Millennium Pipeline Company v. Basil Seggos ( 2017 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued March 3, 2017                   Decided June 23, 2017
    No. 16-1415
    MILLENNIUM PIPELINE COMPANY, L.L.C.,
    PETITIONER
    v.
    BASIL SEGGOS AND NEW YORK STATE DEPARTMENT OF
    ENVIRONMENTAL CONSERVATION,
    RESPONDENTS
    CPV VALLEY, LLC,
    INTERVENOR
    On Petition for Review from the
    New York State Department of Environmental Conservation
    Catherine E. Stetson argued the cause for petitioner. With
    her on the briefs was Sean Marotta.
    Elizabeth W. Whittle was on the brief for intervenor CPV
    Valley, LLC in support of petitioner.
    Brian M. Lusignan, Assistant Attorney General, Office of
    the Attorney General for the State of New York, argued the
    cause for respondents. With him on the brief were Eric T.
    Schneidermann, Attorney General, Barbara D. Underwood,
    2
    Solicitor General, Frederick A. Brodie, Assistant Solicitor
    General, and Lisa M. Burianek, Deputy Bureau Chief.
    Before: TATEL, SRINIVASAN, and WILKINS, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge SRINIVASAN.
    SRINIVASAN, Circuit Judge:          Millennium Pipeline
    Company, L.L.C., would like to extend its existing natural gas
    pipeline in Orange County, New York. Before it can break
    ground, however, it must gain the approval of the Federal
    Energy Regulatory Commission (FERC). Millennium must
    also comply with environmental regulations like the Clean
    Water Act, which requires it to show that its pipeline will meet
    all applicable water-quality requirements.           33 U.S.C.
    § 1341(a)(1).
    As part of that permitting process, Millennium submitted
    an application for a water-quality certificate to the New York
    State Department of Environmental Conservation. More than
    a year has passed, but the Department has taken no formal
    action on Millennium’s application. Millennium now asks us
    to compel the Department to act on the application.
    We dismiss Millennium’s petition for review. Even if the
    Department has unlawfully delayed acting on Millennium’s
    application, its inaction would operate as a waiver, enabling
    Millennium to bypass the Department and proceed to obtain
    approval from FERC. The Department’s delay, then, causes
    Millennium no cognizable injury. Millennium therefore lacks
    standing to proceed with its petition.
    3
    I.
    A.
    For any company desiring to construct a natural gas
    pipeline, all roads lead to FERC. The Natural Gas Act of 1938
    vests the agency with “exclusive jurisdiction” over the
    interstate transportation of natural gas. Schneidewind v. ANR
    Pipeline Co., 
    485 U.S. 293
    , 300-01 (1988). No company or
    person may construct a natural gas pipeline without first
    obtaining “a certificate of public convenience and necessity”
    from the agency. 15 U.S.C. § 717f(c).
    Before FERC can issue a certificate of public convenience,
    the agency must ensure that the proposed pipeline complies
    with all applicable federal, state, and local regulations. See 15
    U.S.C. § 717b(d); 18 C.F.R. § 4.38. The Clean Water Act, the
    statute at issue in this case, is one such regulatory regime. See
    33 U.S.C. § 1341(a)(1); 15 U.S.C. § 717b(d)(3). Because
    Millennium’s proposed pipeline would traverse several
    streams in southern New York, the Clean Water Act requires
    the State to certify that any discharge from the pipeline will
    comply with the Act’s water-quality requirements. 33 U.S.C.
    § 1341(a)(1). FERC cannot sign off on the construction until
    New York either grants a water-quality certificate or waives the
    Act’s requirements. See 
    id. To prevent
    state agencies from indefinitely delaying
    issuance of a federal permit, Congress gave States only one
    year to act on a “request for certification” under the Clean
    Water Act. Alcoa Power Generating Inc. v. FERC, 
    643 F.3d 963
    , 972 (D.C. Cir. 2011) (quoting 33 U.S.C. § 1341(a)(1)).
    That deadline is established by section 401 of the Act, which
    requires a State to grant or deny the certificate “within a
    reasonable period of time (which shall not exceed one year)
    4
    after receipt of [a] request.” 
    Id. If the
    State fails to act within
    that period, the Act’s “certification requirements” are deemed
    “waived,” such that the pipeline no longer needs a water-
    quality certificate to begin construction. 
    Id. B. On
    November 9, 2016, FERC issued a provisional
    certificate of public convenience for Millennium’s proposed
    project, a 7.8-mile extension of its existing natural gas pipeline.
    The Commission, however, conditioned its approval on proof
    of Millennium’s receipt of “all authorizations required under
    federal law,” including the Clean Water Act. Millennium
    Pipeline Co., 157 FERC ¶ 61,096, 
    2016 WL 6662548
    , at *35
    (2016). To that end, Millennium must present FERC with
    documentation of the applicable permits or evidence of waiver
    thereof. 
    Id. Millennium had
    previously applied for a water-quality
    certificate from the New York State Department of
    Environmental Conservation.         The Department received
    Millennium’s request on November 23, 2015, and responded
    by sending Millennium a notice of incomplete application.
    Over the next year, the Department sent Millennium several
    requests for supplemental information. Millennium has
    complied with the Department’s requests each time. In
    November 2016, the Department wrote a letter indicating that
    Millennium had “fully responded” to its requests, but it would
    “continue its review of the Application, as supplemented, to
    determine if a valid request for a [water-quality certificate] has
    been submitted.” N.Y. State Dep’t of Envtl. Conservation,
    Letter on Application for Section 401 Water Quality
    Certification, Freshwater Wetlands and Protection of Waters
    Permit (Nov. 18, 2016). The Department stated that it had “at
    5
    a minimum, until August 30, 2017 to either approve or deny
    the Application.” 
    Id. Frustrated by
    the agency’s delay, Millennium brought a
    petition for review in this Court under section 19(d)(2) of the
    Natural Gas Act. That provision gives us “original and
    exclusive jurisdiction” to review “an alleged failure to act by a
    . . . State administrative agency acting pursuant to Federal law
    to issue, condition, or deny any permit required under Federal
    law.” 15 U.S.C. § 717r(d)(2). If we find that an agency has
    delayed unlawfully, the Act requires us to remand the
    proceeding to the agency and “set a reasonable schedule and
    deadline for the agency to act on remand.” 
    Id. § 717r(d)(3).
    Millennium argues that the Department failed to act within
    the Clean Water Act’s one-year statutory window, and
    therefore asks us to compel the Department either to grant its
    application or to take action within a specified schedule. The
    Department counters that it need only act within one year of
    receiving a complete or valid application, and it alleges
    Millennium has repeatedly failed to meet that requirement.
    II.
    Before reaching the merits of Millennium’s claim, we first
    examine Millennium’s standing to sue. Article III of the
    Constitution limits our jurisdiction to “Cases” and
    “Controversies.” U.S. Const. art. III, § 2, cl. 1. To satisfy the
    case-and-controversy requirement, a petitioner must allege (i)
    that it suffered an injury in fact; (ii) that a causal connection
    exists between the injury and challenged conduct; and (iii) that
    it is likely, as opposed to speculative, that the injury will be
    redressed by a favorable decision. Lujan v. Defs. of Wildlife,
    
    504 U.S. 555
    , 560-61 (1992).
    6
    Millennium fails at the first prong. It asks us to hold that
    the Department violated the Clean Water Act’s statutory
    deadline. Even if that were so, Millennium would suffer no
    cognizable injury from the violation. We therefore dismiss
    Millennium’s petition for want of standing.
    A.
    All agree that the Clean Water Act gave the Department a
    “reasonable period of time (which shall not exceed one year)”
    to act on Millennium’s application. 33 U.S.C. § 1341(a)(1).
    Millennium thus does not purport to have suffered any injury
    from the Department’s inaction within that period. Millennium
    instead challenges the Department’s continued, allegedly
    unlawful delay, which it claims will prevent it from
    constructing its pipeline.
    Even if the Department has unlawfully delayed, however,
    it can no longer prevent the construction of Millennium’s
    pipeline. Millennium ultimately needs one permit to begin
    construction on its pipeline:         the certificate of public
    convenience from FERC. Typically, the Clean Water Act
    poses a hurdle to obtaining that certificate. The Act forbids any
    federal agency from granting a license or permit until the
    “certification required by [the Act] has been obtained or has
    been waived.” 33 U.S.C. § 1341(a)(1) (emphasis added). That
    provision also makes clear that waiver occurs after one year of
    agency inaction. 
    Id. Once the
    Clean Water Act’s requirements have been
    waived, the Act falls out of the equation. 
    Id. As a
    result, if the
    Department has delayed for more than a year—as Millennium
    alleges—the delay cannot injure Millennium. Instead, the
    delay triggers the Act’s waiver provision, and Millennium then
    7
    can present evidence of waiver directly to FERC to obtain the
    agency’s go-ahead to begin construction.
    We have previously dismissed a petition for review for
    lack of standing when faced with highly similar allegations of
    state inaction. See Weaver’s Cove Energy, LLC v. R.I. Dep’t
    of Envtl. Mgmt., 
    524 F.3d 1330
    , 1332 (D.C. Cir. 2008). That
    case, like this one, involved a petition for review under section
    19(d)(2) of the Natural Gas Act. The petitioner, a natural gas
    company, claimed that two state agencies had failed to process
    its applications within the Clean Water Act’s one-year
    deadline. 
    Id. Although the
    state agencies had acted by the time
    the petitioner sought judicial review (one had provisionally
    denied the certificate, while another had granted it), the
    petitioner asked for a declaration that the agencies had waived
    any right to deny its applications. 
    Id. The petitioner
    in Weaver’s Cove, as here, asserted its
    standing was “self-evident” because it was the object of
    delayed agency action. See 
    id. at 1333.
    But we held that
    “[e]ven a final adverse decision would not support” the
    petitioner’s standing. 
    Id. Instead, the
    petitioner’s theory
    ultimately was that “it benefited from the agencies’ inaction”:
    by delaying, the agencies had forfeited their opportunity to
    deny the water-quality certificate. 
    Id. If the
    petitioner was
    correct, we explained, the agencies could not block the
    pipeline’s construction even if they went on to deny the permit
    outright, because any decision “would be too late in coming
    and therefore null and void.” 
    Id. The same
    is true here. If the Clean Water Act’s
    requirements are waived, there is nothing left for the
    Department—and therefore for this Court—to do. Under the
    Natural Gas Act, if a reviewing court finds that an agency has
    unlawfully delayed, the court “shall remand the proceeding to
    8
    the agency to take appropriate action consistent with the order
    of the Court” and “shall set a reasonable schedule and deadline
    for the agency to act on remand.” 15 U.S.C. § 717r(d)(3).
    Millennium contends that we should require the Department to
    grant its application, or, at minimum, should set a deadline for
    the Department’s decision. But to what effect? If we were to
    determine the Department exceeded the Clean Water Act’s
    deadline, we necessarily would conclude the Clean Water
    Act’s requirements have been waived. At that point, the
    Department’s decision to grant or deny would have no legal
    significance.
    So what can Millennium do in the face of the Department’s
    continued inaction? Millennium can go directly to FERC and
    present evidence of the Department’s waiver. To be sure,
    FERC could ultimately decline to find waiver. But in that
    event, FERC—not the Department—would be blocking the
    construction.    See Weaver’s 
    Cove, 524 F.3d at 1333
    .
    Millennium could immediately appeal any adverse FERC
    decision on the waiver question to this Court under section
    19(b) of the Natural Gas Act, which affords judicial review to
    parties aggrieved by FERC’s orders. See 
    Alcoa, 643 F.3d at 968
    ; 15 U.S.C. § 717r(b). And insofar as Millennium has
    concerns that FERC might itself delay action, the present
    petition under section 19(d)(2) could not support our review in
    any event: that provision targets state agencies, and thus can
    provide no basis to force FERC’s hand.
    Millennium suggests that the Department might stand as
    an independent barrier to construction even if FERC issues a
    final certificate of public convenience. Millennium cites a
    letter in which the Department “reminds” the company that,
    “regardless of any action by FERC, . . . no construction
    activities may commence” unless the Department issues a
    water-quality certificate. See N.Y. State Dep’t of Envtl.
    9
    Conservation, Letter on Application for Section 401 Water
    Quality Certification, Freshwater Wetlands and Protection of
    Waters Permit (Nov. 18, 2016). That letter, however, does not
    purport to say that the Department would retain independent
    authority to stop construction even if FERC were to issue a
    certificate of public convenience.       As the Department
    acknowledged at oral argument, if FERC issues a certificate of
    public convenience, Millennium would have all the authority it
    needs to begin construction. See Oral Arg. Tr. 19:10-18; see
    also 15 U.S.C. § 717b(e). And if the Department were to
    disagree with FERC’s decision, the Department’s recourse
    would be to seek review in this Court pursuant to section 19(b).
    See 15 U.S.C. § 717r(b). Otherwise, the Department could no
    longer block Millennium’s construction.
    B.
    In 2005, Congress amended section 19(d) of the Natural
    Gas Act to allow this Court to compel action from foot-
    dragging agencies. See Energy Policy Act of 2005, Pub. L.
    109-58, 119 Stat. 594, 690 (2005). Millennium, joined by
    intervenor CPV Valley, argues that our interpretation would
    render Congress’s amendments toothless. We disagree. As
    amended, section 19(d)’s judicial review provisions have full
    force when, unlike with the Clean Water Act, there is no built-
    in remedy for state inaction already in place.
    The Clean Water Act’s certification requirements, as
    explained, automatically expire after one year of agency delay.
    33 U.S.C. § 1341(a)(1). Not all federal and state regulations
    include that type of waiver provision, however. In those
    circumstances, Congress recognized that state agencies could
    effectively block the construction of natural gas pipelines by
    indefinitely delaying action on permit applications. Congress
    amended the Natural Gas Act to ensure that “sheer inactivity
    10
    by the State” could not frustrate “the Federal application”
    process. See H.R. Rep. 91-940, at 55 (1970) (Conf. Rep.), as
    reprinted in 1970 U.S.C.C.A.N. 2712, 2741.
    Our decision today has no effect on situations in which a
    State’s “sheer inactivity” could actually frustrate the federal
    permitting process. Consider our decision in Dominion
    Transmission, Inc. v. Summers, 
    723 F.3d 238
    , 243 (D.C. Cir.
    2013). There, we reviewed a petition brought under section
    19(d)(2) for a state agency’s alleged failure to act on a Clean
    Air Act permit. 
    Id. at 242.
    Less than a month after receiving
    the request, the state agency informed the applicant “it would
    not be able to process the application.” 
    Id. There was
    no
    argument in Dominion Transmission that the state agency’s
    inaction operated as a waiver under the Clean Air Act, as the
    Act’s 18-month deadline for agency action had yet to run. See
    42 U.S.C. § 7661b(c). We held that the agency had failed to
    justify its refusal to act on the application, and, pursuant to
    section 19(d)(3), we remanded to the agency with instructions
    to complete the permitting process within a reasonable
    timeframe. 
    Id. at 245.
    Likewise, a state agency’s failure to comply with
    applicable FERC deadlines could trigger judicial review under
    section 19(d)(2). In its 2005 amendments to the Natural Gas
    Act, Congress authorized FERC to set a schedule for all federal
    permits. 119 Stat. at 689. Pursuant to that authority, FERC
    generally requires States to act within 90 days of the
    Commission’s issuance of its own environmental report
    “unless a schedule is otherwise established by Federal law.” 18
    C.F.R. § 157.22. The Natural Gas Act requires state agencies
    to “comply with the deadlines established by the Commission,”
    15 U.S.C. § 717n(b)(2), and if a state agency exceeds FERC’s
    deadline, the applicant could pursue remedies under section
    19(d), 
    id. § 717n(c)(2).
    Because FERC’s schedules do not
    11
    include a waiver provision, we could remand to any delaying
    agency with instructions to act on the application. See 
    id. § 717r(d)(3).
    Along those lines, Millennium initially suggested in this
    case that the Department, in addition to exceeding the Clean
    Water Act’s statutory deadline, also failed to comply with
    FERC’s schedule (which required state agencies to act by
    August 7, 2016). Millennium did not reiterate that argument in
    its reply brief, however. And at oral argument, Millennium
    indicated that the Department’s failure to meet FERC’s
    deadline, rather than presenting a freestanding basis for relief,
    simply bore on whether the agency had acted within a
    “reasonable time” under the Clean Water Act’s waiver
    provision. Oral Arg. Tr. 13:12-16. To the extent Millennium’s
    argument folds into its Clean Water Act claim in that fashion,
    Millennium lacks standing for the reasons discussed above.
    And even if Millennium sought to make a separate argument
    about FERC’s schedule, it would lose on the merits. FERC’s
    regulations specify that its deadlines under the Natural Gas Act
    apply “unless a schedule is otherwise established by Federal
    law.” 18 C.F.R. § 157.22 (emphasis added). The Clean Water
    Act, a federal law, establishes just such a statutory schedule. In
    fact, FERC anticipated that agencies acting pursuant to the
    Clean Water Act would not be bound by its deadlines. See
    Regulations Implementing the Energy Policy Act of 2005, 71
    Fed. Reg. 62,912, 62,915 n.18 (Oct. 27, 2006). The Clean
    Water Act thus provides the only applicable deadline for our
    purposes.
    12
    *   *   *    *   *
    For the foregoing reasons, the petition for review is
    dismissed.
    So ordered.
    

Document Info

Docket Number: 16-1415

Judges: Tatel, Srinivasan, Wilkins

Filed Date: 6/23/2017

Precedential Status: Precedential

Modified Date: 11/5/2024