National Ass'n of Home Builders v. United States Army Corps of Engineers , 417 F.3d 1272 ( 2005 )


Menu:
  •   United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued April 19, 2005                 Decided July 29, 2005
    No. 04-5009
    NATIONAL ASSOCIATION OF HOME BUILDERS,
    APPELLANT
    v.
    UNITED STATES ARMY CORPS OF ENGINEERS ET AL .,
    APPELLEES
    No. 04-5010
    NATIONAL ASSOCIATION OF HOME BUILDERS,
    APPELLANT
    v.
    UNITED STATES ARMY CORPS OF ENGINEERS ET AL .,
    APPELLEES
    No. 04-5011
    NATIONAL ASSOCIATION OF HOME BUILDERS,
    APPELLANT
    2
    v.
    UNITED STATES ARMY CORPS OF ENGINEERS ET AL .,
    APPELLEES
    Appeals from the United States District Court
    for the District of Columbia
    (No. 00cv00379)
    (No. 00cv00558)
    (No. 00cv01404)
    Virginia S. Albrecht argued the cause for the appellants.
    Karma B. Brown, Duane J. Desiderio, Felicia K. Watson,
    Lawrence R. Liebesman, Rafe Petersen, Ethan Arenson, David
    E. Frulla, Andrew D. Herman and Elizabeth A. Gaudio were on
    brief.
    Peter L. Gray, Robin S. Conrad, Richard S. Moskowitz, Alan
    C. Raul and Brian T. Fitzpatrick were on brief for amici curiae
    Honorable Donald A. Manzullo et al. Prasad Sharma and
    Stephen A. Bokat entered appearances.
    Greer S. Goldman, Attorney, United States Department of
    Justice, argued the cause for appellees United States Army Corp
    of Engineers et al. David C. Shilton, Martin McDermott and
    Stephanie Tai, Attorneys, United States Department of Justice,
    were on brief.
    Howard I. Fox was on brief for appellees, Natural Resources
    Defense Council and Sierra Club.
    3
    Eliot Spitzer, Attorney General, State of New York, Peter H.
    Lehner, Philip M. Bein and Tracy Hughes, Assistant Attorneys
    General, State of New Mexico, were on brief for amici curiae
    States of New York and New Mexico.
    Before: GINSBURG, Chief Judge, and HENDERSON and
    GARLAND, Circuit Judges.
    Opinion for the court filed by Circuit Judge HENDERSON.
    KAREN LECRAFT HENDERSON, Circuit Judge: The National
    Association of Home Builders (NAHB) and others1
    (collectively, the appellants) appeal the dismissal of their multi-
    pronged challenge to the issuance of certain permits by the
    United States Army Corps of Engineers (Corps) pursuant to
    section 404(e) of the Clean Water Act (CWA), 
    33 U.S.C. § 1344
    . The district court granted summary judgment to the
    Corps, concluding that it lacked subject matter jurisdiction to
    entertain any of the appellants’ claims because the Corps’
    issuance of the permits did not constitute “final agency action”
    subject to judicial review under the Administrative Procedure
    Act (APA), 
    5 U.S.C. § 704
    . See Nat’l Ass’n of Home Builders
    v. United States Army Corps of Eng’rs, 
    297 F. Supp. 2d 74
    (D.D.C. 2003), reprinted in Joint Appendix (J.A.) at 146-52.
    We disagree; the appellants’ claims, with one exception, are
    cognizable. Accordingly, we reverse the district court in part
    and remand for further proceedings consistent with this opinion.
    I.
    The CWA aims to “restore and maintain the chemical,
    physical, and biological integrity of the Nation’s waters,” 33
    1
    The other appellants are the National Stone, Sand and Gravel
    Association (NSSGA), the American Road and Transportation
    Builders Association (ARTBA), the Nationwide Public Projects
    Coalition (NPPC), the National Federation of Independent Businesses
    (NFIB) and Wayne Newnam, an Ohio homebuilder.
    
    4 U.S.C. § 1251
    (a), by prohibiting the discharge of pollutants into
    navigable waters of the United States—except, that is, by
    permit, see 
    id.
     § 1311(a). The CWA divides the authority to
    issue permits to discharge pollutants between the United States
    Environmental Protection Agency and the United States
    Secretary of the Army, acting through the Corps, conferring on
    the latter the power to issue permits for discharges of “dredged
    or fill material” only. Id. § 1344(a). Responsibility for the day-
    to-day administration of the permitting regime falls to the
    Corps’ district and division engineers.         See 
    33 C.F.R. § 320.1
    (a)(2).
    The Corps issues a permit under section 404 of the CWA
    either on a class-wide (“general permit”) or a case-by-case
    (“individual permit”) basis. 
    33 U.S.C. § 1344
    (a), (e). The
    Corps issues a general permit “on a State, regional, or
    nationwide basis for any category of activities involving
    discharges of dredged or fill material.” 
    Id.
     § 1344(e)(1); see
    also 
    33 C.F.R. § 323.2
    (h). Before issuing a general permit for
    a “category of activities,” the Corps must “determine[] that the
    activities in such category are similar in nature, will cause only
    minimal adverse environmental effects when performed
    separately, and will have only minimal cumulative adverse
    effect on the environment.” 
    33 U.S.C. § 1344
    (e)(1); see also 
    33 C.F.R. § 323.2
    (h)(1). A general permit has a statutorily-limited
    lifespan—i.e., no longer than five years—and may be revoked
    or modified if the authorized activities “have an adverse impact
    on the environment or . . . are more appropriately authorized by
    individual permits.” 
    33 U.S.C. § 1344
    (e)(2).
    The Corps’ individual permit process is, by contrast, “a longer,
    more comprehensive procedure.” New Hanover Township v.
    United States Army Corps of Eng’rs, 
    992 F.2d 470
    , 471 (3d Cir.
    1993). The Corps makes a formal decision on an individual
    application following site-specific documentation and analysis,
    public interest review, public notice and comment and, if
    5
    necessary, a public hearing. See 
    33 C.F.R. § 320.4
    ; 
    id.
     §§ 323,
    325; see also Home Builders Ass’n of Greater Chicago v. United
    States Army Corps of Eng’rs, 
    335 F.3d 607
    , 612 (7th Cir. 2003).
    If the Corps initially denies an individual application, the
    applicant may challenge that determination through an
    administrative appeals process. See 
    33 C.F.R. § 331
    . Indeed, a
    disappointed applicant must exhaust his administrative remedies
    before heading to federal court. See 
    id.
     § 331.12.
    Thus a party desiring to discharge fill or dredged material into
    our nation’s navigable waters may do so in either of two ways.
    See New Hanover Township, 
    992 F.2d at 471
    . If the proposed
    discharge activity is covered by a general permit, the party may
    proceed without obtaining an individual permit or, in some
    cases, even without giving the Corps notice of the discharge.
    See 
    33 C.F.R. § 330.1
    (e)(1) (“In most cases, permittees may
    proceed with activities authorized by [nationwide general
    permits] without notifying the [district engineer].”); New
    Hanover Township, 
    992 F.2d at 471
     (discharger may “simply
    operate under the [general] permit without informing the Corps
    in advance unless the [general] permit in question requires
    advance approval from the Corps”). On the other hand, if the
    proposed discharge is not covered by a general permit, the party
    must secure an individual permit before undertaking the
    discharge. See 
    33 C.F.R. § 323.3
    (a). A party that discharges
    without meeting the conditions of a general permit or obtaining
    an individual permit faces both civil and criminal enforcement
    actions. See 
    33 U.S.C. § 1319
    ; 
    33 C.F.R. § 326.5
    -.6.
    This litigation involves several nationwide permits, or NWPs,
    a species of general permit designed to minimize delays and
    paperwork for projects with minimal environmental impact. See
    
    33 C.F.R. § 330.1
    (b). The Corps has issued this kind of permit
    for five-year intervals since 1977, see Nat’l Ass’n of Home
    Builders, 
    297 F. Supp. 2d at 77
    ; Public Notice Concerning
    Changes to Nationwide Permit 26, 
    63 Fed. Reg. 39,276
    , 39,277
    6
    (July 22, 1998), including the once widely-used but now defunct
    NWP 26, see Final Notice of Issuance, Reissuance, and
    Modification of Nationwide Permits, 
    61 Fed. Reg. 65,874
    ,
    65,892 (Dec. 13, 1996) (noting 13,837 activities were authorized
    by NWP 26 in 1995 alone). There are currently 43 NWPs in
    force—covering activities ranging from “Single-family
    Housing” (NWP 29) to “Mining Activities” (NWP 44) to
    “Cranberry Production Activities” (NWP 34)—that are subject
    to 27 General Conditions (GCs)2 —regarding matters like “Soil
    Erosion and Sediment Controls” (GC 3) and “Notification” (GC
    13). See Issuance of Nationwide Permits; Notice, 
    67 Fed. Reg. 2020
    , 2077, 2078-94 (Jan. 15, 2002). In their current version,
    the assorted NWPs, applicable conditions and relevant
    definitions span nearly 20 pages in the Federal Register. See 
    id. at 2077-94
    .
    In 1996, the Corps proposed to reissue a number of existing
    NWPs, albeit with modifications, that were otherwise set to
    expire on January 21, 1997. See Proposal to Issue, Reissue, and
    Modify Nationwide Permits; Public Hearing, 
    61 Fed. Reg. 30,780
     (June 17, 1996). As to NWP 26, which, at the time,
    authorized a party to discharge dredged or fill materials
    affecting up to ten acres of water into headlands and isolated
    wetlands without an individual permit and required only notice
    to a Corps district engineer of any discharge causing loss or
    substantial adverse modification of one to ten acres of wetlands,
    the Corps gave public notice of—and sought comment
    on—proposed changes to its “pre-construction notification”
    timeline and acreage threshold limits. See 
    id. at 30,783
    . It also
    notified the public that it planned to “initiate a process to
    regionalize” NWP 26 to “further improve its effectiveness.” 
    Id.
    2
    The Corps’ GCs “must be followed in order for any authorization
    by an NWP to be valid.” Issuance of Nationwide Permits; Notice, 
    67 Fed. Reg. 2020
    , 2089 (Jan. 15, 2002).
    7
    Following public comment, the Corps decided to replace
    NWP 26 with “activity-specific” general permits. See Final
    Notice of Issuance, Reissuance, and Modification of
    Nationwide Permits, 
    61 Fed. Reg. 65,874
    , 65,875 (Dec. 13,
    1996). To allow ample time to develop replacement permits,
    however, it reissued NWP 26 for a two-year period but with
    more stringent conditions. See 
    id. at 65,877, 65,891, 65,895
    .
    In July 1998, the Corps published a proposed suite of activity-
    specific general permits to replace NWP 26, see Proposal to
    Issue and Modify Nationwide Permits, 63 Fed Reg. 36,040
    (July 1, 1998), and extended, once more, the life of NWP 26
    until December 30, 1999 “or the effective date of the new and
    modified NWPs, whichever comes first,” Proposal to Issue and
    Modify Nationwide Permits; Notice, 
    64 Fed. Reg. 39,252
    ,
    39,260 (July 21, 1999). That same month the Corps also
    reissued the NWP regarding single-family housing (NWP 29),
    but reduced the authorized maximum acreage impact from one-
    half to one-quarter acre. See Final Notice of Modification of
    Nationwide Permit 29 for Single Family Housing, 
    64 Fed. Reg. 47,175
     (Aug. 30, 1999).
    The Corps issued a second proposed set of activity-specific
    NWPs to replace NWP 26 one year later. See 64 Fed. Reg. at
    39,252. In March 2000, following another round of public
    comment, the Corps promulgated activity-specific permits
    consisting of five new NWPs and six modified NWPs, all
    intended to replace NWP 26. See Final Notice of Issuance and
    Modification of Nationwide Permits, 
    65 Fed. Reg. 12,818
     (Mar.
    9, 2000). With some of the activity-specific NWPs, the Corps
    reduced the authorized maximum per-project acreage impact
    from ten acres to one-half acre and required preconstruction
    notification for impacts greater than one-tenth acre. See 65
    Fed. Reg. at 12,818. Although December 30, 1999 preceded
    the effective date of the replacement permits, the Corps
    nevertheless decided to have NWP 26 expire the same day the
    new permits took effect—June 7, 2000. Compare 
    65 Fed. Reg.
     8
    at 12,818 (extending NWP 26’s expiration date to June 5,
    2000), with Final Notice of Issuance and Modification of
    Nationwide Permits, 
    65 Fed. Reg. 14,255
     (Mar. 16, 2000)
    (making June 7, 2000 “the correct effective date for the new
    and modified NWPs, as well as the correct expiration date for
    NWP 26.”).
    The Corps’ new permits prompted three law suits the district
    court eventually consolidated into one. The NAHB’s suit was
    filed on February 28, 2000, followed by the NSSGA’s suit on
    March 16, 2000, and the NFIB’s suit on June 14, 2000.
    Together, the three suits allege four claims against the Corps,
    to wit: (1) it exceeded its statutory authority under the CWA by
    imposing certain permit conditions; (2) it acted arbitrarily and
    capriciously, in violation of the APA, 
    5 U.S.C. § 706
    (2)(A), by
    failing to provide a rational basis for its permit acreage
    thresholds; (3) it violated the Regulatory Flexibility Act (RFA),
    
    5 U.S.C. §§ 601
     et seq., by failing to evaluate the potential
    impact of the permits on small businesses and other small
    entities as well as alternatives to the permits; and (4) it violated
    the National Environmental Policy Act (NEPA), 
    42 U.S.C. §§ 4231
     et seq., by failing to prepare a Programmatic
    Environmental Impact Statement (PEIS) for the permits. The
    National Resources Defense Council and the Sierra Club (the
    intervenors) intervened in the district court proceedings in
    support of the Corps.
    The appellants moved for summary judgment on February
    15, 2001. The Corps and intervenors responded with motions
    for summary judgment of their own on June 14, 2001. While
    the parties’ cross-motions for summary judgment lay pending,
    on January 15, 2002, the Corps reissued all 43 NWPs, including
    the eleven March 2000 NWPs it issued to replace NWP 26, to
    make their expiration dates coincide, thereby “reduce[ing]
    confusion regarding the expiration of the NWPs and the
    9
    administrative burden of reissuing NWPs at different times.”3
    See 67 Fed. Reg. at 2020. In November 2003, the district court
    granted summary judgment to the Corps, concluding that “the
    Corps’ issuance of the new NWPs and general conditions,
    while constituting the completion of a decisionmaking process,
    does not constitute a ‘final’ agency action because no legally
    binding action has taken place as to any given project until
    either an individual permit application is denied or an
    enforcement action is instituted.” Nat’l Ass’n of Home
    Builders, 
    297 F. Supp. 2d at 78
    . Calling the “general permit
    program . . . the first step of a larger permitting process that
    enables the agency to streamline the overall process by limiting
    the pool of applicants at the front-end of the process,” the
    district court concluded that a party not eliminated from the
    applicant pool must “simply apply for an individual permit”
    and, consequently, “is not legally denied anything until [his]
    individual permit is rejected.” 
    Id. at 80
    .
    The appellants now appeal the district court’s judgment,
    which we review de novo. See, e.g., Mylan Labs., Inc. v.
    Thompson, 
    389 F.3d 1272
    , 1278 (D.C. Cir. 2004).
    II.
    The jurisdictional infirmity the lower court found fatal to this
    case was the want of a final agency action subject to judicial
    review; that is only one of the issues, however, joined by the
    parties and requiring our resolution. First, we consider whether
    the Corps took “final agency action” subject to challenge under
    the APA and, if so, whether the appellants’ challenge is
    otherwise ripe for judicial review. Next, we address whether
    3
    Some of the NWPs expired on February 11, 2002, while others
    expired on March 11, 2002. See 67 Fed. Reg. at 2020. As the Corps
    reissued all of the NWPs, GCs and applicable definitions on March 18,
    2002, they expire five years from that date. See id.; see also 
    33 U.S.C. § 1344
    (e)(2) (general permits limited to five-year lifespan).
    10
    the appellants may challenge the Corps’ compliance with the
    RFA and, again, whether that challenge is ripe. Finally, we
    review the appellants’ standing vel non to challenge the Corps’
    compliance with NEPA.
    A.
    Where, as here, no more specific statute provides for judicial
    review, the APA empowers a federal court to review a “final
    agency action for which there is no other adequate remedy in a
    court.” 
    5 U.S.C. § 704
    ; see Home Builders Ass’n of Greater
    Chicago, 
    335 F.3d at 614
    . “[T]wo conditions,” the United
    States Supreme Court tells us, “must be satisfied for agency
    action to be ‘final.’ ” Bennett v. Spear, 
    520 U.S. 154
    , 177
    (1997). “First, the action must mark the consummation of the
    agency’s decisionmaking process—it must not be of a merely
    tentative or interlocutory nature. And second, the action must
    be one by which rights or obligations have been determined, or
    from which legal consequences will flow.” 
    Id. at 177-78
    (internal quotation marks & citations omitted). In other words,
    an agency action is final if, as the Supreme Court has said, it is
    “ ‘definitive’ ” and has a “ ‘direct and immediate . . . effect on
    the day-to-day business’ ” of the party challenging it, FTC v.
    Standard Oil Co., 
    449 U.S. 232
    , 239 (1980) (quoting & citing
    Abbott Labs. v. Gardner, 
    387 U.S. 136
    , 152 (1967), overruled
    on other grounds by Califano v. Sanders, 
    430 U.S. 99
    , 105
    (1977)); see also Reliable Automatic Sprinkler Co. v. Consumer
    Prods. Safety Comm’n, 
    324 F.3d 726
    , 731 (D.C. Cir. 2003), or
    if, as our court has said, “it imposes an obligation, denies a
    right or fixes some legal relationship.” Reliable Automatic
    Sprinkler Co., 
    324 F.3d at
    731 (citing Role Models Am., Inc. v.
    White, 
    317 F.3d 327
    , 331-32 (D.C. Cir. 2003)). There can be
    little doubt that under these standards the Corps’ issuance of the
    11
    NWPs challenged by the appellants constitutes final agency
    action subject to judicial review.4
    We need not tarry long on the finality test’s first prong;
    plainly, the Corps’ issuance of the revised NWPs “mark[s] the
    consummation of [its] decisionmaking process.” Bennett, 
    520 U.S. at 178
    . There is nothing “tentative” or “interlocutory”
    about the issuance of permits allowing any party who meets
    certain conditions to discharge fill and dredged material into
    navigable waters. The intervenors argue, however, that, by
    “setting terms and conditions for NWPs, the Corps did not
    finally decide that a would-be discharger must comply with
    those terms and conditions, nor did the Corps finally deny
    authorization for discharges that exceed those terms and
    conditions.” Intervenors’ Br. at 15. In their view, “[a] would-
    be discharger remains free to pursue an individual or general
    permit that is free of those restrictions.” Intervenors’ Br. at 15.
    The district court similarly opined that a party whose activities
    do not meet the conditions set by the NWPs has not been
    “denied anything until [he] has exhausted all of [his] permit
    options.” Nat’l Ass’n of Home Builders, 
    297 F. Supp. 2d at 80
    .
    This is so, said the district court, because “the general permit
    program, in effect, is the first step of a larger permitting process
    that enables the agency to streamline the overall process by
    limiting the pool of applicants at the front-end of the process.”
    
    Id.
     If the issuance of the NWPs had merely altered the
    procedural framework for obtaining the Corps’ permission to
    discharge fill or dredged material into navigable waters, the
    district court’s reasoning—now advanced by the
    intervenors—might be sound. A requirement that a party
    participate in additional administrative proceedings “is different
    in kind and legal effect from the burdens attending what
    4
    Only the intervenors make a “finality” challenge. The Corps does
    not challenge the finality of its issuance of the NWPs but instead
    questions the ripeness of the claim. See opinion infra at 15.
    12
    heretofore has been considered to be final agency action.”
    Standard Oil Co., 
    449 U.S. at 242
    . We have in fact noted that
    “the doctrine of finality” would be no more than “an empty
    box” if the mere denial of a procedural advantage constituted
    final agency action subject to judicial review. ALCOA v.
    United States, 
    790 F.2d 938
    , 942 (D.C. Cir. 1986).
    But the NWPs do not simply work a change in the Corps’
    permitting procedures, thereby disadvantaging some within the
    class of would-be dischargers. The NWPs are not a definitive,
    but otherwise idle, statement of agency policy—they carry
    easily-identifiable legal consequences for the appellants and
    other would-be dischargers.          Admittedly, our precedent
    announces no self-implementing, bright-line rule in this regard;
    the finality inquiry is a “pragmatic” and “flexible” one. See,
    e.g., Ciba-Geigy Corp. v. EPA, 
    801 F.2d 430
    , 435-36 (D.C. Cir.
    1986) (“[W]e are to apply the finality requirement in a
    ‘flexible’ and ‘pragmatic’ way.” (quoting & citing Abbott
    Labs., 
    387 U.S. at 149-50
    )). Nevertheless, if an EPA directive
    forbidding the use of third-party human test data to evaluate
    pesticides’ effects constituted final agency action subject to
    judicial review before the EPA invoked it against any pesticide
    applicant, see CropLife Am. v. EPA, 
    329 F.3d 876
    , 881-83
    (D.C. Cir. 2003), and a Federal Communications Commission
    decision putting the burden on telephone companies to show
    their entitlement to certain costs was suitable for judicial review
    before any telephone company was denied costs, see Mountain
    States Tel. & Tel. Co. v. FCC, 
    939 F.2d 1035
    , 1041 (D.C. Cir.
    1991), the Corps’ issuance of NWPs likewise satisfies the
    second prong of the finality test. To our mind, all three
    constitute challenges to agency action “with legal consequences
    that are binding on both petitioners and the agency.” CropLife
    Am., 
    329 F.3d at 882
    ; see also Mountain States Tel. & Tel. Co.,
    
    939 F.2d at 1041
    .
    13
    The Corps’ NWPs create legal rights and impose binding
    obligations insofar as they authorize certain discharges of
    dredged and fill material into navigable waters without any
    detailed, project-specific review by the Corps’ engineers. See,
    e.g., 65 Fed. Reg. at 12,818 (“The terms and limits of the new
    and modified NWPs are intended to authorize activities that
    have minimal adverse effects on the aquatic environment,
    individually and cumulatively.”). The “direct and immediate”
    consequence of these authorizations for the appellants’ “day-to-
    day business” is not hard to understand: While some builders
    can discharge immediately, others cannot. If the appellants’
    planned activities do not meet the applicable NWP’s conditions
    and thresholds, they have two options. They can either put
    their projects on hold and run the Corps’ individual-permit
    gauntlet or modify the projects to meet the conditions. Either
    way, through increased delay or project modification, the
    NWPs directly affect the investment and project development
    choices of those whose activities are subject to the CWA.
    Indeed, the Corps itself appreciated that its permits would
    influence project design. “Many project proponents,” it noted,
    “will design their projects to comply with the 1/2 acre limit so
    that they can qualify for an NWP and receive authorization
    more quickly than they could through the standard permit
    process.” 65 Fed. Reg. at 12,821. We would be hard pressed,
    and in fact decline, to conclude that the NWPs do not “impose[]
    an obligation, den[y] a right or fix[] some legal relationship.”
    Reliable Automatic Sprinkler Co., 
    324 F.3d at 731
    .
    In addition, the intervenors argue that environmental groups,
    such as themselves, may challenge the Corps’ issuance of
    NWPs as final agency action but the appellants may not. This
    is so, they say, because an environmental group would
    challenge the discharges authorized by the Corps—that is, it
    would oppose an agency action—while the appellants challenge
    the Corps’ failure to authorize certain discharges—that is, they
    seek to compel agency action. The appellants seek to compel
    14
    agency action in this instance, the intervenors maintain,
    because “the Corps did not finally decide that a would-be
    discharger must comply with [the NWP] terms and conditions,
    nor did the Corps finally deny authorization for discharges that
    exceed those terms and conditions.” Intervenors’ Br. at 15.
    Thus “would-be dischargers” such as the appellants “remain
    free to pursue an individual or general permit.” Intervenors’
    Br. at 15. It is true that a party seeking to challenge an
    agency’s failure to act faces a different burden from that borne
    by a challenger of agency action. An action to “compel agency
    action unlawfully withheld or unreasonably delayed,” 
    5 U.S.C. § 706
    (1), is similar to a petition for mandamus and we apply a
    six-factor standard to determine if “the agency has a duty to act
    and [if] it has ‘unreasonably delayed’ in discharging that duty.”
    In re Am. Rivers, 
    372 F.3d 413
    , 418 (D.C. Cir. 2004); see also
    Telecomms. Research & Action Ctr. v. FCC, 
    750 F.2d 70
    , 76
    (D.C. Cir. 1984). A challenge to agency action, by contrast, is
    simply resolved according to the APA. But the case on which
    the intervenors principally ground their argument—Norton v.
    S. Utah Wilderness Alliance, 
    542 U.S. 55
    , 
    124 S. Ct. 2373
    (2004)—tends only to demonstrate why the oppose
    action/compel action dichotomy does not make the Corps’
    action non-final as to the appellants. In S. Utah Wilderness
    Alliance, various environmental groups challenged the Bureau
    of Land Management’s failure to protect public lands from
    damage allegedly caused by off-road vehicles. See 
    id.
     at 2377-
    78. At the outset, the Supreme Court noted that “[f]ailures to
    act are sometimes remediable under the APA, but not always,”
    and ultimately held that the BLM’s failure was not reviewable
    because “a claim under § 706(1) can proceed only where a
    plaintiff asserts that an agency failed to take a discrete agency
    action that it is required to take,” id. at 2379 (emphases in S.
    Utah Wilderness Alliance), and the BLM did not fail to take
    “required” action, id. at 2380, 2384. Here the appellants
    challenge not the Corps’ failure to act—i.e., “the omission of an
    15
    action without formally rejecting a request,” id. at 2379—as
    unreasonable under APA section 706(1); instead, they attack
    the NWPs the Corps did issue as arbitrary and capricious and
    beyond its permitting authority under APA section 706(2)(A).
    Because the Corps’ NWPs mark the completion of the Corps’
    decision-making process and affect the appellants’ day-to-day
    operations, they constitute final agency action regardless of the
    fact that the Corps’ action might carry different (or no)
    consequences for a different challenger, such as an
    environmental group. In any event, the notion that “would-be
    dischargers” like the appellants nevertheless “remain free to
    pursue an individual or general permit” suggests a
    ripeness—not a finality—problem.                  See Office of
    Communication of United Church of Christ v. FCC, 
    911 F.2d 813
    , 816-17 (D.C. Cir. 1990) (FCC’s refusal to adopt anti-
    trafficking policy and presumption that broadcast license
    transfer in less than three years is contrary to public interest are
    matters ripe for review). We turn to that issue now.
    B.
    Both the Corps and the intervenors, recognizing that we may
    affirm the district court on an alternative ground, see, e.g.,
    Tymshare, Inc. v. Covell, 
    727 F.2d 1145
    , 1150 (D.C. Cir. 1984)
    (“In this appeal, appellee has sought to justify the judgment
    below upon a ground argued below but not relied upon by the
    opinion of the district court. We may of course sustain on such
    a ground.”) (citing Langnes v. Green, 
    282 U.S. 531
    , 538-39
    (1931)), maintain that the appellants’ challenge is not ripe for
    judicial review. Not so.
    The doctrine of ripeness shares with its statutory counterpart,
    viz., finality, “the dual concerns of prematurity of judicial
    intervention in agency processes and the proper and principled
    exercise of judicial power.” USAA Fed. Sav. Bank v .
    McLaughlin, 
    849 F.2d 1505
    , 1508 (D.C. Cir. 1988). That is,
    “its basic rationale,” the Supreme Court tells us, “is to prevent
    16
    the courts, through avoidance of premature adjudication, from
    entangling themselves in abstract disagreements over
    administrative policies, and also to protect agencies from
    judicial interference until an administrative decision has been
    formalized and its effects felt in a concrete way by the
    challenging parties.” Abbott Labs., 
    387 U.S. at 148-49
    . The
    ripeness doctrine has two components: “[It] requires us to
    consider ‘the fitness of the issues for judicial review and the
    hardship to the parties of withholding court consideration.’ ”
    Village of Bensenville v. FAA, 
    376 F.3d 1114
    , 1119 (D.C. Cir.
    2004) (quoting & citing Abbott Labs., 
    387 U.S. at 149
    ).
    Neither of these considerations—which we address in
    turn—counsels in favor of postponement here.
    The appellants’ challenge easily satisfies the first ripeness
    prong—fitness. “[T]he fitness of an issue for judicial decision
    depends on whether it is ‘purely legal, whether consideration of
    the issue would benefit from a more concrete setting, and
    whether the agency’s action is sufficiently final.’ ” Atl. States
    Legal Found. v. EPA, 
    325 F.3d 281
    , 284 (D.C. Cir. 2003)
    (quoting & citing Clean Air Implementation Project v. EPA,
    
    150 F.3d 1200
    , 1204 (D.C. Cir. 1998)). The appellants’ APA
    challenge is “purely legal,” Atl. States Legal Found., 
    325 F.3d at
    284: They allege that the Corps exceeded its statutory
    authority in drafting the NWPs and that the Corps failed to
    offer a reasoned basis for their conditions and restrictions. See
    J.A. 8-9, 27, 44-51, 73-78; Appellants’ Br. at 14-16. We have
    repeatedly held that “[c]laims that an agency’s action is
    arbitrary and capricious or contrary to law present purely legal
    issues.” See, e.g., Atl. States Legal Found., 
    325 F.3d at
    284
    (citing Fox Television Stations, Inc. v. FCC, 
    280 F.3d 1027
    ,
    1039 (D.C. Cir. 2002)). We have also often observed that a
    purely legal claim in the context of a facial challenge, such as
    the appellants’ claim, is “presumptively reviewable.” Nat’l
    Mining Ass’n v. Fowler, 
    324 F.3d 752
    , 757 (D.C. Cir. 2003);
    see also Mountain States Tel. & Tel. Co., 
    939 F.2d at 1041
     (“In
    17
    light of the wholly legal and facial nature of the present
    challenge, we cannot agree that our ability to review the
    agency’s decision would be increased by delay.”).
    While we have cautioned that sometimes “even purely legal
    issues may be unfit for review,” Atl. States Legal Found., 
    325 F.3d at 284
    , we cannot accept the Corps’ argument that the
    appellants’ purely legal challenge is unfit for review at this
    time. It initially argues that the NWPs are not fit for review
    because their applicability to a given activity remains within the
    Corps’ discretion. We have already debunked this theory. In
    Appalachian Power Co. v. EPA, 
    208 F.3d 1015
    , 1022 (D.C.
    Cir. 2000), we explained that “the fact that a law may be altered
    in the future has nothing to do with whether it is subject to
    judicial review at the moment.” 
    Id.
     In addressing the ripeness
    of an EPA Guidance, we recently explained that “if the
    possibility . . . of future revision in fact could make agency
    action non-final as a matter of law, then it would be hard to
    imagine when any agency rule . . . would ever be final as a
    matter of law.” Gen. Elec. Co. v. EPA, 
    290 F.3d 377
    , 380 (D.C.
    Cir. 2002). That the Corps retains some measure of discretion
    with respect to the NWPs does not make the appellants’ purely
    legal challenge unripe.
    The Corps and the intervenors further argue that the
    appellants’ APA challenge remains “hopelessly abstract” until
    “a member submits an actual individual permit application
    proposing a specific project, has its application denied or
    unlawfully conditioned, and completes the administrative
    appeal process provided by Corps regulations.” Appellees’ Br.
    at 24; see also Intervenors’ Br. at 20- 23. While it is
    undoubtedly true that a “claim is not ripe for adjudication if it
    rests upon contingent future events that may not occur as
    anticipated, or indeed not occur at all,” we see no reason here
    to “wait for a rule to be applied to see what its effect will be.”
    Atl. States Legal Found., 
    325 F.3d at 284
     (internal quotation
    18
    marks & alteration omitted). No further factual development
    is necessary to evaluate the appellants’ challenge. All of the
    facts necessary for judicial review were before the Corps when
    it issued the permits and, on APA review, its action necessarily
    stands or falls on that administrative record and its statutory
    permitting authority under the CWA. See Fox Television
    Stations, 
    280 F.3d at 1039
     (issue fit for judicial review because
    whether agency action is arbitrary and capricious or contrary to
    law is “purely legal” question); cf. Elec. Power Supply Ass’n v.
    FERC, 
    391 F.3d 1255
    , 1263 (D.C. Cir. 2004) (claim fit for
    review “as it can be wholly resolved by an analysis of the
    Sunshine Act, the Act’s legislative history, and its construction
    by relevant case law”).
    Relying on Lujan v. Nat’l Wildlife Fed’n, 
    497 U.S. 871
    (1990), the intervenors also argue that the appellants’ challenge
    is not ripe because the CWA does not explicitly provide for
    facial review of a NWP and because the appellants need not
    adjust their conduct immediately. In Lujan, the Supreme Court
    rejected the National Wildlife Federation’s attempt to challenge
    the “continuing (and thus constantly changing) operations of
    the [Bureau of Land Management] in reviewing withdrawal
    revocation applications and the classifications of public lands
    and developing land use plans.” 
    Id. at 890
    . The Court
    explained:
    [R]espondent cannot seek w h o l e s a l e
    improvement of this program by court decree
    . . . . Under the terms of the APA, respondent
    must direct its attack against some particular
    “agency action” that causes it harm. Some
    statutes permit broad regulations to serve as the
    “agency action,” and thus to be the object of
    judicial review directly, even before the concrete
    effects normally required for APA review are
    felt. Absent such a provision, however, a
    19
    regulation is not ordinarily considered the type
    of agency action “ripe” for judicial review under
    the APA until the scope of the controversy has
    been reduced to more manageable proportions,
    and its factual components fleshed out, by some
    concrete action applying the regulation to the
    claimant’s situation in a fashion that harms or
    threatens to harm him. (The major exception, of
    course, is a substantive rule which as a practical
    matter requires the appellant to adjust his
    conduct immediately. Such agency action is
    “ripe” for review at once, whether or not
    explicit statutory review apart from the APA is
    provided.)
    
    Id. at 891
     (internal citations omitted; second emphasis added).
    But the appellants, unlike the National Wildlife Federation in
    Lujan, do not seek “wholesale” revision of the Corps’ permitting
    framework.       Rather, they challenge a specific agency
    action—i.e., the Corps’ issuance of NWPs authorizing certain
    discharges of dredged and fill material—that requires them to
    adjust their conduct immediately, as discussed above. And
    “[s]uch agency action,” the Court observed in Lujan, “is ‘ripe’
    for review at once, whether or not explicit statutory review apart
    from the APA is provided.” 
    Id.
     Accordingly, “[i]n light of the
    wholly legal and facial nature of the present challenge,” the
    appellants’ APA claim is fit for judicial review now. Mountain
    States Tel. & Tel. Co., 
    939 F.2d at 1041
    .
    Turning to the hardship prong of the ripeness test, we
    conclude that this requirement is also satisfied.          Any
    institutional interest in postponing review must be balanced
    against the resultant hardship to the appellants in order to
    determine whether immediate review is proper. See Consol.
    Rail Corp. v. United States, 
    896 F.2d 574
    , 577 (D.C. Cir. 1990)
    (“If we have doubts about the fitness of the issue for judicial
    20
    resolution, then we balance the institutional interests in
    postponing review against the hardship to the parties that will
    result from delay.”). On the one hand, no institutional interest
    of the court supports postponement. See Mountain States Tel.
    & Tel. Co., 
    939 F.2d at 1041
    . The administrative process has
    run its course, resulting in general permits and conditions that
    the appellants have challenged as arbitrary, capricious and
    contrary to law under the APA. Their success depends on the
    administrative record and the statutory parameters of the Corps’
    permitting authority under the CWA. On the other hand, we
    cannot agree with the Corps that the appellants face no hardship
    as a result of postponed judicial review because, as it would
    have us believe, legal consequences flow only from “a collective
    permitting decision on a specific project” and consequently any
    alleged harm is purely “hypothetical at this time.” Appellees’
    Br. at 28. Nor do we agree with the intervenors’ similar
    suggestion that any alleged harm is ameliorated by the
    appellants’ ability to “pursue further agency remedies.”
    Intervenors’ Br. at 23. To the contrary, the fact of the matter is
    that in the absence of judicial review the appellants are left with
    the choices we identified earlier: They must either modify their
    projects to conform to the NWP thresholds and conditions (as
    the Corps contemplates they will do) or refrain from building
    until they can secure individual permits. The NWPs therefore
    affect the appellants’ activities in a “direct and immediate” way.
    See Elec. Power Supply Ass’n, 
    391 F.3d at 1263
     (hardship
    demonstrated where “implementation of the market monitor
    exemption will have a direct and immediate impact on the
    appellant that rises to the level of hardship.” (internal quotation
    marks & alteration & citations omitted)); Better Gov’t Ass’n v.
    Dep’t of State, 
    780 F.2d 86
    , 93 (D.C. Cir. 1986) (DOJ guidelines
    caused hardship where “ ‘direct and immediate impact’ ” on
    appellants’ “primary conduct” would be “felt immediately”
    (citing & quoting Abbott Labs., 
    387 U.S. at 152
    ; Toilet Goods
    Ass’n, Inc. v. Gardner, 
    387 U.S. 158
    , 164 (1967))); cf. Texas v.
    21
    United States, 
    523 U.S. 296
    , 301 (1998) (no hardship where
    party “not required to engage in, or to refrain from, any
    conduct”); Pfizer Inc. v. Shalala, 
    182 F.3d 975
    , 979 (D.C. Cir.
    1999). Accordingly, we hold that the appellants’ APA challenge
    is ripe for judicial review.
    C.
    For “any rule subject” to the RFA, “a small entity that is
    adversely affected or aggrieved by final agency action is entitled
    to judicial review of agency compliance with the requirements
    of sections 601, 604, 605(b), 608(b), and 610.” 
    5 U.S.C. § 611
    (a)(1). The Corps and the intervenors have an argument
    apiece as to why the appellants cannot challenge the Corps’
    compliance with the RFA under this provision. We reject both
    and hold instead that the appellants’ RFA claim, like their APA
    claim, is justiciable.
    The NWPs, the Corps says, do not constitute a “rule” subject
    to review under section 604 of the RFA for two reasons, both of
    which hinge on the RFA’s definition of a rule as “any rule for
    which the agency publishes a general notice of proposed
    rulemaking pursuant to section 553(b) of [the APA], or any
    other law.” 
    5 U.S.C. § 601
    (2). The Corps initially contends that
    the NWPs fall within the APA’s definition of
    “adjudication”—defined as an “agency process for the
    formulation of an order,” 
    id.
     § 551(7)—rather than “rule,” which
    is defined as “the whole or a part of an agency statement of
    general or particular applicability and future effect designed to
    implement, interpret, or prescribe law or policy,” id. § 551(4).
    Each NWP constitutes an “adjudication,” so the Corps’
    argument goes, because it fits the APA’s definition of
    adjudication as the formulation of an “order,” id. § 551(7), an
    “order” includes a “licensing” disposition, id. § 551(6), and a
    “license” includes a “permit,” id. § 551(8). We reject this
    elaborate statutory construction for the more straightforward
    one.
    22
    Each NWP easily fits within the APA’s definition of “rule.”
    This is so because each NWP, which authorizes a permittee to
    discharge dredged and fill material (and thereby does not allow
    others without an individual permit), is a legal prescription of
    general and prospective applicability which the Corps has issued
    to implement the permitting authority the Congress entrusted to
    it in section 404 of the CWA. See 
    33 U.S.C. § 1344
    (e). As
    such, each NWP constitutes a rule: An “agency statement of
    general or particular applicability and future effect designed to
    implement, interpret, or prescribe law or policy.” 
    5 U.S.C. § 551
    (4); see generally Hercules, Inc. v. EPA, 
    598 F.2d 91
    , 117
    (D.C. Cir. 1978). It is of course the Corps’ decision whether to
    proceed by rule or adjudication, see SEC v. Chenery Corp., 
    332 U.S. 194
    , 203 (1947), but “rules is rules,” no matter their gloss.
    See Granholm ex rel. Mich. Dep’t of Natural Res. v. FERC, 
    180 F.3d 278
    , 282 (D.C. Cir. 1999) (quoting & citing BART L E T T J.
    WHIT T I N G , MODERN PROVERBS AND PROVERBIAL SAYINGS 541
    (1989)).
    Relying again on section 601(2) of the RFA, the Corps asserts
    that the NWPs are not rules because it did not issue any notice
    of proposed rulemaking pursuant to APA’s rulemaking
    provision, 
    5 U.S.C. § 553
    , or publish them in the Code of
    Federal Regulations. We have explained that an agency must
    comply with the “procedures laid down” in the APA only when
    it promulgates “legislative rules.” Appalachian Power Co., 
    208 F.3d at 1020
    . “Legislative rules,” we have said, “are those that
    grant rights, impose obligations, or produce other significant
    effects on private interests.” Batterton v. Marshall, 
    648 F.2d 694
    , 701-02 (D.C. Cir. 1980).
    Despite our declarations that “[o]nly ‘legislative rules’ have
    the force and effect of law” and “ ‘legislative rule’ is one the
    [a]
    agency has duly promulgated in compliance with the procedures
    laid down in the statute or in the Administrative Procedure Act,”
    Appalachian Power Co., 
    208 F.3d at 1020
    , we have not
    23
    hesitated to consider an agency pronouncement issued without
    meeting required APA procedures a rule. See 
    id.
     at 1020 n.11
    (“We have also used ‘legislative rule’ to refer to rules the
    agency should have, but did not, promulgate through notice and
    comment rulemaking.” (citing Am. Mining Cong. v. Dep’t of
    Labor, 
    995 F.2d 1106
    , 1110 (D.C. Cir. 1993)). While an
    “agency’s characterization of an official statement as binding or
    nonbinding has been given some weight, of far greater
    importance is the language used in the statement itself.” Brock
    v. Cathedral Bluffs Shale Oil Co., 
    796 F.2d 533
    , 537-38 (D.C.
    Cir. 1986) (citation omitted; emphasis added). As we said in
    Appalachian Power Co.:
    If an agency . . . treats the document in the
    same manner as it treats a legislative rule, if it
    bases enforcement actions on the policies or
    interpretations formulated in the document, if
    it leads private parties or State permitting
    authorities to believe that it will declare
    permits invalid unless they comply with the
    terms of the document, then the agency’s
    document is for all practical purposes
    “binding.”
    
    208 F.3d at 1021
    . The NWPs authorize certain discharges of
    dredged and fill material and in so doing “grant rights, impose
    obligations, [and] produce other significant effects on private
    interests.” Batterton, 
    648 F.2d at 701-02
    ; see also Appalachian
    Power Co., 
    208 F.3d at 1021
    .
    The intervenors, for their part, contend that “even if an NWP
    could be considered a ‘rule’ within the meaning of the RFA,
    [the appellants’] claims here do not challenge final agency
    action, . . . and thus are not cognizable under the RFA’s judicial
    review provision.” Intervenors’ Br. at 28 (citing 
    5 U.S.C. § 611
    (a)(3)(A)). We have already explained at length that, as
    the Corps’ NWPs represent its final word, there can be little
    24
    doubt that the appellants do challenge a final agency action.
    Accordingly, we hold that the appellants are entitled to press
    their RFA challenge now as the Corps’ issuance of the NWPs
    constitutes final agency action in the form of a legislative rule
    and their challenge focuses on the Corps’ compliance with
    sections 604 and 605 of the RFA. See J.A. 27-28.
    Although both the Corps and the intervenors appear not to
    question the ripeness of the appellants’ RFA claim, we briefly
    explain why we think the RFA claim is ripe. The Supreme
    Court has admonished that “ ‘procedural rights’ are special,”
    Lujan v. Defenders of Wildlife, 
    504 U.S. 555
    , 572 n.7 (1992),
    and that “a person with standing who is injured by a failure to
    comply with the NEPA procedure may complain of that failure
    at the time the failure takes place, for the claim can never get
    riper.” Ohio Forestry Ass’n, Inc. v. Sierra Club, 
    523 U.S. 726
    ,
    737 (1998). The RFA, similar to NEPA in the environmental
    sphere, requires an agency to evaluate the adverse economic
    effects of and less harmful alternatives to its actions before
    taking them. See Associated Fisheries of Maine, Inc. v. Daley,
    
    127 F.3d 104
    , 114 (1st Cir. 1997) (“[A] useful parallel can be
    drawn between RFA § 604 and the National Environmental
    Policy Act, which furthers a similar objective . . . .”). Thus, as
    with a NEPA challenge, the appellants may complain of the
    Corps’ alleged failure to comply with the procedures set forth
    in sections 604 and 605 of the RFA at the time the alleged
    failure occurred, i.e., when the Corps issued the NWPs without
    complying with those procedures. In sum, the appellants’ RFA
    challenge “can never get riper.” Ohio Forestry Ass’n, 523 U.S.
    at 737.
    25
    D.
    Finally, we address the Corps’ assertion that the appellants
    lack prudential standing to maintain their NEPA challenge.5
    Three propositions bearing on federal court jurisdiction are by
    now obvious: Want of jurisdiction robs a federal court of the
    power to act, see, e.g., B & J Oil & Gas v. FERC, 
    353 F.3d 71
    ,
    74-75 (D.C. Cir. 2004), standing is a prerequisite to
    jurisdiction, see, e.g., Crow Creek Sioux Tribe v. Brownlee, 
    331 F.3d 912
    , 915-16 (D.C. Cir. 2003), and the appellants bear the
    burden of establishing their standing to sue, see, e.g., KERM,
    Inc. v. FCC, 
    353 F.3d 57
    , 59 (D.C. Cir. 2004). A fourth is now
    equally manifest in our Circuit. When a complainant’s standing
    is not “self-evident,” he must “supplement the record to the
    extent necessary to explain and substantiate [his] entitlement to
    judicial review.” Sierra Club v. EPA, 
    292 F.3d 895
    , 900 (D.C.
    Cir. 2002). That is, in Sierra Club, we put on notice all
    complainants whose standing is unclear that they must prove
    their standing by a “substantial probability,” 
    id. at 899
    , and that
    they should do so “by the submission of [their] arguments and
    any affidavits or other evidence appurtenant thereto at the first
    appropriate point in the review proceeding,” 
    id. at 900
    . Our
    Sierra Club rule is rooted in notions of fairness and judicial
    economy not difficult to grasp: As the complainant is ordinarily
    in possession of the facts on which he relies for standing,
    making those facts manifest at the outset saves the parties and
    the court from squandering time and energy, either by
    “flail[ing] at the unknown in an attempt to prove the negative”
    or by needlessly wrangling over an uncontested point. 
    Id. at 901
    .
    5
    Although the district court did not make explicit the basis for
    dismissing the NEPA claim, presumably it did so for the same reason
    it dismissed the RFA claim, i.e., no final agency action. See Nat’l
    Ass’n of Home Builders, 
    297 F. Supp. 2d at
    78 n.5.
    26
    We think that it is fairly “self-evident” that the various
    appellants as representatives of the regulated parties satisfy the
    “irreducible constitutional minimum” of Article III standing,
    Lujan, 
    504 U.S. at 560
     (injury-in-fact, causation, redressability)
    and the additional requirements for representational standing,
    see Hunt v. Wash. State Apple Adver. Comm’n, 
    432 U.S. 333
    ,
    342-43 (1977) (one member with standing to sue in his own
    right, association seeks to protect interests germane to its
    purpose, no individual member need participate in lawsuit).
    But as the Supreme Court has explained, constitutional standing
    is not the end of the game because the “question of standing
    ‘involves both constitutional limitations on federal-court
    jurisdictionand prudential limitations on its exercise.’
    ” Bennett, 
    520 U.S. at 162
     (quoting & citing Warth v. Seldin,
    
    422 U.S. 490
    , 498 (1975)). Prudential standing requires “that
    a plaintiff’s grievance must arguably fall within the zone of
    interests protected or regulated by the statutory provision.”
    Bennett, 
    520 U.S. at 162
    ; Nuclear Energy Inst. v. EPA, 
    373 F.3d 1251
    , 1266 (D.C. Cir. 2004). The zone-of-interest test,
    however, is intended to “exclude only those whose interests are
    so marginally related to or inconsistent with the purposes
    implicit in the statute that it cannot reasonably be assumed that
    Congress intended to permit the suit.” Clarke v. Sec. Indus.
    Ass’n, 
    479 U.S. 388
    , 399 (1987). And it is by no means self-
    evident to us that the appellants have prudential standing to
    advance their NEPA challenge.
    The Corps and the intervenors agree with our conclusion but
    for reasons with which we do not agree. The Corps offers that
    the appellants do not fall within NEPA’s zone-of-interest
    because their claims are more likely to frustrate than effectuate
    NEPA’s purposes, their asserted injury is “purely economic”
    and their interest is merely “in avoiding ‘unnecessary delays,
    regulatory uncertainty, and considerable cost to [their]
    members.’ ” Appellees’ Br. at 35-36 (quoting NSSGA’s
    complaint; alteration in Appellees’ Br.). The intervenors
    27
    similarly assert that the appellants do not constitute “an
    appropriate representative of the environmental interests
    underlying the statute.” Intervenors’ Br. at 28 n.14. The
    premise underlying this reasoning is flawed—commercial
    entities are not per se excluded from NEPA’s zone-of-interest.
    “[A]n allegation of injury to monetary interest alone may
    not,” of course, “bring a party within the zone of environmental
    interests as contemplated by NEPA for purposes of standing.”
    Realty Income Trust v. Eckerd, 
    564 F.2d 447
    , 452 (D.C. Cir.
    1977). But we have often observed that “a party is not
    precluded from asserting cognizable injury to environmental
    values because his ‘real’ or ‘obvious’ interest may be viewed
    as monetary” or “ ‘disqualified’ from asserting a legal claim
    under NEPA because the ‘impetus’ behind the NEPA claim
    may be economic.” Id.; see also Mountain States Legal Found.
    v. Glickman, 
    92 F.3d 1228
    , 1236 (D.C. Cir. 1996). “[P]arties
    motivated by purely commercial interests routinely satisfy the
    zone of interests test,” we have said, as “[c]ongruence of
    interests, rather than identity of interests, is the benchmark.”
    Amgen, Inc. v. Smith, 
    357 F.3d 103
    , 109 (D.C. Cir. 2004). We
    have even observed that “it surely does not square with the
    broad Congressional purpose in NEPA of assuring that
    environmental values would be adequately and pervasively
    considered in federal decision-making for private parties who
    may not be ‘pure of heart’ to be excluded from vindicating the
    Act.” Realty Income Trust, 564 F.2d at 453.
    Thus the appellants’ problem is not that their “economic
    interests . . . blight [their] qualifying ones,” Mountain States
    Legal Found., 
    92 F.3d at 1236
    ; rather, they have failed to
    demonstrate by a “substantial probability” that they have any
    qualifying ones, Sierra Club, 
    292 F.3d at 899
    . Prudential
    standing need only be shown by one appellant and, as only the
    NPPC presses the NEPA challenge, it is no surprise that the
    appellants rely solely on NPPC’s averments in their effort to
    28
    demonstrate prudential standing. See Mountain States Legal
    Found., 
    92 F.3d at 1232
     (Because “prudential standing can be
    shown for at least one appellant,” court need “not consider the
    standing of the other appellants to raise th[is] claim.” (citing
    Watt v. Energy Action Educ. Found., 
    454 U.S. 151
    , 160 (1981);
    Vill. of Arlington Heights v. Metro. Hous. Dev. Corp., 
    429 U.S. 252
    , 264 n.9 (1977))). The NPPC’s membership is principally
    composed of local government agencies that “are involved in
    municipal, industrial and agricultural water supply, flood
    control, irrigation, wastewater and stormwater management,
    street and highway construction and maintenance, and
    environmental quality amenities.” J.A. 125. To support its
    contention that it falls within NEPA’s zone-of-interest to
    challenge the NWPs, it relies on the averments of its Executive
    Director, Robert Tonsing, in paragraph eight of his affidavit:
    [D]ue to the inflexible one-half acre rule, the
    incentive for NPPC members to narrowly tailor
    their projects so as to fit under the “minimal
    effects” acreage cap has been significantly
    reduced. In many cases, under the three-acre
    rule previously enforced by the Corps, members
    would scale back their projects in order to satisfy
    the “minimal effect” standard. But with the one-
    half acre rule, it is virtually impossible for NPPC
    members to do so because very few projects can
    fit within the one-half acre cap. Thus, the
    imagined environmental benefit to be achieved
    by the Corps’ inflexible one-half acre rule is
    unlikely to be realized.
    J.A. 128.     In their brief, the appellants characterize this
    paragraph as supporting the proposition that “[t]he restrictions
    in the [permits] and the delays in processing times mean that
    NPPC members cannot provide [their] important public services
    in a timely manner, increasing flood risk for the communities
    29
    that NPPC members serve, posing a significant threat to people
    and property.” Appellants’ Br. at 13 (citing J.A. 128, ¶ 8).
    NPPC’s theory of prudential standing, so far as we can tell, is
    rooted in the contention that the Corps’ failure to issue more
    lenient NWPs prevents NPPC from improving the environment.
    We need not conclude that NPPC’s theory fails to “square with
    the broad Congressional purpose in NEPA of assuring that
    environmental values would be adequately and pervasively
    considered in federal decision-making.” Realty Income Trust,
    564 F.2d at 453. Even if we accept that it may be possible for
    NPPC’s members to suffer a procedural injury sufficient to
    bring them within NEPA’s zone-of-interest, nowhere does
    NPPC point to any evidence “supporting the proposition that
    there is a ‘substantial probability’ of ‘actual or imminent’ injury
    to its members arising from” the Corps’ failure to conduct an
    environmental analysis (i.e., a PEIS) of permits it did not issue
    but should have. Sierra Club, 
    292 F.3d at 902
     (quoting & citing
    Am. Petroleum Inst. v. EPA, 
    216 F.3d 50
    , 63 (D.C. Cir. 2000)).
    Tonsing’s declaration offers plenty of speculation: Paragraph
    eight speaks of its members’ “reduced” incentives in attempting
    to bring their projects within the parameters of the general
    permits, of the “very few” projects that “can” fit the new
    conditions, of the “virtual[] impossib[ility]” of meeting the
    conditions and of the “imagined environmental benefits”
    resulting from them. J.A. 128. But it offers nothing concrete
    from which we can conclude there is a “substantial probability”
    that NPPC’s members will suffer an injury sufficient under
    Sierra Club. See 
    292 F.3d at 898
    . The declaration does not
    mention a single specific project or activity that will not be
    undertaken because of the more restrictive NWPs the Corps did
    issue—as opposed to some other, presumably more lenient,
    permits favored by NPPC’s membership. See J.A. 125-29.
    Further casting doubt on the likelihood that, under its theory,
    NPPC will suffer any NEPA procedural harm is that, to the
    extent that NPPC members refuse to scale back their projects
    30
    and try to secure an individual permit instead, the environmental
    impact of any such project would be evaluated as part of the
    individual permitting process. See 
    33 C.F.R. § 325.2
    (a)(4) (“A
    decision on a permit application will require either an
    environmental assessment or an environmental impact statement
    unless it is included within a categorical exclusion.”).
    Accordingly, because “a NEPA claim may not be raised by a
    party with no . . . apparent environmental interest,” we are
    constrained to hold that the appellants cannot advance theirs.
    Town of Stratford, Conn. v. FAA, 
    285 F.3d 84
    , 88 (D.C. Cir.
    2002) (citation omitted). NEPA “cannot be used as a handy
    stick by a party with no interest in protecting against an
    environmental injury to attack a defendant.” 
    Id.
    Because we conclude that the appellants have not
    demonstrated a “substantial probability” that they fall within
    NEPA’s zone of interest, we affirm the dismissal of this claim.
    In view of this holding, we do not reach the NEPA ripeness
    issue. See N.J. Television Corp. v. FCC, 
    393 F.3d 219
    , 221
    (D.C. Cir. 2004) (“The priority for jurisdictional issues . . .
    doesn’t control the sequence in which we resolve non-merits
    issues that prevent us from reaching the merits.” (citing Ruhrgas
    AG v. Marathon Oil Co., 
    526 U.S. 574
    , 584-85 (1999); Grand
    Council of the Crees v. FERC, 
    198 F.3d 950
    , 954 (D.C. Cir.
    2000))); see also Galvan v. Fed. Prison Indus., Inc., 
    199 F.3d 461
    , 463 (D.C. Cir. 1999) (“There is an array of nonmerits
    questions that we may decide in any order.”).
    III.
    For the foregoing reasons, the district court’s grant of
    summary judgment to the Corps on the appellants’ APA and
    RFA claims is reversed and remanded for further proceedings
    consistent with this opinion. The dismissal of the appellants’
    NEPA claim is affirmed.
    So ordered.
    31
    

Document Info

Docket Number: 04-5009, 04-5010, 04-5011

Citation Numbers: 368 U.S. App. D.C. 23, 417 F.3d 1272, 35 Envtl. L. Rep. (Envtl. Law Inst.) 20157, 60 ERC (BNA) 2078, 2005 U.S. App. LEXIS 15573, 2005 WL 1789740

Judges: Ginsburg, Henderson, Garland

Filed Date: 7/29/2005

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (58)

Califano v. Sanders , 97 S. Ct. 980 ( 1977 )

Atl St Leg Fdn Inc v. EPA , 325 F.3d 281 ( 2003 )

Texas v. United States , 118 S. Ct. 1257 ( 1998 )

National Ass'n of Home Builders v. United States Army Corps ... , 297 F. Supp. 2d 74 ( 2003 )

new-hanover-township-paradise-watchdogs-beverly-ream-individually-and-as , 992 F.2d 470 ( 1993 )

clean-air-implementation-project-v-environmental-protection-agency , 150 F.3d 1200 ( 1998 )

Usaa Federal Savings Bank v. Ann D. McLaughlin Secretary of ... , 849 F.2d 1505 ( 1988 )

Warth v. Seldin , 95 S. Ct. 2197 ( 1975 )

Village of Arlington Heights v. Metropolitan Housing ... , 97 S. Ct. 555 ( 1977 )

Ruhrgas Ag v. Marathon Oil Co. , 119 S. Ct. 1563 ( 1999 )

Richard A. Batterton, Secretary of Employment & Social ... , 648 F.2d 694 ( 1980 )

Crow Creek Tribe v. White, Thomas E. , 331 F.3d 912 ( 2003 )

Nuclear Energy Institute, Inc. v. Environmental Protection ... , 373 F.3d 1251 ( 2004 )

Norton v. Southern Utah Wilderness Alliance , 124 S. Ct. 2373 ( 2004 )

Fox Television Stations, Inc. v. Federal Communications ... , 280 F.3d 1027 ( 2002 )

Hunt v. Washington State Apple Advertising Commission , 97 S. Ct. 2434 ( 1977 )

Better Government Association v. Department of State ... , 780 F.2d 86 ( 1986 )

The Toilet Goods Association, Inc. v. John w.ga Rdner, ... , 87 S. Ct. 1520 ( 1967 )

Grand Council of the Crees v. Federal Energy Regulatory ... , 198 F.3d 950 ( 2000 )

Associated Fisheries of Maine, Inc. v. Daley , 127 F.3d 104 ( 1997 )

View All Authorities »