Natl Assn Regu Util v. FERC ( 2007 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 13, 2006           Decided January 12, 2007
    No. 04-1148
    NATIONAL ASSOCIATION OF REGULATORY UTILITY
    COMMISSIONERS, ET AL.,
    PETITIONERS
    V.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    TENASKA, INC., ET AL.,
    INTERVENORS
    Consolidated with
    04-1149, 04-1152, 05-1050, 05-1292
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    Laurence G. Chaset argued the cause for Governmental
    Petitioners. With him on the briefs were James Bradford
    Ramsay, Thomas D. Samford, IV, Arocles Aguilar, Aubrey
    Williams Turner, Jr., Gisele Lunsford Rankin, Florence P.
    Belser, and Robert D. Cedarbaum.
    2
    Andrew W. Tunnell argued the cause for Utility
    Petitioners. With him on the brief were S. Chris Still, Kevin
    A. McNamee, Neil H. Butterklee, John D. McGrane, Heath K.
    Knakmuhs, and Antoine P. Cobb.
    Lona T. Perry, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With her on
    the brief were Robert H. Solomon, Solicitor, and Samuel
    Soopper, Attorney.
    Ashley C. Parrish argued the cause for intervenors
    Tenaska, Inc., et al. With her on the briefs were Neil L. Levy,
    Jennifer L. Key, Glen L. Ortman, Harvey L. Reiter, and
    Jonathan D. Schneider. Gregory O. Olaniran entered an
    appearance.
    Before: SENTELLE, Circuit Judge, and EDWARDS and
    WILLIAMS, Senior Circuit Judges.
    Opinion for the Court filed by Senior Circuit Judge
    WILLIAMS.
    Opinion dissenting in part filed by Circuit Judge
    SENTELLE.
    WILLIAMS, Senior Circuit Judge: In 1996 the Federal
    Energy Regulatory Commission issued Order No. 888 in the
    hopes of fostering competition in the electric generating
    industry. Such competition clearly depended on generators’
    having adequate means of getting their power to market.
    FERC’s solution in Order No. 888 was to require transmission
    providers, which typically have a natural monopoly, to give
    generators equal access to transmission facilities. The
    Commission implemented the requirement in part by
    mandating the filing of suitable tariffs. See Transmission
    Access Policy Study Group v. FERC, 
    225 F.3d 667
    , 682–83
    3
    (D.C. Cir. 2000) (“TAPS”). We affirmed Order No. 888 in
    TAPS.
    In the period directly after issuing Order No. 888, FERC
    had monitored one element of the process—the
    interconnection agreements between operators of generators
    and transmission facilities—on a case-by-case basis. Finding
    that approach “inadequate” and “inefficient,” FERC issued
    Order No. 2003 and three successive rehearing orders.
    Standardization of Generator Interconnection Agreements
    and Procedures, Order No. 2003, 104 F.E.R.C. ¶ 61,103 at
    30,
    430 P 10
     (2003), order on reh’g, Order No. 2003-A, 106
    F.E.R.C. ¶ 61,220 (2004), order on reh’g, Order No. 2003-B,
    109 F.E.R.C. ¶ 61,287 (2004), order on reh’g, Order No.
    2003-C, 111 F.E.R.C. ¶ 61,401 (2005). In the interests of
    achieving transparency and preventing transmission facility
    owners from favoring affiliated generators over independents
    in interconnection, the orders require all transmission facilities
    to adopt a standard agreement for interconnecting with
    generators larger than 20 megawatts.
    Here we review claims advanced by two sets of
    petitioners (the two sets are generally aligned with each other
    in their positions): four utilities (“Utility Petitioners”) and six
    state regulatory agencies (together with an association of such
    agencies, the National Association of Regulatory Utility
    Commissioners) (“Governmental Petitioners”).                  They
    challenge Order No. 2003 and its sequels on the grounds that
    FERC exceeded its jurisdiction, unlawfully commandeered
    states, departed from its own precedent without explanation,
    and made policy decisions that are arbitrary and capricious.
    We reject all of these claims and affirm the orders.
    4
    * * *
    Petitioners raise a succession of claims that FERC’s
    orders usurp jurisdiction not provided by Congress. FERC’s
    interpretations of the jurisdictional provisions of the Federal
    Power Act (the “Act”) enjoy Chevron deference. Detroit
    Edison Co. v. FERC, 
    334 F.3d 48
    , 53 (D.C. Cir. 2003) (citing
    TAPS, 225 F.3d at 694).
    Section 201(b)(1) of the Act makes the statute applicable
    to “the transmission of electric energy in interstate commerce
    and to the sale of electric energy at wholesale in interstate
    commerce” and gives FERC jurisdiction not only over such
    transmission and sales but also over “all facilities for such
    transmission or sale of electric energy.”             
    16 U.S.C. § 824
    (b)(1). At the same time the Act precludes FERC
    “jurisdiction . . . over facilities used in local distribution or
    only for the transmission of electric energy in intrastate
    commerce.” 
    Id.
     Order No. 2003 asserts jurisdiction over the
    terms of interconnection between generators and transmission
    providers, even where the transmission facility also engages in
    local distribution, but only insofar as the interconnections are
    “for the purpose of making sales of electric energy for resale
    in interstate commerce.” Order No. 2003 at 30,545–
    46 P 804
    .
    Utility Petitioners claim that this represents an unlawful
    exercise of jurisdiction over dual-use facilities—ones that
    engage in both transmission and local distribution.
    Petitioners believe that our opinion in Detroit Edison
    controls. There we rejected FERC’s attempt to assert
    jurisdiction over unbundled retail service, although such
    service involved neither jurisdictional sales nor jurisdictional
    transmission. Sales under FERC-jurisdictional tariffs would
    have enabled the shipper to escape stranded cost charges
    imposed under state-approved tariffs. 
    334 F.3d at 52
    .
    FERC’s purported jurisdictional hook was that the power was
    5
    being shipped over dual-use facilities that provided both retail
    and wholesale distribution services. 
    Id. at 52, 54
    . We were
    unconvinced by this theory for asserting jurisdiction over non-
    jurisdictional transactions.
    Here the issue is the inverse of Detroit Edison; Order No.
    2003 applies to jurisdictional transactions only. FERC
    determined that the provisions of Order No. 2003 should
    apply “to interconnections to the facilities of a public utility’s
    Transmission System that, at the time the interconnection is
    requested, may be used either to transmit electric energy in
    interstate commerce or to sell electric energy at wholesale in
    interstate commerce.” Order No. 2003-C at 31,
    656 P 51
    .
    “Interconnections,” though seemingly not defined explicitly in
    the orders, clearly are not “facilities,” as that would make the
    term “Interconnection Facilities,” as used in the standardized
    agreements, a redundancy. See, e.g., Order No. 2003 at
    30,577. In fact interconnections appear to be relationships
    between parties with respect to electricity flowing over
    facilities, and the orders here by their terms control the
    agreements governing those relationships.              See, e.g.,
    “Standard Large Generator Interconnection Agreement
    (LGIA),” id. at 30,616–67.            By establishing standard
    agreements FERC has exercised its jurisdiction over the terms
    of those relationships. Cf. TAPS, 225 F.3d at 696 (“FPA
    § 201 makes clear that all aspects of wholesale sales are
    subject to federal regulation, regardless of the facilities used.”
    (emphasis added)).
    In their reply briefs petitioners note that the orders
    regulate certain facets of the engineering and construction of
    facilities needed for the relevant transmissions. Utility
    Petitioners’ Reply Br. at 4; Governmental Petitioners’ Reply
    Br. at 5–6 & n.9. But petitioners identify no specific aspect of
    the regulations that they claim is untethered to the
    Commission’s authority over interstate transmissions and
    6
    wholesale sales. As FERC’s authority generally rests on the
    public interest in constraining exercises of market power, see
    Associated Gas Distributors v. FERC, 
    824 F.2d 981
    , 1003
    (D.C. Cir. 1987), whether in the utility’s rates or other service
    terms, and as a common test for the lawfulness of rates is their
    connection to the reasonably-incurred costs of providing the
    regulated service, National Fuel Gas Supply Corp. v. FERC,
    
    900 F.2d 340
     (D.C. Cir. 1990), it is hard to see how the statute
    could leave FERC weaponless against conduct that might
    encourage or cloak the running up of unreasonable costs. The
    Commission’s indisputable authority to disallow recovery of
    costs imprudently incurred by jurisdictional firms may, of
    course, impinge as a practical matter on the behavior of non-
    jurisdictional ones. So far as appears, petitioners in this facial
    attack have identified no impingement that exceeds what may
    be encompassed in such conventional exercises of
    jurisdiction.
    Utility Petitioners also dispute FERC’s assertion of
    jurisdiction over facilities jointly owned by private firms and
    states. This presents questions analogous to those raised by
    the transmission-and-distribution facilities just discussed,
    though here the divide is between private and public
    ownership rather than between transmission and distribution.
    Section § 201(f) of the Act provides that “[n]o provision in
    this subchapter shall apply to, or be deemed to include, the
    United States, a State or any political subdivision of a State.”
    
    16 U.S.C. § 824
    (f). (They are brought back in with respect to
    particular sections not relevant here. See §3(22) of the Act,
    
    16 U.S.C. § 796
    (22); §§ 210–213, 16 U.S.C. §§ 824i–824l;
    Bonneville Power Administration v. FERC, 
    422 F.3d 908
    , 916
    (9th Cir. 2005).) Therefore, according to petitioners, FERC
    may not regulate jointly-owned facilities. Although Order
    No. 2003 explicitly states that it applies only “to
    Interconnection Service provided by the public utility on its
    portion of a jointly owned facility,” Order No. 2003 at 30,546
    
    7 P 807
    , petitioners claim that FERC’s purported distinction is
    not possible. In their view, an interconnection affects an
    entire facility, not simply the public utility’s portion, and
    FERC’s purported exercise of authority over the service
    therefore violates § 201(f). The argument fails for reasons
    similar to those discussed in the context of FERC’s authority
    to regulate jurisdictional transactions occurring over non-
    jurisdictional facilities.
    Any proper construction of § 201 must give effect to both
    FERC’s jurisdiction over certain transactions occurring over
    public utilities and to § 201(f)’s exclusion of state facilities.
    As FERC notes in its brief, jurisdictional utilities should not
    be able, without linguistic support from Congress, to escape
    regulation “simply by partnering with non-jurisdictional
    utilities.” Respondent’s Br. at 32. FERC navigated a similar
    problem in Order No. 888, which required equal access to
    transmission services. There the Commission stated clearly
    that it had authority to regulate a public utility,
    notwithstanding incidental effects on nonjurisdictional
    entities:
    The fact that a public utility may jointly own, with a non-
    jurisdictional entity, transmission facilities through which
    it engages in sales for resale and/or transmission of
    electric energy in interstate commerce does not alter the
    Commission’s authority to regulate that public utility. . . .
    The fact that . . . an order may affect a non-jurisdictional
    joint owner does not undermine the validity of the
    Commission’s order.
    Order No. 888-A, FERC Stats. & Regs. ¶ 61,182 at 30,219, 
    62 Fed. Reg. 12,274
    , 12,300/2 (Mar. 4, 1997). FERC relied on
    the same logic in Order No. 2003. See Order No. 2003 at
    30,
    546 P 807
    . Utility Petitioners accept the validity of Order
    No. 888 as well as other cases that they view as
    8
    distinguishable from the present situation. See, e.g., Mid-
    Continent Area Power Pool, 89 F.E.R.C. ¶ 61,135 at 61,387–
    88 (1999); Bonneville Power, 
    422 F.3d at 925
    .
    According to petitioners, however, Order No. 888
    affected the non-jurisdictional entities only in the sense of
    invalidating contractual provisions between jurisdictional and
    non-jurisdictional co-owners, whereas Order No. 2003
    “addresses the request for and construction of facilities . . . by
    a non-jurisdictional co-owner.” Utility Petitioners’ Reply Br.
    at 5–6. The supposed distinction is of no account, however.
    As discussed above, assertion of jurisdiction over specified
    transactions, even though affecting the conduct of the
    owner(s) with respect to its facilities, is not per se an exercise
    of jurisdiction over the facility. The contract modifications
    mandated in Order No. 888, forcing the non-jurisdictional
    owner to permit certain transactions to occur over the jointly
    owned facility, obviously affected that owner’s ownership
    rights in, and conduct with respect to, the facility; the
    modifications removed a hitherto valid veto power over the
    use in question. To the extent that Order No. 2003 conditions
    a jurisdictional utility’s participation in the transmission and
    interconnection markets on that utility’s securing physical
    changes in the facilities, and those changes bear a close
    enough relation to FERC’s exercise of jurisdiction over
    jurisdictional transactions (petitioners pose no challenge to the
    adequacy of that relation), the Order effects no legally
    material extension of the authority exercised in Order No.
    888.
    The Governmental Petitioners challenge FERC’s
    articulation of its assertion of jurisdiction over
    interconnections with dual-use facilities (ones for
    transmission and local distribution)—namely, FERC’s claim
    of authority where such facilities are “used to transmit electric
    energy in interstate commerce on behalf of a wholesale
    9
    purchaser pursuant to a Commission-filed OATT [Open
    Access Transmission Tariff].” Order No. 2003 at 30,545–
    46 P 804
    . See also Order No. 2003-A at 31,071–
    72 P 710
    .
    Governmental Petitioners claim that this involves
    jurisdictional “boot-strapping.” They cite our opinion in
    Columbia Gas Transmission Corp. v. FERC, 
    404 F.3d 459
    (D.C. Cir. 2005), where FERC had asserted jurisdiction based
    solely on a voluntarily filed tariff “even if FERC would not
    otherwise have jurisdiction.” 
    Id. at 461
    . Here we have the
    exact opposite of boot-strapping.        FERC is exercising
    jurisdiction only over “interconnections to a ‘distribution’
    facility when the facility is included in a public utility’s
    Commission-filed OATT and the interconnection is for the
    purpose of facilitating a jurisdictional wholesale sale of
    electric energy.” Order No. 2003-A at 31,
    075 P 730
    (emphasis added).
    Governmental Petitioners also object that FERC’s
    approach creates uncertainty by making jurisdiction turn on
    (among other things) whether the facility is covered by an
    OATT. FERC acknowledged the potentiality for uncertainty,
    but reasoned that most cases would present no controversy
    and that, if a dispute should arise, it would depend in the first
    instance on the transmission provider to make the relevant
    information available to potential interconnecting customers.
    Order No. 2003-A at 31,
    072 P 712
    . On the record before us,
    we see no grounds for upsetting the Commission’s judgment.
    Closely related to the jurisdictional claims is the
    Governmental Petitioners’ assertion that FERC erred by not
    applying its seven-factor test, which we approved in TAPS,
    225 F.3d at 696, to determine whether a facility is an exempt
    local distribution facility or a covered transmission facility.
    But here, as often mentioned above, at least with regard to the
    exercises of power disputed before us, FERC is exerting
    jurisdiction over transactions, based on the transactions’
    10
    satisfaction of the Act’s jurisdictional criteria. It thus has had
    no occasion to decide whether a facility as such should be
    classified as jurisdictional or not.
    * * *
    In its proposal leading to Order No. 2003 FERC had
    contemplated requiring transmission providers to use
    reasonable efforts, including available “eminent domain
    authority, if necessary, to facilitate the interconnection” of
    generators. See Order No. 2003 at 30,
    483 P 384
    . Responding
    to comments suggesting that the requirement would unduly
    burden transmission firms, id. at 30,
    484 P 391
    , FERC reduced
    this to a provision forbidding such firms from discriminating
    in the exercise of eminent domain powers to the detriment of
    independent generators and to the advantage of affiliates. See,
    e.g., Order No. 2003-A at 31,
    003 P 298
    . Utility Petitioners
    object that these provisions of Order No. 2003 and its sequels
    impermissibly “commandeer” states’ eminent domain
    authority, contrary to the Supreme Court’s holdings in New
    York v. United States, 
    505 U.S. 144
     (1992), and Printz v.
    United States, 
    521 U.S. 898
     (1997). Whether FERC has
    commandeered states is a question of law that we review de
    novo.
    The orders here are a far cry from what the Supreme
    Court found objectionable in New York and Printz. In New
    York, the Court invalidated a provision of the Low-Level
    Radioactive Waste Policy Amendments of 1985 that gave
    states a Hobson’s choice: either take title to low-level
    radioactive waste generated by third parties or regulate the
    waste pursuant to Congress’s direction. Congress didn’t have
    authority to impose either option on states directly and thus
    could not force states to choose one or the other. The Court
    emphasized that Congress may not “commandeer” states by
    11
    compelling them either to create or administer a federal
    regulatory scheme. 
    505 U.S. at
    174–77. In Printz the Court
    found that New York’s anti-commandeering principle
    precluded a provision of the Brady Handgun Violence
    Prevention Act requiring local law enforcement officers to
    help conduct background checks on individuals seeking to
    purchase a firearm. 
    521 U.S. at 933
    .
    We recognize that a state’s authority to exercise the
    eminent domain power, and to license public utilities to do so,
    is an important state power. But FERC has done nothing
    more than impose a non-discrimination provision on public
    utilities. The orders explicitly leave state law untouched,
    specifying that any exercise of eminent domain by a public
    utility pursuant to the orders’ non-discrimination mandate be
    “consistent with state law.” Order No. 2003-A at 31,144,
    LGIA § 5.13; see also id. at 31,
    004 P 300
    . Thus the states
    remain completely free to continue licensing public utilities to
    exercise eminent domain, or to discontinue that practice. To
    be sure, if hitherto a utility would not have exercised eminent
    domain to enable interconnection with an independent
    generator, the orders, conditionally, compel the utility either
    to broaden its use of the state-provided authority for the
    benefit of independents, or to drop the use for its own and its
    affiliates’ power. But the modifier conditionally is critical.
    Nothing in the federal rule compels either continued state
    retention of the license, or public utilities’ continued
    employment of eminent domain. The intrusion on state power
    is surely no greater than (many would say dramatically less
    than) that of a federal command that, if a state hires
    employees for the performance of traditional governmental
    functions, it must pay them no less than a federally
    determined wage. See Garcia v. San Antonio Metropolitan
    Transit Authority, 
    469 U.S. 528
     (1985). Moreover, we
    believe that our dissenting colleague’s focus on the “plain
    statement” requirement that applies to purported federal
    12
    creation of state obligations is misplaced; the orders here
    leave state law completely undisturbed and bind only
    utilities—not state officials.
    Related to Utility Petitioners’ “commandeering” claim is
    their assertion that Order No. 2003-A involves an unlawful
    taking. They concede, as they must, that the Order explicitly
    requires that any uses of eminent domain by transmission
    providers be at the expense of the benefiting generator. Order
    No. 2003-A at 31,
    003 P 298
    . But the Utility Petitioners claim
    that exercising eminent domain power on behalf of
    independent generators could undermine transmission
    providers’ “good will” in their relation to landowners.
    Assuming that that is so, we note that petitioners make no
    claim that the injury to such good will is any more severe than
    the one inflicted by uses of eminent domain for
    interconnection to affiliated generators. Anti-discrimination
    rules commonly require the incurrence of costs by the
    obligated parties; their very imposition presupposes that some
    such parties would, in pursuit of their self-interest, violate the
    anti-discrimination norm. We cannot see that the potential
    loss of good will rises above the sort of costs commonly
    inflicted by such mandates.
    * * *
    The remaining significant challenge, brought by both sets
    of petitioners, is to the so-called “At or Beyond” rule. The
    rule is intended to guide assignment of costs as between a
    transmission facility and an interconnecting generator. Under
    the rule, “the Interconnection Customer [is] solely responsible
    for the costs of Interconnection Facilities, which are defined
    as all facilities and equipment between the Generating Facility
    and the Point of Interconnection with the Transmission
    System. Network Upgrades, which are defined as all facilities
    13
    and equipment constructed at or beyond the Point of
    Interconnection for the purpose of accommodating the new
    Generating Facility,” are (ultimately) the responsibility of the
    “Transmission Provider.” Order No. 2003 at 30,518–
    19 P 676
    (emphasis added).
    Petitioners claim that the “At or Beyond” rule departs
    from the Commission’s own precedents, is based on factual
    conclusions unsupported by substantial evidence, and is
    otherwise arbitrary or capricious. In our review we defer to
    an agency’s reasonable application of its own precedents and
    uphold factual conclusions supported by substantial evidence.
    See Williams Gas Processing – Gulf Coast Co., L.P. v. FERC,
    
    373 F.3d 1335
    , 1341 (D.C. Cir. 2004). We reject all of these
    assertions.
    In their claim of departure from precedent, petitioners
    point to our decision in Entergy Services, Inc. v. FERC, 
    391 F.3d 1240
     (D.C. Cir. 2004). There we considered whether
    FERC’s use of the “At or Beyond” rule in the decision under
    review represented a departure from an earlier FERC decision,
    Consumers Energy Co., 95 F.E.R.C. ¶ 61,233 (2001), in
    which FERC had used a “From” test to differentiate between
    Network Upgrades and Interconnection Facilities, assigning
    the transmission provider only the costs for “facilities from the
    point where the generator connects to the grid,” id. at 61,804
    (emphasis added). In Entergy we explicitly observed that the
    two tests might be fully consistent, see Entergy, 391 F.3d at
    1249, 1251, but we thought that the difference in language
    was potentially significant and that FERC had failed to
    adequately explain its precedents, see id. at 1251.
    In its order on remand from Entergy, Nevada Power Co.,
    113 F.E.R.C. ¶ 61,007 (2005), the Commission explained both
    the relation between the two labels and prior anomalies in its
    rulings. In essence, it said that “From” was a vague term and
    14
    that “At or Beyond” was simply “clearer terminology” that
    offered “a more precise way” of explaining FERC precedent.
    Id. at 61,
    013 P 12
    . And, acknowledging some past anomalies
    (principally in Consumers Energy), in which it had assigned
    to the interconnecting generator the cost of some facilities at
    the actual point of interconnection, it explained that “the issue
    was not raised, and the Commission did not discuss it or rule
    on it.” Id. at 61,
    013 P 13
    ; see also id. at 61,014 PP 14–15.
    We note that since then the Commission has continued to
    adhere to the “At or Beyond” approach. See Duke Energy
    Hinds, LLC, 117 F.E.R.C. ¶ 61,210 at *
    5 P 23
     (2006). In
    short, the “At or Beyond” rule can no longer be considered an
    unexplained departure from FERC precedent.
    Petitioners also contend that the “At or Beyond” rule
    violates the basic “cost causation” principle, under which
    costs are to be allocated to those who cause the costs to be
    incurred and reap the resulting benefits. But FERC has long
    taken the view that customer “but-for” causation isn’t
    dispositive of this issue. “[E]ven if a customer can be said to
    have caused the addition of a grid facility, the addition
    represents a system expansion used by and benefitting all
    users due to the integrated nature of the grid.” Public Service
    Co. of Colorado, 62 F.E.R.C. ¶ 61,013 at 61,061 (1993).
    (Indeed, for purposes of marginal cost pricing, all customers
    cause the incurrence of the costs associated with coincident
    peak load, whether by adding or merely continuing their
    usage. Town of Norwood, Mass. v. FERC, 
    962 F.2d 20
    , 24
    n.1 (D.C. Cir. 1992).) We have endorsed the approach of
    “assign[ing] the costs of system-wide benefits to all customers
    on an integrated transmission grid.” Western Massachusetts
    Electric Co. v. FERC, 
    165 F.3d 922
    , 927 (D.C. Cir. 1999).
    Utility Petitioners take issue, however, with the empirical
    conclusion that Network Upgrades benefit the entire network.
    They point to an affidavit by James E. Howell, Jr., an
    15
    administrator with Southern Company Services, who claimed
    that the addition of unnecessary new facilities causes
    interruptions with power lines and decreases the network’s
    reliability. Utility Petitioners object that because FERC did
    not address the Howell Affidavit directly, the Commission’s
    factual conclusions are unsupported by substantial evidence.
    The doctrine obliging agencies to address significant
    comments leaves them free to ignore insignificant ones. See
    Troy Corp. v. Browner, 
    120 F.3d 277
    , 289 (D.C. Cir. 1997).
    The evidence to which the petitioners point is one conclusory
    paragraph that offers no specific basis for undermining the
    Commission’s long-held understanding that Network
    Upgrades provide system-wide benefits. FERC said as much
    in Order No. 2003-B, referring to the contents of the Howell
    Affidavit as “unsupported hypothetical generalizations.”
    Order No. 2003-B at 31,
    292 P 56
    . Though the modifier
    “hypothetical” is inaccurate (the paragraph asserts flat out, for
    example, that “installation of a new substation . . . results in
    the affected transmission line being less reliable”), Howell’s
    generalizations are indeed unsupported, and thus insufficient
    (on their own) to draw in question the factual premises
    underlying the Commission’s cost assignment practice.
    Both sets of petitioners argue that the “At or Beyond”
    rule is inconsistent with FERC’s obligation to ensure efficient
    siting of facilities pursuant to § 212 of the Act, 16 U.S.C.
    § 824k, added by the Energy Policy Act of 1992. In pursuit of
    this claim Governmental Petitioners misquote § 212(a) as
    saying that the rates and terms in question must “promote the
    economically efficient siting of transmission and generation of
    electricity.” Governmental Petitioners’ Br. at 35 (emphasis
    added). The word “siting” in fact appears nowhere in the
    relevant section. In reality the statute requires that rates
    “promote the economically efficient transmission and
    generation of electricity.” 16 U.S.C. § 824k(a). No matter;
    FERC has understandably identified efficient siting as one of
    16
    its goals in administering the statute. Pricing Policy for
    Transmission Services; Policy Statement, 
    59 Fed. Reg. 55,031
    , 55,035 (Oct. 26, 1994).
    Petitioners’ argument is essentially that assignment to the
    transmission owner of the costs of facilities located at or
    beyond the point of interconnection creates an improper
    incentive. This is in essence a variation on petitioners’
    argument that the “At or Beyond” rule violates cost causation
    principles. Recall that the rule sticks generator owners with
    the entire cost of the link between the generator and the
    transmission facility; that, presumably, is the cost most
    affected by siting choices. Siting also will affect the
    economic viability of the interconnection upgrades. Order
    2003-B at 31,288 PP 32, 33. As to these, the orders require
    the generator to supply the upfront financing; more important,
    they call for a rate structure that imposes on the generator
    most or all of the risk of non-recovery. Order No. 2003-A at
    31,
    054 P 613
    . We see no substantial basis for petitioners’
    siting incentive theory.
    * * *
    Petitioners’ remaining objections concern the effectuation
    of the larger policies we’ve already discussed. These are
    questions of agency policy that we would overturn only if the
    Commission’s decisions were arbitrary or capricious. 
    5 U.S.C. § 706
    (2)(A). Having carefully considered petitioners’
    arguments and FERC’s explanations of its policies in the
    orders under review, we see no basis for any such finding.
    The issues do not merit discussion in a published opinion.
    17
    * * *
    For the foregoing reasons, we uphold Orders No. 2003,
    2003-A, 2003-B, and 2003-C against all objections raised by
    petitioners.
    So ordered.
    SENTELLE, Circuit Judge, dissenting in part: I concur in
    most of the majority’s opinion, but I cannot join that part of the
    opinion that upholds the eminent domain provisions of Order
    No. 2003. See Maj. Op. 10-12. FERC is a “creature of statute,”
    and the agency has “only those authorities conferred upon it by
    Congress.” Cal. Indep. Sys. Operator Corp. v. FERC, 
    372 F.3d 395
    , 398 (D.C. Cir. 2004) (internal quotation marks omitted).
    “[A]n agency literally has no power to act . . . unless and until
    Congress confers power upon it.” 
    Id.
     (quoting La. Pub. Serv.
    Comm’n v. FCC, 
    476 U.S. 355
    , 374 (1986)). I do not believe
    that Congress has authorized FERC to regulate the use of state-
    granted eminent domain power, and thus I respectfully dissent
    from that portion of the majority’s opinion.
    * * *
    Under FERC’s new Standard Large Generator
    Interconnection Agreement, transmission providers are required
    to take certain steps to help generators obtain necessary land for
    interconnection facilities. Transmission providers “shall at
    Interconnection Customer’s expense use efforts, similar in
    nature and extent to those that it typically undertakes on its own
    behalf or on behalf of its Affiliates, including use of its eminent
    domain authority.” Order No. 2003-A, 
    69 Fed. Reg. 15,932
    ,
    15,953-54, 16,033 (2004). In other words, to the extent that
    transmission providers use eminent domain to interconnect with
    their own generation facilities, they must now use eminent
    domain on behalf of unaffiliated generators as well. The issue
    before us is whether FERC has statutory authority to regulate
    transmission providers’ use of state-granted eminent domain
    power, and – if FERC does have such authority – whether the
    provisions of Order No. 2003 that address eminent domain are
    constitutional.
    2
    Courts may not presume that Congress has intended to
    regulate the “substantial sovereign powers” of states unless the
    federal statute in question is unmistakably clear. The Supreme
    Court has held that “if Congress intends to alter the usual
    constitutional balance between the States and the Federal
    Government, it must make its intention to do so unmistakably
    clear in the language of the statute.” Gregory v. Ashcroft, 
    501 U.S. 452
    , 460-61 (1991) (quoting Atascadero State Hosp. v.
    Scanlon, 
    473 U.S. 234
    , 242 (1985)) (internal quotation marks
    omitted). “This plain statement rule is nothing more than an
    acknowledgment that the States retain substantial sovereign
    powers under our constitutional scheme, powers with which
    Congress does not readily interfere.” Gregory, 
    501 U.S. at 461
    .
    Courts have applied this clear statement rule in a variety of cases
    involving federal regulation of the “substantial sovereign
    powers” of the states. See, e.g., Raygor v. Regents of Univ. of
    Minn., 
    534 U.S. 533
    , 543-44 (2002) (whether the federal
    supplemental jurisdiction statute tolls the statutes of limitation
    for state law claims in state court); Kimel v. Fla. Bd. of Regents,
    
    528 U.S. 62
    , 73-74 (2000) (whether a federal statute abrogates
    state sovereign immunity); Gregory, 
    501 U.S. at 461-67
    (whether the federal Age Discrimination in Employment Act
    applies to state judges); Will v. Mich. Dep’t of State Police, 
    491 U.S. 58
    , 65 (1989) (whether states are “persons” that may be
    sued under 
    42 U.S.C. § 1983
    ); Rice v. Santa Fe Elevator Corp.,
    
    331 U.S. 218
    , 230 (1947) (whether a federal statute preempts
    state law); Am. Bar Ass’n v. FTC, 
    430 F.3d 457
    , 471-72 (D.C.
    Cir. 2005) (whether a federal statute should be interpreted to
    regulate the practice of law, which has long been regulated at the
    state level).
    I believe that eminent domain is easily classified as a
    “substantial sovereign power” of the states, and thus the clear
    statement rule applies to federal regulation of this power.
    Courts have long recognized that eminent domain is at the very
    3
    core of state sovereignty. As the Supreme Court has stated:
    The power of eminent domain is an attribute of sovereignty,
    and inheres in every independent state. . . . The taking of
    private property for public use upon just compensation is so
    often necessary for the proper performance of governmental
    functions that the power is deemed to be essential to the life
    of the state. It cannot be surrendered, and if attempted to be
    contracted away, it may be resumed at will.
    Georgia v. City of Chattanooga, 
    264 U.S. 472
    , 480 (1924). See
    also Jackson v. Metro. Edison Co., 
    419 U.S. 345
    , 353 (1974)
    (noting that eminent domain “is traditionally associated with
    [state] sovereignty”). Courts have also emphasized that even if
    eminent domain authority has been delegated to a public utility
    or a privately-owned corporation, it is still the state that is acting
    whenever the eminent domain power is used:
    The right of eminent domain is an attribute of sovereignty.
    . . . It is none the less a public right, because the state
    sometimes consents that it may be exercised by a quasi
    public corporation, like a common carrier. Such license or
    permission is granted because its exertion in that form is
    thought to be for the public interest. . . . It permits them to
    proceed in their own names, but really on behalf of the state
    ....
    Louisville & N.R. Co. v. W. Union Tel. Co., 
    268 F. 4
    , 8 (6th Cir.
    1920). See also Baldwin v. Appalachian Power Co., 
    556 F.2d 241
     (4th Cir. 1977) (“By exercising the delegated power of
    eminent domain, a public service corporation acts as an agent of
    the state . . .”); Louisiana v. Chambers Inv. Co., 
    595 So.2d 598
    ,
    601 (La. 1992) (“[Eminent domain] always involves the taking
    or damaging of property interests by the state or some alter ego
    of the state, such as a public utility, that has been delegated the
    4
    power to condemn.”); Wissler v. Yadkin River Power Co., 
    74 S.E. 460
    , 460 (N.C. 1912) (“This power of eminent domain is
    conferred upon corporations affected with public use, not so
    much for the benefit of the corporations themselves, but for the
    use and benefit of the people at large.”). Thus, eminent domain
    is properly categorized as a “substantial sovereign power” of the
    states, even when that power has been delegated to a public
    utility. Accordingly, we should not presume that Congress
    intended to regulate the use of state eminent domain authority
    unless the federal statute in question is “unmistakably clear.”
    Turning to the instant case, Order No. 2003 will require
    transmission providers either to forego the use of their state-
    granted eminent domain power altogether, or to use this power
    to condemn property on behalf of unaffiliated generators. These
    provisions of Order No. 2003 cannot possibly be lawful unless
    Congress has “unmistakably” authorized FERC to regulate the
    use of state-granted eminent domain power. FERC has not
    identified – and I have not found – any such clear statement of
    congressional intent in the relevant statutes. The federal statutes
    pertaining to the “regulation and development of power” are
    codified in title 16 of the U.S. Code. See 
    16 U.S.C. §§ 791-839
    .
    Noticeably absent from these sections of the Code is any
    provision granting FERC authority to dictate the manner in
    which state eminent domain power may be used.
    Congress’s treatment of eminent domain in other provisions
    of the energy statutes confirms that we should not infer from
    FERC’s general grant of jurisdiction that the agency also has the
    power to regulate state eminent domain. When Congress
    addresses issues involving eminent domain, it tends to do so in
    a clear, detailed, and specific manner. See 16 U.S.C. § 824a-
    4(a) (granting the Secretary of Energy limited authority to use
    eminent domain to acquire rights-of-way “through North
    Dakota, South Dakota, and Nebraska for transmission facilities
    5
    for the seasonal diversity exchange of electric power to and from
    Canada”); id. § 824p(e) (granting eminent domain authority to
    certain licensees to build transmission facilities in “national
    interest electric transmission corridor[s]”); id. § 814 (granting
    eminent domain authority to certain licensees to acquire land
    “necessary to the construction, maintenance, or operation of any
    dam, reservoir, diversion structure, or the works appurtenant
    thereto”); id. § 831c(h)-(i) (authorizing the TVA to use eminent
    domain to “acquire real estate for the construction of dams,
    reservoirs, transmission lines, power houses, and other
    structures, and navigation projects at any point along the
    Tennessee River”). Although these provisions address federal
    eminent domain authority – rather than FERC’s power to
    regulate state eminent domain – they nonetheless show the
    specificity that Congress uses when it addresses eminent
    domain. These provisions reinforce my conclusion that FERC’s
    jurisdiction over interstate transmission and wholesale sales of
    electric energy does not include – sub silentio – the authority to
    regulate state eminent domain.
    * * *
    Under well-established principles of statutory interpretation,
    courts should not presume that Congress has intruded upon a
    core area of state sovereignty unless the relevant federal statute
    is clear and unambiguous. Here, FERC has not identified any
    federal statute that clearly authorizes the Commission to
    regulate the use of state eminent domain power. Thus, I would
    hold that the provisions of Order No. 2003 that impose
    restrictions on transmission providers’ use of state-granted
    eminent domain power are beyond the scope of FERC’s
    statutory authority. Because I would resolve this issue on
    statutory grounds, I do not need to address the constitutional
    issue of “commandeering.” Of course, in the future, Congress
    might pass a statute that specifically authorizes FERC to
    6
    regulate how transmission providers use their eminent domain
    power. Such a statute may raise constitutional issues under New
    York v. United States, 
    505 U.S. 144
     (1992), and Printz v. United
    States, 
    521 U.S. 898
     (1997), but those issues are not before us
    at this time.
    For the aforementioned reasons, I respectfully dissent from
    the portions of the majority opinion that address the eminent
    domain provisions of Order No. 2003. I join the remainder of
    the majority’s opinion.
    

Document Info

Docket Number: 04-1148

Filed Date: 1/12/2007

Precedential Status: Precedential

Modified Date: 12/21/2014

Authorities (19)

bonneville-power-administration-city-of-tacoma-port-of-seattle-coral , 422 F.3d 908 ( 2005 )

Georgia v. City of Chattanooga , 44 S. Ct. 369 ( 1924 )

American Bar Ass'n v. Federal Trade Commission , 430 F.3d 457 ( 2005 )

national-fuel-gas-supply-corporation-v-federal-energy-regulatory , 900 F.2d 340 ( 1990 )

Gregory v. Ashcroft , 111 S. Ct. 2395 ( 1991 )

Printz v. United States , 117 S. Ct. 2365 ( 1997 )

Troy Corporation v. Carol M. Browner, Administrator, United ... , 120 F.3d 277 ( 1997 )

Williams Gas Processing - Gulf Coast Co. v. Federal Energy ... , 373 F.3d 1335 ( 2004 )

Jon-Karl Baldwin v. Appalachian Power Company, a Corporation , 556 F.2d 241 ( 1977 )

CA Indep Sys Oprtr v. FERC , 372 F.3d 395 ( 2004 )

State Through DOTD v. Chambers Inv. Co. , 595 So. 2d 598 ( 1992 )

associated-gas-distributors-v-federal-energy-regulatory-commission-air , 824 F.2d 981 ( 1987 )

New York v. United States , 112 S. Ct. 2408 ( 1992 )

Kimel v. Florida Board of Regents , 120 S. Ct. 631 ( 2000 )

Detroit Edison Co. v. Federal Energy Regulatory Commission , 334 F.3d 48 ( 2003 )

Columbia Gas Transmission Corp. v. Federal Energy ... , 404 F.3d 459 ( 2005 )

Western Massachusetts Electric Company v. Federal Energy ... , 165 F.3d 922 ( 1999 )

Atascadero State Hospital v. Scanlon , 105 S. Ct. 3142 ( 1985 )

Louisiana Pub. Serv. Comm'n v. FCC , 106 S. Ct. 1890 ( 1986 )

View All Authorities »