City of Boston Delegation v. FERC ( 2018 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 19, 2017                 Decided July 27, 2018
    No. 16-1081
    CITY OF BOSTON DELEGATION,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    ALGONQUIN GAS TRANSMISSION, LLC, ET AL.,
    INTERVENORS
    Consolidated with 16-1098, 16-1103
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    Thomas S. Fitzpatrick argued the cause for petitioner City
    of Boston Delegation. With him on the briefs was Joshua S.
    Grossman.
    Carolyn Elefant argued the cause for petitioners
    Riverkeeper, Inc., et al. With her on the briefs were Jeffrey M.
    Bernstein, Rebecca F. Zachas, and Alexander English.
    2
    Ross R. Fulton, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on
    the briefs were James P. Danly, General Counsel, Robert H.
    Solomon, Solicitor, and Holly E. Cafer, Senior Attorney.
    Jeremy C. Marwell argued the cause for intervenor
    Algonquin Gas Transmission, LLC, et al. With him on the
    briefs were Anita R. Wilson, Michael B. Wigmore, Andrew N.
    Beach, and Steven E. Hellman.
    Before: HENDERSON and SRINIVASAN, Circuit Judges, and
    WILLIAMS, Senior Circuit Judge.
    Opinion for the Court filed by Circuit Judge SRINIVASAN.
    SRINIVASAN, Circuit Judge: In March 2015, the Federal
    Energy Regulatory Commission approved an application from
    Algonquin Gas Transmission, LLC, to undertake an upgrade to
    its natural gas pipeline system. The $972 million project would
    enable Algonquin to meet some of the increasing demand for
    natural gas in New England and reduce pricing volatility in the
    region.
    A number of parties now seek to challenge the
    Commission’s approval of Algonquin’s project. They allege,
    among other things, that the Commission erred in assessing the
    project’s environmental impacts, unreasonably relied on expert
    opinions concerning the project’s safety, and failed to
    recognize the bias of a third-party contractor. At the outset, we
    dismiss one party’s petition for review for want of standing.
    We deny the remaining petitions for review on the merits.
    3
    I.
    A.
    The Natural Gas Act grants the Federal Energy Regulatory
    Commission authority to regulate the interstate transportation
    of natural gas. 15 U.S.C. §§ 717b, 717c. To construct or
    operate an interstate natural gas pipeline, a company must
    obtain “a certificate of public convenience and necessity,” 15
    U.S.C. § 717f(c), known as a Section 7 certificate. The
    Commission will grant a Section 7 certificate “only if the
    public benefits from the project outweigh any adverse effects.”
    Certification of New Interstate Natural Gas Pipeline Facilities,
    
    88 FERC ¶ 61,227
    , at 61,750 (Sept. 15, 1999), clarified, 
    90 FERC ¶ 61,128
    , at 61,396-98 (Feb. 9, 2000), further
    clarified, 
    92 FERC ¶ 61,094
    , at 61,373-75 (July 28, 2000).
    As part of the process of issuing a Section 7 certificate, the
    Commission must satisfy the requirements of the National
    Environmental Policy Act (NEPA), 
    42 U.S.C. § 4321
     et seq.
    NEPA establishes an environmental review process under
    which federal agencies “identify the reasonable alternatives to
    [a] contemplated action and look hard at the environmental
    effects of their decisions.” Minisink Residents for Envtl. Pres.
    & Safety v. FERC, 
    762 F.3d 97
    , 102 (D.C. Cir. 2014)
    (alterations and internal quotation marks omitted). In the case
    of “major Federal actions significantly affecting the quality of
    the human environment,” NEPA calls for the relevant federal
    agency to prepare “a detailed” environmental impact statement.
    
    42 U.S.C. § 4332
    (2)(C).
    B.
    Algonquin Gas Transmission, LLC, operates a natural gas
    pipeline system that starts in New Jersey, runs north through
    4
    New York, Connecticut, and Rhode Island, and ends in
    Massachusetts. In light of increasing demand for natural gas in
    the New England area, Algonquin planned several discrete
    projects to increase the capacity of its pipeline system. One of
    those projects, the Algonquin Incremental Market Project
    (AIM Project), is the subject of the petitions for review we
    consider in this case.
    In February 2014, Algonquin applied to the Commission
    for authorization to construct the AIM Project. The proposal
    sought to replace 29.2 miles of existing pipeline with larger
    diameter pipe, construct 8.2 miles of new pipeline, build three
    new meter stations, and modify various other compressor and
    meter stations.
    Of particular relevance, the AIM project included a
    proposal to construct roughly five miles of new pipeline known
    as the West Roxbury Lateral, which would run adjacent to an
    active quarry outside of Boston. The project also sought to
    install larger-diameter replacement pipeline next to the Indian
    Point Energy Center, a nuclear facility in Westchester County,
    New York. Overall, the AIM Project would give Algonquin an
    additional 342,000 dekatherms per day of natural gas transport
    capacity from Ramapo, New York, to various cities in
    Connecticut, Rhode Island, and Massachusetts.
    In addition to the AIM Project, Algonquin is pursuing two
    other upgrades to its northeast pipeline system. Those ventures
    are known as the Atlantic Bridge Project and the Access
    Northeast Project. In the Atlantic Bridge Project, Algonquin
    seeks to create 132,705 dekatherms per day of capacity from
    New Jersey and New York to various points on its system, by
    replacing several miles of pipeline with larger-diameter pipes
    and constructing or modifying a number of compressor and
    meter stations. Algonquin applied for a Section 7 certificate
    5
    for Atlantic Bridge in October 2015, and the Commission
    granted the certificate in January 2017. Order Issuing
    Certificate, Algonquin Gas Transmission, LLC, 
    158 FERC ¶ 61,061
     (Jan. 25, 2017) (Atlantic Bridge Certificate Order). In
    the Access Northeast Project, Algonquin planned to install
    pipeline and modify facilities in order to provide natural gas to
    electric power plants in New England. Pre-filing review for the
    Access Northeast Project began in November 2015, but
    Algonquin withdrew the pre-filing application in June 2017.
    On January 23, 2015, the Commission issued its final
    environmental impact statement under NEPA for the AIM
    Project. On March 3, 2015, after receiving comments on the
    environmental impact statement, the Commission issued an
    order granting Algonquin a Section 7 certificate to construct
    and operate the AIM Project. Order Issuing Certificate,
    Algonquin Gas Transmission, LLC, 
    150 FERC ¶ 61,163
     (Mar.
    3, 2015).
    Several parties in the agency proceedings, including the
    petitioners in this case, requested rehearing before the
    Commission. The City of Boston Delegation alleged that the
    Commission failed to give adequate consideration to the safety
    risks of running the West Roxbury Lateral adjacent to an active
    quarry.     The Town of Dedham, Massachusetts, and
    Riverkeeper, Inc., argued in part that the Commission
    impermissibly segmented its NEPA review by failing to
    consider Algonquin’s three planned projects together in a
    single environmental impact statement. Additionally, a
    coalition of environmental groups, community organizations,
    and individuals alleged, among other claims, that the
    Commission insufficiently examined the cumulative impact of
    the Atlantic Bridge and Access Northeast projects, and failed
    adequately to consider safety issues raised by the pipeline’s
    proximity to the Indian Point nuclear facility.
    6
    The Commission denied the parties’ requests for rehearing
    and dismissed their requests for a stay. Order Denying
    Rehearing, Algonquin Gas Transmission, LLC, 
    154 FERC ¶ 61,048
     (Jan. 28, 2016) (Rehearing Order). A number of
    parties now seek review in this court of the Commission’s grant
    of a Section 7 certificate for the AIM Project.
    In particular, we consider three petitions for review,
    brought by (i) the City of Boston Delegation; (ii) the Town of
    Dedham, Massachusetts; and (iii) Riverkeeper, Inc., along with
    a coalition of environmental groups, community organizations,
    and individuals. The Delegation, in its own briefing, raises
    challenges focused on the West Roxbury Lateral. The Town
    of Dedham, together with Riverkeeper, Inc., and the coalition,
    jointly present a separate set of arguments addressing, among
    other things, the cumulative environmental impacts of
    Algonquin’s three projects and the safety concerns raised by
    the AIM Project’s proximity to the Indian Point nuclear
    facility. Algonquin, as intervenor, has submitted a brief
    supporting the Commission.
    II.
    Before reaching the merits of petitioners’ claims, we must
    first examine their standing to sue. Although the Commission
    did not initially contest the petitioners’ standing, Algonquin
    raised the issue as intervenor. And because we have an
    independent obligation to assure ourselves of our jurisdiction,
    we asked for supplemental briefing addressing the question of
    standing.
    To establish standing under Article III of the Constitution,
    petitioners must demonstrate (i) an injury in fact, (ii) that is
    fairly traceable to the challenged conduct, and (iii) that is likely
    to be redressed by a favorable decision. Lujan v. Defenders of
    7
    Wildlife, 
    504 U.S. 555
    , 560-61 (1992). We hold that the City
    of Boston Delegation lacks standing because it has failed to
    demonstrate an injury in fact. We therefore dismiss the
    Delegation’s petition for review for lack of jurisdiction without
    reaching the merits of the Delegation’s arguments. We
    conclude that the remaining petitioners have adequately
    demonstrated standing and thus reach the merits of their
    petitions.
    A.
    The City of Boston Delegation consists of nine elected
    representatives from Boston, including the Mayor, a
    congressman, five city councilors, a state senator, and a state
    representative. The Delegation’s claim of injury for standing
    purposes rests on the West Roxbury Lateral’s allegedly adverse
    safety, health, and environmental effects on the City. The
    Delegation stakes its standing primarily on the Mayor’s
    participation in the petition. The Delegation’s theory is that,
    because the Mayor regularly initiates litigation on behalf of the
    City, the Mayor’s involvement in the petition effectively makes
    the City of Boston a party. As a result, the Delegation asserts,
    the harms to the City caused by the pipeline can supply the
    requisite injury in fact for purposes of establishing the
    Delegation’s standing.        We are unpersuaded by the
    Delegation’s theory.
    While the City of Boston could in theory bring an action,
    the Mayor does not act as the City when he files a lawsuit in
    his own name. Under Massachusetts law, the City of Boston
    “may in its corporate capacity sue and be sued by its name.”
    
    Mass. Gen. Laws ch. 40, § 2
     (2018). And in practice, the City
    does in fact sue in its own name. See, e.g., City of Boston v.
    Boston Police Superior Officers Fed’n, 
    993 N.E.2d 693
     (Mass.
    2013). The city code specifies the process by which a lawsuit
    8
    is initiated on behalf of the City of Boston: the City’s
    Corporation Counsel “shall, subject to the direction of the
    Mayor, institute any suit or proceeding in behalf of the City
    which he shall deem the interest of the City requires.” City of
    Boston Mun. Code, Ordinance § 5-8.1. That process did not
    take place here.
    The Delegation reads the ordinance to encompass any
    lawsuit determined by the Mayor to be in the City’s interest,
    thus affording the Mayor discretion to sue on behalf of the City.
    The ordinance, though, does not support that reading. Rather,
    the ordinance requires the Corporation Counsel to institute suit
    (subject to the Mayor’s direction), and in doing so, the
    Corporation Counsel must “deem the interest of the City
    requires” bringing the litigation.
    There is no indication here that the Mayor directed the
    Corporation Counsel to file this petition, or that the
    Corporation Counsel made the requisite determination that “the
    interest of the City require[d]” seeking review of the
    Commission’s order. The ordinance’s procedure for initiating
    suit on behalf of the City thus was not followed. And the
    Mayor, per the terms of the ordinance, does not inherently
    litigate on behalf of the City whenever he appears in his own
    name, at least without the necessary determination by the
    Corporation Counsel. We are not at liberty to disregard the city
    code’s prescribed process by which an action is brought in the
    City’s name. We therefore cannot treat the City as a de facto
    petitioner merely by virtue of the Mayor’s participation.
    The Delegation has pointed us to no cases supporting a
    contrary conclusion. For instance, the Delegation cites RicMer
    Properties v. Board of Health of Revere, 
    794 N.E.2d 1236
    (Mass. 2003), for the proposition a municipality in
    Massachusetts can represent “the public interest” by asserting
    9
    parens patriae standing on behalf of the municipality’s
    residents. 
    Id. at 1240
    . RicMer does not help the Delegation.
    There, the mayor and city council abided by the ordinary
    process of directing the corporation counsel to intervene on
    behalf of the city, and the city itself intervened. 
    Id.
     at 1238 &
    n.2. The other cases referenced by the Delegation likewise do
    not support the proposition that a mayor, in her own name, can
    assert a city’s parens patriae interest even if the city itself is not
    a party: those cases involved actions brought by a municipality
    itself. See Town of Sudbury v. Dep’t of Pub. Utils., 
    218 N.E.2d 415
    , 419 (Mass. 1966) (towns have standing to “represent the
    public interest”); Town of Wilmington v. Dep’t of Pub. Utils.,
    
    165 N.E.2d 99
    , 103 (Mass. 1960) (same).
    Here, by contrast, the Mayor is a member of the
    Delegation in his own name, and the process for bringing suit
    in the name of the City through Corporation Counsel was not
    followed. In these circumstances, we cannot conclude that the
    Delegation, purely by virtue of the Mayor’s participation, is
    acting on behalf of the City in pursuing the petition for review.
    It follows that the Delegation cannot assert injuries to the City
    itself (or assert the City’s parens patriae interest in its residents)
    as the basis of the Delegation’s standing. See Maiden Creek
    Assocs., L.P. v. U.S. Dep’t of Transp., 
    823 F.3d 184
    , 193 (3d
    Cir. 2016). And because the City itself is not a party, we have
    no occasion to consider whether the City, if it were a party,
    could establish standing based on a parens patriae theory. Cf.
    City of Olmstead v. FAA, 
    292 F.3d 261
    , 268 (D.C. Cir. 2002)
    (declining to decide whether a municipality can “sue the
    federal government under the doctrine of parens patriae”); Md.
    People’s Counsel v. FERC, 
    760 F.2d 318
    , 321-22 (D.C. Cir.
    1985) (state agency has parens patriae standing to challenge
    Commission orders in federal court).
    10
    Because the Delegation is not petitioning as the City of
    Boston, it can establish standing only by demonstrating that its
    individual members suffer an injury in fact from the pipeline
    project. The Delegation’s attempts to do so in passing, by
    briefly asserting that certain of its members individually have
    standing, are inadequate. For instance, the Delegation
    observes, without any elaboration, that two of its members
    reside in the West Roxbury neighborhood and that the Mayor
    has an interest in the neighborhood’s safety as the city’s chief
    executive. Those “[b]are allegations” are insufficient to
    demonstrate a “substantial probability” that the Delegation has
    sustained an injury in fact sufficient to confer standing. Sierra
    Club v. EPA, 
    292 F.3d 895
    , 898 (D.C. Cir. 2002). And because
    the Delegation has not established that it has standing to seek
    review of the Commission’s decision, we must dismiss the
    Delegation’s petition for review for lack of jurisdiction.
    B.
    Unlike the Delegation, the remaining petitioners—the
    Town of Dedham, Riverkeepers, Inc., and the various coalition
    members—have established Article III standing to bring their
    petitions for review.           Generally, petitioners must
    “demonstrate standing for each claim [they] seek[] to press.”
    DaimlerChrysler Corp. v. Cuno, 
    547 U.S. 332
    , 352 (2006).
    But when multiple petitioners bring claims jointly, only one
    petitioner needs standing to raise each claim. Comcast Corp.
    v. FCC, 
    579 F.3d 1
    , 6 (D.C. Cir. 2009). In addition, for this
    court to have jurisdiction under the Natural Gas Act to consider
    an issue, the party seeking review must have presented the
    same issue to the Commission in an application for rehearing.
    15 U.S.C. § 717r(b).
    As part of the AIM Project, Algonquin installed new
    pipeline through the Town of Dedham, Massachusetts, running
    11
    the pipeline underneath town roads and a town-owned park.
    The Town alleges that the pipeline has caused significant
    construction-related harm from increased traffic, noise, and
    disruption of businesses. The Town further notes that the
    project would require “future, inconvenient re-opening of the
    Town roads” to maintain the pipeline, which would again visit
    the same injuries on the Town. Riverkeeper Opening Br. 9.
    Under our precedents, that kind of injury to the property
    interests of a landowner whose land is transected by a natural
    gas pipeline constitutes a sufficient injury in fact to substantiate
    standing. Sierra Club v. FERC, 
    867 F.3d 1357
    , 1366 n.2 (D.C.
    Cir. 2017); see 
    id. at 1366
    ; Minisink, 762 F.3d at 106.
    The Town also alleges that the operation of the pipeline
    through its property “poses an ongoing safety risk” that will
    affect the Town financially. Riverkeeper Opening Br. 9. We
    have held that the presence of a “continuing safety hazard”
    caused by the nearby installation of a natural gas pipeline can
    establish an injury in fact. Moreau v. FERC, 
    982 F.2d 556
    , 565
    (D.C. Cir. 1993); Myersville Citizens for a Rural Cmty., Inc. v.
    FERC, 
    783 F.3d 1301
    , 1317 (D.C. Cir. 2015). And considered
    in the context of the financial harm alleged by the Town and
    the infringement of its property interests, the safety risk further
    demonstrates an injury in fact for purposes of standing.
    Beyond the Town, Reynolds Hills, Inc.—a member of the
    coalition seeking review—has demonstrated its standing so as
    to enable our consideration of petitioners’ remaining
    arguments. Reynolds Hills is a non-profit neighborhood
    community in Westchester County, New York. As with the
    Town, the AIM Project involved construction of a pipeline
    upgrade across Reynolds Hills’s property. Reynolds Hills
    adequately alleged an injury to its property interests and the
    aesthetic interests of its members caused by the project. It also
    adequately alleged an increased safety risk from the upgraded
    12
    pipeline on its property and from the project’s alleged effects
    on the Indian Point nuclear facility. Those allegations of harm
    from the project—which we assume are true for purposes of
    standing, see Parker v. District of Columbia, 
    478 F.3d 370
    , 377
    (D.C. Cir. 2007)—demonstrate that Reynolds Hills has
    suffered an injury in fact.
    In addition to establishing injury in fact, the Town and
    Reynolds Hills also satisfy the second and third requirements
    of standing. Their injuries are fairly traceable to the
    construction and operation of the pipeline as approved by the
    Commission’s certificate order, and the injuries would be
    redressed by vacatur of that order on any ground. See Sierra
    Club, 867 F.3d at 1366.
    Finally, between the Town and Reynolds Hills, they
    exhausted before the Commission all the issues raised
    collectively in the joint petitioners’ brief (except a
    conflict-of-interest claim we discuss below, Part III.C). In the
    Town’s application for rehearing to the Commission, the Town
    argued that the Commission improperly segmented its
    environmental review by failing to consider Algonquin’s three
    projects together. Meanwhile, Reynolds Hills argued on
    rehearing that the Commission inadequately assessed the
    cumulative environmental impacts of Algonquin’s three
    projects, and failed to give proper consideration to the safety
    concerns arising from the project’s effects on the Indian Point
    nuclear facility. We therefore have jurisdiction to address the
    merits of the arguments raised in the petitions brought by the
    Town, Riverkeeper, and the coalition.
    III.
    We review the Commission’s grant of a Section 7
    certificate “under the familiar arbitrary and capricious
    13
    standard,” bearing in mind that “the grant or denial of” such a
    certificate “is a matter peculiarly within the discretion of the
    Commission.” Minisink, 762 F.3d at 105-06 (brackets and
    citation omitted). Applying that standard, we sustain the
    Commission’s order against the challenges brought jointly by
    the Town, Riverkeeper, and the coalition.
    A.
    In the first set of arguments raised by petitioners, they
    contend that the Commission failed to comply with NEPA in
    approving the AIM Project. NEPA generally obligates
    agencies to take a “‘hard look’ at the environmental impacts of
    a proposed action.” Myersville, 783 F.3d at 1324. An
    environmental impact statement is “deficient, and the agency
    action it undergirds is arbitrary and capricious, if the EIS does
    not contain sufficient discussion of the relevant issues and
    opposing viewpoints, or if it does not demonstrate reasoned
    decisionmaking.” Sierra Club, 867 F.3d at 1368 (internal
    quotation marks and citations omitted). In evaluating an
    agency’s NEPA analysis, we apply a “rule of reason,” and have
    “refused to ‘flyspeck’ the agency’s findings in search of ‘any
    deficiency no matter how minor.’” Myersville, 783 F.3d at
    1322-23 (quoting Nevada v. Dep’t of Energy, 
    457 F.3d 78
    , 93
    (D.C. Cir. 2006)).
    Petitioners present two related arguments under NEPA.
    First, petitioners contend that the Commission improperly
    segmented its environmental review by failing to examine the
    AIM Project and Algonquin’s two other pipeline upgrade
    projects together in a single environmental statement. Second,
    petitioners submit that the Commission failed to give adequate
    consideration to the cumulative environmental impacts of the
    three upgrade projects. We find no basis to set aside the
    Commission’s order on those grounds.
    14
    1.
    Under the Council on Environmental Quality’s regulations
    implementing NEPA, agencies must consider all “connected
    actions,” “cumulative actions,” and “similar actions” within a
    single environmental impact statement.                
    40 C.F.R. § 1508.25
    (a). “An agency impermissibly ‘segments’ NEPA
    review when it divides connected, cumulative, or similar
    federal actions into separate projects and thereby fails to
    address the true scope and impact of the activities that should
    be under consideration.” Del. Riverkeeper Network v. FERC,
    
    753 F.3d 1304
    , 1313 (D.C. Cir. 2014). The rule ensures that
    an agency considers the full environmental impact of
    “connected, cumulative, or similar” actions before they are
    undertaken, so that it can assess the true costs of an integrated
    project when it is best situated to evaluate “different courses of
    action” and mitigate anticipated effects. 
    Id. at 1313-14
    .
    This court has developed a set of factors that help clarify
    when “physically connected projects can be analyzed
    separately under NEPA.” 
    Id. at 1315
    . As relevant here, when
    an agency considers projects non-contemporaneously, see 
    id. at 1318
    , and when projects have “substantial independent
    utility,” 
    id. at 1316
    , separate environmental statements can be
    appropriate.
    Applying those considerations in Delaware Riverkeeper,
    we concluded that the Commission had impermissibly
    segmented its review of four pipeline upgrades. The projects,
    we explained, were “connected and interrelated” and
    “functionally and financially interdependent,” and they also
    had significant “temporal overlap,” 
    id. at 1319
    , because they
    were “either under construction” or “pending before the
    Commission for environmental review and approval” at the
    same time, 
    id. at 1308
    .
    15
    In Minisink and Myersville, by contrast, we sustained the
    Commission’s conduct of separate environmental assessments.
    In Minisink, we noted that the projects in question lacked the
    temporal overlap that had characterized the projects in
    Delaware Riverkeeper. Rather, the application for the
    later-in-time project had yet to be submitted when the main
    project was under consideration. Minisink, 762 F.3d at 113
    n.11. In Myersville, we reasoned that, unlike Delaware
    Riverkeeper, the projects were “unrelated” and did not depend
    on one another for their justification. 783 F.3d at 1326-27.
    Because the case before us is more in line with Minisink
    and Myersville than with Delaware Riverkeeper, we conclude
    that the Commission did not act arbitrarily and capriciously in
    declining to consider Algonquin’s three projects in a single
    environmental impact statement. With regard to temporal
    overlap, the Commission issued the AIM Project certificate in
    March 2015, Algonquin submitted the application for Atlantic
    Bridge in October 2015, and Algonquin has yet to file the
    Access Northeast application. The projects thus were not under
    simultaneous consideration by the agency.
    Nor are the projects “financially and functionally
    interdependent.” Del. Riverkeeper, 753 F.3d at 1319. On that
    score, we consider “whether one project will serve a significant
    purpose even if a second related project is not built,” Coal. on
    Sensible Transp., Inc. v. Dole, 
    826 F.2d 60
    , 69 (D.C. Cir.
    1987), and we look to the “commercial and financial viability
    of a project when considered in isolation from other actions,”
    Del. Riverkeeper, 753 F.3d at 1316. In denying rehearing, the
    Commission observed that Algonquin’s three projects “held
    separate open seasons,” “executed individual precedent
    agreements” with largely distinct shippers, and “have different
    negotiated and recourse rates and separate in-service dates.”
    Rehearing Order ¶ 75. In those circumstances, the Commission
    16
    reasonably concluded that “the projects do not depend on the
    other[s] for access to the natural gas market.” Id. ¶ 78.
    Factual developments after the Commission’s completion
    of environmental review for the AIM Project highlight the
    permissibility of conducting separate environmental
    assessments for Algonquin’s three projects.           Following
    issuance of the environmental impact statement for the AIM
    Project, the Atlantic Bridge Project was significantly curtailed:
    the project’s planned capacity decreased by nearly 40 percent,
    and the length of pipeline to be replaced decreased by 88
    percent. Atlantic Bridge Certificate Order ¶ 86 & n.82. If the
    Commission’s environmental impact statement for the AIM
    Project had taken into account the Atlantic Bridge Project as
    then conceived, the review would have substantially overstated
    the environmental impact of the Atlantic Bridge Project. With
    regard to the Access Northeast Project, meanwhile, Algonquin
    withdrew the project from the Commission’s pre-filing process
    in June 2017, and it is uncertain when (or whether) the project
    will go forward. Order Denying Stay, Algonquin Gas
    Transmission, LLC, 
    160 FERC ¶ 61,015
    , at ¶ 6 & n.13 (Aug.
    21, 2017).
    In short, the functional and temporal distinctness of the
    three projects, as underscored by factual developments
    concerning the Atlantic Bridge and Access Northeast Projects,
    substantiate that it was permissible for the Commission to
    prepare a separate environmental impact statement for the AIM
    Project.
    2.
    Relatedly, the joint petitioners contend that the
    Commission failed to give sufficient consideration to the
    cumulative environmental impacts of the AIM, Atlantic
    17
    Bridge, and Access Northeast Projects. This second species of
    petitioners’ arguments under NEPA fares no better than the
    first.
    An environmental impact statement must assess the
    “cumulative impacts” of a proposed action. Sierra Club v.
    FERC, 
    827 F.3d 36
    , 49 (D.C. Cir. 2016). A project’s
    “cumulative impact” is “the impact on the environment which
    results from the incremental impact of the action when added
    to other past, present, and reasonably foreseeable future
    actions.” 
    40 C.F.R. § 1508.7
    . To satisfy “hard look” review,
    an agency’s cumulative impacts analysis must contain
    “sufficient discussion of the relevant issues” and be
    “well-considered.” Myersville, 783 F.3d at 1324-25 (citation
    omitted). But importantly, the adequacy of an environmental
    impact statement is judged by reference to the information
    available to the agency at the time of review, such that the
    agency is expected to consider only those future impacts that
    are reasonably foreseeable.
    At the time of the Commission’s consideration of the AIM
    Project, the impacts of the Atlantic Bridge Project were
    reasonably foreseeable. And the Commission thoroughly
    considered the environmental effects of Atlantic Bridge
    throughout the cumulative impacts section of the AIM
    Project’s environmental impact statement. The statement
    “contains sufficient discussion of” the cumulative impacts of
    Atlantic Bridge and is “well-considered.” Myersville, 783 F.3d
    at 1325.
    The cumulative impacts discussion of the Access
    Northeast Project is much more limited, and understandably so.
    At the time of the AIM Project’s environmental impact
    statement, Access Northeast was months away from entering
    the pre-filing process and over a year away from issuance of a
    18
    notice of intent to prepare an environmental impact statement.
    Given Access Northeast’s preliminary stage and the resulting
    lack of available information about its scope at the time, the
    project was “too preliminary to meaningfully estimate [its]
    cumulative impacts.” Theodore Roosevelt Conservation
    P’ship v. Salazar, 
    616 F.3d 497
    , 513 (D.C. Cir. 2010); see
    Minisink, 762 F.3d at 113. Additionally, the AIM Project and
    Access Northeast would “not overlap in time,” meaning the
    short-term impacts from constructing the former would abate
    before construction commenced on the latter, and no long-term
    cumulative impacts were reasonably anticipated. Rehearing
    Order ¶¶ 144-145. In light of “the uncertainty surrounding
    [Access Northeast], and the difference in timing between the
    two projects, this discussion suffices under NEPA.” Minisink,
    762 F.3d at 113.
    None of this means that Algonquin will circumvent full
    consideration of the environmental impact of projects that
    continue to take shape. To the contrary, later projects can fully
    account for the cumulative impacts when those effects become
    better known. And in fact, the environmental assessment for
    the Atlantic Bridge Project considered the cumulative impacts
    of the Access Northeast Project once the latter project’s details
    were better defined and its anticipated impacts better
    understood. Atlantic Bridge Certificate Order ¶¶ 98 n.98,
    107-110 (citing Environmental Assessment at 2-129 to 2-130,
    2-131 to 2-143). For purposes of the AIM Project, however,
    the Commission adequately considered the cumulative impacts
    of the other two projects based on the information then
    available to the agency.
    B.
    Petitioners    next   challenge    the    Commission’s
    determination that the AIM Project posed no increased threat
    19
    to the Indian Point nuclear power plant in Westchester County,
    New York. According to petitioners, the Commission’s
    conclusion is unsupported by substantial evidence. We
    disagree.
    The AIM Project involved installing 2,159 feet of pipeline
    across the property of the Indian Point facility. The pipeline
    would be located 1,600 feet from the “power plant structures,”
    and 2,370 feet from Indian Point’s “protected security barrier
    around the main facility sites.” Rehearing Order ¶ 197. During
    the Commission’s consideration of the AIM Project, Entergy—
    the operator of Indian Point—undertook a safety evaluation as
    required by the relevant regulations.         That evaluation
    determined that the project would pose no additional safety
    risks to its facility. The Nuclear Regulatory Commission
    (NRC) conducted an independent analysis and reached the
    same conclusion. Relying on those expert analyses, the
    Commission found that the AIM Project “would not pose any
    new safety hazards” to Indian Point. AIM Project Final
    Environmental Impact Statement at ES-8 (Jan. 23, 2015).
    In evaluating an application for a Section 7 certificate, the
    Commission must determine that the proposed project is in the
    “public interest,” which requires assessing potential “safety
    concerns.” Washington Gas Light Co. v. FERC, 
    532 F.3d 928
    ,
    932 (D.C. Cir. 2008). If the Commission’s safety findings are
    unsupported by substantial evidence, we vacate the certificate
    order. 
    Id. at 932-33
    . Petitioners seek vacatur here, arguing that
    the Commission erred in adopting the NRC’s safety finding
    concerning the Indian Point facility.
    The Commission’s factual findings are “conclusive” for
    our purposes if “supported by substantial evidence.” 15 U.S.C.
    § 717r(b). Substantial evidence “requires more than a scintilla,
    but can be satisfied by something less than a preponderance of
    20
    the evidence.” Minisink, 762 F.3d at 108 (citation omitted).
    The     Commission’s       safety  finding     meets     the
    substantial-evidence threshold.
    The Commission of course can rely on expert reports in its
    decisions. See Murray Energy Corp. v. FERC, 
    629 F.3d 231
    ,
    238 (D.C. Cir. 2011). Here, it relied on two: Entergy’s safety
    evaluation and NRC’s confirming analysis. The Commission
    discussed those evaluations in its environmental impact
    statement, its certificate order, and its rehearing order, in
    support of its finding that the “AIM Project can safely operate
    near Indian Point.” Rehearing Order ¶ 201. Those expert
    opinions qualify as substantial evidence supporting the
    Commission’s safety finding, and the Commission acted well
    within its discretion in relying on them to grant Algonquin’s
    certificate.
    Petitioners contend that the Commission erred in accepting
    Entergy’s and NRC’s safety findings rather than those of
    competing expert analyses that found safety risks to Indian
    Point from the AIM Project. Specifically, petitioners and their
    experts fault Entergy and NRC for assuming that gas flow
    could be terminated within three minutes of a pipeline rupture,
    and estimating a blast radius based on that assumption. But
    whereas Entergy’s analysis assumed a three-minute response
    time, NRC directly responded to the opposing experts’
    concerns about that assumption; after conducting an analysis
    that assumed a “catastrophic failure” and continuous gas flow
    for one hour, NRC still concluded that the pipeline posed no
    safety threat. AIM Project Final Environmental Impact
    Statement at 4-278. In ratifying NRC’s “extensive formal
    responses” to petitioners’ experts, the Commission found
    NRC’s assumptions reasonable and its analysis persuasive.
    Rehearing Order ¶ 201.
    21
    In general, we defer to the Commission’s “resolution of
    factual disputes between expert witnesses,” and accept its
    decision “to credit” one expert’s “conclusions” over another
    expert’s if its choice is “reasonable.” Murray Energy Corp.,
    
    629 F.3d at 239
     (citation omitted). Here, the Commission was
    faced with Entergy and NRC’s analyses, on one hand, and
    critiques from two independent experts, on the other. It
    permissibly decided to credit the NRC’s expert conclusions,
    and to accept that NRC’s “extensive formal responses” had
    adequately addressed the opposing experts’ concerns.
    Rehearing Order ¶ 201.
    The expert conclusion adopted by the Commission,
    moreover, was that of another federal agency. Agencies can be
    expected to “respect [the] views of such other agencies as to
    those problems” for which those “other agencies are more
    directly responsible and more competent.” City of Pittsburgh
    v. Fed. Power Comm’n, 
    237 F.2d 741
    , 754 (D.C. Cir. 1956).
    So, for instance, we sustained an agency’s decision against
    undertaking a rulemaking in reliance on the opinion of “other
    government agencies and non-governmental expert
    organizations with specific expertise” on the matter. EMR
    Network v. FCC, 
    391 F.3d 269
    , 273 (D.C. Cir. 2004).
    In that regard, NRC has particular expertise in assessing
    external threats to the nuclear facilities it regulates. See, e.g.,
    New York v. NRC, 
    824 F.3d 1012
    , 1019-20 (D.C. Cir. 2016).
    The Commission determined that it was “satisfied as to
    [NRC’s] competence and the validity of their basic data and
    analysis,” Rehearing Order ¶ 203, and chose to credit NRC’s
    safety conclusions. We see no basis to reject the Commission’s
    decision to do so.
    22
    C.
    As their final ground for overturning the Commission’s
    grant of a Section 7 certificate, petitioners contend that a
    third-party contractor that the Commission relied on to prepare
    the environmental impact statement—Natural Resource
    Group—had a conflict of interest. Petitioners did not present
    that objection to the agency. We therefore lack jurisdiction to
    consider the issue unless we conclude that “there is reasonable
    ground for [petitioners’] failure” to raise the argument on
    rehearing before the agency. 15 U.S.C. § 717r(b).
    In a case involving an analogous exhaustion provision and
    a conflict-of-interest claim, we held that a petitioner had
    demonstrated a “reasonable ground” to excuse the lack of
    exhaustion because the petitioner “had no reason during the
    [environmental review] process to suspect the alleged defects
    in the selection and supervision of [the contractor].”
    Communities Against Runway Expansion, Inc. (CARE) v. FAA,
    
    355 F.3d 678
    , 686 (D.C. Cir. 2004). Our decision in CARE
    controls here in light of the similar circumstances. We
    therefore have jurisdiction to consider the merits of petitioners’
    conflict-of-interest claim.
    We reject petitioners’ argument on the merits, however.
    Petitioners’ claim of a conflict of interest rests on an allegation
    that Natural Resource Group was also hired by a consortium
    that included Algonquin’s parent company to perform
    public-affairs work in connection with a separate project. That
    ostensible conflict did not arise until the environmental-review
    process for the AIM Project was substantially underway.
    Neither the Commission nor Natural Resource Group failed to
    follow the conflicts disclosure rules in place at the time. See
    Fed. Energy Reg. Comm’n, Handbook for Using Third-Party
    Contractors to Prepare Envtl. Documents for Nat. Gas
    23
    Facilities & Hydropower Projects at 4-1 to 4-6 (Dec. 2014).
    In addition, the Commission later once again hired the Natural
    Resource Group to assist with the environmental statement for
    the Atlantic Bridge Project. In doing so, the Commission found
    that the supposed conflict identified by petitioners here was not
    a “disqualifying conflict” under the Commission’s rules.
    Letter from Chairman Norman Bay to Sen. Elizabeth Warren
    2, FERC Docket No. CP16-9 (July 19, 2016). Petitioners offer
    no basis for disagreeing with that conclusion.
    Finally, even if petitioners had identified an actual conflict
    of interest, it would afford a ground for invalidating the
    environmental impact statement only if it rose to the level of
    “compromis[ing] the objectivity and integrity of the NEPA
    process.” CARE, 
    355 F.3d at 686-87
     (formatting modified).
    That bar has not been met here.
    *   *    *   *    *
    For the foregoing reasons, we dismiss the City of Boston
    Delegation’s petition for review for lack of jurisdiction, and we
    deny the remaining petitions for review.
    So ordered.