Qwest Corp v. FCC ( 2007 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued February 6, 2007            Decided March 23, 2007
    No. 05-1450
    QWEST CORPORATION,
    PETITIONER
    V.
    FEDERAL COMMUNICATIONS COMMISSION
    AND UNITED STATES OF AMERICA,
    RESPONDENTS
    MCLEODUSA TELECOMMUNICATIONS SERVICES, INC., ET AL.,
    INTERVENORS
    Consolidated with
    05-1469, 06-1014, 06-1039, 06-1043
    On Petitions for Review of an Order of the
    Federal Communications Commission
    L. Andrew Tollin argued the cause for petitioner Qwest
    Corporation. With him on the briefs were Michael Deuel
    Sullivan and Robert B. McKenna.
    David P. Murray and Russell M. Blau argued the cause
    for CLEC Petitioners. On the briefs were Thomas Jones,
    Randy J. Branitsky, Richard M. Rindler, Patrick J. Donovan,
    2
    Joshua M. Bobeck, and Mary C. Albert. Jason D. Oxman
    entered an appearance.
    Joseph R. Palmore, Counsel, Federal Communications
    Commission, argued the cause for respondents. With him on
    the brief were Thomas O. Barnett, Assistant Attorney General,
    U.S. Department of Justice, Catherine G. O’Sullivan and
    Nancy C. Garrison, Attorneys, Samuel L. Feder, General
    Counsel, Federal Communications Commission, Eric D.
    Miller, Deputy General Counsel, John E. Ingle, Deputy
    Associate General Counsel, and Nandan M. Joshi, Counsel.
    L. Andrew Tollin, Michael Deuel Sullivan, Robert B.
    McKenna, Scott H. Angstreich, Michael E. Glover, and
    Edward H. Shakin were on the brief for intervenors Qwest
    Corporation and the Verizon Companies in support of
    respondents.
    David E. Mills and J. G. Harrington were on the brief for
    intervenor Cox Communications, Inc.
    Before: GRIFFITH and KAVANAUGH, Circuit Judges, and
    WILLIAMS, Senior Circuit Judge.
    Opinion for the Court filed by Senior Circuit Judge
    WILLIAMS.
    WILLIAMS, Senior Circuit Judge: Qwest, the incumbent
    local exchange carrier (“ILEC”) in Omaha, Nebraska,
    petitioned the Federal Communications Commission for
    forbearance under § 10(c) of the Communications Act, 
    47 U.S.C. § 160
    (c), from some of its obligations under §§ 251(c)
    and 271 of the Act, 
    47 U.S.C. §§ 251
    , 271, in the Omaha
    Metropolitan Statistical Area (“MSA”). The Commission
    granted the petition in part, relieving Qwest of the duty to
    provide its competitors access to certain unbundled network
    3
    elements.    In re Petition of Qwest Corporation for
    Forbearance Pursuant to 
    47 U.S.C. § 160
    (c) in the Omaha
    Metropolitan Statistical Area, 
    20 FCC Rcd 19
    ,415 (2005)
    (“Order”). Qwest and several competing local exchange
    carriers (“CLECs”) now seek review of various aspects of the
    Commission’s order.
    Qwest asserts that the Commission failed to act on its
    forbearance request before a statutory deadline, and that
    therefore the petition should have been “deemed granted” in
    full.    The CLEC petitioners, in turn, challenge the
    Commission’s grant of forbearance as to §§ 251(c)(3) and
    271(c)(2)(B)(ii), attacking the Commission’s interpretation of
    § 10(d) of the Act as unreasonable and its analysis under
    § 10(a) and (b) as arbitrary and capricious. Qwest’s claim,
    however, is barred by the exhaustion requirement of 
    47 U.S.C. § 405
    (a), a conclusion compelled by In re Core
    Communications, Inc., 
    455 F.3d 267
     (D.C. Cir. 2006)
    (“Core”). We find the CLECs’ claims ill-founded.
    ***
    Qwest’s petition requested forbearance from many of the
    statutory and regulatory obligations to which it is subject as
    the incumbent local exchange carrier in the Omaha MSA,
    including its obligations under § 251(c) and the “competitive
    checklist” requirements of § 271(c)(2)(B)(i)-(vi) and (xiv).
    Order, 20 FCC Rcd at 19,416 ¶ 1 n.2. Section 10 of the Act
    provides that the Commission “shall forbear from applying
    any regulation or any provision” if it determines that: (1) the
    enforcement of such a regulation or provision is not necessary
    to ensure that rates or services are “just and reasonable and are
    not unjustly or unreasonably discriminatory”; (2) enforcement
    is “not necessary for the protection of consumers”; and (3)
    forbearance from applying such a regulation or provision is
    4
    “consistent with the public interest.” 
    47 U.S.C. § 160
    (a)(1)-
    (3). In evaluating the public interest, the Commission must
    ask whether forbearance “will promote competitive market
    conditions.” 
    Id.
     § 160(b). Section 10(d) provides that no
    petition for forbearance may be granted as to the obligations
    in §§ 251(c) or 271 until the Commission “determines that
    those requirements have been fully implemented.” Id.
    § 160(d).
    Any petition for forbearance “shall be deemed granted if
    the Commission does not deny the petition . . . within one year
    after the Commission receives it,” unless the Commission
    extends the deadline “an additional 90 days.” Id. § 160(c).
    The Commission timely granted itself a 90-day extension and,
    on the last day of the extended period, issued a news release
    announcing that it had voted to grant Qwest’s petition in part.
    News Release, FCC Grants Qwest Forbearance Relief in
    Omaha MSA, Sept. 16, 2005, Joint Appendix at 652. The
    release stated that the Commission was relieving Qwest of the
    “obligation to provide unbundled network elements (UNEs) to
    competitors in 9 of Qwest’s 24 wire center service areas,”
    noting “the substantial infrastructure investment made by Cox
    Communications, Inc. in its competitive network” in the
    Omaha MSA. Id. The release explained, however, that the
    Commission was leaving in place the other requirements of
    § 251(c), as well as the obligation under § 271 to provide
    wholesale access to local loops, transport, and switching at
    just and reasonable prices. Id.
    The Commission issued the text of its Order on
    December 2, 2005, stating, anomalously, that its “decision
    shall be effective on Friday, September 16, 2005.” 20 FCC
    Rcd at 19,471 ¶ 112 & n.282. As prefigured in the release,
    the Order granted Qwest forbearance from providing
    unbundled loops and dedicated transport elements under 
    47 U.S.C. § 251
    (c)(3), as well as related obligations in
    5
    §§ 251(c)(6) and 271. The Commission found those sections
    to have been “fully implemented” within the meaning of
    § 10(d). 20 FCC Rcd at 19,439 ¶ 51. The “substantial
    intermodal competition” provided by Cox’s voice-enabled
    cable plant was “sufficient” to merit forbearance, the
    Commission held, in light of the continued applicability of
    other statutory and regulatory provisions designed to promote
    competition, such as the resale and interconnection
    requirements under § 251(c)(4), and access to loops,
    switching, and transport services under § 271(c)(2)(B)(iv)-
    (vi). 20 FCC Rcd at 19,444, 19,446 ¶¶ 59, 62. The
    Commission relieved Qwest from the application of certain
    “dominant carrier” regulations under 
    47 U.S.C. § 214
     and 
    47 C.F.R. §§ 61.38
     & 61.41-.49 (2006) in mass market switched
    access and mass market broadband Internet access services,
    but it denied the petition in all other respects. 
    Id. at 19
    ,417
    ¶ 2, 19,424 ¶¶ 15-16.
    * * *
    We begin with Qwest’s claim that its petition should have
    been “deemed granted” under § 10(c) because the
    Commission’s actions (a vote and press release) did not
    constitute a “den[ial]” under § 10(c).
    
    47 U.S.C. § 405
    (a) provides that “[t]he filing of a petition
    for reconsideration shall not be a condition precedent to
    judicial review of any such order [of the Commission] . . .
    except where the party seeking such review . . . relies on
    questions of fact or law upon which the Commission . . . has
    been afforded no opportunity to pass.” As we noted in Core,
    this circuit has “strictly construed” § 405(a), “holding that we
    generally lack jurisdiction to review arguments that have not
    first been presented to the Commission.” 
    455 F.3d at 276
    (internal quotation marks omitted). While the statute does not
    6
    require that the Commission’s opportunity “be afforded in any
    particular manner, or by any particular party,” Coalition for
    Noncommercial Media v. FCC, 
    249 F.3d 1005
    , 1008 (D.C.
    Cir. 2001), the Commission must have somehow been put on
    notice of the problem. Time Warner Entertainment Co. v.
    FCC, 
    144 F.3d 75
    , 79 (D.C. Cir. 1998) (“Time Warner”).
    Qwest acknowledges both the fact that it never raised the
    issue before the Commission and the principle that failure to
    do so isn’t excused merely because the issue arose
    unequivocally only at the moment the Commission took
    action. That principle is clear. In Core, as here, the
    Commission voted to deny a petition for forbearance and
    issued a press release within the statutory deadline, publishing
    its written order only after the deadline had passed; like
    Qwest, Core then argued, without seeking reconsideration,
    that its petition should be “deemed granted.” 
    455 F.3d at
    274-
    75. Yet, noting our precedents under § 405(a), we held that
    “even when a petitioner has no reason to raise an argument
    until the FCC issues an order that makes the issue relevant,
    the petitioner must file a petition for reconsideration with the
    Commission before it may seek judicial review.” Id. at 276-
    77 (internal quotation marks omitted).
    Qwest tries to distinguish Core by noting a subtle
    difference between its claim and Core’s. Whereas Core
    argued that the Commission was bound by § 10(c) to issue a
    fully fledged explanation of its ruling by the deadline (on pain
    of the petition’s being deemed granted), Qwest argues more
    modestly that § 10(c) requires simply a “legally effective
    public notice” with “enough detail about the rulings to allow
    the parties to alter their course of conduct.” Qwest Reply Br.
    at 5. This situates Qwest’s claim (it says) under “step one” in
    the conventional lexicon of Chevron U.S.A. Inc. v. Natural
    Resources Defense Council, Inc., 
    467 U.S. 837
     (1984), i.e., a
    claim to which Congress has spoken “directly.” By contrast,
    7
    Qwest locates Core’s claim under “step two,” pointing to our
    statement in Core that we would “ordinarily accord deference
    to the Commission’s interpretation of . . . § 160(c)” under
    Chevron, and that petitioner’s failure to have raised its claim
    before the Commission “create[d] a problem regarding the
    extent of deference we owe the FCC’s statutory
    interpretation.” Core, 
    455 F.3d at 276
    . Exhaustion under
    § 405(a) would serve no purpose here, Qwest contends,
    because its claim is that the Commission violated the plain
    meaning of § 10(c), a question on which a reviewing court
    would owe the Commission no deference.
    We think Qwest has misread Core on two levels. First,
    we see no evidence that the court judged Core’s claim to fall
    within step two. The court never embarks on an exegesis of
    § 10(c), thus exercising a self-restraint wholly in keeping with
    one of the functions of exhaustion doctrine—to avoid
    premature judicial pronouncements. Moreover, the court’s
    statement quoted above—that we would “ordinarily accord
    deference to the Commission’s interpretation of . . .
    § 160(c)”—makes complete sense as a simple recognition that
    a Commission reading of § 10(c) would fall within the general
    bailiwick of Chevron analysis.
    Second, even if Core had classified Core’s argument as
    belonging to step two, exhaustion is not excused simply
    because we might owe an agency no deference. Section
    405(a) applies on its face to all “questions of fact or law.” 
    47 U.S.C. § 405
    (a). This court has frequently required § 405
    exhaustion for questions on which the Commission would
    have received no deference. See, e.g., Lutheran Church-
    Missouri Synod v. FCC, 
    141 F.3d 344
    , 349 & n.6 (D.C. Cir.
    1998) (First Amendment claim); Time Warner, 
    144 F.3d at 80
    (collecting cases requiring exhaustion for asserted violations
    of Administrative Procedure Act). In fact, we have been
    “sticklers” in requiring § 405(a) exhaustion where a party
    8
    “complains of only a technical or procedural mistake, such as
    an obvious violation of a specific APA requirement.” Id. at
    80-81.
    Moreover, although courts have acknowledged the
    relationship between administrative exhaustion and deference
    to administrative agencies, see McCarthy v. Madigan, 
    503 U.S. 140
    , 145 (1992), exhaustion serves other purposes as
    well. For instance, “‘[o]ne of the purposes of [section 405] is
    to afford the Commission the initial opportunity to correct
    errors in its decision or the proceeding leading to decision’”—
    a goal equally applicable here. Time Warner, 
    144 F.3d at 80
    (quoting Rogers Radio Communication Services v. FCC, 
    593 F.2d 1225
    , 1229 (D.C. Cir. 1978)) (alterations in original); see
    also McCarthy, 
    503 U.S. at 145
     (exhaustion discourages
    disregard of agency procedures); Woodford v. Ngo, 
    126 S. Ct. 2378
    , 2385 (2006) (agency proceedings “generally . . .
    resolve[] [claims] much more quickly and economically” than
    courts and “may produce a useful record for subsequent
    judicial consideration”).
    Qwest next attempts to distinguish Core by arguing that
    the Commission here had already provided its view on the
    issue, i.e., it had had an “opportunity to pass” for purposes of
    § 405(a). Qwest relies primarily on the Order’s reference to
    § 10(c) in its effective date paragraph, 20 FCC Rcd at 19,471
    ¶ 112 & n.282, and a footnote from a report unrelated to the
    instant proceedings, In re 2002 Biennial Regulatory Review,
    
    18 FCC Rcd 4726
    , 4739 ¶ 33 n.70 (2003) (“[F]ailure to act on
    [a § 10] forbearance petition within [the] statutory period
    causes it to be granted by operation of law.”); see also Petition
    of Core Communications, Inc. for Forbearance under 
    47 U.S.C. § 160
    (c) from Application of the ISP Remand Order,
    
    19 FCC Rcd 20
    ,179, 20,189 ¶ 28 & n.74 (2004) (noting
    § 10(c)’s requirements and the statutory consequences of
    failure to meet the deadline). But while the cited phrases
    9
    manifest Commission awareness of the statutory deadline,
    they cannot be described as dispositions of an (unmade) claim
    that a vote and press release on the statutory deadline could
    not qualify as a “den[ial]” under § 10(c). See Qwest Br. at 3.
    Moreover, Qwest ignores our recent statement in Core—
    where the Commission had employed an effective-date
    provision virtually identical to the one here—that § 405(a)
    barred us from being “the first authority to construe the
    meaning” of § 10(c). 
    455 F.3d at 277
    .
    Finally, Qwest urges us to recognize certain exceptions to
    the exhaustion requirement: where agency action is alleged to
    be ultra vires, and where seeking an agency’s view would be
    futile. In fact, the parties dispute the existence of such
    exceptions. Compare Washington Ass’n for Television &
    Children v. FCC, 
    712 F.2d 677
    , 681-82 (D.C. Cir. 1983)
    (“WATCH”) (interpreting § 405 to “permit[] courts some
    discretion to waive exhaustion”), and Petroleum
    Communications, Inc. v. FCC, 
    22 F.3d 1164
    , 1170 (D.C. Cir.
    1994) (discussing futility and “patent violation[s] of the
    agency’s statutory authority” as “recognized exceptions” to
    exhaustion requirement), with Booth v. Churner, 
    532 U.S. 731
    , 741 n.6 (2001) (“[W]e will not read futility or other
    exceptions into statutory exhaustion requirements where
    Congress has provided otherwise.”), and Avocados Plus Inc.
    v. Veneman, 
    370 F.3d 1243
    , 1247 (D.C. Cir. 2004) (“If the
    statute does mandate exhaustion, a court cannot excuse it.”).
    We need not, however, resolve this disagreement; even
    assuming the availability of such exceptions, Qwest has failed
    to show that either applies.
    In its ultra vires arguments, Qwest looks to WATCH’s
    statement that exhaustion may be excused for challenges to
    agency action “‘patently in excess of [the agency’s]
    authority.’” 
    712 F.2d at 682
     (quoting Detroit Edison Co. v.
    NLRB, 
    440 U.S. 301
    , 312 n.10 (1979)) (alteration in original);
    10
    see also Petroleum Communications, 
    22 F.3d at 1170
    (implying readiness to except “patent violation[s]” of statutory
    authority from § 405(a)). Whatever the exact meaning of
    § 10(c), we can’t say that the Commission’s action here falls
    into the outer darkness of a “patent” violation. See also
    Mitchell v. Christopher, 
    996 F.2d 375
    , 378 (D.C. Cir. 1993)
    (ultra vires exception limited to “challenges that concern the
    very composition or ‘constitution’ of an agency”); Northwest
    Airlines, Inc. v. FAA, 
    14 F.3d 64
    , 73 (D.C. Cir. 1994) (failure
    to raise an issue “will not be excused merely because the
    litigant couches its claim in terms of the agency’s exceeding
    its statutorily-defined authority or ‘jurisdiction’”).
    As to futility, our decisions entertaining the exception
    have demanded a very convincing record. In Omnipoint
    Corp. v. FCC, 
    78 F.3d 620
     (D.C. Cir. 1996), for example, we
    found futility only where the Commission “was rapidly
    expediting the proceeding and appeared ‘wedded to the
    procedures that it had employed.’” 
    78 F.3d at 635
     (quoting
    City of Brookings Municipal Tel. Co., 
    822 F.2d 1153
    , 1163
    (D.C. Cir. 1987)). Similarly, in Tribune Co. v. FCC, 
    133 F.3d 61
    , 67 (D.C. Cir. 1998), we suggested that futility was
    appropriate only where the Commission’s position had
    “crystallized” or where the Commission was “firmly
    entrenched.” And in Nat’l Science and Technology Network,
    Inc. v. FCC, 
    397 F.3d 1013
    , 1014 (D.C. Cir. 2005), we said
    that futility required a “showing that an adverse decision was
    a certainty.”
    Here Qwest points to little more than the agency’s
    treatment of Core’s petition, where it had taken a similar
    approach (vote and press release on the deadline, with
    decision to follow). And in this case, it says, the timeliness
    arguments advanced in Core put the Commission on notice
    about disagreement with its reading of § 10(c). But one
    swallow doesn’t make a summer, and Qwest points to no case
    11
    (and we are aware of none) in which a single adverse decision
    by an agency, without more, demonstrated that its position
    had “crystallized” or that a future result was “a certainty.”
    Qwest adds that the § 10(c) deadline would not bind the
    Commission’s consideration of a petition for reconsideration.
    True enough, though hardly assurance that the Commission
    would drag its feet on such a petition, especially with the
    potential of a mandamus action hovering in the background.
    Moreover, the Commission’s treatment of the deadline on
    Core’s petition occurred in October 2004, see Core, 
    455 F.3d at 274
    , at which point Qwest’s petition had been pending for
    four months. Qwest’s failure at that point to file a memo
    insisting on its view of § 10(c) undermines its reliance on the
    risk of delay inherent in a post-decision petition for
    reconsideration.
    Thus we reject Qwest’s claim as barred by the exhaustion
    requirement of § 405(a).
    * * *
    We next turn to the CLEC petitioners’ claims, beginning
    with their contention that § 251(c) was not “fully
    implemented” for the purposes of § 10(d). Our review of an
    agency’s interpretation of the statute it administers is
    governed by the familiar Chevron framework, under which we
    ask first whether Congress has “directly spoken” to the precise
    issue before us and, if it has not, whether the agency’s
    interpretation is reasonable. 
    467 U.S. at 842-43
    ; see also
    Cellular Telecommunications & Internet Ass’n v. FCC, 
    330 F.3d 502
    , 507 (D.C. Cir. 2003).
    Section 10(d) of the Act provides that “the Commission
    may not forbear from applying the requirements of section
    12
    251(c) or 271 . . . until it determines that those requirements
    have been fully implemented.” 
    47 U.S.C. § 160
    (d). In the
    Order, the Commission held that § 251(c) had been fully
    implemented “because the Commission has issued rules
    implementing section 251(c) and those rules have gone into
    effect.” 20 FCC Rcd at 19,440 ¶ 53. The Commission
    reasoned that “[the FCC itself] is the entity that ‘implements’
    section 251(c),” noting that § 251(d)(1) requires the
    Commission to “complete all actions necessary to establish
    regulations to implement the requirements of [§ 251].” Id.
    The CLECs dispute the Commission’s reliance on
    § 251(d), and draw a contrast between that subsection’s
    requirement that “the Commission . . . complete all actions
    necessary to establish regulations to implement” § 251(c) and
    § 10(d)’s reference to “fully implemented.” 
    47 U.S.C. §§ 160
    (d), 251(d) (emphasis added). The Commission’s
    reading of § 10(d), they argue, gives no meaning to the term
    “fully,” which in their view must implicate something more
    than the rulemaking contemplated by § 251(d). But the
    Commission stated that § 251(c) would be fully implemented
    only “once the Commission has completed its work of
    promulgating rules implementing section 251(c) and those
    rules have taken effect.” 20 FCC Rcd at 19,440 ¶ 54 n.135
    (emphasis added). We cannot say that such a reading is
    unreasonable. The statute does not define “implemented,” an
    ambiguity not clearly resolved one way or the other by
    reference to § 251(d). The Commission’s interpretation does
    give independent meaning, albeit a modest one, to the term
    “fully”—i.e., that regulations have both been promulgated and
    taken effect. In addition, it might well be thought that
    completion of “all actions necessary to establish regulations
    to implement” a section would naturally add up to “full[]
    implement[ation]” of that section. We also note petitioners’
    failure to have offered any workable alternative test. See
    CLEC Br. at 41.
    13
    The CLECs further believe that under the plain language
    of § 251 the Commission can make a finding of full
    implementation of § 251(c) only if it can point to
    implementing action by the ILECs. To support this notion
    they point to the Commission’s own analysis in the Section
    271 Broadband Forbearance Order, In re Petition for
    Forbearance of the Verizon Telephone Companies Pursuant
    to 
    47 U.S.C. § 160
    (c), 
    19 FCC Rcd 21
    ,496 (2004), where it
    rested a finding of implementation of the competitive
    checklist requirements of § 271(c) on the Bell Operating
    Companies’ having established compliance with those
    requirements and having secured entitlement to provide in-
    region interLATA service. Id. at 21,503 ¶¶ 15-16; see also
    Order, 20 FCC Rcd at 19,440-41 ¶ 54. Even assuming the
    CLECs’ reading of § 10(d) is reasonable, the Commission’s is
    also: “[T]he BOCs [Bell Operating Companies] have a role in
    implementing section 271(c) that incumbent LECs do not
    have in implementing section 251(c).” Order, 20 FCC Rcd at
    19,441 ¶ 54. In one case, company action subjects a company
    to the duties in question; in the other, Commission action does
    so. The Commission’s reading of § 10(d) reflects that
    distinction.
    We are equally unconvinced by petitioners’ argument that
    the Commission’s interpretation would allow forbearance
    from § 251(c) before the benefits from unbundling were
    “significantly realized.” This disregards the independent
    requirements of § 10, such as § 10(b)’s mandate to consider
    whether forbearance would “promote competitive market
    conditions.”
    Finally, the CLEC petitioners complain that the
    Commission’s interpretation of § 10(d) is inconsistent with a
    1996 order, In re Implementation of the Local Competition
    Provisions in the Telecommunications Act of 1996, 
    11 FCC Rcd 15
    ,499 (1996) (“Local Competition Order”), which they
    14
    believe contemplates a role for States and service providers in
    implementing § 251(c) inconsistent with the Commission’s
    application of § 10(d) here. This is distinct from arguments
    based on the plain language of § 10(d) or the alleged
    inconsistency with the Commission’s analysis of forbearance
    from § 271 duties. But the argument is barred under § 405(a)
    because the Commission never had an “opportunity to pass”
    on it. Indeed, the CLECs appear to concede that the 1996
    order was never mentioned in the proceedings below. CLEC
    Reply Br. at 14. See Cellco Partnership v. FCC, 
    357 F.3d 88
    ,
    102 (D.C. Cir. 2004) (“[Where petitioner] never argued to the
    Commission that its decision [on review] . . . was inconsistent
    with its [prior] decision . . . it cannot now argue that the
    Commission erred by failing to reconcile these two
    decisions.”). Nor was the substance of the inconsistency
    claim presented well enough to satisfy § 405(a), especially in
    light of our admonition that the Commission “need not sift
    pleadings and documents to identify arguments that are not
    stated with clarity by a petitioner.” Bartholdi Cable Co. v.
    FCC, 
    114 F.3d 274
    , 279 (D.C. Cir. 1997) (internal quotation
    marks omitted). None of the various record citations to which
    the CLECs refer, see CLEC Reply Br. at 14 n.5, is plausibly
    read as presenting the argument that the Commission’s
    proposed reading of § 10(d) was inconsistent with a prior
    Commission order discussing the roles of states and service
    providers under § 251(c).
    * * *
    Last, we reach the CLECs’ challenges to the
    Commission’s forbearance analysis under § 10(a) and (b).
    Our review here is governed by 
    5 U.S.C. § 706
    (2)(A), under
    which we set aside agency action that is “arbitrary, capricious,
    an abuse of discretion, or otherwise not in accordance with
    15
    law.” See AT&T Inc. v. FCC, 
    452 F.3d 830
    , 837 (D.C. Cir.
    2006).
    The Order grants Qwest forbearance from the obligation
    to provide unbundled loops and transport in “9 of Qwest’s 24
    wire centers in the Omaha MSA where competitive
    deployment is greatest.” 20 FCC Rcd at 19,444 ¶ 59. The
    Commission “tailor[ed] Qwest’s relief” to Cox’s “extensive”
    voice-enabled cable network, selecting nine wire centers in
    which “sufficient facilities-based competition” existed “to
    ensure that the interests of consumers and the goals of the Act
    [were] protected under the standards of section 10(a).” Id. at
    19,444-46 ¶¶ 59, 61-62. The Commission also relied on
    competitors’ continued access to interconnection rights under
    § 251(c) and to Qwest’s loops, switching and transport under
    § 271(c)(2)(b)(iv)-(vi). Id. at 19,446-47 ¶¶ 62, 64.
    Although the Commission recognized that Cox’s market
    share was larger in the residential than the enterprise market,
    it concluded that Cox nonetheless posed a “substantial
    competitive threat to Qwest” in both sectors. Id. at 19,448
    ¶ 66. Cox had proven itself a “very successful[]” competitor
    even in the mass market (where revenue potential was
    “relatively low” compared to the enterprise market), was
    “actively marketing” itself to enterprise customers, had won
    over a “large number of significant Omaha businesses,” and
    had doubled its enterprise sales in Omaha each year for five
    consecutive years. Id. Moreover, Cox had relevant technical
    expertise, economies of scale and scope, sunk investments in
    network infrastructure (implying that the incremental costs for
    continuing and extending service would be relatively modest),
    and an established presence and brand in the Omaha MSA.
    Id.
    In challenging the Commission’s reliance on Cox’s
    activities, the CLECs point to the Commission’s discussion in
    16
    its 2005 unbundling order, in which it declined to find that
    cable company competition throughout the country justified
    relieving ILECs of their obligation to provide unbundled
    network elements, and claim that “nothing” in the record
    distinguishes Cox from those facts. See In re Unbundled
    Access to Network Elements, Review of the Section 251
    Unbundling Obligations of Incumbent Local Exchange
    Carriers, 
    20 FCC Rcd 2533
    , 2556-57 ¶ 39 (2005) (“Triennial
    Review Remand Order,” or “TRRO”). But the TRRO
    explicitly noted that these matters varied by geographic
    market. 
    Id.
     Cox’s filings here, in fact, demonstrate its
    substantial coverage of the enterprise market, including
    provision of DS0 loops to business users. Order, 20 FCC Rcd
    at 19,450-51 ¶ 69. And we see nothing unreasonable in the
    factors invoked by the Commission—enumerated above—in
    forecasting an increase in competition. See id. at 19,448 ¶ 66.
    The CLECs also contend the Commission erred in relying
    on average network coverage across the nine wire centers,
    rather than examining each wire center individually. In theory
    the average could conceal substantial variation between
    individual centers, including possibly centers where Cox had
    no footprint at all. But in light of the Commission’s reliance
    on data showing Cox’s aggressive expansion in both the
    residential and enterprise markets, we cannot say that the
    possibility of wide variance in existing coverage is enough to
    undermine the Commission’s conclusions.
    Finally, petitioners take issue with the Commission’s
    reliance on Qwest’s wholesale offerings (ILEC plant usable
    by CLECs independently of the unbundled network element
    mandate) in granting forbearance in the enterprise and mass
    markets. These include both services Qwest is legally obliged
    to make available (under § 271(d)(2)(B)(iv)-(vi) and
    § 251(c)(4)) and ones it has offered voluntarily (such as
    Qwest Platform Plus (“QPP”) services, which are
    17
    commercially negotiated wholesale services integrating loops,
    switching and transport into a single package). See Order, 20
    FCC Rcd at 19,448-50 ¶¶ 67-68. The CLECs again point to
    the TRRO, in which the Commission declined to adopt a
    general rule relieving the ILECs of unbundling obligations in
    local exchange markets whenever “carriers are potentially
    able to compete using special access or other tariffed
    alternatives.” See TRRO, 20 FCC Rcd at 2560 ¶ 46.
    But the TRRO explicitly recognized that an ILEC’s
    tariffed offerings could, in certain circumstances, be an
    avenue for competitive entry. See, e.g., TRRO, 20 FCC Rcd
    at 2561 ¶ 48 (“[A] carrier could, in theory, use [a] tariffed
    offering to enter a market.”). The Commission in fact relied
    on carriers’ “successful[] use[] [of] special access to compete”
    in the wireless and long-distance markets in concluding that
    ILECs need no longer provide access to UNEs in those
    markets. Id. at 2554-55 ¶ 36, 2560 ¶ 46. With respect to local
    exchange services, the TRRO stated only that “the availability
    of a tariffed alternative should not foreclose unbundled
    access.” Id. at 2561 ¶ 48 (emphasis added). As the TRRO
    explicitly left open the possibility that “sufficient facilities-
    based competition” might eventually make UNE relief
    appropriate in the local exchange market, either generally or
    in geographically specific markets, id. at 2556 ¶¶ 38 & 39
    n.116, the Order seems simply to apply that concept: here the
    Commission found the combination of tariffed ILEC facilities
    and facilities-based competition adequate to assure
    competition even if it partially relaxed Qwest’s obligations in
    the Omaha market. Compare id. at 2556-57 ¶ 39 with Order,
    20 FCC Rcd at 19,447-49 ¶¶ 65 & 67 n.177.
    The CLECs offer additional arguments, in part traceable
    to the Commission’s language in the TRRO, as to why
    Qwest’s wholesale services are not, on their own, a sufficient
    substitute for UNEs. For instance, absent other avenues for
    18
    competition, ILECs could thwart competition by undue hikes
    in the price of their wholesale inputs. Similarly, the CLECs
    complain that the loop component of the QPP service was
    available as a § 251(c)(3) network element, and thus that the
    Commission was wrong to rely on the continued availability
    of QPP offerings in granting forbearance from unbundling.
    But Cox’s independent cable infrastructure greatly mitigates
    these potential risks. In addition, the CLECs have provided
    no reason to disturb the Commission’s predictive judgment
    that “Qwest will not react to [the forbearance] decision . . . by
    curtailing wholesale access” to its high-capacity offerings,
    especially in light of the Commission’s finding that facilities-
    based competition from Cox gives Qwest a strong incentive to
    maximize use of its network by setting attractive prices on its
    wholesale alternatives. Order, 20 FCC Rcd at 19,448-49 ¶ 67,
    19,455 ¶ 79.
    In sum, we hold that the Commission reasonably
    concluded that § 251(c) was “fully implemented” for the
    purpose of § 10(d). Further, we find nothing arbitrary about
    granting forbearance in the nine wire centers, given Cox’s
    extensive network coverage in the residential market and
    growing competitive presence in the enterprise market.
    ***
    Accordingly, Qwest’s petition is dismissed as barred by
    
    47 U.S.C. § 405
    (a), and the CLECs’ petitions are denied on
    the merits.
    So ordered.