Sierra Club v. FERC ( 2022 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued January 19, 2022                Decided June 28, 2022
    No. 20-1427
    SIERRA CLUB, ET AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    MOUNTAIN VALLEY PIPELINE, LLC AND PUBLIC SERVICE
    COMPANY OF NORTH CAROLINA, D/B/A DOMINION ENERGY
    NORTH CAROLINA,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Benjamin A. Luckett argued the cause for petitioners. With
    him on the briefs was Elizabeth F. Benson.
    Matthew W.S. Estes, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. On the brief
    were Matthew R. Christiansen, General Counsel, Robert H.
    Solomon, Solicitor, and Anand R. Viswanathan, Attorney.
    2
    Jeremy C. Marwell argued the cause for respondent-
    intervenors Mountain Valley Pipeline, LLC and Public Service
    Company of North Carolina, Inc. With him on the brief were
    Matthew Eggerding, Matthew X. Etchemendy, James T.
    Dawson, Charlotte Taylor, Stephen Petrany, and James Olson.
    Before: SRINIVASAN, Chief Judge, WILKINS and WALKER,
    Circuit Judges.
    Opinion for the Court filed by Circuit Judge WILKINS.
    WILKINS, Circuit Judge. Petitioners, all environmental
    organizations, seek to vacate the Federal Energy and
    Regulatory Commission’s (“FERC” or the “Commission”)
    order giving the green light to Mountain Valley, LLC to
    construct a new pipeline. That pipeline, the “Southgate
    Project,” would extend Mountain Valley’s Mainline System
    Project, connecting its terminus in Virginia to facilities in
    North Carolina. Its “newness,” as an extension of the non-
    operational Mainline System Project, is one of the prime
    subjects of dispute. Petitioners also request that we vacate the
    Commission’s denial of rehearing.
    Petitioners challenge the Commission’s Certificate Order
    and its denial of rehearing as arbitrary and capricious on two
    bases: the approved return on equity rate and the adequacy of
    the Commission’s Environmental Impact Statement. Because
    the Commission’s decisions on both scores were reasonable
    and supported by substantial evidence, we deny the petition for
    review.
    I.
    The Natural Gas Act, 
    52 Stat. 821
     (1938) (codified as
    amended at 
    15 U.S.C. §§ 717
    –717z) empowers the
    3
    Commission to regulate the interstate transportation and sale of
    natural gas. Under Section 7 of the Act, a natural gas company
    cannot construct gas transportation facilities or extend its
    currently operational facilities without first obtaining a
    certificate of public convenience and necessity from the
    Commission. 15 U.S.C. § 717f(c)(1)(A). The Commission
    will issue a certificate if it finds that the service “is or will be
    required by the present or future public convenience and
    necessity.” Id. § 717f(e). The applicant must also be “able and
    willing properly to do the acts and to perform the service
    proposed and to conform to” the Act’s provisions as well as the
    Commission’s rules and regulations. Id.
    The Commission will approve a pipeline’s proposed rate
    of sale as long as it is “just and reasonable.” Id. § 717c(a). If,
    however, the company is proposing a newly certificated
    service, the Commission will apply the less exacting “public
    interest” standard, under Section 7, to set the initial rate a
    pipeline can charge. Missouri Pub. Serv. Comm’n v. FERC,
    
    337 F.3d 1066
    , 1068 (D.C. Cir. 2003). Such a rate “hold[s] the
    line” until the Commission can engage in more extensive
    ratemaking proceedings under Sections 4 and 5 of the Act
    down the road. Gulf South Pipeline Co. v. FERC, 
    955 F.3d 1001
    , 1005 (D.C. Cir. 2020) (quoting Atl. Ref. Co. v. Pub. Serv.
    Comm’n of State of NY, 
    360 U.S. 378
    , 391–92 (1959)).
    Prior to approving a certificate on a proposed pipeline, the
    National Environmental Policy Act (“NEPA”) requires the
    Commission to evaluate the action’s environmental impacts. If
    the agency finds that the action is likely to significantly impact
    the environment, it must draft an environmental impact
    statement (“EIS”), detailing the action’s environmental
    impacts, potential mitigation methods, the action’s cumulative
    impacts, and reasonable alternatives to the action, including a
    no-action alternative. 
    40 C.F.R. §§ 1502.14
    , 1502.16,
    4
    1501.3(a)(3). NEPA requires agencies to “take a ‘hard look’ at
    the environmental consequences before taking a major action.”
    Baltimore Gas & Elec. Co., Inc., 
    462 U.S. 87
    , 97 (1983).
    II.
    The Mainline System Project has been plagued with issues
    since construction commenced in February 2018. Mountain
    Valley had planned for Mainline to consist of a new 303.5-
    mile-long pipeline from Wetzel County, West Virginia to an
    interconnection with a compressor station in Pittsylvania
    County, Virginia. Following a series of adverse rulings from
    the Fourth Circuit, construction on the Mainline System has
    proceeded in fits and starts, culminating in a stop-work order
    in October 2019. As of June 2020, construction along the
    project’s right-of-way was 92% complete.
    Despite Mainline’s setbacks, on November 6, 2018,
    Mountain Valley filed an application with the Commission for
    the Southgate Project, which would connect the Mainline
    System’s terminus in Pittsylvania County, Virginia to
    Dominion Energy’s local facilities in Rockingham and
    Alamance Counties, North Carolina. Consisting of 75.1 miles
    of an underground natural gas transmission pipeline system,
    the pipeline would have the capacity to transport 375 million
    cubic feet of gas per day. Final EIS Executive Summary-1–2.
    Mountain Valley cites the project as necessary to meet the
    needs of Dominion Energy, its anchor shipper,1 which has
    pressed for additional natural gas transportation services in the
    1
    An anchor shipper is “one or a very few shippers with very large,
    significant volumes of natural gas that will financially support the
    initial design and cost of a project.” Regulations Governing the Open
    Season for Alaska Natural Gas Transportation Projects, 
    110 FERC ¶ 61,095
    , ¶ 12 n.8 (2005).
    5
    region. 
    Id.
     at Executive Summary-1. Petitioners jointly filed a
    protest in opposition to the project.
    On June 18, 2020, the Commission issued a certificate of
    public convenience and necessity, approving Mountain
    Valley’s application to build and operate the Southgate Project.
    See Mountain Valley Pipeline, LLC, 
    171 FERC ¶ 61,232
     (2020)
    (“Certificate Order”). Just over two months later, on August
    20, 2020, it denied Petitioners’ request for a rehearing.
    Mountain Valley Pipeline, LLC, 
    172 FERC ¶ 62,100
     (2020)
    (“Rehearing Order”). Particularly relevant to Petitioners’
    claims, the Commission approved Mountain Valley’s
    requested initial rate of return on equity at 14 percent, rather
    than the typical 10.55 percent, because “[w]ithout cash flows
    from existing operations and a proven track record,”
    Southgate’s capital funding outlook more closely resembled
    that of a new pipeline than an extension of an operational one.
    Certificate Order, ¶ 57. As for the project’s environmental
    impacts, the Commission noted that the EIS had fleshed out
    specific practices to mitigate erosion as well as sedimentation,
    and evaluated the cumulative impacts arising from its temporal
    and geographic proximity to the Mainline System. Id. ¶¶ 75,
    93, 141; Rehearing Order, ¶¶ 28–31. Commissioner (now
    Chairman) Glick partially dissented from the Commission’s
    Certificate Order, opposing the 14 percent return on equity rate
    and the failure to address the project’s greenhouse gas effects.
    Certificate Order, ¶¶ 1–23 (Glick, Comm’r, dissenting).
    In October 2020, Petitioners filed a petition for our
    review.2 They urge us to vacate and remand the Commission’s
    2
    The Public Service Company of North Carolina, Monacan Indian
    Nation, Sappony Tribe, and Mountain Valley Pipeline filed motions
    to intervene in the appeal, all of which were granted. See Clerk’s
    Order (Dec. 9, 2020). The Monacan Indian Nation and Sappony
    Tribe later moved to withdraw as intervenors in August 2021, after
    6
    Certificate Order of June 18, 2020, as well as its order of
    August 20, 2020, denying Petitioners’ request for rehearing.
    III.
    Our jurisdiction over this appeal is secure under the
    Natural Gas Act. See 15 U.S.C. § 717r(b). The Act vests this
    Court with exclusive jurisdiction to review an objection to a
    Commission order so long as “such objection . . . [has] been
    urged before the Commission in the application for rehearing.”
    Id. Petitioners have satisfied this exhaustion requirement—
    they present the same arguments on appeal as set forth in their
    rehearing request. See J.A. 763 (objecting to return on equity
    rate); J.A. 764 (adequacy of mitigation measures); J.A. 764–65
    (consideration of cumulative impacts). We are similarly
    assured that Petitioners have met their burden of establishing
    Article III standing.3 That being settled, we turn to the merits.
    they reached an agreement with the Southgate Project’s developer.
    Their motion to withdraw was granted. See Clerk’s Order (Sept. 3,
    2021).
    3
    To establish associational standing to sue on their members’ behalf,
    as Petitioners seek to do here, they must show: “(1) at least one of its
    members would have standing to sue in his or her own right; (2) the
    interests it seeks to protect are germane to the organization’s
    purpose; and (3) neither the claim asserted nor the relief requested
    requires the participation of individual members in the lawsuit.”
    Sierra Club v. FERC, 
    827 F.3d 59
    , 65 (D.C. Cir. 2016) (internal
    quotation marks and citations omitted). To meet the first prong,
    Petitioners must demonstrate that: “(1) at least one of its members
    has suffered an injury-in-fact that is concrete and particularized and
    actual or imminent, not conjectural or hypothetical; (2) the injury is
    fairly traceable to the challenged action; and (3) it is likely, as
    opposed to merely speculative, that the injury will be redressed by a
    favorable decision.” 
    Id.
     (internal quotation marks and citations
    omitted). We are satisfied that Petitioners have met this burden here.
    7
    IV.
    We will review both Petitioners’ Natural Gas Act and
    NEPA claims under the arbitrary and capricious standard.
    Marsh v. Oregon Nat. Res. Council, 
    490 U.S. 360
    , 378 (1989)
    (Natural Gas Act); Minisink Residents for Envtl. Pres. & Safety
    v. FERC, 
    762 F.3d 97
    , 106 (D.C. Cir. 2014) (NEPA). In doing
    so, we ask whether “the Commission’s judgment is supported
    by substantial evidence and that the methodology used in
    arriving at that judgment is either consistent with past practice
    or adequately justified.” Emera Maine v. FERC, 
    854 F.3d 9
    ,
    22 (D.C. Cir. 2017) (quoting Town of Norwood, Mass. v.
    FERC, 
    80 F.3d 526
    , 533 (D.C. Cir. 1996)). And while the
    Court cannot review an agency’s environmental analysis to
    “second-guess substantive decisions committed to the
    discretion of the agency,” it is clear that “simple, conclusory
    statements of no impact are not enough to fulfill an agency’s
    duty under NEPA.” Delaware Riverkeeper Network v. FERC,
    
    753 F.3d 1304
    , 1313 (D.C. Cir. 2014) (internal quotation marks
    and citation omitted). An arbitrary and capricious agency
    action in the NEPA context is one that “is not the product of
    reasoned decisionmaking.” Id. at 1313 (internal quotation
    marks and citation omitted).
    A.
    In setting “just and reasonable rates” for interstate
    pipelines under the Natural Gas Act, the Commission must
    Sierra Club and Appalachian Voices Member Margaret Whitehead
    attested that the project would traverse her property, thereby
    permanently reducing her tree farm area and threatening a small lake.
    See Add. 74–75. A favorable decision by this Court, halting
    construction on the pipeline, would remedy this stated injury.
    8
    balance the interests of the pipeline and its ratepayers. COST-
    OF-SERVICE RATES MANUAL, 
    FERC 1
     (1999). To do so, the
    Commission typically conducts “cost-of-service ratemaking,”
    meaning that it sets a rate “based on a pipeline’s cost of
    providing service including an opportunity for the pipeline to
    earn a reasonable return on its investment.” 
    Id.
     This rate is
    also referred to as the “recourse rate.”4 But the Commission
    also allows pipeline companies to charge “negotiated rates,”
    which permit a pipeline to forgo cost-of-service rates with an
    individual shipper. Alternatives to Traditional Cost-of-Service
    Ratemaking for Natural Gas Pipelines, 
    74 FERC ¶ 61,076
    ,
    ¶¶ 61,224–25 (1996).
    Zooming in further, the rate of return is made up of two
    principal components: return on equity and return on debt.
    Sierra Club v. FERC, 
    867 F.3d 1357
    , 1376 (D.C. Cir. 2017).
    The return on equity is “the cost to the utility of raising capital.”
    Emera Maine, 854 F.3d at 20 (internal quotation marks and
    citations omitted). Because equity investment is riskier than
    debt investment, equity investors usually earn a higher rate of
    return than debt investors. Sierra Club, 867 F.3d at 1376. If
    the pipeline is greatly indebted, its equity investors take on
    more risk and therefore will expect a higher rate of return, and
    vice versa. Id. at 1377. Typically, “greenfield” or new
    pipelines take on more risk and will accordingly be rewarded
    with higher rates of return. PennEast Pipeline Co., 
    162 FERC ¶ 61,053
    , ¶ 59 (2018).
    4
    The Commission defines a recourse rate as a “cost-of-service based
    rate for natural gas pipeline service that is on file in a pipeline’s tariff
    and is available to customers who do not negotiate a rate with the
    pipeline company.”           Glossary, FERC (Aug. 31, 2020),
    https://www.ferc.gov/about/what-ferc/about/glossary#:~:text=class
    %20of%20customers.-,Recourse%20Rate,rate%20with%20the%20
    pipeline%20company.
    9
    Here, Mountain Valley proposed that the Commission
    treat Southgate as a separate rate zone from the Mainline
    System so that the project’s costs and risks are borne by
    Mountain Valley and Southgate customers alone, rather than
    its Mainline System customers. Certificate Order, ¶ 25. As a
    result, it suggested a capital structure of 50 percent debt and 50
    percent equity, a proposed cost of debt of 6 percent, a return on
    equity of 14 percent, and a 5 percent depreciation rate based on
    a 20-year contract with Dominion. Id. ¶ 53. The Commission
    approved the proposal. Id. ¶ 54. While it acknowledged that
    14 percent is higher than the typical return on equity for
    expansion projects, the Commission nonetheless found it
    reasonable, given that the Mainline System was not yet
    operational, did not have an existing revenue base, and
    Mountain Valley had no proven track record. Id. ¶ 57.
    Typically, FERC’s policy for expansion projects is to “require
    a pipeline to use the [return on equity] approved in its last NGA
    section 4 rate proceeding, or, if the pipeline has not filed a rate
    case, the [return on equity] from the last litigated NGA section
    4 rate case.” Id. ¶ 22 (Glick, Comm’r, dissenting). Because
    Mountain Valley had not yet litigated a rate case, the
    Commission would have applied the return on equity rate
    authorized in El Paso Natural Gas Company, its most recent
    NGA case, of 10.55 percent. 
    145 FERC ¶ 61,040
    , ¶ 686
    (2013).
    Petitioners challenge the 14 percent return on equity as
    inadequately supported and, by extension, arbitrary and
    capricious. In doing so, they fix their gaze on two of the
    Commission’s purported errors.
    First, they assert that the Commission did not consider
    current market conditions or support the authorized return on
    equity with empirical data. Rather than “closely scrutiniz[ing]”
    10
    Mountain Valley’s requested rate, the Commission simply
    relied on previous rates for new market entrants to approve the
    14 percent return on equity here. Pet’rs’ Br. at 20–21. In their
    view, such a decision risks skewing incentives for building new
    and unnecessary pipelines. When setting an initial rate under
    Section 7, the Commission is not required, however, to set a
    return on equity rate based on market conditions and empirical
    data. It is true that “[a] rate of return may be reasonable at one
    time and become too high or too low by changes affecting
    opportunities for investment, the money market and business
    conditions generally.” Bluefield Waterworks & Imp. Co. v.
    Pub. Serv. Comm’n of West Virginia, 
    262 U.S. 679
    , 693 (1923).
    But the Natural Gas Act does not compel an explicit
    consideration of market conditions in all circumstances. See
    15 U.S.C. § 717c(a). Indeed, the Commission’s typical policy
    in Section 7 proceedings is to apply the rate determined in the
    last NGA section 4 proceeding. Petitioners do not challenge
    this policy, nor do they provide support for the claim that
    market conditions and empirical data must factor into the
    Commission’s calculus. Thus, their focus on these factors is
    unavailing.
    Petitioners’ fear that the return on equity presents a
    market-skewing incentive is similarly misplaced. The
    Commission explained that Mountain Valley’s precedent
    agreement for 80 percent of the project’s capacity indicated the
    need for the project. Precedent agreements are often—though
    not always—reliable indicators of market need for a pipeline
    project. See Appalachian Voices v. FERC, No. 17-1271, 
    2019 WL 847199
    , at *1 (D.C. Cir. Feb. 19, 2019) (per curiam); but
    see Envtl. Def. Fund v. FERC, 
    2 F.4th 953
    , 973 (D.C. Cir.
    2021). Here, the long-term agreement shows an actual need for
    the Project, not an attempt on Mountain Valley’s part to
    overbuild purely for profit.
    11
    Second, Petitioners argue that the Commission erred in
    treating Mountain Valley as a new market entrant, in spite of
    its prior experience with the Mainline System Project.
    Petitioners rely heavily on Commissioner Glick’s dissent from
    the Certificate Order in support of this argument.
    Commissioner Glick characterized the 14 percent return on
    equity as a break from precedent for incremental expansion
    projects. Certificate Order, ¶ 4 & n.330 (Glick, Comm’r,
    dissenting). In Cheyenne Connector, LLC, for example, the
    Commission rejected a pipeline company’s proposed return on
    equity of 13 percent because the project “has more in common
    with the incremental expansions constructed by existing
    pipelines than with greenfield pipeline projects.” 
    168 FERC ¶ 61,180
    , ¶ 52 (2019). See also Gulfstream Natural Gas Sys.,
    LLC, 
    170 FERC ¶ 61,199
    , ¶¶ 18–19 (2020) (rejecting a return
    on equity of 14 percent for existing pipeline’s expansion
    project); Cheniere Corpus Christi Pipeline, LP, 
    169 FERC ¶ 61,135
    , ¶¶ 34–35 (2019) (same). Because the Commission
    already granted Mountain Valley a 14 percent return on equity
    as a new market entrant for Mainline, Commissioner Glick
    believed it should not receive such a favorable return on equity
    the second time around. Certificate Order, ¶ 22 (Glick,
    Comm’r, dissenting). Further, Commissioner Glick would
    have treated Mountain Valley as an existing pipeline company
    due to its executed binding service contracts with shippers. 
    Id.
    Those contracts provide a level of revenue security that most
    greenfield projects do not enjoy. 
    Id.
    The question of whether the Commission should have
    treated Mountain Valley and Southgate as a “new market
    entrant” and “greenfield pipeline,” respectively, depends on
    whether we take a formalist or functionalist approach.
    Formally, as Petitioners would have it, Southgate is an
    extension of a partially constructed pipeline, and this is not
    Mountain Valley’s first rodeo at the Commission.
    12
    Functionally, as the Commission views it, Mountain Valley
    does not have the track record or revenue stream of existing
    pipeline operations and should be treated as new to the market.
    In these circumstances, the Commission’s functional approach
    was reasonable.
    In City of Oberlin, Ohio v. FERC, 
    937 F.3d 599
     (D.C. Cir.
    2019), we set out a host of factors to consider in determining
    whether the Commission acted in the public interest in
    approving a particular return on equity. First, although a “bare
    citation to precedent” or reflexive use of a past rate will not
    suffice, invoking precedent to balance consumer and investor
    interests will aid the Commission’s case. Id. at 609 (quoting
    Sierra Club, 867 F.3d at 1378). Second, the Commission can
    support its approval of a rate by responding to specific
    objections in its Certificate Order. Id. And finally, it should
    explain the risks the proposed pipeline faces and why that
    justifies the return on equity. Id. What will doom the
    Commission’s approval of a return on equity is a “fail[ure] to
    consider an important aspect of the problem, offer[ing] an
    explanation for its decision that runs counter to the evidence
    before the agency, or [one that] is so implausible that it could
    not be ascribed to a difference in view or the product of agency
    expertise.” Id. at 610.
    First, in looking to past precedent, the Commission will
    typically charge the rate set under the last Section 4 proceeding.
    But it has repeatedly approved higher rates for greenfield
    projects. See PennEast Pipeline Co., 
    162 FERC ¶ 58
    (approving a 14 percent return on equity for new market
    entrant, despite the fact that its system capacity was 90 percent
    subscribed); Mountain Valley Pipeline, LLC, 
    161 FERC ¶ 61,043
    , ¶ 84 (2017) (upholding 14 percent return on equity
    with stipulation that Mountain Valley must shift its capital
    structure from 40 percent to 50 percent debt); Appalachian
    13
    Voices, 
    2019 WL 847199
    , at *1 (upholding 14 percent return
    on equity for Mountain Valley’s Mainline System Project);
    Corpus Christi LNG, L.P. Cheniere Corpus Christi Pipeline
    Co., 
    111 FERC ¶ 61,081
    , ¶ 33 (2005) (approving 14 percent
    return on equity for a new pipeline with a 50-50 debt to equity
    ratio).
    The Commission’s decision in Rockies Express Pipeline
    LLC, 
    116 FERC ¶ 61,272
     (2006) is particularly instructive.
    There, the Commission approved a 13 percent return on equity
    for an expansion project, linking up to a previously authorized,
    but not yet completely operational, greenfield pipeline. Id.
    ¶¶ 4, 44. The higher rate was warranted, in the Commission’s
    view, given the attendant risks of a pipeline that size. Id.
    Rather than making a “bare citation” to Rockies Express, the
    Commission invoked that precedent as an example of
    approving higher initial rates when a project faces greater risks
    from the outset. By contrast, the pipeline projects Petitioners
    cite for support concerned expansion proposals for pipelines
    that had been operational for a year or more.5 The Commission
    acted reasonably in denying the requested 14 percent return on
    equity in those cases, where the pipeline companies did not
    face the same risks as non-operational new market entrants.
    5
    Cheyenne Connector expanded a pipeline that had been in operation
    since 2009. Rockies Express Pipeline, TALLGRASS LEADING
    ENERGY SOLUTIONS, https://www.tallgrassenergy.com/Operations_
    REX.aspx (last visited Feb. 25, 2022). In Gulfstream Natural Gas
    System, LLC, the Commission denied a higher return on equity for a
    pipeline expansion of a system that had been in service for over 18
    years. 
    170 FERC ¶ 61,199
    , ¶¶ 18–20. So too in Cheniere Corpus
    Christi Pipeline, LP, the original pipeline had been in service for a
    year when the Commission denied the higher requested rate for its
    expansion. Corpus Christi Pipeline, CHENIERE, https://www.
    cheniere.com/where-we-work/cc-pipeline (last visited Feb. 25,
    2022).
    14
    Second, the Commission detailed Petitioners’ objections
    in its Certificate Order and squarely addressed them in
    explaining its reasoning behind treating Mountain Valley as a
    new market entrant. It specifically noted that its reasoning for
    approving lower return on equity rates in extensions of existing
    pipeline systems did not apply here because those pipelines
    “obtained revenues for service on their existing systems.”
    Certificate Order, ¶ 57.
    Finally, the Commission enumerated the specific risks of
    this project: Mountain Valley was not an established pipeline
    company; it did not have an existing revenue base or a proven
    track record; and the Mainline System was not yet operational.
    
    Id.
     As a result, FERC found it appropriate to treat Mountain
    Valley as a new market entrant proposing a greenfield pipeline
    “because there are no established operations or revenue streams
    that would reduce the risk to the level experienced by natural
    gas companies whose existing systems are in service.” 
    Id.
     We
    find that treatment appropriate.
    B.
    Petitioners also attack the Commission’s Environmental
    Impact Statement as inadequate on two fronts: its discussion of
    potential mitigation measures and the project’s cumulative
    impacts. Under NEPA’s implementing regulations, an EIS
    must include potential mitigation measures that will “avoid,
    minimize, or compensate for effects” of the proposed activity.
    See 
    40 C.F.R. § 1508.1
    (s); see also 
    id.
     §§ 1502.14(e);
    1502.16(a); 1505.3. While NEPA requires an agency to
    consider mitigation measures, significantly, “it does not
    mandate the form or adoption of any mitigation.” Id.
    § 1508.1(s). NEPA also requires that the Commission’s EIS
    consider the “cumulative impacts” of a proposed project. 40
    
    15 C.F.R. § 1508.7
    . A “cumulative impact” is defined as an
    environmental impact that “results from the incremental impact
    of the action when added to other past, present, and reasonably
    foreseeable future actions.” 
    Id.
    First, Petitioners contend that the Commission failed to
    take a “hard look” at the environmental consequences of the
    Southgate Project in its corresponding EIS, particularly with
    regard to sedimentation and erosion. Its reliance on measures
    that proved ineffective for the Mainline System and its failure
    to discuss the effectiveness of these measures was arbitrary and
    capricious, in Petitioners’ view. Petitioners rely in part on a
    report from their own expert hydrogeologist, who criticizes the
    measures discussed in the EIS—including silt fences, compost
    socks, water bars, traverse trench drains, and trench breakers to
    prevent stormwater runoff—as ineffective.
    Petitioners’ argument does not accurately reflect the EIS,
    given that the Commission discussed potential mitigation
    measures for erosion and runoff in detail. To mitigate both, the
    Commission noted that Mountain Valley must route water
    discharged from excavation to vegetated land surfaces. EIS 4-
    50. Trench breakers (sandbags or foam) would be installed to
    prevent water movement in the pipeline, thereby working to
    inhibit erosion. EIS 2-19. Sediment barriers, like silt fences
    and straw bales, as well as trench plugs would be installed and
    maintained throughout construction to prevent erosion. EIS 2-
    22. Mountain Valley would then install “[p]ermanent erosion
    control features,” like slope breakers, on steep terrain. EIS 2-
    21. While Petitioners’ expert criticizes the Commission’s
    reliance on silt fences, she also noted that they are “not
    effective in steep slope areas,” which is why they had failed for
    Mainline. J.A. 235. Yet, Southgate will traverse flatter terrain
    and silt fences may therefore prove effective.
    16
    Further, the EIS distinguishes these measures from those
    that failed for Mountain Valley in the past. Pointing to
    empirical data, it cites 2018 as a record-breaking year for
    precipitation in the region. EIS 1-12. The Commission does
    not expect that precipitation level to repeat and therefore, to
    cause the same erosion and sediment control issues. 
    Id.
     Still,
    to avoid experiencing such issues, Mountain Valley proposed
    monitoring weather conditions during construction and
    adjusting control measures. 
    Id.
     It will also document the
    effectiveness of its erosion control measures through weekly
    reports and allow FERC representatives on-site to enforce
    compliance. EIS 1-13. Third-party inspectors would have the
    authority to stop work on the pipeline immediately, if needed.
    EIS 1-12, 2-30. As a result, the Commission concluded that
    Mountain Valley’s proposed surface water mitigation
    measures would “adequately avoid or minimize potential
    impacts on surface water resources.” EIS 5-5.
    On the whole, Petitioners’ criticisms miss the point of the
    mitigation measure discussion as an “information-forcing”
    exercise. Mayo v. Reynolds, 
    875 F.3d 11
    , 15 (D.C. Cir. 2017)
    (internal quotation marks and citation omitted). Again, NEPA
    does not mandate that the Commission formulate a specific
    mitigation plan, only that it discuss mitigation “in sufficient
    detail to ensure that environmental consequences have been
    fairly evaluated.” Robertson v. Methow Valley Citizens
    Council, 
    490 U.S. 332
    , 352 (1989). This EIS, fulsome in its
    discussion of potential mitigation measures and differences
    from the Mainline System, meets NEPA’s mark.
    Second, Petitioners argue that the Commission failed to
    consider the cumulative impact of the Southgate and Mainline
    System on aquatic resources in the affected area. In their
    account, the Commission purposefully restricted the temporal
    and geographic area of the project in its cumulative impact
    17
    consideration to avoid overlap with the Mainline System
    Project. Petitioners express particular concern over the
    increased “turbidity plumes”—cloudy water resulting from
    sediment—that could result from the projects’ overlap.
    Sediment resulting from these plumes may have long-term
    negative impacts on aquatic life and these effects “could be
    additive, if turbidity plumes settled within common stream
    segments.” Pet’rs’ Br. at 41 (quoting EIS 4-243). Chief among
    their concerns is turbidity plumes settling in the Kerr Reservoir,
    which sits downstream of both projects.
    The purpose of the cumulative impact consideration in an
    EIS is to present a realistic picture of a proposed activity’s
    impacts. American Rivers v. FERC, 
    895 F.3d 32
    , 55 (D.C. Cir.
    2018). Requiring such a consideration prevents “agencies from
    gaming the system by artificially segmenting significant
    actions into piecemeal, and individually insignificant,
    components.” Id. at 54. Where an agency pays scant attention
    to past actions that have damaged the geographic area at issue
    or discusses cumulative impacts in conclusory phrases, it has
    not met NEPA’s standard. Id. at 55 (agency “fell far short of
    the NEPA mark” in failing to consider past actions that
    damaged the area’s ecosystem); NRDC v. Hodel, 
    865 F.2d 288
    ,
    289 (D.C. Cir. 1988) (per curiam) (allowing agency’s
    boilerplate analysis of cumulative impacts “to pass muster here
    would eviscerate NEPA”).
    As a practical matter, an agency can typically identify the
    location where cumulative impacts are likely to occur by first
    choosing a single “ecoregion” or “watershed.” 6 Consideration
    of Cumulative Impacts in EPA Review of NEPA Documents
    6
    “A watershed is a land area where precipitation collects and funnels
    to an outlet—usually a stream.” J.A. 85 (internal quotation marks
    omitted).
    18
    4.2, U.S. EPA (1999). Though these boundaries “should not
    be overly restricted in cumulative impact analysis,” they should
    also not be so expansive that the “analysis becomes unwieldly
    and useless for decision-making.” 
    Id.
     Making this selection
    demands a “high level of technical expertise and is properly left
    to the informed discretion of the responsible federal agencies.”
    Kleppe v. Sierra Club, 
    427 U.S. 390
    , 412 (1976).
    In addition to naming the relevant geographic area, the
    cumulative impact analysis must identify: “the impact expected
    in that area; those other actions—past, present, and proposed,
    and reasonably foreseeable that have had or will have impact
    in the same area; the effects of those other impacts; and the
    overall impact that can be expected if the individual impacts
    are allowed to accumulate.” Sierra Club v. FERC, 
    827 F.3d 36
    , 49 (D.C. Cir. 2016) (internal quotation marks, citation, and
    numbering omitted). A cumulative impacts analysis will pass
    a “hard look” review if it “contain[s] sufficient discussion of
    the relevant issues and [is] well-considered.” City of Boston
    Delegation v. FERC, 
    897 F.3d 241
    , 253 (D.C. Cir. 2018)
    (internal quotation marks and citation omitted).
    The Commission fulfilled that standard. First, the
    Commission designated “hydrologic unit code-10” (“HUC-
    10”) as the geographic scope for its cumulative analysis on
    surface water resources, which averages to about 130,000
    acres. EIS 4-227, 4-230. Second, the Commission identified
    in-stream activities, including dredging and open pipeline
    crossing techniques, as likely to result in increased turbidity in
    this area. EIS 4-242. It noted that turbidity plumes could travel
    downstream for a few miles, but that the impacts would be felt
    only temporarily, given the limited duration of these in-water
    activities and the plumes’ tendency to disperse within several
    days. 
    Id.
     Third, FERC named other actions that would likely
    have an impact in the same area, with a particular focus on the
    19
    Mainline System Project. EIS 4-236. The Southgate Project
    and Mainline System Project would overlap at two perennial
    streams and one intermittent stream within the Cherrystone
    Creek-Banister River HUC-10 watershed. 
    Id.
     But the
    Commission stipulated that the Projects’ stream crossings are
    three and a half miles apart, the Projects would not share
    overlapping workspace, and their construction would not take
    place at the same time. Id.; EIS 4-243. Lastly, the Commission
    maintained that the cumulative impacts of the two projects on
    turbidity would be limited because of the geographic and
    spatial distance between the crossings. EIS 4-243. The
    Commission acknowledged that sediment can accumulate
    when turbidity plumes settle in a stream, but found this impact
    unlikely given the projects’ spatial separation and the erosion
    and sediment controls that will be in place. 
    Id.
     Additionally,
    the Kerr Reservoir is more than 30 miles away from both
    projects, remains outside the geographic scope of the analysis,
    and therefore is likely to face only negligibly increased
    sedimentation as a result. J.A. 886. Thus, in its cumulative
    analysis, the Commission recognized the pertinent issues and
    reasonably concluded that the two projects are geographically
    and temporally separated enough to mitigate any compounded
    effects.
    Such a conclusion aligns with our deference to the
    Commission on issues that demand its technical and scientific
    expertise. Myersville Citizens for a Rural Community, Inc. v.
    FERC, 
    783 F.3d 1301
    , 1308 (D.C. Cir. 2015) (“when
    considering FERC’s evaluation of scientific data within its
    technical expertise, we afford FERC an extreme degree of
    deference”) (internal quotation marks and citation omitted).
    What’s more, Petitioners do not marshal compelling evidence
    to counter the Commission’s cumulative impacts analysis. The
    City of Roanoke briefing lists downstream sediment as a
    concern of the Mountain Valley pipeline but does not present
    20
    any statistical evidence contradicting FERC’s conclusions.
    J.A. 829–36. Further, the research Petitioners presented in
    their rehearing request, allegedly demonstrating that fine
    sediment can travel hundreds of miles and therefore will
    accumulate between the two Projects, is taken from an
    environmental product company’s website. J.A. 803.7 Upon
    review, the web page in question does not claim that sediment
    may travel hundreds of miles. These sources thus do not call
    into question the Commission’s analysis.
    For the foregoing reasons, we deny the petition for review.
    So ordered.
    7
    Petitioners cite Sediment Transport and Deposition: Fundamentals
    of Environmental Measurements, FONDRIEST ENVIRONMENTAL,
    INC., https://www.fondriest.com/environmental-measurements/para
    meters/hydrology/sediment-transport-deposition/#std2 (Dec. 5,
    2014).