Louisiana Public Service Commission v. Federal Energy Regulatory Commission , 866 F.3d 426 ( 2017 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued December 2, 2016              Decided August 8, 2017
    No. 14-1063
    LOUISIANA PUBLIC SERVICE COMMISSION,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    MISSISSIPPI PUBLIC SERVICE COMMISSION, ET AL.,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Michael R. Fontham argued the cause for petitioner. With
    him on the briefs were Paul L. Zimmering and Noel J. Darce.
    Lona T. Perry, Deputy Solicitor, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief was Robert H. Solomon, Solicitor.
    Clifford M. Naeve argued the cause for intervenors
    supporting respondent. On the brief were John S. Moot,
    Matthew W.S. Estes, Gregory W. Camet, Glen Ortman, Dennis
    Lane, and Paul Randolph Hightower. Adrienne E. Clair
    entered an appearance.
    2
    Before: ROGERS, KAVANAUGH and WILKINS, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge WILKINS.
    WILKINS, Circuit Judge: This case continues a lengthy
    saga of litigation dealing with the allocation of production costs
    among Entergy Corporation’s utility operating companies
    (“Operating Companies”). During the period relevant here,
    Entergy1 sold electricity, both wholesale and retail, in
    Arkansas, Louisiana, Mississippi, and Texas, through five
    Operating Companies under the framework provided by the
    Entergy System Agreement. The System Agreement sets forth
    a rate schedule administered by the Federal Energy Regulatory
    Commission (“FERC”) that allocates certain costs among the
    Operating Companies and seeks to maintain rough equalization
    of those costs among them. In Louisiana Public Service
    Commission v. FERC (“LPSC”), 
    522 F.3d 378
     (D.C. Cir.
    2008), we affirmed FERC’s imposition of a so-called
    “bandwidth” remedy (“Bandwidth Remedy” or “Remedy”) to
    address unjust allocations of production costs among the
    Operating Companies and return them to “rough equalization.”
    We remanded to FERC, however, to address, among other
    things, its decision to delay the effective date of the Remedy
    until January 2006 when FERC had decided the Remedy was
    necessary in June 2005. The Louisiana Public Service
    Commission (“LPSC”) petitions this Court for review of
    FERC’s decision on remand.
    1
    We use “Entergy” in this Opinion to refer to either Entergy
    Corporation (the corporate parent of the Operating Companies and
    their affiliates) or Entergy Services, Inc. (a service affiliate that has
    acted on behalf of the Operating Companies in various FERC
    proceedings).
    3
    I.
    We described the relevant background at length in LPSC
    and we recount it only briefly here. In Opinion No. 480, issued
    on June 1, 2005, FERC determined that cost allocations under
    the System Agreement were unjust and unreasonable, and
    announced the Bandwidth Remedy to cure the disparities going
    forward. See La. Pub. Serv. Comm’n v. Entergy Servs., Inc. et
    al., 111 F.E.R.C. ¶ 61,311 (2005) (“Op. No. 480”), on reh’g,
    113 F.E.R.C. ¶ 61,282 (2005) (“Op. No. 480-A”). The Remedy
    provides that when an Operating Company’s production costs
    deviate more than 11 percent above or below the Entergy
    System’s average on an annual basis, 2 the Operating
    Companies with the lower costs will make payments
    (“Bandwidth Payments” or “Payments”) to the ones with
    higher costs such that their overall costs return to rough
    equalization. Op. No. 480, 111 F.E.R.C. ¶ 61,311, at 62,372.
    At the outset, FERC ordered that the Remedy be implemented
    prospectively and declared it would be “effective” in 2006. Id.
    at 62,373. FERC later clarified that the first of any Bandwidth
    Payments would be made in 2007, once a full year of 2006 cost
    data was available. Op. No. 480-A, 113 F.E.R.C. ¶ 61,282, at
    62,140. Such data is reported in Entergy’s annual Form 1 filed
    with FERC each April, covering the previous calendar year.
    FERC envisioned the first set of Bandwidth Payments
    would be calculated and exchanged as follows: in April 2007,
    Entergy would report the production costs of each of the
    Operating Companies for the 2006 calendar year in its Form 1.
    Based on that data, Entergy would use a formula to determine
    whether any Operating Company’s production costs exceeded
    the established bandwidth. If so, Bandwidth Payments based
    2
    This range – from 11 percent above average to 11 percent below
    average – is the “bandwidth,” hence the term “Bandwidth Remedy.”
    4
    on 2006 data would be exchanged thereafter, but no later than
    December 2007, to eliminate any severe disparities. The
    process would repeat the following year, with Entergy
    determining in 2008 to what extent Bandwidth Payments
    should be exchanged based on 2007 production cost data.
    Putting aside certain disputes about the formula used, LPSC
    acknowledges that Payments were made in 2007 based on 2006
    disparities, and again in 2008 based on 2007 disparities.
    In LPSC, we held that FERC’s “remedial choice” of the
    Bandwidth Remedy was a lawful way to return the Entergy
    System to rough equalization of its production costs. 
    522 F.3d at 391
    . But we remanded to FERC to address certain issues
    with its implementation. Of particular relevance here, we
    determined that FERC would need to explain its decision to
    delay implementation of the Bandwidth Remedy to a later date
    – i.e., making it “effective” January 1, 2006 with Payments
    commencing in 2007 – when it found that as of June 1, 2005,
    the cost allocations under the System Agreement were unjust
    and unreasonable. See 
    id. at 400
    .
    On remand, FERC advanced the “effective date” of the
    Bandwidth Remedy from January 1, 2006 up to June 1, 2005,
    and ordered that Bandwidth Payments be exchanged based on
    production cost disparities that occurred in the June –
    December 2005 period. See La. Pub. Serv. Comm’n v. Entergy
    Servs., Inc. et al., 137 F.E.R.C. ¶ 61,047 (2011) (“Order on
    Remand”); La. Pub. Serv. Comm’n v. Entergy Servs., Inc. et
    al., 146 F.E.R.C. ¶ 61,152 (2014) (“Reh’g Order”). FERC
    explained that although the agency initially contemplated that
    the Remedy would apply to cost data on an annual basis, it
    made an exception for the 7-month period now lodged between
    the old and new “effective” dates of the Remedy – i.e., the
    period from June 1, 2005 through December 31, 2005. Reh’g
    5
    Order, 146 F.E.R.C. ¶ 61,152, at 61,624-25. It ordered the
    Remedy to be applied to that period. Id. at 61,625-26.
    In the instant case, LPSC is satisfied with FERC’s decision
    that the Remedy should begin as of June 1, 2005, but it
    challenges the way in which the Remedy has been
    implemented. Specifically, LPSC claims that FERC neglected
    to provide a remedy for a portion of the post-2005 period and
    that FERC engaged in unlawful retroactive ratemaking with
    respect to its application of the Remedy to the June – December
    2005 period. 3
    II.
    We review FERC’s orders under the Administrative
    Procedure Act’s “arbitrary and capricious” standard.
    Sithe/Independence Power Partners, L.P. v. FERC, 
    165 F.3d 944
    , 948 (D.C. Cir. 1999). The “scope of review under [that]
    standard is narrow.” Motor Vehicle Mfrs. Ass’n of United
    States, Inc. v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43
    (1983). As we explained in LPSC when approving FERC’s
    selection of the Bandwidth Remedy, “[T]he breadth of agency
    discretion is, if anything, at zenith when the action assailed
    relates primarily . . . to the fashioning of policies, remedies and
    sanctions.” 
    522 F.3d at 393
     (quoting Niagara Mohawk Power
    Corp. v. FPC, 
    379 F.2d 153
    , 159 (D.C. Cir. 1967)). Similarly,
    we owe FERC “great deference” in fashioning electricity rate
    design. FERC v. Elec. Power Supply Ass’n, 
    136 S. Ct. 760
    ,
    3
    In its petition for review, LPSC also challenged FERC’s decision
    on remand regarding Section 206 refunds for the September 2001 –
    May 2003 effective period. FERC has since requested that we
    remand this issue to FERC in light of our more recent decision in
    Louisiana Public Service Commission v. FERC, 
    772 F.3d 1297
     (D.C.
    Cir. 2014). We agree that FERC should reconsider this issue and
    remand to FERC for further proceedings.
    6
    782 (2016), as revised (Jan. 28, 2016) (quoting Morgan Stanley
    Capital Grp. Inc. v. Pub. Util. Dist. No. 1, 
    554 U.S. 527
    , 532
    (2008)). “A court is not to ask whether a regulatory decision is
    the best one possible or even whether it is better than the
    alternatives.” 
    Id.
     Rather, we ask whether the agency has
    “examined the relevant considerations and articulated a
    satisfactory explanation for its action, including a rational
    connection between the facts found and the choice made.” 
    Id.
    (quoting State Farm, 
    463 U.S. at 43
    ) (alterations omitted).
    III.
    LPSC contends that, on remand, FERC eliminated a 7-
    month delay (i.e., by providing a remedy for June to December
    2005) but still left open a 17-month gap (i.e., January 2006 to
    May 2007 4) to which it asserts FERC failed to apply the
    Bandwidth Remedy. At first glance, this argument appears to
    contradict LPSC’s acknowledgment that Bandwidth Payments
    have been exchanged based on all production cost disparities
    from June 1, 2005 onward. But LPSC’s challenge stems
    primarily from a disagreement with FERC about what it means
    for the Remedy to be “effective.”
    When FERC said the Remedy was “effective” January 1,
    2006, that meant production cost disparities would be roughly
    equalized from that date forward, with Payments commencing
    once the prior year’s data had been collected. In LPSC’s view,
    however, the Remedy could not effectuate the “just and
    reasonable rate” under 16 U.S.C. § 824e(a) until Payments
    were exchanged – only then could the proper rate be
    “thereafter observed and in force.” As such, FERC’s original
    4
    This is the gap between the 2005 period addressed on remand and
    the date the first set of Bandwidth Payments were exchanged as
    originally contemplated by FERC.
    7
    announcement in Opinion No. 480 that the Bandwidth Remedy
    would be “effective” in 2006 was a “fiction” because no
    Payments were made until June 2007. Pet’r Br. 34, 42. Under
    that premise, LPSC sought on remand to have the Remedy
    (theoretically) begin with Payments in 2005 based on 2004
    data, Payments in 2006 based on 2005 data, and so on, until the
    purported “two year delay” was resolved. See Reh’g Order,
    146 F.E.R.C. ¶ 61,152, at 61,625.
    FERC addressed this point on remand, explaining there
    was simply no basis for LPSC’s assertion that FERC was
    required to provide a remedy for a “two year delay” or
    Payments based on disparities occurring in “calendar years
    2004 and 2005.” Id. FERC correctly observed that this Court’s
    decision ordering remand did not provide the directive sought
    by LPSC. Id. at 61,625-26.
    LPSC relies here – as it did before FERC – on a reference
    in LPSC to the delay of the Bandwidth Remedy “until 2007,”
    
    522 F.3d at 400
    , as an endorsement of its view that the Remedy
    does not begin until Bandwidth Payments commence. In that
    decision, although we took issue with the unexplained delay of
    the Remedy beyond June 2005, we did not purport to resolve
    the outer bound of that delay. See 
    id.
     In any event, we
    understood the “effective” date of the Remedy was January 1,
    2006, even though Payments would not commence until 2007.
    See, e.g., 
    id. at 388, 399
    . Read in its proper context, our
    reference to 2007 simply did “not tak[e] sides in any dispute”
    over the meaning of the effective date of the Bandwidth
    Remedy. AT&T Wireless Servs., Inc. v. FCC, 
    365 F.3d 1095
    ,
    1103 (D.C. Cir. 2004).
    On remand, rather than attempting to offer an explanation
    for delaying the Remedy to a date beyond June 2005, FERC
    sought to cure it by advancing the “effective date” to June 1,
    8
    2005. Order on Remand, 137 F.E.R.C. ¶ 61,047, at 61,214-15.
    In doing so, FERC reiterated its conceptualization of the
    Bandwidth Remedy as one that would come into play only “if
    the Entergy System exceeded historical cost disparities” – that
    is, if any Operating Company has production costs more than
    11 percent above or below the Entergy System average. Id. at
    61,210; see also Op. No. 480, 111 F.E.R.C. ¶ 61,311, at 62,356.
    In practice, that meant the Remedy would be “effective” in
    2006 but Payments would only be triggered if severe
    production cost disparities existed among the Operating
    Companies across the entire year – a determination that would
    not be made until after that year’s end. See Reh’g Order, 146
    F.E.R.C. ¶ 61,152, at 61,625-26. On remand, FERC explained
    that Payments had already been exchanged for 2006 and 2007
    production cost disparities, and thus there was no basis for
    LPSC’s contention that FERC had left a “two year delay”
    unresolved. Id. at 61,625 (“[T]he 2006 calendar year’s data is
    accounted for under the bandwidth formula th[r]ough
    payments the following year. Similarly, the 2007 calendar
    year’s data is roughly equalized through payments
    commencing in 2008.”). LPSC offers no basis for undermining
    the great deference we owe to FERC in fashioning the
    Bandwidth Remedy the way it did.
    LPSC claims that FERC’s explanation on remand is
    “specious” because it deviates from the way FERC typically
    designs formula rates. Pet’r Br. 31. But FERC confronted an
    unusual problem here – one that is only highlighted by LPSC’s
    comparison of this case to Louisiana Public Service
    Commission v. FERC, 
    482 F.3d 510
     (D.C. Cir. 2007). There,
    we held that it was unlawful for FERC to continue to allow any
    amount of “interruptible load” to be included in cost allocations
    among the Operating Companies after FERC determined that
    such inclusion resulted in an unjust and unreasonable rate. See
    
    id. at 514, 518
    . However, the Bandwidth Remedy evaluates
    9
    total production costs for disparities among the Operating
    Companies at year’s end – there is no factor comparable to
    interruptible load that can be preemptively controlled for to
    maintain a just and reasonable rate going forward. To the
    extent LPSC asserts the Remedy should have used historical
    disparities as a proxy for future ones, we are mindful of our
    obligation to refrain from asking “whether a regulatory
    decision is . . . better than the alternatives,” as long as the
    agency gives a “satisfactory explanation” for its decision. Elec.
    Power Supply Ass’n, 
    136 S. Ct. at 782
    . We have reviewed
    LPSC’s remaining arguments challenging FERC’s decision to
    proceed as it did on remand and find they are all without merit.
    On remand, FERC retroactively applied its Remedy such
    that it cured any severe disparities from June 1, 2005 onward.
    LPSC does not dispute that, prior to FERC’s final decision on
    remand, the Bandwidth Remedy (as conceived of by FERC)
    had been applied and Payments exchanged based on cost data
    from 2006 and 2007 – the period it claims FERC has
    neglected. 5 Nor does it dispute that FERC applied the Remedy
    to the June – December 2005 period on remand. Thus, any
    severe production cost disparities that post-date June 2005 have
    been accounted for with Bandwidth Payments, and we agree
    with FERC that there was nothing left for it to resolve on
    remand. Accordingly, LPSC’s petition is denied with respect
    to FERC’s advancement of the effective date to the 2005
    period.
    5
    To the extent LPSC claims that “[t]he 2007 payments and receipts
    did nothing to remedy undue discrimination in 2006,” it is taking
    issue with the fact that the Bandwidth Remedy was not structured to
    use prior year data as a proxy for disparities going forward, and
    instead Payments were not exchanged until 2007. Pet’r Br. 34.
    10
    IV.
    LPSC also challenges the particular formula FERC applied
    to the 2005 period, arguing FERC engaged in unlawful
    retroactive ratemaking. To be sure, LPSC does not object to
    FERC’s altering the “effective date” of the Bandwidth Remedy
    to cure disparities in the previously-overlooked 2005 period.
    Indeed, that is the result LPSC urged. That result is also
    consistent with FERC’s ample authority to remedy its own
    errors after being reversed in court, notwithstanding the
    prohibition on retroactive ratemaking. See, e.g., Pub. Utils.
    Comm’n v. FERC, 
    988 F.2d 154
    , 162 (D.C. Cir. 1993); see also
    Xcel Energy Servs. v. FERC, 
    815 F.3d 947
    , 955-56 (D.C. Cir.
    2016). 6
    Rather, LPSC contends that FERC should have
    retroactively applied to that period the methodology announced
    in Opinion No. 480 in June 2005 (which was not to go into
    effect until January 2006), instead of the methodology later
    integrated into the System Agreement in 2006. LPSC agrees
    that if the 2006 formula “had adhered to” the one announced in
    Opinion No. 480, FERC’s decision on remand “would be
    lawful.” Pet’r Br. 57. However, when presented with the 2006
    methodology, FERC determined that it did adhere to the one
    announced in Opinion No. 480. See La Pub. Serv. Comm’n v.
    Entergy Servs., Inc., 117 F.E.R.C. ¶ 61,203, at 62,000-01
    (2006), on reh’g, 119 F.E.R.C. ¶ 61,095 (2007), aff’d, La. Pub.
    Serv. Comm’n v. FERC, 341 Fed. App’x 649 (D.C. Cir. 2009).
    As we previously held, LPSC waived any dispute it had with
    that conclusion by failing to raise it in the compliance
    6
    City of Anaheim v. FERC does not control the outcome here
    because, in that case, FERC was not “responding to a court decision
    when it imposed retroactive surcharges.” 
    558 F.3d 521
    , 525 (D.C.
    Cir. 2009).
    11
    proceedings. See La. Pub. Serv. Comm’n v. FERC, 606 F.
    App’x 1, 5 (D.C. Cir. 2015). In sum, there is no basis for
    LPSC’s contention that FERC engaged in unlawful retroactive
    ratemaking. Accordingly, we deny its petition as to the
    application of the Bandwidth Remedy to the 2005 period.
    V.
    For the foregoing reasons, LPSC’s petition for review of
    FERC’s decisions regarding the implementation of the
    Bandwidth Remedy to the June 2005 – May 2007 period is
    denied. We grant FERC’s request to remand to FERC for
    further consideration of the denial of Section 206 refunds for
    the September 2001 – May 2003 effective period.
    So ordered.