City of Oberlin, Ohio v. FERC ( 2019 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued May 6, 2019                 Decided September 6, 2019
    No. 18-1248
    CITY OF OBERLIN, OHIO,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    NEXUS GAS TRANSMISSION, LLC,
    INTERVENOR
    Consolidated with 18-1261
    On Petitions for Review of Orders of
    the Federal Energy Regulatory Commission
    Carolyn Elefant argued the cause for petitioners. With her
    on the briefs were Aaron Ridenbaugh and David A. Mucklow.
    Carol J. Banta, Senior Attorney, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were James P. Danly, General Counsel,
    and Robert H. Solomon, Solicitor.
    2
    David A. Super argued the cause for intervenor. With him
    on the brief were Kevin A. Ewing and Britt Cass Steckman.
    Before: ROGERS, SRINIVASAN, and WILKINS, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge WILKINS.
    Concurring Opinion filed by Circuit Judge ROGERS.
    WILKINS, Circuit Judge: In reviewing an agency’s
    justifications for its actions, principles of administrative law
    demand, sensibly, that we strike a balance. On the one hand,
    we must not micromanage. Agencies are the experts and
    requiring full exposition at every turn would impede their
    ability to carry out their specialized statutory duties. On the
    other hand, we must insist on reasoned justifications.
    The instant matter asks us, once again, to perform this
    balancing act. Petitioners are the City of Oberlin, Ohio, and the
    Coalition to Reroute Nexus, an organization of landowners.
    They ask us to vacate the Federal Energy Regulatory
    Commission’s order authorizing Nexus Gas Transmission,
    LLC, to construct and operate an interstate natural gas pipeline
    and exercise the right of eminent domain to acquire any
    necessary rights-of-way. Petitioners also ask us to vacate the
    Commission’s order denying their requests for rehearing. In
    short, Petitioners complain that the Commission’s orders
    allowed the pipeline to transect their properties, to their
    properties’ detriment, and gave Nexus the right to condemn
    certain easements over their objections.
    2
    3
    Petitioners raise many arguments, the vast majority of
    which we reject. We agree with them, however, that the
    Commission failed to adequately justify its determination that
    it is lawful to credit Nexus’s contracts with foreign shippers
    serving foreign customers as evidence of market demand for
    the interstate pipeline. Accordingly, we remand without
    vacatur to the Commission for further explanation of this
    determination.
    I.
    The Natural Gas Act, 52 Stat. 821 (1938) (codified as
    amended at 15 U.S.C. §§ 717-717z), vests authority in the
    Commission to regulate the transportation and sale of natural
    gas in interstate commerce. In passing it, Congress had two
    principal aims: “encourag[ing] the orderly development of
    plentiful supplies of . . . natural gas at reasonable prices,”
    Minisink Residents for Envtl. Pres. & Safety v. FERC, 
    762 F.3d 97
    , 101 (D.C. Cir. 2014) (quoting NAACP v. Fed. Power
    Comm’n, 
    425 U.S. 662
    , 669-70 (1976)) (alteration in original),
    and “protect[ing] consumers against exploitation at the hands
    of natural gas companies,” id. (quoting Fed. Power Comm’n v.
    Hope Nat. Gas Co., 
    320 U.S. 591
    , 610 (1944)) (alteration in
    original).
    Section 7 of the Act requires an entity seeking to construct
    or extend an interstate pipeline for the transportation of natural
    gas to obtain from the Commission a “certificate of public
    convenience and necessity.” 15 U.S.C. § 717f(c)(1)(A). In a
    policy statement, the Commission set forth the criteria it
    considers in reviewing an application for a Section 7 certificate.
    Certification of New Interstate Nat. Gas Pipeline Facilities, 88
    FERC ¶ 61,227 (Sept. 15, 1999), clarified, 90 FERC ¶ 61,128
    (Feb. 9, 2000), further clarified, 92 FERC ¶ 61,094 (July 28,
    3
    4
    2000) (“Certificate Policy Statement”). First, an applicant must
    demonstrate that it is “prepared to develop the project without
    relying on subsidization by the sponsor’s existing customers.”
    88 FERC at 61,750. If the applicant makes this showing, the
    Commission will issue a certificate of public convenience and
    necessity only if a project’s public benefits (such as meeting
    unserved market demand) outweigh its adverse effects (such as
    a deleterious environmental impact on the surrounding
    community). 90 FERC at 61,396. If the Commission issues a
    Section 7 certificate to an applicant, the Act confers on the
    certificate holder the right to “exercise . . . eminent domain” to
    acquire any land necessary to the project’s completion. 15
    U.S.C. § 717f(h).
    As part of the Section 7 certificating process, before
    approving an interstate gas pipeline the Commission must
    complete an environmental review of the proposed project
    under the National Environmental Policy Act (“NEPA”), 42
    U.S.C. § 4321 et seq. Specifically, for federal actions of
    requisite significance (including the issuance of a Section 7
    certificate), NEPA requires an agency to prepare an
    Environmental Impact Statement, § 4332(C), in which the
    agency must “identify the reasonable alternatives to the
    contemplated action and . . . . look hard at the environmental
    effects of [its] decision,” including a project’s impact on public
    safety. Corridor H Alts., Inc. v. Slater, 
    166 F.3d 368
    , 374 (D.C.
    Cir. 1999) (citation omitted).
    Lastly, we note that the Commission has limited authority
    to regulate the import and export of natural gas under Section
    3 of the Act, 15 U.S.C. § 717b. See generally EarthReports,
    Inc. v. FERC, 
    828 F.3d 949
    , 952-53 (D.C. Cir. 2016). Section
    3 provides that no person shall import or export natural gas
    “without first having secured an order of the Commission
    4
    5
    authorizing it to do so,” and it instructs that the Commission
    shall issue such an order unless its finds that the import or
    export “will not be consistent with the public interest.” 15
    U.S.C. § 717b(a). As the Commission has explained, however,
    Congress transferred Section 3’s regulatory function to the
    Secretary of Energy. See Rover Pipeline, LLC, 158 FERC ¶
    61,109, ¶ 49 n.43 (Feb. 2, 2017) (citing 42 U.S.C. § 7151(b)).
    Subsequently, the Secretary delegated back to the Commission
    the narrow authority to approve or disapprove the construction
    and siting of facilities where natural gas will be imported or
    exported. Id. (citing U.S. Dep’t of Energy, Delegation Order
    No. 00-004.00A, § 1.21.A (eff. May 16, 2006)). But the
    Secretary retains exclusive authority to approve or disapprove
    the import and export of natural gas. Id.
    II.
    On November 20, 2015, Nexus sought from the
    Commission authorization under Section 7 to build and operate
    approximately 257 miles of a new natural gas pipeline to
    transport 1.5 million dekatherms per day (“dth/day”) of
    Appalachian Basin shale gas to consuming markets in northern
    Ohio, southeastern Michigan, and Ontario, Canada. The
    pipeline begins and ends in the United States; it extends from
    Hanover Township in Columbiana County, Ohio, to Ypsilanti
    Township in Washtenaw County, Michigan. In marketing the
    pipeline from 2012 through 2015, Nexus entered into precedent
    agreements – i.e., long-term contracts – with eight different
    entities, for 885,000 dth/day, or 59%, of the pipeline’s 1.5
    million dth/day capacity. Of the eight entities Nexus contracted
    with, four are affiliates of the pipeline’s sponsors, and two are
    “Canadian companies serving customers in Canada.” Resp’t’s
    Br. 28 (citing J.A. 1228). Nexus’s precedent agreements with
    the Canadian shippers are for a total of 260,000 dth/day. Id.
    5
    6
    On August 25, 2017, the Commission issued an order
    granting Nexus a Section 7 certificate of public convenience
    and necessity. See Nexus Gas Transmission, LLC, 160 FERC ¶
    61,022 (Aug. 25, 2017); J.A. 1036-123. And on July 25, 2018,
    the Commission issued an order denying Petitioners’ requests
    for rehearing. See Nexus Gas Transmission, LLC, 164 FERC ¶
    61,054 (July 25, 2018); J.A. 1206-89. In its orders, the
    Commission made three determinations that are especially
    relevant to Petitioners’ challenges. First, it found that Nexus’s
    precedent agreements were “the best evidence” that the
    pipeline served unmet market demand. Id. at 1218. Second, it
    approved Nexus’s proposed 14% return on equity, subject to
    the condition that Nexus design its initial customer rate based
    on a hypothetical capital structure of 50% equity and 50% debt.
    Id. at 1233. Third, it found that the pipeline does not “represent
    a significant safety risk to the public.” Id. at 1259.
    On October 2, 2017 (i.e., after the Commission issued
    Nexus a Section 7 certificate but before it denied Petitioners’
    requests for rehearing), Nexus filed a condemnation action,
    pursuant to Section 7, see 15 U.S.C. § 717f(h), against
    Petitioners in the Northern District of Ohio. On December 28,
    2017, the district court found that Nexus had the right to
    exercise eminent domain to condemn certain easements over
    Petitioners’ properties. See Nexus Gas Transmission, LLC v.
    City of Green, No. 5:17-cv-2062, 
    2017 WL 6624511
    , at *3
    (N.D. Ohio Dec. 28, 2017), appeal dismissed, 
    2018 WL 2072616
     (6th Cir. Feb. 9, 2018). Shortly thereafter, Nexus
    exercised that right. See Pet’rs’ Br., Standing Addendum 3.
    In September 2018, Petitioners filed the instant matter.
    They ask us to vacate the Commission’s order of August 25,
    2017, granting Nexus a Section 7 certificate, as well as its order
    6
    7
    of July 25, 2018, denying Petitioners’ requests for rehearing.
    On May 6, 2019, we heard oral argument. Thereafter, based on
    certain post-argument events, Nexus filed a motion to dismiss
    for lack of subject matter jurisdiction, which, for reasons
    explained below, we denied.
    III.
    We have jurisdiction over the petitions pursuant to the
    Natural Gas Act. See 15 U.S.C. § 717r(b). Under the statute,
    any party that is “aggrieved” by an order of the Commission
    may petition for review of that order, so long as they first seek
    rehearing with the Commission. Id. § 717r(a)-(b). Petitioners
    meet these criteria. They sought rehearing of the Commission’s
    order granting Nexus a Section 7 certificate, and we have held
    that landowners like Petitioners, who are “forced to choose
    between selling to a FERC-certified developer and undergoing
    eminent domain proceedings,” are “‘aggrieved’ within the
    meaning of the Act.” Sierra Club v. FERC, 
    867 F.3d 1357
    ,
    1365 (D.C. Cir. 2017) (citing B&J Oil & Gas v. FERC, 
    353 F.3d 71
    , 75 (D.C. Cir. 2004)).
    Before proceeding, however, we must also discharge our
    “independent duty to ensure that at least one petitioner has
    standing under Article III of the Constitution.” Sierra Club,
    867 F.3d at 1365 (internal citation omitted). To establish
    Article III standing, a petitioner “must have (1) suffered an
    injury in fact, (2) that is fairly traceable to the challenged
    conduct of the defendant, and (3) that is likely to be redressed
    by a favorable judicial decision.” Spokeo, Inc. v. Robbins, 
    136 S. Ct. 1540
    , 1547 (2016) (internal citation omitted).
    In its motion to dismiss submitted after oral argument,
    Nexus argues that Petitioners no longer suffer redressable
    7
    8
    injuries in fact. According to Nexus, this is because, since oral
    argument, Petitioners and Nexus executed easement
    agreements that settled the issue of compensation for Nexus’s
    takings, see Pet’rs’ Response to Motion to Dismiss, Exhibits 2,
    6, and thereafter the parties entered into joint notices and
    stipulations of dismissal in the condemnation action in the
    Northern District of Ohio, see id. Exhibits 3, 7.
    The law of our circuit is clear that a landowner is injured
    in fact when she is put to the choice of having to either reach
    an agreement with a pipeline seeking to access her property or
    have her property condemned. See Gunpowder Riverkeeper v.
    FERC, 
    807 F.3d 267
    , 271-72 (D.C. Cir. 2015) (“[A] landowner
    made subject to eminent domain by a decision of the
    Commission has been injured in fact because the landowner
    will be forced either to sell its property to the pipeline company
    or to suffer the property to be taken through eminent domain.”)
    (internal citation omitted); see also B&J Oil, 353 F.3d at 75
    (“[Petitioner] unquestionably suffers from an injury-in-fact. As
    a result of the Commission’s orders, [petitioner] . . . must either
    sell its land to [the pipeline] or allow [the pipeline] to take its
    property through eminent domain. . . . That [the pipeline]
    ultimately will compensate [petitioner] for its property does
    nothing to erase [petitioner’s] legally cognizable injury.”).
    Accordingly, the fact that the parties reached an agreement as
    to compensation for Nexus’s takings does nothing to vitiate
    Petitioners’ injuries to their property interests.1 In addition,
    Petitioners’ injuries are directly traceable to the Commission’s
    orders (because the orders permitted the pipeline to transect
    1
    We note, too, that the joint stipulations of dismissal that the parties
    executed explicitly provide that the dismissal of the claims in the
    condemnation action “shall have no application” to Petitioners’
    claims in the instant matter. Pet’rs’ Resp. to Mot. to Dismiss 8
    (quoting Exs. 3, 7).
    8
    9
    their land and authorized Nexus to condemn it), and if we
    vacate those orders Petitioners’ injuries are likely to be
    redressed, see Nexus Gas Transmission, LLC, 162 FERC ¶
    61,011, at P 7 (2018) (“[T]o the extent that [Nexus] elects to
    proceed with construction, it bears the risk that . . . our orders
    will be overturned on appeal. If this were to occur, [Nexus]
    might not be able to utilize any new facilities and could be
    required to remove them or to undertake further remediation.”).
    We find, therefore, that Petitioners have Article III standing to
    bring the petitions.
    IV.
    We must set aside a decision of the Commission if it is
    arbitrary and capricious or otherwise contrary to law. TNA
    Merch. Projects, Inc. v. FERC, 
    857 F.3d 354
    , 358 (D.C. Cir.
    2017). Accordingly, where an agency’s “explanation is lacking
    or inadequate, the court must remand for an adequate
    explanation of the agency’s decision and policy.” BP Energy
    Co. v. FERC, 
    828 F.3d 959
    , 965 (D.C. Cir. 2016) (citing Maher
    Terminals LLC v. Fed. Mar. Comm’n, 
    816 F.3d 888
    , 892 (D.C.
    Cir. 2016)). The Commission’s factual findings are conclusive
    “if supported by substantial evidence.” 15 U.S.C. 717r(b).
    A.
    Petitioners argue that the Commission’s finding that
    Nexus’s precedent agreements are the “best evidence” of
    project need, see J.A. 1218, is not supported by substantial
    evidence. In support of this argument, Petitioners wage a three-
    pronged attack.
    First, Petitioners assert that the Commission contravened
    its Certificate Policy Statement by relying on Nexus’s
    9
    10
    precedent agreements for “a paltry 59 percent of new capacity”
    as the best evidence of project need. Pet’rs’ Br. 24-25.
    Specifically, Petitioners contend that the policy statement only
    allows precedent agreements to serve as “strong evidence of
    market demand” when they represent “most of the new
    capacity” of the pipeline and that 59% is not “most of the new
    capacity.” Id. (citing 88 FERC at 61,749). But that argument is
    fundamentally misguided: the Certificate Policy Statement
    imposes no bright-line rule about when precedent agreements
    may be persuasive evidence of market demand. Instead, it lays
    out a flexible inquiry that allows the Commission to consider a
    wide variety of evidence to determine the public benefits of the
    project. And here, the Commission engaged in that broad-
    ranging inquiry reasonably. Although the precedent
    agreements represented only 59% of Nexus’s capacity, the
    Commission determined that existing pipelines could not
    absorb that amount of gas. See J.A. 1050-53, 1219-20. Given
    that analysis, the Commission reasonably concluded under the
    Certificate Policy Statement that the precedent agreements –
    which firmly established that there was more demand for
    natural gas in the Nexus pipeline’s delivery region than
    existing pipelines could meet – were the best evidence of
    project need.
    Second, Petitioners assert, Nexus’s precedent agreements
    are not meaningful evidence of project need because half of
    them are with affiliates of the pipeline’s sponsors. According
    to Petitioners, this is problematic because affiliate agreements
    “are not necessarily the product of arms-length negotiations.”
    Pet’rs’ Br. 25-26. This argument, too, is without merit. The
    Commission rationally explained that it fully credited Nexus’s
    precedent agreements with affiliates because it found no
    evidence of self-dealing (a finding Petitioners do not dispute),
    and because Nexus bears the risk for any unsubscribed
    10
    11
    capacity. See J.A. 1125. Moreover, as the Commission
    explained, when it ended its policy of requiring pipelines to
    demonstrate a specific subscription rate, “it was reducing ‘the
    significance of whether the [precedent agreements] are with
    affiliated or unaffiliated shippers.’” J.A. 1224 (quoting 88
    FERC at 61,748). Consistent with this, this Court has also
    recognized that “it is Commission policy to not look behind
    precedent or service agreements to make judgments about the
    needs of individual shippers.” Myersville Citizens for a Rural
    Cmty., Inc., v. FERC, 
    783 F.3d 1301
    , 1311 (D.C. Cir. 2015)
    (quoting Dominion Transmission, Inc., 141 FERC ¶ 61,1240,
    at P 66 (Dec. 12, 2012)); see also Appalachian Voices v. FERC,
    No. 17-1271, 
    2019 WL 847199
    , at *1 (D.C. Cir. Feb. 19, 2019)
    (holding that the Commission “reasonably explained that ‘[a]n
    affiliated shipper’s need for new capacity and its obligation to
    pay for such service under a binding contract are not lessened
    just because it is affiliated with the project sponsor’”) (quoting
    Mountain Valley Pipeline, LLC, 161 FERC ¶ 61,043, ¶ 45 (Oct.
    13, 2017)) (alteration in original).
    Third, Petitioners argue, Nexus’s precedent agreements
    are not strong evidence of market demand because a substantial
    portion of them are dedicated for export. In Petitioners’ view,
    because the Secretary of Energy authorizes exports under
    Section 3 of the Act, the Commission may not use precedent
    agreements for export “to justify project need under Section 7
    [,] which governs certificates for projects in interstate
    commerce.” Pet’rs’ Br. 21. Moreover, Petitioners contend,
    because Section 7 confers on a certificate holder the right to
    exercise eminent domain, crediting export agreements toward
    a Section 7 finding of project need runs afoul of the Takings
    Clause, as a private pipeline selling gas to foreign shippers
    serving foreign customers does not serve a “public use” within
    the meaning of the Fifth Amendment. Id. at 36 (quoting U.S.
    11
    12
    CONST. amend. V (“[P]rivate property [shall not] be taken for
    public use, without just compensation.”)).
    This argument raises legitimate questions, which the
    Commission has heretofore failed to adequately answer. On the
    record before us, two of Nexus’s precedent agreements for a
    total of 260,000 dth/day are, as the Commission concedes, with
    “Canadian companies serving customers in Canada.” Resp’t’s
    Br. 12 (citing J.A. 1228). If the Commission excluded these
    agreements from its Section 7 analysis of project need, Nexus
    would have precedent agreements for only 625,000 dth/day, or
    approximately 41.6% of its 1.5 million dth/day capacity. And
    because the Commission never considered whether the public
    benefits of the Nexus pipeline would outweigh its adverse
    impacts if it were only subscribed for 625,000 dth/day (a
    substantial decrease from the analyzed 805,000 dth/day), we
    may affirm its finding of public convenience and necessity only
    if the Commission’s inclusion of the export precedent
    agreements in its analysis was proper.
    But the Commission never explained why it is lawful to
    credit demand for export capacity in issuing a Section 7
    certificate to an interstate pipeline. In response to Petitioners’
    argument that it is not, the Commission simply recited its
    findings that: (1) a substantial amount of the pipeline’s
    subscribed capacity is for domestic consumption; (2) all
    shipper commitments have secondary delivery rights within the
    United States; and (3) Nexus’s application listed eleven
    interconnections with potential customers. J.A. 1228-29. But
    these facts do not explain why it is lawful for the Commission
    to predicate a Section 7 finding of project need on precedent
    agreements with foreign shippers serving foreign customers.
    Section 7 states that the Commission may issue a certificate of
    public convenience and necessity for “the transportation in
    12
    13
    interstate commerce,” § 717f(c)(2) (emphasis added), and we
    have explicitly refused to “interpret ‘interstate commerce’”
    within the context of the Act “so as to include foreign
    commerce,” Border Pipe Line Co. v. Fed. Power Comm’n, 
    171 F.2d 149
    , 152 (D.C. Cir. 1948). See also Distrigas Corp. v.
    Fed. Power Comm’n, 
    495 F.2d 1057
    , 1063 (D.C. Cir. 1974)
    (reaffirming Border Pipe Line).
    Moreover, in response to Petitioners’ argument that
    relying on demand for export in issuing a Section 7 certificate
    runs afoul of the Takings Clause, the Commission merely
    stated that it has previously addressed this issue and offered
    citation to authority. J.A. 1229 (collecting FERC cases). But
    just one of the FERC cases the Commission cites addressed the
    specific question of whether predicating a Section 7 finding of
    project need on precedent agreements for export contravenes
    the Takings Clause. See Transcon. Gas Pipe Line Co., 161
    FERC ¶ 61,250 (Dec. 6, 2017), at ¶¶ 30-35. Furthermore, in
    that single case, the Commission relied on the inadequate
    explanation that such a circumstance does not present a
    Takings Clause problem because: once the Commission
    determines that a pipeline is required by the public convenience
    and necessity, Section 7 authorizes the certificate holder to
    exercise the right of eminent domain, and “Congress did not
    suggest that there was a further test . . . such that certain
    certificated pipelines furthered a public use . . . while others did
    not.” Id. ¶¶ 31-32. This reasoning begs the unanswered
    question of whether – given the fact that Section 7 authorizes
    the use of eminent domain – it is lawful for the Commission to
    13
    14
    credit precedent agreements for export toward a finding that a
    pipeline is required by the public convenience and necessity.2
    When pressed on this issue at oral argument, the
    Commission again did not explain why it is lawful to credit
    precedent agreements for export in issuing a Section 7
    certificate for the construction and operation of an interstate
    pipeline. See Oral Arg. 16:45-28:10. Rather, the Commission
    repeated that, in approving Nexus’s application, it was
    “looking at the benefits to the domestic markets.” Oral Arg.
    27:34-39. As we have explained, this statement has no
    explanatory value with respect to the question of why it is
    lawful for the Commission, as it did here, to predicate a Section
    7 finding of need for an interstate pipeline on a pipeline’s
    precedent agreements for export. 3
    Accordingly, we remand to the Commission for further
    explanation of why – under the Act, the Takings Clause, and
    2
    We acknowledge that, in Transcontinental Gas, in an attempt to
    fortify its reasoning, the Commission also “note[d]” that before any
    gas is exported, the Department of Energy, pursuant to Section 3 of
    the Act, would first “need to find that such exportation is not
    inconsistent with the public interest.” Id. at 34 (citing 15 U.S.C. §
    717b(a)). True. It is insufficient, however, to simply assume that such
    a finding under Section 3, which does not authorize the exercise of
    eminent domain, is somehow equivalent to a finding that a given
    export constitutes a public use within the meaning of the Takings
    Clause.
    3
    To the extent that Petitioners argue that the Commission can never
    lawfully issue a Section 7 certificate where a pipeline has precedent
    agreements for export, see Pet’rs’ Br. 33-35, we note that we
    disagree. We disagree because a pipeline may clearly be required by
    the public convenience and necessity independent of any of its
    precedent agreements for export. But, as explained, the Commission
    has not made any finding to that effect in this case.
    14
    15
    the precedent of this Court and the Supreme Court – it is lawful
    to credit precedent agreements with foreign shippers serving
    foreign customers toward a finding that an interstate pipeline is
    required by the public convenience and necessity under Section
    7 of the Act.
    B.
    Petitioners also attack the Commission’s approval of the
    specific formula that Nexus used to design its initial consumer
    rate.
    As we had occasion to discuss relatively recently, one of
    the Commission’s duties under the Act is to regulate the rates
    pipelines charge their customers. See generally Sierra Club,
    867 F.3d at 1376-79. As part of a Section 7 proceeding, the
    Commission reviews a pipeline’s proposed initial rate and will
    approve it if the agency finds that it is in the “public interest.”
    Atl. Ref. Co. v. Pub. Serv. Comm’n, 
    360 U.S. 378
    , 390-91
    (1959). A pipeline’s initial rate remains in place until
    permanent “just and reasonable” rates are established pursuant
    to ratemaking procedures under Sections 4 and 5 of the Act.
    See Mo. Pub. Serv. Comm’n v. FERC, 
    601 F.3d 581
    , 583 (D.C.
    Cir. 2010) (citing 15 U.S.C. §§ 717c-d).
    Nexus sought to design its initial rate based on a 14%
    return on equity (“ROE”) and a hypothetical capital structure
    of 60% equity and 40% debt. See J.A. 1234; see generally
    Sierra Club, 867 F.3d at 1376 (“Like most businesses, a
    pipeline company is funded by both equity (i.e., investments
    made by shareholders) and debt. A pipeline’s ratio of equity
    financing to debt financing is called its ‘capital structure.’”)
    (internal citations omitted). The Commission, however, did not
    accept Nexus’s proposal. Rather, it approved Nexus’s proposed
    15
    16
    ROE of 14% but only on the condition that Nexus design its
    initial rate according to a hypothetical capital structure of 50%
    equity and 50% debt. J.A. 1236. In other words, in forcing
    Nexus to design its initial rate according to a 50:50, as opposed
    to 60:40, equity to debt ratio, the Commission “require[d] the
    pipeline to charge a lower rate than it had originally requested.”
    Sierra Club, 867 F.3d at 1378.
    But Petitioners are not satisfied with the Commission’s
    effort to reign in Nexus’s initial rate. They argue that a 14%
    ROE is excessive, even assuming a 50:50 equity to debt ratio,
    as compared to the returns on other utility investments that state
    commissions have approved. See Pet’rs’ Br. 43 (citing J.A.
    1778).4 Moreover, Petitioners contend, the Commission failed
    to adequately explain why a 14% ROE and 50:50 equity to debt
    ratio is appropriate for the Nexus pipeline specifically.
    Petitioners point out that the Commission, in its order issuing
    Nexus a Section 7 certificate, supported its approval of this
    formula with nothing more than citation to FERC precedents
    demonstrating that the Commission has previously approved a
    14% ROE and 50:50 equity to debt ratio for new pipelines. Id.
    (citing J.A. 1063). Moreover, Petitioners add, in its order
    denying Petitioners’ requests for rehearing, the Commission
    merely: (1) offered the generic observation that relatively
    higher ROE’s are appropriate for new market entrants like
    4
    In addition, Petitioners raise a half-hearted challenge to the
    Commission’s very use of a hypothetical capital structure as a
    mechanism by which to lower Nexus’s initial rate. As Petitioners
    ultimately concede, however, “Sierra Club allows the Commission
    to use a hypothetical capital structure to minimize rate impacts.”
    Pet’rs’ Br. 45-46 (referring to Sierra Club, 867 F.3d at 1378 (“FERC
    is allowed to . . . use a hypothetical capital structure to decrease a
    pipeline’s proposed rates, in the interest of consumer protection.”)
    (emphasis in original) (internal citation omitted)).
    16
    17
    Nexus because they face greater business risks than their
    established counterparts; and (2) noted that Nexus bears the
    financial risk for any unsubscribed capacity. Id. at 43-44 (citing
    J.A. 1235-36). But nowhere, Petitioners emphasize, has the
    Commission explained “why a flat 14 percent return should
    apply to all new pipelines irrespective of geographic location,
    size and cost and need [sic].” Id. at 43.
    In response, the Commission reiterates that its approval of
    a 14% ROE and 50:50 equity to debt ratio was appropriate for
    the Nexus pipeline because new pipelines are inherently
    riskier, and Nexus bears responsibility for any unsubscribed
    capacity. Resp’t’s Br. 41-42 (citing J.A. 1235-36).
    In Sierra Club, when considering the precise question
    before us – i.e., whether the Commission was justified in
    approving a 14% ROE based on a 50:50 equity to debt ratio for
    a new pipeline on the ground that the Commission had done so
    previously for new pipelines – we “confess[ed] to being
    skeptical that a bare citation to precedent, derived from another
    case and another pipeline, qualifies as the requisite ‘substantial
    evidence.’” Sierra Club, 867 F.3d at 1378 (citing N.C. Utils.
    Comm’n v. FERC, 
    42 F.3d 659
    , 664 (D.C. Cir. 1994) (“[N]aked
    citation of prior authority for the use of a hypothetical [capital
    structure] under one circumstance does not automatically
    justify such in another.”)). Ultimately, however, we did not
    reach this issue because we found that petitioner never properly
    raised it, having “confin[ed] itself to attacking the use of a
    hypothetical capital structure more generally.” Id.
    Here, by contrast, Petitioners, in their requests for
    rehearing and opening brief, argued explicitly that the
    Commission’s bare citation to precedent is inadequate to
    support its finding that a 14% ROE based on a 50% equity and
    17
    18
    50% debt capital structure is appropriate for the Nexus
    pipeline. See J.A. 1176; Pet’rs’ Br. 43-44. Thus, the issue is
    properly before us.
    However, after a close examination of the record, we find
    that the Commission’s explanation is hardly as bare as the
    Petitioners suggest. The Commission did not simply cite its
    precedent but applied its “established policy” balancing both
    consumer and investor interests to the particular pipeline at
    issue, J.A. 1233, and responded to Petitioners’ specific
    objections. It explained the nature of initial rates, as distinct
    from rates under NGA sections 4 and 5, specifically how
    “Congress gave the Commission the discretion in section 7
    certificate proceedings to approve initial rates that will ‘hold
    the line’ and ‘ensure that the consuming public may be
    protected’ while awaiting adjudication of just and reasonable
    rates under the more time-consuming ratemaking sections of
    the NGA.” J.A. 1233 (quoting Atl. Ref. Co. v. Pub. Serv.
    Comm’n of N.Y., 
    360 U.S. 378
    , 390 (1950)). It explained the
    different risks confronting existing pipelines and the greenfield
    pipeline at issue, which faces increased business risks
    (regulatory, contractual, and construction) and greater risks of
    constructing and servicing new routes because it does not have
    an existing revenue base, and why Petitioners’ reliance on state
    proceedings was misplaced. J.A. 1234-35. It rejected
    Petitioners’ argument that Nexus faced no risk for the
    unsubscribed pipeline capacity because “Nexus faces a very
    real risk that any unsubscribed capacity will reduce its ability
    to meet its revenue requirement.” J.A. 1236. It also explained
    that adjusting Nexus’s proposed hypothetical capital structure
    reduced the impact of the ROE and thereby “ensures that
    Nexus’s rates are on a level playing field with other greenfield
    pipelines.” J.A. 1236. It concluded, on the record before it, that
    18
    19
    an ROE of 14% with an increased debt level would “hold the
    line.” J.A. 1236.
    Notably, the Commission even provided an example of
    how, under its policy, an existing pipeline seeking to expand
    service would be required to use the ROE underlying its
    existing system rates, tending to yield a lower rate in view of
    the lower risk involved. J.A. 1234. In the example provided, an
    existing pipeline’s ROE was 12.2 % rather than the requested
    13.0%. Further, it noted that Nexus would be required to file a
    cost and revenue study three years out that would provide data
    by which the Commission and interested parties could
    determine whether the rates remain just and reasonable. J.A.
    1235. It is true that the Commission never discussed another
    possible ROE, other than to reject the equity/debt ratio Nexus
    initially proposed. See J.A. 1234. But we are ill-equipped to
    second guess the Commission’s expert judgment that a 14%
    ROE with 50/50 equity/debt capital structure will “hold the
    line,” and on this record, we find no basis on which to conclude
    the Commission’s explanation in response to Petitioners’
    objections is inadequate. See BP Energy Co. v. FERC, 
    828 F.3d 959
    , 965 (D.C. Cir. 2016). Nor can we find that the
    Commission “entirely failed to consider an important aspect of
    the problem, offered an explanation for its decision that runs
    counter to the evidence before the agency, or is so implausible
    that it could not be ascribed to a difference in view or the
    product of agency expertise.” Motor Veh. Mfrs. Ass’n of U.S.
    v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983).
    Accordingly, Petitioners’ attack on the Commission’s
    approval of the specific formula that Nexus used to design its
    initial consumer rate is unsuccessful.
    19
    20
    C.
    Finally, Petitioners raise two arguments attacking the
    Commission’s finding that the pipeline does not “represent a
    significant safety risk to the public.” J.A. 1259. We reject both.
    First, Petitioners argue, the Commission impermissibly
    delegated its obligations under NEPA to independently review
    the pipeline’s potential adverse impacts on public safety.
    Specifically, Petitioners contend, within its Environmental
    Impact Statement (“EIS”), the Commission over relied on
    Nexus’s commitment to comply with safety standards
    promulgated by the Pipeline and Hazardous Materials Safety
    Administration, a division of the Department of Transportation
    (“DOT”).
    Petitioners are wrong. As they concede, see Pet’rs’ Br. 50,
    DOT has exclusive authority to establish safety standards for
    natural gas pipelines, see Memorandum of Understanding
    Between DOT and FERC Regarding Natural Gas
    Transportation                                         Facilities,
    https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/19
    93_DOT_FERC.pdf. And we have held that it is reasonable for
    the Commission to reference such standards as a component of
    its review of a pipeline’s safety risks, see EarthReports, 828
    F.3d at 958, which is exactly what the Commission did here. In
    a thorough analysis, see J.A. 1019-43, the Commission
    explained in detail how Nexus’s compliance with DOT
    standards would address the specific safety concerns that
    commenters raised. See, e.g., J.A. 1028 (“The DOT regulations
    specified in 49 CFR 192 require that pipeline operators
    establish and maintain liaison with appropriate fire, police, and
    public officials . . . .”). Moreover, the Commission enumerated
    specific actions Nexus committed to take to account for safety
    20
    21
    risks that DOT regulations might not fully address. See, e.g.,
    J.A. 1028 (“In addition to the DOT-required surveys described
    previously, Nexus . . . would monitor portions of its pipeline
    system using a supervisory control and data acquisition
    system.”). Accordingly, the Commission fulfilled its duty to
    independently consider the pipeline’s safety risks and, in so
    doing, it considered DOT regulations in an appropriate fashion.
    Second, Petitioners contend, the Commission arbitrarily
    failed to consider moving the pipeline away from residences
    and buildings. This is not so. As an initial matter, as the
    Commission pointed out, see J.A. 1025, DOT regulations do
    not require natural gas pipelines to remain a minimum distance
    from residences or buildings. DOT has, however, developed a
    classification system that grades each segment of a pipeline
    based on population density at a given segment’s location, see
    49 C.F.R. § 192.5, and subjects “high consequence areas,” i.e.,
    pipeline segments close to more densely populated areas, to
    stricter safety standards, see id. §§ 192.903, 192.907, 192 App.
    E. In accordance with this regulatory scheme, the Commission
    accounted for every mile of the Nexus pipeline. See J.A. 1020-
    27. Accordingly, although the Commission may not have
    considered the pipeline’s proximity to buildings and residences
    in precisely the way Petitioners would prefer, Petitioners’
    argument that the Commission arbitrarily failed to consider this
    issue is unfounded.
    21
    22
    V.
    Before concluding, we offer a word regarding our remedy.
    “The decision to vacate depends on two factors: the likelihood
    that ‘deficiencies’ in an order can be redressed on remand, even
    if the agency reaches the same result, and the ‘disruptive
    consequences’ of vacatur.” Black Oak Energy, LLC v. FERC,
    
    725 F.3d 230
    , 244 (D.C. Cir. 2013) (quoting Allied-Signal, Inc.
    v. U.S. Nuclear Regulatory Comm’n, 
    988 F.2d 146
    , 150-51
    (D.C. Cir. 1993)). Accordingly, we remand without vacatur,
    because we find it plausible that the Commission will be able
    to supply the explanations required, and vacatur of the
    Commission’s orders would be quite disruptive, as the Nexus
    pipeline is currently operational.
    ***
    For the foregoing reasons we grant in part and deny in part
    the petitions for review. We grant the petitions insofar as we
    remand without vacatur to the Commission for further
    explanation of why it is lawful to credit precedent agreements
    for export toward a Section 7 finding that an interstate pipeline
    is required by the public convenience and necessity. We deny
    the petitions in all other respects.
    So ordered.
    22
    ROGERS, Circuit Judge, concurring.           This court has
    recently reaffirmed its understanding that the Commission acts
    lawfully under the Natural Gas Act (“the Act”) in granting a
    Section 7 certification of public convenience and necessity
    when “much of the [imported] gas will be used for domestic
    consumption.” Town of Weymouth v. FERC, 
    2018 WL 6921213
    , at *1 (D.C. Cir. Dec. 27, 2018) (unpubl.). This
    harkens back to the court’s recognition that “the Commission
    has long regarded Section 3’s public interest standard and
    Section 7’s public convenience and necessity standard as
    substantially equivalent.” Distrigas Corp. v. FERC, 
    495 F.2d 1057
    , 1065 (D.C. Cir. 1974) (noting FERC Opinion 613).
    There, the court declined to overrule Border Pipe Line Co. v.
    FPC, 
    171 F.2d 149
    , 150–51 (D.C. Cir. 1948), where the court
    held the power commission lacked jurisdiction under Section 7
    to regulate a company located in Texas that transported gas
    exclusively to Mexico, drawing on the historical distinction
    between “interstate commerce” and “exports.” In Distrigas,
    495 F.2d at 1063, the court “agree[d] with the Commission that
    neither the language nor the legislative history of the Act’s
    interstate commerce definition unambiguously establishes the
    correctness of the Border construction.” It stated that it “would
    not hesitate” to overrule Border Pipe Line if it were convinced
    that that case’s interpretation of Section 7 “would inevitably
    place imports of natural gas into the sort of regulatory gap” that
    the Act was designed to fill. Id. at 1063–64. But the court
    concluded there was no regulatory gap over imported gas
    entering an existing pipeline because FERC had “plenary and
    elastic” authority under Section 3 to place conditions —
    including conditions substantively equivalent to Section 7
    certification requirements — on imported gas. Id. at 1064.
    In neither Distrigas nor Border Pipe Line was the issue
    precisely the same as in the instant case, namely, whether the
    Commission has authority under Section 7 to consider in
    certification proceedings precedent agreements with a foreign
    shipper in evaluating market need for a new pipeline to be
    2
    located exclusively within the United States. Whether, absent
    congressional action, a similar workaround as the court applied
    in Distrigas, or other approach for concluding the Commission
    had jurisdiction to consider two Canadian shippers’ precedent
    agreements where a significant amount of that gas was
    expected to be used domestically, would be possible remains
    to be seen. Here, the Commission’s findings regarding the
    need for and the nature of the NEXUS pipeline are supported
    by substantial evidence in the record considered as a whole,
    and the Commission reasonably explained that petitioners
    mischaracterized the extent to which the project may be used
    to export gas. See Rehg Order ¶ 45; Resp’t’s Br. 28. So
    understood, it appears on this record that the question on
    remand is whether the Commission’s “substantial equivalence”
    interpretation is contrary to the Act. I join the remand to allow
    the Commission the opportunity to provide an explanation of
    its authority to rely in Section 7 certification proceedings on
    precedent agreements with foreign shippers serving foreign as
    well as domestic customers.