No Gas Pipeline v. Federal Energy Regulatory Commission , 756 F.3d 764 ( 2014 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued February 19, 2014                Decided July 1, 2014
    No. 12-1470
    NO GAS PIPELINE,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    STATOIL NATURAL GAS, LLC, ET AL.,
    INTERVENORS
    Consolidated with 12-1474, 12-1475
    On Petitions for Review of Order of the
    Federal Energy Regulatory Commission
    John J. Zimmerman argued the cause for Environmental
    Petitioners. With him on the briefs was Carolyn Elefant.
    Jason T. Watson argued the cause and filed the briefs for
    petitioner Jersey City. Derek S. Fanciullo entered an
    appearance.
    Jennifer S. Amerkhail, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With her on the
    2
    brief were David L. Morenoff, Acting General Counsel, and
    Robert H. Solomon, Solicitor.
    John P. Elwood argued the cause for intervenors. With him
    on the brief were Anita R. Wilson, Andrew N. Beach, Jeremy C.
    Marwell, Steven E. Hellman, Kirstin E. Gibbs, Christopher M.
    Heywood, Peter P. Garam, and Shira R. Rosenblatt.
    Before: HENDERSON and GRIFFITH, Circuit Judges, and
    SENTELLE, Senior Circuit Judge.
    Opinion for the Court filed by Senior Circuit Judge
    SENTELLE.
    SENTELLE, Senior Circuit Judge: The Federal Energy
    Regulatory Commission (“FERC”) entered an order granting a
    certificate of public convenience and necessity for the
    construction of a natural gas pipeline connecting New York and
    New Jersey (“NJ-NY Project” or “Project”). The city of Jersey
    City and a coalition of environmental groups filed separate
    petitions for review on differing grounds. For the reasons set
    forth below, we conclude that we do not have jurisdiction over
    any of the petitions, and we will therefore dismiss all without
    reaching the merits of any.
    BACKGROUND
    The Natural Gas Act (“NGA”) requires entities seeking to
    construct natural gas facilities to obtain a certificate of public
    convenience and necessity from FERC.                  15 U.S.C.
    § 717f(c)(1)(A). In the proceeding under review, the
    Commission granted such a certificate to two subsidiaries of
    Spectra Energy Corporation, Texas Eastern Transmission, LP
    and Algonquin Gas Transmission, LLC (collectively “Spectra”),
    to expand its existing natural gas transportation pipeline in
    3
    Connecticut and New Jersey, and to extend a new pipeline from
    New Jersey into lower Manhattan in New York. See Tex. E.
    Transmission, LP, 139 FERC ¶ 61,138 P.7 (2012).
    Three environmentalist groups, NO Gas Pipeline, Sierra
    Club, and Food & Water Watch (collectively “environmental
    petitioners”), filed two petitions for review of the order, alleging
    that FERC did not comply with the National Environmental
    Policy Act, 42 U.S.C. § 4321 et seq., in the proceedings and
    grant of the certificate. The city of Jersey City filed a separate
    petition for review, arguing that FERC could not constitutionally
    conduct the proceedings and grant the order because its financial
    structure created “possible temptation” to be biased in favor of
    pipeline companies, and also, that FERC exercised actual bias
    in violation of “either Due Process or the APA.” Jersey City Br.
    at 2. None of the petitions brings the order for review within the
    jurisdiction of this court. The environmental petitioners lack
    standing, and the petition of Jersey City raises questions not
    preserved in the administrative proceedings.
    In addition to the NGA requirement that entities seeking to
    construct natural gas facilities obtain a certificate of public
    convenience and necessity from FERC, the NEPA imposes
    requirements on agencies such as FERC to prepare
    environmental impact statements in compliance with the Act.
    42 U.S.C. § 4321 et seq. In processing the application of
    Spectra, FERC issued a draft environmental impact statement
    (“DEIS”) on September 9, 2011, and a final environmental
    impact statement (“FEIS”) on March 16, 2012. In the course of
    the environmental review, FERC received hundreds of
    comments, including expressions of concerns over the level of
    radon present in natural gas and radon’s effect on indoor air
    quality. The Commission responded to these concerns,
    ultimately concluding that radon from home use of natural gas
    was not likely to pose a hazard, and citing factors which in
    4
    FERC’s view would reduce radon in natural gas.
    FERC approved the project on May 21, 2012.
    Environmental petitioners had moved to intervene on
    January 26, 2011, and filed their concerns about the radon and
    also about the possibility of cyber attacks on Spectra’s computer
    systems, which they believed could result in explosions. After
    the March 16, 2012, release of the FEIS, environmental
    petitioners moved to supplement the record with a study
    regarding radon from Marcellus Shale gas. Spectra requested
    leave to respond on the radon issue and did so with a substantive
    response and two additional radon studies. On May 21, 2012,
    FERC issued its order granting the certificates of convenience
    and necessity. See 139 FERC ¶ 61,138. In the order granting
    the certificates, FERC addressed the radon issue and made
    specific reference to the Marcellus Shale gas, noting that the
    proposed pipeline expansion “is not designed to serve as a
    gathering system for gas from Marcellus Shale.” 
    Id. at P.73.
    Petitioners sought rehearing. On October 18, 2012, FERC
    entered its order denying rehearing. 141 FERC ¶ 61,043. In the
    rehearing order, FERC addressed the newly submitted radon
    studies, 
    id. at P.49-56,
    and the environmental petitioners’
    comments concerning the risk of cyber attack on Spectra’s
    control systems, 
    id. at P.60-65.
    The environmental groups filed
    their current petitions for review.
    STANDING
    We will not reach the merits of environmental petitioners’
    claims, because we have no jurisdiction to do so. It is
    fundamental to federal jurisprudence that Article III courts such
    as ours are courts of limited jurisdiction. Therefore, “we must
    examine our authority to hear a case before we can determine
    the merits.” Wyo. Outdoor Council v. U.S. Forest Serv., 
    165 F.3d 43
    , 47 (D.C. Cir. 1999) (citing Steel Co. v. Citizens for a
    5
    Better Env’t, 
    523 U.S. 83
    (1998)). In order for us to have
    jurisdiction over a case or controversy, the party bringing the
    claim bears the burden of establishing that it has standing. See,
    e.g., Lujan v. Defenders of Wildlife, 
    504 U.S. 555
    , 561 (1992).
    The “irreducible constitutional minimum of standing contains
    three elements.” 
    Id. at 560.
    These elements require that the
    plaintiffs must have suffered first an “injury in fact”; second, the
    injury must be “fairly traceable to the challenged action of the
    defendant”; and third, the injury must be redressable by a
    favorable decision in the litigation. 
    Id. at 560-61
    (internal
    punctuation and citations omitted). Environmental petitioners’
    claims founder on at least the first two of the required elements.
    These petitioners seek to proceed under associational
    standing. To establish Article III standing as an association, at
    least one member must meet the three elements set forth in
    Lujan. First, the member or members must have suffered an
    “injury in fact”—that is, “an invasion of a legally protected
    interest which is (a) concrete and particularized . . . and (b)
    actual or imminent, not conjectural or hypothetical.” 
    Id. at 560
    (quotations omitted). Petitioners have provided the court with
    affidavits demonstrating the reasons why their members object
    to the pipeline, but nothing in the affidavits establishes an injury
    in fact satisfying the constitutional minimum set forth in Lujan.
    Environmental petitioners, or at least some of them, submit
    declarations attesting that their members are “injured by the
    certainty that radon levels in the residences will increase once
    gas from sources that have higher radon levels . . . than currently
    supplied gas begins to flow through [the proposed] pipelines into
    their homes.” Env. Pets. Br. at 13 (emphasis added). This will
    not carry petitioners’ burden of establishing standing. In order
    to establish injury in fact, claimants must demonstrate
    “concrete” injury. See, e.g., Occidental Permian Ltd. v. FERC,
    
    673 F.3d 1024
    , 1026 (D.C. Cir. 2012). The “irreducible
    6
    constitutional minimum” referenced in Lujan requires the
    showing of “a concrete injury that has either transpired or is
    ‘imminent.’” 
    Id. A “conjectural
    or hypothetical” injury is not
    sufficient. See 
    Lujan, 504 U.S. at 560
    .
    The affidavits from petitioners’ members express concerns
    over injuries that have neither occurred nor become imminent.
    The increased risk to their health is something that may occur if
    the pipeline or the pipeline suppliers tap into gas that has more
    radon than the current mix; nothing occurs to alleviate any
    increased radon in that case; the radon does not become diluted
    by mixing with other gas; and the radon in fact reaches and
    permeates their homes. Like the injuries claimed in Occidental
    Permian, these concerns are “far too speculative to represent a
    concrete injury” establishing 
    standing. 673 F.3d at 1026
    (internal quotation marks omitted).
    Neither do petitioners’ declarations carry their burden with
    respect to the second element of standing: causation. Causation
    requires that the injury “be fairly traceable to the challenged
    action of the defendant and not the result of the independent
    action of some third party not before the court.” 
    Lujan, 504 U.S. at 560
    (internal punctuation and citations omitted). For the
    speculative injuries to occur here, the producers and transporters
    of the gas would need to have chosen high radon shale gas as the
    sole or predominant source of the gas transported by the project,
    then transported and delivered the gas without in some fashion
    diluting or processing it so as to reduce the radon content to
    something approaching that of the gas petitioners are presently
    receiving. Then, and only then, would the projected injury
    become imminent, and possibly occur. Again, petitioners have
    failed in carrying their burden of establishing standing. We will
    not reach the merits of their radon-based claim, as we do not
    have jurisdiction.
    7
    Likewise, we lack jurisdiction over petitioners’ claims of
    potential harm from the safety of the pipeline operations, and
    specifically, the danger of cyber terrorism. Without rehashing
    the requirements for establishing constitutional standing set
    forth in the discussion of the radon claims, we note that the same
    infirmities exist with respect to the second set of claims. There
    is no showing that any such danger is either actual or imminent.
    There is no showing that it could occur without the intervening
    acts of third parties.
    JERSEY CITY’S PETITION
    Jersey City brings a claim more fundamental than that of
    petitioners. We might also describe it as novel, and even
    creative. Briefly put, the City contends that FERC cannot
    constitutionally regulate the pipeline industry. In more detail,
    Jersey City reasons that due process “requires fair adjudicative
    proceedings before neutral and detached decisionmakers.”
    Jersey City Br. at 14 (citing Ward v. Vill. of Monroeville, 
    409 U.S. 57
    , 59-60 (1972)). Thus, petitioner argues, the Constitution
    mandates adjudicative proceedings free from actual bias, and the
    appearance of bias. 
    Id. (citing In
    re Murchison, 
    349 U.S. 133
    ,
    136 (1955)). Jersey City then analyzes the financial structure of
    FERC and notes that under the applicable statutory scheme,
    FERC receives its funding from the pipeline industry, not from
    the taxpayers. Thus, Jersey City reasons, FERC is beholden to
    the pipelines applying to it for certificates, and may not
    constitutionally adjudicate their application.
    Once again, we cannot consider the merits of the petition,
    as we have no jurisdiction. This is true for multiple reasons.
    First, Jersey City asserts that we have jurisdiction under the
    Natural Gas Act, 15 U.S.C. § 717r(b). That section provides
    that any party “aggrieved by an order issued by the Commission
    [in a proceeding under this chapter] may obtain a review of such
    8
    order” in this court. But petitioner’s claim does not come within
    the jurisdictional grounds of this statute. Although petitioner
    claims to be an aggrieved party, it has not demonstrated how it
    has been injured and indeed does not challenge any part of
    FERC’s ruling either as to its reasoning, its findings, or any
    decision in the administrative proceeding. The petition simply
    does not meet the parameters of 15 U.S.C. § 717r(b). Jersey
    City is not actually seeking review of the order.
    Insofar as Jersey City sets forth a statutory quarrel, its
    complaint is against the Budget Act and the financial structure
    that it creates. It is that provision that sets forth the funding of
    the Commission by assessments, not the Natural Gas Act, and
    certainly not the order which Jersey City purports to bring
    before us. Jersey City’s claims do not come within the
    jurisdictional grant of § 717r(b).
    We do not have original jurisdiction over claims arising
    from the Budget Act. We have never seen a claim directly
    parallel to the one asserted by Jersey City, but we have observed
    in other contexts that “[i]nitial review occurs at the appellate
    level only when a direct-review statute specifically gives the
    court of appeals subject-matter jurisdiction to directly review
    agency action.” Watts v. SEC, 
    482 F.3d 501
    , 505 (D.C. Cir.
    2007). As we observed in Watts, “Congress is free to ‘choose
    the court in which judicial review of agency decisions may
    occur.’” 
    Id. (quoting Five
    Flags Pipe Line Co. v. Dep’t of
    Transp., 
    854 F.2d 1438
    , 1439 (D.C. Cir. 1988)). As we further
    observed in Watts, “[b]ecause district courts have general
    federal question jurisdiction under 28 U.S.C. § 1331, the
    ‘normal default rule’ is that ‘persons seeking review of agency
    action go first to district court rather than to a court of appeals.’”
    
    Id. at 505
    (quoting Int’l Bhd. of Teamsters v. Pena, 
    17 F.3d 1478
    , 1481 (D.C. Cir. 1994)). There is no statute that takes this
    petition outside that normal rule. The NGA gives us jurisdiction
    9
    to review orders in proceedings under that Act, not claims
    unanchored in pipeline proceedings but arising under the Budget
    Act. We have no jurisdiction.
    With respect to this conclusion, we stress the narrowness of
    our jurisdictional holding. The precise direct-review statute at
    issue in this case allows a party aggrieved by a FERC order
    issued under the Natural Gas Act to “obtain a review of such
    order.” 15 U.S.C. § 717r(b) (emphasis added). Here, however,
    Jersey City does not target any aspect of FERC’s actual decision
    and there is no claim properly before us that the process that
    produced the decision was tainted by actual bias or some other
    improper motivation. Instead, the City’s claim centers wholly
    on another statute (the Budget Act), which lacks a direct-review
    provision. Furthermore, the nature of the precise claim raised by
    Jersey City—a constitutional challenge to FERC’s funding
    structure—potentially implicates factual issues not explored in
    the record (e.g., the extent to which FERC’s financial needs will
    increase with time and the ability of existing pipeline companies
    to absorb these costs and remain profitable) because the claim
    is so tangential to the substance of the order. This prospect
    further counsels against reading 15 U.S.C. § 717r(b) as granting
    us jurisdiction over Jersey City’s claim because, as Congress
    must surely be aware, this court, unlike the district court, is not
    well equipped to make factual determinations. See Doe v. Gen.
    Hosp. of Dist. of Columbia, 
    434 F.2d 427
    , 432 (D.C. Cir. 1970).
    Thus, given this unique set of circumstances, and with the
    understanding that this opinion leaves intact our existing
    precedent, see, e.g., AirLine Pilots Ass’n v. CAB, 
    750 F.2d 81
    (D.C. Cir. 1984), as it must, see United States v. Carson, 
    455 F.3d 336
    , 384 n.43 (D.C. Cir. 2006) (per curiam) (“[W]e are, of
    course, bound to follow circuit precedent absent contrary
    authority from an en banc court or the Supreme Court.”), we
    conclude that we lack jurisdiction.
    10
    Again, lest we overlook anything which we should address,
    we note that Jersey City has made no real attempt to
    demonstrate standing. We further note that while Jersey City
    asserts that there is actual bias and not merely an appearance, it
    provides no foundation upon which we could review that claim.
    Its only asserted basis for the actual bias is that FERC has
    consistently granted applications from pipelines. This adds
    nothing to the strength of an otherwise unsupported claim.
    Presumably under most regulatory schemes, by the time
    applicants and their expert counsel have worked through
    changes, adaptations, and amendments, they are not likely to
    pursue many certificates that are hopeless. The fact that they
    generally succeed in choosing to expend their resources on
    applications that serve their own financial interests does not
    mean that an agency which recognizes merit in such applications
    is biased.
    We finally note that Jersey City’s alleged constitutional
    claim of actual bias is also barred as untimely. Jersey City has
    shown us nothing of record to establish that it raised this issue
    before FERC’s issuance of the initial order. FERC regularly
    rejects requests for rehearing that raise issues not previously
    presented where there is no showing that the issue is “based on
    matters not available for consideration . . . at the time of the
    final decision.” 18 C.F.R. § 385.713(c)(3); see also Rehearing
    Order P.19 and nn.29-30. As we have noted in the context of a
    different agency, a disqualification request in a petition for
    reconsideration to the agency comes too late. Lead Indus. Ass’n,
    Inc. v. EPA, 
    647 F.2d 1130
    , 1174 (D.C. Cir. 1980) (“[A] litigant
    who neglect[s] to present his constitutional claim to the
    administrative agency in timely fashion [may] be precluded
    from raising it before the reviewing court.”). For all the reasons
    set forth above, Jersey City’s petition will also be dismissed for
    lack of jurisdiction.
    11
    CONCLUSION
    In short, the petitions are dismissed.