Northern Virginia Electric Co v. FERC ( 2019 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 18, 2019           Decided December 20, 2019
    No. 17-1262
    NORTHERN VIRGINIA ELECTRIC COOPERATIVE, INC.,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    Consolidated with 17-1265, 18-1230, 18-1234
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    Adrienne E. Clair argued the cause for petitioners. With
    her on the briefs were Rebecca L. Shelton, Alan I. Robbins, and
    Debra D. Roby.
    Elizabeth E. Rylander, Attorney, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were Robert H. Solomon, Solicitor, and
    Lona T. Perry, Deputy Solicitor. Anand Viswanathan,
    Attorney, entered an appearance.
    2
    Christopher R. Jones argued the cause for intervenor
    Virginia Electric and Power Company. With him on the brief
    was Miles H. Kiger.
    Sean T. Beeny, Denise C. Goulet, and Phyllis G. Kimmel
    were on the brief for intervenor North Carolina Electric
    Membership Corporation in support of respondent.
    Before: GARLAND, Chief Judge, WILKINS, Circuit Judge,
    and WILLIAMS, Senior Circuit Judge.
    Opinion for the Court filed by Senior Circuit Judge
    WILLIAMS.
    WILLIAMS, Senior Circuit Judge: In the mid to late 2000s,
    the Virginia Electric and Power Company (known in this case
    by its trade name, “Dominion”) sought to construct three
    projects to upgrade its electricity transmission grid. The state
    of Virginia required Dominion to place the new transmission
    wires underground rather than use cheaper overhead wiring,
    thereby increasing the cost of the three projects from about $84
    million to $233 million in total. Dominion serves customers in
    both Virginia and North Carolina. This case involves a simple
    question: How should the cost of undergrounding be allocated
    among Dominion’s customers?
    In a series of proceedings, the Federal Energy Regulatory
    Commission concluded that Dominion’s Virginia customers,
    but not its North Carolina customers, should bear those costs;
    the evidence showed that Virginia customers benefited from
    the undergrounding, while no evidence showed that North
    Carolina customers benefited. In the Commission’s words, this
    decision represented “a limited exception” to a general
    principle that all of a utility’s customers should share the costs
    of upgrading the grid. Old Dominion Elec. Coop., 146 FERC
    61,200 ¶ 52 (2014) (“Allocation Order”), reh’g denied, 161
    3
    FERC 61,055 (2017) (“First Order on Rehearing”); see also
    Old Dominion Elec. Coop., 161 FERC 61,054 (2016), reh’g
    denied, 164 FERC 61,006 (2018) (“Second Order on
    Rehearing”).
    In this petition, Virginia power wholesalers who buy
    electricity from Dominion challenge the Commission’s
    decision on procedural and substantive grounds. None of them
    persuades us. We tackle first the procedural theories, then the
    substantive ones.
    I.
    The petitioners argue: (1) that the Commission did not
    properly invoke its power under § 206 of the Federal Power
    Act, 16 U.S.C. § 824e; (2) that the Commission failed to
    provide adequate notice of its intent to modify Dominion’s filed
    rate; and (3) that the Commission’s administrative law judge
    misinterpreted a Commission order and thereby improperly
    cabined the scope of an evidentiary hearing.
    1. The claim that a proper § 206 proceeding was missing
    turns on special rules relating to Commission supervision of
    formula rates—the sort used by Dominion. The formula rate,
    filed as a tariff with the Commission, identifies the categories
    into which Dominion’s costs fall. With the formula in place,
    Dominion files an annual update informing the Commission
    and its customers of the projected costs for each category in the
    formula. Unless modified by the Commission, Dominion
    recovers the costs under the formula rate, subject to a later true-
    up procedure. See Virginia Elec. & Power Co., 123 FERC
    61,098 ¶ 6 (2008) (“Order Approving Formula”).
    At least in Dominion’s case, the tariff creates a procedure,
    known as a “Formal Challenge,” through which a customer can
    challenge the legitimacy of inputs. See 
    id. ¶ 16
    (describing the
    4
    Formal Challenge process). (We use initial capitals for the
    name, to emphasize that it is a word of art and not, so far as we
    can determine, based on any especially high level of formality.)
    Although the parties here have spoken and written as if such a
    Formal Challenge were located under § 206, see, e.g., Oral
    Argument at 8:23, it seems more accurately akin to a
    continuation of the § 205 proceeding in which the utility files
    its formula rate. See 16 U.S.C. § 824d. That’s because the
    annual update supplements the utility’s initial § 205 filing,
    which is simply a formula without the necessary inputs.
    Consequently, in a Formal Challenge, the utility not the
    complainant bears the burden of proving the justness and
    reasonableness of its inputs, just as the utility does when it first
    files the formula rate under § 205. See Order Approving
    Formula, 123 FERC 61,098 ¶ 47 (noting that those who launch
    a Formal Challenge to Dominion’s annual update do not bear
    the burden of proof); cf. Midwest Indep. Transmission Sys.
    Operator, Inc., 143 FERC 61,149 ¶ 120 n.199 (2013) (citing
    § 205 on this point regarding a different tariff). In contrast, in
    a conventional § 206 proceeding, the complainants or the
    Commission must prove the unjustness and unreasonableness
    of the utility’s rate. See 16 U.S.C. § 824e(b) (placing the
    burden of proof “upon the Commission or the complainant”).
    For purposes of this case, there is a further key distinction
    between a Formal Challenge and a § 206 proceeding: In a
    Formal Challenge proceeding, a party cannot advance “attacks
    on the formula rate itself” and cannot advocate “that expenses
    should be treated differently from how the formula prescribes.”
    Delmarva Power & Light Co., 160 FERC 61,102 ¶ 19 (2017);
    see also Ameren Ill. Co., 156 FERC 61,209 ¶ 71 (2016).
    When Dominion filed its formula rate in 2008, it did not
    distinguish between its Virginia and North Carolina customers.
    In its 2010 annual update, Dominion proposed including the
    undergrounding costs at issue here as inputs into the formula
    5
    rate for all its customers. On March 17, 2010, Dominion’s
    customers in both Virginia and North Carolina objected and
    instituted a Formal Challenge to the undergrounding costs’
    inclusion. By its own terms, their complaint did not “seek [] to
    challenge the formula rate, but rather [to] challenge only the
    inputs into the formula rate for the 2010 Annual Update.” J.A.
    52.
    The Virginia customers now argue that because they
    launched a Formal Challenge to the annual update’s inputs—
    and not a standard § 206 proceeding—the Commission lacked
    the statutory authority to modify the formula rate itself so as to
    saddle the Virginia but not North Carolina customers with
    costs.
    But in fact the Commission broadened the scope of the
    complaint proceedings. On March 24, 2010, a week after
    Dominion’s customers filed their Formal Challenge, Dominion
    responded by filing its own proposal under § 205 to assign
    those costs directly to its customers in case the Commission
    determined that Dominion could not include the costs in its
    existing formula rate. See Virginia Elec. & Power Co., 131
    FERC 61,171 ¶¶ 1, 4, 18 (2010) (“May 20, 2010 Order”). To
    make sure that there was no meaningful gap between any grant
    of relief to the customers and its proposed recovery system,
    Dominion asked the Commission to waive the usual 60-day
    notice requirement (see § 205(d)) and establish a refund
    effective date that would allow it to collect a revised rate (if
    needed) as of March 25, 2010. On May 20, 2010, the
    Commission       “reject[ed]    Dominion’s     [proposal]    as
    unnecessary,” May 20, 2010 Order ¶ 18, explaining:
    The effective date for a change in the allocation of
    costs, i.e., ordering a different allocation of costs
    among customers as compared to the current
    allocation of costs, if required at all, will be
    6
    determined in the Complaint proceeding [the Formal
    Challenge] based on the requirements of section 206
    of the FPA as applicable to these circumstances.
    
    Id. (emphasis added).
    In announcing that these proceedings would determine a
    refund effective date for “a different allocation of costs among
    customers as compared to the current allocation of costs,” the
    Commission said that it considered the Formal Challenge
    procedures too limited and sought, on its own initiative, to
    invoke the broader powers of a conventional § 206 proceeding.
    See 16 U.S.C. § 824e (permitting the Commission to initiate a
    § 206 proceeding “upon its own motion”). Tellingly, the
    petitioners’ briefs never grapple with the language of the May
    20, 2010 Order. See Appellant Br. 44 (alluding to the First
    Order on Rehearing’s reference to the Commission’s rejection
    of Dominion’s § 205 filing but making no mention of the
    Commission’s initiation of its own proceeding under § 206 in
    the May 20, 2010 Order).
    At oral argument, petitioners’ counsel argued that the
    Commission could not possibly have acted to initiate a § 206
    proceeding, because the Commission eventually set the refund
    effective date as March 17, 2010, the day that the complainants
    filed their Formal Challenge, see Old Dominion Elec. Coop.,
    133 FERC 61,009 ¶ 36 (2010) (“October 2010 Order”). Where
    the Commission files its own § 206 proceeding, the refund
    effective date may “not be earlier than the date of the
    publication by the Commission of notice of its intention to
    initiate such proceeding.” 16 U.S.C. § 824e(b). By contrast, in
    a proceeding on a party’s complaint, the refund effective date
    may be as early as the date of the complaint’s filing. See 
    id. Here, the
    Commission’s May 20, 2010 Order post-dated the
    complaint by about three months, and the Commission chose
    the earlier date of the complaint as the refund effective date.
    7
    From the Commission’s use of this earlier date, the petitioners
    would have us infer that the Commission never initiated its own
    § 206 proceeding.
    Whatever merit may lie in this argument, the petitioners
    advanced it far too late. It does not appear in their briefs before
    us. See Davis v. District of Columbia, 
    793 F.3d 120
    , 127 (D.C.
    Cir. 2015) (“Generally, arguments raised for the first time at
    oral argument are forfeited.”). Nor, as far as we can tell, does
    it appear in an application for rehearing before the
    Commission. See 16 U.S.C. § 825l(b) (limiting judicial review,
    absent “reasonable ground,” to objections “urged before the
    Commission in the application for rehearing”); Save Our
    Sebasticook v. FERC, 
    431 F.3d 379
    , 382 (D.C. Cir. 2005)
    (noting that 16 U.S.C. § 825l(b)’s exhaustion requirement
    ensures that “a reviewing court” gains “the benefit of the
    agency’s expert view of why it thought the petitioner’s
    arguments failed”). We thus decline to address it.
    2. Petitioners next advance a related objection: As they
    see it, the Commission failed to provide the parties and the
    public adequate notice that it would consider requiring some,
    but not all, of Dominion’s customers to pay for the
    undergrounding. See Pub. Serv. Comm’n v. FERC, 
    397 F.3d 1004
    , 1012 (D.C. Cir. 2005) (noting that the Due Process
    Clause, the Administrative Procedures Act, and the Federal
    Power Act all require the Commission to provide notice). But
    the Commission’s May 20, 2010 Order placed everyone on
    notice from the very beginning that the Commission might
    allocate the costs differently between Dominion’s customers.
    
    See supra
    . That makes this case very different from Public
    Service Commission, the case on which petitioners principally
    rely. See Appellant Br. 40; Reply Br. 11–13. There, the
    Commission actively disclaimed its intention to adopt a
    particular policy, refused to develop a necessary factual record
    about the policy, but later reversed course and adopted the
    8
    policy anyway. See 
    id. at 1012.
    Here, by contrast, from May
    20, 2010 onward the Commission consistently contemplated
    ordering an allocation of costs different from the allocation in
    the filed formula rate.
    What’s more, the petitioners not only had notice but took
    advantage of the opportunity to litigate the cost allocation issue
    before the Commission. Consider the course of proceedings
    after the May 20, 2010 Order. In October 2010, the
    Commission issued an order concluding that the
    undergrounding costs “[do] not raise material issues of disputed
    fact.” October 2010 Order, 133 FERC 61,009 ¶ 35. As a result,
    the Commission “reserved” the “determination” for itself and
    directed the parties to brief the issue if they could not settle. 
    Id. They couldn’t.
    At this point, Dominion’s North Carolina customers
    argued they should not bear any of the costs of undergrounding,
    because the state of Virginia mandated undergrounding for
    “local aesthetic reasons” which did not benefit anyone in North
    Carolina. J.A. 659; see infra Part II. The Virginia customers
    responded, urging the Commission to reject the North Carolina
    proposal. The Commission concluded that it would not be just
    and reasonable to stick the North Carolina customers with the
    costs and sent the matter to an administrative law judge to
    determine the appropriate amount of costs for the Virginia
    customers to bear. See Allocation Order, 146 FERC 61,200
    ¶¶ 48–52.
    This sequence of events provided the petitioners adequate
    notice and process.
    3. This leads us to the third and final procedural objection.
    The petitioners argue that the Commission’s order instructed
    the ALJ to decide whether Dominion’s Virginia and North
    Carolina customers should bear the costs and to select a method
    9
    for assigning percentages of those costs to whoever would
    ultimately bear them. Thus, they say, it was error for the ALJ,
    approved by the Commission, to read the order as merely
    empowering the ALJ to determine the precise amount of costs
    to be born. See Old Dominion Elec. Coop., 154 FERC 63,014
    ¶ 36 (concluding “that the Commission has already decided the
    allocation issue”); Second Order on Rehearing, 164 FERC
    61,006 ¶¶ 45, 63 (affirming the ALJ’s interpretation of the
    order).
    The Commission’s order clearly refutes the claim. It stated
    that the North Carolina customers “have shown that it is not
    just and reasonable for wholesale transmission customers
    outside the Commonwealth of Virginia . . . to be allocated the
    incremental costs of undergrounding the Projects,” and
    provided three pages of explanation. Allocation Order, 146
    FERC 61,200 ¶¶ 48, 49–59. At the end of this discussion, the
    Commission then announced that “[t]he determination of the
    appropriate amount of undergrounding costs to be allocated to
    each [] customer for their Virginia loads in the Dominion Zone
    is a factual matter that cannot be properly calculated based on
    the filings made to date. The Commission will therefore
    establish a hearing, before an [ALJ], for the limited purpose of
    determining the appropriate assignment of those costs.” 
    Id. ¶ 56.
    The ALJ proceeded in full accord with this mandate.
    II.
    Finally, petitioners claim that the Commission acted
    arbitrarily by requiring Dominion’s Virginia customers to bear
    the costs of undergrounding. We see nothing arbitrary in its
    conclusion.
    The Commission has long adhered to the cost causation
    principle, under which a utility should assign costs to those
    customers who caused them or benefit from them. But “[w]hen
    10
    a system is integrated, any system enhancements are presumed
    to benefit the entire system.” W. Mass. Elec. Co. v. FERC, 
    165 F.3d 922
    , 927 (D.C. Cir. 1999). Thus, in the mine run of cases,
    all customers on a grid benefit from—and share in—the costs
    of upgrading the grid. See 
    id. Here the
    Commission concluded that only Dominion’s
    Virginia customers benefited from the incremental cost of
    undergrounding the three projects. As a result, only the
    Virginia customers should bear those costs. This created “a
    limited exception to [the Commission’s] general policy that
    utilities do not directly assign individual cost items that are
    included in projects that have system-wide benefits.”
    Allocation Order, 146 FERC 61,200 ¶ 52; Second Order on
    Rehearing, 164 FERC 61,006 ¶ 17 (affirming, a second time on
    rehearing, the “narrowly-crafted exception”).
    Indeed, as the Commission recognized, its departure from
    its policy of having all customers pay for upgrading a grid here
    maintained consistency with the broader cost causation
    principle:     Though the benefits of conventional grid
    enhancement are shared throughout the grid, here Virginians
    uniquely caused and benefited from the undergrounding. See
    Second Order on Rehearing, 164 FERC 61,006 ¶ 28.
    Under § 206, the Commission of course bore the burden of
    proving that the existing cost allocation was unjust and
    unreasonable, see 16 U.S.C. § 824e(b), as it expressly
    acknowledged, see First Order on Rehearing, 161 FERC 61,055
    ¶ 30 n.75. Indeed, more than substantial evidence in the record
    supports the Commission’s conclusion that Virginians but not
    North Carolinians benefited from undergrounding the three
    projects—all located in Virginia. For instance, according to a
    report by a hearing officer for a Virginia body which heard
    testimony regarding undergrounding, “one hundred sixty-seven
    public witnesses” testified at a hearing in Leesburg, Virginia,
    11
    “the overwhelming majority” speaking in favor of
    undergrounding one of the three projects. J.A. 226. The
    witnesses pointed to benefits they believed undergrounding
    would afford them, including better aesthetics and avoidance of
    electromagnetic radiation. A second report recounted similar
    testimony regarding a different project from dozens of Virginia
    residents and public officials, including their statements of
    belief that undergrounding would lessen the negative impact on
    local property values and the tax base.
    The Commission also rested on the insistence of the
    Virginia legislature that Dominion underground all three
    projects. It noted that the costs were “a direct result of
    legislation [adopted by the Commonwealth of Virginia]. . .
    intended to benefit citizens of the Commonwealth of Virginia.”
    Allocation Order, 146 FERC 61,200 ¶ 50.
    The petitioners mainly contend that the Commission
    lacked affirmative evidence that North Carolinians didn’t
    benefit from the undergrounding. See, e.g., Reply Br. 22. But
    this ignores (1) the mountain of evidence that Virginians
    clamored for the undergrounding; (2) the Virginia legislature’s
    apparent intent to act for the benefit of its citizens; (3) the
    absence of any evidence that North Carolina customers caused
    or benefited from the undergrounding. Put it all together, and
    it adds up to substantial evidence that Virginians benefited from
    the undergrounding but North Carolinians did not.
    Finally, the petitioners—Dominion’s wholesale power
    customers—also complain that the Commission should have
    placed the cost on Dominion’s retail customers and not on the
    wholesale power companies who purchase service from
    Dominion. See Appellant Br. 62. But they offer no evidence
    that their Virginia retail customers benefit any less than
    Dominion’s Virginia retail customers, nor is there any obvious
    reason to think so.
    12
    * * *
    The petitions for review are
    Denied.
    

Document Info

Docket Number: 17-1262

Filed Date: 12/20/2019

Precedential Status: Precedential

Modified Date: 12/20/2019