Baltimore Gas and Electric Company v. FERC ( 2020 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 17, 2019                Decided March 27, 2020
    No. 18-1298
    BALTIMORE GAS AND ELECTRIC COMPANY,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    MARYLAND OFFICE OF PEOPLE’S COUNSEL AND MARYLAND
    PUBLIC SERVICE COMMISSION, INTERVENORS
    On Petition for Review of Orders of the Federal Energy
    Regulatory Commission
    Matthew E. Price argued the cause and filed the briefs for
    petitioner.
    Jared B. Fish, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on the
    brief were James P. Danly, General Counsel, and Robert H.
    Solomon, Solicitor.
    Stephen C. Pearson argued the cause for intervenors. With
    him on the brief were Miles H. Mitchell, Ransom E. Davis,
    2
    Paula M. Carmody, William F. Fields, Joseph G. Cleaver, and
    Scott H. Strauss.
    Before: HENDERSON and RAO, Circuit Judges, and
    WILLIAMS, Senior Circuit Judge.
    Opinion for the Court filed by Senior Circuit Judge
    WILLIAMS with respect to Parts I, II, and IV.
    Opinion for the Court filed by Circuit Judge RAO with
    respect to Part III.
    Dissenting Opinion filed by Senior Circuit Judge
    WILLIAMS with respect to Part III.
    WILLIAMS, Senior Circuit Judge: This case arises out of
    the Federal Energy Regulatory Commission’s effort to apply its
    “matching” principles to divergences between the timing of
    deductions for tax purposes and timing for purposes of
    allocating costs to ratepayers. While Congress and other bodies
    imposing taxes may want to allow early depreciation of an asset
    (to encourage investment), for example, the Commission wants
    a cost (less offsetting tax benefits) to be charged in the period
    over which the resulting asset provides services to the utility’s
    customers.
    I.
    In December 2016, Baltimore Gas and Electric Company
    (“BGE”) filed a new rate proposal with the Commission under
    § 205 of the Federal Power Act, 16 U.S.C. § 824d. The
    proposal sought a net recovery of approximately $38 million
    from future ratepayers relating to various costs incurred by
    BGE dating back to 2005. It is undisputed that consumers had
    not been charged for these costs between 2005 and the 2016
    filing.
    3
    The relevant items are in fact a good deal more
    complicated than the accelerated depreciation example used
    above, but their details do not affect the issues before us. They
    arise from (1) a transition problem posed by a switch in
    Commission handling of such matters, (2) a change in tax rates,
    and (3) differences between ratemaking and tax treatments of
    the equity component of construction costs. The sums involved
    in the first and third categories totaled about $42 million, offset
    by about $4 million in the second (which BGE proposed to
    return to the ratepayers). FERC expects utilities to track these
    amounts according to Financial Accounting Standard 109
    (“FAS 109”), a financial accounting and reporting standard
    promulgated by the not-for-profit Financial Accounting
    Standards Bureau intended to set forth recording requirements
    to facilitate “tax normalization,” i.e., resolution of timing
    differences exemplified by the matters discussed above. See
    FERC Br. 12; Accounting for Income Taxes, FERC Docket No.
    AI93-5-000 (Apr. 23, 1993) (“1993 Guidance”).
    FERC denied BGE’s request to recover these amounts,
    declining to find BGE’s proposed rate “just and reasonable,” as
    required by § 205(a). Specifically, it found BGE’s request in
    violation of the procedural requirements that it had developed
    for implementation of the matching principle in this context and
    had stated in its order, Regulations Implementing Tax
    Normalization for Certain Items Reflecting Timing Differences
    in the Recognition of Expenses or Revenues for Ratemaking
    and Income Tax Purposes, Order No. 144, FERC Stats. & Regs.
    ¶ 30,254 (1981). Order No. 144 requires that any such
    adjustment “be made in the applicant’s next rate case following
    applicability of the rule.” Id. at ¶ 31,519. It also requires
    applicants “to begin the process of making up deficiencies in or
    eliminating excesses in their deferred tax reserves so that,
    within a reasonable period of time to be determined on a case-
    4
    by-case basis, they will be operating under a full normalization
    policy.” Id. at ¶ 31,560.
    FERC concluded that BGE had breached the requirements
    of Order No. 144 by failing to file for recovery of these amounts
    in its “next rate case,” which, according to FERC, was BGE’s
    2005 rate filing. Order Rejecting Proposed Tariff Revisions,
    PJM Interconnection, LLC, 
    161 FERC ¶ 61,163
     (2017)
    (“Order”). On requests for clarification and rehearing, the
    Commission made clear its position that the “reasonable period
    of time” requirement of Order No. 144 “was intended to work
    in conjunction with the ‘next rate case’ requirement,” so that it
    does not “negate the requirement that applicants must seek
    recovery in their next rate case.” Order on Rehearing and
    Clarification, PJM Interconnection, LLC, 
    164 FERC ¶ 61,173
    ,
    at P 18 (2018) (“Rehearing Order”).
    Although neither party speaks directly to the issue, we take
    it that, for purposes of this case anyway, the “next rate case
    following applicability of the rule” is the “next rate case” after
    the utility has incurred an item (including either a cost or a
    benefit) requiring “normalization” under Order No. 144 and the
    1993 Guidance, not counting periods in which a rate case or
    settlement had itself normalized the treatment of the item (or
    adequately addressed its normalization). Indeed, even though
    FERC denied recovery of such amounts for years past, its
    denial was without prejudice to BGE’s recovery of FAS 109
    amounts properly allocable to future years, leaving open BGE’s
    opportunity to achieve normalization prospectively. See
    Rehearing Order at PP 37–38; see also FERC Br. 15.
    BGE petitioned for review and claims that FERC’s
    application of Order No. 144 was arbitrary and capricious
    under the Administrative Procedure Act, 
    5 U.S.C. § 706
    (2)(A),
    misapplying the “next rate case” and “reasonable period of
    time” requirements. BGE also asserts that FERC erred in
    5
    failing to recognize BGE’s 2006 settlement of the 2005 rate
    case as an example of the sort of settlement briefly discussed in
    Order No. 144. That order had said that it left “undisturbed the
    ability of the parties to reach a settlement on any of the issues
    covered by the rule.” Order No. 144 at ¶ 31,519. BGE argues
    the settlement qualified under Order No. 144 and as a result
    preserved BGE’s ability to recover the FAS 109 amounts here
    at issue.
    For the reasons developed below we find that FERC’s
    orders were not arbitrary and capricious and therefore deny the
    petition for review.
    II.
    We begin with the 2006 settlement agreement, which BGE
    claims preserved its right to recover FAS 109 amounts dating
    back to 2005. As BGE acknowledges, BGE Br. 32 n.5, we have
    long applied Chevron deference to FERC’s reasonable
    interpretations of settlement agreements it approves, Nat’l Fuel
    Gas Supply Corp. v. FERC, 
    811 F.2d 1563
    , 1569 (D.C. Cir.
    1987), and we do so here. The question before us is whether
    FERC’s determination that BGE’s settlement agreement did
    not preserve FAS 109 amounts for recovery in a later rate case
    filing is “reasonable and reasonably explained,” Nw. Corp. v.
    FERC, 
    884 F.3d 1176
    , 1179 (D.C. Cir. 2018), which we answer
    in the affirmative. BGE’s arguments that FERC is wrong in its
    application of Order No. 144’s settlement provision are not
    convincing.
    The rate filing by BGE that led to the 2006 settlement
    expressly excluded the FAS 109 amounts, and line items in a
    spreadsheet attached to the ultimate agreement described
    certain amounts as “net of” or “less” FAS 109 amounts. BGE
    claims that the spreadsheets and contemporaneous testimony
    explaining the same indicate that the parties intended these
    6
    amounts to be recoverable at a later date. BGE Br. 45; BGE
    Add. 34. But the Commission observed that the settlement “did
    not expressly reserve deferred income tax issues,” but rather,
    “was silent on this point.” Rehearing Order at PP 16–17. That
    seems an apt characterization. A mere description of how the
    parties calculated figures says nothing about an intent to agree
    on later recovery of amounts not included in the calculation,
    especially as such a recovery, starting after lapse of the
    settlement but allowing recovery of amounts properly due over
    the settlement’s time in effect, would have seriously
    compromised the Commission’s matching principle. It is thus
    hard to see more in the settlement references than an agreement
    to disagree. And FERC’s insistence that a settlement do more
    than that fits comfortably within Order No. 144’s admittedly
    vague language on settlements.
    BGE suggests that because 
    18 C.F.R. § 35.24
     “require[s]
    utilities to adopt some mechanism to pass through FAS 109
    amounts to customers,” the settlement agreement’s near silence
    should be understood as merely leaving undisturbed a
    background expectation that FAS 109 amounts will eventually
    be recovered. BGE Br. 49 (emphasis in original). But while the
    heading of § 35.24(b)(1) reads, “Tax normalization required,”
    and the text goes on to specify details for fulfillment of the
    requirement, understanding normalization as a requirement is
    entirely consistent with Order No. 144’s imposing conditions
    on utilities’ recovery of deferred tax amounts and with the
    Commission’s reading the Order’s language on settlements as
    requiring more than the opaque treatment applied in the 2006
    settlement. Indeed, as the Commission requires normalization
    in order to fulfill the matching principle, it would seem to
    contradict itself if it allowed the 2006 settlement’s language to
    allow indefinite postponement of a utility’s recovery of FAS
    109 amounts. FERC reasonably interpreted its regulations and
    the settlement agreement to mean that BGE simply failed to
    7
    comply with 
    18 C.F.R. § 35.24
     by its next rate case, as required
    by Order No. 144.
    BGE also introduces information about its rates before
    2005, pointing to settlements reached in 1996 and 1997, and
    conjures a new argument out of the settlements. These were
    “black box” settlements, meaning that they stated rates without
    linking the dollar amounts to specific inputs. BGE argues that
    these should be “presumed,” BGE Br. 16–17, 24, 33, to have
    addressed the FAS 109 amounts, and that therefore they
    fulfilled Order No. 144’s “next rate case” requirement. The
    Commission responds, accurately, that BGE never made such
    an argument in its petition for rehearing, and that accordingly
    it’s not properly before us. See 16 U.S.C. § 825l(b). We
    therefore do not address it. We confess ourselves unclear as to
    just how recovery of FAS 109 amounts in 1996–2005
    (assuming it occurred), followed by a gap from 2005 to the
    effective date of BGE’s 2016 filing, could satisfy the matching
    principle as to amounts properly allocable to that period.
    III.
    Finally, BGE argues that, notwithstanding the
    requirements of Order No. 144, FERC has been more
    permissive with four “similarly situated” utilities and fails to
    explain its disparate treatment of BGE’s filing. BGE Br. 38–
    42; BGE Reply Br. 15–21.
    On arbitrary and capricious review, FERC bears the
    burden “to provide some reasonable justification for any
    adverse treatment relative to similarly situated competitors.”
    ANR Storage Co. v. FERC, 
    904 F.3d 1020
    , 1025 (D.C. Cir.
    2018). To determine whether an agency must justify a prior
    contrary decision, therefore, we ask whether the regulated
    parties at issue are “similarly situated.” See, e.g., W. Deptford
    Energy, LLC v. FERC, 
    766 F.3d 10
    , 20 (D.C. Cir. 2014) (“It is
    8
    textbook administrative law that an agency must provide[]
    a reasoned explanation for departing from precedent or treating
    similar situations differently, and Commission cases are no
    exception.”) (citations and quotation marks omitted) (emphasis
    added); LeMoyne-Owen College v. NLRB, 
    357 F.3d 55
    , 60–61
    (D.C. Cir. 2004) (Roberts, J.) (“An agency is by no means
    required to distinguish every precedent cited to it by an
    aggrieved party. But where, as here, a party makes a significant
    showing that analogous cases have been decided differently,
    the agency must do more than simply ignore that argument.”)
    (citations omitted) (emphasis added).
    Here, BGE has made a threshold showing that it is
    similarly situated to four utilities that received more favorable
    treatment by the Commission. FERC responds that these four
    prior actions are not binding precedent because three of them
    were issued by staff exercising subdelegated authority and none
    of the four “squarely presented” or “necessarily resolved” the
    issues presented in this case.1 FERC Br. 44–48. The agency
    argues in the alternative that it did reasonably distinguish
    1
    In Midcontinent Independent System Operator, Inc., 
    153 FERC ¶ 61,374
     (2015), the only order of the four issued directly by the
    Commission, the utility received approval to recover FAS 109
    amounts arising from a 2011 change in tax rates. FERC approved the
    other three rate filings in letter orders issued by agency staff. PPL
    Electric Utilities Corp., Letter Order, FERC Docket No. ER12-1397
    (May 23, 2012), and Duquesne Light Co., Letter Order, FERC
    Docket No. ER13-1220 (Apr. 26, 2013), sought recovery of
    unfunded FAS 109 amounts related to the Pennsylvania Public
    Utility Commission’s decision to pass on certain income tax savings
    to customers. Virginia Electric & Power Co. (VEPCO), Letter Order,
    FERC Docket No. ER16-2116-000 (Aug. 2, 2016), sought FAS 109
    amounts related to the equity component of construction costs and
    a recent tax law change. Each letter order purports to constitute final
    agency action on the part of the Commission. See, e.g., 
    id. at 2
     (“This
    order constitutes final agency action.”).
    9
    BGE’s submission from those in the four prior orders. FERC
    Br. 49–52. We take each of the Commission’s arguments in
    turn.
    A.
    First, FERC argues that three of the four prior orders cited
    by BGE need not be distinguished because they were issued by
    agency staff under authority subdelegated by the Commission.
    The agency’s regulations delegate to certain staff the authority
    to “[r]eject” or “[a]ccept for filing all uncontested tariffs or rate
    schedules” if the filings “comply with all applicable statutory
    requirements, and with all applicable Commission rules,
    regulations and orders.” 
    18 C.F.R. § 375.307
    (a)(1)(i)–(ii).2
    Setting aside the permissibility of FERC’s subdelegation,
    which is not a question before us, the Commission cannot lend
    its authority to staff and then disclaim responsibility for the
    actions they take. Delegated staff actions are actions of the
    agency. See 
    5 U.S.C. § 551
    (13) (“‘[A]gency action’ includes
    the whole or a part of an agency rule, order, license, sanction,
    relief, or the equivalent or denial thereof.”); 
    id.
     § 551(6)
    (“‘[O]rder’ means the whole or a part of a final disposition …
    other than rule making.”); Sprint Nextel Corp. v. FCC, 
    508 F.3d 1129
    , 1131 n.3 (D.C. Cir. 2007) (“‘Agency action’
    encompasses any reviewable action that an agency might
    take.”). Neither the APA nor our precedents distinguish
    between binding orders signed by staff and those signed by the
    Commission for purposes of arbitrary and capricious review.
    Because staff exercise only authority delegated to them by the
    2
    Under the Federal Power Act, proposed rates go into effect by
    operation of law sixty days after filing with the Commission, barring
    further action by the agency. See 16 U.S.C. § 824d(d). When filings
    are “rejected,” the Commission treats them as never filed, meaning
    they cannot lawfully go into effect. See 
    18 C.F.R. § 385.2001
    (b)(2).
    10
    Commission, their decisions to accept, reject, or take other
    actions on filings are decisions of the Commission until
    superseded by subsequent agency action. 
    18 C.F.R. § 385.1902
    (a) (“Any staff action … taken pursuant to authority
    delegated to the staff by the Commission is a final agency
    action that is subject to a request for rehearing.”);3 see also Pub.
    Citizen, Inc. v. FERC, 
    839 F.3d 1165
    , 1169 (D.C. Cir. 2016)
    (“[W]e have previously defined ‘order’ expansively to include
    any agency action capable of review on the basis of the
    administrative record.”) (citation and quotation marks omitted).
    FERC must exercise its statutory authority in accordance
    with the APA, and its decision to delegate to staff cannot erase
    the requirements of reasoned decisionmaking. Procedural
    differences between this case, in which the Commission
    rejected BGE’s filing, and cases decided by staff letter orders
    are insufficient standing alone to justify disparate treatment of
    similarly situated utilities. It is not enough for FERC to say,
    “the staff did it.” Reasoned decisionmaking requires FERC to
    explain differential treatment under the same rules. See ANR
    Storage, 904 F.3d at 1024 (citing W. Deptford, 766 F.3d at 20).
    B.
    Second, FERC maintains that the four prior orders need not
    be distinguished because none “squarely presented” or
    “necessarily resolved” the issue in this case. Specifically, the
    3
    Whether those actions would be reviewable without further
    exhaustion of administrative remedies is, of course, a different
    question. See 16 U.S.C. § 825l(b) (“No objection to the order of the
    Commission shall be considered by the court unless … urged before
    the Commission in the application for rehearing unless there is
    reasonable ground for failure so to do.”). In this case, BGE raised its
    arbitrary and capricious argument based on these four prior orders in
    its request for rehearing before the Commission.
    11
    Commission notes the three staff letter orders cited by BGE
    were uncontested and that none of the four provided a reasoned
    analysis on the collection of accrued FAS 109 amounts.
    These arguments ring hollow because we rejected them in
    substantially similar form only two years ago. In ANR Storage
    Co. v. FERC, we held in no uncertain terms that distinguishing
    prior orders in similar cases simply as “unreasoned” or
    “unopposed” fails to satisfy the APA’s reasoned
    decisionmaking requirement. 904 F.3d at 1025. As our decision
    emphasized, the duty to explain inconsistent treatment is
    incumbent on the agency and cannot be waived by the decisions
    of third parties. See id. (“[N]either of those parties could
    contract away FERC’s statutory duty—imposed by the APA
    and owed to all other regulated parties—to provide some
    reasonable justification for any adverse treatment relative to
    similarly situated competitors.”).
    The Commission’s attempt to evade this holding pulls
    from dicta in San Diego Gas & Electric Co. v. FERC, in which
    we approved the agency’s rejection of an incentive award
    despite the granting of the award in prior cases. 
    913 F.3d 127
    (D.C. Cir. 2019). We held that approval of the incentive was
    not required by prior orders because earlier decisions “[did] not
    amount to policy or precedent.” 
    Id. at 142
     (citation and
    quotation marks omitted). For this principle, San Diego Gas
    cited an earlier decision in which we required FERC to explain
    inconsistencies, even though we ultimately concluded such
    inconsistencies had been adequately explained. 
    Id.
     (citing Gas
    Transmission Nw. Corp. v. FERC, 
    504 F.3d 1318
    , 1320 (D.C.
    Cir. 2007)). Applying longstanding principles of arbitrary and
    capricious review, San Diego Gas maintained the requirement
    that agencies must reasonably explain disparate treatment of
    similarly situated parties. Contrary to the view of our dissenting
    colleague, San Diego Gas did not, and could not have, altered
    settled law.
    12
    Our standards for arbitrary and capricious review
    distinguish between an agency’s burden of explanation when
    announcing new rules and when applying existing rules in
    individual cases. When an agency seeks to change policy, we
    assess its actions under the rigorous standards of FCC v. Fox
    Television Stations, Inc., by requiring the agency to “display
    awareness that it is changing position,” show “the new policy
    is permissible under the statute,” and “show that there are good
    reasons for the new policy.” 
    556 U.S. 502
    , 515–16 (2009). By
    contrast, an agency applying existing policy must explain how
    an outcome coheres with previous decisions. We require
    agencies to justify different results reached under the same rule
    in order to lend predictability and intelligibility to the
    announced standard, promote fair treatment, and facilitate
    judicial review. See LeMoyne, 
    357 F.3d at 61
    . If a party
    plausibly alleges that it has received inconsistent treatment
    under the same rule or standard, we must consider whether the
    agency has offered a reasonable and coherent explanation for
    the seemingly inconsistent results. See Point Park Univ. v.
    NLRB, 
    457 F.3d 42
    , 50 (D.C. Cir. 2006) (“Without a clear
    presentation of the [agency’s] reasoning, it is not possible for
    us to perform our assigned reviewing function and to discern
    the path taken by the [agency] in reaching its decision.”).
    In the view of our dissenting colleague, an agency need not
    explain disparate outcomes under the same rule unless parties
    opposed the agency’s administration of the rule in the prior
    cases. Dissenting Op. at 2. Thus, the dissent frames our
    decision as fashioning a new requirement for agency action. 
    Id. at 7
    . But it cannot be argued “the great principle that like cases
    must receive like treatment” is anything but black letter
    administrative law. NLRB v. Gen. Stencils, Inc., 
    438 F.2d 894
    ,
    905 (2d Cir. 1971) (Friendly, J.).
    13
    The APA’s requirement of reasonableness incorporates
    basic principles of fair notice and equal treatment inherent to
    the rule of law. Regulated parties are entitled to know what an
    agency’s rules require and to assume that administration of the
    rules will be reasonably predictable and coherent across cases.
    FERC cannot avoid its obligation to provide a reasoned
    explanation for contrary treatment of “similarly situated”
    parties solely because those decisions were uncontested or
    unreasoned. See ANR Storage, 904 F.3d at 1025.
    C.
    Under our standards for reasoned decisionmaking, FERC
    fares far better on its final argument: that it in fact provided an
    adequate explanation to distinguish this case from prior
    decisions. The Commission reasonably determined BGE
    waited far longer than the other four utilities to collect
    accumulated FAS 109 amounts and failed to offer an adequate
    reason for the delay. See Rehearing Order at P 28 (noting PPL
    and Duquesne involved delays of four and seven years,
    respectively, compared to BGE’s twelve). Moreover, FERC
    offered specific ways in which each of the four prior cases
    differed from BGE’s filings in at least one key respect. See id.
    at P 28 n.86 (distinguishing BGE from PPL, Duquesne, and
    VEPCO based on the type of makeup provisions sought and on
    specific accounting matters), P 30 (noting Midcontinent and
    VEPCO sought collection on deficiencies going forward rather
    than accumulated amounts). Because FERC detailed these
    differences in the administrative orders rejecting BGE’s filing,
    we conclude the Commission met its burden to reasonably
    explain the decision. This is enough to survive arbitrary and
    capricious review.
    14
    IV.
    FERC’s rejection of BGE’s tariff filing is a reasonable and
    reasonably explained application of Order No. 144.
    Accordingly, the petition for review is
    Denied.
    WILLIAMS, Senior Circuit Judge, dissenting with respect
    to Part III:
    BGE argues that, notwithstanding the requirements of
    Order No. 144, FERC has been more permissive with four other
    “similarly situated” utilities. Pointing to four orders that it
    views as reaching decisions inconsistent with FERC’s ruling
    here, BGE argues that FERC’s rejection of its rate filing, and
    failure (in BGE’s view) to distinguish the prior decisions,
    violates the standard requirement that agency decisions be
    reasoned. BGE Br. 38; BGE Reply 15–21.
    The majority agrees with BGE that the Commission was
    obliged to distinguish these orders, but finds that it did so
    adequately. I believe that under the circumstances the
    Commission was under no obligation to distinguish the orders,
    and therefore don’t reach the question of whether its efforts to
    do so were good enough.
    I would hold that FERC’s duty to distinguish the orders
    cited by BGE, or to articulate an intentional break with them
    that would satisfy the requirements of FCC v. Fox Television
    Stations, Inc., 
    556 U.S. 502
    , 515–16 (2009), turns on whether
    the pertinent issues were “squarely presented and necessarily
    resolved by the agency” in those past cases, as we held in San
    Diego Gas & Electric Company v. FERC, 
    913 F.3d 127
    , 142
    (D.C. Cir. 2019). That standard is met if but only if the
    Commission’s seeming resolution of the issue has been clearly
    opposed (typically by a party opposing the agency’s decision
    though in some cases staff opposition would likely suffice). As
    far as we know, no such opposition was presented in the
    generation of the four orders at issue here.1
    1
    I am uncertain whether it should make any difference
    whether the agency action was by staff or by the Commissioners
    themselves. Cf. Maj. Op. 9–10. Under my view it would make no
    2
    This approach, established in our case law, ensures that
    any comparisons between new and old cases rest on a clash
    between an agency rejection of clearly asserted propositions of
    fact, law or policy, and is analogous to how, in federal courts,
    “[q]uestions which merely lurk in the record, neither brought to
    the attention of the court nor ruled upon, are not to be
    considered as having been so decided as to constitute
    precedents,” Cooper Industries, Inc. v. Aviall Services, Inc.,
    
    543 U.S. 157
    , 170 (2004) (quoting Webster v. Fall, 
    266 U.S. 507
    , 510 (1925), and relied on in San Diego Gas & Electric
    Co., 913 F.3d at 142)).
    Given the number of uncontested issues that an agency
    typically resolves—uncontested, we may infer, either because
    any adversely affected parties got no notice or, having notice,
    thought it not worth the trouble to oppose—a requirement that
    an agency address its past vermicelli, either by reconciling its
    current decision with the earlier record or by applying Fox
    Television, would tie courts and agencies in linguistic knots for
    little or no benefit to the rule of law. Indeed, the majority’s
    approach invites a litigant to dive deep into the records of past
    agency cases, find one with facts loosely comparable to its own
    case, and then require the agency to adjudicate, ex post and
    likely on a limited record, whether and to what extent each past
    case is like the present one. Our precedents do not require this.
    difference here, because in the four allegedly contradictory
    decisions neither staff nor Commissioners confronted a claim
    contrary to their disposition.
    As a general matter I agree with the majority that the
    decisionmakers’ lack of reasoning in their prior ruling should not
    excuse their disregard of an apparent contradiction with that ruling.
    Maj. Op. 10.
    3
    The majority rests its more sweeping view of the agency’s
    duty to distinguish prior cases largely on ANR Storage Co. v.
    FERC, 
    904 F.3d 1020
     (D.C. Cir. 2018). But our decision there
    appears to have been driven overwhelmingly by the incongruity
    between the Commission’s denying ANR Storage marketing
    flexibility after having granted the same flexibility to two
    subsidiaries of DTE Energy that were direct competitors of
    ANR Storage. As measured by FERC’s own criterion for
    granting flexibility—absence of market power in the relevant
    market—ANR and DTE were nearly identical twins: ANR’s
    market share was substantially the same as DTE’s. 904 F.3d at
    1025. As we said, “[B]y FERC’s own reckoning, ANR and
    DTE appear virtually indistinguishable with respect to their
    current market power.” Id. at 1024–25.
    Thus, our primary theme in ANR Storage was FERC’s
    wholly unexplained divergence in its treatment of two virtually
    identical competitors. See id. at 1024 (“DTE was then a strong,
    established competitor, just as ANR is today.”); id. at 1025
    (referring to “FERC’s statutory duty—imposed by the APA
    and owed to all other regulated parties—to provide some
    reasonable justification for any adverse treatment relative to
    similarly situated competitors” (emphasis added)); id. at 1026
    (“ANR and DTE seem indistinguishable as leading competitors
    with virtually identical shares in the same relevant markets.”).
    In ANR Storage, FERC had offered an astonishing argument (a
    promising candidate for a chutzpah award) that ANR’s “market
    power posed a greater concern because [its] largest
    competitor—DTE—already was charging market rates,” to
    which we replied, “We frankly doubt that FERC may pick
    winners and losers in this way, based on which of two
    otherwise indistinguishable competitors happens to win a race
    to the FERC equivalent of a courthouse.” Id. at 1025–26
    (emphasis added).
    4
    ANR Storage’s insistence that the Commission confront its
    different treatment of two competing utilities is, incidentally,
    boosted by our precedent treating such disparate treatment as a
    freestanding violation of the FPA’s ban on discriminatory rates
    where two utilities are in competition. In Dynergy Midwest
    Generation, Inc. v. FERC, 
    633 F.3d 1122
    , 1125, 1127 (D.C.
    Cir. 2011), we vacated a FERC order approving a regional
    transmission organization’s method of compensating
    competing generators for their provision of certain specialized
    power. The case is distinct from ANR Storage in that the
    competing public utilities were selling the special power to yet
    another FERC-regulated utility, the regional transmission
    organization. 
    Id. at 1124
    . But what unifies the cases is they
    arise from the technologically induced development of
    competition between power generators subject to regulation
    under the terms of the FPA—which had been passed in a quite
    different era, when generators subject to its terms could
    generally be expected to wield monopoly power. Unlike in
    ANR Storage, there is no suggestion here that any of the firms
    said to have been treated more favorably than BGE was in any
    way its competitor.
    Besides reversing FERC because of its utterly inconsistent
    treatment of competitors, ANR Storage used language
    potentially applicable to non-competitive situations. We said,
    for example, “In particular, [an agency] decision must give a
    ‘reasoned analysis’ to justify the disparate treatment of
    regulated parties that seem similarly situated, W. Deptford
    Energy, LLC v. FERC, 
    766 F.3d 10
    , 21 (D.C. Cir. 2014).” ANR
    Storage, 904 F.3d at 1024. The majority accordingly treats the
    case as applying that precept even in a case where no one
    opposed the agency ruling in the prior “precedents.” Some
    language of the decision may point that way, but in partial
    response to a Commission argument that the application for
    flexibility by one of DTE’s two subsidies had been unopposed,
    we noted that the other subsidiary’s application “was opposed,”
    5
    904 F.3d at 1025 (emphasis in original). So ANR Storage
    hardly represents adoption of the majority’s demanding rule.
    Nor do the other cases cited by the majority support its
    position. West Deptford Energy involved a Commission’s
    switcheroo on whether a generator joining a regional
    transmission organization should be governed by the tariff in
    effect at the time it applied to join or at the time it actually
    joined. Four times the Commission had confronted filings by
    a regional transmission organization proposing the former rule,
    and four times the Commission had insisted on the latter. See
    766 F.3d at 19–21. We thought that “the Commission failed,
    at multiple steps, to provide any reasoned explanation of how
    its [latest] decision conformed to the Federal Power Act and
    prior precedent,” id. at 24, and we therefore required an
    explanation. West Deptford Energy is thus wholly different
    from the sort of case, like the instant one, in which the
    Commission’s past treatment of the issue now relevant was
    uncontested by anyone before the agency.
    Similarly, in LeMoyne-Owen College v. NLRB, 
    357 F.3d 55
     (D.C. Cir. 2004) (Roberts, J.), the College contested the
    application of the Board’s stated standard for classifying
    faculty members as managerial employees. It had called the
    Regional Director’s attention to distinctions between its
    situations and the cases on which he had relied, as well as to
    favorable cases that he had ignored—all cases in which the
    conflict had been clearly posed. Its claim having been brushed
    off by the Regional Director, the College raised the point before
    the Board, which dismissed the matter, “declaring in a one-
    sentence order that the College had ‘raised no substantial issues
    warranting review.’” 
    Id. at 60
    . We thought differently and
    reversed. NLRB v. General Stencils, Inc., 
    438 F.2d 894
     (2d Cir.
    1971), see Maj. Op. 12–13, is also a standard example of an
    agency’s failing to explain the relationship between the
    6
    decision being reviewed and prior contested decisions resting
    on an apparently inconsistent theory.
    The majority cites Point Park University v. NLRB, 
    457 F.3d 42
    , 50 (D.C. Cir. 2006), for the proposition that an agency
    must explain its reasoning so we can “perform our assigned
    reviewing function.” Maj. Op. 12. While that’s of course true,
    the opinion’s concern was with the NLRB’s complete failure to
    present reasoning clear enough to enable the court to discern
    “the path taken.” 457 F.3d at 50. Very specifically, the Board
    had failed to meet our insistence in LeMoyne-Owen that it
    explain “which factors are significant and which less so, and
    why.” Id. (quoting LeMoyne-Owen). See also NLRB v. Yeshiva
    University, 
    444 U.S. 672
     (1980). The case in no way fits the
    majority’s idea that an agency must reconcile a decision under
    review with all prior rulings, even if never contested.
    Finally, in San Diego Gas & Electric Company v. FERC
    (mysteriously dismissed as “dicta” by the majority, see Maj.
    Op. 11), the court acknowledged that FERC had treated like
    parties differently; FERC denied San Diego Gas recovery of
    costs incurred before the agency issued an order granting
    recovery of those costs, whereas FERC had granted similar pre-
    order costs for other utilities. 
    913 F.3d 127
    , 142. We found
    this apparent inconsistency no cause for reversal. “We have
    previously held that, ‘[i]n the absence of protests,’ the
    Commission’s decision to approve rate increases does not
    amount to ‘policy or precedent.’” 
    Id.
     (emphasis added) (citing
    Gas Transmission Nw. Corp. v. FERC, 
    504 F.3d 1318
    , 1320
    (D.C. Cir. 2007)). Accordingly, we required no explanation of
    the difference.
    In my view, the majority breaks from our sensible and
    well-reasoned precedents, and I therefore respectfully dissent.