Transcanada Power Marketing Ltd. v. Federal Energy Regulatory Commission ( 2015 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued September 15, 2015        Decided December 22, 2015
    No. 14-1103
    TRANSCANADA POWER MARKETING LTD.,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    ESSENTIAL POWER MASSACHUSETTS, LLC, ET AL.,
    INTERVENORS
    Consolidated with 14-1104, 14-1105
    On Petitions for Review of Orders of
    the Federal Energy Regulatory Commission
    Kenneth L. Wiseman argued the cause for petitioners.
    With him on the briefs were Mark Sundback, Allison
    Hellreich, William M. Rappolt, and Elizabeth W. Whittle.
    Carol J. Banta, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With her on
    the brief were David L. Morenoff, General Counsel, and
    Robert H. Solomon, Solicitor.
    2
    David T. Musselman and Cara J. Lewis were on the brief
    for intervenors The Essential Power Companies and PSEG
    Companies in support of respondent. Jodi L. Moskowitz
    entered an appearance.
    Before: TATEL and PILLARD, Circuit Judges, and
    EDWARDS, Senior Circuit Judge.
    Opinion for the Court filed by Senior Circuit Judge
    EDWARDS.
    EDWARDS, Senior Circuit Judge: In June 2013, pursuant
    to section 205(d) of the Federal Power Act (“FPA”), 16
    U.S.C. § 824d(d) (2012), the Independent System Operator
    for New England (“ISO New England”) filed a tariff revision
    with the Federal Energy Regulatory Commission
    (“Commission” or “FERC”). The tariff filing reflected ISO
    New England’s concern over “the region’s growing reliance
    on natural gas-fired generators, which can be vulnerable to
    supply shortages and price volatility. . . . [ISO New England]
    had found that many dual-fuel or oil-fired generators did not
    keep sufficient fuel supplies on hand to meet increased
    demand in extended or repeated periods of cold weather.
    Accordingly, [ISO New England] proposed [a] Winter
    Reliability Program [that] included an Oil Inventory Service
    component, which would compensate oil-fired and dual-fuel
    generators, selected through a bidding process, to maintain
    specified supplies of oil and to provide energy when system
    conditions were stressed.” Br. for Respondent at 3.
    On September 16, 2013, the Commission issued an Order
    Conditionally Accepting Tariff Revisions in Docket ER13-
    1851. This Order tentatively approved the Winter 2013-14
    Reliability Program (“Program”). In this same Order,
    however, FERC rejected the tariff proposal to allocate costs to
    3
    Regional Network Load (i.e., to transmission owners) as
    inconsistent with cost-causation principles and directed ISO
    New England to submit a compliance filing that would
    allocate the costs of the Program to Real-Time Load
    Obligation (i.e., to Load-Serving Entities). On October 7,
    2013, in Docket ER13-2266, the Commission issued an Order
    Accepting Bid Results, which effectively approved the
    Program and the results of ISO New England’s bid-selection
    process. On October 15, 2013, ISO New England submitted a
    compliance filing that explained how it had considered and
    selected the bids. On April 8, 2014, FERC issued orders
    denying requests for rehearing of the Orders issued in Docket
    ER13-1851 and Docket ER13-2266.
    On June 6, 2014, Petitioners TransCanada Power
    Marketing Ltd. (“TransCanada”) and the Retail Energy
    Supply Association filed petitions for review with this court
    challenging the Orders issued by FERC approving the Winter
    2013-14 Reliability Program. TransCanada, which is a Load-
    Serving Entity, principally contends that FERC’s actions
    should be overturned because, inter alia, (1) there was
    insufficient evidence in the record to allow FERC to
    determine whether the cost-based Program and resulting rates
    were just and reasonable; (2) FERC acted in contravention of
    cost causation principles when it allocated the costs of the
    Program to Load-Serving Entities; and (3) FERC abused its
    discretion in failing to consolidate the proceedings in Docket
    Nos. ER13-1851 and ER13-2266. The Retail Energy Supply
    Association, whose members include Load-Serving Entities,
    joins TransCanada only with respect to the issue relating to
    the allocation of cost.
    We decline to assess FERC’s conditional approval of the
    Program in Docket ER13-1851 because FERC made it clear
    that its decision was only tentative. Any alleged defects in the
    4
    Program were subject to challenge by interested parties and
    final review by FERC in Docket ER13-2266. Indeed, that is
    exactly what happened.
    The Commission’s decision regarding the allocation of
    the costs of the Program to Load-Serving Entities was a final
    action in Docket ER13-1851. It is therefore ripe for review.
    However, we find no merit in Petitioners’ challenges to the
    cost-allocation decision. The Commission reasonably
    explained that its decision, unlike the proposed alternative,
    adhered to cost-causation principles and agency precedent.
    We therefore deny the petitions for review of the cost-
    allocation decision in Docket ER13-1851.
    In Docket ER13-2266, FERC gave its stamp of approval
    to the Program and found that the arrangement pursuant to
    which suppliers would be compensated at their as-bid price
    was just and reasonable. TransCanada challenges FERC’s
    decision in Docket ER13-2266, principally on the ground that
    the record upon which FERC relied is devoid of any evidence
    regarding how much of the Program cost was attributable to
    profit and risk mark-up. TransCanada argues that, without this
    information, FERC could not properly assess whether the
    Program’s rates were just and reasonable. We agree and thus
    grant in part the petition for review of Docket ER13-2266.
    The case is hereby remanded to FERC so that it may either
    offer a reasoned justification for the Order or revise its
    disposition to ensure that the rates under the Program are just
    and reasonable.
    Because we remand only one of the two dockets, we need
    not address whether the Commission abused its discretion in
    declining to consolidate them.
    5
    I. BACKGROUND
    ISO New England is a “private, non-profit entity [that]
    administer[s] New England energy markets and operate[s] the
    region’s bulk power transmission system.” PSEG Energy Res.
    & Trade LLC v. FERC, 
    665 F.3d 203
    , 205-06 (D.C. Cir.
    2011) (alterations in original) (quoting Blumenthal v. FERC,
    
    552 F.3d 875
    , 878 (D.C. Cir. 2009)). To provide access to the
    transmission system, ISO New England sets rates “in a single,
    unbundled, grid-wide tariff.” See Braintree Elec. Light Dep’t
    v. FERC, 
    667 F.3d 1284
    , 1286 n.1 (D.C. Cir. 2012) (quoting
    NRG Power Mktg., LLC v. Me. Pub. Utils. Comm’n, 
    558 U.S. 165
    , 169 n.1 (2010)). “Under its tariff, ISO[] [New England]
    is obligated to assure that New England’s power supply
    ‘conforms to proper standards of reliability.’” 
    Id. (quoting ISO
    New England, Inc., Transmission, Markets, and Services
    Tariff § I.1.3 (“Tariff”)). ISO New England must file its tariff
    with the Commission for approval under section 205 of the
    FPA. Braintree Elec. Light Dep’t v. FERC, 
    550 F.3d 6
    , 9
    (D.C. Cir. 2008) (citing 16 U.S.C. § 824d(d)). The
    Commission can reject the proposed rates only if it finds that
    the rates are not “just and reasonable.” Atl. City Elec. Co. v.
    FERC, 
    295 F.3d 1
    , 9 (D.C. Cir. 2002) (citing 16 U.S.C. §
    824d(e)).
    A. The Winter 2013-2014 Reliability Program
    On June 28, 2013, ISO New England filed with the
    Commission proposed revisions to section III of its Tariff.
    The revisions, which were titled the “Winter 2013-14
    Reliability Program,” were intended to maintain system
    reliability during the 2013-2014 cold-weather months. In its
    filing, ISO New England explained that during the mild 2012-
    2013 winter, it had seen instances where generators had
    lacked sufficient fuel to allow for reliable operation during
    6
    extended periods of cold weather. Therefore, an immediate
    solution was needed to avoid serious threats to system
    reliability for the upcoming winter. The Program was
    designed to be a time-limited, discrete, out-of-market
    solution, which, in future years, would yield to a market-
    based solution.
    In order to better understand the Program, it is helpful to
    have at least a general sense of the New England region’s
    power system and electricity markets, as well as the parties
    who participated in or were affected by the Program. The
    following summary outlines the system and the principal
    parties:
    The Energy Pathway: First, a “generator” produces the
    required electric energy. Next, a “transmission owner” (i.e., an
    entity that owns and maintains transmission facilities)
    “transmits” the energy to a “local distributor” (also called a
    “network customer,” “transmission customer,” or “local public
    utility”). Finally, the local distributor “distributes” the energy
    to end-users. The amount of energy demanded by end-users is
    often called “Load.” This entire system (i.e., the network of
    facilities, equipment, and transmission lines) is called “the
    grid.”
    The Various Parties and “Load” Concepts:
       Load-Serving Entities (such as TransCanada) secure
    electric energy, transmission service, and related services
    to serve the demands of their customers. Load-Serving
    Entities sell the energy that they acquire pursuant to
    contracts with local distributors and end-users. After a
    local distributor or end-user purchases energy, the
    transmission owner transmits the energy to the local
    distributor, who then distributes it to the end-user.
    7
    Real-Time Load Obligation is a Load-Serving Entity’s
    total energy commitment for a certain time period. If the
    costs of the Program are allocated to Real-Time Load
    Obligation (which is fulfilled by Load-Serving Entities
    such as TransCanada), then the Load-Serving Entities
    assume the responsibility for the cost of the Program. The
    Load-Serving Entities try to recoup these costs from end-
    users under their existing contracts.
       Transmission Owners own the energy transmission lines
    that are used to transmit energy from the generators to the
    local distributors. This service is called “Regional
    Network Service.” Transmission owners charge Regional
    Network Service charges for their services.
    Regional Network Load: At any particular time, a certain
    amount of energy will require Regional Network Service.
    This energy is called Regional Network Load. If the
    Winter Reliability Program costs are allocated to Regional
    Network Load, then transmission owners bear those costs.
    Transmission owners, in turn, can recoup these costs
    through Regional Network Service charges.
       Independent System Operators (“ISOs”) are independent,
    federally regulated organizations formed at the
    recommendation of FERC to impartially coordinate,
    control, and monitor the operation of a regional bulk
    electric power system, including the dispatch of electric
    energy over the system, and the monitoring of the
    electricity markets to ensure the safety and reliability of
    the system.
       End-users are the consumers who use the energy.
    See the ADDENDUM for references that define and discuss the
    New England region’s power system, the principal parties in the
    system, and “load” concepts.
    8
    ****
    The Program proposed by ISO New England included an
    Oil Inventory Service component. ISO New England
    indicated that it would first solicit bids from oil-fuel and dual-
    fuel generators. The bid sheets would instruct generators to
    state the price at which they would agree to establish a
    specified quantity of fuel by December 1, 2013. ISO New
    England would then select generators (to provide up to 2.4
    million megawatt-hours (“MWh”) of energy) based on the
    following criteria:
    (a) Cost (dollars/MWh of providing the service);
    (b) Asset’s historical availability and performance;
    (c) Asset’s ability to respond within the Operating Day to
    contingencies and other changed conditions;
    (d) Diversity of location and sensitivity to North/South
    and East/West constraints;
    (e) Dual fuel capability; and
    (f) Replenishment capability.
    ISO New England retained discretion to accept or reject any
    and all bids received. Generators selected to participate in the
    Program would receive their “as-bid” price. Obligations
    would lapse on February 28, 2014, or on the date on which a
    generator had fully depleted its offered fuel inventory,
    whichever was earlier.
    ISO New England estimated that “the costs of providing
    the Winter Reliability Program services . . . [would] range
    9
    from $16 to $43 million.” ISO New England, Winter 2013-14
    Reliability Program Proposal 25 n.68 (June 28, 2013),
    reprinted in Joint Appendix 25 (citation omitted). It proposed
    allocating this cost to Regional Network Load, which is the
    energy that a transmission customer designates for
    transmission service. Tariff § I.2.2. As explained above,
    Regional Network Load is paid for by transmission owners,
    who, in turn, pass on the cost to transmission customers. ISO
    New England Inc., 144 FERC ¶ 61,204, 62,140 & n.54 (2013)
    (“Order Conditionally Accepting Tariff Revisions”). The
    alternative would have been to allocate the cost to Real-Time
    Load Obligation, which is paid for by Load-Serving Entities
    (i.e., suppliers who contract with distribution companies and
    end-users to provide energy). 
    Id. The term
    “Real-Time Load Obligation[], or Real-Time
    Load, refers to [a] load serving entit[y’s] [total energy]
    obligation . . . during a given hour of operation.” ISO New
    England, Inc., 115 FERC ¶ 61,145, 61,516 n.4 (2006) (“2005-
    2006 Order On Rehearing”) (citing Tariff § III.3.2.1(b)(i)).
    Although Real-Time Load costs may be unforeseeable, Load-
    Serving Entities are able to offset the risk of unanticipated
    costs by negotiating appropriate arrangements in their
    contracts with distribution companies and end-users. 
    Id. at 61,517.
    Due to the Program’s urgent nature, ISO New England
    requested the Commission to approve the Program prior to
    receiving information regarding the accepted bids. However,
    ISO New England acknowledged that the accepted bids would
    also require Commission approval, as those bids would
    constitute the Program’s rates. ISO New England agreed to
    provide not only the bid prices, but also a description of its
    evaluation process.
    10
    On August 26, 2013, ISO New England filed the bid
    results with the Commission. Of the 2.29 million MWh
    offered, ISO New England proposed accepting 1.995 million
    MWh at a price of $78.8 million – nearly double ISO New
    England’s estimated cost of providing Program services. ISO
    New England provided the Commission with information on
    the prices and energy amounts, stating that publication of
    more granular information might convey sensitive
    commercial information.
    B. The Commission’s Conditional Approval of the
    Program and Its Final Decision on Cost Allocation
    On September 16, 2013, the Commission issued an Order
    in Docket ER13-1851 conditionally approving the Program.
    Order Conditionally Accepting Tariff Revisions, 144 FERC ¶
    61,204. The Commission made it very clear that, apart from
    cost allocation, its approval of the principal aspects of the
    Program was tentative and subject to further review. On this
    point, the Commission said:
    ISO[] [New England]’s procurement decisions under
    the [Program] remain subject to Commission review.
    ISO[] [New England] is required to file . . . the
    results of the bid submission and selection process.
    
    Id. at 62,137.
    TransCanada also understood that, in
    conditionally approving the Program in Docket No. ER13-
    1851, “FERC had no evidence regarding the costs upon which
    a rate would be based. That evidence was to be submitted in
    Docket No. ER13-2266.” Br. of Petitioners at 28.
    In addition to tentatively approving the Program in
    Docket ER13-1851, FERC positively rejected ISO New
    England’s proposal to allocate cost to Regional Network
    11
    Load. Order Conditionally Accepting Tariff Revisions, 144
    FERC at 62,142. The Commission explained that, under cost-
    causation principles, the entities that benefit from the Program
    should bear its cost. 
    Id. On this
    point, FERC determined that
    the “Program does not address . . . a transmission-related
    concern,” and, therefore, costs should not be allocated to
    Regional Network Load. 
    Id. at 62,143.
    Rather, according to
    FERC, Load-Serving Entities benefit because the Program
    “protect[s] reliability by ensuring that sufficient energy will
    be available to satisfy the needs of entities that are obligated
    to serve load in New England.” 
    Id. at 62,142-43
    (quoting ISO
    New England, Inc., 113 FERC ¶ 61,220, 61,877 (2005)
    (“2005-2006 Order”)). Therefore, the Commission concluded
    that, “[b]ecause real-time load is the primary beneficiary, . . .
    [the] costs of the Program should be allocated to Real-Time
    Load Obligation.” 
    Id. at 62,142.
    In further support of its decision on cost allocation, the
    Commission looked to agency precedent. In particular, FERC
    noted that a “similar . . . time-limited, out-of-market . . .
    reliability measure[] directly benefitting real-time load” had
    been approved for the 2005-2006 winter, with the cost
    allocated to Real-Time Load Obligation. 
    Id. (citing 2005-
    2006 Order, 113 FERC ¶ 61,220). In light of this precedent,
    the Commission found no merit in the concerns raised by
    some parties that, because Load-Serving Entities could not
    foresee the Program’s cost, they would need to include risk
    premiums in their contracts. 
    Id. at 62,143.
    According to the
    Commission, risk premiums are the appropriate way for
    Load-Serving Entities to recoup such costs. See 2005-2006
    Order, 113 FERC at 61,878.
    On April 8, 2014, Petitioners’ requests for rehearing of
    the Commission’s Order in Docket ER13-1851 were denied.
    ISO New England Inc., 147 FERC ¶ 61,026 (2014) (“Order
    12
    Denying Rehearing of Tariff Revisions”). On June 6, 2014,
    Petitioners filed timely petitions for review with this court.
    C. The Commission’s Approval of the Program’s Rates
    On October 7, 2013, in Docket ER13-2266, the
    Commission issued an order approving the Program’s rates.
    ISO New England Inc., 145 FERC ¶ 61,023 (2013) (“Order
    Accepting Bid Results”). In response to concerns over the
    Program’s high cost, the Commission ordered ISO New
    England to explain, among other things, how it applied its bid
    selection criteria. 
    Id. at 61,103.
    ISO New England’s
    subsequent compliance filing indicated that it had first
    arranged the bid results by price, and then, based on a supply
    offer curve, had chosen a discernible breaking point from
    which to select the bid winners. ISO New England then had
    reviewed the remaining criteria and had determined that no
    changes to its selection were necessary. No party protested the
    compliance filing, which the Commission accepted by letter
    order on November 13, 2013.
    During the course of the proceedings in Docket ER13-
    2266, TransCanada argued that the record lacked information
    regarding the generators’ costs. Br. of Petitioners at 28, 38-41.
    According to TransCanada, such information was needed for
    the Commission to determine how much of the total cost of
    the Program was attributable to a profit and risk mark-up. 
    Id. at 42-43.
    To support this argument, TransCanada pointed to
    the large disparity between the Program’s estimated and
    actual cost as potential evidence of high mark-ups. 
    Id. at 33-
    38. The Commission was unpersuaded. On November 6,
    2013, TransCanada filed a timely request for rehearing of the
    Order Accepting Bid Results, which the Commission denied
    on April 8, 2014. ISO New England Inc., 147 FERC ¶ 61,027
    (2014) (“Order Denying Rehearing of Bid Results”).
    13
    In denying the request for rehearing, the Commission
    gave its final stamp of approval to the Program. 
    Id. FERC dismissed
    TransCanada’s main argument – that the
    Commission could not properly assess whether the Program’s
    rates were just and reasonable without inquiring into how
    much cost was attributable to a profit and risk mark-up:
    Under a competitive as-bid program in which
    resources are selected based on both price and non-
    price factors, it is reasonable that participants with
    greater reliability benefits will be paid higher prices,
    and the record in this case does not persuade us that
    participants included excessive profits “unrelated to
    actual risks and costs” in submitting their bids.
    
    Id. at 61,078
    (footnote omitted). The Commission simply
    stated that, after “balanc[ing] the actual costs . . . with the
    [Program’s pressing] need,” it had concluded that the
    Program’s rates were reasonable. 
    Id. On June
    6, 2014, TransCanada filed a timely petition for
    review with this court. The petitions for review of FERC’s
    decisions in Docket ER13-1851 and ER13-2266 were
    consolidated by the court. The Essential Power Companies
    and the PSEG Companies – organizations some of whose
    members include generators selected by ISO New England to
    participate in the Program – intervened on behalf of the
    Commission.
    II. ANALYSIS
    “We review final orders of the Commission under the
    arbitrary and capricious standard of the Administrative
    Procedure Act, 5 U.S.C. § 706(2)(A). An agency action will
    14
    be upheld if the agency articulate[d] a satisfactory explanation
    for its action including a rational connection between the facts
    found and the choice made. Motor Vehicle Mfrs. Ass’n of
    United States, Inc. v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983). The Commission’s factual findings will be
    upheld if supported by substantial evidence. 16 U.S.C. §
    825l(b).” FirstEnergy Serv. Co. v. FERC, 
    758 F.3d 346
    , 352
    (D.C. Cir. 2014) (alteration in original) (citation omitted).
    A. Docket ER13-1851
    Petitioners’ challenges to FERC’s decisions in Docket
    ER13-1851 focus on two claims: first, in conditionally
    approving the Program, “the Commission failed to adequately
    consider the costs of the Program before accepting it,” and
    second, FERC erred in ordering ISO New England to allocate
    Program costs to Real-Time Load Obligation. Order Denying
    Rehearing of Tariff Revisions, 147 FERC at 61,073; see also
    Br. of Petitioners at 16-17. We hold that the first claim is
    unripe for judicial review and that the second claim lacks
    merit.
    We decline to assess FERC’s conditional approval of the
    Program in Docket ER13-1851 because FERC made it clear
    that its decision was only tentative. Any alleged defects in the
    Program, apart from Petitioners’ challenges to cost allocation,
    were subject to final review by FERC in Docket ER13-2266.
    Petitioners clearly understood that, in conditionally approving
    the Program in Docket No. ER13-1851, “FERC had no
    evidence regarding the costs upon which a rate would be
    based. That evidence was to be submitted in Docket No.
    ER13-2266.” Br. of Petitioners at 28.
    Although FERC generally approved the Program in the
    Order Conditionally Accepting Tariff Revisions, the
    15
    Commission conditioned its final approval of the Program on
    review of ISO New England’s procurement process, bid
    results, and explanation of costs. In other words, it was not
    until FERC issued its Order in Docket ER13-2266, accepting
    ISO New England’s bid results, that the questions relating to
    the procurement process, bid results, and cost of the Program
    became live issues. The Commission’s Order in Docket
    ER13-2266 addressed the issues that arose from the
    Commission’s tentative approval of the Program in Docket
    ER13-1851.
    The Commission’s approach was made clear in its Order
    Accepting Bid Results. In that Order, FERC explained that in
    the earlier “September 16, 2013 Order, the Commission relied
    in part on the fact that ISO[] [New England] must submit the
    Bid Results (including a description of the evaluation
    process), considering the Tariff revisions as a whole and
    ISO[] [New England’s] own record statements regarding what
    the description would entail.” Order Accepting Bid Results,
    145 FERC at 61,102. In other words, no final approval of the
    Program would be given until FERC assessed ISO New
    England’s submissions on these matters. Indeed, as a part of
    the Order Accepting Bid Results, FERC required ISO New
    England to submit a compliance filing “further detailing its
    evaluation process in selecting winning bids.” 
    Id. Under 16
    U.S.C. § 825l(b), we have jurisdiction to review
    “an order issued by the Commission” that is challenged by an
    aggrieved party. Although the statute does not specifically
    limit our review to “final orders,” we have held that we will
    not entertain challenges to Commission decisions that are not
    ripe for review. For example, in OMYA, Inc. v. FERC, 
    111 F.3d 179
    (D.C. Cir. 1997) (per curiam), the court refused to
    “decide whether the economic analysis the Commission
    adopted . . . and applied in th[at] case, g[a]ve[] unequal
    16
    consideration to power purposes,” because “[t]he issue [was]
    not yet ripe.” 
    Id. at 182.
    The court explained that “[h]ow
    much each challenged requirement will cost [the petitioner] is
    not yet certain. Until these figures are set, any economic
    assessment of the conditions on the license would be
    speculative and premature.” 
    Id. Tellingly, the
    court found that
    the petitioner “may raise this issue before the Commission
    once the costs of each condition are established.” 
    Id. Likewise, in
    Northern Indiana Public Service Co. v. FERC,
    
    954 F.2d 736
    , 740 (D.C. Cir. 1992), we held that there was no
    agency decision ripe for review because the Commission
    merely approved the concept of a program but did not give its
    final authorization. These decisions are controlling here.
    TransCanada’s claims relating to ISO New England’s
    procurement process, bid results, and explanation of costs
    were properly raised and considered in conjunction with
    Docket ER13-2266. FERC did not purport to render any final
    decision on these matters in Docket ER13-1851, so it did not
    render a decision that was ripe for review.
    ****
    Petitioners’ second challenge to Docket ER13-1851 –
    that the Commission erred in ordering ISO New England to
    allocate Program costs to Real-Time Load Obligation – raises
    an issue that is ripe for review because FERC’s decision on
    this point was indisputably final. Nonetheless, we find no
    merit in Petitioners’ claim.
    Petitioners first allege that the Commission failed to
    evaluate, as required by section 205(e), whether allocating
    cost to Regional Network Load would be just and reasonable.
    We disagree. The Commission’s analysis in support of its
    decision is straightforward and reasonable. The Commission
    17
    noted that “Regional Network Load . . . is paid for by
    transmission owners,” Order Conditionally Accepting Tariff
    Revisions, 144 FERC at 62,140, but found that the “Program
    does not address . . . a transmission-related concern,” 
    id. at 62,143.
    In other words, the Commission found that ISO New
    England’s proposal violated principles of cost causation.
    While the Commission did not use the magic words “not just
    and reasonable,” 16 U.S.C. § 824d(a), this did not reflect a
    fatal flaw in its decision. See R.I. Consumers’ Council v.
    FPC, 
    504 F.2d 203
    , 213 n.19 (D.C. Cir. 1974) (holding that
    “an order is not invalidated by mere failure to use the magic
    words”); see also Interstate Nat. Gas Ass’n of Am. v. FERC,
    
    285 F.3d 18
    , 47 (D.C. Cir. 2002) (holding that no magic
    words were required under a similar provision of the Natural
    Gas Act); Papago Tribal Util. Auth. v. FERC, 
    723 F.2d 950
    ,
    956-58 (D.C. Cir. 1983) (no magic words required under a
    similar provision of the FPA).
    Petitioners also contend that end-users, and not Load-
    Serving Entities, are the real beneficiaries of the Program.
    Petitioners thus argue that Load-Serving Entities should not
    shoulder the burden of Program costs that they cannot easily
    pass on to end-users. In advancing this argument, Petitioners
    implicitly suggest that Real-Time Load refers solely to end-
    users. This assumption finds no support in the record.
    In its Order Conditionally Accepting Tariff Revisions,
    FERC explained:
    The Winter Reliability Program does not address, nor
    was it intended to address, a transmission-related
    concern. ISO[] [New England] proposed the Winter
    Reliability Program specifically to address concerns
    related to resource performance coupled with the
    18
    region’s increased dependence on natural gas, both of
    which are generation-related concerns.
    144 FERC at 62,143. The Commission explained further that
    the Program benefits Load-Serving Entities by ensuring that
    sufficient energy will be available for them to meet their
    obligations. 
    Id. at 62,142-43
    .
    The Commission’s decision was consistent with its
    precedent. In addressing the 2005-2006 Winter Package
    program, FERC explained:
    We disagree with [petitioner] that the Commission
    acted inconsistently with cost causation principles when
    it approved the proposal to allocate the cost . . . to Real-
    Time Load Obligations. Under cost causation principles,
    costs are allocated to the parties who cause the
    incurrence of such costs. Network Load, i.e.,
    transmission customers, do not cause ISO[] [New
    England] to posture generation resources in order to
    maintain the stability and reliability of the transmission
    system. [Load-Serving Entities], on the other hand,
    purchase power in the real time energy market to serve
    load and are, therefore, the entities that directly cause
    ISO[] [New England] to posture generation resources to
    ensure that the [Load Serving Entities] have adequate
    generation to meet their real time load obligations. Thus
    it is reasonable and consistent with cost causation
    principles to allocate these costs to [Load Serving
    Entities].
    2005-2006 Order On Rehearing, 115 FERC at 61,517. The
    simple point here is that because the Program was designed to
    allow Load-Serving Entities to meet their Real-Time Load
    19
    obligations, the Commission’s decision on cost allocation
    properly followed cost causation principles.
    Finally, FERC rejected Petitioner’s argument that it was
    unfair to impose the cost burden on Load-Serving Entities,
    especially on such short notice:
    We are also unpersuaded by ISO[] [New England]’s
    argument that the timing of the Program warrants
    allocating the costs to Regional Network Load. At the
    crux of ISO[] [New England]’s argument is a concern
    that the timing of the Program is unfair to [Load Serving
    Entities] because it imposes unavoidable costs on short
    notice. The Commission was similarly unpersuaded by
    this argument in the 2005-2006 Winter Package
    proceeding. While ISO[] [New England]’s timing of its
    filing is not ideal, and we encourage ISO[] [New
    England] to plan for future winters further in advance,
    that timing and admonition has no bearing upon the
    appropriate application of cost causation principles here.
    As the Commission previously explained in the Winter
    2005-2006 proceeding, [Load Serving Entities]
    “voluntarily assume Real-Time Load Obligation when
    entering into bilateral contracts with end-use
    customers[;]” those “contracts contain inherent risk
    associated with unforeseeable future costs, and we would
    expect that risk to be captured in bilateral contracts
    between [Load Serving Entities] and end-use customers.”
    Order Conditionally Accepting Tariff Revisions, 144 FERC at
    62,143 (alteration in original) (quoting 2005-2006 Order On
    Rehearing, 115 FERC at 61,517). We can find no flaws in this
    reasoning.
    20
    Petitioners contend that FERC’s reliance on the decision
    addressing the 2005-2006 Winter Package is misplaced. We
    disagree. The Commission’s explanation of its precedent is
    eminently reasonable. Furthermore, the decision in the case
    involving the 2005-2006 Winter Package surely does not
    compel the result that Petitioners seek in this case, and
    FERC’s rationale in support of its decision on cost allocation
    here easily survives review.
    In sum, we conclude that the Commission did not err in
    allocating the Program’s cost to Real-Time Load Obligation.
    B. Docket ER13-2266
    In its decision in Docket ER13-2266, the Commission
    approved ISO New England’s procurement process, bid
    selections, and Program rates. For the most part, we find
    FERC’s decisions in support of the Program to be clear, well
    supported, and reasonable. TransCanada raises one
    compelling concern, however.
    TransCanada points out that, in approving the Program,
    FERC relied on a record that is devoid of any evidence
    regarding how much of the Program cost was attributable to
    profit and risk mark-up. TransCanada reasonably contends
    that, without this information, FERC could not properly
    assess whether the Program’s rates were just and reasonable.
    This is a valid concern, and one that requires further
    consideration by FERC.
    In its Order Denying Rehearing of Bid Results, FERC
    said:
    As to TransCanada’s argument that the Commission
    failed to appropriately find that the rates associated with
    21
    the Bid Results are just and reasonable, we disagree. In
    addressing cost concerns, including concerns about the
    disparity between the estimated and actual overall costs
    of the Program, the Commission in the October 7, 2013
    Order emphasized that the Winter Reliability Program
    involved a novel approach to addressing reliability
    concerns, the costs of which could not be easily
    identified with certainty. In conditionally accepting the
    Bid Results, the Commission balanced the actual costs
    reflected in the Bid Results with the need to make such
    expenditures to address pressing reliability risks. The
    balancing of cost with other critical considerations is in
    keeping with the FPA, under which the Commission may
    consider a wide variety of factors in determining whether
    rates are just and reasonable. The mere fact that the
    actual costs of the program exceeded the cost estimate
    does not serve to make the Bid Results unjust and
    unreasonable. To that end, we are unpersuaded by
    TransCanada’s assertion that the disparity indicates that
    market participants included “excessive profit margins”
    in their bids. This argument is speculative and not based
    on any evidence in this proceeding. Under a competitive
    as-bid program in which resources are selected based on
    both price and non-price factors, it is reasonable that
    participants with greater reliability benefits will be paid
    higher prices, and the record in this case does not
    persuade us that participants included excessive profits
    “unrelated to actual risks and costs” in submitting their
    bids.
    147 FERC at 61,078 (footnotes omitted). In TransCanada’s
    view, this response is vague and evasive, and hardly the
    product of reasoned decision making. We agree that the
    Commission’s reasoning in response to the point raised by
    22
    TransCanada is inadequate to support a determination that the
    contested Program rates were just and reasonable.
    It is well established that the Commission must “respond
    meaningfully to the arguments raised before it.” Pub. Serv.
    Comm’n v. FERC, 
    397 F.3d 1004
    , 1008 (D.C. Cir. 2005). It is
    indisputable that, under established ratemaking principles,
    rates that permit excessive profits are not just and reasonable.
    Farmers Union Cent. Exch., Inc. v. FERC, 
    734 F.2d 1486
    ,
    1502-03 (D.C. Cir. 1984). To be sure, the Commission may
    determine rates via a variety of formulae, and rate
    determination methodologies may vary depending upon the
    circumstances of each case. Me. Pub. Utils. Comm’n v.
    FERC, 
    520 F.3d 464
    , 471 (D.C. Cir. 2008) (per curiam), rev’d
    in part on other grounds sub nom. NRG Power Mktg., 
    558 U.S. 165
    . Nevertheless, in all cases, the Commission must
    explain its reasoning when it purports to approve rates as just
    and reasonable.
    FERC’s brief argues that the Commission understood
    from the outset that the prospective costs of the Program
    would be difficult to estimate. Therefore, according to FERC,
    “the fact that the Program resulted in an actual cost higher
    than the estimate does not alone demonstrate that the Program
    design is unjust and unreasonable.” Order Denying Rehearing
    of Tariff Revisions, 147 FERC at 61,074. This argument is
    specious because it does not address the valid concern raised
    by TransCanada. The point made by TransCanada is not that
    the cost disparity rendered the rates per se unreasonable.
    Rather, the claim is that, considering this disparity, the
    Commission should have either inquired into the profit and
    risk mark-up or explained its decision not to do so.
    In its Order Denying Rehearing of Bid Results, the
    Commission rejected as “speculative and not based on any
    23
    evidence in this proceeding” any claim that the suppliers
    might have achieved “excessive profit margins” in their bids.
    147 FERC at 61,078. This is a perplexing response to the
    query raised by TransCanada. There is no doubt that there is
    no evidence in the record on profit margins – that is precisely
    the point being pressed by TransCanada. FERC does not say
    that the figures for profit and risk mark-up are unavailable.
    They simply never addressed the matter.
    The Commission also relies on the fact that, in approving
    the Program, it took non-cost criteria into account. As noted
    above, the Commission claimed that it “balanc[ed] [the actual
    cost] with other critical considerations,” such as the “pressing
    reliability risks.” Order Denying Rehearing of Bid Results,
    147 FERC at 61,078. FERC also asserted that ISO New
    England selected the bids based on “both price and non-price
    factors,” which made it “reasonable that participants with
    greater reliability benefits will be paid higher prices.” 
    Id. However, “when
    [the Commission] chooses to refer to non-
    cost factors in ratesetting, it must . . . offer a reasoned
    explanation of how the [relevant] factor[s] justif[y] the
    resulting rates.” Farmers 
    Union, 734 F.2d at 1502
    . Here, the
    Commission did not explain what its “balancing” entailed, or
    how it applied the non-cost factors. Rather, it simply
    concluded that the profit margins were not unreasonably high,
    without ever discussing the margins or their connections to
    particular suppliers.
    It is true that the Commission referred to “reliability
    benefits,” as if to suggest that certain suppliers should be free
    to command high prices because of their reliability. 147
    FERC at 61,078. But neither ISO New England nor FERC
    explained this in a way that demonstrates that there would be
    no excess of profits. This is not reasoned decision making.
    24
    Intervenors contend that Tejas Power Corp. v. FERC,
    
    908 F.2d 998
    , 1004 (D.C. Cir. 1990), permits the Commission
    to rely on competitive market forces to ensure that profits are
    not excessively high. Intervenors also point out that the
    Commission expressly referred to the Program as a
    “competitive as-bid program.” Order Denying Rehearing of
    Bid Results, 147 FERC at 61,078. The Commission, however,
    provided no explanation for why it believed that the Program
    was competitive. Nor did FERC purport to explain the
    economic forces that it believed restrained the suppliers in
    their confidential bid offers.
    In this case, the Program occurred outside of the usual
    ISO New England energy markets, and the Commission made
    no effort to define the relevant market or determine the
    participants’ market power. The Commission’s reference to a
    “competitive as-bid program,” without further explanation, is
    simply a talismanic phrase that does not advance reasoned
    decision making. See 
    Tejas, 908 F.2d at 1004-05
    (concluding
    substantial evidence did not support a finding that the market
    was competitive where the Commission had made no finding
    regarding market power).
    Because the Commission did not adequately explain its
    decision on this point, we are constrained to remand the case
    for further consideration.
    III. CONCLUSION
    For the reasons set forth above, we deny the petitions for
    review of the Commission’s Order in Docket ER13-1851. We
    grant in part the petition for review of the Commission’s
    Order in Docket ER13-2266, and remand the case to FERC so
    that it may either offer a reasoned justification for the Order
    or revise its disposition to ensure that the rates under the
    25
    Program are just and reasonable as required by 16 U.S.C. §
    824d.
    So ordered.
    26
    ADDENDUM
    The following materials variously define and discuss the
    New England region’s power system, the principal parties in
    the system, and “load” concepts:
    ISO New England Inc., 144 FERC ¶ 61,204, 62,140 & n.54,
    62,143 (2013) (discussing “Load-Serving Entities,” “Real-
    Time Load Obligation,” and “Regional Network Load”).
    ISO New England, Inc., 115 FERC ¶ 61,145, 61,516 n.4
    (2006) (defining “Real-Time Load Obligation”).
    ISO New England, Inc., Transmission, Markets, and Services
    Tariff
       § I.2.2 (defining “Network Customer,” “Regional
    Network Load,” and “Transmission Customer”).
    http://www.iso-ne.com/static-assets/documents/
    regulatory/tariff/sect_1/sect_i.pdf
       § II.11 (defining and explaining “Regional Network
    Service”).
    http://www.iso-ne.com/static-assets/documents/
    regulatory/tariff/sect_2/oatt/sect_ii.pdf
       § III.3.2.1(b)(i) (defining “Real-Time Load
    Obligation”).
    http://www.iso-ne.com/static-assets/documents/
    2014/12/mr1_sec_1_12.pdf
    “How Electricity Flows,” http://www.iso-ne.com/about/what-
    we-do/in-depth/how-electricity-flows-from-wholesale-to-
    retail (website provided by ISO New England) (providing an
    overview of the energy pathway in the New England region);
    27
    “Glossary       and        Acronyms,”        http://www.iso-
    ne.com/participate/support/glossary-acronyms         (website
    provided by ISO New England) (defining “Independent
    System Operator,” “Load-Serving Entity,” and “Transmission
    Owner”).