United States v. Hirani Engineering & Land ( 2023 )


Menu:
  • United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 13, 2022            Decided January 31, 2023
    No. 19-7010
    UNITED STATES OF AMERICA, FOR THE USE AND BENEFIT OF
    AMERICAN CIVIL CONSTRUCTION, LLC,
    APPELLEE
    v.
    HIRANI ENGINEERING & LAND SURVEYING, PC,
    APPELLEE
    COLONIAL SURETY COMPANY,
    APPELLANT
    Consolidated with 19-7011, 19-7015
    Appeals from the United States District Court
    for the District of Columbia
    (No. 1:14-cv-00745)
    Michael C. Delaney argued the cause for appellants/cross-
    appellees. With him on the supplemental brief were Laurence
    Schor and Karen L. Dowd.
    2
    Herman M. Braude argued the cause and filed the
    supplemental brief for appellee/cross-appellant.
    Before: SRINIVASAN, Chief Judge, HENDERSON, Circuit
    Judge, and ROGERS, Senior Circuit Judge.
    Opinion for the Court filed by Senior Circuit Judge
    ROGERS.
    ROGERS, Senior Circuit Judge: This case returns to the
    court after a limited remand of the record to the district court.
    United States ex rel. Am. Civ. Constr., LLC v. Hirani Eng’g &
    Land Surveying, PC, 
    26 F.4th 952
    , 954 (D.C. Cir. 2022)
    (“Hirani IV”), amending 
    962 F.3d 587
     (D.C. Cir. 2020). Upon
    consideration of the original and the supplemental briefs, and
    the post-remand oral argument, there remain three issues
    before this court: The surety (“Colonial”) for the prime
    contractor (“Hirani”) challenges the district court’s award of
    quantum meruit damages on the Miller Act claim of the
    subcontractor (“ACC”), and the district court’s award as
    double recovery for the subcontractor. The subcontractor
    continues to challenge the district court’s denial of recovery
    under the Miller Act for the reasonable value of its
    superintendent’s services at the job site. For the following
    reasons, the court affirms the district court’s judgment except
    to remand for the district court to expressly address whether
    there would be impermissible double recovery for the
    subcontractor.
    I.
    The surety has withdrawn the statute of limitations
    defense. Colonial Suppl. Br. 1 (Aug. 4, 2022). It has also
    withdrawn the hearsay objections to daily reports on when the
    subcontractor last furnished labor or materials. Oral Arg.
    3
    Recording 2:10-2:17 (Oct. 13, 2022). Therefore, only two of
    its contentions remain before the court.
    A.
    First, the surety contends that the district court erred as a
    matter of law in granting the subcontractor quantum meruit
    recovery on its Miller Act claim where there is an express
    contract from which damages could be calculated and the
    award exceeded that against the prime contractor. Colonial
    Br. 28-37 (July 19, 2019); Colonial Suppl. Br. 1-5 (Aug. 4,
    2022). But the surety has likely misread this court’s denial of
    quantum meruit on the subcontractor’s D.C. breach-of-contract
    claim against the prime contractor to preclude the surety’s
    liability on a quantum meruit theory under the Miller Act.
    Hirani IV, 26 F.4th at 960; Colonial Suppl. Br. 2 (Aug. 4,
    2022). This court affirmed the district court’s grant of
    “restitution,” which it had viewed to reflect the subcontractor’s
    claim. Hirani IV, 26 F.4th at 960. Even if D.C. contract law
    caps the subcontractor’s restitution recovery against the prime
    contractor to expectation damages and does not permit
    recovery in quantum meruit where there is an express contract,
    no such limit applies to the claim against the surety under the
    Miller Act.
    The scope of Miller Act remedies is a matter of federal
    law. F.D. Rich Co. v. United States ex rel. Indus. Lumber Co.,
    
    417 U.S. 116
    , 127 (1974). In United States ex rel. Heller
    Electric Co. v. William F. Klingensmith, Inc., 
    670 F.2d 1227
    (D.C. Cir. 1982), a subcontractor sought to recover delay
    damages under the Miller Act from its prime contractor’s
    surety. The “possible complication” of the subcontractor’s
    claim was that delay damages “represent the value of material
    and services provided at the particular time they were provided,
    as opposed to the time the parties initially expected them to be
    4
    provided” as reflected by the contract price. 
    Id. at 1232
    .
    Relying on “cases decided under the Miller Act that allow
    quantum meruit recovery against a surety,” 
    id.,
     the court
    explained that “[a]ny other interpretation would undermine the
    security interest that Congress intended to provide
    subcontractors on government projects, particularly in times of
    generally rising prices,” 
    id. at 1233
    . Indeed, in Continental
    Casualty Co. v. Allsop Lumber Co., 
    336 F.2d 445
    , 455 (8th Cir.
    1964), see Colonial Br. 33 (July 19, 2019), that court
    recognized the permissibility of recovery under the Miller Act
    in quantum meruit where there was a breach of an express
    contract. See also United States ex rel. Susi Contracting Co. v.
    Zara Contracting Co., 
    146 F.2d 606
    , 610 (2d Cir. 1944).
    The Supreme Court has interpreted the Miller Act broadly
    in view of its “highly remedial” nature. Clifford F. MacEvoy
    Co. v. United States ex rel. Calvin Tomkins Co., 
    322 U.S. 102
    ,
    107 (1944). The Court explained that the Act is “entitled to a
    liberal construction and application in order properly to
    effectuate the Congressional intent to protect those whose labor
    and materials go into public projects.” 
    Id.
     Other courts have
    heeded that instruction, see Glassell-Taylor Co. v. Magnolia
    Petroleum Co., 
    153 F.2d 527
    , 529-30 (5th Cir. 1946)
    (collecting cases), and this court will too.
    Second, this court need not resolve the surety’s contention
    that the district court awarded the subcontractor double
    recovery. “If we do not decide it now, we may never need to.”
    Nat’l Treasury Emps. Union v. United States, 
    101 F.3d 1423
    ,
    1431 (D.C. Cir. 1996).
    According to the subcontractor, it sought damages it could
    not recover against the prime contractor because such recovery
    on its D.C. breach-of-contract claim was limited by contract
    expectancy, while its quantum meruit claim for recovery
    5
    against the surety arises under the Miller Act and includes work
    beyond the subcontract. It relies on Heller Electric Co., 
    670 F.2d at 1232-33
    . In that case, this court cited United States ex
    rel. Mariana v. Piracci Constr. Co., 
    405 F. Supp. 904
     (D.D.C.
    1975), and United States ex rel. Otis Elevator Co. v. Piracci
    Constr. Co., 
    405 F. Supp. 908
     (D.D.C. 1975), in awarding the
    subcontractor the value of services and materials that it
    provided including delay damages representing the value of
    material and services which were different than what the
    parties initially expected. Heller Electric Co., 
    670 F.2d at 1232
    . Here the district court too relied on Heller Electric’s
    holding. United States ex rel. Am. Civ. Constr., LLC v. Hirani
    Eng’g & Land Surveying, P.C., 
    263 F. Supp. 3d 99
    , 115
    (D.D.C. 2017) (“Hirani I”).
    The subcontractor had sought the same amount of
    damages against the surety and its principal, the prime
    contractor, based on quantum meruit recovery, arguing that
    because of “the piecemeal adverse uncontemplated
    performance of 25 months versus the eight months the parties
    originally contemplated, the judgment should be the same
    against both defendants, although the judgment could only be
    collected once.” ACC Br. 74 (Oct. 11, 2019). Moreover,
    according to the subcontractor, “there would be no double
    recovery as Hirani is probably insolvent and judgment proof
    [having] . . . assigned all of its assets under a standard
    indemnity agreement to Colonial.” ACC Reply Br. 1 n.1 (Feb.
    11, 2020).
    The district court acknowledged that the subcontractor’s
    Miller Act claim seeks both “monetary compensation for work
    performed beyond what the Subcontract called for” and “also
    . . . the unpaid amounts that [it] claims it is owed for work
    performed under the Subcontract,” which it described as
    “contract damages.” Hirani I, 
    263 F. Supp. 3d at
    115 n.7. The
    6
    district court did not indicate whether any (or what part) of the
    Miller Act award against the surety is only for work performed
    beyond that specified in the subcontract. On remand the
    district court can clarify whether there would be any
    impermissible double recovery in light of the subcontractor’s
    revision, if any, to its damages calculation of December 10,
    2018.
    B.
    The subcontractor renews its contention that the district
    court erred in denying recovery for its superintendent’s on-site
    labor. ACC Br. 64-66 (Oct. 11, 2019); ACC Reply Br. 2-9
    (Feb. 11, 2020).
    Miller Act payment bonds cover “[e]very person that has
    furnished labor or material in carrying out work provided for
    in a contract.” 
    40 U.S.C. § 3133
    (b)(1). The Act does not define
    the term “labor,” and the issue is one of first impression for this
    court. The district court and the parties agree that “labor” can
    include “skilled professional work which involves actual
    superintending, supervision, or inspection at the job site.”
    Colonial Reply Br. 26 (Dec. 18, 2019) (quoting United States
    ex rel. Olson v. W.H. Cates Constr. Co., 
    972 F.2d 987
    , 990 (8th
    Cir. 1992)); see United States ex rel. Am. Civ. Constr., LLC v.
    Hirani Eng’g & Land Surveying, P.C., 
    345 F. Supp. 3d 11
    , 50
    (D.D.C. 2018) (“Hirani II”); ACC Br. 66 (Oct. 11, 2019). The
    subcontractor maintains that this is the end of the inquiry:
    “[L]abor” includes work by “an actual superintendent or
    supervis[or] at the job site, and excludes off-site professionals
    such as an architect or engineer.” ACC Br. 66 (Oct. 11, 2019).
    The surety challenged the notion that mere on-site presence
    constituted “labor” by a superintendent. Colonial Reply Br. 26
    (Dec. 18, 2019). The district court essentially agreed, ruling
    that “the on-site supervisory work of a project manager falls
    7
    within the purview of the Miller Act if such a superintendent
    did some physical labor at the job site.” Hirani II, 345 F. Supp.
    3d at 50 (quoting W.H. Cates, 
    972 F.2d at 991
    ).
    Both the subcontract and government quality control
    standards for the Project required the preparation of daily
    reports certifying the work’s progress. Subcontract at ¶ 16.1
    (Suppl. App. 2402 (Oct. 11, 2019)); Contractor Quality Control
    Plan at ¶ 7.2 (Suppl. App. 2494-95 (Oct. 11, 2019)). The daily
    form submitted by the subcontractor pursuant to the
    subcontract required “verif[ication]” of the “manpower and
    equipment . . . present at [the] site” and “confirm[ation of] . . .
    the work performed at [the] site.” See, e.g., Daily Manpower,
    Equipment, and Field Overhead Tracking Form for Field
    Verification (Feb. 21, 2013) (“Form”). The subcontractor
    explained that because “construction activities have to be
    continuously supervised, inspected and ultimately certified as
    being in conformance with the contract requirements,” ACC
    Reply Br. 7-8 (Feb. 11, 2020), its superintendent had to be on-
    site to account for, among other things, hours worked by crew
    members, usage and standby hours for each piece of
    equipment, materials delivered, weather throughout the day,
    and all work performed, see Form.                 These on-site
    responsibilities reflected the government’s quality control
    standards, under which the superintendent as “the most senior
    site manager at the project, is responsible for the overall
    construction activities at the site . . . includ[ing] all quality,
    workmanship, and production of crews and equipment.”
    Contractor Quality Control Plan at ¶ 4.4 (Suppl. App. 2478-79
    (Oct. 11, 2019)). The superintendent is therefore required to
    “maintain a physical presence at the project site at all times”
    and “may only be absent from the project for short periods of
    time.” 
    Id.
     In addition, the superintendent supervised the traffic
    flow along 17th Street adjacent to the work site. Trial Tr. at
    102:23-103:3 (Mar. 7, 2018 AM). At trial, the subcontractor
    8
    also presented expert testimony that the reasonable value of the
    superintendent’s services was $3,000 per week, for a total of
    $306,000 over the course of the project. See id. at 100:9-13;
    ACC’s Proposed Findings of Fact & Conclusions of Law 58,
    ECF No. 82 (Apr. 13, 2018).
    The surety challenged this evidence, asserting that the
    subcontractor offered nothing to show that the superintendent
    performed “labor” within the meaning of the Miller Act,
    Colonial’s Proposed Findings of Fact & Conclusions of Law
    51-54, ECF No. 83 (Apr. 13, 2018), and that the
    subcontractor’s expert’s calculation of the value of the
    superintendent’s services was “grossly unreasonable,”
    exceeding weekly rates for superintendents across the United
    States, id. at 53. The district court noted the objection to the
    reasonableness of the weekly rate, Hirani II, 345 F. Supp. 3d
    at 49, but in denying recovery relied on the absence of evidence
    the superintendent performed physical on-site labor, id. at 50.
    Other courts have taken into account the nature of a
    superintendent’s oversight responsibilities in concluding that a
    superintendent’s cost was compensable “labor.” Referencing
    the trend in other courts, the Eighth Circuit concluded that “the
    on-site supervisory work of a project manager falls within the
    purview of the Miller Act if such a superintendent did some
    physical labor at the job site or might have been called upon to
    do some on-site manual work in the regular course of his job.”
    W.H. Cates, 
    972 F.2d at 991
     (emphasis added); see 
    id.
     at 990-
    91 (citing cases from the Third, Fourth, Fifth, and Ninth
    Circuits). That is, “only certain professional supervisory work
    is covered by the Miller Act, namely, ‘skilled professional
    work which involves actual superintending, supervision, or
    inspection at the job site.’” 
    Id. at 990
     (quoting United States
    ex rel. Naberhaus-Burke, Inc. v. Butt & Head, Inc., 
    535 F. Supp. 1155
    , 1160 (S.D. Ohio 1982)). The Eighth Circuit
    9
    acknowledged that the term labor generally includes physical
    rather than professional work but distinguished those
    professionals who superintend on-site as performing labor. 
    Id.
    (citing United States ex rel. Farwell, Ozmun, Kirk & Co. v.
    Shea-Adamson Co., 
    21 F. Supp. 831
    , 837 (D. Minn. 1937)
    (relying on state and federal cases)).
    Given that the construction work at issue had to be
    supervised and inspected for conformance with the subcontract
    and other requirements, such as government quality control
    standards, the superintendent’s on-site supervisory work
    constitutes “labor” within the meaning of the Miller Act. In
    Mining Co. v. Cullins, 
    104 U.S. 176
     (1881), the Supreme Court
    interpreted “labor” under a territorial mechanic’s lien law to
    include the work of an on-site superintendent. 
    Id. at 177
    . Such
    a construction is consonant with the Miller Act’s remedial
    purpose. MacEvoy, 
    322 U.S. at 107
    .
    Accordingly, the court affirms the judgment of the district
    court in part but reverses and remands in part to allow the
    district court to determine whether there is any impermissible
    double recovery and to award the reasonable value of the
    superintendent’s on-site services under the Miller Act.