Solar Energy Industries Association v. FERC ( 2023 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued September 7, 2022          Decided February 14, 2023
    No. 21-1126
    SOLAR ENERGY INDUSTRIES ASSOCIATION,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION ,
    RESPONDENT
    NEWSUN ENERGY LLC AND BROADVIEW SOLAR, LLC,
    INTERVENORS
    Consolidated with 21-1136, 21-1142, 21-1149, 21-1175
    On Petitions for Review of Orders of
    the Federal Energy Regulatory Commission
    Jeremy C. Marwell argued the cause for petitioners The
    Edison Electric Institute and Northwestern Corporation. With
    him on the briefs were Sarah N. Norcott and James T. Dawson.
    2
    Heather Curlee argued the cause for petitioner Solar
    Energy Industry Association. With her on the briefs was Todd
    G. Glass.
    Adam Lowney and Christopher Jones were on the brief for
    amicus curiae Pacificorp d/b/a/ Pacific Power and Rocky
    Mountain Power in support of petitioners.
    Jared B. Fish, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on
    the brief were Matthew R. Christiansen, General Counsel, and
    Robert H. Solomon, Solicitor. Anand Viswanathan, Attorney,
    entered an appearance.
    Robert M. Loeb argued the cause for intervenors NewSun
    Energy LLC and Broadview Solar, LLC. With him on the brief
    were Gregory M. Adams, Adam Wenner, and Jeremy R.
    Peterman. Peter Richardson entered an appearance.
    Kip D. Nelson, Nick Jimenez, and Irion A. Sanger were on
    the brief for amici curiae Carolinas Clean Energy Business
    Association, et al. in support of respondent.
    Before: PILLARD and WALKER, Circuit Judges, and
    SENTELLE , Senior Circuit Judge.
    Opinion for the Court filed by Senior Circuit Judge
    SENTELLE .
    Opinion concurring in part and dissenting in part filed by
    Circuit Judge WALKER.
    SENTELLE, Senior Circuit Judge: The Edison Electric
    Institute and NorthWestern Corporation, d/b/a NorthWestern
    Energy, (collectively, “Utilities”) petition for review of an
    3
    order by the Federal Energy Regulatory Commission
    (“Commission”) in which the Commission granted Broadview
    Solar’s application to become a qualifying facility under the
    Public Utility Regulatory Policies Act of 1978 (“PURPA”).
    The Solar Energy Industries Association (“SEIA”) petitions for
    review of the Commission’s denial of its motion to intervene
    in the adjudication of Broadview’s application.
    Because we conclude that the Commission’s interpretation
    of the statute is entitled to deference and that the Commission
    did not act arbitrarily or capriciously, we deny the Utilities’
    petitions. We dismiss SEIA’s petitions because it lacks Article
    III standing.
    Background
    Section 210 of PURPA was enacted with the goal of
    promoting the creation and use of alternative energy. See Am.
    Paper Inst., Inc. v. Am. Elec. Power Serv. Corp., 
    461 U.S. 402
    ,
    404–05 (1983). It does so, in part, by directing the Commission
    to prescribe rules affording “qualifying small power production
    facilities,” also commonly known as “qualifying facilities,”
    certain benefits. See 16 U.S.C. § 824a-3(a)–(b). To be a
    qualifying facility under the Act, a facility must use “biomass,
    waste, renewable resources, geothermal resources, or any
    combination thereof” to produce energy and have “a power
    production capacity which, together with any other facilities
    located at the same site . . . , is not greater than 80 megawatts.”
    Id. § 796(17)(A)(i)–(ii). Facilities may self-certify that they
    meet these requirements, or they may apply for certification
    from the Commission. See 
    18 C.F.R. § 292.207
    (a)–(b). One
    notable benefit to being a qualifying facility is the mandatory
    purchase obligation. Under it, electric utilities are required to
    purchase the energy generated by qualifying facilities,
    4
    providing those facilities with a guaranteed market. See 16
    U.S.C. § 824a-3(a)(2); 
    18 C.F.R. § 292.303
    (a).
    In September 2019, Broadview applied for certification
    from the Commission that its Montana facility was a qualifying
    facility. That facility consists of a 160 MW solar array and a
    50 MW battery storage system, both of which produce or store
    direct current, or DC, power. Because the nation’s electric grid
    runs on alternating current, or AC, power, solar facilities must
    also have devices known as inverters to convert DC power into
    grid-usable AC power. Broadview’s Montana facility has
    inverters with a total net capacity of 80 MW.
    In its application, Broadview noted its intent to
    interconnect with and sell energy to NorthWestern Energy, as
    it would be entitled to do under the mandatory purchasing
    requirement as a qualifying facility. The Edison Electric
    Institute, a trade association representing investor-owned
    electric companies across the United States subject to
    mandatory purchasing requirements, and NorthWestern
    Energy filed motions to intervene in the Broadview docket,
    objecting to certification of Broadview’s facility. Both
    motions were timely filed by the October 2, 2019, deadline.
    The Commission denied Broadview’s application for
    certification in a September 2020 Order, determining that
    Broadview’s facility exceeded the statute’s maximum “power
    production capacity” of 80 MW. See Broadview Solar, LLC,
    
    172 FERC ¶ 61,194
     (2020), set aside, 
    174 FERC ¶ 61,199
    (2021), reh’g denied and modified, 
    175 FERC ¶ 61,228
     (2021).
    In reaching this conclusion, the Commission determined that
    the relevant “capacity” was that of the solar array, which was
    160 MW of DC power, and not the inverters’ “conversion
    limit” of 80 MW of AC power. 
    Id. at 62,276
    . The Commission
    acknowledged it was departing from its previous approach set
    5
    out in Occidental Geothermal, Inc., 
    17 FERC ¶ 61,231
     (1981),
    which focused on the facility’s net output, or “send-out,”
    capacity. It determined, however, that the send-out approach
    was inconsistent with the statute’s text. Broadview filed a
    request for rehearing. After the Commission issued its
    September 2020 Order, SEIA also filed a motion to intervene,
    nearly one year after the original deadline.
    In March 2021, the Commission issued a new Order
    granting Broadview qualifying facility status and setting aside
    its September 2020 Order. Broadview Solar, LLC, 
    174 FERC ¶ 61,199
     (2021). After determining that § 796(17)(A) was
    ambiguous as to the proper measure of a facility’s “power
    production capacity,” the Commission determined that its
    former send-out approach was the best interpretation because
    it takes into account all of the facility’s components working
    together, not just the maximum capacity of one subcomponent,
    and focuses on grid-usable AC power. Broadview Solar, LLC,
    
    174 FERC ¶ 61,199
    , at 61,797. Because Broadview’s send-out
    capacity at any single point in time is capped by the inverters’
    net output capacity of 80 MW of power, the Commission
    determined that Broadview’s facility met the statutory
    requirements and granted it qualifying facility status. 
    Id. at 61,799, 61
    ,801–02. In the same March 2021 Order, the
    Commission also determined SEIA failed to establish good
    cause for its untimely motion to intervene and denied that
    motion. 
    Id. at 61,795
    .
    The Utilities and SEIA filed requests for rehearing. The
    Commission issued its June 2021 Order, reaffirming that
    Broadview was a qualifying facility and modifying its March
    2021 Order to reject the Utilities’ arguments that Broadview’s
    facility represented a novel subversion of the statute and that
    the battery’s capacity had to be calculated separately from the
    6
    capacity of the solar array. Broadview Solar, LLC, 
    175 FERC ¶ 61,228
     (2021). This appeal followed.
    Analysis
    A. PURPA
    i.      Chevron Challenge
    The Utilities argue that the Commission exceeded its
    statutory authority because, in their view, the “power
    production capacity” of Broadview’s facility is the total
    amount of DC power generated by the solar array and not the
    grid-usable AC power produced by the inverters working in
    conjunction with the solar array and battery. The Commission
    argues that the statute is ambiguous as to the proper measure of
    a facility’s “power production capacity” and that its
    interpretation, focusing on the amount of AC power being sent
    out to the grid, is reasonable. We agree with the Commission.
    In interpreting the statute, this Court’s analysis is governed
    by the two-step framework set out in Chevron U.S.A. Inc. v.
    Natural Resources Defense Council, Inc., 
    467 U.S. 837
     (1984).
    Under step one, the court asks “whether Congress has directly
    spoken to the precise question at issue.” 
    Id. at 842
    . If it has,
    “the court, as well as the agency, must give effect to the
    unambiguously expressed intent of Congress.” 
    Id.
     at 842–43.
    But “if the statute is silent or ambiguous with respect to the
    specific issue,” the court moves to step two and must uphold
    any agency interpretation that is “reasonable.” 
    Id.
     at 843–44.
    The parties’ dispute in this case turns on the meanings of
    “facility” and “power production capacity” in 
    16 U.S.C. § 796
    (17)(A). PURPA does not define these terms. In plain
    language, a facility’s “power production capacity” is the
    maximum amount of power that the facility can produce. But
    7
    the statute does not state whether the relevant capacity is that
    of the individual subcomponent generating DC power, i.e., the
    solar array, or of all the facility’s components working together
    to produce grid-usable AC power, which would include the
    inverters. Because Congress has not spoken to the issue, we
    move to step two and must defer to any reasonable agency
    interpretation.
    To determine whether the Commission’s interpretation
    was reasonable, we look to see if it “is based on a permissible
    construction of the statute in light of its language, structure, and
    purpose” and consistent with the legislative history. Nat’l
    Treasury Emps. Union v. Fed. Lab. Rels. Auth., 
    754 F.3d 1031
    ,
    1042 (D.C. Cir. 2014) (quoting Am. Fed’n of Labor v. Chao,
    
    409 F.3d 377
    , 384 (D.C. Cir. 2005)); see also Bell Atl. Tel. Co.
    v. FCC, 
    131 F.3d 1044
    , 1048-49 (D.C. Cir. 1997).
    We start with the text. On appeal, the Commission raised
    for the first time the argument that “capacity” has an industry-
    specific definition meaning the maximum amount of power
    that can be supplied to the power grid, i.e., for end-user
    demand. Because this was not a basis for the Commission’s
    decision, we do not consider it here. See Secs. & Exch.
    Comm’n v. Chenery Corp., 
    318 U.S. 80
    , 87, 95 (1943). Even
    so, the Commission’s interpretations of “power production
    capacity” as “the facility’s net output to the electric utility,” and
    of “facility” as “all of the putative [qualifying facility’s]
    component parts as they work together as a whole,” were
    eminently reasonable. See 
    175 FERC ¶ 61,228
    , at 62,316–17
    (internal quotation marks and citation omitted). As discussed,
    the statute is ambiguous on the meanings of “power production
    capacity” and “facility.” The only grid-usable “power” that
    Broadview produces is AC power, and Broadview’s inverters
    work with the solar array and battery as an integral component
    in producing that power.
    8
    The Commission’s interpretation was further guided, and
    is amply supported, by the statute’s structure and purpose.
    Determining qualifying facility status by the facility’s net
    output brings various provisions of PURPA into harmony. One
    of the main benefits of being a qualifying facility is the
    mandatory purchasing requirement. But the mandatory
    purchasing requirement only applies to grid-usable power—
    meaning AC power. The Commission’s interpretation of
    “power production capacity” similarly focuses on net output of
    grid-usable AC power. Thus, the measure used to determine
    whether a facility is eligible for qualifying facility status is the
    same used to determine benefits available to those qualifying
    facilities.
    The Commission’s focus on net output is likewise
    “consistent with the statutory purpose” of PURPA. Troy Corp.
    v. Browner, 
    120 F.3d 277
    , 285 (D.C. Cir. 1997) (citing
    Chevron, 
    467 U.S. at 843
    ). Title II of PURPA was intended
    “to encourage the development of . . . small power production
    facilities” and promote the use of alternative energy sources,
    such as solar. Conn. Valley Elec. Co. v. FERC, 
    208 F.3d 1037
    ,
    1045 (D.C. Cir. 2000) (quoting FERC v. Mississippi, 
    456 U.S. 742
    , 750 (1982)). Excluding facilities from qualifying facility
    status because their component parts have individual
    production capacities over 80 MW, even though the overall
    facility cannot send out more than 80 MW to the grid, would
    be inconsistent with that goal.
    Compared to facilities that rely on other energy sources,
    solar facilities are relatively inefficient at generating power. A
    solar array needs sunlight; cloud cover and nighttime hinder its
    production capabilities. Broadview addressed this by installing
    a solar array with a capacity of 160 MW and a battery, enabling
    it to produce extra power to be stored in the battery while
    9
    conditions are optimal and then release that power to the grid
    when conditions prevent the array from producing enough
    power to meet the inverters’ 80 MW limit. The Utilities
    complain that this allows Broadview to circumvent the
    statutory restrictions on qualifying facilities. But viewed in
    light of the statute’s purpose, this arrangement is a feature, not
    a bug: Broadview is able to more consistently produce, send
    out, and sell the maximum amount of renewable energy
    permitted under the statute.
    The Commission’s interpretation is also consistent with
    the legislative history. See City of Cleveland v. U.S. Nuclear
    Reg. Comm’n, 
    68 F.3d 1361
    , 1367–68 (D.C. Cir. 1995). The
    Utilities rely on one sentence from a House Committee Report
    stating that “[t]he power production capacity of the facility
    means the rated capacity of the facility.” H.R. Rep. No. 95-
    1750, at 89 (1978) (Conf. Rep.). While neither the legislative
    history nor PURPA defines “rated capacity,” it is most
    frequently used to refer to the performance anticipated under
    “standard operating conditions.” Occidental, 
    17 FERC ¶ 61,231
    , at 61,444–45. The Utilities adopt this definition in
    their briefing but fail to apply that definition to the House
    Committee’s full quote, which referred to the “rated capacity
    of the facility.” H.R. Rep. No. 95-1750, at 89 (1978) (Conf.
    Rep.) (emphasis added). Broadview’s facility consists of a
    solar array, battery, and inverters that can regularly produce 80
    MW of grid-usable power. As the Commission previously
    recognized, “a facility’s power production capacity is not
    necessarily determined by the nominal rating of even a key
    component of the facility. . . . [I]t is not uncommon for smaller
    facilities to find it most economic to employ commercially
    available components[,] some of which have individual
    capabilities significantly exceeding the overall facility
    capabilities.” Occidental, 
    17 FERC ¶ 61,231
    , at 61,445.
    10
    The Commission’s determination that Broadview is a
    qualifying facility with a “power production capacity . . . not
    greater than 80 megawatts,” 
    16 U.S.C. § 796
    (17)(A)(ii),
    because its component parts, working together, produce no
    more than 80 MW of grid-usable AC power was reasonable and
    well-supported by the statute’s text, structure, purpose, and
    legislative history.
    ii.     Arbitrary and Capricious Challenges
    The Utilities raise several other arguments, none of which
    compels a different result than their first. First, the Utilities
    claim the Commission acted arbitrarily and capriciously by
    granting Broadview’s application and ignoring errors on one of
    Broadview’s form submissions. The Commission requires that
    all qualifying facility applicants complete its Form 556. See 
    18 C.F.R. § 292.207
    (a)(1), (b)(2). That form provides a formula
    for calculating the facility’s maximum net power production
    capacity, starting with the “maximum gross power production
    capacity at the terminals of the individual generator(s)” and
    subtracting out certain enumerated figures, including electrical
    losses and power used to run the facility’s equipment. FERC
    Form No. 556. When asked for the “maximum gross power
    production capacity at the terminals of the individual
    generator(s),” Broadview, in one submission, reported a value
    of approximately 82.5 MW, while the Utilities claim the
    correct value was 160 MW. Because of that error, the Utilities
    claim the Commission could not grant Broadview’s
    application.
    This argument fails because it treats an applicant’s
    completion of Form 556—a tool meant to aid the Commission
    in its eligibility determination—as itself determinative. As the
    Commission explained in its March 2021 Order, “Form No.
    556 was always intended to be a flexible tool . . . to submit
    11
    information relevant to whether a facility meets the
    requirements to be considered a [qualifying facility].” 
    174 FERC ¶ 61,199
    , at 61,800. Even assuming the correct input on
    the form was 160 MW, Broadview explained its facility’s novel
    setup and why its “maximum net power production capacity”
    was 80 MW. The Commission’s decision to treat Broadview’s
    Form 556 submissions as helpful for determining, but not
    dispositive of, the facility’s eligibility was not arbitrary or
    capricious.
    The Utilities also argue the Commission’s decision to treat
    the solar array and battery as a single facility was arbitrary and
    capricious. Because the Commission’s decision to do so was
    not inconsistent with the statutory text nor the Commission’s
    own precedent, this argument also fails.
    When determining whether a facility is eligible for
    qualifying facility status, the Commission must look at the
    combined power production capacity of “facilities located at
    the same site.” 
    16 U.S.C. § 796
    (17)(A)(ii); see also 
    18 C.F.R. § 292.204
    (a)(1)–(2). As we have discussed, the Commission’s
    interpretation of “facility” to encompass all the components
    working together to produce grid-usable AC power was
    reasonable. But standing on its own, Broadview’s battery can
    store only DC power and cannot deliver any usable power to
    the grid. Accordingly, the battery is not a separate “facility”
    under the Commission’s reasonable interpretation of the
    statutory text.
    Citing Luz Development & Finance Corp., 
    51 FERC ¶ 61,078
     (1990), the Utilities argue that Broadview’s battery
    must be considered a separate facility and its capacity
    aggregated with that of the solar array or inverters. But Luz
    merely recognized that a battery can be a standalone qualifying
    facility, 
    id. at 61,172
    ; that possibility does not compel the result
    12
    that it must be a separate facility. The battery in Luz was used
    to store energy purchased from the grid until it was later resold
    during periods of higher demand, 
    id. at 61,168
    , and is easily
    distinguishable from Broadview’s battery that stores DC power
    until it can be sent through the inverters and transformed into
    grid-usable AC power.
    Finally, the Utilities challenge the Commission’s decision
    to look at Broadview’s instantaneous net power output and not
    its power output over time. The statute measures “power
    production capacity” in “megawatts.” But power production
    over time is measured in “megawatt-hours.” Rather than being
    arbitrary and capricious, the Commission’s focus on
    instantaneous power production adhered to the statutory
    language.
    B. SEIA’s Petitions
    Turning now to SEIA’s petitions for review of the
    Commission’s denial of its motion to intervene, “[o]ur analysis
    begins and ends with consideration of our jurisdiction.”
    Swanson Grp. Mfg. LLC v. Jewell, 
    790 F.3d 235
    , 239 (D.C. Cir.
    2015).
    For this Court to have jurisdiction, the plaintiff must have
    standing.     “The ‘irreducible constitutional minimum of
    standing contains three elements’: (1) the plaintiff must have
    suffered injury in fact, an actual or imminent invasion of a
    legally protected, concrete and particularized interest; (2) there
    must be a causal connection between the alleged injury and the
    defendant’s conduct at issue; and (3) it must be ‘likely,’ not
    ‘speculative,’ that the court can redress the injury.” Ctr. for
    Law & Educ. v. Dep’t of Educ., 
    396 F.3d 1152
    , 1157 (D.C. Cir.
    2005) (quoting Lujan v. Defs. of Wildlife, 
    504 U.S. 555
    , 560–
    61 (1992)).
    13
    SEIA fails on the first requirement as it has not suffered an
    Article III injury-in-fact. SEIA’s claimed injury is that it was
    “effectively precluded” from defending the net output, or send-
    out, approach in the Commission’s adjudication of
    Broadview’s application. Pet. Br. at 9–10. According to SEIA,
    any reconsideration of that approach was likely to occur, if at
    all, during the Commission’s contemporaneous rulemaking or
    the ensuing Ninth Circuit litigation. Because SEIA failed to
    anticipate FERC’s decision to reconsider the send-out
    approach in the Broadview adjudication, it also failed to timely
    intervene in that proceeding and thus could not participate to
    defend the approach.
    At the outset, it should be noted that agencies have “very
    broad discretion to decide whether to proceed by adjudication
    or rulemaking.” Conf. Grp., LLC v. FCC, 
    720 F.3d 957
    , 965
    (D.C. Cir. 2013). The Commission’s decision to consider the
    send-out approach in the Broadview adjudication, rather than
    through the rulemaking process, was within the bounds of its
    discretion. SEIA’s claimed injury presupposes that it had a
    right to participate in any proceedings regarding the send-out
    approach. It did not. “[T]he mere fact that an adjudication
    creates a precedent that could harm a non-party does not create
    the injury-in-fact required for Article III standing.” 
    Id. at 959
    .
    SEIA’s failure to timely intervene is the result of its own
    mistaken judgment. The effect of that mistake—SEIA’s
    inability to participate in the Commission’s proceedings—does
    not give rise to an Article III injury. Accordingly, its petitions
    are dismissed.
    14
    CONCLUSION
    For the reasons stated above, we deny the Utilities’
    petitions and dismiss SEIA’s petitions.
    WALKER, Circuit Judge, concurring in part and dissenting in
    part:
    The Public Utility Regulatory Policies Act gives lucrative
    benefits to small facilities that produce solar power. It defines
    them as facilities with a “power production capacity” of no
    more than 80 megawatts. 
    16 U.S.C. § 796
    (17)(A)(ii).
    Broadview is a solar-power facility. At its peak, it can pro-
    duce up to 130 megawatts of useful power. So it is not a “small
    facility.”
    Because the Federal Energy Regulatory Commission con-
    cluded otherwise, I would grant the petitions for review and
    vacate FERC’s decision.
    I. Background
    A. The Public Utility Regulatory Policies Act
    The Public Utility Regulatory Policies Act encourages
    companies to produce renewable energy. See 16 U.S.C.
    § 824a-3(a); see generally FERC v. Mississippi, 
    456 U.S. 742
    ,
    745-46, 750-51 (1982) (describing the Act’s history).
    To achieve that goal, the Act gives extraordinary benefits
    to “small power production facilit[ies].”            
    16 U.S.C. § 796
    (17)(A). Those facilities produce electricity from “bio-
    mass, waste, renewable resources, [or] geothermal resources.”
    
    Id.
     § 796(17)(A)(i). The Act exempts them from several regu-
    latory burdens. Id. § 824a-3(e)(1) (directing FERC to make
    rules exempting “small power production facilities” from reg-
    ulation under various statutes). And it guarantees them a viable
    market by forcing public utilities to buy power that small facil-
    ities produce. 16 U.S.C. § 824a-3(a)(2), (b).
    2
    Requiring public utilities to purchase all the power pro-
    duced by small facilities is strong medicine. It can force them
    to buy power that they do not need or to buy power at an above-
    market price. That cost is passed on to consumers. Powering
    America: Reevaluating the Public Utility Regulatory Policies
    Act’s Objectives and its Effects on Today’s Consumers: Hear-
    ing Before the H. Subcomm. on Energy & Commerce, 115th
    Cong. 84 (2017) (testimony of Terry L. Kouba, Vice President,
    Alliant Energy).
    Thus, the Act’s definition of “small facility” plays a key
    role in the statutory scheme: It keeps the mandatory-purchasing
    regime within bounds. The broader the definition of “small fa-
    cility,” the greater the number of power plants that get special
    regulatory treatment under the Act.
    The Act defines “small facility” as a “facility” with a
    “power production capacity” of no more than 80 megawatts.
    Id. § 796(17)(A)(ii).
    B. Broadview’s Design
    Broad Reach Power makes solar and wind energy in Cali-
    fornia, Montana, Texas, Utah, and Wyoming. Its complex in
    Yellowstone County, Montana cost at least $2 billion to build.
    In 2019, the Montana Complex could deliver 620 megawatts of
    power. That is only slightly less than the amount of power pro-
    duced by the Hoover Dam in 1939, when it became the world’s
    largest hydroelectric facility. The Story of the Hoover Dam,
    Bureau       of     Reclamation        (July    13,     2022),
    https://perma.cc/6JWN-BY77.
    In 2019, the Montana Complex contained four separate but
    similar solar-power projects. One of them is called Broad-
    view I.
    3
    Broadview includes a solar array, a battery, and inverters.
    With 470,000 solar panels, its solar array produces up to 160
    megawatts of direct-current power. The battery stores some of
    those megawatts. And the inverters convert up to 80 mega-
    watts from DC power to alternating-current power. Because
    the electric grid accepts only AC power, inversion makes the
    power ready for the grid to receive it.
    Depending on the time of day, Broadview’s components
    serve different purposes. During the day, the solar array sends
    80 megawatts of power to the inverters and charges the battery.
    But at night, it can’t generate power. That’s when the battery
    matters most. At night, it sends stored power to the inverters
    and then on to the grid. With the battery, Broadview can de-
    liver more power to the grid than it could without it.
    C. FERC’s Decision
    In 2019, Broadview asked FERC to certify it as a “small
    facility.” It argued that its “power production capacity” was
    not greater than 80 megawatts because its inverters can send
    only 80 megawatts to the grid at once.             
    16 U.S.C. § 796
    (17)(A)(ii). 1
    FERC initially denied Broadview’s application, but it re-
    versed course on rehearing. According to FERC, the Public
    Utility Act’s definition of “small facility” is ambiguous
    1
    Because Broadview is more than one mile apart from the other fa-
    cilities in the Montana Complex, FERC analyzes it separately under
    the small-facility rule. 
    18 C.F.R. § 292.204
    (a)(1)-(2); see also Order
    re. Broadview Solar III, 
    2021 WL 3641570
     (Aug. 13, 2021) (accept-
    ing withdrawal of an application for small-facility status for another
    plant in Montana Complex).
    4
    because the statute “neither defines the terms ‘facility’ and
    ‘power production capacity,’ nor explains how the Commis-
    sion is supposed to ascertain the ‘power production capacity’
    of any particular ‘facility.’ ” JA 200. FERC decided to inter-
    pret “power production capacity” to mean the “maximum out-
    put that the facility can produce for the electric [grid].” JA 201.
    Two intervenors, Northwestern Energy and the Edison
    Electric Institute, petitioned for this Court’s review. If Broad-
    view is a small facility, the Public Utility Act’s mandatory-pur-
    chasing rule will force Northwestern and some of Edison’s
    members to buy Broadview’s power — even if they don’t need
    it.
    II. Chevron
    The majority opinion captures the central issue: “The par-
    ties’ dispute in this case turns on the meanings of ‘facility’ and
    ‘power production capacity’ in 
    16 U.S.C. § 796
    (17)(A). [The
    Public Utility Act] does not define these terms. In plain lan-
    guage, a facility’s ‘power production capacity’ is the maximum
    amount of power that the facility can produce. But the statute
    does not state whether the relevant capacity is that of the indi-
    vidual subcomponent generating DC power, i.e., the solar ar-
    ray, or of all the facility’s components working together to pro-
    duce grid-usable AC power, which would include the invert-
    ers.” Majority Op. 6-7.
    I agree with that summary. The statute does not expressly
    state whether “power production capacity” includes “all the fa-
    cility’s components working together.” But a lack of express
    language does not mean that the statute has no answer to the
    question presented. I would not so quickly conclude, as the
    Court’s next sentence does, that “Congress has not spoken to
    the issue” and so we “must defer to any reasonable agency
    5
    interpretation” under Chevron v. Natural Resources Defense
    Council, 
    467 U.S. 837
     (1984). Majority Op. 7.
    That is the path of “Chevron maximalism.” Buffington v.
    McDonough, 
    143 S. Ct. 14
    , 21 (2022) (Gorsuch, J., concurring
    in denial of certiorari). When no express text makes the answer
    immediately obvious, some maximalists make a beeline to
    agency deference — before any inquiry into statutory struc-
    ture, cross-references, context, precedents, dictionaries, or can-
    ons of construction. Then, they use the tools of statutory inter-
    pretation not to find the best reading of the text but instead to
    test whether the agency’s interpretation is “reasonable.” 
    Id. at 20
    .
    On the D.C. Circuit, Chevron maximalism is alive and well.
    See, e.g., Loper Bright Enterprises, Inc. v. Raimondo, 
    45 F.4th 359
    , 369 (D.C. Cir. 2022) (“some question” about the meaning
    of a statute is enough to trigger Chevron deference); American
    Hospital Association v. Azar, 
    967 F.3d 818
     (D.C. Cir. 2020)
    (relying heavily on Chevron), rev’d sub nom American Hospi-
    tal Association v. Becerra, 
    142 S. Ct. 1896
    , 1906 (2022) (not
    mentioning Chevron).
    But the Supreme Court’s recent decisions repudiate maxi-
    malism. Indeed, the Court has not deferred to an agency under
    Chevron since 2016. See, e.g., Becerra v. Empire Health Foun-
    dation, 
    142 S. Ct. 2354 (2022)
     (not mentioning Chevron); Na-
    tional Federation of Independent Business v. OSHA, 
    142 S. Ct. 661 (2022)
     (same); BNSF Railway Co. v. Loos, 
    139 S. Ct. 893 (2019)
     (same). Instead, the Court has policed the limits of def-
    erence to agencies. See, e.g., West Virginia v. EPA, 
    142 S. Ct. 2587 (2022)
    .
    The most important limit is found in Chevron itself: “If a
    court, employing traditional tools of statutory construction,
    6
    ascertains that Congress had an intention on the precise ques-
    tion at issue, that intention is the law and must be given effect.”
    Chevron, 
    467 U.S. at
    843 n.9. In other words, courts must try
    every tool of statutory construction before declaring the text
    ambiguous and proceeding to agency deference. If they do,
    they “will almost always reach a conclusion about the best in-
    terpretation” of the statute, thus resolving any ambiguity. Ki-
    sor v. Wilkie, 
    139 S. Ct. 2400
    , 2448 (2019) (Kavanaugh, J.,
    concurring); see also SAS Institute Inc. v. Iancu, 
    138 S. Ct. 1348
    , 1358 (2018) (quoting Chevron, 
    467 U.S. at
    843 n.9)
    (“Even under Chevron, we owe an agency’s interpretation of
    the law no deference unless, after ‘employing traditional tools
    of statutory construction,’ we find ourselves unable to discern
    Congress’s meaning.”).
    True, Congress may leave “a gap for the agency to fill.”
    Chevron, 
    467 U.S. at 843
    . “For example, Congress might [di-
    rect] an agency to issue rules to prevent companies from dump-
    ing ‘unreasonable’ levels of certain pollutants. In such a case,
    what rises to the level of ‘unreasonable’ is a policy decision.”
    Brett M. Kavanaugh, Fixing Statutory Interpretation, 
    129 Harv. L. Rev. 2118
    , 2152 (2016). Where an agency uses its
    expertise to fill such a gap, courts should not second guess the
    agency’s decision. 
    Id.
    But today’s case is different. The Public Utility Act does
    not invite FERC to fill a policy gap. Instead, as FERC recog-
    nizes, the meaning of the statute’s technical language “turns on
    legal principles of the sort that a court usually [applies] — i.e.,
    principles of statutory interpretation — and not determinations
    specifically entrusted to an agency’s expertise.” FERC Br. 40
    n.9 (cleaned up). And courts should not defer when a statute’s
    meaning can be resolved using normal interpretive tools. “The
    judiciary is the final authority on issues of statutory construc-
    tion.” Chevron, 
    467 U.S. at
    843 n.9.
    7
    So here there is every reason to resist the temptation “ha-
    bitua[lly] to defer to the interpretive views of [the] agenc[y].”
    Valent v. Commissioner of Social Security, 
    918 F.3d 516
    , 525
    (6th Cir. 2019) (Kethledge, J., dissenting). Instead, we can de-
    cide this case by applying, in FERC’s words, the “legal princi-
    ples of the sort that a court usually [applies] — i.e., principles
    of statutory interpretation.” FERC Br. 40 n.9 (cleaned up).
    That approach follows the Supreme Court’s recent Chevron
    caselaw and avoids further entrenching a vertical split between
    how the Supreme Court and lower courts apply Chevron. 2
    III. Broadview Is Not a “Small Facility”
    Applying the normal tools of statutory interpretation,
    Broadview is not a “small facility” under the Public Utility Act
    because its “power production capacity” is greater than 80
    megawatts.
    A. “Facility”
    Start with the term “facility.” 
    16 U.S.C. § 796
    (17)(A). A
    facility is “something . . . that is built, installed, or established
    to serve a particular purpose.” Facility (def. 4b), Merriam-
    2
    Though the Supreme Court has given up on Chevron maximalism
    (and perhaps on Chevron altogether), lower courts have not. Be-
    tween 2003 and 2013, lower courts applied Chevron in 74.8% of stat-
    utory interpretation cases involving agencies and reached step two
    65.7% of the time. Kent H. Barnett & Christopher J. Walker, Chev-
    ron in the Circuit Courts, 
    116 Mich. L. Rev. 1
    , 29, 33 (2017). That
    trend has continued since then. In 2020 and 2021, circuit courts ap-
    plied Chevron 84.5% of the time and reached step two in 59.2% of
    those cases. See Brief of the Cato Institute and Liberty Justice Center
    as Amicus Curiae in Support of Petitioners at 21, Loper Bright v.
    Raimondo, No. 22-451 (2022) (supporting petition for certiorari).
    8
    Webster (2023). The statute’s focus on a “facility” suggests
    that we should assess the production capacity of a power plant
    as a whole, not the capacity of an individual component.
    That rules out a few possibilities.
    First, it tells us that we should not look only at the capacity
    of Broadview’s 160-megawatt solar array. That approach
    would ignore the facility’s other components — for instance,
    the inverters that limit the array’s output to the grid.
    Second, it tells us that we should not exclude the power
    used to charge the facility’s battery. The battery is part of the
    facility. So refusing to count power that the solar array sends
    to the battery fails to give full meaning to the word “facility.”
    FERC says we shouldn’t count power sent to the battery
    because it is “not useful to anybody.” See Oral Arg. Tr. 31.
    But a battery like Broadview’s lets a solar facility send power
    to the grid at times when it otherwise could not. By allowing
    the facility to deliver power at night, the battery “increase[s]
    [Broadview’s] ability to provide reliable and/or timely service
    to . . . customers.” JA 54 (Pasley Affidavit).
    The battery also makes Broadview more efficient. A solar-
    power facility without a battery sends to the grid “approxi-
    mately 25 to 30 percent” of the maximum power its array could
    theoretically generate each day. 
    Id.
     With the battery, Broad-
    view sends “approximately 35 to 40 percent,” 
    id.,
     because it is
    “capable of sustaining its maximum output for additional hours
    in the day,” JA 23. That increased efficiency makes the facility
    more profitable. See Christopher Cerny, A Broad View of
    Broadview Solar: How FERC’s Whiplash-Inducing Orders Ex-
    pand the Scope of PURPA, 23 Minn. J.L. Sci. & Tech. 363, 406
    (2022).
    9
    In short, the battery is useful. It lets Broadview make more
    money by prolonging its maximum output.
    B. “Power Production Capacity”
    Turn next to the phrase “power production capacity.”
    1. “Power”
    Power means “a source or means of supplying energy, es-
    pecially[ ] electricity.” Power (def. 6), Merriam-Webster
    (2023). “Power” includes both DC power and AC power. See
    Chemeheuvi Tribe of Indians v. Federal Power Commission,
    
    489 F.2d 1207
    , 1217 (D.C. Cir. 1973) (discussing history of
    power transmission). So both the DC power used to charge the
    battery and the AC power sent directly to the grid count as
    “power.”
    Yet FERC claims that only the 80 megawatts of AC power
    sent to the grid should count as Broadview’s power-production
    capacity. That adds an atextual limit that Congress didn’t
    adopt. The Public Utility Act says “power production capac-
    ity,” not “AC power production capacity.” And Congress is
    perfectly capable of saying “AC” when it wants to. See, e.g.,
    26 U.S.C. § 48E(a)(2)(A)(ii) (defining a “qualified facility” as
    one “with a maximum net output of less than 1 megawatt (as
    measured in alternating current))” (emphasis added).
    2. “Production”
    After “power” comes “production.” To “produce” some-
    thing is to “create” it, or to “cause [it] to accrue.” Produce
    (defs. 6 & 7), Merriam-Webster (2023). Another apt synonym
    is to “generate.” See Facebook, Inc. v. Duguid, 
    141 S. Ct. 10
    1163, 1171-72 (2021) (noting the “close[ ] connect[ion]” be-
    tween the verb “produce” and the noun “generator”).
    Power sent to a battery like Broadview’s is created and does
    accrue. Before the sun’s rays hit Broadview’s array, the battery
    is empty. It is charged when the facility converts solar energy
    into useful power. If Broadview did not “produce” the power
    used to charge the battery, what did? 3
    Consider what happens when the battery charges. Broad-
    view uses a lithium-ion battery. Charging that battery prompts
    a chemical reaction, causing lithium ions to move within the
    battery. How Does a Lithium-Ion Battery Work?, Energy.gov
    (Sept. 14, 2017), https://perma.cc/CUA8-Y9UK (during charg-
    ing “[l]ithium ions are released by the cathode and received by
    the anode”). Without power, that chemical reaction could not
    happen. So Broadview must “produce” the power used to
    charge the battery.
    3. “Capacity”
    In the statute’s context, “capacity” means “the maximum
    amount of power that the facility can produce.” Majority Op.
    6-7; see also Capacity (def. 5), Merriam-Webster (2023) (de-
    fining “capacity” as “maximum output”).
    But here, FERC rewrites the statute. It says “capacity” in-
    cludes only the power that a facility supplies to the electric grid.
    3
    Some power at facilities like Broadview is lost to inefficiencies dur-
    ing production. FERC allows power plants to deduct those “electri-
    cal losses” from their power production capacity. See JA 210. So if
    Broadview had a 160-megawatt array, 80-megawatt inverters, and no
    battery, it would count as a “small facility” — albeit an inefficient
    one that loses half of its potential output during production.
    11
    Yet that changes “power production capacity” to “power deliv-
    ery capacity.” And the word “production” means something
    different from “delivery.” See Deliver (def. 5), Merriam-Web-
    ster (2023) (“[T]o send . . . to an intended target or destina-
    tion.”). 4
    To its credit, FERC conceded at oral argument that “power
    production capacity” would likely include power never deliv-
    ered to the grid if it is used “on site” for a “useful” purpose like
    powering an on-site factory. Oral Arg. Tr. 30. But that con-
    cession just highlights the problem with FERC’s approach:
    Charging a battery like Broadview’s is a useful purpose.
    C. Broadview’s “Power Production Capacity”
    Broadview has the capacity to produce 130 megawatts of
    power. It produces 80 megawatts of inverted AC power that is
    delivered to the grid while producing 50 megawatts of not-yet-
    inverted DC power to charge its battery. 5 Because “power”
    4
    FERC conflated “production” and “delivery” in its rehearing order,
    although its counsel wisely retreated from that approach on appeal.
    Compare JA 201 (FERC: “ ‘ production’ and ‘delivery’ . . . are over-
    lapping”), with Oral Arg. Tr. 33 (FERC: “we’re not talking about
    delivery”); 
    id. at 37
     (“[Y]ou’re not depending on a conflation of the
    words production and delivery — right? [FERC:] Correct.”).
    5
    The record is unclear on the amount of power the battery can re-
    ceive from the array. But the parties agree that the battery can take
    in up to 50 megawatts. Compare Edison Br. 10 n.3 (“The Broadview
    Project’s battery can be charged at the same rate as it dis-
    charges — i.e., it can receive and send out 50 megawatts of energy
    each hour.”), with FERC Br. 14 (“[U]p to 50 megawatts of power is
    diverted to battery storage for later release.”).
    12
    includes AC and DC power, Broadview’s power production ca-
    pacity is the sum of the two:
    80 + 50 = 130
    Consider an analogy. Every weekday, a lumberjack cuts
    down two trees and chops them into sellable timber. But he
    has a small truck and can take only one tree’s worth of timber
    to market daily. What is the lumberjack’s daily timber “pro-
    duction capacity”? Two trees. Every day he works, he can turn
    two trees into sellable timber. (Maybe he delivers some of the
    other trees on the weekends.)
    Broadview is similar. When the sun is out, Broadview pro-
    duces 80 megawatts of power for the inverters and 50 mega-
    watts of power for the battery — the equivalent of the lumber-
    jack’s two trees. Like the lumberjack’s second tree, the 50
    megawatts of power sent to the battery is still produced even
    though it isn’t immediately delivered to the market for use on
    the grid. The key is that the 50 megawatts produced by the
    solar array and sent first to the battery is not wasted by the fa-
    cility. Those 50 megawatts end up on the grid — just like the
    80 megawatts sent from the solar array directly to the inverters.
    That gives Broadview a power production capacity of 130
    megawatts. And because the power production capacity of a
    “small facility” cannot exceed 80 megawatts, Broadview is not
    a “small facility.” 
    16 U.S.C. § 796
    (17)(A).
    13
    IV. Conclusion
    The following three facts are uncontested:
    1. When the Public Utility Act says “power,” it does not
    specify between AC power and DC power.
    2. Broadview can send 80 megawatts of AC power di-
    rectly to the grid for sale via the inverters.
    3. At the exact same moment, up to 50 megawatts of DC
    power goes straight to the battery, then later to the in-
    verters, and then on to the grid for sale.
    Because Broadview can produce 80 megawatts for its in-
    verters while it simultaneously produces 50 megawatts for its
    battery, Broadview’s facility is capable of producing more than
    80 megawatts of power. So it is too large to be a “small facil-
    ity.”
    For that reason, I would grant the petitions, vacate the re-
    hearing orders, and remand to FERC for reconsideration. 6
    6
    I agree with the majority that Solar Energy lacks standing to chal-
    lenge FERC’s denial of its motion to intervene.