Entergy Svcs v. FERC ( 2004 )


Menu:
  •   United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued September 10, 2004         Decided December 10, 2004
    No. 02-1199
    ENTERGY SERVICES, INC.,
    PETITIONER
    V.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    SOUTHERN COMPANY SERVICES, INC., ET AL.,
    INTERVENORS
    Consolidated with
    02-1336, 02-1375, 03-1023
    On Petitions for Review of an Order of the
    Federal Energy Regulatory Commission
    J. Wayne Anderson argued the cause for petitioners.
    With him on the briefs were Floyd L. Norton, IV., Heath K.
    Knakmuhs, S. Chris Still, Kevin A. McNamee, and Gerard A.
    Clark. Andrew W. Tunnell and Matthew W. Estes entered
    appearances.
    2
    Thomas D. Samford, IV, was on the brief for Alabama
    Public Service Commission in support of petitioner and reversal
    of orders.
    Marlene K. Stern was on the brief of amicus curiae
    Florida Public Service Commission in support of petitioner and
    urging reversal. With her on the brief was David E. Smith.
    Harold A. McLean entered an appearance.
    Thurbert E. Baker, Attorney General, Attorney General's
    Office of the State of Georgia, and Daniel S. Walsh, Assistant
    Attorney General, were on the brief for amicus curiae Georgia
    Public Service Commission in support of petitioner.
    Dennis Lane, Solicitor, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on the
    brief were Cynthia A. Marlette, General Counsel, and Laura J.
    Vallance, Attorney.
    Ashley C. Parrish argued the cause for intervenor
    Tenaska, Inc. With him on the brief was Neil L. Levy.
    Before: SENTELLE, TATEL and ROBERTS, Circuit Judges.
    Opinion for the Court filed by Circuit Judge SENTELLE.
    Concurring opinion filed by Circuit Judge TATEL.
    SENTELLE, Circuit Judge: Electricity utility companies
    Entergy Services, Inc., Southern Company Services, Inc., and
    Nevada Power Company, Inc., petition for review of various
    orders of the Federal Energy Regulatory Commission in which
    the Commission held that certain costs incurred by customers
    connecting generators to petitioners’ networks must be “spread”
    across all customers and not “directly assigned” to the respective
    3
    generator companies. Specifically, the Commission found that
    because the connection facilities in each case were located “at
    or beyond” the point of connection to the network, they
    constituted “network upgrades” not directly assignable to
    individual generators.
    Petitioners contend (1) that the Commission’s orders
    should be reversed because they are unsupported by substantial
    evidence, and (2) that the Commission’s orders should be
    reversed because the “At or Beyond” rule constitutes an
    arbitrary departure from Commission precedent. Because we
    agree with Intervenor Tenaska, Inc. that Entergy and Southern
    lack standing to pursue their claims, we limit our review to the
    objections advanced by Nevada Power. However, because we
    hold that the order from which Nevada Power petitions has not
    adequately explained the Commission’s apparent departure from
    prior practice, we vacate and remand that order for further
    proceedings.
    I. Background
    A. Regulatory Background
    Petitioners in this case–Entergy Services, Inc.
    (“Entergy”), Southern Company Services, Inc. (“Southern”), and
    Nevada Power Co. (“Nevada Power”)–are electricity utility
    companies that own transmission systems providing electricity
    to large geographic regions. In order to foster a more
    competitive, efficient market for electricity, federal regulation
    requires that such “transmission providers” open their networks
    to transmission customers–other sellers of electricity seeking to
    supply power to their own customers. See Promoting Wholesale
    Competition Through Open Access Nondiscriminatory
    Transmission Services by Public Utilities; Recovery of Stranded
    Costs by Public Utilities and Transmitting Utilities, Order No.
    4
    888, FERC Stats. & Regs. ¶ 31,036 (1996), 
    61 Fed. Reg. 21,540
    (“Order No. 888”), on reh’g, Order No. 888-A, FERC Stats. &
    Regs. ¶ 31,048, 62 Fed. Reg.12,274 (1997), on reh’g, Order No.
    888-B, 81 F.E.R.C. ¶ 61,248 (1997), on reh’g, Order No. 888-C,
    82 F.E.R.C. ¶ 61,046 (1998), aff’d, Transmission Access Policy
    Study Group v. FERC, 
    225 F.3d 667
     (D.C. Cir. 2000), aff’d sub
    nom., New York v. FERC, 
    535 U.S. 1
     (2002).
    In implementation of Order No. 888, the Commission
    promulgated a pro forma Open Access Transmission Tariff
    (“OATT”) that sets forth the minimum terms and conditions
    under which transmission providers may offer their services to
    would-be customers. See Order No. 888-A at 30,503-43
    (including the final OATT); 
    18 C.F.R. § 35.28
    (c)(1) (requiring
    public utilities owning, controlling, or operating facilities
    transmitting electricity in interstate commerce to “have on file
    with the Commission a tariff of general applicability for
    transmission services” or a tariff approved by the Commission
    consistent with Order No. 888).
    Under this tariff regime, some costs incurred by an
    interconnecting customer are borne by the respective customer,
    while other costs are spread across all customers on the network.
    In general, when a Generator of electricity connects to a
    Transmission Provider’s network consistent with Order No. 888,
    the Transmission Provider cannot require the Generator to bear
    costs incurred for the development of equipment that benefits all
    users of the network. Duke Energy Co., 95 F.E.R.C. ¶ 61,279 at
    61,980 (2001). Such costs, spread across all customers, are
    known as “network upgrades.” The Generator must initially
    finance the costs, but upon completion of the interconnection
    project the Transmission Provider spreads the cost among all
    customers and rebates to the Generator its initial investment by
    providing it with transmission credits against its tariff expenses.
    By contrast, when a new Generator incurs cost developing
    5
    equipment of no benefit to the existing customers, the costs are
    assigned to the Generator alone. This is known as “direct
    assignment,” and the equipment is known as “direct assignment
    facilities.”
    The specific tariff and other interconnection details are
    finalized in an Interconnection Agreement (“IA”) between the
    Transmission Provider and the Generator. IAs are drafted by the
    parties and are submitted to the Commission for approval.
    B. Factual Overview
    The consolidated cases before this court arise from the
    Commission’s disapproval of four IAs submitted for its
    approval.
    Entergy submitted an unexecuted IA to the Commission
    on November 14, 2001. Amelia Energy Center, LP (“Amelia”)
    was the other party to the agreement. At issue were two
    connection facilities: (1) a new Switching Station section to
    accommodate two new 230 kV radial power lines from the
    Generators; and (2) the re-routing of three existing power lines.
    The Commission held that the IA could not directly assign costs
    for the facilities at issue to Amelia, because the facilities were
    located “at or beyond” the point of interconnection with the grid,
    and as such provided benefit to all users. See Entergy Gulf
    States, Inc., 98 F.E.R.C. ¶ 61,014 (2002), reh’g denied, 99
    F.E.R.C. ¶ 61,095 (2002). On June 14, 2002, the Commission
    accepted Entergy’s proposed termination of the IA; prior to
    termination, the IA was of indefinite duration.
    Southern submitted two IAs for Commission approval.
    It submitted its first IA, between its Alabama Power
    transmission system and Blount County Energy, LLC
    (“Blount”), on November 30, 2001. At issue was a replacement
    6
    breaker at the Miller Steam Plant substation. The Commission
    held that the cost of the breaker could not be directly assigned
    to the Generator, in light of the “At or Beyond” rule. Southern
    Company Services, Inc., Letter Order, Docket No. ER02-430-
    000 (Jan. 25, 2002), reh’g denied, 100 F.E.R.C. ¶ 61,246 (2002).
    On January 24, 2003, the Commission accepted Southern’s
    request to terminate the Blount IA; prior to termination, the IA
    was of a forty-year term, subject to prior termination by mutual
    assent.
    Southern submitted its second IA, between its Georgia
    Power transmission system and Athens Development, LLC
    (“Athens”), on June 5, 2002. At issue were three 115 kV
    breakers at two Georgia Power substations. The Commission
    held that the cost of the breakers could not be directly assigned
    to Athens, in light of the “At or Beyond” rule. Southern
    Company Services, Inc., Letter Order, Docket No. ER02-2015-
    000 (July 30, 2002), reh’g denied, 101 F.E.R.C. ¶ 61,309 (2002).
    On August 9, 2002, Southern filed a “Notice of Cancellation”
    regarding the Athens IA. See Southern Company Services, 103
    F.E.R.C. ¶ 61,279 (2003). The IA was cancelled effective
    January 6, 2003, when the parties submitted a revised IA. Prior
    to cancellation, the original IA was of a term of no less than ten
    years, subject to exceptions.
    Nevada Power submitted an unexecuted IA to the
    Commission on May 29, 2002. GenWest, LLC (“GenWest”)
    was the other party to the agreement. At issue was a “one line
    terminal” to be added to Nevada Power’s Harry Allen 500 kV
    Switchyard. The Commission held that the cost of the one line
    terminal could not be directly assigned to GenWest, in light of
    the “At or Beyond” rule. Nevada Power Co., 100 F.E.R.C. ¶
    61,077 at 61,302 (2002) (“Nevada Power I”), reh’g denied, 101
    F.E.R.C. ¶ 61,036 (2002) (“Nevada Power II”). Neither party
    has cancelled the agreement. It is for a term of at least ten years,
    7
    subject to exceptions.
    Following these administrative proceedings, Entergy,
    Southern, and Nevada Power filed these petitions for review.
    II. Analysis
    A. Jurisdiction
    Three of the four IAs at issue in these consolidated cases
    have been cancelled by the parties, with the consent of the
    Commission. Therefore, the cases arising under those three
    contracts are now moot, and we lack jurisdiction to hear these
    petitions. Moreover, because petitioners fail to show injury in
    fact resulting from the Commission’s “At or Beyond” rule per
    se, they lack standing to challenge generally the Commission’s
    policies that underlie those orders.
    A challenge to a specific Commission order regarding an
    interconnection agreement is moot when the contract is
    terminated. Northwest Pipeline Corp. v. FERC, 
    863 F.2d 73
    ,
    76-77 (D.C. Cir. 1988) (“Obviously, the challenged rate terms
    disappeared into the regulatory netherworld when the
    certificates themselves entered the archives. . . . Thus, to the
    extent it seeks [review of Orders affecting the certificates,
    Petitioner’s] claim is, beyond reasonable dispute, moot.”). The
    Entergy and Southern IAs have joined their predecessors in the
    regulatory netherworld; Entergy and Southern bring no live
    controversy to this court. Arguably, at least, the flaw in
    jurisdiction over two of the IAs should be viewed entirely in
    terms of standing rather than mootness, as Entergy and Southern
    (with reference to its second petition) had already terminated
    their IAs before seeking the assistance of an Article III court.
    By way of comparison, in Advanced Management Technology,
    Inc. v. FAA, 
    211 F.3d 633
     (D.C. Cir. 2000), we had to decide
    8
    whether standing or mootness doctrine applied in a situation
    where the petitioner filed its challenge to the agency’s
    termination of a contract after the agency had re-awarded the
    contract to petitioner. “The claim may sound like one of
    mootness–a justiciable controversy existed but no longer
    remains–but the timing makes [Petitioner’s] problem one of
    standing . . . . Standing is assessed ‘at the time the action
    commences,’ i.e., in this case, at the time [Petitioner] sought
    relief from an Article III court.” 
    Id. at 636
     (quoting Friends of
    the Earth, Inc. v. Laidlaw Envtl. Servs., Inc., 
    528 U.S. 167
    , 191
    (2000)) (internal citation omitted). In any event, we lack Article
    III jurisdiction to consider their specific complaints.
    Petitioners treat the justiciability analysis as a question
    of mootness. Under the mootness analysis, Petitioners argue
    that a challenge to agency action is not moot “where there is a
    reasonable chance of the dispute arising again between the
    government and the same [petitioner].” Legal Assistance for
    Vietnamese Asylum Seekers v. Dep’t of State, 
    74 F.3d 1308
    ,
    1311 (D.C. Cir. 1996) (“LAVAS”), vacated on other grounds,
    
    519 U.S. 1
     (1997). Granted, we so held in LAVAS, but that is
    not a parallel for the present case. In LAVAS, we noted that the
    precedents upon which we relied therein stood “for the
    proposition that the government cannot escape the pitfalls of
    litigation by simply giving in to a plaintiff’s individual claim
    without renouncing the challenged policy . . . .” 
    Id.
     That is not
    what happened in the petition before us today. The government
    did not give in; Petitioners abandoned the petition. While it may
    be true that the government cannot by selective surrender
    establish mootness to prevent challenge to its policies, this does
    not prevent mootness from occurring where the would-be
    challengers have abandoned the case or controversy that they
    would have us decide. The Entergy and Southern petitions fall
    into the latter category, not the former. There is no ongoing case
    or controversy. These challenges are moot.
    9
    These Petitioners cannot take refuge under the broader
    doctrine of “capable of repetition yet evading review.” See, e.g.,
    Weinstein v. Bradford, 
    423 U.S. 147
    , 148-49 (1975). The very
    contracts at issue establish operative terms of at least ten years.
    Some were of indefinite duration. Such contracts provide ample
    time for both administrative and judicial review. Indeed, the
    present petition did not evade review; Petitioners themselves
    chose to abandon the undertakings that gave rise to the
    controversy. If further proof is needed that such contracts do not
    fall within that exception to the mootness rule, the petition of
    Nevada Power, which remains an active controversy before us,
    clearly establishes that an IA need not evade review.
    Southern and Entergy claim that they are nonetheless
    before the court with a justiciable controversy because they are
    asserting facial challenges to the ongoing policy as well as
    seeking review of their underlying contracts. This argument
    also fails to keep them in court. While it is true that a petitioner
    with a mooted individual controversy may at times have
    standing to challenge an ongoing policy, such a petitioner must
    demonstrate standing to obtain each type of relief sought. See
    City of Houston v. HUD, 
    24 F.3d 1421
    , 1429 (D.C. Cir. 1994).
    Even if we assume that Entergy and Southern have properly
    raised a challenge to Commission policies beyond the specific
    orders for which they have sought review, they have not
    demonstrated that they have standing to challenge such ongoing
    policies.
    To meet “the irreducible constitutional minimum for
    standing,” petitioners must show, inter alia, that they suffer an
    actual injury in fact which is caused by the Commission’s
    policy. Lujan v. Defenders of Wildlife, 
    504 U.S. 555
    , 560-61
    (1992). The Commission’s “At or Beyond” rule challenged by
    Petitioners does not affect Entergy or Southern until they are
    confronted with it in a matter before the Commission regarding
    10
    a “live” interconnection agreement. Until then, they are in a
    position identical to that of any other utility company whose
    hypothetical future interconnection agreements may be
    evaluated according to the rule. To open the courthouse doors
    to Entergy and Southern for the purposes of their policy
    challenge disembodied from the original Commission orders
    would open the door to every other utility company’s challenges
    to Commission policies. Federal courts do not have the
    jurisdiction to render advisory opinions on such matters, with
    respect to FERC or any other administrative agency.
    Entergy and Southern lack standing to proceed before
    this Court.   This Court therefore lacks jurisdiction over the
    Entergy and Southern petitions.1 Their cases are dismissed.
    B. Limitation of Issues
    The elimination of the Entergy and Southern cases limits
    the matters remaining for this Court’s consideration. This
    Court’s power to review FERC petitions is tightly
    circumscribed: “No objection to the order of the Commission
    shall be considered by the court unless such objection shall have
    been urged before the Commission in the application for
    1
    In reaching this conclusion, we do not ignore Capitol
    Technical Servs, Inc. v. FAA, 
    791 F.2d 964
    , 967 (D.C. Cir. 1986),
    cited by the separate opinion of our colleague. Rather, we simply do
    not read that case, or any other, as suggesting that standing need not
    be established for a general challenge when such general challenge is
    all that is left in the case. True, we did not in Capitol Technical
    Services address the question of standing, but it seems that standing to
    challenge the general policy in that case was clear enough. As the
    Capitol Technical Services panel explained in analyzing ripeness, “the
    hardship to Capitol is concrete and easily perceived; noncompliant
    foreign aircraft cannot reasonably expect to contract with Capitol for
    major maintenance at locations they cannot reach.” 
    Id. at 969
    .
    11
    rehearing unless there is reasonable ground for failure so to do.”
    16 U.S.C. § 825l(b) (2004). “Parties seeking review of FERC
    orders must petition for rehearing of those orders and must
    themselves raise in that petition all of the objections urged on
    appeal.” Platte River Whooping Crane Critical Habitat Maint.
    Trust v. FERC, 
    876 F.2d 109
    , 113 (D.C. Cir. 1989) (emphasis in
    original).
    We construe § 825l narrowly. In Kelley ex rel. Mich.
    Dep’t of Nat’l Resources v. FERC, we held that objections not
    explicitly presented in proceedings below, but arguably
    “implicit” in other objections, were not properly preserved:
    “Suffice to say that an argument ‘implicit’ in prior requests
    before the Commission’s staff does not satisfy the strict standard
    of § 313(b) [of the Federal Power Act, codified at 16 U.S.C. §
    825l].” 
    96 F.3d 1482
    , 1488 (D.C. Cir. 1996).
    While § 825l offers petitioners an exception–i.e., a
    “reasonable ground for failure” to urge the objection
    below–Nevada Power offers no such reasonable ground for its
    failure to raise several objections in its petition for FERC
    rehearing. Therefore, any objections raised by Petitioners’
    consolidated briefs but not raised by Nevada Power in its
    administrative proceedings are not properly before this Court.
    The only issues raised by Nevada Power in its petition
    for rehearing and preserved in Petitioners’ consolidated briefs
    are whether: (1) the Commission’s determination that the
    facilities at issue benefit the entire network was not supported by
    substantial evidence, and (2) the Commission’s “At or Beyond”
    rule represents an unjustified departure from past precedent.
    Request for Rehearing at 6-12, Nevada Power Co., Docket No.
    ER02-1913-001 (Aug. 16, 2002). A different version of these
    arguments advanced by Entergy or Southern that was not
    advanced by Nevada Power–e.g., that the Commission ignored
    12
    evidence that the facilities in question actually decrease network
    stability–is not properly before this Court in our consideration
    of Nevada Power’s case. Such an argument was not even
    implicit–let alone explicit–in Nevada Power’s objections before
    the Commission. Indeed, the evidence allegedly ignored by the
    Commission–a sworn affidavit–was introduced in Southern’s
    proceedings, not Nevada Power’s.
    C. Substantial Evidence
    Nevada Power argues that the Commission’s finding that
    facilities located “at or beyond” the point of interconnection to
    the network benefit the entire network was not supported by
    substantial evidence. See 
    5 U.S.C. § 706
    (2)(E) (2004) (“The
    reviewing court shall . . . hold unlawful and set aside agency
    action, findings, and conclusions found to be . . . unsupported by
    substantial evidence . . . .”). It argues that GenWest was the sole
    beneficiary of the facilities at issue, and that geographic location
    of the additions to the Harry Allen Switchyard is not itself
    sufficient justification for a finding to the contrary.
    But Nevada Power’s view of “benefit” is too narrow.
    Like the petitioners in another recent challenge to the
    Commission’s policy, this Petitioner suffers from a “cramped
    view of what constitutes a ‘benefit.’” Entergy Services, Inc. v.
    FERC, 
    319 F.3d 536
    , 543 (D.C. Cir. 2003) (“Entergy I”).
    Nevada Power focuses on the benefit of “reliability” (or
    “stability”), which we recognized in Entergy I, 
    id. at 544
    . See
    Brief for Petitioners at 30. So does Nevada Power’s expert.
    Answer of Nevada Power Co. at Ex. A (Whalen Aff. at 2),
    Nevada Power Co., Docket No. ER02-1913-000 (July 3, 2002).
    But “stability” is not the only “benefit” recognized by the
    Commission: the Commission cites the new facilities’
    contribution to the Switchyard’s “expanded energy flow.” Brief
    for Respondent at 48. Indeed, the Whalen affidavit recognizes
    13
    that, but for the added facilities, GenWest could not contribute
    its energy flow to the network. 
    Id.
     This Court has recognized
    that system expansion is a “benefit” sufficient to support the
    Commission’s pricing policy, Entergy I, 
    319 F.3d at 544
    , and we
    repeat that recognition here today.
    The justifications that this Court accepted for the
    Commission’s application of the pre-existing cost allocation
    policy to those specific facilities also warrant this Court’s
    approval of the policies’ application to the facilities here. As we
    noted, “[o]ur conclusion that the Commission has adequately set
    forth its rationale rests . . . on its explanation in the Consumers
    Energy decisions that the Commission relied upon in the order
    to review.” 
    Id. at 543
    .
    The Consumers Energy explanation was the
    Commission’s justification of “a standard policy that requires
    credits for customer-funded network upgrades,” Consumers
    Energy Co., 96 F.E.R.C. ¶ 61,132 at 61,560 (2001) (“Consumers
    Energy II”) (emphasis added), quoted in Entergy I, 
    319 F.3d at 543
    , not just for certain types of customer-funded network
    upgrades. Petitioner contends that the facilities before us are not
    network upgrades. However, Consumers Energy resolves the
    question by its reference to the Commission’s May 17, 2001
    order. The Commission defined “network upgrades” by the
    point of connection of facilities, without a case-specific analysis
    of marginal benefit to other users:
    The Commission’s policy
    regarding credits for network
    upgrades associated with the
    interconnection of a generating
    facility has been, and continues
    to be, that all network upgrade
    costs (the cost of all facilities
    14
    from the point where the
    generator connects to the grid),
    including those necessary to
    remedy short-circuit and stability
    problems, should be credited
    back to the customer that funded
    the upgrades once delivery
    service begins.
    Consumers Energy Co., 95 F.E.R.C. ¶ 61,233 at 61,804 (2001)
    (“Consumers Energy I”) (emphasis added). In short, the
    Commission’s definition of “network upgrade,” accepted by
    Entergy I, includes any changes to facilities located on the grid.
    The Consumers Energy I justification, quoted above and in
    Entergy I, set forth an overarching defense of at least a “From”
    test: “all facilities from the point where the generator connects
    to the grid.” 
    Id.
     (emphasis added).
    Petitioners urge us to read Entergy I narrowly, restricting
    it to the facilities at issue in that case: short-circuit and stability
    network upgrades. 
    319 F.3d at 544
    . But to adopt such a narrow
    reading would be to adopt a “cramped” view of Entergy I’s “less
    cramped view.” 
    Id. at 543
    . Entergy I does not endorse the
    Commission’s policy merely with respect to short circuit and
    stability network upgrades. As this Court said in that case, such
    a limited holding was a mere “consequen[ce]” of the much
    larger holding: that the Commission had reasonably explained
    its crediting pricing policy generally. 
    Id.
     That pricing policy,
    spelled out in Consumers Energy, makes no mention of specific
    reference to short circuit and stability network upgrades. It
    referred to “all facilities from the point” of interconnection.
    Consumers Energy I, 95 F.E.R.C. at 61,804 (emphasis added).
    15
    D. Departure from Precedent
    The only difficulty–and though it is a small one, it is one
    upon which potentially millions of dollars of cost allocation
    rest–is whether “from” as a test of allocation justified by the
    Commission in Consumers Energy I equates to “at or beyond”
    as the Commission urges in the present controversy, or merely
    to “beyond.” Either is a natural reading of “from.” For
    example, when a bridal couple declares their fealty “from this
    day forward,” we would not likely interpret this as a declaration
    of faithfulness to begin the next day. The Commission’s “at or
    beyond” test is consistent with such an immediate beginning
    inclusive of everything from the point of commencement
    including that point. On the other hand, if a travel guide tells us
    that it is “one hundred miles from City A to City B,” we would
    not necessarily assume that any distance within the city of
    commencement is included within that one hundred miles.
    Neither construction would be unreasonable. Normally, we
    would defer to the Commission’s interpretation of its own prior
    ruling. Cassell v. FCC, 
    154 F.3d 478
    , 483 (D.C. Cir. 1998).
    However, such deference would presuppose that the
    Commission had justified the subsequent usage in the prior
    declaration it purports to interpret. Such justification is not
    present on the record before us.
    As we noted above, FERC’s explanation of its policy
    application to the present contract depends upon its adoption of
    its rationale from the Consumers Energy decisions. As we
    further discussed above, justification by adoption of a prior
    ruling is perfectly appropriate and adequate. The difficulty is
    that the Commission’s explanation in Consumers Energy, at
    least on its face, is not consistent with the Commission’s
    application of the test to the facts before us. Nevada Power’s
    petition does not depend on any inherent flaw in the “from” test
    as applied to improvements beyond the point of interconnection,
    16
    but only as to those precisely “at” the interconnection. It
    appears from the face of Consumers Energy II that the
    Commission’s application of its test to the facts before it in that
    case may have been consistent with Nevada Power’s
    interpretation rather than the one FERC advances now. The
    total interconnection cost at issue in Consumers Energy was
    $13.2 million. Of that total, the Commission permitted (albeit
    almost sub silentio) direct assignment of the “$3 million . . .
    attributable to the physical interconnection of the generating
    facility with consumers’ transmission grid,” and approved credit
    for the “remaining $10.2 million in network upgrade costs . . .
    .” Consumers Energy I, 95 F.E.R.C. at 61,082. If the
    Commission had intended “from” to mean “at or beyond” rather
    than simply “beyond,” then it is not at all clear what accounts
    for the $3 million in direct assignment, as the interconnection
    presumably is “at” the determinative point. We therefore must
    vacate the order under review and remand the controversy to the
    Commission for further proceedings.
    The progression of Commission pronouncements of its
    network upgrade policy demonstrates that the “At or Beyond”
    test is the product of regulatory evolution – marked by change,
    not consistency–beginning with Consumers Energy.                The
    Commission issued Consumers Energy I on May 17, 2001.
    There it described “all network costs” as “the cost of all
    facilities from the point where the generator connects to the
    grid.” 95 F.E.R.C. at 61,804 (emphasis added). As we noted,
    supra, in that analysis the Commission did not consider “the
    physical interconnection of the generating facility with . . . the
    grid” to be a “network upgrade.” Consumers Energy I itself was
    a clarification, see Entergy I, 
    319 F.3d at 541
    , of a prior order in
    which the Commission excluded from “system upgrades” “the
    cost of minimum facilities needed to establish the
    interconnection.” Amer. Elec. Power Service Corp., 91 F.E.R.C.
    ¶ 61,308, at 62,051 (2000) (“AEP”), quoted in Consumers
    17
    Energy II, 96 F.E.R.C. at 61,559.
    Less than one month after the issuance of Consumers
    Energy I, Commissioner Wood called for a change in policy.
    He proposed that “costs of transmission beyond the power plant
    busbar which are needed to accommodate the output of the new
    generation facility should be borne by the transmission service
    provider . . . .” Detroit Edison Co., 95 F.E.R.C. ¶ 61,415 at
    62,540 (2001). Commissioner Wood credited his “recent
    experience” on Texas’s regulatory body with demonstrating the
    need for interconnection cost-allocation policies that foster fair,
    efficient competition between old and new generators. 
    Id.
    While this may appear to be a restatement, not change, of policy
    in light of Consumers Energy I, the concurrence’s further
    explanation reveals a difference.            Looking back to
    Commissioner Wood’s experience, we see that the policies of
    the Public Utility Commission of Texas reflected an “At or
    Beyond” test rather than a “From” test. In at least one case the
    Texas Commission, in a decision authored by then-
    Commissioner Wood, included as “transmission costs” “the
    transmission switching facilities, necessary to provide the
    interconnection between [Generator] and [Transmission Service
    Provider].” Petition of Pasadena Cogeneration, L.P. for
    Declaratory Order, Docket No. 20,760, Public Util. Comm. of
    Texas, at ¶¶ I.15-18, III.1-2, 1999 Tex. PUC LEXIS 32 (Aug. 2,
    1999). Commissioner Wood’s discussion of the role of efficient
    cost-allocation in generator competition in Detroit Edison
    mirrors his discussion in Pasadena Cogeneration. Given the
    facts in Pasadena Cogeneration, he clearly endorsed an “At or
    Beyond” test in 1999. He appears to have called for a similar
    test in his 2001 Detroit Edison concurrence.
    One month after Commissioner Wood’s statement in
    Detroit Edison, the Commission denied a rehearing in
    Consumers Energy, and it made no reference to either a “From”
    18
    test or an “At or Beyond” test, but it referred only to network
    “upgrade” costs. Consumers Energy II, 96 F.E.R.C. at 61,561.
    The day after Consumers Energy II, however, the
    Commission stated its policy in a manner resembling an “At or
    Beyond Test” more than a “From” test of the sort suggested in
    Consumers Energy I, as it described the difference between a
    direct-assignment “interconnection facility” and a “network
    upgrade.” As the Commission noted: “Interconnection facility
    costs are those costs associated with facilities on the generator’s
    side of the interconnection with the grid, which traditionally
    have been directly assigned to the generator. Network upgrade
    costs are any upgrades necessary to grid facilities to allow the
    generator to inject its power at the interconnection.” Removing
    Obstacles to Increased Electric Generation And Natural Gas
    Supply In The Western United States, 96 F.E.R.C. ¶ 61,155, at
    61,674 (2001) (emphasis added). Removing Obstacles cited
    Consumers Energy I as a proper statement of its network
    upgrade cost-allocation policies, id. at 61,674 n.37, but did not
    explain why Consumers Energy I did not consider “the physical
    interconnection of the generating facility with . . . the grid” to be
    a “network upgrade,” 95 F.E.R.C. at 61,802. Nor did it explain
    why Consumers Energy II did not consider AEP’s “minimum
    facilities needed to establish the interconnection” to be “system
    upgrades.”
    In the three years following Removing Obstacles and
    Consumers Energy, the Commission has reiterated that its “At
    or Beyond” test was born not in Removing Obstacles but in
    Consumers Energy I and II. In the administrative proceedings
    regarding Entergy’s petition now before this Court, the
    Commission equated Consumers Energy’s “from the point [of
    interconnection]” language with an “At or Beyond” rule. Order
    Denying Rehearing, Entergy Gulf States, Inc., 99 F.E.R.C. ¶
    61,095, at 61,399 (2002) (“Entergy makes much of the fact that
    19
    we referred to network facilities as all those ‘from’ the point
    where the customer connects to the grid in Consumers, while
    referring to them, for the first time, as facilities ‘at or beyond’
    that point in Entergy. . . . [W]e fail to see a meaningful
    distinction between these phrases . . . .”). The Commission has
    continued to maintain this position in its hearings on Southern’s
    more recent IAs. Southern Co. Servs., 108 F.E.R.C. ¶ 61,220 at
    62,226 (2004); Southern Co. Servs., 108 F.E.R.C. ¶ 61,229 at
    62,249 (2004). In Tampa Electric Co., the Commission traced
    the lineage of the “At or Beyond” test at as far back as
    Consumers Energy, and perhaps as far back as 1992’s Pub.
    Service Co. of Colorado. 99 F.E.R.C. ¶ 61,192 at 61,795 (2002)
    (citing 59 F.E.R.C. ¶ 61,311 at 62,149 (1992)).                The
    Commission repeated this genealogical claim in its denial of
    rehearing in Nevada Power. 101 F.E.R.C. ¶ 61,036 at 61,145
    (2002). But in none of these cases did the Commission take
    account of Consumers Energy I and II’s discussion of facilities
    at the point of “interconnection.”
    Reading these cases, recounting the Commission’s
    development of a “From” test, tracing its transformation into an
    “At or Beyond” test, and keeping in mind the Commission’s
    subsequent assertions that the two tests are one and the same, we
    are left with the conclusion that the “At or Beyond” test
    represents an apparent departure from Consumers Energy’s
    “From” test. That departure may be slight, but it is a departure
    nonetheless.
    We do not suggest that the Commission may not directly
    assign the costs at issue–as is apparent from our discussion in
    Part C, the same substantial evidence appears to support either
    test. But if the Commission does so, it must provide further
    explanation. The Commission may change its practices, but it
    must do so with “reasoned analysis indicating that prior policies
    and standards are being deliberately changed, not casually
    20
    ignored.” Entergy I, 
    319 F.3d at 541
    . Departures from
    precedent must not violate the Administrative Procedure Act’s
    prohibition on arbitrary and capricious decisionmaking.     
    5 U.S.C. § 706
    (2)(A); TransCanada Pipelines Ltd. v. FERC, 
    24 F.3d 305
    , 308 (D.C. Cir. 1994).
    Although an agency’s interpretation of its own precedent
    is entitled to deference, Cassell v. FCC, 
    154 F.3d 478
    , 483 (D.C.
    Cir. 1998), this Court cannot accept the Commission’s assertion
    that “it has not now nor has it ever directly assigned the costs of
    the network at its borders.” Brief for Respondent at 44. We will
    therefore allow the petition of Nevada Power and remand this
    case to the Commission for further explanation.                 That
    explanation may take the form of a clarification of Consumers
    Energy I that in some way establishes that we have misread the
    Commission’s apparent direct assignment of costs occurring
    precisely at the point of interconnection or an explanation of
    why it has departed from that policy. It must do one or the other
    if we are to sustain the result reached in the order on review.
    Conclusion
    For the reasons set forth above, we conclude that the
    petitions of Southern and Entergy must be dismissed. However,
    as to the order from which Nevada Power petitions for review,
    we order that it be vacated and the case remanded to the
    Commission for further proceedings consistent with this
    opinion.
    So ordered.
    TATEL, Circuit Judge, concurring in part and concurring
    in the judgment: I agree with the court on the merits and join
    Parts I and II.B-D of its opinion. I also agree that we lack
    jurisdiction over the Entergy and Southern petitions, but I cannot
    join Part II.A because, in my view, the court’s approach
    “incorrectly conflate[s] our case law on initial standing to bring
    suit with our case law on postcommencement mootness,”
    Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., Inc., 
    528 U.S. 167
    , 174 (2000) (citations omitted).
    Two of the three petitions fail—unarguably, in my
    view—on standing grounds alone. Entergy filed its petition for
    review on June 24, 2002, ten days after FERC accepted the
    company’s proposed termination of its Interconnection
    Agreement (“IA”) with Amelia Energy Center. Southern filed
    its second petition for review on February 13, 2003, more than
    a month after the effective cancellation of its IA with Athens
    Development. Since neither IA remained in effect at the time
    the companies sought judicial review, precedent requires that we
    address jurisdiction as a question of standing, not mootness.
    In Advanced Management Technology, Inc. v. FAA, 
    211 F.3d 633
     (D.C. Cir. 2000), we had to decide whether standing or
    mootness doctrine applied in a situation where the petitioner
    filed its challenge to the agency’s termination of a contract after
    the agency had re-awarded the contract to petitioner. “The
    claim may sound like one of mootness—a justiciable
    controversy existed but no longer remains—but the timing
    makes [petitioner’s] problem one of standing. . . . Standing is
    assessed ‘at the time the action commences,’ i.e., in this case, at
    the time [petitioner] sought relief from an Article III court.” 
    Id. at 636
     (quoting Laidlaw Envtl. Servs., 
    528 U.S. at 191
    ) (internal
    citation omitted); see also WorldCom, Inc. v. FCC, 
    308 F.3d 1
    ,
    10 (D.C. Cir. 2002) (where petitioner lacked standing at the
    onset of its suit because the issue had lost “practical
    significance,” it could not argue that its situation was “capable
    of repetition yet evading review” since “that familiar exception
    2
    to mootness cannot confer standing on a claim when injury in
    fact was missing at the outset”) (internal quotation marks
    omitted); City of Orrville v. FERC, 
    147 F.3d 979
    , 985 n.5 (D.C.
    Cir. 1998) (“Because [petitioner’s] preliminary permit expired
    before it petitioned for review, . . . its claims are properly
    disposed of on standing, rather than mootness, grounds.”). The
    court cites Northwest Pipeline Corp. v. FERC, 
    863 F.2d 73
    , 76
    (D.C. Cir. 1988), but in that case we applied a mootness analysis
    because petitioner filed for review in 1987 (as the docket
    number makes clear) well before “the challenged rate terms
    disappeared into the regulatory netherworld” in June 1988. See
    
    id.
    Given this case law, I believe this court had no reason to
    consider whether mootness exceptions apply to the Entergy and
    second Southern petitions, as the two companies lacked standing
    in the first place. Once their IAs had terminated, neither
    qualified as a party “aggrieved by an order issued by the
    Commission” within the meaning of section 313(b) of the
    Federal Power Act, 16 U.S.C. § 825l(b). “The requirement of
    aggrievement serves to distinguish a person with a direct stake
    in the outcome of a litigation from a person with a mere interest
    in the problem.” City of Orrville, 
    147 F.3d at 985
     (quoting
    North Carolina Utils. Comm’n v. FERC, 
    653 F.2d 655
    , 662
    (D.C. Cir. 1981)). After their IAs terminated, Entergy and
    Southern had only a “mere interest.” They thus lack standing to
    petition for review in this court.
    Southern’s first petition for review presents a different,
    more complex situation.         Southern filed that petition on
    November 1, 2002, almost three months before FERC accepted
    the termination of the company’s IA with Blount County
    Energy. “[A]t the time the action commence[d],” Laidlaw Envtl.
    Servs., 
    528 U.S. at 191
    , Southern therefore had standing to
    challenge FERC’s modification of the company’s IA, as well as
    3
    the policies on which that order rested. With the cancellation of
    the IA, Southern’s specific challenge became moot, and (as the
    court notes) neither the “voluntary cessation” nor the “capable
    of repetition yet evading review” exception applies.
    We thus need to determine whether a justiciable
    controversy remains due to Southern’s broader reason for
    objecting to the challenged order—namely, the company’s claim
    that the policies underlying that order require it to revise other
    IAs, revisions that will cost it some $22 million. This court
    faced a similar issue in Capitol Technical Services, Inc. v. FAA,
    
    791 F.2d 964
    , 967 (D.C. Cir. 1986), where petitioner,
    maintenance provider for foreign aircraft, sought an exemption
    from an FAA noise-control regulation so that it could fly two
    DC-8s to the United States for servicing. By the time we heard
    the petition, however, the time for servicing the two airplanes
    had passed. 
    Id. at 965-66
    . We held that although petitioner’s
    challenge to the FAA’s denial of an exemption for the specific
    planes had become moot, the “challenge to th[e] general policy
    is not moot” because “[c]learly Capitol sought not only a
    particular exemption, but also a decision favorable to the
    continued viability of its business.” 
    Id. at 968
    ; see also City of
    Houston v. Dep’t of Hous. & Urban Dev., 
    24 F.3d 1421
    , 1428-
    1430 (D.C. Cir. 1994); Better Gov’t Ass’n v. Dep’t of State, 
    780 F.2d 86
    , 90-92 (D.C. Cir. 1986). Significantly, we did not
    reevaluate whether Capitol had standing to petition for review
    on policy grounds. Had we done so under the court’s logic
    today, we would have concluded that Capitol lacked standing to
    pursue its policy challenge, since Capitol was in a “position
    identical to that of any other [maintenance provider] whose
    hypothetical future [requests for foreign aircraft exemptions]
    may be evaluated according to the rule,” see majority slip op. at
    9-10. Instead, we applied mootness doctrine to evaluate the
    justiciability of Capitol’s policy challenge and found “plainly
    meritless” the agency’s argument that “[i]f Capitol wishes to
    4
    obtain exemptions for future flights by noncompliant foreign
    operators to its maintenance facilities . . . it should reapply for
    exemptions and, if unsatisfied, seek review of those decisions.”
    
    791 F.2d at 989
    . Concluding that Capitol’s policy concerns
    remained alive, we went on to find its challenge ripe because the
    FAA’s policy was fit for review and Capitol would suffer
    hardship without immediate review. 
    791 F.2d at
    969 & n.26
    (applying the ripeness test developed in Abbot Laboratories v.
    Gardner, 
    387 U.S. 136
     (1967)). As to fitness, we observed that
    the issues were “purely legal . . . [and] there can be no question
    that the agency action has taken final form; indeed, the agency
    has not even suggested that any further policy evolution could
    be expected.” 
    Id.
    Disregarding Capitol Technical Services, the court today
    holds that once a petitioner’s specific challenge has become
    moot, we must go back and reevaluate the petitioner’s standing.
    In support, the court relies on City of Houston, 
    24 F.3d at
    1429-
    30 & n.6, which stands for the proposition, established since at
    least City of Los Angeles v. Lyons, 
    461 U.S. 95
     (1983), that
    plaintiffs in civil suits must establish standing separately for
    each type of relief they seek—declaratory relief, injunctive
    relief, damages, etc. By contrast, like the petitioner in Capitol
    Technical Services, Southern has filed a petition for review of an
    agency action and seeks the same relief on both specific and
    policy grounds: vacatur of FERC’s order based on a finding that
    the order was arbitrary and capricious. At the time Southern
    petitioned for review, it plainly had standing to seek this relief,
    and under Capitol Technical Services our jurisdiction over
    Southern’s policy challenge should turn on whether that
    challenge has also become moot or, alternatively, whether it is
    unripe for review.
    As to mootness, we have typically applied the policy-
    challenge exception to mootness in situations where the specific
    5
    requests became moot due to circumstances beyond petitioners’
    control. See Capitol Technical Servs., Inc., 
    791 F.2d at 967-68
    ;
    City of Houston, 
    24 F.3d at 1424, 1428-29
    ; Better Gov’t Ass’n,
    
    780 F.2d at 88, 90-92
    . But Southern’s specific request became
    moot due to its voluntary decision to seek cancellation of its IA.
    I am thus unsure whether Southern’s policy challenge remains
    alive. In any event, I am convinced the challenge is unripe.
    To begin with, this case differs from Capitol Technical
    Services in a significant respect. There, the FAA “ha[d] not
    even suggested that any further policy evolution could be
    expected.” 
    791 F.2d at 969
    . At the time of Southern’s
    challenge, by contrast, FERC’s policy had not yet become final.
    Indeed, in later rulemaking orders, FERC revisited its “At or
    Beyond Test” (and particularly its explanations for the test). See
    Standardization of Generator Interconnection Agreements and
    Procedures, Order No. 2003, [Regs. Preambles] FERC Stats. &
    Regs. ¶ 31,146, 
    68 Fed. Reg. 49,846
     (2003); on reh’g, Order No.
    2003-A, [Regs. Preambles] FERC Stats. & Regs. ¶ 31,160, 
    69 Fed. Reg. 15,932
     (2004). Absent a specific need for relief, it
    seems unfair to require FERC to defend its earlier, less complete
    explanation of its policy. Moreover, the “only hardship”
    Southern “will endure as a result of delaying consideration of
    this issue is the burden of having to file another suit.” See Webb
    v. Dep’t of Health & Human Servs., 
    696 F.2d 101
    , 107 (D.C.
    Cir. 1982). Because this relatively minimal hardship does not
    outweigh the relatively strong interest in postponing judicial
    review, I would find Southern’s policy challenge unripe.
    Over a quarter century ago, Justice Brennan warned that
    “Art. III jurisprudence . . . in such areas as mootness and
    standing is creating an obstacle course of confusing standardless
    rules to be fathomed by courts and litigants.” Kremens v.
    Bartley, 
    431 U.S. 119
    , 140 (1977) (Brennan, J., dissenting). The
    opinion in this case may add still more obstacles to the already
    6
    littered course. Until today, where a petitioner sought review
    after the challenged order had ceased to aggrieve it, as with two
    of the petitions in this case, we evaluated the case under
    standing doctrine alone. Yet the court today addresses mootness
    even though “if a plaintiff lacks standing at the time the action
    commences, the fact that the dispute is capable of repetition yet
    evading review will not entitle the complainant to a federal
    judicial forum.” See Laidlaw Envtl. Servs., 
    528 U.S. at 191
    .
    Moreover, we have no reason to reevaluate a petitioner’s
    standing during the course of a proceeding, as we retain
    authority to weed out those cases that cease to present justiciable
    controversies by using the doctrines designed for that
    purpose—mootness and ripeness. The court’s midstream
    assessment of standing muddies this sensible framework. True,
    standing and mootness are closely related, but they are cousins,
    not twins.
    

Document Info

Docket Number: 18-3055

Filed Date: 12/10/2004

Precedential Status: Precedential

Modified Date: 2/19/2016

Authorities (20)

Transcanada Pipelines Limited v. Federal Energy Regulatory ... , 24 F.3d 305 ( 1994 )

legal-assistance-for-vietnamese-asylum-seekers-thua-van-le-em-van-vo-thu , 74 F.3d 1308 ( 1996 )

N. Conant Webb, M.D. v. Department of Health and Human ... , 696 F.2d 101 ( 1982 )

Northwest Pipeline Corporation v. Federal Energy Regulatory ... , 863 F.2d 73 ( 1988 )

New York v. Federal Energy Regulatory Commission , 122 S. Ct. 1012 ( 2002 )

Better Government Association v. Department of State ... , 780 F.2d 86 ( 1986 )

City of Houston, Texas v. Department of Housing and Urban ... , 24 F.3d 1421 ( 1994 )

Lujan v. Defenders of Wildlife , 112 S. Ct. 2130 ( 1992 )

Capitol Technical Services, Inc. v. Federal Aviation ... , 791 F.2d 964 ( 1986 )

Friends of the Earth, Inc. v. Laidlaw Environmental ... , 120 S. Ct. 693 ( 2000 )

Abbott Laboratories v. Gardner , 87 S. Ct. 1507 ( 1967 )

platte-river-whooping-crane-critical-habitat-maintenance-trust-v-federal , 876 F.2d 109 ( 1989 )

north-carolina-utilities-commission-v-federal-energy-regulatory , 653 F.2d 655 ( 1981 )

Weinstein v. Bradford , 96 S. Ct. 347 ( 1975 )

Cassell v. Federal Communications Commission , 154 F.3d 478 ( 1998 )

WrldCom Inc v. FCC , 308 F.3d 1 ( 2002 )

Advn Mgmt Technol v. FAA , 211 F.3d 633 ( 2000 )

City of Orrville v. Federal Energy Regulatory Commission , 147 F.3d 979 ( 1998 )

Kremens v. Bartley , 97 S. Ct. 1709 ( 1977 )

Entergy Services, Inc. v. Federal Energy Regulatory ... , 319 F.3d 536 ( 2003 )

View All Authorities »