (AAIA), 
    49 U.S.C. § 47101
    (a)(1). FAA also noted its
    obligation to decide whether to approve the Authority’s ALP
    pursuant to AAIA, 
    49 U.S.C. § 47107
    (a)(16). FAA
    14                CITY OF LOS ANGELES V. FAA
    explained that its purpose and need addressed the
    Authority’s goals of building an energy-efficient terminal in
    compliance with the Americans with Disabilities Act and
    state building codes, consolidating air facilities, and
    maintaining connections to rail and bus lines.
    This purpose and need statement was sufficiently broad
    in light of the relevant statutory context. It is appropriate for
    an agency to draft a purpose and need statement with
    reference to the agency’s statutory mandates. See League of
    Wilderness Defs.-Blue Mountains Biodiversity Project v.
    U.S. Forest Serv., 
    689 F.3d 1060
    , 1070 (9th Cir. 2012);
    Westlands Water Dist. v. U.S. Dep’t of Interior, 
    376 F.3d 853
    , 866 (9th Cir. 2004). FAA did just that. AAIA directs
    FAA to promote airport safety and efficiency, see 
    49 U.S.C. § 47101
    (a), (b), and the purpose and need statement
    incorporated those goals. Thus, FAA acted reasonably in
    limiting its inquiry to alternatives consistent with AAIA
    policies. Cf. HonoluluTraffic.com v. Fed. Transit Admin.,
    
    742 F.3d 1222
    , 1230-31 (9th Cir. 2014) (finding purpose and
    need reasonable where stated objectives were consistent
    with authorizing statute).
    Nor did FAA err in accounting for the Authority’s goals.
    A private entity’s goals may be relevant to an agency’s
    purpose and need when the agency is deciding whether to
    approve a private project. See Alaska Survival, 
    705 F.3d at 1085
    ; Nat’l Parks & Conservation Ass’n, 
    606 F.3d at 1071
    (describing inquiry as whether the agency’s purpose and
    need statement “properly states the [agency’s] purpose and
    need, against the background of a private need, in a manner
    broad enough to allow consideration of a reasonable range
    of alternatives”). And here, inclusion of the Authority’s
    objectives in the purpose and need statement did not
    unreasonably exclude alternatives that failed to meet those
    CITY OF LOS ANGELES V. FAA             15
    objectives. See Nat’l Parks & Conservation Ass’n, 
    606 F.3d at 1072
    . Application of the purpose and need statement to
    the nine potential action alternatives at Step 1 of the
    screening process eliminated five options. In ruling out
    those options, FAA referenced components of the purpose
    and need statement drawn from FAA’s statutory mandates.
    Accordingly, FAA probably would have eliminated those
    alternatives notwithstanding the Authority’s goals.
    FAA defined its purpose and need in the context of the
    applicable statutory framework and incorporated private
    goals without unreasonably eliminating alternatives from
    consideration. Therefore, its purpose and need statement
    was not too narrow to survive NEPA review.
    C.
    Next, we consider whether FAA considered a reasonable
    range of alternatives given the purpose and need statement.
    Audubon Soc’y of Portland, 40 F.4th at 982. As we
    explained, an EIS must “objectively evaluate all reasonable
    alternatives.” 
    40 C.F.R. § 1502.14
    (a). We defer to an
    agency’s technical expertise. Alaska Survival, 
    705 F.3d at 1087
    . However, “[t]he existence of a viable but unexamined
    alternative renders the environmental review conducted
    under NEPA inadequate.” Env’t Def. Ctr., 36 F.4th at 877
    (internal quotation marks omitted).
    1.
    Here, to identify reasonable alternatives for detailed
    study, FAA made a list of ten potential alternatives. Those
    alternatives included construction of a new airport on a
    16                 CITY OF LOS ANGELES V. FAA
    different site, construction of a remote landside facility, 5
    transfer of aviation activity to other airports, use of other
    modes of transportation like buses and rail, reconfiguration
    of runways, replacement of the terminal in each of the four
    Airport quadrants, and no action. Then, FAA used a two-
    step screening process to decide which of those alternatives
    to study in detail. At Step 1, FAA considered whether an
    alternative could achieve the purpose and need of the
    proposed action by meeting “current FAA Airport Design
    Standards, passenger demand, and state building
    requirements, as well as improving utilization and
    operational efficiency of the passenger terminal building.”
    Alternatives that could not satisfy those objections were
    eliminated. At Step 2, FAA ruled out alternatives that
    “would not be practical or feasible to implement from a
    technical or economic standpoint.” As FAA described in the
    FEIS, the criteria at Step 2 included “whether the alternative
    is consistent with the development agreement entered into
    by the City of Burbank and the Authority and ratification of
    Measure B by Burbank voters.”
    At Step 1, FAA rejected transfer of aviation activity, use
    of other modes of transportation, airfield reconfiguration,
    and construction of a terminal in the southwest and
    northwest quadrants. Specifically, FAA found that FAA and
    the Authority could not require airlines to operate out of
    different airports and transferring those operations would not
    bring the existing terminal into compliance with FAA
    standards. FAA reached similar conclusions about the
    modes of transportation alternative.          As to airfield
    5
    This alternative would involve construction of a remote terminal
    (“remote landside facility”) and construction of a separate facility
    located more proximate to the runways.
    CITY OF LOS ANGELES V. FAA               17
    reconfiguration, FAA pointed to state law restrictions on
    changing the Airport’s runways and noted that airfield
    reconfiguration would not bring the existing terminal into
    compliance with California’s building standards or improve
    its efficiency. Finally, construction in the southwest and
    northwest quadrants would not meet FAA standards because
    it would increase the number of aircrafts required to taxi
    across active runways.
    At Step 2, FAA eliminated all remaining alternatives
    except a northeast quadrant terminal, as proposed by the
    Authority, and the no action alternative. FAA screened out
    construction of a new airport at a different location because
    neither the Joint Powers Agreement nor Measure B
    authorized a new airport. Likewise, FAA eliminated the
    remote landside facility alternative because of a lack of
    authorization from Measure B. FAA also noted that the
    Authority would need to acquire property for the remote site
    and passengers would experience increased travel times.
    FAA ruled out a southeast quadrant terminal because of
    space limitations and the need to continue using the existing
    terminal during construction.
    In sum, out of the four action alternatives that met the
    Project’s purpose and need, FAA eliminated from detailed
    study three alternatives that “would not be practical or
    feasible to implement from a technical or economic
    standpoint” or that were inconsistent “with the development
    agreement . . . and . . . Measure B.” FAA eliminated
    construction of a new airport or a remote landside facility
    and listed Measure B as one reason for their elimination.
    FAA eliminated the southeast terminal alternative without
    reference to Measure B.
    18                CITY OF LOS ANGELES V. FAA
    2.
    Los Angeles argues that FAA improperly eliminated the
    new airport, remote landside facility, and southeast terminal
    alternatives on the basis that those alternatives were not
    approved pursuant to Measure B.
    But contrary to the premise of Los Angeles’s argument,
    FAA eliminated the new airport, remote landside facility,
    and southeast terminal alternatives based on rational
    considerations that were independent from Measure B.
    First, FAA concluded that the new airport alternative
    was not feasible “because the Joint Powers Agreement that
    forms [the Authority] does not provide the authority . . . to
    construct a replacement airport and close the existing
    airport.” Although FAA also stated that the Measure B vote
    did not authorize a new airport, the fact that the extant
    Airport operator could not shut down the Airport and build
    a new one was an independent reason for FAA to conclude
    that new airport construction is too “remote and speculative”
    to study in detail. Protect Our Cmtys. Found., 
    825 F.3d at 580
    . Indeed, Los Angeles does not argue that the Joint
    Powers Agreement was an insufficient ground for FAA to
    eliminate the new airport construction alternative.
    Second, FAA listed three reasons to eliminate a remote
    landside facility alternative aside from Measure B: (i) no
    space existed near the Airport for such a facility; (ii) “[s]ite
    selection would be limited by . . . the Authority’s inability to
    condemn or purchase property if the owners were unwilling
    to sell”; and (iii) travel time for passengers would increase.
    Los Angeles does not argue that those rationales were
    insufficient grounds to reject the remote landside facility
    alternative. At most, Los Angeles contends that FAA only
    said that implementation of a remote landside facility would
    CITY OF LOS ANGELES V. FAA                19
    be “difficult” on account of those factors, not infeasible. Los
    Angeles cites no authority that FAA had to use the word
    “infeasible” to eliminate an alternative from consideration.
    Cf. Env’t Def. Ctr., 36 F.4th at 877 (“Agencies do not have
    to consider . . . impractical alternatives.”). And all that
    NEPA requires is a brief discussion of the reasons for
    eliminating the remote landside facility alternative. Protect
    Our Cmtys. Found., 
    825 F.3d at 581
     (quoting 
    40 C.F.R. § 1502.14
    (a)).     FAA’s analysis of the space, property
    acquisition, and travel time factors met that standard.
    Finally, FAA did not rely on Measure B in eliminating
    the southeast terminal alternative, and Los Angeles does not
    argue that FAA’s stated reasons to eliminate that alternative
    were unreasonable. Los Angeles is therefore incorrect that
    FAA rejected a southeast terminal because of Measure B.
    It is simply not the case, as Los Angeles argues, that
    FAA used Measure B to “guarantee[] no alternative could
    survive the EIS’s screening process,” or that FAA’s
    reference to Measure B “ensured that all reasonable
    alternatives . . . are rejected.” There was no alternative that
    FAA found “feasible to implement from a technical and
    economic standpoint” that FAA then rejected as inconsistent
    with Measure B. Rather, FAA cited technical or economic
    reasons to cull the alternatives from the field. Los Angeles
    does not explain why FAA acted arbitrarily and capriciously
    in doing so.
    Moreover, Los Angeles has not met its burden, as a party
    challenging an agency’s failure to consider an alternative,
    “to show that the alternative is viable.” Alaska Survival, 
    705 F.3d at 1087
    ; Audubon Soc’y of Portland, 40 F.4th at 983
    (same).
    20                CITY OF LOS ANGELES V. FAA
    In in its opening brief, Los Angeles argues that the new
    airport and remote landside facility alternatives would meet
    FAA’s purpose and need—a conclusion that FAA reached
    as well—but does not explain how those alternatives were
    practical or feasible given FAA’s analysis. And in its reply,
    Los Angeles speculates that “[i]f Measure B . . . had not been
    part of the [calculus], [the remote landside facility
    alternative] might have been carried forward for detailed
    evaluation.” But Los Angeles does not respond to FAA’s
    analysis of available land for development, property
    acquisition issues, and travel time.
    Los Angeles also argues that the “airfield
    reconfiguration alternative” outlined in its comment letter
    was a reasonable alternative. Los Angeles forfeited that
    argument by raising it for the first time in its reply brief. See
    Martinez-Serrano v. INS, 
    94 F.3d 1256
    , 1259 (9th Cir.
    1996); Barnes v. FAA, 
    865 F.3d 1266
    , 1271 n.3 (9th Cir.
    2017); Kaffaga v. Estate of Steinbeck, 
    938 F.3d 1006
    , 1018
    n.8 (9th Cir. 2019); Burlington N. & Santa Fe Ry. Co. v.
    Vaughn, 
    509 F.3d 1085
    , 1093 n.3 (9th Cir. 2007). In any
    event, Los Angeles’s comment merely told FAA that it
    “should fully consider an airfield reconfiguration alternative
    that would also include upgrades to the existing terminal”
    without explaining why such an alternative would be
    practical or feasible. FAA did consider, and reject, an
    airfield reconfiguration alternative in the FEIS because state
    law restricted relocation or lengthening of the Airport’s
    runways. NEPA did not require FAA to consider further
    permutations of that alternative. See Westlands Water Dist.,
    376 F.3d at 871-72; Headwaters, Inc. v. Bureau of Land
    Mgmt., 
    914 F.2d 1174
    , 1181 (9th Cir. 1990) (“NEPA does
    not require a separate analysis of alternatives which are not
    significantly distinguishable from alternatives actually
    CITY OF LOS ANGELES V. FAA              21
    considered, or       which     have    substantially   similar
    consequences.”).
    In addition, Los Angeles argues that a “same size
    replacement terminal” alternative raised in the DEIS
    comments was viable. Like the airport reconfiguration
    alternative, this argument was newly raised in the reply brief
    and forfeited. Regardless, Los Angeles does not explain
    why a same size replacement terminal is practical or feasible
    or distinguish that alternative from those FAA did consider.
    See Westlands Water Dist., 376 F.3d at 871-72; Headwaters,
    
    914 F.2d at 1181
    .
    Accordingly, Los Angeles “has not provided a sufficient
    basis for questioning [FAA’s] determination not to further
    consider” the new airport, remote landside facility, same size
    replacement terminal, and airfield reconfiguration options.
    Audubon Soc’y of Portland, 40 F.4th at 983.
    Further, Los Angeles objects that FAA considered only
    the Project and the no action alternative. But “there is no
    minimum number of alternatives that must be discussed” in
    an EIS. Imperial Cnty., 
    767 F.3d at 797
     (quoting Laguna
    Greenbelt, Inc. v. U.S. Dep’t of Transp., 
    42 F.3d 517
    , 524
    (9th Cir. 1994). We have approved of an agency’s decision
    to compare the proposed action to only a no action
    alternative where the circumstances justified that choice.
    Imperial Cnty., 
    767 F.3d at 797-98
    ; Te-Moak Tribe of W.
    Shoshone of Nev., 
    608 F.3d 592
    , 602 n.11 (9th Cir. 2010).
    Other circuits have done the same. See Webster v. U.S. Dep’t
    of Agric., 
    685 F.3d 411
    , 427 (4th Cir. 2012); Citizens Against
    Burlington, Inc. v. Busey, 
    938 F.2d 190
    , 197 (D.C. Cir.
    1991); Tongass Conservation Soc’y v. Cheney, 
    924 F.2d 1137
    , 1141-42 (D.C. Cir. 1991); cf. Save Our Cumberland
    Mountains v. Kempthorne, 
    453 F.3d 334
    , 345 (6th Cir. 2006)
    22                    CITY OF LOS ANGELES V. FAA
    (rejecting agency’s decision to only consider approval or
    disapproval of permit where agency claimed it had no
    authority to consider other alternatives). Given FAA’s
    unchallenged technical and economic analysis that led to
    elimination of all alternatives except the proposed action and
    no action—as well as Los Angeles’s failure to identify a
    viable alternative that FAA did not consider—the
    circumstances here justify FAA’s conclusions. 6
    3.
    Finally, Los Angeles argues that because FAA’s
    screening process rejected alternatives that failed to meet the
    Project’s purpose and need and were inconsistent with
    Measure B, FAA predetermined the outcome of its NEPA
    review.
    6
    In addition, Los Angeles argues that FAA did not adequately consider
    the no action alternative. The FEIS studied the impacts of the no action
    alternative in detail because the regulations require it to do so. FAA
    asserted that the no action alternative would not meet the Project’s
    purpose and need because it would not remedy the facility’s
    nonconforming status. And in a table summarizing its analysis, FAA
    wrote “no” in a column that asked whether the alternative was practical,
    feasible, and consistent with Measure B. Los Angeles concludes that
    FAA “never considered the No Action Alternative a viable option.” But
    Los Angeles does not show that FAA predetermined its choice of the
    proposed action as the preferred alternative. Even assuming that FAA
    considered the no action alternative to be not practical or feasible, it does
    not follow that FAA would have granted the ALP application had the
    environmental impacts of the proposed action been significant as
    compared to the status quo. Indeed, the no action alternative serves as
    the benchmark against which an agency can compare the impacts of the
    action alternatives. See Kilroy v. Ruckelshaus, 
    738 F.2d 1448
    , 1453 (9th
    Cir. 1984). FAA made that comparison in selecting the proposed action
    as the preferred alternative, and Los Angeles does not suggest otherwise.
    CITY OF LOS ANGELES V. FAA                  23
    NEPA requires that an agency prepare the EIS
    “objectively” and “not as a subterfuge designed to
    rationalize a decision already made.” Metcalf v. Daley, 
    214 F.3d 1135
    , 1142 (9th Cir. 2000). An agency predetermines
    the outcome of its analysis in violation of NEPA when it
    makes “an irreversible and irretrievable commitment of
    resources” before finishing its review. 
    Id. at 1143
    . The
    standard for predetermination is high and not met by mere
    partiality on the part of the agency. See 
    id. at 1142
     (“NEPA
    does not require that agency officials be subjectively
    impartial.” (cleaned up)); see Forest Guardians v. U.S. Fish
    & Wildlife Serv., 
    611 F.3d 692
    , 714 (10th Cir. 2010); Env’t
    Def. Fund v. Corps of Eng’rs of the U.S. Army, 
    470 F.2d 289
    ,
    295 (8th Cir. 1972). Indeed, an agency “can formulate a
    proposal or even identify a preferred course of action before
    completing an EIS.” Ass’n of Pub. Agency Customers, Inc.
    v. Bonneville Power Admin., 
    126 F.3d 1158
    , 1185 (9th Cir.
    1997). And an agency can make statements favoring the
    proposed action, City of Mukilteo v. U.S. Dep’t of Transp.,
    
    815 F.3d 632
    , 638 (9th Cir. 2016), so long as the agency does
    not select its preferred alternative until the end of its review,
    Pac. Coast Fed. Of Fishermen’s Ass’ns v. Blank, 
    693 F.3d 1084
    , 1101 (9th Cir. 2012).
    Los Angeles has not met its burden to show that FAA
    predetermined its analysis prior to finishing the EIS.
    Metcalf, 
    214 F.3d at 1143
    . Los Angeles argues that FAA
    made “an irreversible and irretrievable commitment to the
    Project” by including Measure B in the screening criteria.
    But as we explained, FAA found that all action alternatives
    other than the Project were not feasible irrespective of
    Measure B, and Los Angeles has not identified any
    reasonable alternative that FAA did not consider. And the
    text of Measure B seems broad enough to admit alternatives
    24                CITY OF LOS ANGELES V. FAA
    other than the Project, as evidenced by the fact that FAA did
    not reference Measure B in eliminating a southeast terminal
    alternative.
    Even if it were true that the Measure B criteria foreclosed
    consideration of alternatives other than the Project, that
    would not be enough to establish an irreversible commitment
    to the Project. An irreversible commitment means that “the
    die already had been cast” in favor of the Project over other
    alternatives, see Metcalf, 
    214 F.3d at 1144
    , including the no
    action alternative. For example, in Metcalf v. Daley, the
    agency signed a contract committing it to support a proposed
    action before it had finished its review. 
    Id. at 1143-44
    . Had
    the agency made “its promise . . . conditional upon a NEPA
    determination that the . . . proposal would not significantly
    affect the environment,” 
    id. at 1144
    , the outcome might have
    been different since the agency still could have selected the
    no action alternative. Here, FAA could have picked the no
    action alternative after reviewing the Project’s
    environmental impacts. FAA made no promises to the
    Authority, and Los Angeles points to no evidence that FAA
    was blocked from denying the ALP. Accordingly, FAA’s
    inclusion of the Measure B criteria did not predetermine the
    outcome of FAA’s NEPA review.
    III.
    In its second issue, Los Angeles challenges FAA’s
    analysis of construction-related impacts. Because FAA
    failed to take a hard look at noise impacts from construction
    and based its cumulative impacts analysis on its inadequately
    considered conclusions about construction noise, we grant
    the petition on those limited grounds, for the reasons stated
    CITY OF LOS ANGELES V. FAA                       25
    in this section. 7 Having considered the rest of Los Angeles’s
    objections to FAA’s impact analysis and found them
    meritless, we deny the petition on all other grounds.
    A.
    “NEPA requires that a federal agency consider every
    significant aspect of the environmental impact of a proposed
    action . . . [and] inform the public that it has indeed
    considered environmental concerns in its decisionmaking
    process.” Earth Island Inst. v. U.S. Forest Serv., 
    351 F.3d 1291
    , 1300 (9th Cir. 2003) (internal quotation mark
    omitted). To accomplish that objective, NEPA “imposes
    procedural requirements designed to force agencies to take a
    ‘hard look’ at environmental consequences.” Ctr. for Cmty.
    Action, 18 F.4th at 598 (citation omitted).
    However, in reviewing the FEIS, we do not “fly-speck”
    FAA’s analysis and “hold it insufficient on the basis of
    inconsequential, technical deficiencies.” Audubon Soc’y of
    Portland, 40 F.4th at 984 (citation omitted). We employ the
    rule of reason to determine whether the EIS contains “a
    reasonably thorough discussion of the significant aspects of
    the probable environmental consequences.” Audubon Soc’y
    of Portland, 40 F.4th at 984 (citation omitted). Ultimately,
    we “must defer to an agency’s decision that is fully informed
    7
    Los Angeles also claims that FAA failed to take a hard look at the
    environmental justice impacts of the project, and the parties agree that
    we review FAA’s study of environmental justice impacts under the APA.
    Since FAA’s conclusion that “there would be no disproportionate noise
    impacts on minority populations” is predicated in part on the agency’s
    inadequate study of construction noise impacts, FAA should reconsider
    this analysis after correcting the construction noise analysis. We need
    not reach Los Angeles’s other arguments regarding FAA’s
    environmental justice analysis.
    26                CITY OF LOS ANGELES V. FAA
    and well-considered.” Id. (cleaned up). But the hard look
    standard is not satisfied when an agency relies “on incorrect
    assumptions or data in an EIS.” Native Ecosystems Council
    v. U.S. Forest Serv., 
    418 F.3d 953
    , 964 (9th Cir. 2005).
    B.
    Building a terminal complex in the northeast quadrant
    and demolishing the southeast terminal is estimated to take
    six years. Construction of the new terminal building,
    parking structures, fire station, and maintenance and cargo
    buildings would happen during the first four years of the
    project. In the fifth year, “approximately 82,020 cubic yards
    . . . of concrete and asphalt” would be demolished in the
    southeast quadrant. During construction and demolition,
    workers would use excavators, graders, dozers, loaders,
    forklifts, tractors, haul trucks, jackhammers, scrapers,
    backhoes, compressors, generators, and pile drivers.
    FAA did not take a hard look at noise impacts from the
    Project because its analysis rested on an unsupported and
    irrational assumption that construction equipment would not
    be operated simultaneously. As a result, FAA “failed to
    consider an important aspect of the problem,” WildEarth
    Guardians, 
    759 F.3d at 1069-70
     (citation omitted): the
    combined noise impacts from construction equipment on
    nearby neighborhoods. And because FAA’s noise analysis
    was deficient, on remand, FAA should reconsider whether
    the Project is consistent with Los Angeles’s noise standards.
    FAA divided its noise impact analysis into two parts.
    First, FAA considered potential noise impacts from Airport
    operations. For aircraft noise, the FEIS defined a significant
    noise impact as (i) a 1.5 decibel or greater noise increase for
    a noise sensitive area within a 65-decibel or greater noise
    contour, or (ii) a 1.5 decibel or greater noise increase that
    CITY OF LOS ANGELES V. FAA                         27
    results in a noise sensitive area falling within the 65-decibel
    or greater noise contour. Those decibel levels use a
    “Community Noise Equivalent Level” (CNEL) standard,
    which estimates sound levels over a 24-hour period. FAA
    concluded that Airport operations would not cause a
    significant noise impact if the proposed action were taken.
    Second, FAA analyzed construction noise. The FEIS
    noted that FAA has not established a significance threshold
    for noise from construction equipment. To estimate noise
    from specific equipment at fifty feet, FAA borrowed data
    from the Federal Highway Administration (FHWA)
    Roadway Construction Noise Model User’s Guide. FAA
    reported those noise levels in terms of an “Leq” standard, not
    CNEL. 8 The Leq standard “is the time-average of the total
    sound energy over a specified period.” Then, FAA
    calculated the noise levels from that equipment at 75, 100,
    150, 450, 900, and 1,250 feet using “the inverse square law
    for sound,” which provides for an “inversely proportional
    relationship between source sound pressure and distance
    from [the] sound source.” According to FAA’s calculations,
    the loudest piece of equipment that FAA studied, a
    jackhammer, would produce 88 decibels at 50 feet and 64
    decibels at 900 feet. Other land uses and noise sources were
    located between the construction and demolition sites and
    the closest noise sensitive land uses—residences that were
    930 and 1,400 feet away from the sites, respectively. Those
    residences were also within the CNEL 70-decibel noise
    contour of the I-5 freeway. FAA also pointed out that
    construction and demolition noise would be temporary and
    8
    On appeal, FAA explains that the FHWA’s model relies on the Lmax
    metric rather than the Leq metric, but this distinction does not affect our
    analysis.
    28               CITY OF LOS ANGELES V. FAA
    intermittent. Given the distances between the residences and
    the Airport and the existing background noise, FAA decided
    that construction noise impacts would be minimal.
    Los Angeles raises several purported errors in this
    analysis. The only one that has merit is Los Angeles’s
    contention that FAA failed to account for the simultaneous
    operation of construction equipment, failed to consider
    whether a significant impact would likely occur because of
    the combined effects of sound sources, and failed to perform
    the necessary calculations to conclude otherwise.
    In its noise analysis, FAA did not adequately “account
    for the fact that construction equipment would operate
    simultaneously,” as Los Angeles argues, even though FAA
    acknowledged that “[i]f two sounds of the same level are
    added, the sound level increases by approximately [three]
    [decibels].” FAA calculated how loud different types of
    equipment would sound at various distances from the site.
    Yet FAA did not calculate noise levels from multiple pieces
    of equipment running at the same time. Instead, based on a
    chart showing noise levels from different categories of
    equipment, FAA concluded that “noise from construction
    and demolition equipment would attenuate to less than
    CNEL 70 [decibels] at the closest noise sensitive land
    use[s].” FAA’s chart lists equipment in the singular, for
    example, “jackhammer,” and the model from which FAA
    copied the data refers to sound from “each piece of
    construction equipment.” Thus, FAA’s conclusion rests on
    an implicit premise that construction noise would be
    generated by one piece of equipment at a time. This
    assumption defies common sense.
    Nor does FAA support its implied assumption that
    construction equipment would run in sequence. FAA
    CITY OF LOS ANGELES V. FAA                 29
    observed that construction “would result in varying levels of
    noise generation subject to change based on the construction
    intensity and distance to a given receptor,” and explained
    that “construction and demolition noise would be temporary
    and . . . intermittent depending on the type of construction
    equipment needed.” These are not the kinds of expert
    scientific or technical judgments to which we defer. Cf. Nat.
    Res. Def. Council v. U.S. Forest Serv., 
    421 F.3d 797
    , 803
    n.13 (9th Cir. 2005) (deferring to Forest Service’s judgment
    on standard for wildlife viability). And even if both of those
    vague statements were true, it would still be the case that
    noise from construction equipment would overlap. This is
    especially true because the schedule shows that the terminal,
    parking structures, fire station, and equipment maintenance
    and airline cargo buildings will be constructed during the
    same five-year period. Indeed, while FAA claims that it did
    not have “specific construction details” when it drafted the
    FEIS, the record indicates that FAA relied on a “detailed
    construction schedule” including “phasing, equipment, [and]
    haul routes” for its air quality analysis. Regardless, a lack of
    details about the schedule does not give FAA the license to
    assume the site would be run in an illogical way.
    The reason FAA’s flawed assumption matters is
    apparent from the record. In its background information
    about noise, FAA explained that “[i]f two sounds of the same
    level are added, the sound level increases by approximately
    [three] [decibels].” So two 88-decibel jackhammers would
    add up to 91 decibels of noise at the site. FAA does not even
    try to calculate the combined effects from multiple pieces of
    equipment or the attenuation of that noise at the nearest
    residence. This is not an “inconsequential[] technical
    deficienc[y],” Audubon Soc’y of Portland, 40 F.4th at 984,
    but appears to be a fundamental error in the agency’s noise
    30                   CITY OF LOS ANGELES V. FAA
    analysis, see WildEarth Guardians v. Mont. Snowmobile
    Ass’n, 
    790 F.3d 920
    , 927 (9th Cir. 2015) (“NEPA requires
    more” than an agency asking the court “to assume the
    adequacy and accuracy of partial data without providing any
    basis for doing so.”).
    FAA’s hedging about noise from the I-5 corridor doesn’t
    change the equation. The FEIS states that the nearest
    residences fall within the CNEL 70-decibel noise contour of
    the I-5 freeway, and the FEIS concludes that construction
    noise would be minimal given that background noise. But
    FAA’s comparison of construction noise to the I-5 contour
    was based on calculations that failed to aggregate equipment
    noise, and it is unclear what FAA would have concluded had
    it found equipment noise to attenuate to more than 70
    decibels at the nearest residence. Moreover, the FEIS
    reports equipment noise and I-5 noise in two different
    standards. Equipment noise was calculated in Leq, I-5 noise
    in CNEL. FAA never explains how, or whether, those
    standards can be mixed and matched to decide that certain
    Leq levels are not significant given certain CNEL levels.
    Since FAA’s analysis studies only sound produced by
    equipment in isolation, the FEIS does not contain a
    “reasonably thorough discussion” of construction noise,
    Audubon Soc’y of Portland, 40 F.4th at 984 (citation
    omitted); see Native Ecosystems Council, 697 F.3d at 1051.
    The petition is granted on this basis. 9
    9
    The dissent argues that in granting the petition, we rely on an argument
    that Los Angeles failed to raise before FAA. But FAA was put on notice
    about this defect in its analysis. Los Angeles’s comment letter said that
    “the DEIS should provide a more thorough assessment of cumulative
    construction effects. . . . [C]onstruction activities, which will all occur
    on the same site during site operations, will likely lead to combined . . .
    CITY OF LOS ANGELES V. FAA                         31
    Los Angeles also asserts that FAA failed to discuss
    inconsistencies between the Project and City noise
    standards. Under NEPA, agencies must “discuss[] . . . .
    [p]ossible conflicts between the proposed action and the
    objectives of . . . local . . . land use plans, policies, and
    controls.” 
    40 C.F.R. § 1502.16
    (c). “Where an inconsistency
    exists,” between “a proposed action” and “local . . . laws,”
    the EIS “should describe the extent to which the agency
    would reconcile its proposed action with the . . . law.” 
    Id.
     §
    1506.2(d). Still, “NEPA does not require an agency to list
    every way in which a project is consistent with . . . a land use
    plan.” Crenshaw Subway Coalition v. L.A. Cnty. Metro.
    noise . . . effects, yet the DEIS does not address these combined effects.”
    Los Angeles also urged FAA to revise the DEIS “to properly explain its
    conclusion that noise will be attenuated such that there will not be
    adverse noise impacts.” Similarly, another comment letter says that “all
    construction equipment identified throughout the Air Quality Appendix
    (Appendix E) should be combined and assessed with existing airport
    operations.” Even assuming that the comment letters are inadequate, this
    flaw in FAA’s analysis was sufficiently obvious that FAA had to address
    it. In Department of Transportation v. Public Citizen, the Supreme Court
    said that “the agency bears the primary responsibility to ensure that it
    complies with NEPA, and an EA’s or an EIS’ flaws might be so obvious
    that there is no need for a commentator to point them out specifically in
    order to preserve its ability to challenge a proposed action.” 
    541 U.S. 752
    , 765 (2004) (citation omitted). We have “interpreted the ‘so
    obvious’ standard as requiring that the agency have independent
    knowledge of the issues that concern petitioners.” Barnes v. U.S. Dep’t
    of Transp., 
    655 F.3d 1124
    , 1132 (9th Cir. 2011). Here, as we explained,
    the agency’s own reference materials instructed it to add together sounds
    from multiple sources. And the CEQA review did analyze simultaneous
    noise effects. FAA did not do so in its EIS. Finally, the government
    does not argue that Los Angeles failed to preserve this issue, and we
    should not take up administrative waiver sua sponte. The government
    “waive[d] waiver . . . by failing to assert it.” Norwood v. Vance, 
    591 F.3d 1062
    , 1068 (9th Cir. 2010) (cleaned up).
    32               CITY OF LOS ANGELES V. FAA
    Transp. Auth., No. 11-CV-9603 (FMO), 
    2015 WL 6150847
    ,
    at *20 (C.D. Cal. Sept. 23, 2015). Having concluded that
    construction noise would not cause a significant impact,
    FAA did not have to say that the proposed action would be
    consistent with Los Angeles’s standards. However, since
    FAA’s conclusion about noise impacts may be revised on
    remand, FAA should take another look at the proposed
    action’s consistency with those standards.
    Los Angeles’s other challenges to FAA’s noise analysis,
    including FAA’s analysis of ambient noise from
    construction truck trips and construction-related vibration
    impacts are not persuasive, and we decline to grant the
    petition on those grounds.
    C.
    Among NEPA’s requirements, an agency must consider
    a project’s “cumulative impacts.” Ctr. for Cmty. Action &
    Env’t Justice v. FAA, 
    18 F.4th 592
    , 603 (9th Cir. 2021).
    Cumulative impacts are “the impact on the environment
    which results from the incremental impact of the action
    when added to other past, present, or reasonably foreseeable
    future actions.” 
    Id.
     (citation omitted). They “can result from
    individually minor but collectively significant actions taking
    place over a period of time.” Kern v. U.S. Bureau of Land
    Mgmt., 
    284 F.3d 1062
    , 1075 (9th Cir. 2002) (citation
    omitted).
    The FEIS assumed that all “[e]nvironmental resource
    categories that would not result in potential adverse effects
    as a result of the . . . Project cannot result in cumulative
    impacts.” FAA listed “Noise and Noise-Compatible Land
    Use” as an impact category that would “not result in
    potential adverse effects.” But FAA’s determination that the
    proposed action would have minimal noise impacts was
    CITY OF LOS ANGELES V. FAA                        33
    based on a flawed study of construction noise. As we
    explained, FAA failed to take a hard look at the noise
    impacts from construction equipment on nearby residences.
    Since FAA did not properly analyze the possible effects of
    the proposed action, it was a clear error in judgment to
    conclude that the action would not have an “incremental
    impact . . . when added to other past, present, or reasonably
    foreseeable future actions.” Ctr. for Cmty. Action, 18 F.4th
    at 603 (citation omitted).
    On remand, the agency must revisit its cumulative
    impacts analysis after taking a hard look at noise impacts
    from construction equipment. 10
    IV.
    The petition for review is GRANTED in part and the
    case is REMANDED to the agency. On remand, FAA is
    directed to address (i) the deficiency in its construction noise
    analysis described in this opinion; (ii) the resulting
    deficiency in its cumulative impacts analysis; and (iii) the
    resulting deficiency in its environmental impacts analysis.
    10
    FAA argues that it “reasonably declined to conduct an extensive
    analysis of cumulative noise impacts, when it found that the Project
    would not produce any significant noise impacts.” This reflects a
    misunderstanding of the cumulative impact requirement.               It is
    uncontested that multiple noise sources that individually fall short of a
    significance threshold may accumulate to surpass the threshold. FAA
    may only decline to consider cumulative noise impacts if it concludes
    either that the cumulative noise impact from relevant sources will not be
    significant or that the project’s impact is so small that consideration of
    its contribution would not provide an “informed analysis.” N. Plains
    Res. Council, Inc. v. Surface Transp. Bd., 
    668 F.3d 1067
    , 1082 (9th Cir.
    2011); Nw. Env’t Advocates v. Nat’l Marine Fisheries Serv., 
    460 F.3d 1125
    , 1140 (9th Cir. 2006).
    34               CITY OF LOS ANGELES V. FAA
    BUMATAY, Circuit Judge, dissenting:
    Our court grants the City of Los Angeles’s petition
    challenging the Federal Aviation Administration’s final
    environmental impact statement on the reconstruction of the
    Bob Hope Burbank Airport. The majority remands for the
    FAA’s reconsideration of the proposed project’s
    construction noise impacts. In doing so, the majority ignores
    the FAA’s reasonable assumptions about noise effects.
    Because the FAA’s construction noise analysis was not
    arbitrary or capricious, I respectfully dissent from granting
    the petition.
    I.
    Our court remands because the majority disagrees with
    the FAA’s assessment that the proposed project’s
    construction impact on noise quality would be “minimal.”
    See Maj. Op. 28–30. The majority says that the FAA erred
    in failing to “account for the simultaneous operation of
    construction equipment” in its analysis. 
    Id. at 28
    . But, in
    reaching this conclusion, the majority relies on an argument
    not raised before the agency and fails to defer to the FAA’s
    reasonable assumptions.
    An agency must take a “hard look at environmental
    consequences.” Bark v. U.S. Forest Serv., 
    958 F.3d 865
    , 868
    (9th Cir. 2020) (simplified). We are only looking for “a
    reasonably thorough discussion of the significant aspects of
    the probable environmental consequences.” Audubon Soc’y
    of Portland, 40 F.4th at 984 (simplified). So analytical
    perfection isn’t necessary. And we “refrain from acting as a
    type of omnipotent scientist and must defer to an agency’s
    decision that is fully informed and well-considered.” Id.
    (simplified).
    CITY OF LOS ANGELES V. FAA                  35
    A.
    The record shows that the FAA thoroughly considered
    the environmental consequences of the project’s
    construction noise. The FAA first identified the nearest
    “noise-sensitive land uses” that could be affected by
    construction noise—residential neighborhoods about 930
    feet away from the airport’s construction zone. And those
    neighborhoods are within the “noise contour” of the I-5
    freeway—meaning that they are already impacted by
    ambient noise reaching 70 decibels. It then factored into its
    analysis the noise levels generated by various construction
    equipment at different distances:
    Putting this all together, the FAA concluded that “the noise
    from construction and demolition equipment would
    attenuate to less than . . . 70 dB at the closest noise sensitive
    land use[s].”
    This is consistent with the data. Even the loudest
    construction equipment—the jackhammer—would generate
    36               CITY OF LOS ANGELES V. FAA
    a noise level of less than 64 decibels at 930 feet away. In
    other words, the construction equipment would be quieter
    than the noise from the freeway. The FAA also noted that
    construction noise would be temporary and intermittent.
    With all this in mind—distance, existing freeway noise, and
    the temporary and intermittent nature of construction—the
    FAA ultimately concluded that the construction noise level
    impact would be “minimal for the closest noise sensitive
    land uses.”
    Simply, the FAA “consider[ed] every significant aspect
    of the environmental impact of [the project] . . . and
    inform[ed] the public that it [had] indeed considered
    environmental concerns in its decisionmaking process.”
    Earth Island Inst. v. U.S. Forest Serv., 
    351 F.3d 1291
    , 1300
    (9th Cir. 2003) (simplified). And that’s all the law requires.
    B.
    To discard the FAA’s analysis, the majority relies on an
    argument that appears for the first time in one sentence of
    the City’s opening brief—that the FAA did not “account for
    the fact that construction equipment would operate
    simultaneously.” Maj. Op. 28. If the FAA analyzed the
    operation of two jackhammers at the same time, then, the
    majority assumes, construction noise would then be
    significant. But the majority only gets there by cherry-
    picking the data.
    The FAA provided several assumptions about sound that
    it used to calculate noise impacts:
    •   If two sounds of the same level are added,
    the     sound    level    increases    by
    approximately 3 dB.        For example:
    60 dB + 60 dB = 63 dB.
    CITY OF LOS ANGELES V. FAA               37
    •   The sum of two sounds of a different level
    is only slightly higher than the louder
    level. For example: 60 dB + 70 dB = 70.4
    dB.
    •   Sound from a “point source,” such as an
    aircraft, decreases approximately 6 dB
    for each doubling of distance.
    •   Although the human ear can detect a
    sound change as faint as 1dB, the typical
    person does not perceive changes of less
    than approximately 3 dB.
    •   A 10 dB change in sound level is
    perceived by the average person as a
    doubling, or halving, of the sound’s
    loudness.
    The majority homes in on the FAA’s background
    assumption that when “two sounds of the same level are
    added, the sound level increases by approximately 3 dB.”
    Maj. Op. 29. The majority then concludes that this
    assumption shows that “two 88-decibel jackhammers would
    add up to 91 decibels of noise at the site.” 
    Id.
     The majority
    then speculates that construction would necessarily require
    two jackhammers operating at the same time. The majority
    thus manufactures a scenario where construction noise could
    be “significant” in its view.
    There are several problems with this scenario. First, it
    ignores the FAA’s conclusion that the closest noise-sensitive
    neighborhoods are 930 feet away from where the
    jackhammers would be operating. So, even if we were to
    add the sounds of two jackhammers running at the same
    time, it would only reach 67 decibels (64 + 3 dB) at that
    distance. Thus, even under the majority’s scenario, the noise
    38               CITY OF LOS ANGELES V. FAA
    level would still “attenuate to less than . . . 70 dB”—as the
    FAA already concluded. And thus, there’s no reason to
    accept that the FAA did not consider multiple construction
    equipment operating at the same time.
    Second, applying those same assumptions to other
    construction equipment would result in even less noise than
    two jackhammers running at once. This is because “[t]he
    sum of two sounds of a different level is only slightly higher
    than the louder level.” As an example, merging two sounds
    of 60 decibels and 70 decibels would only result in a 70.4
    decibel noise. So running a backhoe (60 dB) and a
    jackhammer (64 dB) at the same time would be only slightly
    louder than just running the jackhammer alone. And we
    shouldn’t speculate on what would happen if three
    jackhammers were to operate simultaneously because no
    party has explained how three sounds would accumulate.
    And really? Does the FAA really need to assume that three
    jackhammers would operate at the same time for its analysis
    to be “reasonably thorough”? Audubon Soc’y of Portland,
    40 F.4th at 984.
    Third, the majority disregards that the closest
    neighborhoods to the project are next to a major highway.
    The highway has a 70-decibel level under the Community
    Noise Equivalent Level (“CNEL”), which averages sound
    levels during a “24-hour equivalent.” Such a rating suggests
    that highway noise is high and sustained throughout the day.
    Meanwhile, the FAA reasonably assumed that construction
    noise would not run all day, every day. So the FAA assessed
    that construction noise would likely be drowned out by the
    highway noise and not have any impact at all during non-
    work hours.
    CITY OF LOS ANGELES V. FAA               39
    And fourth, the majority never acknowledges that “the
    typical person does not perceive changes of less than
    approximately 3 dB.” And thus, even under the majority’s
    scenario, any noise change would barely be perceptible to
    the typical person.
    Rather than picking and choosing the data we want, we
    should have deferred to the FAA’s reasonable analysis. I
    would have denied the City’s petition challenging the FAA’s
    construction noise analysis.
    II.
    The majority rightly rejects the bulk of the City’s
    petition. I agree with those parts of the majority opinion. I
    also agree with the majority that the City has standing to
    pursue this petition based on the proposed project’s impact
    on the City’s roads and tax base. But our court errs by
    granting the petition and remanding for reconsideration of
    the project’s construction noise impacts, cumulative
    impacts, and related assessments. Such a decision was based
    on faulty assumptions. I thus respectfully dissent.
    

Document Info

Docket Number: 21-71170

Filed Date: 3/29/2023

Precedential Status: Precedential

Modified Date: 3/29/2023

Authorities (30)

City of Mukilteo v. U.S. Dept. of TransporTation , 815 F.3d 632 ( 2016 )

Barnes v. Federal Aviation Administration , 865 F.3d 1266 ( 2017 )

Environmental Defense Fund, Inc. v. Corps of Engineers of ... , 470 F.2d 289 ( 1972 )

Samuel Martinez-Serrano v. Immigration and Naturalization ... , 94 F.3d 1256 ( 1996 )

Winter v. Natural Resources Defense Council, Inc. , 129 S. Ct. 365 ( 2008 )

The Lands Council v. McNair , 537 F.3d 981 ( 2008 )

Northern Plains Resource Council, Inc. v. Surface ... , 668 F.3d 1067 ( 2011 )

Webster v. United States Department of Agriculture , 685 F.3d 411 ( 2012 )

Alaska Survival v. Surface Transportation Board , 705 F.3d 1073 ( 2013 )

California ex rel. Imperial County Air Pollution Control ... , 767 F.3d 781 ( 2014 )

Protect Our Communities Foundation v. Jewell , 825 F.3d 571 ( 2016 )

Burlington Northern & Santa Fe Railway Co. v. Vaughn , 509 F.3d 1085 ( 2007 )

Wildearth Guardians v. U.S. Environmental Protection Agency , 759 F.3d 1064 ( 2014 )

Department of Transportation v. Public Citizen , 124 S. Ct. 2204 ( 2004 )

League of Wilderness Defenders-Blue Mountains Biodiversity ... , 689 F.3d 1060 ( 2012 )

Headwaters, Inc. v. Bureau of Land Management , 914 F.2d 1174 ( 1990 )

Tongass Conservation Society v. Richard B. Cheney in His ... , 924 F.2d 1137 ( 1991 )

Te-Moak Tribe of Western Shoshone v. United States ... , 608 F.3d 592 ( 2010 )

Arrington v. Daniels , 516 F.3d 1106 ( 2008 )

Robertson v. Methow Valley Citizens Council , 109 S. Ct. 1835 ( 1989 )

View All Authorities »