DC v. DOL ( 2016 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued September 10, 2015             Decided April 5, 2016
    No. 14-5132
    DISTRICT OF COLUMBIA AND CCDC OFFICE LLC,
    APPELLEES
    v.
    DEPARTMENT OF LABOR, ET AL.,
    APPELLANTS
    METROPOLITAN REGIONAL COUNCIL OF CARPENTERS,
    UNINCORPORATED LABOR ORGANIZATION, ET AL.,
    APPELLEES
    Consolidated with 14-5133
    Appeals from the United States District Court
    for the District of Columbia
    (No. 1:13-cv-00730)
    John S. Koppel, Attorney, U.S. Department of Justice,
    argued the cause for appellants. With him on the briefs were
    Benjamin C. Mizer, Acting Assistant Attorney General,
    Vincent H. Cohen, Jr., Acting U.S. Attorney, and Michael Jay
    Singer, Attorney. Jeffrica J. Lee, Attorney, U.S. Department
    of Justice, entered an appearance.
    2
    Terry R. Yellig and Esmeralda Aguilar were on the brief
    for intervenors-defendants-appellants Metropolitan Regional
    Council of Carpenters, et al.
    Carl J. Schifferle, Assistant Attorney General, Office of
    the Attorney General for the District of Columbia, argued the
    cause for appellee District of Columbia. With him on the
    brief were Karl A. Racine, Attorney General, Todd S. Kim,
    Solicitor General, and Loren L. AliKhan, Deputy Solicitor
    General.
    Maurice Baskin argued the cause and filed the brief for
    appellee CCDC Office LLC.
    Kevin J. McKeon was on the brief for amici curiae
    Associated Builders and Contractors, Inc. and National
    Association of Manufacturers in support of appellee CCDC
    Office LLC. Shelly L. Ewald entered an appearance.
    Before: GARLAND, ∗ Chief Judge, KAVANAUGH, Circuit
    Judge, and WILLIAMS, Senior Circuit Judge.
    Opinion for       the   Court   filed   by   Circuit   Judge
    KAVANAUGH.
    KAVANAUGH, Circuit Judge: CityCenterDC is a large
    private development in the heart of Washington, D.C. It
    features upscale retail stores such as Hermès, Boss, and Louis
    Vuitton; high-end restaurants such as DBGB and Centrolina;
    the large private law firm of Covington & Burling; and luxury
    residences.
    ∗
    Chief Judge Garland was a member of the panel at the time
    the case was argued but did not participate in this opinion.
    3
    The question in this case is whether the Davis-Bacon Act
    applies to the construction of CityCenterDC. As relevant
    here, the Davis-Bacon Act applies when the District of
    Columbia enters into a “contract . . . for construction” of
    “public works.” 1 The Act guarantees prevailing wages to
    construction workers on those projects. If the Act applies
    here, the construction workers who helped build
    CityCenterDC might be entitled to higher wages than they in
    fact received.
    As the statutory definition reveals, two conditions must
    be present in order for the Davis-Bacon Act to apply here: (1)
    D.C. must have been a party to the contracts for construction
    of CityCenterDC, and (2) CityCenterDC must be a public
    work. To illustrate, suppose the District of Columbia
    contracted with a construction contractor to build a new
    public park. That would be a classic example of a
    construction project covered by the Davis-Bacon Act.
    But this case differs from the classic Davis-Bacon
    scenario in two critical respects, each of which independently
    suffices to take the CityCenterDC construction project outside
    the reach of the Davis-Bacon Act.
    1
    The relevant statutory provision provides in full: “The
    advertised specifications for every contract in excess of $2,000, to
    which the Federal Government or the District of Columbia is a
    party, for construction, alteration, or repair, including painting and
    decorating, of public buildings and public works of the Government
    or the District of Columbia that are located in a State or the District
    of Columbia and which requires or involves the employment of
    mechanics or laborers shall contain a provision stating the
    minimum wages to be paid various classes of laborers and
    mechanics.” 
    40 U.S.C. § 3142
    (a).
    4
    First, the District of Columbia was not a party to the
    construction contracts for the building of CityCenterDC.
    D.C. owns the land on which CityCenterDC stands, but D.C.
    rented the land to private developers in a series of 99-year
    leases. The private developers then entered into construction
    contracts with general contractors to build CityCenterDC.
    The developers – not D.C. – contracted with the construction
    contractors who built CityCenterDC. That matters for
    purposes of the Davis-Bacon Act. Put simply, because D.C.
    was not a party to the construction contracts, the Davis-Bacon
    Act does not apply to CityCenterDC.
    Second, and an independent reason why the Davis-Bacon
    Act does not apply here, CityCenterDC is not a “public
    work.” To qualify as a public work, a project must possess at
    least one of the following two characteristics: (i) public
    funding for the project’s construction or (ii) government
    ownership or operation of the completed facility, as with a
    public highway or public park. Here, CityCenterDC’s
    construction was not publicly funded, and CityCenterDC is
    not a government-owned or government-operated facility. So
    CityCenterDC is not a public work. 2
    In short, D.C. was not a party to the contracts for
    construction of CityCenterDC, and CityCenterDC is not a
    public work. For either of those two alternative and
    independent reasons, the Davis-Bacon Act does not apply to
    the construction of CityCenterDC.
    2
    At least one of those two characteristics is necessary for a
    project to qualify as a public work; we need not and do not decide
    whether either characteristic alone is sufficient for a project to
    qualify as a public work.
    5
    It bears emphasis, moreover, that in the 80 years since its
    enactment, the Davis-Bacon Act has never been applied to a
    construction project such as CityCenterDC that is privately
    funded, privately owned, and privately operated. The novelty
    of the U.S. Department of Labor’s interpretation strongly
    buttresses our conclusion that the Act does not apply here.
    See, e.g., FDA v. Brown & Williamson Tobacco Corp., 
    529 U.S. 120
    , 160 (2000); Loving v. IRS, 
    742 F.3d 1013
    , 1021
    (D.C. Cir. 2014).
    In a thorough and persuasive opinion, the District Court
    held that the Davis-Bacon Act does not apply to
    CityCenterDC. We affirm the judgment of the District Court.
    I
    To evaluate whether the Davis-Bacon Act applies to the
    construction of CityCenterDC, we begin by examining the
    history of the Act, the details of CityCenterDC, and the
    procedural background of this case.
    A
    In 1931, Congress passed and President Hoover signed
    the Davis-Bacon Act. By that point in the Great Depression,
    economic activity, including construction, had already
    declined significantly. To offset the dropoff in private
    construction and to help put construction workers back to
    work, the Federal Government launched a variety of
    construction projects to build and repair public works. But
    the government construction projects led to a collateral
    problem. Some government agencies awarded construction
    contracts to contractors who hired cheap itinerant labor and
    made low-wage bids. The market impact, Congress believed,
    6
    was to depress wages for local construction workers below
    what the local workers otherwise would receive.
    To prevent government contracts from depressing wages
    for local construction workers, the Davis-Bacon Act
    guaranteed prevailing local wages to construction workers on
    federal and D.C. construction projects for public buildings.
    Offering a succinct summary of the Act’s purpose, one
    Member of Congress remarked: “The purpose of this bill is to
    require the contractors, including subcontractors, to pay not
    less than the prevailing rate of wages for work of a similar
    nature in the city, town, village, or other civil division of the
    State in which the public buildings are located, or in the
    District of Columbia.” 74 Cong. Rec. 6515 (1931) (statement
    of Rep. Kopp) (internal quotation marks omitted).
    As initially enacted, the Davis-Bacon Act covered only
    federal and D.C. contracts for construction of “public
    buildings.” Pub. L. No. 71-798, 
    46 Stat. 1494
     (1931). In
    1935, Congress passed and President Franklin Roosevelt
    signed a new law that amended the Act to cover federal and
    D.C. contracts for construction of “public works,” as well as
    public buildings. Act of Aug. 30, 1935, Pub. L. No. 74-403,
    
    49 Stat. 1011
    .
    B
    In July 2001, a District of Columbia task force
    recommended a “mixed-use” urban neighborhood on the site
    of the D.C. convention center. In September 2002, acting on
    that recommendation, D.C. issued a Request for Proposals for
    a Development Partner. D.C. ultimately chose various
    developers, whom we will refer to collectively as “the
    Developers.”
    7
    D.C. and the Developers entered into 99-year ground
    lease agreements for the right to use the property. Under
    those lease agreements, the Developers agreed to pay D.C. at
    least $2 million each year.
    D.C. and the Developers also entered into development
    agreements. The development agreements obligated the
    Developers to, among other things, build CityCenterDC. As
    required by those development agreements, the Developers
    would enter into contracts with general contractors for
    construction of CityCenterDC. D.C. maintained the right to
    approve the Developers’ general contractors for various
    components of the project, and to approve the construction
    contracts entered into between the Developers and the
    contractors.
    Under the lease agreements and the development
    agreements, D.C. would not be a party to any construction
    contracts for the building of CityCenterDC.       Rather,
    according to the lease agreements and the development
    agreements, the required follow-on construction contracts
    would be executed between the Developers and general
    contractors.
    Construction of CityCenterDC began in 2011. Today,
    CityCenterDC is already home to several upscale shops and
    restaurants, and to a major private law firm. When it is
    finished, CityCenterDC will house approximately 60 retail
    stores and nearly 700 residential units. A 370-room hotel
    catering to luxury travelers is scheduled to open in the next
    three years.
    To summarize the basic contractual relationships
    underlying CityCenterDC: (1) D.C. and the Developers
    entered into various lease agreements and development
    8
    agreements; and (2) those lease agreements and development
    agreements, in turn, directed the Developers (not D.C.) to
    execute construction contracts with general contractors.
    D.C. provided no public funding for construction of
    CityCenterDC.     D.C. does not occupy any space at
    CityCenterDC. D.C. does not own or operate any of the
    businesses located there. And D.C. does not offer any
    government services there.
    C
    In April 2008, a labor union – the Mid-Atlantic Regional
    Council of Carpenters – asked D.C. to determine whether the
    Davis-Bacon Act applied to the construction of
    CityCenterDC. In response to that request, Deputy D.C.
    Mayor Neil Albert concluded that the Act did not apply
    because “the District will not be party to any construction
    contracts, the project to be built will not be owned by the
    District and no District funds will be used to pay construction
    costs.”
    The following year, the Carpenters requested a ruling on
    the issue from the U.S. Department of Labor. In August
    2010, the Chief of the Branch of Government Contracts at the
    U.S. Department of Labor ruled that the Davis-Bacon Act did
    not apply to CityCenterDC because the project was not a
    public work. The Branch Chief noted the primarily private
    purpose of the project and the lack of government funding,
    among other things.
    The Carpenters administratively appealed the Branch
    Chief’s ruling within the U.S. Department of Labor. In June
    2011, the Administrator of the Wage and Hour Division of the
    U.S. Department of Labor overturned the Branch Chief’s
    9
    decision. The Administrator determined that the various
    development agreements qualified as contracts for
    construction within the meaning of the Davis-Bacon Act.
    And the Administrator concluded that CityCenterDC was a
    public work. Describing the private component of the project
    as “not insubstantial,” the Administrator nonetheless found
    that CityCenterDC “sufficiently” served the public interest to
    qualify as a public work.
    D.C. then appealed that ruling to the Administrative
    Review Board of the U.S. Department of Labor. The Board
    affirmed, concluding that the various agreements between
    D.C. and the Developers were contracts for construction
    under the Davis-Bacon Act and, further, that CityCenterDC
    was a public work within the meaning of the Act.
    D.C. then filed suit in federal court, seeking declaratory
    and injunctive relief against the U.S. Department of Labor.
    On cross-motions for summary judgment, the District
    Court ruled for D.C. The District Court concluded that the
    “plain language of the statute, as well as its history and
    purpose” make clear that the Davis-Bacon Act does not cover
    private projects like CityCenterDC. District of Columbia v.
    Department of Labor, 
    34 F. Supp. 3d 172
    , 182 (D.D.C. 2014).
    In reaching its conclusion, the District Court noted the novelty
    of the position advanced by the U.S. Department of Labor:
    “All parties in this case agree that” the Davis-Bacon Act “has
    never before been applied to a project that, like
    CityCenterDC, is privately financed, privately owned, and
    privately maintained.” 
    Id.
    Our review of the District Court’s interpretation of the
    Davis-Bacon Act is de novo.
    10
    II
    For the Davis-Bacon Act to apply, a project must involve
    (1) a “contract . . . to which the Federal Government or the
    District of Columbia is a party, for construction” of (2)
    “public works.” 
    40 U.S.C. § 3142
    (a). The CityCenterDC
    project meets neither requirement. First, D.C. is not a party to
    the contracts for construction of CityCenterDC. Second,
    CityCenterDC is not a public work.
    A
    By its terms, the Davis-Bacon Act applies to construction
    contracts between a federal or D.C. government agency and a
    construction contractor. In this case, the U.S. Department of
    Labor seeks to stretch the Act to cover a three-party
    relationship in which a government agency rents property to a
    private developer, and the private developer in turn enters into
    a construction contract with a construction contractor. Or put
    another way, the Department contends that the Act covers
    contracts entered into by D.C. that are not themselves
    construction contracts but rather are contracts with developers
    where the developers will then separately enter into
    construction contracts with construction contractors.
    No court has previously sanctioned such a significant
    expansion of the Davis-Bacon Act. We will not be the first.
    The U.S. Department of Labor insists that the statutory
    term “contract . . . for construction” is sufficiently indefinite
    to render its reading a reasonable one deserving deference. It
    is true that under Chevron, assuming it applies here, the
    fundamental question is not whether we think the
    Department’s interpretation is correct, but whether the
    Department’s interpretation of the Act is at least reasonable in
    11
    light of any ambiguities in the statute. In making that
    determination, however, Chevron itself tells us that we must
    first employ the traditional tools of statutory construction to
    interpret the statute and to resolve any ambiguities. Chevron
    U.S.A. Inc. v. Natural Resources Defense Council, Inc., 
    467 U.S. 837
    , 843 n.9 (1984). Only if we are then still left with an
    ambiguity do we proceed to step two. In step two, we defer to
    the agency’s reading if that reading is at least reasonable.
    “No matter how it is framed, the question a court faces
    when confronted with an agency’s interpretation of a statute it
    administers is always, simply, whether the agency has stayed
    within the bounds of its statutory authority.” City of
    Arlington v. FCC, 
    133 S. Ct. 1863
    , 1868 (2013). In this case,
    we conclude that the U.S. Department of Labor has not done
    so. Its interpretation of the phrase “contract . . . for
    construction” contravenes the text, structure, and purpose of
    the Act.
    The text of the Act is straightforward. As relevant here,
    the Act covers contracts “for construction” to which “the
    District of Columbia is a party.” But the parties to the
    contracts for construction in this case were the private
    developers and general contractors.         The Act cannot
    reasonably be read to cover construction contracts, such as
    these, to which D.C. is not a party. That reading would
    require us to erase the phrase “to which the Federal
    Government or the District of Columbia is a party” from the
    statute. Courts are not at liberty to rewrite laws in that
    fashion. See generally Milner v. Department of the Navy, 
    131 S. Ct. 1259
    , 1271 (2011); Exxon Mobil Corp. v. Allapattah
    Services, Inc., 
    545 U.S. 546
    , 557 (2005).
    Contrary to the U.S. Department of Labor’s suggestion,
    moreover, neither the lease agreements nor the development
    12
    agreements between D.C. and the Developers are themselves
    contracts for construction to which D.C. is a party. A contract
    for construction means a contract in which one party will
    perform construction in exchange for the other party’s
    payment or other consideration. The lease agreements and the
    development agreements were not contracts for construction
    under any reasonable understanding of what a contract for
    construction entails. Rather, those agreements refer to the
    eventual construction that the Developers would pay for.
    Those agreements define “Construction Contract” as “each
    contract with a General Contractor for the construction of all
    or any part” of CityCenterDC. D.C. itself never entered into
    contracts for construction of CityCenterDC.
    The Department’s interpretation of the statutory term
    “contract . . . for construction” would significantly enlarge the
    scope of the Davis-Bacon Act.                 The Department’s
    interpretation would embrace any lease, land-sale, or
    development contract between the Federal Government or
    D.C. and another party, so long as the agreements required the
    counterparty in turn to undertake more than an incidental
    amount of construction. The terms of the Davis-Bacon Act
    are not so malleable. A contract for construction is a contract
    for construction. And a lease, land-sale, or development
    agreement that contemplates one of the parties entering into a
    future contract for construction with a third party construction
    contractor is not itself a contract for construction. 3
    3
    The Department cites a few agency decisions indicating that
    certain kinds of lease agreements may fall within the Davis-Bacon
    Act’s definition of “contract . . . for construction.” See, e.g.,
    Phoenix Field Office, Bureau of Land Management, 
    2001 WL 767573
     (2001); Crown Point, Indiana Outpatient Clinic, 
    1987 WL 247049
     (1987), aff’d sub nom. Building & Construction Trades
    Department, AFL-CIO, v. Turnage, 
    705 F. Supp. 5
     (D.D.C. 1988);
    Military Housing Ft. Drum, New York, 
    1985 WL 167239
     (1985).
    13
    The U.S. Department of Labor retorts that modern
    mixed-use projects often employ three-party relationships
    involving a government agency, a private developer, and a
    construction contractor. No doubt that is true. And the U.S.
    Department of Labor may ask Congress to update the statute
    to cover this new situation. See U.S. CONST. art. II, § 3, cl. 2
    (Recommendations Clause). When a new situation arises
    outside the scope of an old statute, the proper approach under
    our system of separation of powers is for Congress to amend
    the statute, not for the Executive Branch and the courts to
    rewrite the statute beyond what the statute’s terms can
    reasonably bear. As judges, we are not authorized to rewrite
    statutory text simply because we might think it should be
    updated. The Davis-Bacon Act applies only when D.C. is a
    party to the construction contracts. Here, D.C. was not a
    party to the construction contracts.
    Our reading of the text of the statute finds additional
    support when we examine the statute’s structure and purpose.
    The Davis-Bacon Act serves broadly as “a minimum wage
    law designed for the benefit of construction workers.” United
    States v. Binghamton Construction Co., 
    347 U.S. 171
    , 178
    (1954). But the Act was not designed to directly regulate
    private construction contracts between private developers and
    private construction companies. It was designed to regulate
    construction contracts where the Federal Government or D.C.
    But in those cases, unlike here, the Government was the lessee not
    the lessor, and the leases required construction for which the
    Government would pay de facto through its rental payments. So
    there, unlike here, the Government did in effect pay the costs of
    construction, albeit indirectly, through the rental payments it made
    as lessee. In any event, even if those scattered agency decisions
    were squarely on point, they would not bind this Court. Because
    those agency decisions are not on point, however, we need not
    decide whether we agree with them.
    14
    was a party. To suddenly extend Davis-Bacon’s coverage to a
    large swath of private construction projects would end-run the
    statute’s careful line-drawing and thwart the structure and
    targeted purpose of the statute.
    It bears emphasis, moreover, that the U.S. Department of
    Labor’s interpretation would generate significant anomalies.
    First, if we were to rule that the Davis-Bacon Act applied
    to CityCenterDC, D.C. would suddenly owe approximately
    $20 million in backpay. See 
    29 C.F.R. § 1.6
    (f) (requiring
    D.C. to pay any increase in wages mandated by the Davis-
    Bacon Act). To put it in perspective, that sum equals the
    combined annual salaries of more than 200 D.C. teachers or
    police officers. But it would be odd to require D.C. – rather
    than the Developers – to pay that amount now. After all, D.C.
    did not pay (and therefore did not allegedly underpay) the
    salaries to begin with. D.C. did not build CityCenterDC or
    pay for the construction of it.
    Second, if we were to rule that the Davis-Bacon Act
    applied to the construction of CityCenterDC, the Act would
    also apply to any significant future improvements within
    CityCenterDC.      After all, D.C.’s agreements with the
    Developers require the Developers not only to construct the
    buildings but also to undertake any repairs or alterations to
    ensure that the buildings meet first-class standards. Imagine
    an overhaul of the gym at one of the luxury rental apartments
    in CityCenterDC. Or a new conference room built at the
    Covington & Burling law firm in CityCenterDC. Under the
    Department’s theory, those construction projects would be
    covered by the Davis-Bacon Act. But that is quite absurd, of
    course. No doubt recognizing as much, even the U.S.
    Department of Labor has disclaimed the notion that those
    kinds of improvements would be encompassed by the Act.
    15
    But what the Department has not done – and cannot do – is
    identify a logical principle that applies the Davis-Bacon Act
    to the construction of CityCenterDC but not to the
    construction of those hypothetical improvements to
    CityCenterDC.
    In short, after examining the text, structure, and purpose
    of the Davis-Bacon Act, as well as the consequences of
    applying the Act to the construction of CityCenterDC, we
    conclude that the Act does not apply because D.C. was not a
    party to the contracts for construction of CityCenterDC. 4
    B
    Even if D.C. were a party to the contracts for
    construction of CityCenterDC, the Davis-Bacon Act still
    would not apply because CityCenterDC is not a public work.
    The Davis-Bacon Act applies to “public buildings” and
    “public works.” Those terms have some overlap. Even
    though CityCenterDC is a building (actually, a group of
    buildings), the U.S. Department of Labor does not contend
    that CityCenterDC is a public building. That is not surprising.
    CityCenterDC is a private building. But the Department
    nonetheless claims that this private building is a “public
    work.” We disagree. As the District Court observed,
    CityCenterDC is quite obviously “an enclave of private
    4
    What about a sham arrangement that a federal agency or D.C.
    enters into with an intermediary just to avoid contracting directly
    with a construction contractor, all for the purpose of avoiding the
    Davis-Bacon Act? The U.S. Department of Labor does not claim
    that D.C. engaged in such a sham here. We therefore need not
    consider whether such a sham exception exists, and if so, what its
    contours might be.
    16
    facilities,” not a public work. District of Columbia v.
    Department of Labor, 
    34 F. Supp. 3d 172
    , 175 (D.D.C. 2014).
    In 1935, when Congress amended the Davis-Bacon Act
    to cover “public works” as well as “public buildings,” the
    phrase “public works” carried a meaning similar to its current
    meaning. Think, for example, of public roads, dams, parks,
    railroads, canals, and docks. The 1933 edition of Black’s Law
    Dictionary defined “public works” as follows: “Works,
    whether of construction or adaptation, undertaken and carried
    out by the national, state, or municipal authorities, and
    designed to subserve some purpose of public necessity, use,
    or convenience; such as public buildings, roads, aqueducts,
    parks, etc.” (3d ed. 1933). The Black’s definition cited a
    series of cases involving public works that ranged from a
    government-owned dam to a public road financed with
    municipal bonds.
    Dictionaries from that era supplied similar definitions.
    One defined public works to encompass “[a]ll fixed works
    constructed or built for public use or enjoyment, as railroads,
    docks, canals, etc., or constructed with public funds and
    owned by the public; often, specif., such works as constitute
    public improvements, as parks, museums, etc., as
    distinguished from those involved in the ordinary
    administration of the affairs of a community, as grading of
    roads, lighting of streets, etc.” Webster’s New International
    Dictionary (2d ed. 1934). The New Standard Dictionary of
    the English Language defined public works as “permanent
    works or improvements made for public use or benefit, as
    roads, canals, or harbors, especially such as are made by or at
    the expense of the local or central government.” (1937). And
    The American College Dictionary defined the term as
    “constructions as roads, dams, post offices, etc. out of
    government funds for public use.” (1947).
    17
    The meaning has not changed over time. The current
    edition of Black’s Law Dictionary defines “public works” as
    “[s]tructures (such as roads or dams) built by the government
    for public use and paid for by public funds.” (10th ed. 2014
    online). The American Heritage Dictionary defines the term
    as “[c]onstruction projects, such as highways or dams,
    financed by public funds and constructed by a government for
    the benefit or use of the general public.” (5th ed. 2015
    online).
    In the 1933 National Industrial Recovery Act, enacted
    two years before Congress added “public works” to the
    Davis-Bacon Act, Congress defined “public works” as “any
    projects of the character heretofore constructed or carried on
    either directly by public authority or with public aid to serve
    the interests of the general public.” Pub. L. No. 73-67, § 202,
    
    48 Stat. 195
    , 201 (1933). The Supreme Court later adopted
    that definition when interpreting the statutorily undefined
    phrase “public work” in the 1935 Miller Act, a statute that
    required contractors on certain public works projects to post
    bonds securing their payment obligations. See United States
    v. Irwin, 
    316 U.S. 23
    , 28 (1942).
    Exercising its authority to enforce the Davis-Bacon Act,
    the U.S. Department of Labor has long maintained a
    regulation that defines “public work” in largely the same way
    that the National Industrial Recovery Act and the Irwin Court
    did: “The term public building or public work includes
    building or work, the construction, prosecution, completion,
    or repair of which, as defined above, is carried on directly by
    authority of or with funds of a Federal agency to serve the
    interest of the general public regardless of whether title
    thereof is in a Federal agency.” 
    29 C.F.R. § 5.2
    (k).
    18
    Although all of these various definitions do not align
    perfectly, it is clear enough that a project must possess at least
    one (if not both) of the following two characteristics 5 in order
    to qualify as a public work under the Davis-Bacon Act: (i)
    public funding for the construction or (ii) government
    ownership or operation of the completed facility. 6
    5
    At least one of the two characteristics is necessary for a
    project to qualify as a public work; we need not and do not decide
    whether either characteristic alone is sufficient for a project to
    qualify as a public work.
    6
    For a project to qualify as a public work, the U.S.
    Department of Labor regulation requires the first of these two
    characteristics – public funding for the construction – but does not
    appear to require the second – government ownership or operation
    of the completed facility. In this case, the U.S. Department of
    Labor argues to this Court that its regulation actually requires
    neither of those characteristics. In particular, the Department says
    that the phrase “construction . . . carried on directly by authority of
    or with funds of a Federal agency” includes situations where D.C.
    neither builds the project nor expends funds for construction, but
    merely leases land to a developer who then pays for the
    construction by contracting with a general contractor. We disagree.
    The Department has not cited any cases where it has previously
    interpreted this regulatory language to stretch to situations in which
    there is no public funding for the construction. So, too, the
    Department has cited no cases in which the similar language in the
    National Industrial Recovery Act or the Miller Act has been applied
    to a project with no public funding for the construction. In light of
    the history, context, and terms of the regulation, the Department’s
    reading of its regulation is not reasonable. It would vastly expand
    the coverage of the regulation – and indeed would stretch the
    regulation beyond what the statute can reasonably bear. Put simply,
    the interpretation that the Department offers to this Court is
    inconsistent with the regulation, see Auer v. Robbins, 
    519 U.S. 452
    (1997), and if adopted would make the regulation inconsistent with
    the statute, see Chevron, 
    467 U.S. 837
     (1984).
    19
    Therefore, to determine whether CityCenterDC is a
    public work, we must assess whether CityCenterDC possesses
    at least one of the following two characteristics: (i) public
    funding for the construction of CityCenterDC or (ii)
    government ownership or operation of CityCenterDC.
    CityCenterDC possesses neither characteristic.
    First, D.C. did not expend funds for the construction of
    CityCenterDC. Quite the opposite. The Developers make
    substantial rental payments to D.C. Those rental payments to
    D.C. pad D.C.’s coffers, not drain them. By contrast to this
    arrangement, every case cited by the Department concerning
    the scope of the Davis-Bacon Act involved the expenditure of
    public funds for construction.        See, e.g., Binghamton
    Construction Co., 
    347 U.S. at 173
    ; Tom Mistick & Sons, Inc.
    v. Reich, 
    54 F.3d 900
    , 902 (D.C. Cir. 1995); see also Irwin,
    
    316 U.S. at 27
     (interpreting “public work” in the Miller Act to
    cover publicly funded university library). The Department
    cites no cases – zero – where no public funds were expended
    for construction and the project was nonetheless declared a
    public work for purposes of the Davis-Bacon Act. This will
    not be the first.
    Second, D.C. does not own or operate CityCenterDC.
    CityCenterDC is privately owned and privately operated. To
    use the District Court’s apt description, CityCenterDC is “an
    In this case, moreover, it is doubtful that this regulation even
    applies to D.C.’s contracts for construction in the first place, as the
    District Court noted. District of Columbia v. Department of Labor,
    34 F. Supp. 3d at 191. The terms of the regulation apply only to
    federal agency contracts for construction, not to D.C. contracts for
    construction. But we need not rest on that point here, because, in
    any event, CityCenterDC is not a public work under the statute or
    regulation.
    20
    enclave of private facilities.” District of Columbia v.
    Department of Labor, 34 F. Supp. 3d at 175.
    In short, CityCenterDC possesses neither characteristic of
    a public work.
    In arguing that CityCenterDC nonetheless should be
    considered a public work, the U.S. Department of Labor
    emphasizes that D.C. helped plan CityCenterDC and that the
    project will produce benefits for the public. But that is true of
    many private projects. Through its zoning, taxing, and
    regulatory powers, D.C. and other local governments are
    often intimately involved in attracting, planning, approving,
    and regulating private development, often down to the nitty-
    gritty details. And private development often benefits the
    public by creating jobs, generating tax revenues, and
    providing places for work, housing, recreation, and
    entertainment. That’s why local governments, including
    D.C., get deeply involved in zoning and urban planning in the
    first place. But those realities do not transform the Davis-
    Bacon Act into an all-encompassing prevailing wage law for
    private development projects in D.C.
    Make no mistake: Under the Department’s reading,
    many future D.C. construction projects that are privately
    funded, privately owned, and privately operated would be
    covered by the Davis-Bacon Act, at least so long as the
    Federal Government or D.C. has some hand in leasing the
    property or even just in planning or approving the use of the
    property. We are unwilling to green-light such a massive,
    atextual, and ahistorical expansion of the Davis-Bacon Act.
    The concept of a public work may well be elastic. But it
    cannot reasonably be stretched to cover a Louis Vuitton.
    CityCenterDC is not a public work.
    21
    ***
    The U.S. Department of Labor has advanced a novel
    reading of the Davis-Bacon Act that would significantly
    enlarge the number and kinds of construction projects covered
    by the Act. Expanding the coverage of the Davis-Bacon Act
    in this way may or may not be a wise policy decision. But
    that choice belongs to the political branches, which may enact
    new legislation if they so choose. Our job is to construe the
    statute as written and long understood. The Department’s
    interpretation of the Davis-Bacon Act contravenes the statute.
    To use the administrative law vernacular, the Department’s
    interpretation fails Chevron step one because it is foreclosed
    by the statute. In any event, the Department’s interpretation
    would likewise fail Chevron step two because it is
    unreasonable in light of the statute’s text, structure, and
    purpose. We affirm the judgment of the District Court.
    So ordered.