Hensel Phelps Construction Co. v. Cooper Carry Inc. ( 2017 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued April 21, 2017                 Decided June 30, 2017
    No. 16-7128
    HENSEL PHELPS CONSTRUCTION CO.,
    APPELLANT
    v.
    COOPER CARRY INC.,
    APPELLEE
    Appeal from the United States District Court
    for the District of Columbia
    (No. 1:15-cv-01961)
    Catherine E. Stetson argued the cause for appellant.
    With her on the briefs was Eugene A. Sokoloff.
    Paul J. Kiernan and Stephen B. Shapiro were on the brief
    for amicus curiae The Associated General Contractors of
    America and Associated General Contractors of Metropolitan
    Washington D.C. in support of appellant.
    Jonathan C. Shoemaker argued the cause for appellee.
    With him on the brief was James F. Lee Jr.
    Before: BROWN and PILLARD, Circuit Judges, and
    SILBERMAN, Senior Circuit Judge.
    2
    Opinion for the Court filed by Circuit Judge BROWN.
    BROWN, Circuit Judge: This controversy concerns
    breach-of-contract and indemnification claims arising out of
    alleged defects in the design of the Marriott Marquis Hotel
    adjacent to the Walter E. Washington Convention Center
    (“the Project”).      Hensel Phelps Construction Company
    (“Hensel Phelps”) claims Cooper Carry “materially breached”
    its contractual obligations in eighteen respects, including by
    failing to meet the applicable standard of care and by failing
    to design the Project in accordance with applicable fire codes.
    Compl. ¶ 24, J.A. 10–11. Additionally, Hensel Phelps argues
    Cooper Cary is contractually obligated to indemnify Hensel
    Phelps for the losses associated with rectifying the alleged
    design errors. The district court granted summary judgment
    to Cooper Carry on both counts. We hold that the statute of
    limitations has run on Hensel Phelps’s breach-of-contract
    claim, and the terms of the indemnification clause do not
    cover first-party claims. We accordingly affirm.
    I.
    A.
    Marriott International entered into an initial Agreement
    with Cooper Carry on March 5, 2008, under which Cooper
    Carry agreed to design and monitor the construction of the
    Project for a lump sum of $14,335,602. The Agreement
    divided Project completion into five phases: conceptual
    design, schematic design, design development, construction
    document, and construction contract administration. As the
    Project progressed, Cooper Carry would bill Marriott on a
    monthly basis, and final payment was due to Cooper Carry
    upon, among other things, “the full completion of the services
    hereunder.”    Agreement Art. 4.05.6, J.A. 25.            The
    3
    construction contract administration phase obligated Cooper
    Carry to perform tasks such as “shop drawing and
    construction materials sample review and approval, answering
    requests for information from contractor(s), preparing
    construction contract change order and field orders,
    confirming the contractors’ percentage of completion of work
    to substantiate payment requests, reviewing and approving
    construction mock-ups, and conducting site observations and
    preparing reports.” J.A. 39. It also required Cooper Carry to
    provide construction administration services as set forth in the
    as-of-yet-unwritten construction contract for the Project.
    Once the construction contract between Marriott and the
    construction entity was finalized, it would be sent to Cooper
    Carry for approval and incorporated by reference into the
    initial Agreement.
    Cooper Carry made numerous promises in the initial
    Agreement, two of which are particularly relevant to this
    litigation. First, Cooper Carry agreed to act in accordance
    with “the professional standards of skill, care and diligence
    ordinarily expected of leading, internationally recognized
    architectural firms on projects of comparable scope and
    complexity.” Agreement Art. 2.01, J.A. 17. Second, Cooper
    Carry represented it was knowledgeable of all applicable
    laws, “codes, ordinances, rules, regulations and other
    requirements      imposed     by [relevant]       governmental
    authorities,” “all . . . governmental approval requirements,”
    and “National Fire Protection Association (‘NFPA’)
    standards.” Agreement Art. 2.05.1, J.A. 19–20. With respect
    to fire safety specifically, Cooper Carry agreed to design the
    Project in conformity with “the BOCA National Building
    Codes, the NFPA National Fire Codes (especially NFPA 101,
    Life Safety Code) and the Marriott Fire Protection/Life Safety
    design.” J.A. 49. In addition to its service-related obligations
    and representations, Cooper Carry acknowledged “Marriott
    4
    may sustain financial loss for which [Cooper Carry] may be
    liable if the Project or any part thereof is delayed because
    [Cooper Carry] negligently fails to perform the Services in
    accordance with this Agreement, including, but not limited to,
    the Schedule.” Agreement Art. 3.01, J.A. 22. Cooper Carry
    also agreed to indemnify Marriott “[t]o the fullest extent
    permitted by law, . . . from and against any claim, judgment,
    lawsuit, damage, liability, and costs and expenses, including
    reasonable attorneys’ fees, as a result of, in connection with,
    or as a consequence of [Cooper Carry’s] performance of the
    Services under this Agreement . . . .” Agreement Art. 6.01,
    J.A. 27.
    The initial Agreement contained a dispute-resolution
    provision, which allowed “[a]ny party . . . from time to time”
    to “call a special meeting for the resolution of disputes that
    would have a material impact on the cost or progress of the
    Project.” Agreement Art. 7.09.1, J.A. 31 (emphasis added).
    If an informal dispute-resolution process failed, the parties
    agreed to attempt mediation, which would last no more than
    twenty working days unless the parties agreed otherwise. “If
    [a] dispute [was] settled through the mediation process, the
    decision [would] be implemented by written agreement
    signed by all the parties involved.” Agreement Art. 7.09.2,
    J.A. 31. The Agreement provided that “[a]ll claims and
    disputes not settled by mediation shall be resolved through
    litigation in [the] court having jurisdiction over same.”
    Agreement Art. 7.09.3, J.A. 32. Additionally, the Agreement
    provided that “[t]he presence of any claim or dispute, or legal
    proceeding arising hereunder shall not relieve [Cooper Carry]
    from its obligation to properly perform its Services as set
    forth herein, nor shall it relieve Marriott from making
    payments with respect to undisputed Services in accordance
    with the terms of this Agreement.” Agreement Art. 7.09.5,
    J.A. 32 (emphasis added).
    5
    B.
    As stated above, the initial Agreement, signed in 2008,
    contemplated that Marriott would enter into a second contract
    governing the Project’s construction. Approximately two-
    and-a-half years later, however, the Project was converted to
    the design-build model of delivery. Under this approach, the
    owner contracts with only one party—the design-builder—to
    both design and construct a project. 1 PHILIP L. BRUNER &
    PATRICK J. O’CONNOR, JR., ON CONSTRUCTION LAW § 2:17
    (Dec. 2016) [hereinafter BRUNER & O’CONNOR].                To
    accomplish this conversion, HQ Hotels—which had
    previously acquired development rights for the Project from
    Marriott—entered into a Design/Build Agreement with
    Hensel Phelps on October 26, 2010, under which Hensel
    Phelps agreed to complete the Project’s construction “no later
    than April 1, 2014” for a guaranteed maximum price of
    $354,517,391. Claim Narrative at 2, J.A. 230. Also on
    October 26, 2010, Marriott assigned its rights and obligations
    under the initial Agreement to Hensel Phelps, without making
    any changes to that document. Accordingly, “any and all
    duties, obligations, and standards of care that Cooper Carry
    owed to Marriott under the [initial Agreement] were assigned
    and transferred to Hensel Phelps.” Compl. ¶ 10, J.A. 7.
    Thereafter, the Project “progressed effectively on a design-
    build basis[,] with Cooper Carry having complete design
    coordination.” Claim Narrative at 2, J.A. 230. As of October
    26, Cooper Carry had completed the first three phases of the
    Project and was in the midst of completing the fourth. The
    Design/Build Agreement also included a list of already-
    completed design documents provided by Cooper Carry.
    Unfortunately, the new arrangement went sour rather
    quickly. On March 8, 2011, Cooper Carry met with the
    District of Columbia Department of Consumer and
    6
    Regulatory Affairs and was promptly informed that its
    designs did not comply with applicable fire codes. Hensel
    Phelps claims that remedying these errors cost it $4,402,380
    and required “significant” design alterations, “[s]ignificant
    changes in mechanical and electrical scopes,” and a ten-and-
    a-half-month delay in the Issued for Construction design
    issuance. See Claim Narrative at 11–14, J.A. 239–42. Over
    the next three years, Hensel Phelps contends it discovered
    approximately seventeen additional defects in Cooper Carry’s
    designs that, when combined with the fire safety issues,
    allegedly cost $8,493,556 to remediate.
    Hensel Phelps initiated dispute-resolution proceedings in
    January 2015, raising, inter alia, breach-of-contract,
    indemnification, and negligent misrepresentation claims.
    Regarding breach of contract, it asserted Cooper Cary “failed
    to meet the high standard stated in the [initial Agreement]
    and/or breached Cooper Carry’s obligations therein,” Claim
    Narrative at 2, J.A. 230 (emphasis added), including its
    “obligations,” “warranties,” and “representations” pertaining
    to “fire and life safety design,” id. at 8–9, 11, J.A. 236–37,
    239. See also Claim Narrative at 12, J.A. 240 (“This failure
    to address fire and life safety is an express breach of the fire
    and life safety obligations contained in the [initial Agreement]
    Scope of Work.”). In support of its allegations, Hensel Phelps
    submitted a detailed Claim Narrative describing the eighteen
    alleged breaches and their respective costs.
    Mediation failed in October 2015. Hensel Phelps filed a
    complaint in district court the following month, alleging
    breach-of-contract and indemnification claims. Cooper Carry
    moved to dismiss or, alternatively, for summary judgment,
    arguing the District of Columbia (“D.C.”) three-year statute of
    limitations for contract claims had already run. Additionally,
    it asserted the plain text of the initial Agreement’s
    7
    indemnification clause did not cover first-party claims.
    Cooper Carry attached Hensel Phelps’s Claim Narrative to its
    motion, and Hensel Phelps did not object.
    The district court granted summary judgment for Cooper
    Carry. Hensel Phelps Constr. Co. v. Cooper Carry, Inc., 
    210 F. Supp. 3d 192
    , 195 (D.D.C. 2016). It found the contract
    was first breached—and the statute of limitations therefore
    began to run—on October 26, 2010, when Hensel Phelps
    assumed Marriott’s rights under the initial Agreement and
    Cooper Carry delivered the defective design documents. 
    Id. at 197
     (“Once the time for compliant performance had passed
    and Hensel Phelps had accepted the initial design documents
    on which its claim for damages is based, the clock began to
    run against Hensel Phelps.”); see also 
    id. at 198
    . The court
    also found the text of the initial Agreement’s indemnification
    clause did not cover first-party claims, noting that, in
    accordance with the traditional purpose of such clauses, it
    “clearly anticipate[d] the problem of third-party litigation.”
    
    Id. at 199
    .
    Hensel Phelps now appeals, arguing—as it did below—
    that the contract was not breached until April 1, 2014, when
    the Project was substantially complete. It asks this Court
    either to reverse the district court’s judgment or to remand for
    further proceedings to interpret the allegedly ambiguous
    provisions of the initial Agreement.
    Hensel Phelps is organized under the laws of Delaware
    with its principal place of business in Colorado; Cooper Carry
    is a Georgia-based corporation with its principal place of
    business in Georgia.        The district court had diversity
    jurisdiction under 
    28 U.S.C. § 1332
    , and we have jurisdiction
    under 
    28 U.S.C. § 1291
    .
    8
    II.
    A.
    This Court reviews the district court’s grant of summary
    judgment de novo, “examin[ing] the record to determine
    whether any genuine issue of material fact pertinent to the
    ruling remains, and if not, whether the substantive law was
    correctly applied.” Caiola v. Carroll, 
    851 F.2d 395
    , 398
    (D.C. Cir. 1988).        All inferences are drawn in the
    nonmovant’s favor. Walker v. Johnson, 
    798 F.3d 1085
    , 1091
    (D.C. Cir. 2015). “[A]mbiguity in a contract raises a genuine
    issue of material fact, which is for the factfinder to resolve.”
    Debnam v. Crane Co., 
    976 A.2d 193
    , 198 (D.C. 2009)
    (quoting Rastall v. CSX Transp., Inc., 
    697 A.2d 46
    , 51 (D.C.
    1997)).
    B.
    All parties agree D.C. law governs this case. See also
    Agreement Art. 7.10, J.A. 32. 
    D.C. Code § 45-401
    (a) directs
    courts to look to the common law where statutes are silent.
    D.C. imported the common law of Maryland as of 1801, and
    so D.C. courts have “customarily[] looked to post-1801
    decisions of the Court of Appeals of Maryland for assistance
    in interpreting the law.” Heard v. United States, 
    686 A.2d 1026
    , 1029 (D.C. 1996); see also Little v. United States, 
    709 A.2d 708
    , 711 (D.C. 1998).
    D.C. courts “adhere[] to an objective law of contracts.”
    Carlyle Inv. Mgmt. L.L.C. v. Ace Am. Ins. Co., 
    131 A.3d 886
    ,
    894–95 (D.C. 2016). This means “the written language
    embodying the terms of an agreement will govern the rights
    and liabilities of the parties regardless of the intent of the
    parties at the time they entered the contract, unless the written
    language is not susceptible of a clear and definite meaning.”
    9
    
    Id.
     “The writing must be interpreted as a whole, giving a
    reasonable, lawful, and effective meaning to all its terms, and
    ascertaining the meaning in light of all the circumstances
    surrounding the parties at the time the contract was made.”
    Id. at 895. “In determining whether a contract is ambiguous,
    [courts] examine the document on its face, giving the
    language used its plain meaning,” Debnam, 
    976 A.2d at 197
    ,
    “unless, in context, it is evident that the terms used have a
    technical or specialized meaning,” Carlyle, 131 A.3d at 895.
    In essence, courts “determine what a reasonable person in the
    position of the parties would have thought the disputed
    language meant.” Id. at 895. Furthermore, “a contract is not
    ambiguous merely because the parties do not agree over its
    meaning, and courts are enjoined not to create ambiguity
    where none exists.” Id.
    Under D.C. law, parties have three years “from the time
    the right to maintain the action accrues” to file a breach-of-
    contract claim. D.C. CODE § 12-301(7). “Accrue” is not
    defined, but “[a]ctions usually accrue when they come into
    existence.” Felter v. Kempthorne, 
    473 F.3d 1255
    , 1259 (D.C.
    Cir. 2007). “An action for breach of contract generally
    accrues at the time of the breach.” Wright v. Howard Univ.,
    
    60 A.3d 749
    , 751 (D.C. 2013); Murray v. Wells Fargo Home
    Mortg., 
    953 A.2d 308
    , 319–20 (D.C. 2008).
    III.
    A.
    Hensel Phelps and Cooper Carry disagree about what
    “first breach” rule this Court should apply to their contract.
    Hensel Phelps argues the Project is governed by a unitary
    construction contract, under which courts typically interpret
    first breach as occurring upon “substantial completion” of the
    Project. See 3 BRUNER & O’CONNOR § 8:23 (defining
    10
    “substantial completion” as “that point in the construction
    where the work is sufficiently complete that the owner may
    occupy or utilize the work for the use for which it was
    intended”). Because substantial completion did not occur
    until April 2014, Hensel Phelps argues its claim is not time-
    barred. By contrast, relying primarily on Comptroller of
    Virginia ex rel. Virginia Military Institute v. King, 
    232 S.E.2d 895
    , 900 (Va. 1977), and Hilliard & Bartko Joint Venture v.
    Fedco Systems, Inc., 
    522 A.2d 961
    , 967 (Md. 1987), Cooper
    Carry asserts we should view the initial Agreement as a
    design agreement, and the contract was thus first breached
    when Hensel Phelps accepted Cooper Carry’s defective
    designs.
    We find it unnecessary to wade into this debate, however.
    For, like most other rules of contract, legal rules that specify
    first breach are default ones, and parties are free to depart
    from them as they wish. Looking to the initial Agreement’s
    terms suffices to demonstrate that Hensel Phelps’s cause of
    action accrued prior to substantial completion.
    As a preliminary matter, we note the parties consented to
    have the initial Agreement interpreted according to its “plain
    meaning.” Agreement Art. 7.20, J.A. 35. We think the plain
    terms of the initial Agreement, read in context, make it clear
    that Hensel Phelps could have initiated dispute-resolution
    procedures for breach of contract in March 2011, after
    discovery of Cooper Carry’s failure to design the Project in
    accordance with applicable fire safety codes. The initial
    Agreement specified that “[a]ny party may from time to time
    call a special meeting for the resolution of disputes that would
    have a material impact on the cost or progress of the Project.”
    Agreement Art. 7.09.1, J.A. 31. No temporal conditions
    precedent needed to be satisfied before parties could
    commence dispute resolution; all that was required was a
    11
    material effect on either the Project’s cost or its progress.
    According to Hensel Phelps, remedying the fire safety errors
    cost almost four-and-a-half million dollars, required
    significant structural and design alterations, and resulted in a
    ten-and-a-half-month delay in the issuance of a necessary
    document. The cost and effects on the schedule suggest the
    fire safety issues met the criteria laid out in Article 7.09.1.
    We also read the initial Agreement to require parties to
    proceed to court if dispute resolution failed. Read in full,
    Article 7 of the initial Agreement set out a series of iterative,
    sequential steps a party needed to walk through in order to
    resolve a dispute, beginning with informal proceedings and
    culminating with a lawsuit filed in court. Removing the
    description of what procedures were to be used within each
    step of the process, the section provided as follows:
    Any party may from time to time call a special
    meeting for the resolution of disputes that would
    have a material impact on the cost or progress of the
    Project. . . . If the dispute has not been resolved
    within five (5) working days . . . , a mediator,
    mutually acceptable to the parties and experienced in
    design and construction matters shall be retained by
    the parties. . . . If the dispute is settled through the
    mediation process, the decision will be implemented
    by written agreement signed by all the parties
    involved. . . . All claims and disputes not settled by
    mediation shall be resolved through litigation in
    court having jurisdiction over same.
    Agreement Arts. 7.09.1–7.09.3, J.A. 31–32 (emphases added).
    The parties added no proviso to the “shall be resolved”
    language indicating such lawsuits could not commence until
    after substantial completion of the Project. Nor did they do so
    12
    in the section entitled “Causes of Action,” which merely
    stated that “[c]auses of action between the parties to this
    Agreement . . . shall be deemed to have accrued and the
    applicable statutes of limitations shall commence to run in
    accordance with the law applicable to this Agreement.”
    Agreement Art. 7.15, J.A. 34. And, in fact, the initial
    Agreement expressly contemplated the possibility of litigation
    before its completion. Article 7.09.5—contained within the
    same section as the dispute-resolution procedures—stated that
    “[t]he presence of any . . . legal proceeding arising hereunder
    shall not relieve [Cooper Carry] from its obligation to
    properly perform its Services as set forth herein, nor shall it
    relieve Marriott from making payments with respect to
    undisputed Services in accordance with the terms of this
    Agreement.” J.A. 32; see also Agreement Art. 5.03, J.A. 26
    (permitting Marriott to terminate Cooper Carry for cause
    “should [Cooper Carry] fail substantially to perform in
    accordance with the terms of this Agreement”). This
    provision contained no language cabining its application only
    to litigation between a party to the initial Agreement and
    subcontractors, as Hensel Phelps argued at oral argument.
    See Oral Arg. Rec. 14:10–14:59. By its plain terms, and
    contextualized within Article 7 as a whole, it applied equally
    to legal disputes between Hensel Phelps and Cooper Carry
    that had not been “resolved” via the dispute-resolution
    procedures.
    Perhaps Hensel Phelps believed a different first breach
    rule would apply once the Design/Build Agreement was
    signed and introduced the concept of substantial completion, a
    concept absent from the initial Agreement. See Design/Build
    Agreement Art. 6.15, J.A. 120. But this belief was never
    enshrined objectively in the text of either the assignment
    agreement or alterations to the initial Agreement’s text, and it
    is objective language, not subjective intent, that guides our
    13
    analysis. Carlyle, 131 A.3d at 894. Here, the terms are clear
    and unambiguous: Hensel Phelps had the right to begin
    dispute-resolution procedures in March of 2011 and to bring a
    lawsuit in court if and when those proceedings failed. We
    must hold Hensel Phelps to its bargain. Because it filed its
    complaint more than three years after the action accrued, its
    breach-of-contract claim is time-barred. 1
    B.
    We similarly find Hensel Phelps’s indemnification
    argument unavailing.
    Hensel Phelps contends the initial Agreement’s
    indemnification clause used broad and expansive language
    and contained no limitation confining its scope only to third-
    party claims.      Like any other contractual provision,
    indemnification clauses must be interpreted by looking to the
    1
    We also find it noteworthy that Hensel Phelps’s characterization
    of events corresponds with our interpretation. Though Hensel
    Phelps argued to this Court that first breach could not have
    occurred until after substantial completion, it repeatedly described
    Cooper Carry’s actions as “breaches” in its Claim Narrative. We
    recognize the initial Agreement provided that “no reference to . . .
    any admissions against interest made in the course [of mediation]
    may be made or offered as evidence in any subsequent litigation.”
    Agreement Art. 7.09.2, J.A. 31. However, Cooper Carry drew
    attention to Hensel Phelps’s characterizations in its response brief.
    Appellee Br. 11–12. Hensel Phelps failed to object in its reply brief
    and expressly disclaimed the Narrative as a statement against
    interest at oral argument. See Oral Arg. Rec. 15:45–17:00. Thus,
    whatever protection the Agreement provided against reliance on
    admissions in the course of mediation is arguably forfeited. We
    need not resolve this forfeiture issue, however; even leaving aside
    Hensel Phelps’s descriptions, Cooper Carry is entitled to summary
    judgment.
    14
    objective language as the expression of the parties’ intent.
    However, this objective analysis also considers the context in
    which words are used. Holland v. Hannan, 
    456 A.2d 807
    ,
    816–17 (D.C. 1983); see also RESTATEMENT (SECOND) OF
    CONTRACTS § 202 (1981) (“[t]he meaning of words . . .
    commonly depends on their context.”). Contextual analysis
    allows courts to “determine what a reasonable person in the
    position of the parties would have thought the disputed
    language meant,” as well as to determine if, “in context, it is
    evident that the terms used have a technical or specialized
    meaning.” Carlyle, 131 A.3d at 895.
    Unquestionably,        indemnification      clauses     have
    traditionally been used and interpreted as extending only to
    third-party claims. 3 BRUNER & O’CONNOR § 10:39; 42
    C.J.S. Indemnity § 1 (June 2017). In the initial Agreement,
    the terms “claim, judgment, lawsuit, damage, liability, and
    costs and expenses,” Art. 6.01, J.A. 27, must be interpreted in
    light of this traditional function. Furthermore, the D.C. Court
    of Appeals has advocated for strict construction of
    indemnification clauses to avoid covering “any obligations
    which the parties never intended to assume.” Am. Bldg.
    Maint. Co. v. L’Enfant Plaza Props., 
    655 A.2d 858
    , 861 (D.C.
    1995); see also 
    id.
     (noting “[t]here is no liability to indemnify
    unless it is plainly spelled out in the contract”); James G.
    Davis Constr. Corp. v. HRGM Corp., 
    147 A.3d 332
    , 340–41
    (D.C. 2016) (reading an indemnification clause covering “any
    and all costs and expenses” to reach first-party claims by
    looking to a second indemnification clause protecting only
    against “loss or losses directly connected with the
    performance of the Construction Contract” and reasoning the
    parties purposely chose a broader formulation for the clause at
    issue). Here, no clear and unequivocal intent to include first-
    party claims appears on the face of the instrument and,
    15
    construing the clause strictly, we decline to expand the scope
    of its reach. 2
    IV.
    For the foregoing reasons, the judgment of the district
    court is
    Affirmed.
    2
    Hensel Phelps argued, both below and to this Court, that the bulk
    of its indemnification claims—approximately 7.2 million dollars’
    worth—do constitute third-party claims. It defined third-party
    claims as those charged to Hensel Phelps by subcontractors,
    whereas first-party claims are those incurred directly by Hensel
    Phelps, such as additional overhead and administration costs. See
    Oral Arg. Rec. 24:43–27:34. But all first-party claims involve
    some payout to a third party. For instance, in Hensel Phelps’s
    example of additional administrative costs, Hensel Phelps must pay
    out to a third party—its employee—to provide that administration
    service.     Reading the clause according to Hensel Phelps’s
    interpretation would render it no different than a standard breach-
    of-contract claim, and we decline to do so here.