GSS Group Ltd. v. National Port Authority of Liberia , 822 F.3d 598 ( 2016 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued March 9, 2016                   Decided May 17, 2016
    No. 14–7041
    GSS GROUP LTD., ALSO KNOWN AS
    GLOBAL SECURITY SEALS GROUP LTD.,
    APPELLANT
    v.
    NATIONAL PORT AUTHORITY OF LIBERIA
    AND REPUBLIC OF LIBERIA,
    APPELLEES
    Appeal from the United States District Court
    for the District of Columbia
    (No. 1:12–cv–00332)
    Stanley McDermott III, pro hac vice, argued the cause for
    the appellant. Charles B. Wayne was with him on brief.
    Colleen E. Roh Sinzdak argued the cause for the
    appellees. Jessica L. Ellsworth was with her on brief.
    Before: HENDERSON, ROGERS and KAVANAUGH, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge HENDERSON.
    2
    KAREN LECRAFT HENDERSON, Circuit Judge: GSS
    Group, Ltd. (GSS), a construction company incorporated in
    the British Virgin Islands and headquartered in Israel, appeals
    the district court’s dismissal of its second attempt to confirm a
    $44 million arbitral award entered against the National Port
    Authority of Liberia (Port Authority) for breach of a
    construction contract. When GSS first tried to confirm the
    award, the district court found, and we affirmed, that it had no
    personal jurisdiction over the Port Authority. When GSS
    filed its second petition, it named not only the Port Authority
    but also the Republic of Liberia, which owns the Port
    Authority, as respondents. The district court again dismissed
    GSS’s petition, finding that issue preclusion barred re-
    litigating its personal jurisdiction over the Port Authority and
    that GSS failed to demonstrate that Liberia was liable for the
    Port Authority’s alleged breach. For the reasons stated below,
    we affirm.
    I. BACKGROUND
    Although resolution of this case is ultimately
    straightforward, the history leading to our disposition is not.
    Three district court orders 1 and one opinion from this Court 2
    have set out the relevant background but a refresher is
    nonetheless needed for completeness.
    1
    See GSS Grp. Ltd. v. Nat’l Port Auth. (GSS Grp. I), 
    774 F. Supp. 2d 134
    (D.D.C. 2011) (order dismissing first petition); GSS Grp. Ltd. v. Nat’l
    Port Auth. (GSS Grp. II), No. 09-cv-1322 (D.D.C. Aug. 10, 2011) (order
    denying GSS’s motion to alter or amend judgment); GSS Grp. Ltd. v.
    Republic of Liber. (GSS Grp. IV), 
    31 F. Supp. 3d 50
    (D.D.C. 2014) (order
    dismissing second petition).
    2
    See GSS Grp. Ltd v. Nat’l Port Auth. (GSS Grp. III), 
    680 F.3d 805
    (D.C. Cir. 2012).
    3
    A. FACTUAL BACKGROUND
    The contract dispute at issue has its genesis in the turmoil
    following Liberia’s Second Civil War. After four years of
    conflict, two separate rebel groups besieged Monrovia,
    Liberia’s capital, in 2003. Within months, Liberian President
    Charles Taylor was exiled and the separate political factions
    signed a Comprehensive Peace Agreement. The Peace
    Agreement created the National Transitional Government of
    Liberia, a power-sharing entity designed to govern the
    recovering nation until it could hold democratic elections.
    Monitoring and enforcing the Peace Agreement became the
    responsibility of the International Contact Group on Liberia
    (ICGL), a multi-national advisory board led by the United
    States and including members of the United Nations, the
    European Union, the Economic Community of West African
    States and the World Bank.
    The Peace Agreement also created the Liberian Contract
    & Monopolies Commission (Commission) to combat the
    corruption and mismanagement that had plagued the nation.
    The Peace Agreement authorized the Commission to ensure
    that “all public financial and budgetary commitments entered
    into by the” National Transitional Government are
    “transparent, non-monopolistic and in accordance with the
    laws of Liberia and internationally accepted norms of
    commercial practice.” Comprehensive Peace Agreement, art.
    XVII(2)(a).      To accomplish its goal, the Commission
    promulgated Liberia’s Interim Public Procurement Policy and
    Procedures (Interim Procedures), which set out ground rules
    for, inter alia, state procurement of contracts for goods and
    services.
    During Liberia’s transition period, revitalizing the war-
    ravaged Monrovian Port (Port) became a priority. The
    4
    responsibility of doing so fell to the Port Authority, a wholly
    Liberian-owned corporation that manages, operates and
    maintains all Liberian ports. Created as “a distinct juridical
    entity with the capacity to enter into contracts and to sue and
    be sued in its own name,” GSS Grp. 
    IV, 31 F. Supp. 3d at 55
    ,
    the Port Authority functions “at some remove from the
    government itself,” GSS Grp. 
    III, 680 F.3d at 808
    . For
    instance, it enjoys expansive financial and administrative
    authority and has exclusive control over all funds it generates.
    Its Board of Directors is primarily comprised of Liberian
    government officials and individuals appointed by Liberia’s
    president.
    On June 9, 2005, the Port Authority awarded GSS a
    multi-million-dollar contract to build a container park at the
    Port. Although the Interim Procedures mandated that the Port
    Authority award such contracts through “open competitive
    bidding,” Interim Procedures 3 (Joint App’x (J.A.) 535), the
    Port Authority did not do so. As a result, on June 23, 2005,
    the Commission informed the Port Authority that the GSS
    contract was invalid and reminded it that all contracts must
    result from competitive bidding.
    Instead of conducting a bid, the Port Authority petitioned
    the Commission for a single-source exemption, which allows
    a Liberian entity to dispense with competitive bidding if, inter
    alia, “there is an urgent need” for the contract and “engaging
    in bid proceedings . . . is impractical due to unforeseeable
    circumstances.” 
    Id. at 12–13
    (J.A. 544–45). The Port
    Authority urged the Commission that any further delay in
    construction of the container park could result in the Port’s
    closure and that the contract would help the Port comply with
    the International Ship and Port Facility Security Code. The
    Commission granted the exemption on August 12, 2005, and
    the parties re-negotiated the contract 10 days later.
    5
    The GSS contract aroused the international community’s
    interest. The ICGL reviewed the contract and came away
    with “deep concerns” about its validity and monetary value.
    Letter from ICGL to Charles Gyude Bryant, Chairman of
    Nat’l Transitional Gov’t of Liber., at 1 (Oct. 19, 2005) (J.A.
    220). It notified the National Transitional Government by
    letter dated October 19, 2005, stating that, in its view, the
    Commission should not have granted the Port Authority the
    exemption and that the contract represented poor value for
    money. Aware of the scrutiny, GSS and the Port Authority
    amended the contract again on October 28, 2005. Their
    efforts failed.    On December 30, 2005, the National
    Transitional Government’s Chairman directed the Port
    Authority to cancel the GSS contract. The letter stated:
    I have taken off considerable time to carefully
    review the analysis of my technical team
    regarding equitable benefits to all parties
    resulting from the contract entered into
    between the [Port Authority] and the GSS.
    Our evaluation shows that the contract as
    negotiated and concluded places the Port
    Authority in a grossly disadvantageous
    position for more than a decade. Additionally,
    the contract does not contribute in any material
    way to compliance with the [International Ship
    and Port Facility Security] regulations and as
    such Security Qualification of the Free Port of
    Monrovia still remains.
    I am therefore directing that the GSS contract
    be cancelled and the Port Authority work[]
    toward a more holistic management contract
    that will improve operational, financial and
    security efficiency levels. The sourcing of any
    6
    managing team must be done through a
    competitive bidding process after proper terms
    of reference are agreed upon and approved by
    the . . . Commission     and     the technical
    committee of the [Economic Governance
    Steering Committee].[3] The GSS shall be free
    to submit an offer at that time.
    Letter from Charles Gyude Bryant, Chairman of Nat’l
    Transitional Gov’t of Liber., to D. Masuleng Coop, Chairman
    of Nat’l Port Auth. (Dec. 30, 2005) (J.A. 977). On January 3,
    2006, the Port Authority sought reconsideration from the
    National Transitional Government. The record does not
    reflect whether the Port Authority’s request prompted a
    response. On January 16, 2006, the National Transitional
    Government abdicated its power and Liberia’s newly elected
    government assumed control.
    On January 26, 2006, the Port Authority informed GSS,
    via letter, that it was cancelling the contract. A rapid volley
    of correspondence between GSS and the Port Authority
    ensued, culminating in a February 16, 2006 letter from the
    3
    The Economic Governance Steering Committee (EGSC) was one
    of two organizations created in 2005 as part of an agreement between the
    ICGL and the National Transitional Government called the “Governance
    and Economic Management Assistance Program” (GEMAP). The
    GEMAP’s goal “was to promote accountability and transparency in fiscal
    management by setting in place internal governmental controls and
    providing for international involvement, all while recognizing and
    preserving Liberian sovereignty.” Aff. of O. Natty B. Davis II, Republic
    of Liber.’s Minister of State, ¶ 12 (J.A. 244). The EGSC, whose
    membership consisted of Liberian government officials as well as
    representatives from the United States (including the United States
    Ambassador to Liberia), the EU, the World Bank and other international
    stakeholders, was the body designed to provide the international
    involvement contemplated by the GEMAP.
    7
    Port Authority explaining that the Interim Procedures demand
    complete transparency and adherence to open bidding and
    concluding that the GSS contract fell well short of those
    standards. It further explained that the Commission only
    granted the single-source exemption because it mistakenly
    thought the contract was necessary to comply with
    international obligations and to avoid the Port’s closure. 4
    Because the exemption was mistakenly granted, the Port
    Authority considered the contract “null and void ab initio.”
    GSS Grp. 
    IV, 31 F. Supp. 3d at 56
    (citation omitted).
    On March 15, 2006, GSS invoked the contract’s
    arbitration clause (which provided that disputes arising under
    the agreement were to be arbitrated in London and in
    accordance with the laws of England and Wales) against the
    Port Authority, but not against Liberia. Meanwhile, a
    separate Liberian governmental organization—the Liberian
    Public Procurement and Concession Commission5—sought a
    Liberian-court declaration that the contract, including the
    arbitration provision, was invalid. Because of the Liberian
    judicial proceedings, the Port Authority declined to participate
    in the London arbitration and GSS appointed the sole
    arbitrator. On February 8, 2008, the Liberian court found the
    4
    According to the Port Authority, the Commission’s mistake was
    caused by a $30,000 bribe that GSS paid the Port Authority’s then-
    managing director to convince the Commission that an urgent need for the
    requested single-source exemption existed.
    5
    Formed in 2005, the Liberian Public Procurement and Concession
    Commission’s mission is “to ensure the economic and efficient use of
    public funds in public procurement and to ensure that public procurement
    and concession processes are conducted in a fair, transparent and non-
    discriminatory manner.” Frequently Asked Questions about PPCC, Public
    Procurement & Concessions Commission, Gov. of the Republic of Liber.,
    http://www.ppcc.gov.lr/content.php?sub=67&related=1&third=67&pg=sp
    (last visited May 9, 2016).
    8
    relevant portions of the contract unenforceable.
    Notwithstanding the Liberian court’s decision, one month
    later, the arbitrator determined that he had jurisdiction of the
    dispute; in June 2008, he concluded that the Port Authority
    was liable for the cancellation and in May 2009, he found that
    GSS suffered damages in the amount of $44,347,260.00.
    B. GSS’S FIRST PETITION TO CONFIRM
    LONDON ARBITRAL AWARD
    On June 16, 2009, GSS filed a petition in the United
    States District Court for the District of Columbia to confirm
    the London arbitral award. 6 The Port Authority moved to
    dismiss the petition on the ground that, inter alia, it had no
    contact whatsoever with the United States (much less the
    District of Columbia) and therefore the district court lacked
    personal jurisdiction. GSS responded that the Port Authority,
    a wholly state-owned enterprise, was not a “person” within
    the meaning of the Due Process Clause and, accordingly, had
    no right to assert a personal-jurisdiction defense. GSS Grp. 
    I, 774 F. Supp. 2d at 138
    .
    The district court rejected GSS’s argument, finding that,
    although a foreign sovereign is not a person under the Due
    Process Clause, the Port Authority “functions more like a
    6
    Statutory subject matter jurisdiction of GSS’s petition is based on
    the Federal Arbitration Act (FAA), 9 U.S.C. §§ 201 et seq, which codifies
    the 1958 Convention on the Recognition and Enforcement of Foreign
    Arbitral Awards (Convention), June 10, 1958, 21 U.S.T. 2517, 330
    U.N.T.S. 3. The Convention, in turn, obligates each contracting nation
    (including the United States) to “recognize [foreign] arbitral awards as
    binding and enforce them in accordance with” local law. 
    Id. art. III.
    Because the United Kingdom is also a party to the Convention, the FAA
    provides U.S. courts with authority to enforce the London arbitral award
    (notwithstanding neither the arbitral award nor the GSS contract has any
    United States connection).
    9
    private corporation” and, accordingly, has due process rights.
    
    Id. at 141.
    Because GSS made no attempt to show that the
    Port Authority had any United States contacts, the district
    court dismissed GSS’s petition for lack of personal
    jurisdiction. In so doing, the district court observed that,
    “[f]or unknown reasons,” GSS declined to argue that the Port
    Authority and Liberia “are legally indistinguishable.” 
    Id. at 138–39.
    GSS moved for reconsideration under Rule 59(e). In its
    motion, GSS argued for the first time that the Port Authority
    was Liberia’s agent and that it was entitled to discovery to
    demonstrate the same. The district court found that GSS had
    waived the arguments by failing to raise them earlier.
    GSS appealed the dismissal and, on May 25, 2012, we
    affirmed in toto. As a threshold matter, we agreed that GSS
    had waived its agency and jurisdictional-discovery arguments.
    We then rejected the only argument GSS had preserved—that
    a foreign, state-owned entity has no due process rights—and
    affirmed the district court’s dismissal because GSS had failed
    to identify “any connection” between the United States and
    the Port Authority. GSS Grp. 
    III, 680 F.3d at 817
    (emphasis
    in original).
    C. GSS’S SECOND PETITION TO CONFIRM
    LONDON ARBITRAL AWARD
    On March 1, 2012 (one day before oral argument here in
    GSS’s appeal of the dismissal of its initial petition), GSS filed
    in district court a second petition to confirm the award. This
    time, however, GSS named Liberia as the sole respondent; 7
    7
    As noted above, 
    see supra
    n.6, the FAA provided the subject matter
    jurisdiction for GSS’s first position, which named the Port Authority as
    the sole respondent. Because GSS named Liberia, a foreign sovereign, as
    10
    three weeks later, it amended the petition to add the Port
    Authority. The thrust of GSS’s second petition was that the
    Port Authority was Liberia’s agent and, accordingly, Liberia
    was liable for the $44 million London award. Because
    Liberia, as a sovereign, may not assert a personal-jurisdiction
    defense, GSS believed that its second petition cleared the
    hurdle that blocked its first. It also served both the Port
    Authority and Liberia with discovery requests to clarify their
    inter se connection.
    The district court was not persuaded. It began with the
    Port Authority’s amenability to suit, concluding that its
    dismissal of GSS’s first petition on the “no personal
    jurisdiction” ground precluded GSS’s second attempt to sue
    the Port Authority in federal court. Despite GSS’s contention
    that the district court did not resolve its agency argument
    when it dismissed GSS’s first petition, the district court
    concluded that collateral estoppel barred issues—not simply
    specific arguments—that had been necessarily decided in
    earlier proceedings. And because “GSS enjoyed every
    the respondent in its second petition, GSS argued that the district court had
    subject matter jurisdiction under the Foreign Sovereign Immunities Act
    (FSIA), 28 U.S.C. §§ 1330 et seq. Under the FSIA, a foreign state, as well
    as its agencies and instrumentalities, is presumed to enjoy sovereign
    immunity from suit in U.S. courts unless one of several statutory
    exceptions applies. See 
    id. § 1604.
    One exception—the only one
    applicable here—is the “arbitration exception,” which provides that “[a]
    foreign state shall not be immune from the jurisdiction of courts of the
    United States . . . in any case . . . in which the action is brought [to enforce
    an arbitration agreement or award that] is or may be governed by a treaty
    or other international agreement in force for the United States calling for
    the recognition and enforcement of arbitral awards.” 
    Id. § 1605(a)(6)(B);
    see also 28 U.S.C. § 1330(a) (district court has subject matter jurisdiction
    of “any nonjury civil action against a foreign state . . . as to any claim for
    relief in personam with respect to which the foreign state is not entitled to
    immunity”).
    11
    opportunity to rely on a theory of agency when it earlier
    litigated the issue of personal jurisdiction,” GSS Grp. 
    IV, 31 F. Supp. 3d at 61
    , the district court applied the issue
    preclusion bar.
    The district court also held that it had no subject matter
    jurisdiction of Liberia. It noted that GSS had to overcome the
    presumption that “government instrumentalities established as
    juridical entities distinct and independent from their
    sovereign”—like the Port Authority—“should normally be
    treated as such.” 
    Id. at 62
    (quoting First Nat’l City Bank v.
    Banco Para El Comercio Exterior de Cuba (Bancec), 
    462 U.S. 611
    , 626–27 (1983)). To do so, GSS had to demonstrate
    either that the Port Authority was Liberia’s agent or that
    treating the Port Authority as distinct from Liberia would
    perpetuate fraud or injustice. The district court found that
    GSS had demonstrated neither.
    To support its agency argument, GSS proffered that
    Liberia controlled the Port Authority’s board of directors; that
    Liberia had assumed a portion of the Port Authority’s
    outstanding debt; that, when the Port Authority contracted
    with a third party to replace the GSS contract in 2010, several
    Liberian government officials, including the Liberian
    president, executed the new agreement; and that Liberia
    forced the Port Authority to cancel the contract. The district
    court found that GSS’s first three arguments were either
    foreclosed by Transamerica Leasing, Inc. v. La Republica de
    Venezuela, 
    200 F.3d 843
    (D.C. Cir. 2000), or not probative of
    Liberia’s control over the Port Authority in 2005–06. It also
    rejected the argument that the directive to the Port Authority
    to cancel the contract created an agency relationship. In so
    doing, it noted that the Port Authority independently
    negotiated and executed the contract and that Liberia’s
    12
    cancellation order was an act of government regulation, not
    commandeering.
    Having found that the Port Authority was not Liberia’s
    agent, the district court made quick work of GSS’s fraud or
    injustice argument. It first recognized that the requisite
    injustice occurs if, for example, a sovereign uses an
    instrumentality to shield itself from costs or risks, to unjustly
    enrich itself or to defeat a statutory policy. It then concluded
    that the “single sentence” GSS offered in support of its
    argument did not suffice to demonstrate injustice. GSS Grp.
    
    IV, 31 F. Supp. 3d at 68
    .
    The district court dismissed GSS’s petition in its entirety
    but did not address GSS’s discovery requests before it did so.
    GSS timely appealed. 8 Our review of the district court’s issue
    preclusion determination, see Hall v. Clinton, 
    285 F.3d 74
    , 80
    (D.C. Cir. 2002), and its dismissal for lack of subject matter
    jurisdiction, see Transamerica Leasing, 
    Inc., 200 F.3d at 847
    ,
    is de novo. We review its denial of jurisdictional discovery
    for abuse of discretion. See Caribbean Broad. Sys., Ltd. v.
    Cable & Wireless P.L.C., 
    148 F.3d 1080
    , 1089 (D.C. Cir.
    1998).
    8
    On February 21, 2015, we held this case in abeyance pending the
    United States Supreme Court’s disposition of OBB Personenverkehr AG v.
    Sachs, 
    136 S. Ct. 390
    (2015). When the Supreme Court granted certiorari
    in OBB Personenverkehr AG, a potential issue was “[w]hether, for
    purposes of determining when an entity is an ‘agent’ of a ‘foreign state,’ ”
    the FSIA’s definition of “agency,” the factors set out in Bancec “or
    common law principles of agency” govern. Pet. for Writ of Cert. at i,
    OBB Personenverkehr AG v. Sachs (No. 13-1067), 
    2014 WL 890906
    at *i
    (Mar. 5, 2014). The Supreme Court ultimately failed to reach the issue.
    See OBB Personenverkehr 
    AG, 136 S. Ct. at 395
    .
    13
    II. ANALYSIS
    On appeal, GSS argues that: (1) the district court had
    subject matter jurisdiction of Liberia: the Port Authority was
    Liberia’s agent and failure to hold Liberia liable for the Port
    Authority’s contract cancellation would permit a miscarriage
    of justice; (2) the district court had personal jurisdiction of the
    Port Authority by virtue of its jurisdiction of Liberia and the
    district court erred by finding that issue preclusion barred the
    claim and (3) the district court abused its discretion by
    dismissing GSS’s petition before allowing GSS to conduct
    jurisdictional discovery. GSS’s appeal turns on whether the
    National Transitional Government’s December 30, 2005
    cancellation order justifies setting aside our general rule that
    “agencies and instrumentalities of a foreign nation are
    presumed to be separate from each other and from the foreign
    state.” Foremost-McKesson, Inc. v. Islamic Republic of Iran,
    
    905 F.2d 438
    , 440 (D.C. Cir. 1990).
    A. REPUBLIC OF LIBERIA
    GSS’s primary argument is that Liberia is liable for the
    Port Authority’s cancellation of the contract and, accordingly,
    the district court had subject matter jurisdiction of it pursuant
    to the FSIA’s arbitration exception. To satisfy its burden,9
    GSS must demonstrate either that Liberia controlled the Port
    Authority “so extensively” that the Port Authority became
    Liberia’s agent or that treating the Port Authority as legally
    separate from Liberia would allow fraud or injustice.
    Transamerica Leasing, 
    Inc., 200 F.3d at 848
    . GSS argues
    that it satisfies both exceptions, relying almost exclusively on
    9
    See Foremost-McKesson, 
    Inc., 905 F.2d at 447
    (“It is . . . clear that
    the plaintiff bears the burden of asserting facts sufficient to withstand a
    motion to dismiss regarding the agency relationship.” (emphasis in
    original)).
    14
    the National Transitional Government’s instruction to cancel
    the contract.
    1. Principal/Agency Relationship
    Our resolution of GSS’s agency argument begins and
    ends with our Transamerica Leasing, Inc. opinion. In that
    case, we explained that a plaintiff may demonstrate that an
    agency relationship exists in one of two ways. The first
    occurs if a sovereign asserts “complete domination” of a
    subsidiary. 
    Id. The second
    results from “ordinary agency
    principles,” which do not require a showing of “complete
    dominion.” 
    Id. at 849
    (emphasis added). GSS makes no real
    attempt to demonstrate that it satisfies the former, instead
    focusing its efforts on the latter.
    In Transamerica Leasing, Inc., we recognized that
    explaining the degree of control necessary to find agency is
    challenging.         See 
    id. Despite the
    caselaw’s
    “often . . . confusing results,” we discerned four prerequisites.
    
    Id. We held
    that no agency relationship arises unless (1) the
    sovereign makes plain its desire for the instrumentality to act
    on the sovereign’s behalf; (2) the instrumentality agrees to so
    act; (3) the sovereign has final say over matters delegated to
    the instrumentality and (4) the sovereign wields its power
    more directly than voting a majority of the instrumentality’s
    stock or choosing the instrumentality’s board of directors. 10
    
    Id. at 849
    –50. Based on these factors, GSS’s argument
    reduces to the following: Liberia ordered the Port Authority
    to cancel the contract and the Port Authority obliged;
    10
    See also RESTATEMENT (SECOND) OF AGENCY § 1 (“Agency is the
    fiduciary relation which results from the manifestation of consent by one
    person to another that the other shall act on his behalf and subject to his
    control, and consent by the other so to act.”).
    15
    therefore, Liberia had the requisite authority over the Port
    Authority to make the latter its agent. 11
    Superficially, GSS has a point—the National Transitional
    Government’s directive left the Port Authority with no
    discretion to ignore the cancellation order.          But in
    Transamerica Leasing, Inc., we recognized that a government
    can wield power not only “as shareholder” but also as
    
    “regulator.” 200 F.3d at 851
    . 12 And read in context, it is
    plain that the National Transitional Government was
    exercising its regulatory authority when it ordered the Port
    Authority to cancel the GSS contract—not commandeering
    the Port Authority in a way that erased the separate juridical
    boundaries between it and Liberia.
    Recall the situation in Liberia during which the contract
    emerged. Between 2003 and 2006, Liberia (and, especially,
    Monrovia) was struggling to recover not only from a four-
    year civil war but also from a history of government
    corruption and financial mismanagement.         To aid the
    recovery, the Commission promulgated Interim Procedures,
    which required state-owned corporations to obtain goods and
    services through competitive bidding.       When the Port
    Authority failed to do so, the Commission immediately
    advised the Port Authority that the procedural violation
    11
    See also Appellant’s Br. 9 (“In short, when Liberia directed the
    [Port Authority] to cancel the Project Agreement, Liberia acted as
    principal, the [Port Authority] was its agent, and that principal-agent
    relationship—manifest in the cancellation of the Project Agreement—
    satisfies the Bancec standard.”).
    12
    See also Transamerica Leasing, 
    Inc., 200 F.3d at 851
    (“[W]e
    cannot say that requiring a shipping company to obtain governmental
    approval for the sale of vessels represents the exercise of Venezuela’s
    authority as shareholder rather than its exercise of governmental power in
    the ordinary course of regulation.”).
    16
    rendered the contract invalid; in addition, the ICGL undertook
    its own review. The Commission’s grant of a single-source
    exemption did not erase the ICGL’s “deep concerns” about
    the contract’s validity and worth and these concerns prompted
    the ICGL to inform the National Transitional Government
    that the Commission should not have granted the exemption
    and that the contract as a whole disproportionately favored
    GSS at the Port Authority’s expense. Letter from ICGL to
    Charles Gyude Bryant, Chairman of Nat’l Transitional Gov’t
    of Liber., at 1 (Oct. 19, 2005) (J.A. 220). With the ICGL’s
    guidance in mind, the National Transitional Government then
    instructed the Port Authority to cancel the contract.
    The National Transitional Government’s December 30,
    2005 letter informed the Port Authority that it had not
    complied with a legal obligation, that it had not satisfied the
    requirement for an exemption therefrom and that it was to
    cancel the contract. This action is the quintessential function
    of a government regulator. Granted, one of the criticisms of
    the contract was “commercial,” Appellant’s Br. 20, but in our
    view, the concern that the contract placed “the Port Authority
    in a grossly disadvantageous position” was an outgrowth of
    Liberia’s broader regulatory goal of remedying past financial
    mismanagement.         Letter from Charles Gyude Bryant,
    Chairman of Nat’l Transitional Gov’t of Liber., to D.
    Masuleng Coop, Chairman of Nat’l Port Auth. (Dec. 30,
    2005) (J.A. 977). In any event, the National Transitional
    Government also ordered the contract’s cancellation because
    it did “not contribute in any material way to compliance with”
    the Port’s international responsibilities.      
    Id. Ensuring compliance
    with international obligations, and correcting a
    17
    state-owned instrumentality when it fails to do so, is a
    hallmark of a sovereign acting in its regulatory capacity. 13
    The National Transitional Government’s directive to the
    Port Authority to “work[] toward a more holistic management
    contract that will improve operational, financial and security
    efficiency levels” emphasized the importance of revitalizing
    the Port in a cost-effective manner, id.; moreover, its
    instruction that “[t]he sourcing of any managing team must be
    done through a competitive bidding process after proper terms
    of reference are agreed upon and approved by
    the . . . Commission and the technical committee of the
    EGSC” reminded the Port Authority of its responsibility to
    follow the Interim Procedures, 
    id. Critically, the
    National
    Transitional Government noted that GSS remained free to
    submit a bid for the contract so long as it complied with all
    applicable procedures. Allowing GSS the opportunity to
    secure the contract (through a competitive bid) underscores
    that Liberia’s interest was in ensuring that the Port Authority
    procured goods and services in accordance with the Interim
    13
    See, e.g., 46 U.S.C. § 42101 (“[T]he Federal Maritime
    Commission shall prescribe regulations affecting shipping in foreign
    trade, . . . to adjust or meet general or special conditions unfavorable to
    shipping in foreign trade, . . . which arise out of or result from laws or
    regulations of a foreign country or competitive methods, pricing practices,
    or other practices employed by owners, operators, agents, or masters of
    vessels of a foreign country.”); 
    id. § 42106(5)
    (“If the Federal Maritime
    Commission finds that conditions unfavorable to shipping in foreign trade
    as described in section 42101 of this title exist, the Commission
    may . . . take any [remedial] action the Commission finds necessary and
    appropriate to adjust or meet any condition unfavorable to shipping in the
    foreign trade of the United States.”).
    18
    Procedures and not in “wresting control of the . . . contract
    from the” Port Authority. Appellant’s Br. 21. 14
    GSS discusses (but does not emphasize) other factors
    that, in its view, demonstrate Liberia’s control of the Port
    Authority. None changes our conclusion. First, GSS argues
    that the Port Authority’s board of directors was controlled by
    Liberia but we have held that state stock ownership and board
    control is an inherent part of state-owned instrumentalities
    and, standing alone, does not create an agency relationship.
    See Transamerica Leasing, 
    Inc., 200 F.3d at 851
    . Next, GSS
    points out that Liberia absorbed $32.2 million of the Port
    Authority’s debt burden but we have held that a sovereign’s
    financial aid to an instrumentality is part and parcel of normal
    state ownership. 
    Id. at 852.
    Finally, GSS points to a 2010
    agreement that replaced the cancelled GSS contract, which
    agreement was executed by several Liberian government
    officials, including the Liberian president. But the 2010
    agreement sheds no light on the degree to which Liberia
    controlled the Port Authority when the Port Authority entered
    into and then cancelled the GSS contract in 2005–06.
    14
    GSS argues that “the principal Liberian regulator,
    the . . . Commission . . . had approved the Project Agreement before
    Liberia cancelled it, indicating that Liberia was not acting in any
    regulatory capacity when it did so.” Appellant’s Br. 10. But the
    Commission initially advised the Port Authority that the contract was
    invalid because it was not awarded through competitive bidding. The
    National Transitional Government also cited the Port Authority’s failure to
    comply with the competitive-bidding requirement when it ordered the
    contract’s cancellation; the only difference between its position and the
    Commission’s earlier position was that the National Transitional
    Government also concluded that the contract did not qualify for a single-
    source exemption.
    19
    2. Fraud or Injustice
    GSS also argues that respecting the boundaries between
    Liberia and the Port Authority would perpetuate fraud or
    injustice. It relies on the Fifth Circuit’s opinion in Bridas
    S.A.P.I.C. v. Government of Turkmenistan (Bridas I), which
    held that a sovereign can be liable for its instrumentality’s
    acts if the sovereign completely controlled the instrumentality
    “with respect to the transaction at issue” and exercised its
    dominion to commit a “fraud or wrong.” 
    345 F.3d 347
    , 359
    (5th Cir. 2003). In GSS’s view, Liberia dominated the Port
    Authority “with respect to” the contract and the Port
    Authority’s cancellation was a “remediable wrong.”
    Appellant’s Br. 31–32. This argument is without merit. The
    Fifth Circuit explained that the requisite “wrong” must
    constitute either “fraud” or “misuse of the corporate form to
    promote injustice,” Bridas S.A.P.I.C. v. Gov’t of Turkm.
    (Bridas II), 
    447 F.3d 411
    , 416–17 (5th Cir. 2006), and not
    simply a run of the mill alleged contractual breach. This case
    is not the “exceptional case[]” to which Bridas I may apply.
    Bridas 
    II, 447 F.3d at 416
    .
    For the foregoing reasons, we affirm the district court’s
    dismissal of the claims against Liberia for lack of subject
    matter jurisdiction under the FSIA.
    B. PORT AUTHORITY
    GSS also argues that issue preclusion does not bar its
    claims against the Port Authority because its claims against
    Liberia differ from its claims against the Port Authority and
    jurisdiction over Liberia necessarily confers jurisdiction over
    the Port Authority. Based on our conclusion that Liberia is
    not subject to suit in a United States court, GSS’s argument
    regarding the Port Authority fails. We note, however, that the
    district court’s issue preclusion analysis is plainly correct.
    20
    Preclusion applies if a later argument “is related to the
    subject-matter and relevant to the issues that were litigated
    and adjudicated previously, so that it could have been raised.”
    
    Hall, 285 F.3d at 81
    (quoting Yamaha Corp. of Am. v. United
    States, 
    961 F.2d 245
    , 257–58 (D.C. Cir. 1992) (emphasis
    omitted)); see also Yamaha 
    Corp., 961 F.2d at 254
    (“[O]nce
    an issue is raised and determined, it is the entire issue that is
    precluded, not just the particular arguments raised in support
    of it in the first case.” (emphases in original)). GSS could
    have raised the agency argument in its first petition; it
    eventually did raise the argument but too late to avoid waiver.
    Accordingly, we again affirm the district court’s dismissal of
    GSS’s petition against the Port Authority.
    C. JURISDICTIONAL DISCOVERY
    Finally, GSS offers two sentences in support of its
    argument that the district court erred by dismissing its petition
    before allowing jurisdictional discovery.              We are
    correspondingly brief in concluding that, without more,
    GSS’s two-sentence claim does not suffice and, thus, the
    district court committed no abuse of its wide discretion.
    For the foregoing reasons, we affirm the district court’s
    dismissal of GSS’s petition.
    So ordered.