Old Dominion Elec. Coop. v. Fed. Energy Regulatory Comm'n , 898 F.3d 1254 ( 2018 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued March 19, 2018                 Decided August 3, 2018
    No. 17-1040
    OLD DOMINION ELECTRIC COOPERATIVE,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    LSP TRANSMISSION HOLDINGS, LLC, ET AL.,
    INTERVENORS
    Consolidated with 17-1041
    On Petitions for Review of Orders of
    the Federal Energy Regulatory Commission
    Jonathan S. Franklin argued the cause for petitioners.
    With him on the briefs were Michael A. Yuffee, Adrienne E.
    Clair, and Rebecca L. Shelton.
    Larisa M. Vaysman and Michael R. Engleman were on the
    brief for intervenors LSP Transmission Holdings, LLC, et al.
    in support of petitioners.
    2
    Lona T. Perry, Deputy Solicitor, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief was Robert H. Solomon, Solicitor.
    Morgan Parke, Stacey L. Burbure, Kenneth G. Jaffe, Neil
    H. Butterklee, Gary E. Guy, Amanda Riggs Conner, Randall V.
    Griffin, Richard P. Bress, David L. Schwartz, Vilna Waldron
    Gaston, and Sandra E. Rizzo were on the brief for intervenors
    FirstEnergy Companies, et al. in support of respondent.
    Kenneth R. Carretta and Elias G. Farrah entered appearances.
    Before: HENDERSON, KAVANAUGH, * and KATSAS, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge KATSAS.
    KATSAS, Circuit Judge: In the past, electric utilities in the
    mid-Atlantic region have shared the costs of high-voltage
    transmission lines, which benefit the entire region. In 2015,
    some of these utilities proposed to eliminate cost sharing for
    projects undertaken only to satisfy an individual utility’s
    planning criteria, including projects that involve high-voltage
    lines. The Federal Energy Regulatory Commission approved
    this change and applied it to deny cost sharing for projects to
    rebuild two high-voltage lines. The petitioners, whose local
    zone now must bear the entire cost of these two projects,
    contend that FERC’s decisions were unlawful or inadequately
    explained.
    *
    Judge Kavanaugh was a member of the panel when this case was
    argued but did not participate in the opinion.
    3
    I
    A
    The Federal Power Act gives FERC jurisdiction over
    facilities that transmit electricity in interstate commerce. See
    16 U.S.C. § 824(b)(1); 42 U.S.C. § 7172(a)(1)(B). Under the
    Act, electric utilities must charge “just and reasonable” rates.
    16 U.S.C. § 824d(a). For decades, the Commission and the
    courts have understood this requirement to incorporate a “cost-
    causation principle”—the rates charged for electricity should
    reflect the costs of providing it. See Ala. Elec. Co-op., Inc. v.
    FERC, 
    684 F.2d 20
    , 27 (D.C. Cir. 1982). We often frame this
    principle as one that ensures “burden is matched with benefit,”
    so that FERC “generally may not single out a party for the full
    cost of a project, or even most of it, when the benefits of the
    project are diffuse.” BNP Paribas Energy Trading GP v.
    FERC, 
    743 F.3d 264
    , 268 (D.C. Cir. 2014); see Midwest ISO
    Transmission Owners v. FERC, 
    373 F.3d 1361
    , 1368–69 (D.C.
    Cir. 2004). This cost-causation principle “add[s] flesh to [the]
    bare statutory bones” of the just-and-reasonable-rate
    requirement. K N Energy, Inc. v. FERC, 
    968 F.2d 1295
    , 1300
    (D.C. Cir. 1992).
    To promote more efficient coordination among electric
    utilities, FERC has promulgated a regulation known as “Order
    No. 1000.” Transmission Planning and Cost Allocation by
    Transmission Owning and Operating Public Utilities, 136
    FERC ¶ 61,051 (2011). It imposes two requirements relevant
    here. First, utilities in each planning region must jointly
    produce a regional transmission plan to determine what new
    facilities would best meet regional needs for electricity. 
    Id. P 148.
    Second, in their respective tariffs, utilities must include
    a formula “for allocating the costs of new transmission
    facilities selected in the regional transmission plan for purposes
    4
    of cost allocation.” 
    Id. P 558.
    This formula must satisfy six
    general principles, the first of which is the cost-causation
    principle: “The cost of transmission facilities must be allocated
    to those within the transmission planning region that benefit
    from those facilities in a manner that is at least roughly
    commensurate with estimated benefits.” 
    Id. P 622.
    Order No.
    1000 requires each utility to show, through compliance filings,
    that its cost-allocation formula is consistent with the six
    specified principles. 
    Id. P 603.
    This case involves disputes within a planning region
    encompassing much of the Mid-Atlantic and part of the
    Midwest. In this region, the transmission of electricity is
    overseen by PJM Interconnection, LLC, which controls but
    does not own the facilities of its member utilities. (“PJM”
    refers to Pennsylvania, New Jersey, and Maryland—the first
    three states in which PJM operated.) The region is subdivided
    into zones that correspond to areas served by each individual
    utility. The utilities are governed by the PJM Operating
    Agreement, which sets forth the respective rights and duties of
    PJM and its members, and the PJM Open Access Transmission
    Tariff, which details the terms on which the utilities provide
    service.
    To comply with the regional-planning requirement of
    Order No. 1000, PJM-member utilities maintain a Regional
    Transmission Expansion Plan. Schedule 6 of the Operating
    Agreement specifies what kind of projects must be included in
    this Regional Plan. As relevant here, Schedule 6 designates
    three categories of projects for inclusion in the Plan: (1)
    projects to satisfy PJM’s own planning and reliability criteria;
    (2) projects to satisfy reliability criteria developed by standard-
    setting organizations such as the North American Electric
    Reliability Corporation (“NERC”); and (3) projects to satisfy
    planning criteria established by individual utilities. The
    5
    utilities submit their individual planning criteria both to FERC,
    on a document called Form 715, and to PJM.
    Schedule 12 of the Tariff addresses the cost-sharing
    requirements of Order No. 1000. Before 2015, Schedule 12
    required regional cost sharing for all “Regional Facilities,”
    which it defined as projects that were (a) included in the
    Regional Plan to satisfy any of the planning criteria described
    above and (b) particular kinds of high-voltage projects.
    Schedule 12 also establishes the cost-allocation formula for
    such Regional Facilities. Half of these costs are allocated on a
    pro rata basis, based on the level of customer demand within
    each zone, regardless of where the specific project at issue is
    located. This method of cost allocation is called the “postage
    stamp” approach. The remaining costs are allocated based on
    an estimate of which zones most directly benefit from the
    project at issue, as made under what is called a “distribution
    factor (‘DFAX’) analysis.” In contrast, the costs of lower-
    voltage facilities, which generally do not qualify as “Regional
    Facilities,” are allocated solely under a DFAX analysis.
    As required by Order No. 1000, PJM submitted this cost-
    allocation methodology to FERC, which approved it in March
    2013. PJM Interconnection, LLC, 142 FERC ¶ 61,214,
    PP 412–26 (2013) (“PJM Compliance Order”). In so doing,
    FERC specifically found that “high-voltage transmission
    facilities have significant regional benefits that accrue to all
    members of the PJM transmission system.” 
    Id. P 413.
    Further,
    it found that the proposed hybrid cost-allocation method for
    high-voltage facilities, incorporating both postage-stamp and
    DFAX components, would satisfy the cost-causation principle
    “that costs be allocated in a manner that is roughly
    commensurate with benefits received.” 
    Id. According to
    FERC, the postage-stamp component “capture[d] the full
    spectrum of benefits associated with high-voltage facilities,
    6
    including difficult to quantify regional benefits, such as
    improved reliability, reduced congestion, reduced power
    losses, greater carrying capacity, reduced operating reserve
    requirements, and improved access to generation.” 
    Id. P 414.
    B
    Petitioners are three Virginia-based members of PJM—
    Old Dominion Electric Cooperative, Dominion Energy
    Services, Inc., and Virginia Electric & Power Co. d/b/a
    Dominion Energy Virginia (collectively “Dominion”). In July
    2013, Dominion proposed to rebuild an aging high-voltage
    transmission line between Elmont and Cunningham, Virginia.
    The project initially did not qualify for cost sharing because it
    was unnecessary to satisfy the extant planning and reliability
    criteria of PJM, NERC, or Dominion.
    In September 2014, Dominion adopted its own “end of
    life” planning criteria, submitted the criteria on Form 715 to
    FERC, and presented them to a PJM planning committee.
    Dominion concluded that replacing the Elmont-Cunningham
    line was necessary to satisfy these new criteria. PJM reviewed
    the project and agreed.
    In March 2015, PJM initiated the first of three proceedings
    at issue here—the “Elmont-Cunningham Proceeding”—by
    filing with FERC proposed cost allocations for the Elmont-
    Cunningham project.           Under Schedule 12’s hybrid
    methodology for high-voltage facilities, nearly half of the costs
    would be allocated to Dominion; the remaining costs would be
    spread among 23 other utilities, with shares ranging from
    roughly 8% to 0.1%. Dayton Power and Light Co., an Ohio-
    based utility, intervened in the proceeding and objected.
    Dayton, which would be responsible for roughly 1% of the
    costs, complained that Dominion had unilaterally imposed
    costs on other utilities by adopting new end-of-life criteria.
    7
    Six days after PJM initiated the Elmont-Cunningham
    Proceeding, a group of member utilities opposed to the
    proposed cost sharing initiated the second proceeding at
    issue—the “Cost-Allocation Proceeding.”           The utilities
    proposed to amend Schedule 12 of the Tariff to prohibit cost
    sharing for any project included in the Regional Plan only to
    satisfy individual utilities’ planning criteria. Under the
    proposed amendment, all costs for such projects would be
    “allocate[d] … to the local zone of the transmission owner that
    filed the planning criteria,” regardless of whether the project
    produced regional benefits. J.A. 55. Dominion opposed the
    amendment as inconsistent with the cost-causation principle.
    FERC initially rejected the utilities’ proposed amendment
    on two grounds. In part, FERC concluded that the amendment
    violated Order No. 1000 by creating a category of projects
    selected for cost allocation but not subject to the approved cost-
    allocation formula. See PJM Interconnection, LLC, 151 FERC
    ¶ 61,172, P 22 (2015). FERC also concluded that the
    amendment was inconsistent with its earlier finding that high-
    voltage transmission lines provide “significant regional
    benefits that accrue to all members of the PJM transmission
    system.” 
    Id. P 23.
    Meanwhile, in the Elmont-Cunningham Proceeding,
    FERC ordered a technical conference to address how PJM
    satisfies its regional-planning obligations under Order No.
    1000. PJM Interconnection, LLC, 152 FERC ¶ 61,197 (2015).
    In that order, FERC rejected Dayton’s process-based argument
    against the proposed cost sharing. Specifically, FERC found
    that “Dominion followed the appropriate procedures to update
    its local planning criteria,” by presenting them both to the PJM
    planning committee and to FERC. 
    Id. P 15.
                                    8
    After the technical conference, FERC reversed course and
    accepted the tariff amendment. PJM Interconnection, LLC,
    154 FERC ¶ 61,096 (2016) (“Cost-Allocation Order”). First,
    FERC concluded that the amendment did not violate Order No.
    1000 because “not all projects included in the [Regional Plan]
    are selected for purposes of cost allocation,” and so the
    amendment merely created a “new category of projects”
    included in the Regional Plan but not selected for cost
    allocation. 
    Id. P 13
    & n.16. FERC further reasoned that
    projects included in the Regional Plan only to satisfy individual
    utilities’ planning criteria “are not needed to meet PJM regional
    criteria or NERC reliability standards,” but instead are included
    “only to ensure that such projects are developed in a manner
    that is consistent with” the Regional Plan. 
    Id. P 13
    . FERC also
    found that the proposal would not undermine the competitive-
    bidding process because only projects “located solely within a
    transmission owner’s zone” and having their costs “allocated
    solely to that zone” would be restricted from competitive
    bidding. 
    Id. P 14.
    Finally, FERC held that the amendment did
    not produce an unjust and unreasonable allocation of costs
    because, of the 303 projects previously included in the
    Regional Plan to address only individual utilities’ planning
    criteria, 98% of them had all of their costs allocated to the local
    zone. 
    Id. P 16.
    On the same day, FERC rejected PJM’s proposed cost
    allocation for the Elmont-Cunningham project.               PJM
    Interconnection, LLC, 154 FERC ¶ 61,097 (2016) (“Elmont-
    Cunningham Order”). FERC found that the project “must go
    into service within three years or less in order to avoid several
    regional Reliability Criteria violations, and PJM followed the
    stakeholder process outlined in its Operating Agreement.” 
    Id. P 27.
    But FERC rejected regional cost sharing as inconsistent
    with the tariff amendment that it had simultaneously approved
    in its Cost-Allocation Order. 
    Id. P 28.
                                   9
    Commissioner LaFleur dissented in part from both orders.
    In the Cost-Allocation Proceeding, she would have narrowed
    the amendment to “preserv[e] the current regional cost
    allocation for certain high voltage projects, even if those
    projects are selected solely to address local planning criteria.”
    Cost-Allocation Order, 154 FERC ¶ 61,096 (LaFleur, Comm’r,
    dissenting in part). She reasoned that FERC’s prior compliance
    finding—“high-voltage transmission facilities have significant
    regional benefits that accrue to all members of the PJM
    transmission system”—did not depend on the type of planning
    criteria underlying the particular project at issue. See 
    id. (quoting PJM
    Compliance Order, 142 FERC ¶ 61,214, P 413).
    Moreover, although the “overwhelming majority of projects
    approved to address local planning criteria” produced only
    local benefits, they were “lower voltage facilities” for which
    costs had never been regionally shared. 
    Id. For the
    same
    reasons, Commissioner LaFleur also dissented from the
    rejection of cost sharing for the Elmont-Cunningham line. See
    Elmont-Cunningham Order, 154 FERC ¶ 61,097 (LaFleur,
    Comm’r, dissenting in part).
    Before FERC issued these decisions, PJM had initiated the
    third and final proceeding at issue—the “Cunningham-Dooms
    Proceeding.” It involved Dominion’s proposal to rebuild a
    high-voltage line from Cunningham to Dooms, Virginia, as
    required by Dominion’s end-of-life criteria. In July 2016,
    FERC applied its Cost-Allocation Order to reject PJM’s
    proposed cost allocation, once again over Commissioner
    LaFleur’s dissent. See PJM Interconnection, LLC, 156 FERC
    ¶ 61,030 (2016).
    After unsuccessfully seeking rehearing of the three orders,
    Dominion timely sought judicial review in this Court.
    10
    II
    Before addressing Dominion’s challenge to FERC’s
    decision to accept the tariff amendment, we must first
    determine what the amendment says and how it operates. On
    that question, Intervenors LSP Transmission Holdings, LLC
    and Northeast Transmission Development, LLC contend that
    the amendment, properly construed, violates Order No. 1000
    by refusing to apply the approved cost-allocation formula to
    projects selected for cost allocation. FERC initially adopted
    this argument, 151 FERC ¶ 61,172, P 22, but later rejected it,
    154 FERC ¶ 61,096, P 13.
    FERC contends that we should not address an argument
    raised only by intervenors. As a general matter, an intervenor
    “may join only on a matter that has been brought before the
    court by a petitioner.” E. Ky. Power Co-op., Inc. v. FERC, 
    489 F.3d 1299
    , 1305 (D.C. Cir. 2007) (quotation marks omitted).
    But the intervenors here challenge the same tariff amendment
    as does Dominion, and their argument under Order No. 1000 is
    closely related to Dominion’s argument under the cost-
    causation principle. Moreover, the intervenors’ argument turns
    on the proper construction of the amendment—a question
    antecedent to determining whether FERC permissibly
    approved it.
    The amendment requires the costs of projects included in
    the Regional Plan to satisfy only Form 715 planning criteria to
    be allocated entirely to the zone of the utility that filed the
    criteria, “[n]otwithstanding” other provisions of Schedule 12.
    Tariff, Schedule 12(xv) (J.A. 72). The intervenors contend that
    the “notwithstanding” proviso should be read to apply only
    after a project has been deemed a Regional Facility, and
    therefore selected in the Regional Plan for cost sharing. Under
    that interpretation, the amendment would violate Order No.
    11
    1000, which requires utilities to have in place “a regional cost
    allocation method for any transmission facility selected in a
    regional transmission plan for purposes of cost allocation.”
    136 FERC ¶ 61,051, P 690.
    FERC ultimately concluded that the amendment creates a
    category of projects included in the Regional Plan but not
    selected for cost sharing. See Cost-Allocation Order, 154
    FERC ¶ 61,096, P 13. We agree. In denoting which facilities
    are to be selected for cost sharing, Schedule 12 distinguishes
    between “Required Transmission Enhancements,” which are
    included in the Regional Plan, and “Regional Facilities”
    selected for cost sharing. See Tariff, Schedule 12(b)(i) (J.A.
    58–59). The amendment qualifies this scheme by stating that
    some “Required Transmission Enhancements”—those
    included in the Regional Plan to satisfy only individual
    utilities’ planning criteria—do not qualify for cost sharing. See
    Tariff, Schedule 12(b)(xv) (J.A. 71–72).            Because the
    amendment         applies    to     “Required      Transmission
    Enhancements,” which are not necessarily selected for cost
    sharing, it does not create a category of facilities selected for
    cost sharing but exempted from the approved cost-sharing
    formula.
    Although we reject the intervenors’ proposed construction
    of the amendment, their argument does highlight something
    unusual about Order No. 1000—it requires a pre-approved
    formula for projects “selected” by member utilities for regional
    cost sharing, and it requires the formula to be consistent with
    the cost-causation principle, but it appears largely silent on
    which projects may or must be selected for cost sharing. We
    elaborate on that point below.
    12
    III
    Dominion contends that FERC arbitrarily violated the
    cost-causation principle by accepting the tariff amendment and
    applying it to prevent any cost sharing for the two high-voltage
    projects at issue here. As noted above, the cost-causation
    principle requires “comparing the costs assessed against a party
    to the burdens imposed or benefits drawn by that party.”
    Midwest ISO Transmission 
    Owners, 373 F.3d at 1368
    .
    Under the arbitrary-and-capricious standard of review, we
    uphold FERC decisions if the agency has “examined the
    relevant considerations and articulated a satisfactory
    explanation for its action, including a rational connection
    between the facts found and the choice made.” FERC v. Elec.
    Power Supply Ass’n, 
    136 S. Ct. 760
    , 782 (2016) (alterations
    adopted) (quoting Motor Vehicle Mfrs. Ass’n of the U.S., Inc.
    v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983)).
    Because this standard is deferential, we do not require FERC,
    in applying the cost-causation principle, to “utilize a particular
    formula,” Ala. Elec. 
    Co-op., 684 F.2d at 27
    , or to “allocate
    costs with exacting precision,” Midwest ISO Transmission
    
    Owners, 373 F.3d at 1369
    . However, we have set aside orders
    when FERC’s allocation of costs was either unreasonable, see
    Pac. Gas & Elec. Co. v. FERC, 
    373 F.3d 1315
    , 1322 (D.C. Cir.
    2004), or inadequately explained, see Sithe/Indep. Power
    Partners v. FERC, 
    285 F.3d 1
    , 4–5 (D.C. Cir. 2002). So too
    have other reviewing courts. See, e.g., Ill. Commerce Comm’n
    v. FERC, 
    756 F.3d 556
    , 565 (7th Cir. 2014); Ill. Commerce
    Comm’n v. FERC, 
    576 F.3d 470
    , 477–78 (7th Cir. 2009).
    A
    Application of the cost-causation principle is simple here,
    because this critical point is undisputed: high-voltage power
    lines produce significant regional benefits within the PJM
    13
    network, yet the amendment categorically prohibits any cost
    sharing for high-voltage projects like those at issue here.
    In the various proceedings below, no party challenged, and
    FERC did not disavow, any of its findings in the PJM
    Compliance Order. There, in approving the original Tariff, the
    Commission found that “high-voltage transmission facilities
    have significant regional benefits that accrue to all members of
    the PJM transmission system.” 142 FERC ¶ 61,214, P 413.
    According to FERC, these benefits include “improved
    reliability, reduced congestion, reduced power losses, greater
    carrying capacity, reduced operating reserve requirements, and
    improved access to generation.” 
    Id. P 414.
    FERC invoked
    these benefits in concluding that the postage-stamp component
    of the original cost-sharing formula—weighted at 50%—
    appropriately captured the “widespread, although difficult to
    quantify benefits” of high-voltage facilities. 
    Id. P 413.
    And it
    held that Schedule 12’s original cost-allocation formula was
    therefore consistent with the cost-causation principle. See 
    id. Historically, FERC
    has pressed this view even farther. For
    years prior to Order No. 1000, FERC took the position that the
    cost of high-voltage transmission lines within PJM should be
    shared based entirely on the postage-stamp method, on the
    theory that “everyone benefits from high-capacity transmission
    facilities because they increase the reliability of the entire
    network.” Ill. Commerce 
    Comm’n, 576 F.3d at 474
    . The
    Seventh Circuit twice set aside that position as going too far,
    see 
    id. at 476–78;
    Ill. Commerce 
    Comm’n, 756 F.3d at 565
    , but
    nothing in those decisions casts doubt on the unchallenged,
    narrower findings in the PJM Compliance Order.
    Given the significant regional benefits of high-voltage
    transmission lines, FERC’s decision to approve the amendment
    was arbitrary. As explained above, the amendment denies cost
    14
    sharing for all projects included in the Regional Plan only to
    satisfy the planning criteria of individual utilities—including
    for high-voltage lines. The amendment thus produces a severe
    misallocation of the costs of such projects. Here, for example,
    under the methodology previously endorsed by FERC as fairly
    matching costs to benefits, Dominion was estimated to enjoy
    only about 47% of the benefits from the Elmont-Cunningham
    project, and 43% of the benefits from the Cunningham-Dooms
    project. Yet, under FERC’s orders approving and applying the
    amendment, Dominion would have to pay all of the costs of
    both projects. This does not amount to a quibble about
    “exacting precision,” Midwest ISO Transmission 
    Owners, 373 F.3d at 1369
    , or a tempering of the cost-causation principle in
    pursuit of “competing goals,” S.C. Pub. Serv. Auth. v. FERC,
    
    762 F.3d 41
    , 88 (D.C. Cir. 2014). Rather, it involves a
    wholesale departure from the cost-causation principle, which
    would “shift a grossly disproportionate share of [the] costs” of
    these high-voltage projects into a single zone. Ill. Commerce
    
    Comm’n, 756 F.3d at 565
    .
    B
    In the administrative proceedings, FERC did not attempt
    to justify its orders as a lawful departure from the cost-
    causation principle. Instead, FERC asserted three possible
    grounds for reconciling its orders with that principle. None of
    them is persuasive.
    First, FERC noted that, of the 303 projects previously
    included in the Regional Plan based only on individual utilities’
    planning criteria, 98% of them produced only local benefits.
    Therefore, FERC reasoned, allocating all of the costs of these
    projects to the local utility at least roughly matched costs to
    benefits. See Cost-Allocation Order, 154 FERC ¶ 61,096,
    P 16.
    15
    FERC’s statistics misleadingly aggregate two very
    different categories of projects. As Commissioner LaFleur
    explained, the 98% of projects that produced no regional
    benefits involved low-voltage facilities. See Cost-Allocation
    Order, 154 FERC ¶ 61,096 (LaFleur, Comm’r, dissenting in
    part). Moreover, the Tariff had always allocated costs for these
    projects under the DFAX method, which resulted in all costs
    being allocated locally. See Tariff, Schedule 12(b)(ii)(A) (J.A.
    60–61). So, there never was any cost sharing for the 98% of
    owner-criteria projects that are low-voltage facilities. Rather,
    the entire purpose and effect of the amendment was to
    eliminate cost sharing for the other 2% of projects—which
    involve high-voltage facilities that FERC has recognized
    produce significant regional benefits.
    Of course, a regulator need not always carve out
    exceptions for arguably distinct subcategories of projects. But
    here, it is undisputed that high-voltage and low-voltage
    projects are significantly different with regard to which utilities
    benefit from them. Moreover, FERC itself has long recognized
    these differences in making appropriate cost allocations—
    including for PJM. See, e.g., PJM Compliance Order, 142
    FERC ¶ 61,214, PP 413–17; Ill. Commerce 
    Comm’n, 576 F.3d at 474
    –76. Thus, FERC could hardly say that trying to
    distinguish between high- and low-voltage facilities was not
    worth the trouble. Nor did FERC express any concern that
    Schedule 12, as originally approved, had proven inaccurate,
    administratively unwieldy, or otherwise problematic in
    distinguishing the two kinds of facilities. Rather, FERC’s
    reasoning would replace a cost-allocation formula about which
    FERC had expressed no concerns with another one that is less
    accurate overall, as well as grossly inaccurate with respect to
    high-voltage projects, in return for no countervailing
    regulatory benefit.
    16
    In a variation on this theme, FERC invokes the cost-
    allocation regime for another planning region in the Midwest.
    See Midwest Indep. Transmission Sys. Operator, Inc., 142
    FERC ¶ 61,215 (2013) (“MISO”), aff’d, MISO Transmission
    Owners v. FERC, 
    819 F.3d 329
    (7th Cir. 2016). In that region,
    80% of the projects at issue historically had at least 75% of
    their costs allocated locally. 
    Id. P 487.
    FERC then approved
    allocating all of these costs locally, and it concluded that the
    revised cost allocation was “roughly commensurate with the
    benefits.” 
    Id. P 518.
    FERC asserts that our case is even more
    straightforward, because 98% of the projects at issue had 100%
    of their costs allocated locally.
    Again, however, FERC combines dissimilar categories of
    projects. As explained above, the 98% of projects highlighted
    by FERC are low-voltage ones with no regional benefits,
    whereas the 2% of projects targeted by the amendment are
    high-voltage ones conceded by FERC to have significant
    regional benefits. Moreover, the MISO order was supported
    by a finding that the benefits of the projects at issue there were
    “realized primarily in the pricing zone in which the project is
    located.” 142 FERC ¶ 61,215, P 520. Here, by contrast,
    FERC’s only relevant finding was that the projects impacted
    by the amendment produced “significant regional benefits.”
    PJM Compliance Order, 142 FERC ¶ 61,214, P 413. In short,
    for purposes of cost causation, the local “baseline reliability
    projects” at issue in MISO are unlike the regional high-voltage
    facilities at issue here. See Midwest ISO Transmission 
    Owners, 819 F.3d at 335
    (“Baseline reliability projects differ from
    multi-value projects, which are larger, have a regional focus,
    and benefit from regional cost sharing.”).
    Second, FERC reasoned that projects included in the
    Regional Plan to satisfy only individual utilities’ planning
    criteria “are not needed to meet PJM regional criteria or NERC
    17
    reliability standards.” Cost-Allocation Order, 154 FERC
    ¶ 61,096, P 13. That is true, but the cost-causation principle
    focuses on project benefits, not on how particular planning
    criteria were developed. See, e.g., S.C. Pub. Serv. 
    Auth., 762 F.3d at 87
    ; Midwest ISO Transmission 
    Owners, 373 F.3d at 1368
    ; K N 
    Energy, 968 F.2d at 1300
    . Moreover, Form 715 is
    not limited to projects with purely local benefits. To the
    contrary, it implements Section 213(b) of the Federal Power
    Act, which requires utilities to inform FERC of all “potentially
    available transmission capacity and known constraints.” 16
    U.S.C. § 824l(b). In addition, under FERC regulations, utilities
    must submit “a detailed description of the transmission
    planning reliability criteria used to evaluate system
    performance.” New Reporting Requirement Implementing
    Section 213(b) of the Federal Power Act, 58 Fed. Reg. 52,420,
    52,421 (Oct. 8, 1993); see 18 C.F.R. § 141.300(a). Neither the
    statute nor the implementing regulation limits reportable
    criteria to those involving projects with only local benefits.
    Finally, FERC appears to claim affirmative support from
    its conclusion that the amendment is consistent with Order No.
    1000. See Cost-Allocation Order, 154 FERC ¶ 61,096, P 13 &
    n.16. As explained above, Order No. 1000 requires cost-
    sharing only for projects “selected in a regional plan for
    purposes of cost allocation,” 136 FERC ¶ 61,051, P 539, and
    the amendment effectively prevented the two projects at issue
    from being selected. However, compliance with Order No.
    1000 does not necessarily ensure compliance with the cost-
    causation principle—a pre-existing, more general rule that, in
    order to ensure just and reasonable rates, FERC must make
    some reasonable effort to match costs to benefits. See, e.g.,
    BNP Paribas 
    Energy, 743 F.3d at 268
    . Indeed, Order No. 1000
    itself recognized the cost-causation principle as a pre-existing
    and generally applicable rule. See 136 FERC ¶ 61,051, P 504.
    As explained above, we fail to see how a categorical refusal to
    18
    permit any regional cost sharing for an important category of
    projects conceded to produce significant regional benefits can
    be reconciled with the background principle. To the contrary,
    the cost-causation principle prevents regionally beneficial
    projects from being arbitrarily excluded from cost sharing—a
    necessary corollary to ensuring that the costs of such projects
    are allocated commensurate with their benefits.
    IV
    We are sensitive to the concern, pressed by Dayton and the
    other amici supporting FERC, that individual utilities should
    not have free rein to impose unjustified costs on an entire
    region by unilaterally adopting overly ambitious planning
    criteria. However, nothing we say here prevents PJM or its
    member utilities from amending the Tariff, the Operating
    Agreement, or PJM’s own planning criteria to address any
    problem of prodigal spending, to establish appropriate end-of-
    life planning criteria, or otherwise to limit regional cost
    sharing—as long as any amendment respects the cost-causation
    principle. Indeed, the cost-causation principle, by allocating
    project costs consistent with project benefits, creates the best
    incentives for PJM member utilities themselves to agree on
    when to invest their scarce resources in transmission
    improvements. Likewise, nothing we say prevents FERC from
    trimming excessive spending in the course of exercising its
    overarching mandate to ensure just and reasonable rates. See
    16 U.S.C. § 824d(a). Nor do we limit the ability of PJM or
    FERC to assess whether individual projects are in fact
    appropriate under the governing planning or reliability criteria.
    Finally, nothing we say constrains PJM’s or FERC’s ability to
    require competitive-bidding processes for regionally beneficial
    projects.
    19
    Instead, we hold only that FERC did not adequately justify
    its approval of the amendment at issue here, which prohibited
    cost sharing for a category of high-voltage projects conceded
    to have significant regional benefits, and which did so only
    because those projects reflected the planning criteria of
    individual utilities. The legal or economic merit of Dominion’s
    particular end-of-life planning criteria, and the appropriateness
    of the Elmont-Cunningham and Cunningham-Dooms projects
    under those criteria, remain open issues on remand.
    *         *        *        *
    The Commission acted arbitrarily and capriciously in
    approving the tariff amendment and applying it to the Elmont-
    Cunningham and Cunningham-Dooms projects. We therefore
    grant the petitions for review, set aside the orders under review
    to the extent that they approved the amendment and applied it
    to the two projects, and remand for further proceedings
    consistent with this opinion.
    So ordered.