Entergy Arkansas, LLC v. FERC ( 2022 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 8, 2021                 Decided July 15, 2022
    No. 20-1262
    ENTERGY ARKANSAS, LLC, ET AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    MISSISSIPPI PUBLIC SERVICE COMMISSION, ET AL.,
    INTERVENORS
    Consolidated with 20-1391
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    Jennifer S. Amerkhail argued the cause and filed the briefs
    for petitioners. Zachary C. Schauf entered an appearance.
    Carol J. Banta, Attorney, Federal Energy Regulatory
    Commission, argued the cause for
    2
    respondent. With her on the brief were Matthew R.
    Christiansen, General Counsel, and Robert H. Solomon,
    Solicitor.
    Before: ROGERS and WILKINS, Circuit Judges, and
    SILBERMAN, Senior Circuit Judge.
    Opinion for the Court filed by Circuit Judge WILKINS.
    WILKINS, Circuit Judge. The instant petition arises from a
    three-year effort to establish a cost allocation method for
    allocating Midcontinent Independent System Operator, Inc.’s
    (“MISO”) share of costs for interregional transmission projects
    connecting a region operated by MISO and an adjacent region
    operated by PJM Interconnection, L.L.C. (“PJM”). In 2016,
    the Federal Energy Regulatory Commission (“FERC” or
    “Commission”) required MISO to institute reforms to its
    interregional planning process and directed MISO to propose a
    cost allocation method for its share of certain interregional
    project costs. Since that time, MISO has twice submitted
    proposals for such cost allocation. Both times, FERC rejected
    the proposals, finding that they were not just and reasonable as
    required by the Federal Power Act (the “Act”), 
    16 U.S.C. §§ 791
     et seq., because they were inconsistent with the cost
    causation principle. After the second rejection, FERC, on its
    own initiative, established a cost allocation method for certain
    MISO-PJM projects. In this consolidated action, Petitioners
    challenge FERC’s rejection of MISO’s second proposal and
    FERC’s corresponding implementation of a cost allocation
    method. For the reasons below, we deny the petitions and
    affirm FERC’s orders in all respects.
    3
    I.
    Section 201 of the Act gives FERC jurisdiction over
    facilities that engage in transmission and sale of electricity at
    wholesale in interstate commerce. 
    16 U.S.C. § 824
    (b)(1).
    Under the Act, FERC has the power to review rates in
    connection with transmission services or sales to ensure that
    such rates are “just and reasonable” and to set aside as
    “unlawful” any rate or charge it deems not just and reasonable.
    16 U.S.C. § 824d(a). Additionally, pursuant to Section 206, if
    FERC finds a rate or charge to be “unjust, unreasonable, unduly
    discriminatory or preferential,” FERC “shall determine the just
    and reasonable rate . . . to be thereafter observed and in force,
    and shall fix the same by order.” 16 U.S.C. § 824e(a).
    In assessing whether a rate is “just and reasonable,” FERC
    and the courts determine, among other things, whether the rate
    comports with the “cost-causation principle” which requires
    that the rates charged for electricity reflect the costs of
    providing it. See Old Dominion Elec. Coop. v. FERC, 
    898 F.3d 1254
    , 1255 (D.C. Cir. 2018) (hereinafter “Old Dominion”).
    “We often frame this principle as one that ensures burden is
    matched with benefit, so that FERC generally may not single
    out a party for the full cost of a project, or even most of it, when
    the benefits of the project are diffuse.” 
    Id.
     (internal quotation
    marks and citations omitted).
    Under a FERC regulation, known as “Order No. 1000,”
    see Transmission Planning and Cost Allocation by
    Transmission Owning and Operating Public Utilities, 
    136 FERC ¶ 61,051
     (2011), electric utilities are subject to two
    relevant requirements:
    First, utilities in each planning region must
    jointly produce a regional transmission plan to
    4
    determine what new facilities would best meet
    regional needs for electricity. Second, in their
    respective tariffs, utilities must include a
    formula for allocating the costs of new
    transmission facilities selected in the regional
    transmission plan for purposes of cost
    allocation. This formula must satisfy six general
    principles, the first of which is the cost-
    causation principle: The cost of transmission
    facilities must be allocated to those within the
    transmission planning region that benefit from
    those facilities in a manner that is at least
    roughly commensurate with estimated benefits.
    Order No. 1000 requires each utility to show,
    through compliance filings, that its cost-
    allocation formula is consistent with the six
    specified principles.
    Old Dominion, 898 F.3d at 1256 (internal quotation marks and
    citations omitted).
    In accordance with Order No. 1000, MISO and PJM
    jointly planned—and subsequently approved as part of their
    respective regional transmission plans—interregional projects
    that connected and benefited both regions. Once interregional
    projects were identified, MISO and PJM allocated the costs of
    such projects between their regions. Each region then allocated
    its share of costs from the interregional project to subdivided
    zones within their own respective regions. This case involves
    the cost allocation method for MISO’s share of a MISO-PJM
    interregional transmission project.
    Under MISO’s original regional transmission plan, MISO
    established different project categories, each with different
    qualifying criteria and cost allocations. MISO’s share of an
    5
    interregional project’s costs is then assigned according to the
    allocation method that corresponds with the MISO project
    type, of which there were historically three. 1 The most relevant
    category to this appeal is the “Market Efficiency Project”—a
    higher-voltage transmission project that reduces congestion
    and lowers the costs of power in the region. Originally, to
    qualify as a Market Efficiency Project, a transmission project
    was required to (1) cost at least $5 million, (2) consist of
    facilities that have voltages of 345 kilovolts (kV) or higher, and
    (3) have a total regional benefit-to-cost ratio of at least 1.25-to-
    1, with benefits measured using an Adjusted Production Cost
    Savings metric (“Production Cost Metric”). J.A. 355. The
    Production Cost Metric measures the extent to which a new
    transmission project will make electricity cheaper by
    measuring the total reduction in costs resulting from the new
    project. See Midwest Independent Transmission System
    Operator, Inc., 
    118 FERC ¶ 61,209
    , ¶ 5 n.6 (2007). Under the
    original plan, once a project was deemed a Market Efficiency
    Project, 20 percent of the project cost was allocated on a
    region-wide basis to all customers across the entire MISO
    footprint (known as the “postage-stamp approach”). The
    remaining 80 percent was allocated to zones based on each
    zone’s proportion of the Production Cost Metric benefits that it
    received. The orders on review stem from FERC’s resolution
    of an earlier complaint proceeding and subsequent filings
    related to this original plan. We start with a brief summary of
    the relevant proceedings and filings.
    1
    The three MISO project types are: Baseline Reliability Projects,
    Market Efficiency Projects, and Multi-Value Projects. See J.A. 354–
    55 (describing the three types of projects and corresponding
    allocation method).
    6
    Northern Indiana Public Service Company Complaint Order
    In 2013, Northern Indiana Public Service Company
    (“NIPSCO”), a utility in northern Indiana whose transmission
    system connects to the “seams” of MISO’s and PJM’s systems,
    filed a complaint against MISO and PJM, seeking reform of the
    MISO-PJM joint interregional transmission planning process.
    Northern Indiana Public Service Co. v. Midcontinent
    Independent System Operator, Inc., 
    155 FERC ¶ 61,058
     (2016)
    (hereinafter “NIPSCO Complaint Order”). FERC granted in
    part and denied in part the NIPSCO Complaint, ordering,
    among other things, that MISO revise its Market Efficiency
    Project criteria. 
    Id. ¶ 54
    . FERC found that MISO’s then-
    current “cost and voltage thresholds prohibit from
    consideration certain transmission projects in the MISO-PJM
    interregional transmission planning process that benefit both
    regions, as evidenced by the Quick Hit Analysis,” 2 which was
    submitted by MISO. 
    Id. ¶ 129
    . Given that the Quick Hit
    Analysis identified interregional projects that were less than the
    current voltage and cost thresholds but nevertheless provided
    benefits to both regions, FERC reasoned that such projects
    “should therefore not be automatically excluded from
    consideration.” 
    Id. ¶ 131
    . Accordingly, FERC directed MISO
    to lower its minimum voltage threshold for a Market Efficiency
    Project from 345 kV to 100 kV and to remove the $5 million
    minimum cost requirement. 
    Id.
    Given the revised lower voltage threshold, FERC found
    that MISO did not address what regional cost allocation
    method would apply to this new gap—that is, how MISO
    would allocate its “share of the cost of an interregional
    2
    “The Quick Hit Analysis [was] an effort by MISO, PJM and its
    stakeholders to identify near-term interregional economic
    transmission projects to remedy recent historical interregional
    congestion issues.” NIPSCO Complaint Order, ¶ 100 n.175.
    7
    economic transmission project operating above 100 kV but
    below the original threshold of 345 kV.” J.A. 357. As such,
    FERC directed MISO to submit a further compliance filing to
    either confirm that MISO would apply the existing cost
    allocation method for Market Efficiency Projects or propose
    tariff revisions to apply a different regional cost allocation.
    2019 First Regional & Interregional Filings
    In February 2019, MISO filed proposals for both its
    regional and interregional transmission projects. J.A. 604–05.
    In its First Regional Filing, MISO proposed to (1) lower the
    minimum voltage threshold for Market Efficiency Projects
    from 345 kV to 230 kV and (2) eliminate the 20 percent region-
    wide cost sharing and instead allocate 100 percent of the costs
    to pricing zones based on a benefit-to-cost ratio measured not
    only by the Production Cost Metric but also two additional
    benefit metrics, the Avoided Reliability Project Savings
    Metric 3 and a MISO-SPP Settlement Agreement Cost Metric
    (“SPP Metric”). Midcontinent Independent System Operator,
    Inc., Order Rejecting Proposed Tariff Revisions, 
    167 FERC ¶ 61,258
    , ¶¶ 15–19 (2019) (hereinafter “First Regional
    Order”). Relevant here is the SPP Metric, which measures any
    savings or increased costs in annual payments—made by
    MISO to another region operator named Southwest Power
    Pool, Inc. (“SPP”) pursuant to a settlement agreement—that
    result from the implementation of a Market Efficiency Project.
    
    Id. ¶ 17
    . MISO also proposed a new category of projects called
    Local Economic Projects, which would operate at above 100
    kV and below 230 kV and would meet certain minimum
    3
    This metric measures the “savings realized by transmission
    customers when a Market Efficiency Project eliminates the need to
    develop one or more future reliability projects.” First Regional
    Order, ¶ 16.
    8
    regional and local benefit-to-cost ratios for each pricing zone
    in which a project is located. 
    Id.
     ¶¶ 9–10. MISO proposed
    allocating 100 percent of the costs of these projects to the
    pricing zones in which the project is located, not based upon
    the benefits MISO calculates will accrue to all impacted pricing
    zones. 
    Id.
    In its First Interregional Filing, MISO proposed to create a
    new interregional transmission project category with SPP and
    PJM called an Interregional Economic Project, defined as any
    transmission project that qualifies as a Market Efficiency
    Project (230 kV or higher) or a Local Economic Project
    (between 100 kV and 230 kV) under the MISO-PJM plan.
    Midcontinent Independent System Operator, Inc., Order
    Rejecting Proposed Revisions and Compliance Filing and
    Directing Further Compliance, 
    167 FERC ¶ 61,259
    , ¶¶ 5–7
    (2019) (hereinafter “First Interregional Order”). MISO
    further proposed to allocate costs of MISO’s share of these
    projects in the same manner as the corresponding regional
    project categories. 
    Id.
     ¶¶ 8–9.
    FERC rejected MISO’s First Regional Filing because it
    determined that the proposed cost allocation method for Local
    Economic Projects was not just and reasonable. First Regional
    Order, ¶ 1. Specifically, FERC found the proposed benefits
    test for the Local Economic Project category—which would
    require both a minimum regional and local benefit-to-cost
    ratio—was inconsistent with the cost causation principle. 
    Id.
    ¶¶ 56–63. MISO would identify the project’s regional benefits,
    but ignore such benefits and instead implement its preferred
    method of allocating 100 percent of the project’s costs to the
    pricing zone where the project is located, rather than to all the
    zones that have been identified as beneficiaries. 
    Id.
     Put
    simply, FERC found that the proposal failed to allocate costs
    commensurate with benefits. 
    Id. ¶ 63
    . Additionally, because
    9
    the proposals in MISO’s First Interregional Filing relied on
    definitions and provisions rejected in the First Regional Filing,
    FERC rejected the interregional proposal as well. First
    Interregional Order, ¶ 21. It directed MISO to submit a further
    compliance filing addressing the allocation of MISO’s share of
    costs for interregional projects between 100 kV and 345 kV.
    
    Id.
    2020 Second Regional & Interregional Filings
    In January 2020, MISO again submitted companion
    proposals for certain regional network upgrades (“Second
    Regional Filing”) and interregional projects (“Second
    Interregional Filing”). In its Second Regional Filing, MISO
    again proposed to create a new project type, Local Economic
    Projects, with the same qualifying criteria as outlined in the
    First Regional Filing. Midcontinent Independent System
    Operator, Inc., Order Rejecting Proposed Tariff Revisions, 
    170 FERC ¶ 61,241
    , ¶¶ 13–16 (2020) (hereinafter “Second
    Regional Order”). However, it removed the requirement that
    the project meet the minimum regional benefit-to-cost ratio and
    instead proposed that the project meet only the minimum local
    benefit-to-cost ratio. 
    Id. ¶ 16
    . MISO contended that this
    change rectified the cost causation principle issue discussed in
    the First Regional Order because costs would only be allocated
    to the local pricing zone based on demonstrable benefits
    identified using the three benefit metrics (outlined in the
    previous section), which would account for project type
    differences. 
    Id.
    In its Second Interregional Filing, which was “designed to
    work seamlessly with the revisions proposed in the [Second
    Regional Filing],” J.A. 300, MISO again proposed to create a
    new Interregional Economic Project category, with differing
    cost allocation methods depending on the voltage level.
    10
    Midcontinent Independent System Operator, Inc., Order
    Rejecting Proposed Revisions and Compliance Filing and
    Establishing Just and Reasonable Rate, 
    170 FERC ¶ 61,242
    (2020) (hereinafter “Second Interregional Order”). For
    Interregional Economic Projects with a voltage level of 230 kV
    or higher, MISO proposed allocating its share of costs from the
    MISO-PJM interregional project the same way as Market
    Efficiency projects, namely allocating 100 percent of the costs
    to the pricing zones that benefit from the project. 
    Id. ¶ 11
    . For
    projects between 100 kV and 230 kV, MISO proposed a cost
    allocation method similar to the category of Local Economic
    Projects in the Second Regional Filing—that is, allocating 100
    percent of the projects’ costs to the pricing zones in which the
    project is located. 
    Id. ¶ 12
    .
    In companion orders issued on March 20, 2020, FERC
    again rejected both MISO’s Second Regional and Second
    Interregional Filing. In rejecting MISO’s Second Regional
    Filing, FERC again found that the cost allocation method for
    Local Economic Projects was not just and reasonable because
    it remained inconsistent with the cost causation principle.
    Second Regional Order, ¶ 59. Despite the removal of the
    regional benefit-to-cost ratio requirement, FERC found
    MISO’s Second Regional Filing to be “identical to the proposal
    previously rejected in the 2019 [First] Regional Order.” 
    Id. ¶ 60
    . FERC determined that the Second Regional Filing was
    not consistent with the cost causation principle because it
    inappropriately relied on the SPP metric, which would
    calculate benefits outside of the local pricing zone where the
    project is located, but then disregard these benefits by
    allocating costs solely within that pricing zone. 
    Id. ¶ 59
    ; see
    also 
    id.
     ¶¶ 66–67. FERC further found it “incongruous” for
    MISO to apply the Production Cost Metric, which MISO states
    is the most reliable measure of a net impact of a project, only
    to the zone where the project is physically located. 
    Id. ¶ 68
    .
    11
    FERC affirmed these findings on rehearing. See Midcontinent
    Independent System Operator, Inc., Order Addressing
    Arguments Raised on Rehearing, 
    172 FERC ¶ 61,100
     (2020)
    (hereinafter “Regional Rehearing Order”).
    Because MISO’s Second Interregional Filing also relied
    on provisions and definitions in the Second Regional Filing,
    FERC again rejected MISO’s interregional filing. Second
    Interregional Order, ¶ 29. FERC also determined that its
    rejection of this filing meant that MISO’s outstanding
    compliance requirement—to establish a cost allocation method
    for interregional projects between 100 kV and 345 kV—
    remained unfulfilled. 
    Id. ¶ 30
    . As such, FERC exercised its
    authority under Section 206 of the Act, to establish a “just and
    reasonable rate.” 
    Id.
     FERC determined that it was appropriate
    to allocate “100% of MISO’s share of the cost of MISO-PJM
    interregional economic transmission projects” between 100 kV
    and 345 kV “that qualify as Market Efficiency Projects” using
    MISO’s Production Cost Metric (“Replacement Method”). 
    Id. ¶ 31
    . On rehearing, FERC again confirmed its rejection of
    MISO’s Second Interregional Filing as well as its
    establishment of a cost allocation method for interregional
    projects between 100 kV and 345 kV. See Midcontinent
    Independent System Operator, Inc., Order on Compliance and
    Addressing Arguments Raised on Rehearing, 
    172 FERC ¶ 61,101
     (2020) (hereinafter “Interregional Rehearing
    Order”).
    2020 Third Regional Filing
    In April 2020, MISO submitted a Third Regional Filing
    with no corresponding interregional filing, which FERC
    subsequently accepted. See Midcontinent Independent System
    Operator, Inc., Order Accepting Proposed Tariff and
    Transmission Owners Agreement Revisions, 
    172 FERC 12
    ¶ 61,095 (2020) (hereinafter “Third Regional Order”).
    Specifically, FERC approved MISO’s proposal to (1) lower the
    Market Efficiency Projects’ minimum threshold voltage from
    345 kV to 230 kV; (2) eliminate the 20 percent system-wide
    allocation; and (3) allocate 100 percent of the project costs
    based on each pricing zone’s identifiable net-positive benefits
    as determined by three separate benefit metrics. 
    Id. ¶¶ 33, 46
    .
    Procedural History
    Petitioners are members of the MISO Transmission
    Owners, which is “a group of investor-owned transmission
    owners, cooperative utilities, and municipal utilities that own
    electric transmission facilities over which . . . [MISO] provides
    electric transmission service.” Case No. 20-1262, Dkt. No.
    1852900, at 2. On July 17, 2020, the MISO Transmission
    Owners group filed a petition for review of the Second
    Interregional Order. 
    Id. at 1
    . After members of the group
    withdrew from the case, the remaining instant Petitioners 4
    moved to rename the appeal and filed a second petition for
    review of the Interregional Rehearing Order. See Case No.
    20-1391, Dkt. No. 1864341, at 1–2. On October 2, 2020, the
    Court consolidated the appeals. Case No. 20-1391, Dkt. No.
    1864529. MISO as well as the Mississippi Public Service
    Commission and the Mississippi Public Utilities Staff
    (together, “MPSC”) filed motions to intervene, which were
    subsequently granted. See Case No. 20-3191, Dkt No.
    1867511, Dkt No. 1865903; Dkt. No. 1869462. While MPSC
    intervened in support of Petitioners, see Case No. 20-1391,
    4
    Petitioners include: Entergy Arkansas, LLC; Entergy Louisiana,
    LLC; Entergy Mississippi, LLC; Entergy New Orleans, LLC;
    Entergy Texas, Inc.; Northern States Power Co. (a Minnesota
    corporation, subsidiary of Xcel Energy Inc.); and Northern States
    Power Company (a Wisconsin corporation, a subsidiary of Xcel
    Energy Inc.).
    13
    Dkt. No. 1872536, MISO only filed a notice advising the Court
    that it “neither supports nor opposes the Petitioners’ or the
    Respondents’ positions” but rather only sought to “preserve its
    opportunity to participate as needed,” Case No. 20-1391, Dkt.
    No. 1871683, at 2.
    II.
    This Court reviews FERC’s orders under the arbitrary and
    capricious standard. FPL Energy Marcus Hook, L.P. v. FERC,
    
    430 F.3d 441
    , 446 (D.C. Cir. 2005). “Under the arbitrary-and-
    capricious standard of review, we uphold FERC decisions if
    the agency has examined the relevant considerations and
    articulated a satisfactory explanation for its action, including a
    rational connection between the facts found and the choice
    made.” Old Dominion, 898 F.3d at 1260 (internal quotation
    marks and citations omitted). “In reviewing FERC’s orders,
    we are particularly deferential to the Commission’s expertise
    with respect to ratemaking issues.” ExxonMobile Oil Corp. v.
    FERC, 
    487 F.3d 945
    , 951 (D.C. Cir. 2007) (per curiam)
    (internal quotation marks and citation omitted); see also Alcoa
    Inc. v. FERC, 
    564 F.3d 1342
    , 1347 (D.C. Cir. 2009) (“In
    matters of ratemaking, our review is highly deferential, as
    issues of rate design are fairly technical and, insofar as they are
    not technical, involve policy judgments that lie at the core of
    the regulatory mission.”) (internal quotation marks, alterations,
    and citations omitted). “The court owes the Commission great
    deference in this realm because the statutory requirement that
    rates be just and reasonable is obviously incapable of precise
    judicial definition, and the Commission must have
    considerable latitude in developing a methodology responsive
    to its regulatory challenge.” S.C. Pub. Serv. Auth. v. FERC,
    
    762 F.3d 41
    , 55 (D.C. Cir. 2014) (per curiam) (internal
    quotation marks and citations omitted) (cleaned up). However,
    the court will set aside FERC’s orders regarding allocation of
    14
    costs if they are either unreasonable or inadequately explained.
    Old Dominion, 898 F.3d at 1260.
    III.
    As an initial matter, we address the question of standing.
    Even where, as here, FERC does not dispute standing, “we
    have an ‘independent obligation to assure ourselves that
    standing exists.’” Exelon Corp. v. FERC, 
    911 F.3d 1236
    , 1240
    (D.C. Cir. 2018) (quoting Summers v. Earth Island Inst., 
    555 U.S. 488
    , 499 (2009)) (alteration accepted). Petitioners assert
    that under FERC’s Replacement Method, MISO will allocate
    some of the costs of rebuilding an existing 138 kV line
    (“Project NC-11”), located on the northern border of Indiana,
    to Petitioners’ customers across eleven zones in the MISO
    region. See Pet’r Br. at 6. Yet, some of these customers do not
    benefit from Project NC-11. Id. at 7. By contrast, Petitioners
    contend that under MISO’s proposed cost allocation method,
    none of the costs would be allocated to its customers consistent
    with cost causation principles. Id. We conclude that these
    assertions are sufficient to establish standing, given that a
    favorable decision by this Court would remedy Petitioners’
    injuries.
    Petitioners challenge both FERC’s rejection of MISO’s
    Second Interregional Filing as well as FERC’s establishment
    of a Replacement Method for cost allocation. We address each
    challenge in turn.
    A. MISO’s Second Interregional Filing
    In its Second Interregional Filing, MISO proposed to
    create a new category of projects called Interregional
    Economic Projects (with voltages between 100 kV and 230
    kV), using the same cost allocation method as used for Local
    15
    Economic Projects in its Second Regional Filing. Second
    Interregional Order, ¶ 12. Specifically, it proposed allocating
    100 percent of MISO’s share of costs of the project to the
    pricing zone in which the project is located. Id. FERC found
    that this allocation method was inconsistent with the cost
    causation principle because it inappropriately relied on the SPP
    Metric, which in FERC’s view would likely identify regional
    transmission benefits that MISO would ultimately disregard in
    allocating costs. Second Regional Order, ¶ 67. The SPP
    Metric measures the reduction in annual payments from MISO
    to SPP pursuant to the MISO-SPP Settlement Agreement that
    allows MISO to make better economic use of its system. Under
    the settlement agreement, MISO pays SPP for the use of
    inadvertent flows over SPP’s grid that are tied to the amount of
    transmission capacity that MISO controls in the MISO-SPP
    Settlement Region. MISO then passes on the SPP charges to
    the utilities on MISO’s grid in a two-part charge based on a pro
    rata share plus an estimate of benefits from increased flows
    allowed by the payments. A new transmission line on MISO’s
    system could increase MISO’s transmission capacity, thereby
    decreasing the payments MISO would have to make to SPP.
    Consequently, it would reduce the payments each utility zone
    makes to MISO. The SPP Metric measures the benefits that
    flow to each utility zone—that is, the reduced payments it
    would have to make to MISO—as a result of a project’s impact
    on MISO’s transmission capacity.            These benefits are
    calculated for all of the pricing zones within the MISO region.
    Yet MISO’s benefit-cost determination would consider only
    the portion of these benefits calculated for the pricing zone in
    which the project is physically located. Second Regional
    Order, ¶ 67.
    FERC found that, based on the Court’s decision in Old
    Dominion, MISO’s proposed allocation method using the SPP
    metric was inconsistent with the cost causation principle. Id.
    16
    ¶ 69. In Old Dominion, FERC approved a proposal to
    eliminate cost-sharing for two high-voltage transmission lines
    that benefitted the entire region, resulting in a local zone
    bearing the entire cost of the two regionally-beneficial projects.
    898 F.3d at 1255. Specifically, although FERC found that
    high-voltage transmission projects have significant regional
    benefits that accrue to all members of the transmission
    operator, it approved a hybrid cost-allocation method which
    allocated half of the costs on a pro rata basis, regardless of
    where the specific project is located (postage stamp
    component), and the remaining costs based on an estimate of
    which zones most directly benefit from the project. Id. at
    1256–57. FERC viewed the hybrid cost allocation method as
    roughly commensurate with the benefits received because the
    postage stamp component captured the full spectrum of
    benefits including those regional benefits that are difficult to
    quantify. Id. at 1257. The Court found that FERC’s decision
    to approve this proposal was arbitrary because “the cost-
    causation principle prevents regionally beneficial projects from
    being arbitrarily excluded from cost sharing—a necessary
    corollary to ensuring that the costs of such projects are
    allocated commensurate with their benefits.” Id. at 1263.
    Here, FERC noted that the concern expressed in Old Dominion
    applied “with similar force” to MISO’s proposed cost
    allocation method because it would determine benefits outside
    of the local zone where the project was located “but then
    disregard these benefits and allocate costs for the project solely
    within one Transmission Pricing Zone.” Second Regional
    Order, ¶ 69.        Petitioners make three main arguments
    challenging this finding, which we address in turn.
    First, Petitioners contend that it was reversible error for
    FERC to reject the Second Interregional Filing simply because
    it shared tariff language with the Second Regional Filing that
    FERC rejected. In Petitioners’ view, FERC was obligated to
    17
    independently evaluate the Second Interregional Filing to
    determine if its local zone allocation was appropriate for low-
    voltage interregional projects. This argument quickly fails.
    According to MISO’s own representations to FERC in its
    filings, the Second Interregional Filing was “designed to work
    seamlessly with the revisions proposed in the [Second Regional
    Filing]” and relied on definitions and provisions in the Second
    Regional Filing. J.A. 300. As such, it was appropriate and well
    within FERC’s discretion to reject MISO’s Second
    Interregional Filing based on its rejection of the Second
    Regional Filing, as it would obviously suffer from the same
    critical flaw. See Tenn. Valley Mun. Gas Ass’n v. FERC, 
    140 F.3d 1085
    , 1088 (D.C. Cir. 1998) (“An agency has broad
    discretion to determine when and how to hear and decide the
    matters that come before it.”).
    Second, Petitioners maintain that FERC’s decision was
    arbitrary and capricious because FERC failed to identify
    significant regional benefits provided by interregional
    transmission projects. In support of this contention, Petitioners
    point to FERC’s statement in its Third Regional Order that
    “neither MISO nor the Commission in the March 2020 Order
    has made the finding that MISO projects between 100 kV and
    230 kV produce ‘significant regional benefits,’” Third
    Regional Order, ¶ 49, as evidence that such projects do not
    have regional benefits. Petitioners also argue that FERC
    ignored the testimony of MISO’s expert that benefits from
    projects below 230 kV are “generally smaller and locally
    concentrated.” J.A. 278.
    These arguments are without merit. First, as FERC noted,
    it made clear that its Third Regional Order was only addressing
    regional projects, not interregional ones. See Third Regional
    Order, ¶ 51. Similarly, MISO’s expert testimony was in
    support of MISO’s Second Regional Filing and therefore
    18
    discussed the mostly localized, rather than regional benefits, of
    regional projects, not interregional ones. Compare J.A. 246–
    83 (expert’s regional filing testimony), with J.A. 319–44
    (expert’s interregional filing testimony). Second, Petitioners’
    argument is fatally flawed because the very subject of these
    compliance filings and orders is the development of cost
    allocation methods for interregional projects that both MISO
    and PJM have already determined would benefit their
    respective regions. Indeed, in its original NIPSCO Complaint
    Order, FERC found that the Quick Hit Analysis submitted by
    MISO demonstrated that some interregional projects below
    345 kV provided benefits to both regional systems and thus,
    ordered MISO to lower the voltage threshold to 100 kV so such
    projects could be accounted for in cost allocation. 5 See
    NIPSCO Complaint Order, ¶¶ 129, 131.
    5
    We reject Petitioners’ contention that FERC is barred on appeal
    from relying on the Quick Hit Analysis. Under the principles of SEC
    v. Chenery Corp., 
    318 U.S. 80
     (1943), a court’s review of an agency
    order is limited to the grounds upon which the agency itself based its
    action and “agency decisions may not be affirmed on grounds not
    actually relied upon by the agency.” Calpine Corp. v. FERC, 
    702 F.3d 41
    , 46 (D.C. Cir. 2012) (citing Chenery, 
    318 U.S. at
    87–88).
    Here, while FERC did not explicitly reference the Quick Hit
    Analysis in its Second Regional Order, it relied on the Quick Hit
    Analysis as the basis for its original directive that MISO lower the
    Market Efficiency Project threshold because the Quick Hit Analysis
    identified lower-voltage interregional projects that benefitted both
    regions and therefore should “not be automatically excluded from
    consideration.” NIPSCO Complaint Order, ¶ 131. In response to
    this finding and directive, MISO was required to submit compliance
    filings demonstrating a cost allocation method for these projects.
    These compliance filings and orders are the subject of the instant
    appeal. As such, the Quick Hit Analysis necessarily was a ground
    that FERC actually relied on in its Second Regional Order because
    it serves as the basis for FERC’s original directive that MISO was
    seeking to comply with. See Second Regional Order, ¶¶ 5–6
    19
    Lastly, Petitioners contend that FERC erroneously
    departed from the cost causation principle in Old Dominion by
    requiring exact precision in cost allocation. We disagree. A
    general principle of Old Dominion is that in order for a cost
    allocation method to be consistent with the cost causation
    principle, such method cannot “prevent[] regionally beneficial
    projects from being arbitrarily excluded from cost sharing.”
    Old Dominion, 898 F.3d at 1263. FERC reasonably concluded
    that MISO’s proposed cost allocation method would do just
    that. The SPP Metric measures the benefits that flow to each
    utility zone, i.e., the reduced payments it would have to make
    to MISO, as a result of a project’s impact on MISO’s
    transmission capacity. These benefits are calculated for all of
    the pricing zones within the MISO region, yet MISO would
    only use the portion of these benefits calculated for the pricing
    zone in which the project is physically located for its benefit-
    cost determination. Second Regional Order, ¶ 67. Because
    MISO’s SPP Metric would identify regional benefits, 6
    disregarding such known benefits in cost allocation is
    inconsistent with the cost causation principle. Accordingly,
    (discussing FERC’s findings and directives in the NIPSCO
    Complaint Order as background and the basis for MISO’s current
    compliance filing). Indeed, Petitioners concede this point but instead
    proffer arguments relating to the underlying merits of the Quick Hit
    Analysis, which are jurisdictionally barred as such arguments were
    not raised on FERC’s rehearing of the NIPSCO Complaint Order in
    2017. See 16 U.S.C. § 825l(b).
    6
    We note that Petitioners’ arguments regarding the irrelevance of the
    SPP Metric to the MISO-PJM interregional planning process are
    jurisdictionally barred by Section 313(b) of the Act because
    Petitioners failed to raise it on agency rehearing. See 16 U.S.C. §
    825l(b).
    20
    FERC reasonably rejected MISO’s Second Interregional
    Filing.
    B. FERC’s Replacement Cost Allocation Method
    Because it found that MISO’s outstanding compliance
    requirement to establish a cost allocation method for MISO’s
    share of MISO-PJM interregional projects between 100 kV and
    345 kV remained unfulfilled, FERC exercised its authority,
    pursuant to Section 206 of the Act, to allocate the entirety of
    MISO’s share of the cost of such projects that qualify as Market
    Efficiency Projects using MISO’s current Production Cost
    Metric. Second Interregional Order, ¶¶ 30–31. We find that
    Petitioners fail to meet its burden of demonstrating that
    FERC’s Replacement Method was not just and reasonable. As
    FERC noted in its order, the Production Cost Metric is one that
    MISO had been using to calculate benefits of Market
    Efficiency Projects since their inception in 2007 and is
    regarded by MISO as one of its most reliable measures of the
    net economic impact of a project. Id. ¶ 31; Midwest
    Independent Transmission System Operator, Inc., 
    118 FERC ¶ 61,209
    , ¶ 30. Additionally, FERC explained that MISO
    already uses this metric in its cost allocation method for Market
    Efficiency Projects at 345 kV and above. Second Interregional
    Order, ¶ 31. To be sure, MISO’s expert did testify that lower-
    voltage projects may be more sensitive to incorrect
    assumptions under this metric, thereby flagging a potential
    flaw in the use of this metric. However, Petitioners have not
    demonstrated that the use of this metric is so unreasonable or
    deficient as to warrant reversal. 7 Rather, at bottom, Petitioners
    7
    Petitioners’ arguments regarding FERC purportedly ignoring its
    evidence concerning a specific interregional project, Project NC-11,
    are not properly before the Court because such evidence is not in the
    administrative record as FERC rejected Petitioners’ late-filed
    21
    simply argue that, in its view, a better method exists. “But
    FERC is not required to choose the best solution, only a
    reasonable one.” Petal Gas Storage, LLC v. FERC, 
    496 F.3d 695
    , 703 (D.C. Cir. 2007) (citation omitted). It is not our job
    to determine that “FERC made the better call,” rather, our
    “important but limited role is to ensure that the Commission
    engaged in reasoned decisionmaking—that it weighed
    competing views, selected a . . . formula with adequate support
    in the record, and intelligibly explained the reasons for making
    that choice.” FERC v. Elec. Power Supply Ass’n, 
    577 U.S. 260
    ,
    295 (2016). FERC has satisfied this standard. Notably, MISO
    still has the right to propose its own cost allocation method for
    FERC to review, and if found to be just and reasonable, to
    approve. See Second Interregional Order, ¶ 31 n.40;
    Interregional Rehearing Order, ¶ 30. Accordingly, we affirm
    FERC’s Replacement Method.
    IV.
    For the foregoing reasons, we deny the petitions for review
    and affirm FERC’s orders in all respects.
    So ordered.
    pleading containing this evidence. See Interregional Rehearing
    Order, ¶ 15.