PPL Wallingford Energy LLC v. Federal Energy Regulatory Commission , 419 F.3d 1194 ( 2005 )


Menu:
  • United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued April 18, 2005                   Decided August 9, 2005
    No. 03-1292
    PPL WALLINGFORD ENERGY LLC AND
    PPL ENERGYPLUS, LLC,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    MASSACHUSETTS MUNICIPAL WHOLESALE ELECTRIC
    COMPANY, ET AL.,
    INTERVENORS
    Consolidated with
    04-1062
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    John Longstreth argued the cause for petitioners. With him
    on the briefs were Donald A. Kaplan and Sandra E. Rizzo.
    David H. Coffman, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on the
    2
    brief were Cynthia A. Marlette, General Counsel, and Dennis
    Lane, Solicitor.
    Before: GINSBURG, Chief Judge, and HENDERSON and
    GARLAND, Circuit Judges.
    Opinion for the Court filed by Circuit Judge GARLAND.
    GARLAND, Circuit Judge: This case raises the question of
    whether FERC’s rejection of a PPL–ISO-NE RMR agreement
    covering CTs in a NEPOOL DCA violates the APA because
    FERC ignored PPL’s objections to FERC’s PUSH and LMP
    assumptions.1 We conclude that it does. For those not fluent in
    the language of FERC, a translation follows.
    I
    Petitioners PPL Wallingford Energy, LLC and PPL
    EnergyPlus, LLC (collectively, “PPL”) challenge orders of the
    Federal Energy Regulatory Commission (FERC) that rejected
    PPL’s agreement with ISO New England, Inc. (ISO-NE) to
    provide electric power on a cost-of-service basis. PPL also
    challenges FERC orders rejecting similar agreements between
    Devon Power, LLC and ISO New England. Because PPL was
    not a party to the latter agreements, it lacks standing to challenge
    the orders that relate to them. PPL does have standing to
    challenge the orders rejecting its own agreement, however, and
    we conclude that those orders violate the Administrative
    Procedure Act (APA). We therefore vacate the orders relating
    to PPL and remand the case to the Commission for further
    proceedings.
    1
    See FERC Br. at x (“Glossary”).
    3
    II
    The Federal Power Act gives FERC jurisdiction over the
    transmission and sale of electric energy at wholesale in interstate
    commerce. See 
    16 U.S.C. § 824
    (b)(1). The Act requires public
    utilities to file schedules with FERC showing, among other
    things, the rates they will charge for the transmission or sale of
    energy. 
    Id.
     § 824d(c). If, after a hearing, FERC “find[s] that
    any rate . . . collected by any public utility for any transmission
    or sale subject to [its] jurisdiction . . . is unjust, unreasonable,
    unduly discriminatory or preferential, the Commission shall
    determine the just and reasonable rate . . . and shall fix the same
    by order.” Id. § 824e(a).
    ISO New England, Inc. is an “independent system
    operator” that runs the New England electricity market, known
    as the New England Power Pool (NEPOOL). See New England
    Power Pool, 79 F.E.R.C. ¶ 61,374 (1997), order on reh’g, 85
    F.E.R.C. ¶ 61,242 (1998). It acts as a middleman, matching bids
    (offers to sell power) by generators with requests from
    customers. See New England Power Pool & ISO New England,
    Inc., 100 F.E.R.C. ¶ 61,287, at 62,261, order on reh’g, 101
    F.E.R.C. ¶ 61,344 (2002), order on reh’g, 103 F.E.R.C. ¶
    61,304, order on reh’g, 105 F.E.R.C. ¶ 61,211 (2003).
    In 2002, FERC proposed the creation of “standard market
    designs” (SMDs) to standardize the sale of electric power, with
    the goal of creating “‘seamless’ wholesale power markets that
    allow sellers to transact easily across transmission grid
    boundaries and that allow customers to receive the benefits of
    lower-cost and more reliable electric supply.” Remedying
    Undue Discrimination Through Open Access Transmission
    Service & Standard Electricity Market Design, Notice of
    Proposed Rulemaking, 100 F.E.R.C. ¶ 61,138, ¶ 9 (2002). In
    response to FERC’s proposal, ISO New England, along with the
    4
    NEPOOL Participants Committee, submitted an SMD for the
    New England region. FERC approved the SMD, with certain
    modifications not relevant here. See New England Power Pool,
    100 F.E.R.C. ¶ 61,287.
    In “chronically constrained” regions identified as
    “Designated Congestion Areas” (DCAs), the New England
    SMD created a complex system of compensation for generators
    under what was known as Market Rule 1. See id. at 62,262.
    First, the SMD attempted price reduction -- “mitigation” in
    FERC parlance -- by setting a price cap “based on the estimated
    price to recover the annual cost of a new combustion turbine
    unit (CT) for the region over the number of hours it is expected
    to operate during the year.” Devon Power LLC, 103 F.E.R.C. ¶
    61,082, at 61,267 n.3 (2003). This estimated price was known
    as the “CT Proxy.” Id. Second, to mitigate the impact of
    mitigation, under certain circumstances the SMD allowed the
    highest bid accepted in a particular area to set the price, called
    the “Locational Marginal Price” (LMP), for all bids accepted in
    that area. See New England Power Pool, 100 F.E.R.C. ¶ 61,287,
    at 62,271.
    To further soften the impact of mitigation, the SMD also
    allowed certain seldom-used generator units needed to assure
    system reliability to “be classified as Reliability-Must-Run
    (RMR) units.” These are units that “must be run” -- i.e., that
    ISO New England can compel to run -- “during certain periods
    to alleviate transmission congestion.” Id. at 62,262. This
    designation entitled the generator to apply for an “RMR Cost-of-
    Service Agreement” if the unit could not recover its costs under
    the CT Proxy mechanism and would otherwise be shut down.
    Id. at 62,263. An RMR agreement provides monthly payments
    to enable the unit to recover its costs plus a reasonable return on
    investment. See PSEG Power Connecticut, LLC, 110 F.E.R.C.
    ¶ 61,020, ¶ 30 (2005). In its order upholding the SMD, 
    FERC
                   5
    confirmed that “ISO-NE has the authority to negotiate individual
    RMR agreements as are required to maintain and/or improve
    system reliability.” New England Power Pool, 100 F.E.R.C. ¶
    61,287, at 62,268. FERC further stated that “such agreements
    are to be filed with the Commission in accordance with the
    Commission’s rules and regulations, and, as such, may be
    subject to the review of the Commission.” 
    Id.
    PPL built a generating station consisting of five natural gas
    combustion turbines in the southwest Connecticut DCA, from
    which it began selling power in December 2001. The units were
    relatively high-cost “peaking” units, intended to run only during
    times of peak demand or system need. On January 16, 2003,
    PPL submitted a request for FERC approval of an RMR
    agreement negotiated with ISO New England to cover four of
    the five units. While the RMR request was pending, PPL filed
    an application with ISO New England to temporarily deactivate
    the four units for economic reasons.             The deactivation
    application was denied, on the ground that the units were
    necessary for reliability purposes, and PPL was required to
    continue operating the units regardless of economic
    considerations. In February 2003, Devon Power, LLC and three
    affiliated entities (collectively, “Devon”) submitted a similar
    request for FERC approval of four RMR agreements for their
    Connecticut units.
    FERC ruled on Devon’s RMR request first, denying it in an
    April 25 order that significantly changed the existing
    compensation scheme. First, it found that “RMR contracts
    suppress market-clearing prices, increase uplift payments, and
    make it difficult for new generators to profitably enter the
    market,” and that “extensive use of RMR contracts undermines
    effective market performance.” Devon Power LLC, 103
    F.E.R.C. ¶ 61,082, at 61,270 (2003) (Devon Order). Fearing
    that it would face a proliferation of RMR agreements, the
    6
    Commission held that such agreements “should be a last resort.”
    
    Id.
     Second, FERC decided to revise Market Rule 1, pursuant to
    Section 206 of the Federal Power Act, 16 U.S.C. § 824e. Id. at
    61,271. The revision entailed the elimination of the CT Proxy
    standard, because “[u]nits that produce energy in substantially
    fewer hours, such as the [Devon] units, are not likely to be able
    to recover all of their fixed costs under the current CT Proxy.”
    Id.
    In place of CT Proxy, FERC adopted a new methodology
    called Peaking Unit Safe Harbor (PUSH) bidding. Id. at 61,274.
    The PUSH methodology gave a generator that had operated at
    ten percent or less of capacity during 2002 a “safe harbor” bid
    price based on the sum of its units’ variable-cost and fixed-cost
    components. The fixed-cost component for 2003 was calculated
    by dividing a unit’s annual fixed costs (including a reasonable
    return on investment) by the number of megawatt hours the unit
    supplied in 2002. The PUSH price would therefore allow the
    generator to recover its costs in 2003 if the generator ran for the
    same number of hours (and had the same costs) as it did in 2002.
    The goal of PUSH bidding was “to provide a market mechanism
    for high cost, seldom run units to recover their fixed costs.” Id.
    FERC maintained that replacing RMR agreements with PUSH
    bidding “changed only the form in which [generators] will be
    able to recover their fixed and variable costs, i.e., use of a safe
    harbor bid within the market rather than an RMR contract.” Id.
    FERC further decided that the revised “Market Rule shall
    provide that the energy bids of peaking units are eligible to
    determine LMP” -- which meant that those units’ PUSH bids
    could set the LMP, thereby serving as the sales price for all
    power sold in the area during the time period. Id.
    FERC declared that it would “direct ISO-NE to make
    compliance filings to reflect these changes in Market Rule 1.”
    Id. The changes were only intended, however, as a temporary
    7
    solution. As initially contemplated, they were to last until June
    1, 2004, when a new system, called LICAP, would be
    implemented. Id. FERC has since pushed back LICAP’s
    implementation date to the beginning of 2006. Devon Power
    LLC, 110 F.E.R.C. ¶ 61,315, ¶ 27 (2005).
    In response to the Devon Order, many industry members
    submitted requests for rehearing and clarification. Devon Power
    Co., 104 F.E.R.C. ¶ 61,123, at 61,414 (2003) (Devon Order on
    Reh’g). PPL was among the industry intervenors. Rejecting the
    intervenors’ arguments to the contrary, FERC maintained that
    “the PUSH bid mechanism gives a generator a reasonable
    opportunity to recover its costs.” Id. at 61,416.
    On May 16, 2003, FERC rejected PPL’s own RMR
    agreement “[o]n the basis of the rationale developed in Devon.”
    PPL Wallingford Energy LLC, 103 F.E.R.C. ¶ 61,185, at 61,716
    (2003). RMR agreements, FERC said, could be used only as a
    “last resort,” and consequently PPL would have to rely on the
    new PUSH system for compensation. Id. PPL requested
    rehearing and clarification, contending (inter alia) that the PUSH
    mechanism denied it a reasonable opportunity to recover its
    costs. See PPL Wallingford Energy LLC, 105 F.E.R.C. ¶
    61,324, at 62,522-23 (2003). FERC denied PPL’s requests for
    rehearing and clarification, again relying on the Devon orders.
    Id. PPL now petitions for review of FERC’s orders in both the
    Devon and PPL proceedings.
    III
    Before we address PPL’s substantive claims, we must
    consider whether it has standing to challenge the FERC orders
    that it has asked us to review. The Federal Power Act provides
    that “[a]ny party to a proceeding . . . aggrieved by an order
    issued by the Commission in such proceeding may obtain a
    8
    review of such order” in this court. 16 U.S.C. § 825l(b). A
    party is “aggrieved” if it satisfies the usual constitutional and
    prudential standing requirements, which include a showing of
    concrete, redressable injury. See, e.g., Wabash Valley Power
    Ass’n, Inc. v. FERC, 
    268 F.3d 1105
    , 1112 (D.C. Cir. 2001).
    There is no doubt that PPL has suffered an injury from, and
    therefore has standing to challenge, the orders that rejected its
    own RMR agreement. The injury is illusory, however, in the
    context of the orders that rejected the Devon agreements --
    agreements to which PPL was not a party.
    PPL admits that it does not seek to reverse FERC’s denial
    of the Devon agreements. See Pet’rs Reply Br. at 8 n.7. Rather,
    it wishes only to challenge the reasoning of the Devon orders as
    later applied to deny its own agreement. See Oral Arg. Tape at
    12:19-12:40. But PPL is free to challenge that reasoning in the
    context of the denial of its agreement, regardless of whether the
    reasoning became agency precedent in another case. See Shell
    Oil Co. v. FERC, 
    47 F.3d 1186
    , 1203 (D.C. Cir. 1995). Indeed,
    that is the challenge we consider in Part IV. As a consequence,
    PPL suffers no injury from its inability to challenge the orders
    denying the Devon agreements. See Oral Arg. Tape at 12:19-
    12:40 (concession by PPL counsel that, if PPL is allowed to
    attack the Devon rationale in its own proceeding, it is not
    “aggrieved in any way by not being able to challenge what
    happened to Devon”); cf. Sea-Land Serv., Inc. v. DOT, 
    137 F.3d 640
    , 648 (D.C. Cir. 1998) (“[M]ere precedential effect within an
    agency is not, alone, enough to create Article III standing, no
    matter how foreseeable the future litigation.”). Accordingly,
    PPL lacks standing to challenge the Devon orders.
    IV
    We now turn to PPL’s contention that the orders denying its
    RMR agreement violated the Administrative Procedure Act
    9
    because they are “arbitrary, capricious, an abuse of discretion,
    or otherwise not in accordance with law.” 
    5 U.S.C. § 706
    (2)(A).
    To survive review under the “arbitrary and capricious” standard,
    an agency must “examine the relevant data and articulate a
    satisfactory explanation for its action including a ‘rational
    connection between the facts found and the choice made.’”
    Motor Vehicle Mfrs. Ass’n of the United States, Inc. v. State
    Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983) (quoting
    Burlington Truck Lines, Inc. v. United States, 
    371 U.S. 156
    , 168
    (1962)). An agency’s “failure to respond meaningfully” to
    objections raised by a party renders its decision arbitrary and
    capricious. Canadian Ass’n of Petroleum Producers v. FERC,
    
    254 F.3d 289
    , 299 (D.C. Cir. 2001); see Public Serv. Comm’n v.
    FERC, 
    397 F.3d 1004
    , 1008 (D.C. Cir. 2005). We have stressed
    that “[u]nless the [agency] answers objections that on their face
    seem legitimate, its decision can hardly be classified as
    reasoned.” Canadian Ass’n, 
    254 F.3d at 299
    ; see Tesoro Alaska
    Petroleum Co. v. FERC, 
    234 F.3d 1286
    , 1294 (D.C. Cir. 2000).
    In rejecting PPL’s proposed RMR agreement, the
    Commission said it was acting on “the basis of the rationale
    developed in Devon, and [in accordance] with the market
    modifications made in that order.” PPL Wallingford Energy
    LLC, 103 F.E.R.C. ¶ 61,185, at 61,716. One of the premises of
    Devon was that the new methodology it announced, PUSH
    bidding, would provide “a generator a reasonable opportunity to
    recover its costs.” Devon Order on Reh’g, 104 F.E.R.C. ¶
    61,123, at 61,416. Indeed, a goal of PUSH bidding was “to
    provide a market mechanism for high cost, seldom run units to
    recover their fixed costs.” Devon Order, 103 F.E.R.C. ¶ 61,082,
    at 61,271. In its pleadings before the Commission, PPL
    challenged that premise by attacking two of its underlying
    assumptions, as well as FERC’s alleged failure to honor its
    commitment to permit RMR agreements as a last resort.
    10
    FERC’s orders failed “to respond meaningfully,” Canadian
    Ass’n, 
    254 F.3d at 299
    , to PPL’s three objections.2
    First, in concluding that an eligible unit could recover its
    costs under PUSH bidding, FERC relied on the fact that the
    PUSH bid price was based on the sum of the unit’s variable
    costs and fixed costs, and that the latter was calculated by
    dividing the unit’s fixed costs by the number of megawatt hours
    it supplied in 2002. Thus, a unit that ran as often in 2003 as in
    2002 could recover all of its costs. PPL, however, challenged
    the assumption that its units would indeed run as often in 2003
    as they had in 2002, pointing out that rising natural gas prices
    (and hence increased generation prices) would reduce demand
    for PPL’s gas-fired generators. Pet. for Reh’g at 7-9 (June 16,
    2003). In particular, PPL argued that the sixty percent increase
    in gas prices between 2002 and 2003 would permit non-gas-
    fired units to compete more effectively against it, and that PPL’s
    units would therefore run for fewer hours. Id. at 9.
    FERC failed to respond directly to PPL’s point about the
    change in gas prices and the consequent reduction in run hours.
    Instead, the Commission simply asserted that PPL had failed to
    suggest an alternative to PUSH methodology. In fact, PPL did
    suggest several alternatives, including continued use of RMR
    agreements, at least when PUSH bidding resulted in under-
    recovery of costs. See Pet. for Reh’g at 28-31 (listing proposed
    modifications of PUSH bidding). Moreover, it was not PPL’s
    burden to present alternatives; it was the Commission’s burden
    to prove the reasonableness of its change in methodology. See
    Atlantic City Elec. Co. v. FERC, 
    295 F.3d 1
    , 10 (D.C. Cir.
    2002). “In order to make any change in an existing rate or
    practice” under section 206 of the Federal Power Act, “
    FERC 2
    Because that failure is sufficient to require vacatur of the PPL
    orders, we have no occasion to consider PPL’s other challenges.
    11
    must first prove that the existing rates or practices are ‘unjust,
    unreasonable, unduly discriminatory or preferential.’ . . . Then
    FERC must show that its proposed changes are just and
    reasonable.” 
    Id. at 10
     (quoting 16 U.S.C. § 824e(a)).
    Second, in further support of its conclusion that the PUSH
    mechanism would provide seldom-used units with an
    opportunity to recover their costs, FERC relied on the
    assumption that “the energy bids of peaking units” would be
    “eligible to determine LMP.” Devon Order, 103 F.E.R.C. ¶
    61,082, at 61,271. This meant that all generating units in the
    region would receive the highest accepted PUSH price for their
    power, and hence that it was possible for a unit to receive
    substantially more than its own PUSH bid. Thus, to the extent
    that the LMP was set by older, more expensive generators than
    PPL’s, PPL could recover revenues higher than its costs even if
    its units operated for fewer hours in 2003 than 2002. In FERC’s
    view, there was thus an “equal risk that eligible units may under-
    recover or over-recover their costs.” Devon Order on Reh’g,
    104 F.E.R.C. ¶ 61,123, at 61,423.
    PPL, however, pointed out that FERC’s assumption
    regarding LMP was in error. ISO New England, it noted, had
    “confirmed that it does not intend to allow PUSH eligible units
    operating at their low operating limits to set LMP.” Pet. for
    Reh’g at 32; see id. at 7-8 & n.17. And if PUSH bids could not
    set the LMP, there was no support for FERC’s premise that the
    risk of under-recovery was balanced by the possibility of over-
    recovery. FERC failed to respond to this objection in any way.
    Finally, FERC had said in Devon that it would permit the
    use of RMR agreements as a “last resort” when PUSH bidding
    would not permit a generator to recover its costs. PPL
    contended that it met the “last resort” standard, id. at 5, and as
    evidence it submitted an expert study showing that PUSH
    12
    bidding would permit the PPL units to recover only thirty
    percent of their fixed costs, id. at 7, Attach. A.3 Once again,
    FERC’s orders contained no response. Indeed, they did not
    address PPL’s evidence at all. In light of the Commission’s
    failure to “answer[] objections that on their face seem
    legitimate, its decision can hardly be classified as reasoned.”
    Canadian Ass’n, 
    254 F.3d at 299
    .
    V
    Although we dismiss for lack of standing PPL’s petition
    challenging the Devon orders, we grant PPL’s petition to review
    the orders rejecting its own proposed agreement, vacate those
    orders as arbitrary and capricious, and remand the case for
    further proceedings consistent with this opinion.
    So ordered.
    3
    This analysis was confirmed by a report filed by ISO New
    England prior to the date FERC issued its PPL decision. The report
    found that PUSH bidders recovered only about thirty-five percent of
    their fixed costs under the PUSH system. See ISO New England, Inc.,
    A Review of Peaking Unit Safe Harbor (PUSH) Implementation and
    Results 1, 29 (Dec. 4, 2003) (J.A. 361, 389). FERC contends that we
    should not consider the ISO report because it was filed only in the
    Devon docket. Because we find the PPL orders arbitrary and
    capricious without reference to the ISO report, we need not decide
    whether the fact that it was filed it in a different, albeit closely related,
    docket removes it from our purview.