Minisink Residents for Environmental Preservation & Safety v. Federal Energy Regulatory Commission , 762 F.3d 97 ( 2014 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued May 1, 2014                  Decided August 15, 2014
    No. 12-1481
    MINISINK RESIDENTS FOR ENVIRONMENTAL PRESERVATION
    AND SAFETY, ET AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    MILLENNIUM PIPELINE COMPANY, L.L.C.,
    INTERVENOR
    Consolidated with 13-1018
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    Carolyn Elefant argued the cause and filed the briefs for
    petitioners.
    Karin L. Larson, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With her on
    the brief were David L. Morenoff, Acting General Counsel,
    and Robert H. Solomon, Solicitor.
    2
    Aaron M. Streett argued the cause for intervenor. On the
    brief were Joseph Koury and Ryan J. Collins.
    Before: KAVANAUGH, MILLETT and WILKINS, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge WILKINS.
    WILKINS, Circuit Judge: Given the choice, almost no one
    would want natural gas infrastructure built on their block.
    “Build it elsewhere,” most would say. The sentiment is
    understandable. But given our nation’s increasing demand for
    natural gas (and other alternative energy sources), it is an
    inescapable fact that such facilities must be built somewhere.
    Decades ago, Congress decided to vest the Federal Energy
    Regulatory Commission with responsibility for overseeing the
    construction and expansion of interstate natural gas facilities.
    And in carrying out that charge, sometimes the Commission is
    faced with tough judgment calls as to where those facilities
    can and should be sited. These petitions present one such
    example.
    In July 2012, the Commission approved a proposal for
    the construction of a natural gas compressor station in the
    Town of Minisink, New York. Many local residents, hoping
    to thwart that result, banded together to fight the compressor
    station’s development. They formed a group called “Minisink
    Residents for Environmental Preservation and Safety”
    (“MREPS”) and mounted a vigorous, but ultimately
    unsuccessful, campaign opposing the project. Undeterred,
    MREPS and several of its individual members now petition
    for our intervention. In doing so, they mainly argue that the
    Commission’s approval of the project was arbitrary and
    capricious, particularly given the existence of a nearby
    alternative site they insist is better than the Minisink locale
    3
    green-lighted by FERC. They also assail some of the
    Commission’s procedural calls along the way. Though we
    respect the concerns they raise, we conclude that, as a legal
    matter, the Commission’s decisions were both reasonable and
    reasonably explained. Consequently, we deny the petitions
    for review.
    I.
    We begin with a quick overview of the regulatory
    framework, before turning to the particulars of these petitions.
    A.
    Congress enacted the Natural Gas Act, ch. 556, 52 Stat.
    821 (1938) (codified as amended at 15 U.S.C. §§ 717-717z),
    with the principal aim of “encourag[ing] the orderly
    development of plentiful supplies of . . . natural gas at
    reasonable prices,” NAACP v. Fed. Power Comm’n, 
    425 U.S. 662
    , 669-70 (1976), and “protect[ing] consumers against
    exploitation at the hands of natural gas companies,” Fed.
    Power Comm’n v. Hope Natural Gas Co., 
    320 U.S. 591
    , 610
    (1944). Along with those main objectives, there are also
    several “‘subsidiary purposes’” behind the NGA’s passage,
    “includ[ing] ‘conservation, environmental, and antitrust’
    issues.” Pub. Utils. Comm’n of Cal. v. FERC, 
    900 F.2d 269
    ,
    281 (D.C. Cir. 1990) (quoting 
    NAACP, 425 U.S. at 670
    &
    n.6).
    The Act vests FERC with broad authority to regulate the
    transportation and sale of natural gas in interstate commerce.
    15 U.S.C. §§ 717b, 717c; see also Schneidewind v. ANR
    Pipeline Co., 
    485 U.S. 293
    , 301 (1988) (“FERC exercises
    authority over the rates and facilities of natural gas companies
    used in [interstate] transportation and sale.”). To achieve this
    4
    objective, Congress equipped the Commission with a variety
    of regulatory tools, one of which captures the focus of our
    review today.
    Under Section 7(c) of the Act, before an applicant can
    construct or extend an interstate facility for the transportation
    of natural gas, it must obtain a “certificate of public
    convenience and necessity” from the Commission. 15 U.S.C.
    § 717f(c)(1)(A); Dominion Transmission, Inc. v. Summers,
    
    723 F.3d 238
    , 240 (D.C. Cir. 2013). The statute provides that
    a certificate “shall be issued to any qualified applicant” upon
    a finding that “the applicant is able and willing properly to do
    the acts and to perform the service proposed . . . and that the
    proposed service” and “construction . . . is or will be required
    by the present or future public convenience and necessity.”
    15 U.S.C. § 717f(e). FERC may, in issuing such a certificate,
    attach “such reasonable terms and conditions as the public
    convenience and necessity may require.” Id.; Murray Energy
    Corp. v. FERC, 
    629 F.3d 231
    , 234 (D.C. Cir. 2011).
    The Commission has issued a policy statement outlining
    the criteria it considers in reviewing such certificate
    applications. Certification of New Interstate Natural Gas
    Pipeline Facilities, 88 FERC ¶ 61,227 (Sept. 15, 1999),
    clarified, 90 FERC ¶ 61,128 (Feb. 9, 2000), further clarified,
    92 FERC ¶ 61,094 (July 28, 2000) (“Certificate Policy
    Statement”). The Commission will first confirm “whether the
    project can proceed without subsidies from the[] existing
    [pipeline’s] customers.” 
    Id., 88 FERC
    ¶ 61,227, at 61,745.
    Then, it will “balanc[e] the public benefits against the adverse
    effects of the project.” 
    Id., 90 FERC
    ¶ 61,128, at 61,396.
    FERC will approve a project only “where the public benefits
    of the project outweigh the project’s adverse impacts.” Id.;
    see also Fla. Gas Transmission Co. v. FERC, 
    604 F.3d 636
    ,
    649 (D.C. Cir. 2010) (Brown, J., concurring in part and
    5
    dissenting in part) (summarizing the factors examined under
    FERC’s Certificate Policy Statement). 1
    In conjunction with the certificating process, the
    Commission must also complete an environmental review of
    the proposed project, as mandated by the National
    Environmental Policy Act (NEPA), 42 U.S.C. §§ 4321-4370h.
    E.g., Midcoast Interstate Transmission, Inc. v. FERC, 
    198 F.3d 960
    , 967 (D.C. Cir. 2000).            Simply stated, the
    Commission’s NEPA obligation requires that it “‘identify the
    reasonable alternatives to the contemplated action’ and ‘look
    hard at the environmental effects of [its] decision[].’” 
    Id. (quoting Corridor
    H Alternatives, Inc. v. Slater, 
    166 F.3d 368
    ,
    374 (D.C. Cir. 1999)) (alterations in original).
    B.
    For    years,    Millennium      Pipeline     Company
    (“Millennium”) has owned and operated a natural gas pipeline
    system extending across much of New York’s southern
    border. In July 2011, seeking to expand its service capacity,
    Millennium applied to the Commission for a certificate of
    public convenience and necessity that would allow for the
    1
    The “public benefits” the Commission examines “could include,
    among other things, meeting unserved demand, eliminating
    bottlenecks, access to new supplies, lower costs to consumers,
    providing new interconnects that improve the interstate grid,
    providing competitive alternatives, increasing electric reliability, or
    advancing clean air objectives.” Certificate Policy Statement, 90
    FERC ¶ 61,128, at 61,396. On the other side of the scale, the
    potential “adverse effects” the Commission will consider are “the
    effects on existing customers of the applicant, the interests of
    existing pipelines and their captive customers, and the interests of
    landowners and the surrounding community, including
    environmental impacts.” 
    Id. 6 construction
    and operation of a natural gas compressor station
    along its existing pipeline. Joint Appendix (“J.A.”) 304-19.
    The proposed site for the project was located in the Town of
    Minisink, New York.
    As explained in its application to FERC, the aim of
    Millennium’s project was twofold. First, the new station
    would allow Millennium to increase natural gas deliveries to
    its eastern interconnection by about 225,000 additional
    dekatherms per day. Second, the compressor would enable
    bi-directional gas flow on an existing segment of
    Millennium’s pipeline. J.A. 305. The project’s footprint, as
    proposed by Millennium, would consist of: (a) two 6,130-
    horsepower natural gas-fired compressor units, to be housed
    in a newly built structure; (b) an additional 1,090 feet of pipe
    connecting the compressor station to the existing pipeline; (c)
    and several ancillary facilities, including a new mainline
    valve, an access driveway, a station control/auxiliary building,
    intake and exhaust silencers, and a filter-separator with a
    liquids tank. The compressor station was to be sited on a
    small part of a much larger, 73.4-acre parcel—a parcel
    acquired and owned by Millennium. See J.A. 305-07. We
    refer to Millennium’s proposal as the “Minisink Project.”
    Consistent with agency regulations, notice of the
    proposed Minisink Project was published in the Federal
    Register. See 76 Fed. Reg. 46,786 (Aug. 3, 2011). Around
    the same time, the Commission issued a “Notice of Intent to
    Prepare an Environmental Assessment,” which was sent to a
    range of interested stakeholders, including lawmakers,
    potentially affected landowners, and environmental and
    public-interest groups. In the months following, Millennium
    sponsored a community meeting at the Minisink Town Hall
    so that those interested could learn more about the proposal
    and voice their views. FERC also hosted its own meeting in
    7
    Minisink concerning the proposal. As might be expected, the
    Minisink Project sparked its fair share of local interest; during
    the review process, the Commission received hundreds of
    verbal and written comments. See J.A. 8-9.
    Most significantly for our purposes, several residents
    urged Millennium and the Commission to pursue a nearby
    alternative site for the compressor station—what came to be
    known as the “Wagoner Alternative.” Under the Wagoner
    Alternative, Millennium would construct a smaller, 5,100-
    horsepower compressor station directly adjacent to its existing
    Wagoner Meter Station, a site located along the pipeline about
    seven miles northwest of Minisink. J.A. 10-11. This
    alternative, its proponents insisted, was far better suited for
    the project, in large part because it was less residentially
    dense than the site proposed in Minisink. See, e.g., J.A. 347-
    50. But it came with a catch: Its implementation would
    require the replacement of a 7-mile segment of pipe along the
    pipeline—a segment the parties call the “Neversink Segment”
    due to its crossing of the Neversink River; according to
    Millennium, no such upgrade would be required by the
    Minisink Project. See J.A. 390-91. Reacting to commenters
    who were pushing the Wagoner Alternative, FERC sent
    notice to landowners within the vicinity of the Wagoner
    Meter Station site and along the Neversink Segment, inviting
    their input and comments on the concept. J.A. 372-74. The
    Commission incorporated the feedback it received into its
    review of Millennium’s proposal.
    FERC released its Environmental Assessment (“EA”) for
    the Minisink Project several months later. See J.A. 428-97.
    Along with its detailed evaluation of the project’s likely
    environmental impacts—on water resources, vegetation and
    wildlife, air quality and noise, and more—the EA also
    analyzed several alternatives to Millennium’s proposal,
    8
    including an in-depth comparison between the Minisink
    Project and the Wagoner Alternative. J.A. 474-89. The EA
    did identify some positive environmental upshots associated
    with the Wagoner Alternative, see J.A. 484-89, but, on
    balance, the assessment found that the Minisink Project was
    environmentally preferable, due principally to the negative
    environmental consequences that would flow from an upgrade
    of the Neversink Segment, J.A. 489 (“[T]he greater
    environmental issues and landowner impacts of replacing the
    Neversink Segment cause us to conclude that the Wagoner
    Alternative does not provide a significant environmental
    advantage over the proposed project.”). Overall, the EA
    concluded that, so long as Millennium implemented certain
    mitigation measures, the Minisink Project was expected to
    have no significant environmental impact. J.A 490-94.
    After receiving and reviewing a slew of comments
    concerning the EA, FERC ruled on Millennium’s application
    in July 2012. By a 3-2 majority, the Commission voted to
    issue a certificate of public convenience and necessity to
    Millennium, allowing the Minisink Project to move forward.
    Millennium Pipeline Co., L.L.C., Order Issuing Certificate,
    140 FERC ¶ 61,045 (July 17, 2012) (“Certificate Order”)
    (reprinted at J.A. 2-50).
    The Commission began its analysis by applying the
    criteria set forth in its Certificate Policy Statement, first
    finding the threshold factor satisfied—that the project would
    not require any subsidization from Millennium’s existing
    customers. Certificate Order, ¶¶ 11-12. From there, the
    Commission weighed the project’s benefits (increased
    capacity to customers in the high-demand northeast market,
    among others) against what FERC viewed as its “minimal
    adverse effect[s],” both market- and environmentally-focused.
    In the end, the Commission concluded that “the public
    9
    convenience and necessity require[d] approval of
    Millennium’s proposal,” subject to certain environmental
    conditions. 
    Id. ¶¶ 13-15.
    The Commission undertook an extensive environmental
    analysis in its order, leaning heavily on the results of the EA.
    With respect to the Wagoner Alternative, in particular, the
    Commission explained as follows:
    The EA evaluated several system and aboveground
    site alternatives, and thoroughly compared the
    Wagoner Alternative to Millennium’s proposed
    Minisink Compressor Station. . . . Ultimately, the EA
    concludes that although there are certain advantages to
    the Wagoner Alternative (primarily, its greater
    distance from the nearest noise-sensitive areas and the
    lack of residences within 0.5 mile of the compressor
    site), the greater environmental issues and landowner
    impacts of replacing the Neversink Segment outweigh
    those advantages, and as a whole result in the
    Wagoner Alternative not providing a significant
    environmental advantage over the proposed project.
    The Commission concurs with this assessment.
    Certificate Order, ¶¶ 26-27. More broadly, the Commission
    also addressed a variety of other comments touching on
    environmental and landowner-related issues. At the end of
    the day, FERC adopted the EA’s findings and concluded that,
    so long as Millennium adhered to the parameters outlined in
    its application and complied with certain environmental
    mitigation measures, the Minisink Project was expected to
    have no significant environmental impact. 
    Id. ¶ 83.
    The Commission’s order also resolved a few procedural
    matters that had been raised. First, the Commission denied a
    request for a full-blown evidentiary hearing for the Minisink
    10
    Project, concluding that the issues at stake could be
    adequately addressed on the written record. The Commission
    also denied a request to stay the proceedings due to a
    resident’s pending Freedom of Information Act (FOIA)
    request for documents from the Commission (generally
    seeking certain hydraulic analyses and systems models that
    Millennium submitted to FERC during the application
    process). 
    Id. ¶¶ 84-87.
    As noted, the Commission’s determination was not
    unanimous; the approval of Millennium’s application drew
    two dissenting votes. At bottom, both dissenters—Chairman
    Wellinghoff and Commissioner LaFleur—explained that, in
    their eyes, the Wagoner Alternative was a preferable
    alternative to the Minisink Project, and that the Commission
    was wrong to conclude otherwise. See J.A. 41-47. In
    addition, Commissioner Clark issued a separate concurrence,
    highlighting his view that, even if one truly thought the
    Wagoner Alternative wrought lesser environmental impacts
    than the Minisink Project, so long as Minisink was still
    considered “an acceptable site that produces minimal adverse
    impacts,” it should still be approved because FERC need not
    limit its approval to sites with “the minimum impact.” J.A. 48
    (second emphasis in original).
    Following the Commission’s approval, MREPS and
    others sought rehearing, and the Commission denied those
    requests through another thorough order.         Millennium
    Pipeline Co., L.L.C., Order Denying and Dismissing Requests
    for Rehearing, Denying Request to Reopen and Supplement
    the Record, and Denying Requests for Stay, 141 FERC ¶
    61,198 (Dec. 7, 2012) (“Reh’g Order”) (reprinted at J.A. 52-
    96).     Therein, after considering and rejecting various
    challenges to its initial decision, FERC reaffirmed its
    certificate approval for the Minisink Project. Additionally,
    11
    the Commission denied a request to reopen and supplement
    the record to include a study prepared by Mr. Richard
    Kuprewicz, who we are told is an “industry expert on pipeline
    engineering and safety.”       Pet’rs’ Br. at 22-23.      The
    Commission reached that result after determining that “Mr.
    Kuprewicz’s study provide[d] no basis for reversing [its]
    approval of the Minisink Project.” Reh’g Order, ¶¶ 75-80.
    Finally, FERC denied a request to stay construction on the
    Minisink Project pending judicial review. 
    Id. ¶¶ 81-83.
    2
    Chairman Wellinghoff and Commissioner LaFleur again
    dissented, jointly reiterating their view that the Wagoner
    Alternative still stood superior to the Minisink Project. See
    J.A. 95-96.
    In January 2013, Minisink resident Michael Mojica filed
    a separate request for rehearing with FERC, focusing on (1)
    the Commission’s refusal to reopen the record to consider Mr.
    Kuprewicz’s study, and (2) Mr. Mojica’s claimed inability to
    timely obtain information he believed necessary to oppose
    Millennium’s application (essentially the documents pursued
    via the aforementioned FOIA request). The Commission,
    joined this time by Chairman Wellinghoff and Commissioner
    LaFleur, unanimously denied the rehearing request.
    Millennium Pipeline Co, L.L.C., Order Denying Rehearing,
    142 FERC ¶ 61,077 (Jan. 31, 2013) (“Second Reh’g Order”)
    (reprinted at J.A. 99-106).
    2
    Before construction on the Minisink Project was complete,
    Petitioners twice sought emergency stays from this Court as well.
    On both occasions we denied their requests. In re Minisink
    Residents for Pres. of the Env’t and Safety, No. 12-1390 (D.C. Cir.
    Oct. 11, 2012) (denying motion for emergency relief); Minisink
    Residents for Envtl. Pres. and Safety v. FERC, No. 12-1481 (D.C.
    Cir. Mar. 5, 2013) (denying petition for stay during pendency of
    these proceedings).
    12
    Meanwhile, MREPS commenced proceedings before this
    Court. In December 2012, MREPS and some of its members
    filed a petition seeking review of the Commission’s
    Certificate Order and Rehearing Order (Case No. 12-1481).
    Then, after his individual rehearing request was denied by
    FERC, Mr. Mojica separately petitioned for our review (Case
    No. 13-1018). 3 Given the sweeping overlap of issues, we
    consolidated the two petitions. We refer to MREPS and the
    various individual petitioners, collectively, as “Petitioners.”
    While the briefing in these appeals unfolded, Millennium
    completed construction of the Minisink Project and placed the
    compressor station into use in June 2013.
    II.
    Petitioners seek review of a final order of the
    Commission, which means we have jurisdiction under 15
    U.S.C. § 717r(b). E.g., Murray Energy 
    Corp., 629 F.3d at 235
    ; Fla. Gas Transmission 
    Co., 604 F.3d at 639
    .
    We review the Commission’s orders, including those
    approving certificate applications, under the familiar arbitrary
    and capricious standard. B&J Oil & Gas v. FERC, 
    353 F.3d 71
    , 75-76 (D.C. Cir. 2004); Midcoast Interstate 
    Transmission, 198 F.3d at 967
    . Our role is limited “to assuring that the
    Commission’s decisionmaking is reasoned, principled, and
    3
    Originally, Mr. Mojica was also a party to the first-filed petition,
    but given the pendency of his rehearing request before FERC at that
    time, he withdrew from participation in the original case to avoid
    any problems under Tennessee Gas. See Tenn. Gas Pipeline Co. v.
    FERC, 
    9 F.3d 980
    , 980-81 (D.C. Cir. 1993) (“It is well-established
    that a party may not simultaneously seek both agency
    reconsideration and judicial review of an agency’s order.”).
    13
    based upon the record.” Am. Gas Ass’n v. FERC, 
    593 F.3d 14
    , 19 (D.C. Cir. 2010); Penn. Office of Consumer Advocate
    v. FERC, 
    131 F.3d 182
    , 185 (D.C. Cir. 1997). We must
    consider “whether the decision was based on a consideration
    of the relevant factors and whether there has been a clear error
    of judgment.” ExxonMobil Gas Mktg. Co. v. FERC, 
    297 F.3d 1071
    , 1083 (D.C. Cir. 2002). In so doing, we “cannot
    substitute [our] judgment for that of the Commission.” Nat’l
    Comm. for the New River, Inc. v. FERC, 
    373 F.3d 1323
    , 1327
    (D.C. Cir. 2004). All the while, we remain mindful that “[t]he
    grant[] or denial of a certificate of public convenience and
    necessity is a matter peculiarly within the discretion of the
    Commission.” Okla. Natural Gas Co. v. Fed. Power
    Comm’n, 
    257 F.2d 634
    , 639 (D.C. Cir. 1958); accord Cal.
    Gas Producers Ass’n v. Fed. Power Comm’n, 
    383 F.2d 645
    ,
    648 (9th Cir. 1967).
    *    *    *
    As a threshold matter, and even though neither FERC nor
    Millennium contests our power to entertain these petitions, we
    have independently assured ourselves that we are presented
    with a justiciable controversy. While the Minisink Project is
    now finished and functional, the petitions under review are
    not moot because Petitioners, through their written
    submissions to this Court and to the Commission, assert that
    the compressor’s operation continues to harm their aesthetic,
    health, and property interests. See Moreau v. FERC, 
    982 F.2d 556
    , 566 n.4 (D.C. Cir. 1993). For much the same reasons,
    we are satisfied that Petitioners have suffered injuries
    sufficient for Article III standing. 
    Id. at 565.
    With this much
    established, we turn to the merits of Petitioners’ arguments. 4
    4
    Our analysis on these points does not rest in any way on the
    online video submission referenced in Petitioners’ brief. See Pet’rs’
    14
    A.
    In urging us to upend FERC’s approval of the Minisink
    Project, Petitioners mount several lines of attack. Chief
    among them is their argument that the Commission failed to
    afford due consideration to the Wagoner Alternative, which
    Petitioners insist was undeniably superior to the Minisink
    Project—in their eyes, “economically, environmentally, and
    operationally” superior. See Pet’rs’ Br. at 6. Specifically,
    Petitioners claim that this alleged failure both violated the
    Commission’s obligations under Section 7 of the NGA, and
    represented a misapplication of the Commission’s own
    Certificate Policy Statement. We disagree.
    We do agree with Petitioners that the Commission was
    obligated to consider, as part of its certificating process under
    the NGA, reasonable alternatives to the project proposed by
    Br. at 5, 27-28. A picture may be worth a thousand words in some
    contexts, but extra-record video clips cannot substitute for proper
    briefing. Where a party’s standing is not apparent from the agency
    record, our rules require that “the brief . . . include arguments and
    evidence establishing the claim of standing.” D.C. CIRCUIT RULE
    28(a)(7) (emphasis added). Petitioners’ choice to use “Video
    Testimonials” skirts this requirement, and if adopted more broadly,
    could wreak havoc on the procedural controls governing appeals
    before this Court, such as word limits, briefing schedules, and the
    like. And this is without even considering the specific failings
    associated with Petitioners’ video account. For one, there is no
    indication that the individuals it portrays are under oath, so their
    remarks are not even evidence. Moreover, Petitioners do not direct
    us to any particular segment of the video they deem relevant,
    whether through a pinpoint citation or otherwise; instead, they
    expect us to review the entirety of the 18-minute recording—which,
    it bears noting, spans more time than their counsel was allotted at
    oral argument—to discern the elements of standing.
    15
    Millennium. See, e.g., N. Natural Gas Co. v. Fed. Power
    Comm’n, 
    399 F.2d 953
    , 973 (D.C. Cir. 1968) (“[T]he duty
    imposed upon the Commission by Section 7 of the Natural
    Gas Act is not merely to determine which of the submitted
    applications is most in the public interest, but also to give
    proper consideration to logical alternatives which might serve
    the public interest better than any of the projects outlined in
    the applications.”); accord Citizens for Allegan Cnty., Inc. v.
    Fed. Power Comm’n, 
    414 F.2d 1125
    , 1133 (D.C. Cir. 1969).
    The trouble with Petitioners’ theory, though, is that the
    Commission satisfied this obligation here. Based on our
    assessment of the record, we are convinced that the
    Commission amply considered alternatives to the Minisink
    Project, devoting especially thorough attention to the
    Wagoner Alternative favored by Petitioners.
    For one, FERC’s Certificate Order unmistakably outlines
    the Commission’s exploration of the Wagoner Alternative as
    an alternate possibility for Millennium’s compressor station.
    See Certificate Order, ¶ 26 (“Numerous comments received
    during scoping also requested that the Commission evaluate
    alternatives to the proposed action . . . . The EA evaluated
    several system and aboveground site alternatives, and
    thoroughly compared the Wagoner Alternative to
    Millennium’s proposed Minisink Compressor Station.”). In
    keeping with the recommendations set out in the EA,
    however, the Commission concluded that the more significant
    environmental impacts associated with the Wagoner
    Alternative—mostly due to improvement of the Neversink
    Segment—rendered that option less preferable than the
    proposed Minisink Project. 
    Id. ¶ 27
    (summarizing some of
    the perceived environmental downsides to the Wagoner
    16
    Alternative). 5 The same holds true with respect to the
    Rehearing Order, wherein the Commission again walked
    through its comparison of the Minisink Project and the
    Wagoner Alternative. Reh’g Order, ¶¶ 66-67. Based on that
    comparison, the Commission reiterated its view that “the
    selection of the Minisink [Project] as opposed to the Wagoner
    Alternative is eminently reasonable.” 
    Id. ¶ 67.
    Furthermore, Petitioners seem to overlook the fact that,
    once the Wagoner Alternative surfaced, the Commission took
    the additional (and, from what we understand, relatively
    unusual) step of issuing a supplemental notice before
    completing its Environmental Assessment. Therein, the
    Commission specifically flagged its consideration of the
    Wagoner Alternative, inviting feedback and input from
    nearby residents and other potentially impacted parties. See
    J.A. 372-74; J.A. 373 (“The Commission wants to ensure that
    5
    For instance, the Commission explained as follows:
    • The Wagoner Alternative would impact ten times more
    land acreage (112.4) than the Minisink Project (10.6);
    •   The Wagoner Alternative would require the clearing of
    more trees and the conscription of more agricultural
    land than the Minisink Project;
    •   The Wagoner Alternative would necessitate the
    placement of pipeline across eleven wetlands and
    twelve waterbodies, raising complications not extant in
    the Minisink Project; and
    •   The Wagoner Alternative had the potential to impact
    five special status species, as opposed to one through
    the Minisink Project.
    Certificate Order, ¶¶ 26-27. FERC’s Certificate Order also
    incorporated the EA itself, which goes through its own relatively
    detailed comparison between the two proposals. See J.A. 484-89.
    17
    all potentially affected landowners for the [Wagoner]
    alternative have the opportunity to participate in the
    environmental review process. . . . You are encouraged to
    become involved in this process and provide your specific
    comments or concerns about Millennium’s proposal and the
    [Wagoner] alternative described above.”) In view of all of
    this, it seems clear that FERC duly considered the Wagoner
    Alternative (and other alternatives), and cogently explained its
    rationale in finding the Minisink Project properly approved
    under the NGA. We would be hard-pressed to read the record
    otherwise.
    In arguing to the contrary, Petitioners marshal only one
    meaningful theory in their favor. They claim that the
    Commission’s analysis was flawed because Millennium either
    planned or needed to upgrade the Neversink Segment all
    along. In other words, according to Petitioners, even if
    Millennium moved forward with the Minisink Project (and
    not the Wagoner Alternative), it still had plans to replace the
    Neversink Segment in the very near future.             So the
    Commission’s decision to account for the environmental
    impacts of a Neversink upgrade only in connection with the
    Wagoner Alternative and not the Minisink Project, Petitioners
    tell us, was unreasonable and misguided. E.g., Pet’rs’ Br. at
    32 (“Had the Commission compared a Minisink/Neversink
    project to a Wagoner/Neversink upgrade, the Wagoner
    alternative would have emerged as the superior choice.”). We
    reject their premise.
    This argument effectively hinges on an ambiguous
    reference in one PowerPoint slide that Petitioners uncovered
    through an internet search in the midst of the agency
    proceedings—a document Petitioners generously refer to as
    18
    the “Currie Report.” 6 This document, Petitioners surmise,
    proves that the construction of a new compressor station at
    Minisink was only Millennium’s first step in a multi-phase
    expansion project, part of which was destined to include a
    Neversink upgrade all along. Notably, Petitioners made this
    very same argument to the Commission, and the Commission
    found it unsubstantiated. Rather, the Commission read the
    “Currie Report” as “merely . . . a marketing document,” and
    found that, as a factual matter, it did not evince “an intent by
    Millennium to pursue an integrated, three-phase expansion of
    its system,” nor “any firm decision by Millennium as to future
    construction,” as had been suggested. Reh’g Order, ¶ 32
    n.41. As to this factual determination, FERC’s findings are
    “conclusive” if “supported by substantial evidence,” 15
    U.S.C. § 717r(b); Colo. Interstate Gas Co. v. FERC, 
    599 F.3d 698
    , 704 (D.C. Cir. 2010)—a standard, we have stated, that
    “requires more than a scintilla, but can be satisfied by
    something less than a preponderance of the evidence,” FPL
    Energy Me. Hydro LLC v. FERC, 
    287 F.3d 1151
    , 1160 (D.C.
    Cir. 2002). On this record, the Commission’s finding falls
    comfortably within that range. We thus accept FERC’s
    conclusion that the “Currie Report” does not establish any
    firm present or future plans by Millennium to upgrade the
    Neversink Segment. 7
    6
    Although never clearly explained, Petitioners seem to call this the
    “Currie Report” because they believe the PowerPoint presentation
    was prepared by an individual named Sean Currie, who is identified
    in at least one FERC filing as Millennium’s Manager of Capacity
    Optimization. See J.A. 126 n.77.
    7
    Petitioners say we should accord FERC’s factual findings no
    deference because it was “biased” in favor of Millennium’s
    application. See Pet’rs’ Br. at 7, 41. In support, Petitioners point
    to an excerpted portion of FERC’s Rehearing Order stating, in part,
    that “there is no incentive for a project sponsor to present an
    application that cannot meet our standards for approval.” Pet’rs’
    19
    In making this argument, Petitioners lean heavily on our
    decision in City of Pittsburgh v. Federal Power Commission,
    
    237 F.2d 741
    (D.C. Cir. 1956). But that decision cannot bear
    the weight Petitioners wish. In City of Pittsburgh, we
    reviewed the issuance of a certificate of public convenience
    and necessity allowing a natural gas supplier to abandon
    service on one pipeline and to transfer that load to another
    pipeline operating below capacity. In the course of contesting
    the Commission’s order, a group of petitioners argued that the
    abandonment would result in rate increases associated with
    future expansions—increases that could be avoided, those
    petitioners said, if the supplier maintained service on the
    pipeline it sought to abandon. After review, this Court set
    aside the order, largely based on the Commission’s failure to
    consider the effects of abandonment on the pipeline’s future
    expansion. 
    Id. at 750
    (“[The Commission] persistently closed
    its eyes even to the existence of the problem of future
    expansion.”). Seizing on that holding, Petitioners insist it
    Br. at 7 (quoting Reh’g Order, at ¶ 45) (emphasis by Petitioners).
    We could see how these remarks might give Petitioners pause.
    After reading that applicants have “no incentive” to pursue
    proposals that cannot secure approval, it is conceivable that one
    might come away thinking the Commission has a thumb on the
    scale for industry applicants. This is hardly the image our federal
    regulators should be projecting to the American public. But as
    another recent decision from this Court explained in turning aside a
    similar argument, “[t]he fact that [applicants] generally succeed in
    choosing to expend their resources on applications that serve their
    own financial interests does not mean that an agency which
    recognizes merit in such applications is biased.” NO Gas Pipeline
    v. FERC, No. 12-1470, slip op. at 10 (D.C. Cir. July 1, 2014). This
    logic holds true here, too. Though FERC’s comments were
    arguably clumsy, it would require quite a leap on our part to equate
    its statements with prejudgment.
    20
    applies equally to the facts of their case because FERC
    glossed over and ignored the possibility of a future Neversink
    Segment replacement. For at least two reasons we can see,
    however, City of Pittsburgh finds no application here.
    First, in City of Pittsburgh, it was clear and unmistakable
    that the pipeline intended to expand service in the future. See
    
    id. at 751
    (“That Texas Eastern would soon move to expand
    its gas deliveries was apparent throughout the [Commission’s]
    proceeding.”); 
    id. at 752
    (“The record amply shows Texas
    Eastern’s intention to apply for authority to expand its
    capacity and its sales.”). Here, on the other hand, the
    Commission examined the record—including the so-called
    “Currie Report”—and found no concrete indication that
    Millennium intended, then or in the future, to upgrade the
    Neversink Segment. So the evidence of “future expansion” is
    a far cry from what we were presented with in City of
    Pittsburgh. Second, and perhaps more fundamentally, the
    shortcoming we took issue with in City of Pittsburgh was the
    Commission’s refusal to examine the effects of future
    expansion altogether; the hearing examiner would not permit
    any questioning or inquiry into the supplier’s plans for
    expansion, nor would the examiner consider several company
    memoranda that supposedly revealed such plans. 
    Id. at 750
    -
    52. Here, in stark contrast, FERC unquestionably did
    consider Petitioners’ theory that Millennium planned (or
    needed) to upgrade the Neversink Segment. See Certificate
    Order, ¶¶ 65, 68; Reh’g Order, ¶¶ 25, 32-33, 47, 73 & n.41.
    It just disagreed with their position that the prospect of such a
    step was sufficiently certain to require its environmental
    effects be taken into account in connection with the Minisink
    Project. Given this, we cannot say that the Commission
    “closed its eyes” to the issue of “future expansion”—here, the
    possible replacement of the Neversink Segment—as was the
    case in City of 
    Pittsburgh. 237 F.2d at 750-52
    .
    21
    Given the foregoing, we have no basis to second-guess
    the Commission’s determination that Millennium had no firm
    plans to upgrade the Neversink Segment in the wake of the
    Minisink Project. Petitioners also press this argument with a
    slightly different gloss, however. They argue that even if
    Millennium was not planning to replace the Neversink
    Segment, circumstances would soon require such a step
    nonetheless. Absent such an upgrade, Petitioners assert, a
    “bottleneck” caused by the smaller-diameter pipe on the
    Neversink Segment would preclude Millennium’s pipeline
    from safely handling the volume, pressure, and speed that
    would be generated by the Minisink Project. (For the most
    part, this theory relies on the aforementioned study prepared
    by Mr. Kuprewicz.) We remain unmoved. The Commission
    considered this argument, too, and based on its assessment of
    the evidence, it again disagreed with Petitioners on the facts.
    FERC found no evidence that the Minisink Project would
    necessitate, as a structural or safety matter, an upgrade of the
    Neversink Segment. See Certificate Order, ¶ 68 (“Staff
    independently evaluated the hydraulic feasibility of the
    Minisink Compressor Station and completed an engineering
    analysis of Millennium’s pipeline system . . . . [T]here is
    nothing in the record to suggest that the operation of the
    Minisink Compressor Station will compromise the safety of
    the Neversink Segment.”); see also Reh’g Order, ¶¶ 75-80
    (summarizing “flaws” in Mr. Kuprewicz’s various
    suppositions, as viewed by FERC). As we explain shortly,
    the Commission’s decision not to reopen the record to
    consider Mr. Kuprewicz’s report was not an abuse of
    discretion, and Petitioners provide no other meaningful basis
    for concluding that FERC’s factual determinations regarding
    the pipeline’s structural integrity were unsupported by
    22
    substantial evidence. We thus find no basis to upset the
    Commission’s finding on this point either. 8
    In our view, then, FERC reasonably concluded that the
    Wagoner Alternative would require replacement of the
    Neversink Segment, while the same was not plainly true of
    the Minisink Project. And with that factual determination in
    hand, it comes as no great shock that the Commission did not
    believe the Wagoner Alternative a better fit for the proposed
    project. On this point, some historical context is in order.
    More than a decade before the Minisink Project was
    proposed, Millennium had sought approval from FERC to
    construct a replacement pipeline for the original Neversink
    Segment. Initially, the Commission approved that proposal
    subject to certain conditions. Millennium Pipeline Co., L.P.,
    Interim Order, 97 FERC ¶ 61,292, at 62,356 (Dec. 19, 2001).
    But due to the extreme difficulty Millennium encountered
    trying to satisfy those conditions—including a host of
    environmental snags—it opted instead to rely on the existing
    7.1-mile-long segment of pipe acquired from a competitor
    (Columbia Gas) for the Neversink River crossing, i.e., the
    “Neversink Segment” as it exists today. See J.A. 401-05
    (describing this background).        FERC authorized that
    8
    We also find it somewhat telling that neither of the dissenting
    commissioners expressed a belief that a Neversink upgrade was
    imminently inevitable. True, both thought a Neversink replacement
    would have yielded longer-term benefits that would have
    outweighed the positive environmental factors the majority
    associated with the Minisink Project (nearly all tied to avoiding, at
    least for the time being, a Neversink upgrade). And mostly for this
    reason, they believed the Wagoner Alternative preferable in the
    long run. But neither suggested that the record, as they saw it,
    showed that Millennium planned or needed to replace the
    Neversink Segment even if it did not pursue the Wagoner
    Alternative, as Petitioners maintain. See J.A. 41-47, 95-96, 106.
    23
    alternative arrangement in 2006. See Millennium Pipeline
    Co., L.L.C., Order Issuing and Amending Certificates,
    Approving Abandonment, Vacating Certificate, and Granting
    and Denying Requests for Rehearing and Clarification, 117
    FERC ¶ 61,319, at 62,576 (Dec. 21, 2006).          Given
    Millennium’s past struggles navigating the environmental
    complications of a Neversink upgrade, the fact that the
    Commission did not think such a course preferable at this
    juncture seems to us an understandable result.
    In sum, as we have stated before, FERC “enjoys broad
    discretion to invoke its expertise in balancing competing
    interests and drawing administrative lines.” Am. Gas 
    Ass’n, 593 F.3d at 19
    (citing ExxonMobil Gas Mktg. 
    Co., 297 F.3d at 1085
    ); see also Columbia Gas Transmission Corp. v. FERC,
    
    750 F.2d 105
    , 112 (D.C. Cir. 1984) (“[A]s an expert agency,
    the Commission is vested with wide discretion to balance
    competing equities against the backdrop of the public
    interest[.]”).  Notwithstanding Petitioners’ pleas to the
    contrary, we conclude that the Commission’s consideration of
    the Wagoner Alternative falls within the bounds of that
    discretion. 9 Under our narrow standard of review, then, we
    9
    We hasten to add that FERC’s obligation to consider alternatives
    in Section 7 proceedings is not boundless. As we have previously
    explained, FERC need not “undertake exhausting inquiries, probing
    for every possible alternative, if no viable alternatives have been
    suggested by the parties, or suggest themselves to the agency.”
    Citizens for Allegan 
    Cnty., 414 F.2d at 1133
    . We do not suggest
    otherwise today, nor must we venture beyond these general
    guideposts. Since the Wagoner Alternative was so fervently
    advocated for during the Minisink Project’s review process, all
    agree that the Commission was obligated to at least consider it.
    24
    have no basis to upset the Commission’s application of its
    Section 7 authority on this point. 10
    B.
    Along with their weighty reliance on the Wagoner
    Alternative, Petitioners make several other arguments against
    the reasonableness of the Commission’s analysis. We treat
    each argument in turn, finding none persuasive.
    1.
    Petitioners claim that the Commission failed to give the
    environmental impacts of the Minisink Project the “hard
    look” NEPA requires. We conclude otherwise.
    NEPA’s “hard look” doctrine is designed “to ensure that
    the agency has adequately considered and disclosed the
    environmental impact of its actions and that its decision is not
    arbitrary or capricious.” Nat’l Comm. for the New 
    River, 373 F.3d at 1327
    . NEPA is a procedural statute; it “‘does not
    mandate particular results, but simply prescribes the necessary
    10
    On the other side of the “public benefits”/“adverse impacts”
    scale, Petitioners appear to separately argue that FERC violated its
    policy statement by relying on Millennium’s existing contracts with
    gas transporters to demonstrate the public benefits of the Minisink
    Project. Pet’rs’ Br. at 35. We reject that claim as well. Petitioners
    identify nothing in the policy statement or in any precedent
    construing it to suggest that it requires, rather than permits, the
    Commission to assess a project’s benefits by looking beyond the
    market need reflected by the applicant’s existing contracts with
    shippers. To the contrary, the policy statement specifically
    recognizes that such agreements “always will be important
    evidence of demand for a project.” Certificate Policy Statement, 88
    FERC ¶ 61,227, at 61,748.
    25
    process.’” Midcoast Interstate 
    Transmission, 198 F.3d at 967
    (quoting Robertson v. Methow Valley Citizens Council, 
    490 U.S. 332
    , 350 (1989)). In reviewing an agency’s compliance
    with NEPA, the “rule of reason applies,” and we “consistently
    decline[] to ‘flyspeck’ an agency’s environmental analysis.”
    Theodore Roosevelt Conservation P’ship v. Salazar, 
    661 F.3d 66
    , 75 (D.C. Cir. 2011) (quoting Nevada v. U.S. Dep’t of
    Energy, 
    457 F.3d 78
    , 93 (D.C. Cir. 2006)).
    Petitioners claim to eschew a flyspecking approach here,
    arguing instead that the Commission’s analysis is laden with
    “gaping holes.” Pet’rs’ Br. at 41. They point to three. In our
    view, though, all fall decidedly more into the “flyspecking”
    camp than anything more.
    First, Petitioners contend that the Commission erred in
    failing to undertake a more fulsome cost-benefit analysis of
    the Minisink Project as compared with the Wagoner
    Alternative. This argument essentially piggybacks off their
    overall Wagoner Alternative theory, and, in that sense, we
    reject it for the reasons already stated. In our view, the
    Commission reasonably assessed the Wagoner Alternative,
    particularly with respect to its environmental implications, as
    most concerns NEPA. See Found. on Econ. Trends v.
    Heckler, 
    756 F.2d 143
    , 147 (D.C. Cir. 1985) (“NEPA’s dual
    mission is . . . to generate federal attention to environmental
    concerns and to reveal that federal consideration for public
    scrutiny.”) (emphasis added). Otherwise, to the extent
    Petitioners contend that the Commission should have focused
    more generally on the monetary costs and benefits of the
    respective proposals, we disagree that NEPA requires such an
    approach, particularly where only an environmental
    assessment, rather than an environment impact statement, is
    involved. See Webster v. U.S. Dep’t of Agric., 
    685 F.3d 411
    ,
    430 (4th Cir. 2012) (“The agency does not,” under NEPA,
    26
    “need to display the weighing of the merits and drawbacks of
    the alternatives in a monetary cost-benefit analysis.”);
    Communities Against Runway Expansion, Inc. v. FAA, 
    355 F.3d 678
    , 687 (D.C. Cir. 2004) (“[I]t is undisputed that the
    FAA was not required to undertake a formal cost-benefit
    analysis as part of the [environmental impact statement].”).
    Second, Petitioners argue that the Commission failed to
    examine the Minisink Project’s impact on property values.
    But as the Commission rightly rejoins, the EA clearly
    addressed this issue. J.A. 457-58. It recognized there may be
    some adverse impacts on surrounding property values due to
    the compressor station.      On balance, though, the EA
    concluded that “the recommended building design and
    landscaping plans would eventually minimize the visual
    impact from the station on the surrounding residential
    properties and would not significantly reduce property values
    or resale values.” J.A. 458. The Commission’s order echoes
    this general assessment. Certificate Order, ¶ 70 (“[W]e
    believe that the visual and noise mitigation measures
    recommended in the EA and included as conditions in this
    order, will mitigate the potential for decreases in property
    values.”). Though we can see how Petitioners may disagree
    with this takeaway, their disagreement does not mean that
    FERC failed to consider the issue altogether, as they suggest.
    Third, Petitioners claim that the Commission failed to
    assess cumulative and future impacts. They accuse FERC of
    ignoring two issues in particular: (1) Millennium’s planned
    development of a second compressor station on the pipeline
    upstream from Minisink (what came to be the “Hancock
    Project”), and (2) the potential construction of a lateral
    pipeline from the Minisink compressor to a proposed power
    plant operated by CPV Valley LLC. The record belies this
    argument on both scores. As for the Hancock Project, the
    27
    EA’s “Cumulative Impacts” discussion flags Millennium’s
    “intent to construct a second compressor station” and explains
    that, because no certificate application had been filed with
    FERC, little was known about the details of the project.
    Nevertheless, given the “typical distances between
    compressor stations (70 miles) and the difference in
    construction timing,” the EA stated that no significant
    cumulative impacts were expected, other than possibly with
    respect to air quality. J.A. 473. In view of the uncertainty
    surrounding the second compressor station, and the difference
    in timing between the two projects, this discussion suffices
    under NEPA. 11 The same holds true with respect to the
    11
    We disagree with Petitioners that the EA’s treatment of the
    “Hancock Project” contravenes this Court’s decision in Delaware
    Riverkeeper, see Pet’rs’ 28(j) Letter (June 16, 2014), which held
    that FERC improperly segmented and failed to consider the
    cumulative impacts of four “connected, contemporaneous, closely
    related, and interdependent” projects. Del. Riverkeeper Network v.
    FERC, 
    753 F.3d 1304
    , 1307 (D.C. Cir. 2014). In faulting the
    Commission’s NEPA analysis of the cumulative impacts of the
    “Northeast Project” under review there, that decision took pains to
    emphasize that the other three projects were all “either under
    construction or were also pending before the Commission for
    environmental review and approval.” 
    Id. at 1308;
    see also 
    id. (“FERC’s NEPA
    review . . . did not consider any of the other
    upgrade projects, even though the first upgrade project was under
    construction during FERC’s review . . . and even though the
    applications for the second and fourth upgrade projects were
    pending before FERC[.]”); 
    id. at 1318
    (“The temporal nexus here is
    clear. Tennessee Gas proposed the Northeast Project while the 300
    Line Project was under construction . . . . [a]nd FERC’s
    consideration of the Northeast Project application overlapped with
    its consideration of the remaining two projects . . . . We emphasize
    here the importance we place on the timing of the four
    improvement projects.”). Those critical facts are worlds apart from
    this case. At the time of its application for the Minisink Project,
    28
    potential development of the CPV Valley power plant. The
    EA’s “Cumulative Impacts” section identifies this possible
    project, too, though it again signals the absence of any firm
    details surrounding project specifics. Even still, the EA
    concluded that because the Minisink Project itself was
    expected to have minimal impacts, no significant cumulative
    impacts were expected to flow from the possible development
    of the CPV Valley power plant, particularly since the
    construction timelines for the two potential projects would be
    quite distinct. J.A. 473-74. In sum, based on our review of
    the EA, we are satisfied that FERC properly considered the
    cumulative impacts of the Minisink Project.
    2.
    Petitioners also assert that the Commission’s approval of
    the Minisink Project contravenes its own siting guidelines.
    We can quickly dispatch these arguments.
    Among its NEPA-implementing regulations, FERC has
    promulgated “[s]iting and maintenance requirements” for the
    construction and upkeep of facilities. 18 C.F.R. § 380.15.
    Petitioners think that the Minisink Project contravenes three
    separate provisions of that regulation. We think not. We first
    agree with the Commission that § 380.15(b) is inapplicable
    Millennium had not yet applied for approval of the Hancock
    Project, nor was construction on either project underway.
    Furthermore, once plans for the Hancock Project were cemented
    and presented to FERC for approval under Section 7, the
    Commission did examine that project alongside the Minisink
    Project (then in the midst of development), and the resulting EA
    found no significant cumulative impacts associated with the two
    projects. See Millennium Pipeline Co., L.L.C., Order Issuing
    Certificate, 145 FERC ¶ 61,007, at ¶ 52 (Oct. 1, 2013). For at least
    these reasons, Delaware Riverkeeper lends no help to Petitioners.
    29
    altogether because, by its terms, it is triggered only by
    facilities constructed on third-party landowners’ property;
    here, as FERC noted below, Reh’g Order, ¶ 3, the Minisink
    Project was built on a parcel owned entirely by Millennium.
    While the parties also disagree whether § 380.15(e) (formerly
    § 380.15(d)) 12 applies to a project involving the construction
    of a compressor station, we need not decide that issue because
    FERC nevertheless complied with the regulation’s directive to
    consider the use or extension of existing rights-of-way.
    Indeed, the Commission explicitly recognized its policy of
    “encourag[ing] pipeline construction on existing right[s]-of-
    way as a means of minimizing environmental disturbance,”
    but it concluded that any such preference does not alone
    provide a basis for rejecting an application that otherwise
    yields limited environmental impacts. Reh’g Order, ¶ 37.
    This leaves only § 380.15(g) (formerly § 380.15(f)),
    which applies to the “[c]onstruction of aboveground
    facilities.” On this point, Petitioners claim that the Minisink
    site is not “unobtrusive,” but, in fleshing out that contention,
    they argue simply that the Wagoner Alternative would have
    been less so. We remain unconvinced by that approach. And
    otherwise, we agree with the Commission that it implemented
    appropriate mitigation measures to reduce the site’s potential
    obtrusiveness.     See Reh’g Order, ¶ 50 (summarizing
    Millennium’s vegetation plans and noise mitigation
    requirements to reduce obtrusiveness); 
    id. at ¶¶
    57-59
    (outlining Commission’s approval of building design and
    12
    After the completion of briefing in these cases, FERC amended
    this regulation, adding a new subsection (c) and reconfiguring the
    existing provisions. As a consequence, the parties’ briefs discuss
    §§ 380.15(d) and (f), which have since been re-designated as §§
    380.15(e) and (g), respectively. See 78 Fed. Reg. 72,794, 72,812-
    13 (Dec. 4, 2013). For clarity’s sake, we refer to the regulation
    using its current numbering.
    30
    Millennium’s agreement with Town of Minisink concerning
    landscaping and screening plan for site). Particularly in view
    of the deference owed FERC’s interpretation of its own
    regulations, see City of Oconto Falls, Wis. v. FERC, 
    204 F.3d 1154
    , 1162 (D.C. Cir. 2000), we reject Petitioners’ argument
    that the Minisink Project violates the siting guidelines.
    C.
    As a final offensive, Petitioners attribute several
    procedural errors to the Commission’s handling of
    Millennium’s application for the Minisink Project. We take
    these arguments in turn, accepting none.
    First, Petitioners declare that the Commission improperly
    refused to hold an evidentiary hearing on Millennium’s
    application. “FERC’s choice whether to hold an evidentiary
    hearing is generally discretionary.” Blumenthal v. FERC, 
    613 F.3d 1142
    , 1144 (D.C. Cir. 2010). “In general, FERC must
    hold an evidentiary hearing only when a genuine issue of
    material fact exists, and even then, FERC need not conduct
    such a hearing if [the disputed issues] may be adequately
    resolved on the written record.” Cajun Elec. Power Coop.,
    Inc. v. FERC, 
    28 F.3d 173
    , 177 (D.C. Cir. 1994) (internal
    citations and quotation marks omitted) (alteration in original).
    We review the Commission’s denial of a hearing request for
    abuse of discretion. Woolen Mill Assocs. v. FERC, 
    917 F.2d 589
    , 592 (D.C. Cir. 1990). Petitioners assert that a hearing
    would have resolved “several key factual disputes,” but when
    push comes to shove, they point to only one—“the question of
    Millennium’s intentions regarding the Neversink upgrade.”
    Pet’rs’ Br. at 53. Of course, the Commission did resolve that
    issue, it just did so on the written record, declining to interpret
    the “Currie Report” as the smoking-gun evidence Petitioners
    portrayed it to be, Reh’g Order, ¶ 32 n.41, and otherwise
    31
    finding that Millennium had no firm present or future
    intention to replace the Neversink Segment, 
    id. ¶ 47.
    From
    FERC’s perspective, there was no need to convene an
    evidentiary hearing to resolve this narrow issue. We perceive
    no abuse of discretion in that determination. 13
    Second, Petitioners complain that their due process rights
    were violated because the Commission failed to timely
    provide them with certain documentation during the
    proceedings—namely, particular hydraulic studies and
    engineering analyses that Millennium provided to FERC as
    part of its application. Petitioners concede, however, that
    MREPS and some of its individual members obtained these
    documents before the deadline to file for rehearing (indeed at
    least one petitioner who requested this information in March
    2012 received access to it at least two months before petitions
    for rehearing were due). Oral Arg. Recording at 38:41-39:08;
    see also Reh’g Order, ¶¶ 70-71. There is no dispute, then,
    13
    We note that, during the agency proceedings, Millennium
    represented that it had “no intention to file an application to replace
    the Neversink Segment before 2014.” Reh’g Order, ¶ 47 (quoting
    “Millennium’s December 9, 2011 Data Response No. 1,” reprinted
    at J.A. 367-70). Given that we have since hit that 2014 marker, we
    asked Millennium’s counsel at oral argument whether the
    company’s intentions had changed. Counsel assured us they had
    not. We were told Millennium still had no present plans to replace
    the Neversink Segment. Although such an upgrade remains a
    possibility down the road if demand eventually dictates, counsel
    relayed, Millennium could and would look to other options as well.
    Oral Arg. Recording at 31:05-31:40, 34:30-34:39. Of course, our
    review is based on the record as it existed before the Commission at
    the time of its decision, see CNG Transmission Corp. v. FERC, 
    40 F.3d 1289
    , 1295 (D.C. Cir. 1994), but we would potentially be
    facing a more troublesome set of facts if Millennium now planned
    to pursue a Neversink upgrade after all. Because we take counsel at
    his word, we confront no such scenario here.
    32
    that Petitioners had the chance to make meaningful use of this
    information in connection with their petitions for rehearing.
    Under our precedent, this fact neutralizes any constitutional
    claim under the Due Process Clause. See 
    Blumenthal, 613 F.3d at 1145-46
    ; see also Jepsen v. FERC, 420 F. App’x 1, 2
    (D.C. Cir. 2011) (per curiam). Relatedly, to the extent
    Petitioners assert that other potentially relevant documents
    were improperly withheld as confidential, the contention that
    such documents “‘might’ support [their] position [is] far too
    speculative to provide a basis for setting aside FERC’s
    judgment,” B&J 
    Oil, 353 F.3d at 78
    , much less for finding a
    due process violation.
    Third, Petitioners fault the Commission for failing to
    reopen the record to consider the “Kuprewicz Report.” We
    review that decision “only for an abuse of discretion,” Cooley
    v. FERC, 
    843 F.2d 1464
    , 1473 (D.C. Cir. 1988), and we find
    none here. Of course, FERC did consider the report, at least
    in a sense. True, the Commission declined to reopen the
    record and revisit its prior findings based on Mr. Kuprewicz’s
    findings. But in the course of so concluding, the Commission
    undertook an analysis of his report and opinions. Reh’g
    Order, ¶¶ 75-80. In the end, the Commission believed his
    analysis “suffer[ed] from several flaws” and did not provide
    support for his position on many points, particularly where his
    assessment differed from that of FERC’s staff. 
    Id. ¶¶ 76,
    79;
    Second Reh’g Order, ¶ 9. The Commission thus found that
    “Mr. Kuprewicz’s study provides no basis for reversing [its]
    approval of the Minisink Project.” Reh’g Order, ¶ 80. This
    decision strikes us as well within the bounds of FERC’s
    discretion, particularly given the highly technical nature of the
    issues raised in the report. See NRG Power Mktg., LLC v.
    FERC, 
    718 F.3d 947
    , 962 (D.C. Cir. 2013). Consequently,
    we find no error in the Commission’s declining to reopen the
    record based on Mr. Kuprewicz’s report.
    33
    III.
    In approving the Minisink Project, the Commission
    accorded the Wagoner Alternative the serious consideration it
    was due, in keeping with its statutory obligations under the
    NGA and NEPA. In its judgment, the Commission did not
    think the Wagoner Alternative preferable and concluded that
    the Minisink Project, as put forward by Millennium, would
    serve the public interest and necessity. We are simply not
    empowered to second-guess the Commission’s determination
    on this point or to substitute our judgment for the
    Commission’s. Our much more limited role is, instead, to
    confirm that FERC thoroughly and reasonably examined the
    issue, and on the record before us, we are assured that it did.
    For this and the other reasons we have explained, the
    petitions for review are denied.
    So ordered.
    

Document Info

Docket Number: 12-1481, 13-1018

Citation Numbers: 412 U.S. App. D.C. 97, 762 F.3d 97, 180 Oil & Gas Rep. 1118, 44 Envtl. L. Rep. (Envtl. Law Inst.) 20190, 2014 WL 3973124, 79 ERC (BNA) 1513, 2014 U.S. App. LEXIS 15672

Judges: Kavanaugh, Millett, Wilkins

Filed Date: 8/15/2014

Precedential Status: Precedential

Modified Date: 11/5/2024

Authorities (30)

Schneidewind v. ANR Pipeline Co. , 108 S. Ct. 1145 ( 1988 )

cajun-electric-power-cooperative-inc-v-federal-energy-regulatory , 28 F.3d 173 ( 1994 )

Commty Agnst Runway v. FAA , 355 F.3d 678 ( 2004 )

Theodore Roosevelt Conservation Partnership v. Salazar , 661 F.3d 66 ( 2011 )

Midcoast Interstate Transmission, Inc. v. Federal Energy ... , 198 F.3d 960 ( 2000 )

city-of-pittsburgh-chotin-towing-corporation-and-greenville-towing , 237 F.2d 741 ( 1956 )

National Committee for the New River, Inc. v. Federal ... , 373 F.3d 1323 ( 2004 )

Corridor H Alternatives, Inc. v. Slater , 166 F.3d 368 ( 1999 )

Pennsylvania Office of Consumer Advocate v. Federal Energy ... , 131 F.3d 182 ( 1997 )

foundation-on-economic-trends-v-margaret-m-heckler-secretary-of-the , 756 F.2d 143 ( 1985 )

northern-natural-gas-company-and-northern-natural-gas-transportation , 399 F.2d 953 ( 1968 )

Columbia Gas Transmission Corporation v. Federal Energy ... , 750 F.2d 105 ( 1984 )

B&J Oil & Gas v. Federal Energy Regulatory Commission , 353 F.3d 71 ( 2004 )

Oklahoma Natural Gas Company v. Federal Power Commission, ... , 257 F.2d 634 ( 1958 )

Colorado Interstate Gas Co. v. Federal Energy Regulatory ... , 599 F.3d 698 ( 2010 )

california-gas-producers-association-independent-oil-and-gas-producers-of , 383 F.2d 645 ( 1967 )

city-of-ocon-to-falls-wisconsin-v-federal-energy-regulatory-commission , 204 F.3d 1154 ( 2000 )

Cng Transmission Corporation v. Federal Energy Regulatory ... , 40 F.3d 1289 ( 1994 )

Citizens for Allegan County, Inc. v. Federal Power ... , 414 F.2d 1125 ( 1969 )

woolen-mill-associates-v-federal-energy-regulatory-commission-burlington , 917 F.2d 589 ( 1990 )

View All Authorities »