-
759 F.2d 898
245 U.S.App.D.C. 172
HOLLISTER RANCH OWNERS' ASSOCIATION, Santa Barbara Citizens
for Environmental Defense, Petitioners,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Fred H. Bixby Ranch Company, Pacific Alaska LNG Company, et
al., Transwestern Pipeline Company, Public
Utilities Commission of the State of
California, Intervenors.
FRED H. BIXBY RANCH COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Public Utilities Commission of the State of California,
Pacific Alaska LNG Company, et al., Indian Center
of Santa Barbara, et al., Intervenors.Nos. 84-1010, 84-1029.
United States Court of Appeals,
District of Columbia Circuit.Argued February 15, 1985.
Decided April 16, 1985.Petitions for Review of an Order of the Federal Energy Regulatory commission.
John R. Staffier and Jeffrey F. Liss, Washington, D.C., with whom George A. Avery and Kenneth G. Jaffe, Washington, D.C., were on brief, for petitioners.
John H. Conway, Atty., F.E.R.C., Washington, D.C., with whom Jerome M. Feit, Sol., F.E.R.C., Washington, D.C., was on brief, for respondent.
1Thomas D. Clarke, Los Angeles, Cal., with whom Jane C.L. Goichman, E.R. Island and Michael D. Gayda, Los Angeles, Cal., were on brief, for intervenors Pacific Alaska LNG Co., et al. Douglas Kent Porter entered an appearance for intervenors.
2J. Calvin Simpson, San Francisco, Cal., and Ellen S. LeVine, San Jose, Cal., were on brief for intervenors the People of the State of Cal., et al.
3Robert H. Loeffler, Washington, D.C., was on brief for amicus curiae State of Alaska urging affirmance of the Commission's order.
4Thomas George Wagner and Cheryl Foley, Houston, Tex., entered appearances for intervenor Transwestern Pipeline Co.
5Before MIKVA and EDWARDS, Circuit Judges, and MacKINNON, Senior Circuit Judge.
6Opinion for the Court filed by Circuit Judge MIKVA.
7Opinion concurring in part and dissenting in part filed by Senior Circuit Judge MacKINNON.
MIKVA, Circuit Judge:
8At issue in this case is the Federal Energy Regulatory Commission's conditional approval of a proposal to construct a liquified natural gas ("LNG") terminal near Point Conception, California. FERC approved the project in 1979, but this court remanded the matter to the Commission in 1980 for further consideration of seismic data. In 1983, following new evidentiary hearings, FERC again found the site "seismically suitable." Petitioners, all of whom live or own property near Point Conception, challenge the merits of that determination and also contend that the 1979 and 1983 orders should be vacated as moot because of alleged abandonment of the proposal by its original backers.
9We agree that the 1979 order must be vacated as moot, and we vacate the 1983 order on different grounds.
I.
10In the late 1970's, a group of companies applied to FERC and to the California Public Utilities Commission ("CPUC") for permission to construct and operate an LNG terminal at Little Cojo Bay, near Point Conception, California. The terminal was to receive and regassify LNG shipped from Alaska and Indonesia.
11Concerns were raised about seismic risks at the proposed site from the very beginning. In April 1978, a geologist hired by the Hollister Ranch Owners' Association ("Hollister") found an active earthquake fault on the site, and several other on-site active faults have been discovered since then. In 1978, the CPUC nonetheless approved the project but conditioned its approval on further seismic studies to be conducted by the applicants. Adopting the recommendations of its Administrative Law Judge ("ALJ"), FERC did the same in 1979, despite the position of the Commission's staff that no LNG terminal should be approved on any site containing an active earthquake fault. The staff adhered to this position throughout the later proceedings on remand. See Pacific Alaska LNG Co., 19 FERC Rep. (CCH) p 63,086, at 65,270 (June 23, 1982).
12The staff reasoned that "[t]here is such uncertainty in the phenomenon of surface faulting that the current state-of-the-art is inadequate to allow the safe design of an LNG facility near an active fault." Pacific Alaska LNG Co., 8 FERC Rep. (CCH) p 63,032, at 65,365 (Aug. 13, 1979). The ALJ rejected this "per se or absolutist" position as unacceptable, based in part on his impression of the need for an LNG terminal in California. He found that there was "a pressing need" for the gas volumes at issue, and that there were "no available alternatives" to the LNG proposal. Id. at 65,319. In connection with the staff's argument that the mere presence of an on-site earthquake fault should disqualify Little Cojo Bay as an acceptable site for an LNG facility, the ALJ noted:
13... Staff's position is based on very remote possibilities and a refusal to consider the geoseismic particulars of a given site location. This is especially disturbing since the entire coast of California is seismically active and Staff's per se approach threatens to impose on the state of California a no-growth energy policy respecting LNG facilities directly contrary to the interest of the citizens of that state as expressed in the LNG Terminal Act.
14Id. at 65,346.
15Nevertheless, the ALJ conditioned his approval of the project on the applicants' completion of further seismic investigations at the site. He also conditioned his approval on prompt completion of the project: gas sales from the facility had to commence by February 15, 1983. See id. at 65,391. FERC affirmed the ALJ's conditional approval and adopted his decision without relevant changes. See Pacific Alaska LNG Co., 9 FERC Rep. (CCH) p 61,041 (Oct. 12, 1979).
16Several parties, including the current petitioners, sought review in this court of FERC's 1979 approval of the Point Conception proposal. While the case was pending, additional information became available on the seismic condition of the Little Cojo site. In April 1980, the court granted Hollister's motion to remand the matter to FERC to allow the Commission to consider the new information in the first instance.
17In response to the remand, FERC ordered new evidentiary hearings on the seismic issues. By this point in the proceedings, however, some participants had dropped out of the project, and the applicants had been forced to give up their rights to a dedicated supply of Indonesian gas. The project sponsors nonetheless "remain[ed] committed" to the project, and the Commission therefore decided to proceed with consideration of Little Cojo's seismic suitability:
18The seismic issues at the Little Cojo site ... fall exclusively within the Commission's jurisdiction, are ripe for decision now, and will entail a significant measure of time for hearing and analysis. Accordingly, ... the Commission will defer consideration of nonseismic issues at this time, pending resolution of the seismic issues by our Commission and the CPUC....
19Pacific Alaska LNG Co., Nos. CP75-140 et al., slip op. at 4 (March 2, 1981).
20After hearing new evidence, the ALJ determined that "the remand record does not warrant a change in the conclusion of the prior Initial Decision that the potential seismic hazards at the site do not present unacceptable risks to public safety or project reliability." Pacific Alaska LNG Co., 19 FERC Rep. (CCH) p 63,086, at 65,272 (June 23, 1982). He therefore affirmed the 1979 Initial Decision "to the effect that the Little Cojo Bay site is seismically suitable for the safe and reliable construction and operation of an LNG receiving terminal." Id. at 65,288.
21The Commission affirmed the ALJ's decision. Pacific Alaska LNG Co., 25 FERC Rep. p 61,005 (Oct. 4, 1983). In response to Hollister's argument that the proceedings should be dismissed as moot because the industrial sponsors were no longer in a position to go forward, FERC noted that the sponsors might choose to proceed at some time in the future, and concluded that a resolution of the seismic issues could therefore prove useful:
22If we find Little Cojo to be seismically suitable, they can proceed with the projects when they are needed in the future; if we find the site to be unsuitable, further efforts to preserve the projects would not be taken.... [A]ll we can say with any certainty now is that the future is uncertain. At some point, LNG may be needed to meet the requirements of gas consumers in California.
23Id. at 61,034.
II.
24Intervening in this case, the People of the State of California and the California Public Utilities Commission contend that FERC's 1979 and 1983 orders are not yet ripe for review because they are merely intermediate steps in an ongoing administrative process. In essence, California argues that petitioners should have to wait until a viable LNG project is actually approved before challenging the 1979 and 1983 orders.
25Even assuming that the collateral challenge envisioned by California would not be time-barred, we do not agree that review at this time would be premature. Cf. Baltimore Gas & Electric Co. v. NRDC, 462 U.S. 87, 103 S. Ct. 2246, 76 L. Ed. 2d 437 (1983) (reviewing NRC regulations setting environmental cost estimates to be used in nuclear power plant licensing). The 1983 order "terminated" the proceedings; it appears that, as far as FERC is concerned, the ball is now in the project applicants' court. If the applicants never decide to go forward--a possibility the record suggests is hardly remote--California's view of ripeness would prevent the petitioners from ever being able to challenge the 1983 order. Petitioners would still be aggrieved by the order, though; they claim credibly that the value of their property is diminished by FERC's official, purportedly final declaration that a neighboring site is "seismically suitable" for an LNG terminal.
26Our conclusion that petitioners' challenges are now ripe for judicial consideration is buttressed by FERC's conspicuous failure to raise a ripeness or exhaustion objection. The judicial policy against unwarranted and premature interference with continuing agency decision-making--the basis for California's ripeness argument--is more typically expressed in terms of the exhaustion requirement; indeed, California itself argues that what is missing in this case is "[e]xhaustion of the administrative process." Brief for Intervenors the People of the State of California and the Public Utilities Commission of the State of California at 13. This court has observed in the past that an agency's failure to make such an argument for itself may indicate that the review sought would not in fact unduly disrupt agency decisionmaking:
27The agency's failure to insist upon exhaustion ... suggests that, in [the agency's] view, the costs--in terms of interfering with agency proceedings, creating an incentive to ignore agency processes in the future, and depriving the agency of a greater opportunity to apply its expertise or of a chance to "correct its own errors"--do not outweigh the benefits of this court's immediate consideration of [the] petition.
28Asarco, Inc. v. EPA, 578 F.2d 319, 321 n. 1 (D.C.Cir.1978). In this case, FERC may well have decided not to argue ripeness or exhaustion for the sensible reason that requiring judicial review to be sought later instead of now would preserve much of the uncertainty the order attempted to remove.
III.
29In United States v. Munsingwear, 340 U.S. 36, 71 S. Ct. 104, 95 L. Ed. 36 (1950), the Supreme Court held that lower court decisions should be vacated if they become moot pending appellate review.
30That procedure clears the path for future relitigation of the issue between the parties and eliminates a judgment, review of which was prevented through happenstance. When that procedure is followed, the rights of all parties are preserved; none is prejudiced by a decision which in the statutory scheme was only preliminary.
31340 U.S. at 40, 71 S. Ct. at 107. The Court later made clear that the same procedure should be followed when mootness prevents review of administrative orders. See A.L. Mechling Barge Lines, Inc. v. United States, 368 U.S. 324, 82 S. Ct. 337, 7 L. Ed. 2d 317 (1961).
32These cases require us to vacate FERC's 1979 approval of the Point Conception proposal. When the applicants failed to meet the Commission's February 1983 deadline for the completion of the project, the 1979 authorization expired according to its own terms. Such expiration is perhaps the most classic way in which a challenge to an order can become moot. See, e.g., Tennessee Gas Pipeline Co. v. FPC, 606 F.2d 1373 (D.C.Cir.1979); Alton & So. Ry. Co. v. International Ass'n of Machinists, 463 F.2d 872, 877-78 (D.C.Cir.1972). Even FERC concedes that "the conditional certificates issued in 1979 are no longer valid." Brief for Respondent at 20. It follows that the 1979 order is now unreviewable and thus fits squarely within the spirit as well as the letter of the Munsingwear rule.
IV.
33Unlike the 1979 order, FERC's 1983 order has not expired, but neither does it grant authority that may be used by private parties in the future. The 1983 order does not give anyone permission to do anything; it purports to be merely declaratory. Since the 1983 order is still in effect, petitioner's challenge to the order is not precluded by mootness, and the Munsingwear rule appears not to apply. Nonetheless, we conclude that the 1983 decision must be vacated for reasons closely tied to the attenuated and abstract nature of the question FERC posed for itself.
34Assessment of the action FERC took in 1983 is made difficult by the ambiguity of the Commission's order. FERC found that "Little Cojo is seismically suitable for the safe and reliable construction and operation of an LNG receiving terminal." Pacific Alaska LNG Co., 25 FERC Rep. (CCH) p 61,005, at 61,034 (Oct. 4, 1983). That language could be read to mean simply that Little Cojo Bay is not the crater of Mauna Loa; i.e., that FERC refuses to rule out the Point Conception site on seismic considerations alone, although it reserves judgment on whether the benefits of the project outweigh all of its costs, including the seismic risks. Petitioners, however, read the order to conclude entirely FERC's considerations of seismic risks at Point Conception and hence to preclude, absent new seismic evidence, any weighing of these risks in future proceedings on the LNG project.
35FERC itself apparently shares petitioners' view of the order. The text of the order suggests that the Commission intends it to have broad preclusive effect: the Commission acted "to resolve the seismic issues" and deferred consideration only of "non-seismic issues." Id. at 61,034-35. Similarly, the ALJ's decision, affirmed by the Commission, states that "[i]t is clear that the seismic conditions, risks and suitability of the site in no way depend upon or vary with changes in project need, financial sponsorship, gas supply or the other non-seismic factors mentioned above." 19 FERC Rep. (CCH) p 63,086, at 65,287. At oral argument, moreover, counsel for the government described the 1983 order as conclusively settling all seismic questions regarding the Point Conception site, subject only to reconsideration based on new evidence.
36Perhaps, on an appropriate record, FERC could proceed in this fashion, conclusively ruling out in advance a set of environmental concerns as insignificant; perhaps not. We need not decide that question, because the record in this case clearly does not support the far-reaching conclusion that seismic risks at Little Cojo Bay are so miniscule that they could never tip the balance in a reasoned determination whether to approve plans for an LNG terminal, no matter how slight the need for the project and no matter how worrisome its other costs. To begin with, at no point in these proceedings did the Commission articulate, let alone justify, criteria--numerical or otherwise--for identifying risks of no possible importance.
37More importantly, the Commission's unarticulated test for negligible risk was apparently tied closely to its assessment in the late 1970's of the need for LNG in California--an assessment which everyone agrees is now hopelessly obsolete. As discussed above, the Commission's staff has argued consistently that scientific understanding of surface faulting is so meager that the presence of active faults on a site should rule it out as a possible location for an LNG terminal. This position was rejected in 1979 in large part because of considerations having nothing to do with the seismic characteristics of Little Cojo Bay: the ALJ feared that the staff's approach would disqualify much of the California coast, and both the ALJ and the Commission perceived a pressing need for an LNG receiving terminal somewhere in California. On remand, neither the ALJ nor the Commission offered any new reason for rejecting the staff's position; the prior conclusion was reaffirmed solely because, as the staff conceded, no new seismic evidence warranted a change in policy, and because neither the ALJ nor the Commission was willing to consider new non-seismic evidence pertaining to the need for the facility.
38The record thus provides patently inadequate support for the 1983 order as construed both by petitioners and by the Commission. The order could perhaps be saved by reading it more narrowly to rule only that seismic risks alone do not permanently disqualify Little Cojo Bay as a potential site for an LNG plant. Such a reading, however, would deprive the order of any significant legal content. Although in general "there is no law ... against the Commission's giving comically irrelevant responses," Transwestern Pipeline Co. v. FERC, 747 F.2d 781, 786 (D.C.Cir.1984), under the circumstances we decline to depart from the Commission's own interpretation of its 1983 decision solely so that we may affirm the order as vacuous.
39Our refusal to transform FERC's decision into a harmless nullity is based in part on the terms of the Administrative Procedure Act, which authorize agencies to issue declaratory orders only "to terminate a controversy or remove uncertainty," 5 U.S.C. Sec. 554(e). FERC was faced with no live "controversy" in 1983, since the sponsors of the Point Conception project were by their own admission no longer prepared to go forward. Although a genuinely conclusive evaluation of the seismic risks could conceivably have alleviated some confusion, FERC was not in a position to make such an evaluation, and an order which in reality concluded next to nothing could not in any meaningful way "remove uncertainty." On the contrary, FERC's 1983 order has served only to exacerbate uncertainty by placing matters in a "peculiar, uncertain limbo," and "that uncertainty this court removes by vacating the order." Tennessee Gas Pipeline Co. v. FPC, 606 F.2d 1373, 1380, 1382 n. 40 (D.C.Cir.1979).
V.
40We therefore vacate both of the orders before us. The 1979 order we vacate as moot, A.L. Mechling Barge Lines, Inc. v. United States, 368 U.S. 324, 82 S. Ct. 337, 7 L. Ed. 2d 317 (1961), and the 1983 order as without substantial support in the record, Natural Gas Act Sec. 19(b), 15 U.S.C. Sec. 717r(b).
41The Commission has compiled a lengthy and instructive record in the proceedings giving rise to the vacated orders and is under no obligation to ignore its results or to retrace its steps. In any future proceedings concerning the Point Conception site, FERC may incorporate by reference any or all of the record developed in these proceedings and may rely to the extent it deems appropriate on the evidence contained in the record. The orders issued in these proceedings, however, may not themselves be accorded any preclusive legal effect.
42It is so ordered.
43MacKINNON, Senior Circuit Judge (concurring in part and dissenting in part):
44The FERC decision that Point Conception is seismically suitable to be a liquified natural gas terminal site has no legal effect since it does not constitute a final judgment on an application to construct and operate a liquified natural gas receiving and regassification facility. The majority seems to reach this conclusion, Maj.Op. at 901 - 902, but then reviews the decision of the FERC ultimately to find that it was not supported by substantial evidence. The majority apparently takes this tack so that it may on the merits reverse the FERC's declaratory order, an order that the FERC concedes gives nobody the right to do anything. The majority confidently declares the 1970's data on the need for LNG in California are hopelessly obsolete. No doubt they are, but reaching this conclusion without so much as citation to the Wall Street Journal sits ill with telling the Commission their lengthy and expensive investigation of the Point Conception site is not supported by substantial evidence.
45The majority states that "... under the circumstances we decline to depart from the Commission's own interpretation of its 1983 decision solely so that we may affirm the order as vacuous." Maj.Op. at 903. But the majority should depart from the Commission's interpretation of its own decision if that interpretation is wrong, as it manifestly is. It should not adopt an incorrect interpretation just so it can reverse on the merits what is really just a free standing, nonbinding advisory opinion, no matter how ill founded that opinion may be.
46If the FERC order has no legal effect, moreover, it is rather difficult to see how there is any "controversy" over which this court has jurisdiction. This court cannot reach the merits of what is merely the FERC's non-final, tentative conclusion about what seismic investigation of the site has revealed so far, beyond vacating the order insofar as it purports to be a final "declaratory order" under 5 U.S.C. Sec. 554(e). The 1983 order, stripped of its pretenses to be "declaratory" under Sec. 554(e), should be taken as the FERC's opinion that seismic risks alone do not permanently disqualify Little Cojo Bay as a LNG terminal site. But this interpretation, according to the majority, would deprive it of "significant legal content." Maj.Op. at 903. Even so, this does not justify construing the FERC's order as something that it clearly is not, a declaratory order, so that the underlying issue of the merits of the proposed site may be reached. What the majority may have inadvertently accomplished, inter alia, is the creation of a precedent that the Commission can issue such ethereal declaratory orders, quite apart from any application. The majority declares it does not reach this issue of whether FERC can issue such orders, Maj.Op. at 902, but it is unclear how this declaration is consistent with reviewing just such an order on its merits. The majority broadens the scope of 5 U.S.C. Sec. 554(e), to say the least. It is hoped that the majority's opinion will be viewed as vacating the 1983 declaratory order as lacking legal effect and criticizing in dicta the FERC's efforts. This seems to be, in fact, one of the two independent, if perhaps inconsistent, positions espoused by the majority. Nonetheless, the 1979 and 1983 orders are vacated, the first order for the right reason, the second order for reasons less clearly so, and in these results I concur.
Document Info
Docket Number: 84-1010
Citation Numbers: 759 F.2d 898, 245 U.S. App. D.C. 172, 1985 U.S. App. LEXIS 28855
Filed Date: 4/16/1985
Precedential Status: Precedential
Modified Date: 9/9/2019