Mexichem Specialty Resins, Inc. v. Environmental Protection Agency ( 2015 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued November 19, 2014             Decided May 29, 2015
    No. 12-1260
    MEXICHEM SPECIALTY RESINS, INC.,
    PETITIONER
    v.
    ENVIRONMENTAL PROTECTION AGENCY AND GINA
    MCCARTHY,
    RESPONDENTS
    AIR ALLIANCE HOUSTON, ET AL.,
    INTERVENORS
    Consolidated with 12-1265, 12-1266, 12-1267
    On Petitions for Review of Final Actions
    of the United States Environmental Protection Agency
    Douglas J. Behr and Jean-Cyril Walker argued the causes
    for Industry Petitioners. With them on the briefs were David
    M. Friedland, Kristen H. Gladd, Marc D. Machlin, and
    Christopher D. Jensen. Eric P. Gotting and Peter L. de la
    Cruz entered appearances.
    Angeline Purdy, Attorney, U.S. Department of Justice,
    argued the cause for respondent. With her on the brief were
    2
    Sam Hirsch, Acting Assistant Attorney General, and Mark
    Kataoka, Counsel, U.S. Environmental Protection Agency.
    Emma C. Cheuse argued the cause for respondent-
    intervenors. With her on the brief was James S. Pew.
    Before: ROGERS, KAVANAUGH and PILLARD, Circuit
    Judges.
    Opinion for the Court filed by Circuit Judge PILLARD.
    Opinion dissenting in part filed by Circuit Judge
    KAVANAUGH.
    PILLARD, Circuit Judge: This case concerns the
    production of polyvinyl chloride (PVC), one of the world’s
    most common and versatile plastics, used in everything from
    water pipes to credit cards. As is true of the making of so
    many good things, however, the less one knows, the better
    one sleeps. PVC production results in the emission of more
    than a dozen known or suspected carcinogens and other
    hazardous air pollutants, a miasma that includes the known
    carcinogens 1,3-butadiene, benzene, and vinyl chloride. See
    Proposed PVC Rule, 76 Fed. Reg. 29,528, 29,532 (May 20,
    2011). Congress has charged the Environmental Protection
    Agency with the difficult task of protecting the health of the
    American public by ensuring that industry reduce to the
    greatest extent it can emissions into the atmosphere of
    carcinogens and similarly dangerous chemicals.
    In 2012, EPA promulgated a Rule setting first-time-ever
    limits on the emission of most hazardous air pollutants from
    PVC production. Petitioners, PVC manufacturers, challenge
    the Rule. They contend that many of the Rule’s emissions
    limits should be vacated on the grounds that EPA did not
    3
    follow required rulemaking procedures, used faulty data in
    setting some of the limits, and poorly designed certain aspects
    of the regulation. They also ask the court to set aside some of
    the Rule’s monitoring and compliance requirements.
    Petitioners raised many of these objections for the first time in
    petitions for reconsideration with EPA that are awaiting
    resolution. The Clean Air Act therefore precludes the court
    from reviewing them now, and we decline Petitioners’ request
    that we stay EPA’s Rule pending the agency’s completion of
    its reconsideration. As to those challenges to the Rule that are
    ready for our review, we hold that EPA acted reasonably and
    in accordance with the Clean Air Act. We therefore deny the
    petitions.
    I.
    The Clean Air Act requires EPA to promulgate
    regulations limiting the emission of hazardous air pollutants
    from      “major      sources”     and     “area     sources.”
    42 U.S.C. § 7412(d)(1). Those pollutants are specified on a
    list of hazardous air pollutants Congress established in 1990
    in an amendment to the Act.1 42 U.S.C. § 7412(b)(1); see
    Nat’l Lime Ass’n v. EPA, 
    233 F.3d 625
    , 628-29, 633-34 (D.C.
    Cir. 2000). For listed pollutants, EPA must set emissions
    standards in two steps: First EPA sets a baseline, or “MACT
    floor,” derived from data about the cleanest-performing
    similar sources already in the market; and, second, EPA
    investigates methods that may not already be in use to discern
    1
    The difference between major sources and area sources is size: A
    “major source” is a stationary source that has the potential to emit
    10 tons per year of any single hazardous air pollutant or 25 tons per
    year of any combination of hazardous air pollutants,
    42 U.S.C. § 7412(a)(1); any smaller stationary source is an “area
    source,” 
    id. § 7412(a)(2).
                                     4
    whether even more stringent, “beyond-the-floor” standards
    are achievable to further reduce emissions.2              See
    42 U.S.C. §§ 7412(d)(2), (d)(3); Nat’l 
    Lime, 233 F.3d at 629
    ,
    634.
    The Rule under review establishes limits on hazardous air
    pollutant emissions from major and area sources at various
    points in the PVC production process. See PVC Rule, 77 Fed.
    Reg. 22,848, 22,851-55 (Apr. 17, 2012); 
    id. at 22,857-59
    (summarizing major source emissions standards); 
    id. at 22,862-63
    (summarizing area source emissions standards).
    The Rule limits the concentration of hazardous air pollutants
    that may remain in PVC resins (the “stripped resins” limits),
    the concentration of hazardous air pollutants that can be
    present in exhaust vented into the atmosphere (the “process
    vent” limits), and the concentration of hazardous air
    pollutants that may be dissolved in wastewater (the “process
    wastewater” limits). Proposed PVC Rule, 76 Fed. Reg. at
    29,531-35; see also 40 C.F.R. § 63.12005. The Rule also
    requires the installation of monitoring equipment and the
    implementation of testing policies and workplace practices,
    all of which are designed to ensure initial and continuous
    compliance with EPA’s emissions limits. See PVC Rule, 77
    Fed. Reg. at 22,859-62 (summarizing compliance
    requirements).
    The Rule stems from Congress’s 1990 amendments to the
    Clean Air Act. In those amendments, Congress (1) mandated
    that EPA regulate over one hundred specified hazardous air
    2
    “MACT” is short for “Maximum Achievable Control
    Technology.” Nat’l 
    Lime, 233 F.3d at 630
    . MACT floors are
    “floors” because they represent the least stringent emissions limits
    EPA may impose, “even though they in fact establish maximum
    emission levels” for manufacturers. 
    Id. at 629.
                                  5
    pollutants, Nat’l 
    Lime, 233 F.3d at 633
    , and (2) required EPA
    to review within ten years of the Act’s amendment all of its
    preexisting emissions standards to ensure that they cover
    listed pollutants. 42 U.S.C. § 7412(q)(1); see Mossville Envtl.
    Action Now v. EPA, 
    370 F.3d 1232
    , 1236-37 (D.C. Cir. 2004).
    As of 1990, EPA already had a longstanding regulation
    limiting the emission of vinyl chloride, one of the hazardous
    air pollutants from PVC sources. 41 Fed. Reg. 46,560 (Oct.
    21, 1976). Congress’s amendments required EPA to revisit
    its pre-1990 vinyl chloride emissions standard and expand it
    to regulate all the newly listed hazardous air pollutants from
    PVC sources.
    EPA got part of the way there. It promulgated a rule in
    1992, the “HON Rule,” that regulated emissions from the
    production of ethylene dichloride and vinyl chloride
    monomer, two inputs to PVC production.3 
    Mossville, 370 F.3d at 1237
    . The HON Rule did not, however, regulate
    emissions arising from the production of PVC itself. 
    Id. Because the
    HON Rule did not cover PVC production, EPA
    still needed to undertake another rulemaking to comply with
    Congress’s mandate that it revisit and expand its earlier vinyl
    chloride regulation. 
    Id. That second
    Rule is at issue here.
    EPA began development in 1998 of a version of the Rule
    that it promulgated in 2002. See 67 Fed. Reg. 45,886, 45,889
    (July 10, 2002). In that Rule, EPA readopted its pre-1990
    limits for vinyl chloride emissions from PVC production,
    determining that those limits were a good estimate of the
    MACT floors for vinyl chloride. 
    Mossville, 370 F.3d at 1237
    .
    In a challenge to the 2002 rule’s lawfulness and rationality
    3
    “HON” is short for “Hazardous Organic NESHAP.” See
    
    Mossville, 370 F.3d at 1237
    . “NESHAP” is short for “National
    Emission Standards for Hazardous Air Pollutants.” 
    Id. at 1235.
                                   6
    under the Clean Air Act, we sustained EPA’s judgment. 
    Id. at 1234,
    1237, 1242. We found the Rule flawed in part,
    however, for its failure to set limits on all of the remaining
    hazardous air pollutants the Act requires EPA to regulate. 
    Id. at 1242-43.
    EPA argued that the same technologies that
    remove vinyl chloride from PVC emissions—“stripping,
    scrubbing, incineration”—reduce the emission of all
    hazardous air pollutants to a similar degree and that the
    emissions limit for vinyl chloride therefore could stand in as a
    “surrogate” for setting individual limits on the emission of
    other hazardous air pollutants. 
    Id. at 1237.
    We found EPA’s
    judgment on that point unsupported by the record and vacated
    and remanded the Rule for further explanation and
    reconsideration, as appropriate. 
    Id. at 1243.
    In 2009, EPA began issuing information requests to PVC
    manufacturers and otherwise gathering the data necessary to
    set MACT floors for non-vinyl chloride hazardous air
    pollutants from PVC production. EPA issued a proposed rule
    in 2011 and accepted comments for a period of two and a half
    months. See Proposed PVC Rule, 76 Fed. Reg. at 29,528; 76
    Fed. Reg. 42,613 (July 19, 2011). After the close of the
    public comment period, PVC manufacturers continued to
    submit data to EPA, including data the manufacturers
    recorded from sampling and testing independently of what
    EPA’s data requests required. In response to some of that
    new information, submitted after the comment period closed,
    EPA revised its Rule. EPA promulgated the Rule in April
    2012. See PVC Rule, 77 Fed. Reg. 22,848. Industry
    Petitioners promptly petitioned EPA for reconsideration and
    sought judicial review, arguing that EPA had given
    Petitioners inadequate notice and opportunity to comment on
    EPA’s post comment period revisions.             EPA granted
    reconsideration on several of Petitioners’ claims.
    7
    II.
    Petitioners challenge three aspects of EPA’s Rule. First,
    Petitioners challenge the Rule’s limit on the concentration of
    organic hazardous air pollutants in process wastewater from
    existing major sources.         Petitioners argue that EPA
    established that limit without providing adequate notice or
    opportunity to comment. They also argue that the limit is not
    a logical outgrowth of the proposed rule and that EPA based
    the limit on data that was incorrect and incomplete.4
    4
    On the eve of oral argument, EPA and Petitioners reached a
    settlement on EPA’s Rule setting wastewater limits for area
    sources. They filed a joint unopposed motion to sever their
    challenge to that Rule and hold it in abeyance, which this court
    granted. See Mexichem Specialty Resins, Inc. v. EPA, No. 12-1260
    (D.C. Cir. Dec. 17, 2014) (order granting joint unopposed motion to
    sever and hold in abeyance the challenge to the area source
    wastewater limit).     The same emissions limit that governs
    wastewater from area sources also governs new major sources.
    That limit was based on a single data point that EPA acknowledges
    to be erroneous. See Resp. Br. 21, 35; PVC Rule, 77 Fed. Reg. at
    22,854, 22,863. Neither EPA nor Intervenors oppose vacatur of
    that emissions limit. See Resp. Br. 35-36; Int. Br. 20, 33. The
    parties did not, however, move to sever and hold in abeyance the
    new major source wastewater emissions limit when they made their
    motion with respect to the area source emissions limit.
    The court, however, is barred from vacating or staying the new
    major source wastewater limit. Petitioners failed to preserve their
    challenges to the wastewater emissions limits, including the new
    major source wastewater limit, and EPA did not waive its
    exhaustion defense. Petitioners were therefore required to show
    irreparable harm from the existence of the new major source
    wastewater limit to obtain a right to a stay or vacatur. Petitioners
    8
    Second, Petitioners challenge the Rule’s limits on
    hazardous air pollutants emitted through process vents.
    EPA’s proposed rule set limits applicable to all PVC process
    vents. During the rulemaking, however, PVC manufacturers
    notified EPA that some PVC manufacturers also discharge
    exhaust generated by other (non-PVC) processes through
    PVC process vents. See PVC Rule, 77 Fed. Reg. at 22,851.
    In response, EPA created a hybrid category in the final
    Rule—“PVC-combined” process vents—setting distinct
    emissions limits for process vents that comingle fumes from
    PVC and non-PVC sources. 40 C.F.R. § 63.12005; see PVC
    Rule, 77 Fed. Reg. at 22,865, 22,869. Petitioners raise a spate
    of objections to EPA’s process vent limits and its decision to
    create the separate PVC-combined process vent category.
    They argue that EPA established the PVC-combined process
    vent limits without providing adequate notice or opportunity
    to comment.       Petitioners claim they were denied an
    opportunity to provide EPA with supplemental data they
    believe is necessary to develop accurate PVC-combined
    process vent limits. Petitioners also maintain that the PVC-
    combined process vent emissions limits as applied to non-
    PVC source emissions when they discharge through a
    common vent with PVC source emissions unlawfully conflict
    with the limits that already apply to the non-PVC sources.
    have not, however, alleged or shown any harm arising from the
    existence of the limit. Indeed, the record contains no evidence that
    Petitioners have any plans to build new major sources. The Clean
    Air Act therefore prevents the court from staying or vacating the
    new major source wastewater limit.
    Because the limits for area sources have been severed and the
    limits for new major sources are not properly before us, we limit
    our discussion in the text to the challenge to the existing major
    source limits.
    9
    Petitioners further contend that EPA’s Rule irrationally fails
    to subcategorize process vents on the basis of their emissions
    control technology.
    Third and finally, Petitioners challenge some of the
    Rule’s continuous compliance and monitoring provisions.
    They argue that EPA’s regulations governing when
    manufacturers may open “bypasses” and mandating the
    installation of monitoring equipment on “pressure relief
    devices” are arbitrary and capricious.5 Petitioners also
    contend that regulations requiring that all bypasses be
    equipped with devices that detect when they are opened are
    “beyond-the-floor” MACT requirements that EPA unlawfully
    imposed without engaging in cost-benefit analysis as required
    by the Clean Air Act.
    We deny the petitions.        Petitioners did not raise
    procedural or merits objections to the wastewater limit during
    the notice and comment period. Petitioners also did not raise
    procedural objections to the PVC-combined process limit
    during the notice and comment period or challenge the
    5
    Bypasses, as their names suggest, allow fumes to bypass
    emissions controls and discharge directly into the atmosphere.
    See 40 C.F.R. § 63.12005 (“Bypass means diverting a process vent
    or closed vent system stream to the atmosphere such that it does not
    first pass through an emission control device.”).
    Pressure relief devices are safety devices that, in the process of
    relieving pressure, can release fumes directly into the atmosphere.
    See 40 C.F.R. § 63.12005 (“Pressure relief device means a safety
    device used to prevent operating pressures from exceeding the
    maximum allowable working pressure of the process component.
    A common pressure relief device is a spring-loaded pressure relief
    valve.”).
    10
    rationality of the limit itself. The Clean Air Act prevents the
    court from considering those objections because Petitioners
    did not initially preserve them in the administrative process,
    and EPA is still considering them in a pending
    reconsideration proceeding. Given the absence of any
    showing of a likelihood of irreparable harm, we also decline
    to stay the effectiveness of the Rule until EPA completes its
    reconsideration.
    We also reject each of Petitioners’ claims that we are
    now able to review on its merits. EPA’s PVC-combined
    process vent limits do not conflict with emissions limits
    applicable to other sources that discharge through PVC-
    combined process vents. EPA reasonably chose not to
    subcategorize process vents on the basis of their control
    technology.    EPA’s bypass and pressure relief device
    regulations are reasonable compliance and monitoring
    requirements, and Petitioners’ argument that the bypass-
    detection regulation is a “beyond-the-floor” MACT
    requirement lacks merit.
    III.
    Several of Petitioners’ challenges to the Rule are barred
    because they were not raised during the notice and comment
    period. See 42 U.S.C. § 7607(d)(7)(B). Under the Clean Air
    Act, “the only objections that may immediately be raised
    upon judicial review are those that were raised during the
    public comment period. Objections raised for the first time in
    a petition for reconsideration must await EPA’s action on that
    petition.” Util. Air Regulatory Grp. v. EPA (UARG), 
    744 F.3d 741
    , 747 (D.C. Cir. 2014). That bar extends both to
    substantive and procedural challenges and applies even if the
    objections could not have been raised during the comment
    period. See 42 U.S.C. § 7607(d)(9)(D)(ii); UARG, 
    744 F.3d 11
    at 747; Am. Petroleum Inst. v. Costle, 
    665 F.2d 1176
    , 1192
    (D.C. Cir. 1981). That requirement serves the important
    function of assuring that the agency has had an opportunity to
    explicate and evaluate objections before we review them. See
    generally Appalachian Power Co. v. EPA, 
    249 F.3d 1032
    ,
    1065 (D.C. Cir. 2001); Appalachian Power Co. v. EPA, 
    135 F.3d 791
    , 799 n.14 (D.C. Cir. 1998).
    Petitioners (1) did not raise their objections to the
    adequacy of notice and comment during the notice and
    comment period, (2) did not object that the final rule was not
    a logical outgrowth of the proposed rule, (3) did not object to
    the reasonableness of the PVC-combined process vent
    emissions limits, and (4) did not object to the wastewater
    limits. See Pet. Br. at 37, 48 (conceding failure to raise the
    foregoing objections during the notice and comment period).
    Those claims are therefore barred.
    Petitioners assert that the court should reach the merits of
    their challenges to the Rule despite their failure to raise them
    during the notice and comment period. The Clean Air Act’s
    otherwise categorical bar on judicial review of objections first
    raised in a petition for reconsideration may be excused only in
    limited circumstances. Our precedents recognize certain
    narrow exceptions to the exhaustion requirement, including
    where the agency completes reconsideration but refuses to
    acknowledge that it has done so, or where it unreasonably
    delays the completion of reconsideration. See Sierra Club v.
    Thomas, 
    828 F.2d 783
    , 792-96 (D.C. Cir. 1987); see generally
    Randolph-Sheppard Vendors of Am. v. Weinberger, 
    795 F.2d 90
    , 104-09 (D.C. Cir. 1986).6
    6
    Congress has partly abrogated Sierra Club v. Thomas, but its
    analytical framework for determining whether EPA’s delay was
    12
    Petitioners suggest that EPA has functionally denied
    their petitions for reconsideration. EPA granted the petitions
    for reconsideration in September 2012 and does not anticipate
    completing its review of those petitions until April 2016.
    Petitioners also cite EPA’s data collection demands during the
    reconsideration proceeding. EPA has issued several requests
    for new data from PVC manufacturers, and EPA anticipates
    opening a new notice and comment period on its proposed
    modifications to the Rule before completing reconsideration.
    According to Petitioners, EPA’s slow pace and ambitious data
    unreasonable remains applicable to whether Petitioners may be
    excused for their failure to exhaust their administrative remedies.
    Thomas addressed the circumstances in which courts may compel
    EPA to take action under the Clean Air Act, and, in that context,
    held that this court had exclusive jurisdiction over claims to compel
    agency action “unreasonably delayed.” 
    Thomas, 828 F.2d at 792
    -
    96. Congress in the 1990 Amendments to the Clean Air Act
    abrogated Thomas’s jurisdictional holding and shifted to the district
    court the power to compel EPA to act. See Clean Air Act
    Amendments, Pub. L. No. 101-549, § 707(f), 104 Stat. 2399, 2683
    (1990); see also 42 U.S.C. § 7604(a) (explaining that “the district
    courts of the United States shall have jurisdiction to compel . . .
    agency action unreasonably delayed”); S. Rep. No. 101-228, at 374
    (1989). Those Amendments do not affect our jurisdiction here,
    however, nor the aspect of Thomas on which we rely. This is not a
    case seeking to compel EPA to take action, but a challenge to
    existing EPA PVC emissions rules.             Petitioners raise their
    unreasonable-delay allegation in an effort to rebut EPA’s
    contention that Petitioners must await completion of EPA’s
    pending reconsideration of the challenged Rule. When it amended
    the Clean Air Act, Congress anticipated this very type of case,
    “where a complaint about agency inaction is ‘embedded’ in a
    challenge to agency action,” and did not withdraw our jurisdiction.
    See S. Rep. No. 101-228, at 374 (citing Ind. & Mich. Electric Co. v.
    EPA, 
    733 F.2d 489
    , 490 (7th Cir. 1984)).
    13
    collection effort show it is not reconsidering the Rule but has
    embarked on a new rulemaking in the guise of
    reconsideration.
    EPA counters that the Clean Air Act requires EPA to
    afford on reconsideration “the same procedural rights as
    would have been afforded” at the time of the original
    rulemaking, 42 U.S.C. § 7607(d)(7)(B), and that, in this case,
    affording the parties those “same procedural rights” requires
    additional data collection and new notice and opportunity for
    comment. The agency is actively gathering additional data to
    inform its action on reconsideration, anticipates holding open
    a new notice and comment period, and predicts that it will
    complete reconsideration by a date certain (April 2016).
    There is thus neither a functional denial nor any suggestion in
    this record that the Agency has finished reconsideration but
    refused to acknowledge it.
    Petitioners also have failed to make the requisite showing
    that EPA has engaged in unreasonable delay. To establish a
    claim of unreasonable delay, petitioners must show that they
    have “a right the denial of which we would have jurisdiction
    to review upon final agency action but the integrity of which
    might be irreversibly compromised by the time such review
    would occur.” 
    Thomas, 828 F.2d at 796
    . To qualify as
    unreasonable, the agency’s delay would have to be “so
    egregious as to warrant mandamus.” 
    Id. at 797
    (internal
    quotation marks omitted). We have identified two avenues to
    establishing an unreasonable delay claim: (1) showing that an
    agency violated a statutory “right to timely decisionmaking”
    implicit in the agency’s regulatory scheme, or (2) showing
    that some other interest—financial, aesthetic, or related to
    human health and welfare, for example—“will be irreparably
    harmed through delay.” 
    Id. at 796-97.
                                  14
    Petitioners have failed to establish that EPA has deprived
    them of a statutory right to timely decisionmaking. In
    evaluating such a claim, we will (a) determine “whether
    Congress has imposed any applicable deadlines,” “exhorted
    swift deliberation concerning the matter,” or otherwise
    “implicitly contemplate[d] timely final action;” (b) determine
    “whether interests other than that of timely decisionmaking
    will be prejudiced by delay;” and (c) determine “whether an
    order expediting the proceedings will adversely affect the
    agency in addressing matters of a competing or higher
    priority.” 
    Id. at 797
    . In assessing those factors, we are
    mindful that, “[a]bsent a precise statutory timetable or other
    factors counseling expeditious action, an agency’s control
    over the timetable” of its proceedings “is entitled to
    considerable deference,” 
    id. (alteration in
    original) (internal
    quotation marks omitted) (quoting Sierra Club v. Gorsuch,
    
    715 F.2d 653
    , 658 (D.C. Cir. 1983)), and that “[e]ven where a
    statutory timetable exists, noncompliance with it has
    sometimes been excused as long as the agency has acted
    rationally and in good faith,” 
    Gorsuch, 715 F.2d at 658
    n.35.
    The text and structure of the Act suggest that judgments
    about the permissible duration of a Clean Air Act
    reconsideration proceeding are fact bound and case specific.
    The Clean Air Act does not specify limits on the permissible
    duration of a reconsideration proceeding, and its provisions
    generally grant the agency broad discretion to correct its own
    mistakes before its rules are subjected to judicial review. See
    42 U.S.C. §§ 7607(d)(7)(B), (d)(8).
    EPA’s forecasted duration of the reconsideration of the
    wastewater limit and the PVC-combined process vent limit is
    reasonably proportionate to the gravity and complexity of the
    rulemaking. EPA has attempted to promulgate a PVC Rule
    multiple times, and, each time, the attempt has taken several
    15
    years. EPA’s first attempt began data collection in 1998, and
    the Rule issued in 2002. See 67 Fed. Reg. 45,886, 45,889
    (July 10, 2002). This rulemaking began data collection in
    2009 for a Rule that issued in 2012. See PVC Rule, 77 Fed.
    Reg. at 22,852, 22,854. The scope of EPA’s reconsideration
    in this case is proportional to the scope of the alleged
    shortcomings in the 2012 rulemaking, and EPA estimates that
    its current reconsideration proceeding will take about four
    years, a duration commensurate with that of EPA’s prior
    efforts to set emissions limits for PVC production.
    Petitioners also have failed to establish unreasonable
    delay in completing reconsideration through the second route
    our cases have identified: they have not shown that their
    interests (in this case, financial) will be irreparably harmed if
    the court awaits the outcome of EPA’s reconsideration
    proceeding. See 
    Thomas, 828 F.2d at 794-96
    ; Randolph-
    Sheppard 
    Vendors, 795 F.2d at 107
    . As we have previously
    explained in the cognate context of preliminary injunctions,
    “[t]his court has set a high standard for irreparable injury.”
    Chaplaincy of Full Gospel Churches v. England, 
    454 F.3d 290
    , 297 (D.C. Cir. 2006). Such injury must be “both certain
    and great,” “actual and not theoretical,” “beyond
    remediation,” and “of such imminence that there is a clear and
    present need for equitable relief to prevent irreparable harm.”
    
    Id. (internal quotation
    marks and citations omitted). Where
    the injuries alleged are purely financial or economic, the
    barrier to proving irreparable injury is higher still, for it is
    “well settled that economic loss does not, in and of itself,
    constitute irreparable harm.” Wisconsin Gas Co. v. FERC,
    
    758 F.2d 669
    , 674 (D.C. Cir. 1985). Financial injury is only
    irreparable where no “adequate compensatory or other
    corrective relief will be available at a later date, in the
    ordinary course of litigation.” 
    Id. 16 Petitioners
    have failed to show any specific, identifiable
    cost they will incur because of the Rule’s emissions limits.
    They acknowledged at oral argument that the record contains
    no evidence of their cost of compliance, and they did not then
    articulate any. See Oral Arg. Rec. at 72:55-75:26. For its
    part, EPA has estimated that “the overall economic impact of
    this final rule on the affected industries and their consumers
    should be low,” amounting to approximately 0.7 percent of
    PVC manufacturers’ revenues. PVC Rule, 77 Fed. Reg. at
    22,900. EPA has also estimated that much of the cost of
    meeting the new emissions standards will arise from verifying
    compliance with the standard (measuring hazardous air
    pollutant concentrations from process vents, for example), not
    purchasing new control technology. See 
    id. at 22,899-900.
    Because costs of measuring emissions in order to monitor
    compliance must be incurred under any emissions limit, they
    are not specific to the emissions limits’ asserted irrationality
    and thus not a source of prejudice arising from delay as such.
    Petitioners also have failed to establish that EPA’s post-
    reconsideration emissions limits will differ materially from
    the current limits.      That showing matters because, if
    Petitioners will have to make the same investments and incur
    the same costs to comply with EPA’s ultimate Rule as they
    have to make under the current Rule, then any delay in
    shifting from the current limits to (presumptively materially
    equivalent) final ones is harmless. The court’s assessment of
    the post-reconsideration rule’s likely modest impact on
    existing emissions limits shows that delay in replacing EPA’s
    current emissions limits is in fact likely to be harmless.
    In particular, with respect to the existing major source
    wastewater limit, Petitioners have failed to show any
    likelihood that the limit will materially change. Petitioners
    argue the court should vacate EPA’s limit because EPA relied
    17
    on a faulty data point in setting the limit. But because EPA
    set the limit through a methodology designed to protect
    against variability of data, the distorting effect of a single,
    erroneous data point was minimized; omitting the faulty data
    point would make the wastewater limit 112 parts per million,
    rather than 110 parts per million.7 See J.A. 317-18, 326-28.
    Given that minimal difference, it is probable that Petitioners
    would have incurred the same costs to comply with either
    limit.
    That conclusion is bolstered by Petitioners’ own
    evidence. Petitioners asserted by post-argument letter to this
    court that their claim of irreparable harm from the Rule’s
    wastewater limit is substantiated by a document they
    submitted to EPA in the ongoing reconsideration proceeding
    measuring emissions from selected PVC production facilities.
    See Letter from Counsel to Petitioners to the Panel (Nov. 21,
    2014). The document (assuming its accuracy) cuts against
    Petitioners’ position, however, for it reveals that Petitioners’
    plants would be unable to comply even with a 1000 parts per
    million wastewater limit, a limit ten times greater than the 110
    parts per million limit in the current Rule. See Letter from
    Richard Krock, Vinyl Institute to Andrea Siefers, USEPA,
    EPA-HQ-OAR-2002-0037-0561, at 28 (Aug. 16, 2013) (“It is
    important to note that even with a 1,000 ppm limit, the facility
    would be in non-compliance at least three times during the
    sampling period.”). Petitioners’ admission that they could not
    comply even with a 1000 parts per million wastewater limit
    shows that, whether EPA had set the limit at 112 parts per
    7
    Intervenors’ expert re-conducted EPA’s analysis without using the
    data point that Petitioners contend is faulty, and the fresh
    calculation produced a new limit of 112 parts per million. See
    Intervenors’ Addendum, Sahu Dec. ¶¶ 9-12, Ex. B.
    18
    million or 110 parts per million, the different limit’s impact
    on Petitioners likely would have been de minimis or zero.
    Petitioners have not attempted to articulate how the
    court’s failure to enjoin the Rule based on their other
    unpreserved objections would result in irreparable harm.
    They have not established that their procedural objections
    mean that the Rule is likely to change after reconsideration.
    Nor have they established that the PVC-combined process
    vent emissions limits will differ so dramatically after
    reconsideration that attempting to comply in the meantime
    with the existing Rule will result in wasteful investments in
    unnecessarily stringent control technologies.
    Because Petitioners have not shown that EPA’s delay
    violates a statutory right to timely decision making or will
    otherwise cause them irreparable harm, they are not entitled to
    immediate judicial review of their unpreserved claims.
    Petitioners’ challenges stemming from the inadequacy of
    notice and comment, to the PVC-combined process vent
    limits, and to the wastewater limits—all first raised in
    petitions for reconsideration before EPA—are barred from
    review at this time.
    IV.
    Petitioners argue that, if the court cannot immediately
    review their unpreserved claims, it should stay the
    effectiveness of the challenged aspects of the Rule pending
    the outcome of EPA’s reconsideration proceeding. For the
    reasons outlined in the preceding Part, they have failed to
    show that awaiting the completion of EPA’s reconsideration
    will cause them irreparable harm. See Part III, supra; Nken v.
    Holder, 
    556 U.S. 418
    , 434 (2009) (outlining the requirements
    for obtaining a stay); D.C. Circuit Rule 18(a)(1). Petitioners
    are accordingly not entitled to a stay.
    19
    The dissent contends that the Court should stay the major
    source wastewater limit because “EPA itself does not oppose
    a stay in this case.” Dissent at 1. But that oversimplifies
    EPA’s position and does not account for the interests of other
    stakeholders who supported the rule and who themselves
    stand to suffer harm from EPA inaction.
    In its briefing and at oral argument EPA was emphatic: it
    did not waive its non-merits, threshold defense that
    Petitioners are barred from challenging the wastewater limits
    because they failed to object to them during the notice and
    comment period. Resp. Br. 33-35; Oral Arg. Rec. at 30:00-
    32:00; 40:30-45:00. EPA contended that, if the court found
    the issue to be properly before the court, then and only then
    would EPA “not oppose” a stay or vacatur of the wastewater
    limits. Resp. Br. 35.
    EPA’s consent is not alone a sufficient basis for us to stay
    or vacate a rule. The court is not bound to accept, and indeed
    generally should not uncritically accept, an agency’s
    concession of a significant merits issue. Cf. Bowen v.
    Georgetown Univ. Hosp., 
    488 U.S. 204
    , 212-13 (1988)
    (holding that courts will not defer to an agency’s litigating
    position where it contradicts the agency’s prior “regulations,
    rulings, or administrative practice”). The risk is that an
    agency could circumvent the rulemaking process through
    litigation concessions, thereby denying interested parties the
    opportunity to oppose or otherwise comment on significant
    changes in regulatory policy. If an agency could engage in
    rescission by concession, the doctrine requiring agencies to
    give reasons before they rescind rules would be a dead letter.
    See Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State Farm
    Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 52 (1983).
    20
    We note, moreover, that the Clean Air Act provides that
    “the effectiveness of [a] rule may be stayed during . . .
    reconsideration . . . by the Administrator [of the EPA] or the
    court for a period not to exceed three months.”
    42 U.S.C. § 7607(d)(7)(B). The partial dissent contends that
    the Court may stay a Clean Air Act rule indefinitely,
    notwithstanding that language, pointing to the more general
    stay provisions of the Administrative Procedure Act, 5 U.S.C.
    § 705, and our decision in Portland Cement Assoc. v. EPA,
    
    665 F.3d 177
    , 189 (D.C. Cir. 2011) (per curiam), which
    granted a stay pending reconsideration without explicitly
    squaring it with the Clean Air Act’s three-month limitation.
    We need not reconcile the divergent authorities on the stay
    question however, because, even assuming the court’s power
    to grant them one, Petitioners have failed to show irreparable
    harm warranting a stay.
    V.
    Petitioners’ preserved challenges to the substance of
    EPA’s Rule fail on their merits. EPA’s PVC-combined
    process vent limits do not conflict with other emissions limits,
    and EPA’s decision not to subcategorize process vents on the
    basis of their emissions control technology was reasonable.
    EPA’s bypass opening requirements are not arbitrary and
    capricious, and its requirement that PVC manufacturers install
    monitoring equipment on pressure relief devices is not
    irrational. Finally, Petitioners’ argument that some of EPA’s
    bypass regulations are unlawful beyond-the-floor MACT
    requirements stems from misapprehension of the Clean Air
    Act and is without merit.
    First, the Rule’s PVC-combined process vent limits do
    not create a regulatory conflict with other emissions limits.
    Petitioners insist that because PVC-combined process vent
    21
    limits, by their very nature, incidentally limit emissions from
    sources outside the PVC source category, the Rule creates a
    conflict with the emissions limits applicable to those other
    sources. But, as EPA explained in the preamble to the present
    Rule, overlapping limits are not necessarily “conflicting” or
    “inconsistent.” PVC Rule, 77 Fed. Reg. at 22,865 (internal
    quotation marks omitted). If a PVC manufacturer chooses to
    discharge combined emissions from PVC and non-PVC
    processes through a single vent, that manufacturer must
    comply with limits applicable to both and, where they differ,
    comply with the more stringent of the two. 
    Id. If the
    two
    limits rely on different methods of measurement, both
    methods must be used. See 
    id. That may
    be burdensome, but
    it is neither unachievable nor unreasonable. Manufacturers
    hold the keys to this particular regulatory box. They can
    avoid the overlap, as EPA explained, by separating PVC-
    production emissions from those emanating from other
    sources. 
    Id. If the
    y do so, the PVC-only process vent limits
    will apply to the emissions from PVC production, and the
    other source’s relevant emissions limits will apply to its
    emissions, eliminating the requirement that the other source
    comply with the PVC-combined emissions limits. 
    Id. Second, EPA
    reasonably decided not to subcategorize
    process vents on the basis of which particular emissions
    control technology PVC manufacturers choose.               The
    conclusion that EPA need not—indeed should not—relax its
    emissions limits when polluters use insufficiently effective
    control technology is inherent in the very idea of technology-
    forcing regulation. Petitioners contend, however, that the
    superior effectiveness of their emissions control technology is
    not accurately measured by EPA’s approach.
    The thrust of Petitioners’ argument is as follows: Most
    PVC production facilities use “thermal oxidizers” to reduce
    22
    their emissions into the atmosphere of hazardous air
    pollutants. Some, however, use “vent gas absorbers,” a
    control technology with a “radically different” emissions
    profile from that of a thermal oxidizer. Pet. Br. 52. Thermal
    oxidizers vent continuously and at high flow rates; vent gas
    absorbers vent intermittently and at very low flow rates.
    EPA’s method of determining compliance with the
    Rule’s process vent limits relies on measuring the
    concentration of hazardous air pollutants in a process vent’s
    effluent stream. A difference in how the two technologies
    operate means a vent gas absorber’s effluent stream has a
    higher maximum concentration of hazardous air pollutants
    than does the relatively consistent effluent stream from a
    thermal oxidizer. Petitioners contend that EPA inaccurately
    rates vent gas absorbers as less effective than thermal
    oxidizers at controlling emissions because of the higher
    concentration of pollutants that vent gas absorbers emit. Vent
    gas absorbers may nonetheless be a better emissions control
    technology than thermal oxidizers, Petitioners claim, because
    they emit their relatively concentrated pollutants only
    intermittently and at lower rates. The Rule’s focus on the
    concentration of hazardous air pollutants means that vent gas
    absorbers rate poorly even though they may in fact be more
    effective.
    Spelling out the objection makes it immediately clear that
    Petitioners’ real dispute is not with inadequate
    subcategorization. Petitioners concede that it was reasonable
    for EPA to require vent gas absorbers and thermal oxidizers to
    meet the same emissions limits.           Instead, Petitioners’
    grievance appears to be that the Rule’s method of measuring
    the emission of hazardous air pollutants erroneously
    concludes that vent gas absorbers are less effective emissions
    controls than thermal oxidizers. Petitioners’ claim, in effect,
    23
    is that EPA acted arbitrarily and capriciously in failing to
    create an alternate method of measuring output from a PVC
    process vent on the basis of the total mass of hazardous air
    pollutants it emits, rather than on the basis of the
    concentration of hazardous air pollutants in its effluent
    stream.
    EPA, however, reasonably chose not to create an
    alternative measurement format on the basis of total mass
    emission rates. In the Rule, EPA explained that it “considered
    setting alternative formats for the process vent emission
    limits” but that, in its judgment, it “did not have sufficient
    information provided from industry on process vent stream
    flow rates and concentrations to develop or evaluate other
    formats, such as mass emission rates.” PVC Rule, 77 Fed.
    Reg. at 22,869. Petitioners counter that EPA’s explanation is
    insufficiently specific and that its want of specificity alone
    suffices to render it arbitrary and capricious. See Ne. Md.
    Waste Disposal Auth. v. EPA, 
    358 F.3d 936
    , 949 (D.C. Cir.
    2004). We disagree. EPA’s explanation, though short, fully
    conveys the agency’s rationale in declining to set an
    alternative measurement format and furnishes concrete
    grounds for framing a challenge to the decision’s substantive
    rationality. Petitioners have done so, arguing that EPA had
    sufficient information to set alternative emissions formats.
    Pet. Br. 53. On the merits, Petitioners have not carried their
    burden of showing that, contrary to EPA’s explanation, it did
    in fact have sufficient data to establish an alternative
    emissions format. We defer to EPA’s judgments about data
    insufficiency, at least in the absence of further information or
    explanation from Petitioners regarding why deference is
    inappropriate. Petitioners’ challenge to EPA’s decision not to
    subcategorize process vents on the basis of their emissions
    control technology therefore lacks merit.
    24
    Third, EPA’s bypass-opening requirements are not
    arbitrary and capricious. Petitioners argue that EPA’s
    regulations make opening a bypass unlawful without
    exception, even if the opening occurs during routine
    maintenance after performing the equipment opening steps
    called for elsewhere under the Rule governing maintenance,
    and that compliance with the Rule is therefore impossible.
    Pet. Br. 55-56 (citing 40 C.F.R. §§ 63.11955, 63.11930(c)).
    Petitioners misread EPA’s regulations. The regulations
    anticipate that regulated entities will be allowed to open
    bypasses during maintenance as long as they comply with the
    opening         provisions        set       forth      therein.
    40 C.F.R. §§ 63.11955(a)-(b). Otherwise, the very existence
    of regulations setting forth instructions for opening bypasses
    would be superfluous. In the preamble to the Rule, EPA
    explained that it does not interpret 40 C.F.R. § 63.11930(c) as
    categorically prohibiting all discharges through bypasses. See
    PVC Rule, 77 Fed. Reg. at 22,885. EPA’s interpretation of its
    own regulations is entitled to our deference. See Auer v.
    Robbins, 
    519 U.S. 452
    , 462-63 (1997). In view of the text of
    EPA’s regulations and the Agency’s repeated representations
    about their meaning, Petitioners’ claims that EPA’s
    regulations arbitrarily and capriciously prohibit opening
    bypasses for purposes of routine maintenance are without
    merit.
    Fourth, EPA’s requirements for monitoring pressure
    relief devices are not arbitrary and capricious. Pressure relief
    devices are important safety equipment that, if not built to
    route emissions through emissions controls, may, when
    triggered, emit significant amounts of hazardous air pollutants
    directly into the atmosphere. See PVC Rule, 77 Fed. Reg. at
    22,881-82. EPA requires that all releases by pressure relief
    devices meet the Rule’s process vent emissions limits. 40
    C.F.R. § 63.11915(c)(1). EPA provides for two methods of
    25
    compliance: (1) PVC manufacturers may route discharges
    from pressure relief devices through emissions control
    equipment to ensure compliance with the Rule, or (2) equip
    their pressure relief devices with release indicators to detect
    uncontrolled discharges. 40 C.F.R. § 63.11915(c)(1)-(2).
    EPA concluded that such monitoring is necessary to ensure
    that uncontrolled emissions will be “identified and controlled
    in a timely manner” and that “repeat problems” will be
    corrected. PVC Rule, 77 Fed. Reg. at 22,882.
    Petitioners contend the regulation is unreasonable,
    however, because EPA did not have enough data about
    hazardous air pollutant releases from pressure relief devices to
    justify imposing a costly monitoring requirement. According
    to Petitioners, releases from pressure relief devices may be so
    rare, insignificant, and well prevented or well detected by
    current industry monitoring methods that the regulation is
    wasteful and unnecessary. EPA responded in the Rule by
    explaining that, in its judgment based on the data in the
    record, PVC facilities had not been effectively detecting and
    recording releases from pressure relief devices. PVC Rule, 77
    Fed. Reg. at 22,882.
    EPA’s judgment was reasonable. The paucity of data
    about the frequency and severity of discharges from pressure
    relief devices could be because the PVC industry lacks
    effective methods for detecting or recording releases. If EPA
    were required to gather exhaustive data about a problem for
    which gathering such data is not yet feasible, the agency
    would be unable to act even if such inaction had potentially
    significant consequences. We have consistently held that, in
    situations in which an agency must make a judgment in the
    face of a known risk of unknown degree, the “agency has
    some leeway reasonably to resolve uncertainty, as a policy
    matter, in favor of more regulation or less.” Ctr. for Auto
    26
    Safety v. Fed. Highway Admin., 
    956 F.2d 309
    , 316 (D.C. Cir.
    1992). Here, the agency’s choices were to do nothing,
    consistent with PVC manufacturers’ assertions that their
    current efforts were adequate, or promulgate a regulation to
    protect against risk. See PVC Rule, 77 Fed. Reg. at 22,881-
    82. Petitioners point to some data EPA had on certain devices
    and claim EPA ignored it. But, as EPA explained in the Rule,
    that data did not give EPA reason to believe that all PVC
    manufacturers have and use effective discharge detection and
    recording technology. 
    Id. EPA recognized
    the high stakes of
    the decision to do nothing, explaining that releases from
    pressure relief devices “have the potential to emit large
    quantities of [hazardous air pollutants], and a large number of
    these releases that may occur may not be identified and
    controlled in a timely manner, and may be due to repeat
    problems that have not been corrected.” 
    Id. at 22,882.
    EPA
    thus reasonably exercised its broad discretion to require
    monitoring of pressure relief devices to ensure compliance
    with the Rule’s emissions limits.
    Fifth, EPA’s regulations designed to ensure the detection
    of discharges through bypasses are not beyond-the-floor
    MACT requirements. The Rule requires PVC manufacturers
    to install a flow indicator, lock-and-key system, or “car seal”
    on bypasses to detect when they are opened. 40 C.F.R. §§
    63.11930(c)(1), (2).8 Petitioners contend that EPA failed to
    determine whether its regulation would be “achievable” in
    light of “cost, energy requirements, and other factors,” as
    8
    A car seal may be an inexpensive plastic fastener (e.g., a zip tie)
    or a steel cable closed in a loop with a small block of aluminum or
    steel. See 40 C.F.R. § 63.12005 (defining “Car-seal” as “a seal that
    is placed on a device that is used to change the position of a valve .
    . . in such a way that the position of the valve cannot be changed
    without breaking the seal”).
    27
    EPA is required to do before imposing a beyond-the-floor
    MACT limit under Section 112(d)(2) of the Clean Air Act.
    Sierra Club v. EPA, 
    353 F.3d 976
    , 989 (D.C. Cir. 2004); see
    42 U.S.C. § 7412(d)(2). Petitioners’ argument lacks merit
    because EPA’s bypass Rule simply is not a beyond-the-floor
    MACT requirement and so is not subject to Section 112(d)(2).
    The requirement was enacted pursuant to EPA’s statutory
    authority under Section 114(a)(1)(C), permitting the agency to
    require the installation, use, and maintenance of monitoring
    equipment to ensure compliance with a MACT emissions
    limit. See 42 U.S.C. § 7414(a)(1)(C); PVC Rule, 77 Fed. Reg.
    at 22,860. Bypass flow indicators, locks, and car seals are all
    monitoring devices: they determine whether a PVC facility is
    in violation of the Rule by identifying either mechanically (as
    with a flow indicator) or visually (as with an open lock or
    broken seal) an open bypass that may discharge pollutants.
    EPA reasonably and lawfully required PVC manufacturers to
    install, use, and maintain them pursuant to Section
    114(a)(1)(C). We therefore reject Petitioners’ argument that
    EPA’s bypass monitoring regulation somehow triggers
    Section 112(d)(2)’s cost-benefit requirements.
    ***
    For the foregoing reasons we deny the petitions for
    review.
    KAVANAUGH, Circuit Judge, dissenting in part: EPA
    issued a rule that imposes limits on emissions of hazardous air
    pollutants by manufacturers of polyvinyl chloride. But EPA
    later concluded that one category of those limits – the so-
    called wastewater limits on hazardous air pollutants that may
    be dissolved in wastewater – was based on bad data. EPA is
    therefore reconsidering the wastewater limits. EPA says that
    it will complete the reconsideration process in 2016.
    Petitioners, who are manufacturers of polyvinyl chloride,
    contend that EPA’s flawed wastewater limits should be stayed
    under 5 U.S.C. § 705, the general Administrative Procedure
    Act provision authorizing stays pending judicial review.
    Petitioners are correct. They obviously have demonstrated a
    likelihood of success on the merits; after all, EPA concedes
    that the wastewater limits are flawed. And petitioners also
    have shown irreparable harm – namely, the high costs to
    comply with the flawed wastewater limits. Moreover,
    petitioners have precedent on their side: In a similar case in
    which EPA was reconsidering a concededly flawed rule, we
    readily granted a stay. See Portland Cement Association v.
    EPA, 
    665 F.3d 177
    , 189 (D.C. Cir. 2011) (“We will, however,
    enter a stay of the NESHAP standards applicable to clinker
    storage piles. EPA has conceded that it ‘did not give
    sufficient notice’ of those standards and has granted PCA’s
    request for reconsideration . . . . Thus, industry should not
    have to build expensive new containment structures until the
    standard is finally determined.”).
    Even EPA itself does not oppose a stay in this case.
    EPA’s position is telling. Given the circumstances here, as
    well as our Portland Cement precedent, I would stay the
    wastewater limits pending judicial review.
    To be sure, the Clean Air Act imposes a 3-month limit on
    stays pending agency reconsideration.        See 42 U.S.C.
    § 7607(d)(7)(B). But Section 705 of the APA authorizes
    2
    courts to stay agency rules pending judicial review without
    any time limit on the duration of the stay. See 5 U.S.C. § 705
    (reviewing court “may issue all necessary and appropriate
    process to postpone the effective date of an agency action or
    to preserve status or rights pending conclusion of the review
    proceedings”); In re GTE Service Corp., 
    762 F.2d 1024
    , 1026
    (D.C. Cir. 1985) (Section 705 provides “statutory authority to
    stay agency orders pending review in this court.”). 1
    Therefore, in this case, we should issue a stay that remains in
    effect pending judicial review.
    For those reasons, I respectfully dissent from the majority
    opinion’s decision not to stay EPA’s wastewater limits. 2
    1
    The Clean Air Act does not displace Section 705, the general
    APA provision governing stays pending judicial review. The Clean
    Air Act expressly provides that several provisions of the APA – 5
    U.S.C. §§ 553-557 and 706 – “shall not, except as expressly
    provided in this subsection, apply to actions to which this
    subsection applies.” 42 U.S.C. § 7607(d)(1). Section 705 is not on
    that list. By contrast, Congress has displaced Section 705 in other
    statutory regimes. Cf. 16 U.S.C. § 1855(f)(1) (fishery management
    regulations subject to judicial review in accordance with
    Administrative Procedure Act, but not with Section 705); 
    id. § 3636(c)
    (Pacific salmon fishing regulations subject to judicial
    review in accordance with Administrative Procedure Act, but not
    with Section 705). Had Congress wanted to prevent courts in Clean
    Air Act cases from issuing stays under Section 705, Congress could
    have done so.
    2
    Petitioners also challenge EPA’s process vent emissions
    limits and the compliance and monitoring provisions. I agree with
    the majority opinion that those claims lack merit.
    

Document Info

Docket Number: 12-1260, 12-1265, 12-1266, 12-1267

Judges: Rogers, Kavanaugh, Pillard

Filed Date: 5/29/2015

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (20)

american-petroleum-institute-v-douglas-m-costle-administrator-and ( 1981 )

Bowen v. Georgetown University Hospital ( 1988 )

Chaplaincy of Full Gospel Churches v. England ( 2006 )

Sierra Club v. Anne M. Gorsuch, Administrator, ... ( 1983 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... ( 1983 )

Nken v. Holder ( 2009 )

Sierra Club v. Environmental Protection Agency ( 2004 )

Northeast Maryland Waste Disposal Authority v. ... ( 2004 )

Portland Cement Ass'n v. Environmental Protection Agency ( 2011 )

Indiana & Michigan Electric Company and Indianapolis Power &... ( 1984 )

Randolph-Sheppard Vendors of America v. Caspar W. ... ( 1986 )

Sierra Club v. Lee M. Thomas, Administrator, Environmental ... ( 1987 )

Mossville Env Actn v. EPA ( 2004 )

Appalachian Power Company v. Environmental Protection ... ( 1998 )

Center for Auto Safety v. The Federal Highway Administration ( 1992 )

National Lime Ass'n v. Environmental Protection Agency ( 2000 )

In Re Gte Service Corporation ( 1985 )

appalachian-power-company-v-environmental-protection-agency-commonwealth ( 2001 )

wisconsin-gas-company-v-federal-energy-regulatory-commission-michigan ( 1985 )

Auer v. Robbins ( 1997 )

View All Authorities »