Gulf South Pipeline Company v. FERC ( 2020 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued January 14, 2020              Decided April 10, 2020
    No. 19-1074
    GULF SOUTH PIPELINE COMPANY, LP,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Michael E. McMahon argued the cause for petitioner.
    With him on the briefs were A. Gregory Junge, Sean Marotta,
    and Matthew J. Higgins.
    Beth G. Pacella, Deputy Solicitor, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were Robert H. Solomon, Solicitor, and
    Carol J. Banta, Senior Attorney. Robert M. Kennedy Jr.,
    Attorney, entered an appearance.
    Before: HENDERSON and RAO, Circuit Judges, and
    RANDOLPH, Senior Circuit Judge.
    Opinion for the Court filed by Circuit Judge RAO.
    2
    RAO, Circuit Judge: Gulf South Pipeline Company filed an
    application with the Federal Energy Regulatory Commission
    (“FERC”) in order to build an expansion to its existing pipeline
    network. Because the expansion facilities will be dramatically
    more expensive to construct than the surrounding facilities
    were, Gulf South requested “incremental-plus rates”—also
    called “additive rates”—under which all natural gas shippers
    who use the new facilities will be charged a higher rate
    reflecting the cost of construction. FERC denied the proposed
    shipping rates. Instead, FERC effectively approved two
    separate rates for using the expansion facilities. Only Entergy
    Louisiana, a new shipper that entered into a long-term contract
    primarily to use the expansion facilities, will pay a higher rate
    reflecting the cost of the expansion. Gulf South’s existing
    shippers will pay a fraction of this cost to use the new facilities.
    We hold that FERC’s rejection of incremental-plus rates
    was arbitrary and capricious. Under FERC’s order, materially
    identical shippers will pay dramatically different rates for the
    use of the same facilities. FERC failed to justify that disparity,
    and its decision violated fundamental ratemaking principles—
    namely, that rates should generally reflect the burdens imposed
    and benefits drawn by a given shipper. We therefore vacate the
    part of FERC’s order denying incremental-plus rates and
    remand for further proceedings consistent with this opinion.
    We deny Gulf South’s petition for review in all other respects,
    including the company’s objections related to its initial rate of
    return and depreciation rate.
    I.
    Gulf South operates an extensive network of natural gas
    pipelines in the southeastern United States. This case is about
    an application filed by Gulf South under Section 7 of the
    3
    Natural Gas Act, 15 U.S.C. § 717f, which governs the
    construction or expansion of pipeline facilities. To build an
    expansion, a company must first receive a “certificate of public
    convenience and necessity issued by the Commission.”
    Id. § 717f(c).
    FERC will grant such a certificate only if it finds the
    project “is or will be required by the present or future public
    convenience and necessity.”
    Id. § 717f(e).
    FERC may “attach
    to the issuance of the certificate and to the exercise of the rights
    granted thereunder such reasonable terms and conditions as the
    public convenience and necessity may require.”
    Id. FERC also
    reviews initial shipping rates proposed by pipeline companies
    for new facilities in Section 7 proceedings, but the
    Commission’s orders are meant only “to hold the line” pending
    more extensive ratemaking proceedings under Section 4 of the
    Natural Gas Act. Atl. Ref. Co. v. Pub. Serv. Comm’n of State of
    N.Y., 
    360 U.S. 378
    , 391–92 (1959); see also 15 U.S.C. § 717c.
    In the Section 7 filing at issue, Gulf South proposed an
    expansion within its existing Lake Charles Zone in Louisiana.
    The Westlake Expansion Project will consist of a compressor
    station, 0.3 miles of pipeline, and a handful of other facilities,
    all of which will serve a new power plant owned and operated
    by Entergy Louisiana. Gas cannot be delivered to the new
    power plant unless a shipper uses the new compressor station,
    which in turn will be used only if a shipper is delivering gas to
    the plant. To deliver gas to Entergy’s power plant, a shipper
    must also use existing Lake Charles facilities—namely, several
    miles of an existing pipeline known as the Index 198-3 loop.
    However, after natural gas passes through the new compressor
    station, it “will, due to pressure differentials, be physically
    isolated from the rest of the Lake Charles Zone.” Request for
    Rehearing of Gulf South Pipeline Co., LP, at 6 (June 18, 2019)
    (“Rehearing Request”).
    4
    Entergy, which both operates the new power plant and
    ships natural gas, entered a precedent agreement with Gulf
    South—i.e., a long-term contract—agreeing to purchase the
    entire shipment capacity of the expansion facilities for 20
    years. Despite that agreement, Gulf South claims existing
    shippers in the Lake Charles Zone will at times be able to
    secure access to the expansion facilities and deliver gas to
    Entergy’s power plant on what is known as a “secondary-firm”
    basis. Gulf South Br. 7–11. FERC does not dispute that this
    could occur on at least some occasions. See, e.g., Gulf South
    Pipeline Co., LP, 166 FERC ¶ 61,089, ¶ 24 (Feb. 1, 2019)
    (“Rehearing Order”) (noting that existing shippers will have
    “limited” access). 1
    FERC approved Gulf South’s application to construct the
    expansion facilities but denied three of the company’s
    requested rates. See Gulf South Pipeline Co., LP, 163 FERC
    ¶ 61,124 (May 17, 2018) (“Certificate Order”). First, FERC
    rejected Gulf South’s proposed incremental-plus rates. Under
    1
    More specifically, Gulf South claims that existing shippers will
    occasionally be able to “bump” Entergy by taking advantage of
    FERC’s open-access policy and priority rules. See Transwestern
    Pipeline Co., 99 FERC ¶ 61,356, ¶ 11–12 (June 27, 2002) (holding
    that a secondary-firm shipper’s deliveries have priority over primary-
    firm shippers like Entergy if the latter fails to schedule a delivery
    early enough). Of course, the expansion facilities will be used
    exclusively to deliver gas to Entergy’s power plant, so it is not clear
    why or when secondary-firm shippers would bump Entergy in order
    to sell to Entergy. See Oral Argument at 8:48–9:45 (discussion in
    which Gulf South suggested that Entergy might be forced to buy gas
    from secondary-firm shippers who secure capacity through FERC’s
    priority rules). In any event, all parties agree that on some occasions
    shippers other than Entergy might obtain access to the facilities on a
    secondary-firm basis, so we assume for the purposes of this appeal
    that it can occur.
    5
    Gulf South’s proposal, all shippers using the expansion
    facilities would pay “both the Lake Charles Zone Rates and the
    Westlake Expansion Rates.”
    Id. at ¶
    16. In other words, all
    shippers would pay their normal rates for use of the Lake
    Charles Zone facilities, but any shipper who uses the expansion
    facilities would pay an additional rate reflecting the cost of
    construction. FERC rejected this proposal in favor of a scheme
    in which only the expansion shipper—i.e., Entergy—would
    pay an incremental rate, while the zone’s existing shippers
    would pay only their normal Lake Charles Zone rates, even
    when they use the expansion facilities.
    Id.
    at ¶
    ¶ 21–22. Because
    the expansion facilities will be far more expensive to construct
    than the existing facilities, the rate disparity is significant.
    Entergy will pay more than four times more than other
    shippers—a rate of $0.1325 per dekatherm of natural gas, while
    existing shippers who use the expansion facilities will pay a
    rate of $0.03 per dekatherm. Rehearing Order at ¶ 20.
    Next, FERC rejected Gulf South’s requested depreciation
    rate of 2.86 percent, which is based on an estimated 35 year
    useful life for the new power plant. Certificate Order at ¶ 19.
    FERC rejected that proposal in favor of a 1.32 percent rate—
    the same depreciation rate set for the existing Lake Charles
    Zone.
    Id. at ¶
    23. Finally, FERC rejected Gulf South’s
    proposed initial rate of return. Gulf South had argued that
    FERC should incorporate recent changes to the company’s
    capital structure, which would allegedly result in an initial rate
    of return of 10.81 percent.
    Id. at ¶
    ¶ 17–18. FERC rejected that
    proposal, reasoning that Gulf South must continue to use its last
    approved rate of return.
    Id. at ¶
    24. FERC set these three initial
    rates under Section 7; however, Gulf South may request
    recalculation of these rates when it next files an application
    under Section 4 of the Natural Gas Act, 15 U.S.C. § 717c, at
    which point FERC will hold a full evidentiary hearing.
    6
    Gulf South filed a request for rehearing, which the
    Commission denied with respect to all three rates. See
    Rehearing Order at ¶¶ 11–30. Gulf South then filed a petition
    for judicial review, claiming that FERC’s rejection of these rate
    proposals was arbitrary and capricious under the
    Administrative Procedure Act (“APA”). See 5 U.S.C.
    § 706(2)(A). We have jurisdiction under the Natural Gas Act’s
    judicial review provision. See 15 U.S.C. § 717r(b).
    II.
    For the reasons discussed below, we conclude that FERC
    failed to reasonably explain its denial of incremental-plus rates.
    FERC’s precedent suggests that incremental-plus rates are
    appropriate when it is possible to track which shippers are
    using expansion facilities, thus ensuring that a pipeline
    company will not over recover its construction costs. FERC
    denied incremental-plus rates here even though Gulf South will
    indisputably be able to track which shippers use the expansion
    facilities. FERC’s sole rationale for doing so was that the
    expansion facilities and existing facilities will be operated as a
    single integrated system, but the Commission failed to explain
    why that fact supported the denial of incremental-plus rates.
    We therefore vacate the Commission’s order in part. However,
    we uphold FERC’s denial of Gulf South’s proposed initial rate
    of return and depreciation rate. In Section 7 proceedings
    governing a project’s initial approval, FERC’s general policy
    is to adopt a company’s last approved initial rate of return and
    last approved depreciation rate until a full hearing can be held
    in the company’s next Section 4 rate case. Gulf South does not
    challenge that policy as a general matter, and it has not shown
    that a departure was warranted in this case.
    7
    A.
    FERC rejected Gulf South’s proposed incremental-plus
    rates under its general policy of disallowing such rates in
    “integrated” systems—that is, in systems where the old and
    new facilities are operated as a single system. Gulf South
    challenges FERC’s integration finding and also argues in the
    alternative that FERC should have approved incremental-plus
    rates regardless of whether the integration finding was correct.
    Although we determine that the record includes substantial
    evidence supporting FERC’s factual finding regarding
    integration, we hold that FERC did not adequately explain why
    this finding justified rejecting incremental-plus rates.
    FERC developed the concept of “integration” to guide its
    discretion in setting rates for pipeline systems, but it is not a
    statutory term. See Battle Creek Gas Co. v. Fed. Power
    Comm’n, 
    281 F.2d 42
    , 46 (D.C. Cir. 1960) (explaining that “the
    Commission has … a general preference for [considering
    integration] whenever it may equitably be” done because there
    are “apparent advantages” to “recogniz[ing] that a gas pipeline
    … is not just a collection of discrete pieces and parts, but an
    integrated system serving all of its customers”). Whether
    facilities are integrated is a question of fact we review under
    the Natural Gas Act’s substantial evidence standard. See
    Chippewa & Flambeau Imp. Co. v. FERC, 
    325 F.3d 353
    , 360
    (D.C. Cir. 2003); Fla. Mun. Power Agency v. FERC, 
    315 F.3d 362
    , 367 (D.C. Cir. 2003). “The finding of the Commission as
    to the facts, if supported by substantial evidence, shall be
    conclusive.” 15 U.S.C. § 717r(b). The standard “requires more
    than a scintilla, but can be satisfied by something less than a
    preponderance of the evidence.” Minisink Residents for Envtl.
    Pres. & Safety v. FERC, 
    762 F.3d 97
    , 108 (D.C. Cir. 2014)
    (citation and quotation marks omitted).
    8
    Facilities are integrated when “the pipeline operate[s] the
    new facilities and the old facilities as a single system.” Tenn.
    Gas Pipeline Co., 80 FERC ¶ 61,070, 61,209 (July 18, 1997).
    “Put another way, an expansion facility is integrated when
    existing facilities effectuate service on the expansion facility,
    or vice versa.” Equitrans, LP, 155 FERC ¶ 61,194, ¶ 10 (May
    20, 2016). “Conversely, an expansion facility is not integrated
    when it is operationally isolated and does not rely on existing
    facilities to effectuate service.”
    Id. at ¶
    10 n.19 (citing Colo.
    Interstate Gas Co., 122 FERC ¶ 61,256, ¶ 60 (Mar. 21, 2008)).
    FERC has said that integration “is commonly illustrated by: (1)
    an inability to know whether old or new [shippers] are using
    either old or new facilities at any particular time; and (2) the
    ability of either the old or new customers to take service from
    either set of facilities if either set of facilities breaks down.”
    Tenn. Gas Pipeline, 80 FERC ¶ 61,070 at 61,209; see also
    Battle 
    Creek, 281 F.2d at 47
    (describing an integrated system
    as one where the “new gas is to be commingled with the old
    gas, and both are to be distributed together to all customers”).
    That said, FERC has explained that while those two
    characteristics are illustrative, the “test for integration is
    broader” and focuses more generally on whether the old and
    new facilities are operated as a single system. Equitrans, 155
    FERC ¶ 61,194 at ¶ 10.
    Gulf South argues that the system will not be integrated
    because the company is able to determine who is using the
    expansion facilities and because old and new shippers cannot
    take service from either set of facilities if one breaks down—
    the two features that “commonly illustrate[ ]” integration.
    Tenn. Gas Pipeline, 80 FERC ¶ 61,070 at 61,209. While this
    system does not share those characteristics, there was enough
    evidence “under our deferential standard of review,” Fla. Mun.
    
    Power, 315 F.3d at 367
    , for FERC to find that the facilities will
    9
    be integrated. There is no dispute that gas delivered to
    Entergy’s new power plant will travel almost entirely through
    existing pipelines. It is also undisputed that the new facilities
    will be segmented by existing facilities. That is, natural gas will
    flow back into existing facilities after it passes through the new
    compressor station, even if it is kept physically isolated due to
    pressure differentials.
    FERC has repeatedly emphasized in prior cases that
    integration depends largely on whether the new facilities will
    rely on the old facilities to effectuate service. See, e.g., Colo.
    Interstate, 122 FERC ¶ 61,256 at ¶ 61 (finding that facilities
    were not integrated because the “system will not use any
    existing pipeline segment on [the existing] mainline system and
    there are no interconnections between the facilities that would
    allow gas to flow from one system to another” and “the existing
    compression facilities on [the existing] mainline system [will
    not] be used to effectuate [the expansion project’s] receipts and
    deliveries”); Equitrans, 155 FERC ¶ 61,194 at ¶ 12 (finding
    that facilities were integrated because “expansion service is
    made possible by the existing system”). The Commission’s
    factual conclusion regarding integration was consistent with its
    precedents in emphasizing that existing facilities will be used
    to effectuate service. We should hesitate to displace agency
    expertise on complex factual questions, and substantial
    evidence supports FERC’s integration finding here.
    That factual finding does not, however, end the matter.
    Our review turns on whether FERC’s order was reasonable,
    and the agency cannot use the term “integration” as a
    placeholder for reasoned decisionmaking. We will uphold
    FERC’s order only if it “articulate[d] … a rational connection
    between the facts found and the choice made.” FERC v. Elec.
    Power Supply Ass’n, 
    136 S. Ct. 760
    , 782 (2016). FERC has
    10
    failed to articulate that connection here. Most importantly, the
    usual justifications for denying incremental-plus rates in
    integrated systems do not apply in this case. In its rehearing
    order, FERC offered this explanation for its general policy:
    The Commission allows incremental plus pricing for
    service utilizing non-integrated facilities because for
    such facilities, the Commission can distinguish
    which customers are using the new facilities and
    which customers are using the existing facilities,
    making it possible to ensure that a company is not
    over-recovering its actual costs. For integrated
    expansions, where it is unclear which customers are
    using the new or old facilities, the Commission has
    found the appropriate means for preventing the over-
    recovery of costs is to authorize pipelines to charge
    only an incremental rate to customers subscribing the
    expansion service.
    Rehearing Order at ¶ 8. That justification has no bearing in this
    case. No one disputes that FERC can easily distinguish which
    customers are using the new facilities and which are using the
    old. The compressor station will be used by every shipper
    delivering gas to Entergy’s power plant—and only those
    shippers. As a result, there is no risk that incremental-plus rates
    will impact existing customers’ service. To the contrary,
    existing customers will be charged a higher rate only if they
    choose to use the new facilities to ship gas to the new power
    plant. No shippers will be charged more for their existing
    services, and FERC has failed to explain why there is a risk that
    Gulf South will over recover its costs for the expansion.
    In addition, Gulf South argues that FERC’s conclusion
    was inconsistent with fundamental principles of cost causation,
    11
    which hold that rates should reflect “the burdens imposed or
    the benefits drawn by” a given shipper. BNP Paribas Energy
    Trading GP v. FERC, 
    743 F.3d 264
    , 267 (D.C. Cir. 2014). We
    agree FERC’s order was inconsistent with those principles. As
    a general rule, the Commission “may not single out a party for
    the full cost of a project, or even most of it, when the benefits
    of the project are diffuse.”
    Id. at 268.
    Instead, “[p]roperly
    designed rates should produce revenues from each class of
    customers which match, as closely as practicable, the costs to
    serve each class or individual customer.” Ala. Elec. Co-op.,
    Inc. v. FERC, 
    684 F.2d 20
    , 27 (D.C. Cir. 1982). While “the
    Commission may rationally emphasize other, competing
    policies and approve measures that do not best match cost
    responsibility and causation,” Carnegie Nat. Gas Co. v. FERC,
    
    968 F.2d 1291
    , 1294 (D.C. Cir. 1992), cost-causation
    principles are the default, and “we have approved the
    Commission’s departure from traditional cost-causation
    principles in only limited circumstances,” United Distrib. Cos.
    v. FERC, 
    88 F.3d 1105
    , 1186 (D.C. Cir. 1996). Here, the rates
    set by FERC do not reflect the benefits drawn by a given
    shipper. When Entergy uses the expansion facilities, it will pay
    a rate of $0.1325 per dekatherm. When existing shippers use
    the same facilities, they will pay their existing Lake Charles
    rate of $0.03 per dekatherm.
    FERC has offered three responses to Gulf South’s cost
    causation argument. While FERC is permitted to depart from
    strict cost causation to further competing policies, see Carnegie
    Nat. 
    Gas, 968 F.2d at 1293
    –94, none of the three responses
    provides a rational justification for the rate disparity in this
    case. First, FERC concluded in its rehearing order that a
    departure from cost-causation principles is appropriate to
    “reflect[ ] the fact that [existing] shippers are paying for the
    underlying facilities under which the pipeline is providing
    12
    service, such as Gulf South’s existing Index 198-3.” Rehearing
    Order at ¶ 19. Similarly, FERC notes that Entergy will be able
    to ship gas to other delivery points in the Lake Charles Zone
    without paying an added fee.
    Id. at ¶
    22. Neither fact justifies a
    departure from cost-causation principles. While it is true that
    existing shippers are already paying for the existing facilities,
    those facilities cost a fraction of the price of the expansion. The
    expansion facilities will cost $56.2 million to build, while the
    net cost of the existing Lake Charles Zone facilities was only
    $6.3 million.
    Id. at ¶
    13. To say that existing shippers should
    enjoy access to the more expensive expansion facilities because
    they are already paying for the less expensive existing facilities
    is not a justification for departing from cost causation. Instead,
    it is a simple admission that FERC’s order is a departure from
    cost causation. FERC’s assurance that Entergy will be able to
    ship gas to other delivery points in the Lake Charles Zone
    without paying an added reservation rate is unavailing for the
    same reason: Those facilities were a fraction of the cost of the
    Westlake Expansion, so Entergy’s open access to the rest of the
    Lake Charles Zone does not cure the disparity in rates charged
    for use of the expansion facilities.
    Second, FERC noted that it has a “longstanding policy …
    that shippers should have access to secondary receipt and
    delivery points in the zone for which they pay a reservation
    charge.”
    Id. at ¶
    22. This policy gives shippers more “flexibility
    in receipt and delivery points.”
    Id. Yet Gulf
    South does not
    challenge FERC’s policy of allowing secondary-firm shippers
    to access expansion facilities. The question is how much those
    shippers should pay if they do so. FERC failed to explain why
    shippers who take advantage of FERC’s open-access policy
    should pay a rate that bears no relation to the cost of the
    facilities they use.
    13
    Third, FERC concluded that incremental-plus rates are
    inappropriate because expansion shippers like Entergy “must
    pay for the cost of the new capacity constructed for their
    needs.”
    Id. at ¶
    19. “To the extent that the pipeline has
    unsubscribed capacity …, then it must make a business
    decision as to whether to move forward with the project.
    However, an existing shipper’s ability to access the
    incremental capacity at a lower rate on a secondary basis in no
    way hinders the pipeline’s ability to recover its costs.”
    Id. Again, this
    explanation does not explain the departure from
    cost-causation principles. This is not a case where, in FERC’s
    words, “the pipeline has unsubscribed capacity,”
    id., thus creating
    a risk that existing customers will be saddled with the
    costs of construction. In those circumstances, it may be rational
    for FERC to hold that only expansion shippers should pay
    higher rates, forcing the company to “make a business decision
    as to whether to move forward” despite the risk.
    Id. Here, Gulf
    South has already entered into a precedent agreement
    accounting for all of the facilities’ capacity for 20 years, cf.
    Myersville Citizens for a Rural Cmty., Inc. v. FERC, 
    783 F.3d 1301
    , 1311 (D.C. Cir. 2015) (noting that FERC’s policy is “to
    not look behind precedent or service agreements” to evaluate
    market need), and FERC has emphasized that as a practical
    matter secondary-firm shippers will have only “limited” access
    to the facilities, Rehearing Order ¶ at 24. For our purposes, the
    question is not whether existing shippers ought to be burdened
    with the costs of construction if Entergy fails to support the
    project. Rather, the question is how much secondary-firm
    shippers should pay if they voluntarily access the new facilities.
    Again, FERC has not adequately explained why existing
    shippers should pay rates that do not reflect the price of the
    facilities they choose to use.
    14
    FERC’s justifications are further belied by the fact that the
    Commission consistently allows incremental-plus rates
    whenever it is possible to readily discern which shippers are
    using expansion facilities. Indeed, FERC has not identified a
    single case where it has denied incremental-plus rates in those
    circumstances. Most notably, whenever a company builds a
    lateral pipeline, FERC will allow incremental-plus rates
    because it can track which facilities shippers are using.
    Rehearing Order at ¶ 8 (“The Commission allows incremental
    plus pricing for service utilizing non-integrated facilities
    because for such facilities, the Commission can distinguish
    which customers are using the new facilities and which
    customers are using the existing facilities.”). When it comes to
    laterals, it does not matter to FERC that existing shippers
    already pay for the zone’s existing facilities, nor that FERC has
    an open-access policy, nor that pipeline companies must make
    business decisions about whether to build a facility without
    shifting costs to secondary-firm shippers. Despite those
    considerations, FERC allows incremental-plus rates because it
    is possible to track the facilities’ use. FERC has not identified
    any reason to treat laterals differently from Gulf South’s
    proposed expansion.
    Indeed, even in integrated systems, FERC has been willing
    to allow incremental-plus rates when it is possible to track
    which shippers are using which facilities—particularly if doing
    so would prevent different shippers from paying an unfair cost
    differential. In Texas Eastern Transmission, LP, a pipeline
    company proposed to build various new facilities, including
    several new pipeline segments. 139 FERC ¶ 61,138, ¶ 7 (May
    21, 2012). FERC concluded that the expansion would be
    integrated with existing facilities,
    id. at ¶
    32, but the
    Commission was nonetheless concerned that the zone’s
    existing rates would “not reflect the significant costs associated
    15
    with the construction of the project,”
    id. at ¶
    33. The expansion
    rate would have been “over 200 percent greater than the
    existing system” rate, which FERC concluded “would not be
    appropriate.”
    Id. The Commission
    therefore allowed Texas
    Eastern to “accomplish its rate objectives in an acceptable
    manner by creating a new rate zone with separate maximum
    recourse rates” for one of the expansion’s components.
    Id. While Gulf
    South’s primary argument is that FERC should
    allow incremental-plus rates within the Lake Charles Zone, the
    company has argued in the alternative that FERC should allow
    the company to charge the same rates by creating a new rate
    zone including only the expansion facilities, as FERC did in
    Texas Eastern. FERC claims that Texas Eastern is inapposite
    because the “extension was easily distinguishable from the rest
    of Texas Eastern’s mainline system. Thus, existing shippers
    would only pay the additional cost of the new rate zone if they
    elected to transport gas to the new delivery point.” Rehearing
    Order at ¶ 15. Yet that is equally true for Gulf South: The
    company can discern which shippers use the expansion
    facilities and which do not, so existing shippers will, as in
    Texas Eastern, “only pay the additional cost of the new rate
    zone if they elect[ ] to transport gas to the new delivery point.”
    Id. In the
    rehearing order, FERC also briefly suggested that it
    has a policy of allowing new rate zones only “when th[e]
    extension is in a distinct operational and geographical area.”
    Id. at ¶
    16. Yet FERC concluded its discussion in the next sentence
    without any explanation of why geographic separation is
    dispositive. Nor do any of the administrative cases cited by the
    Commission explain why geographically distinct facilities
    should be treated differently. Rehearing Order at ¶ 16 n.42. We
    have no basis to review FERC’s policy because the
    16
    Commission has said nothing about what the policy means or
    why it is justified. See Columbia Gas Transmission Corp. v.
    FERC, 
    448 F.3d 382
    , 387 (D.C. Cir. 2006) (“It will not do for
    a court to be compelled to guess at the theory underlying the
    agency’s action; nor can a court be expected to chisel that
    which must be precise from what the agency has left vague and
    indecisive.”) (quoting SEC v. Chenery Corp., 
    332 U.S. 194
    ,
    196–97 (1947)). Similarly, FERC did not explain why Texas
    Eastern’s expansion was geographically distinct but Gulf
    South’s is not. Both expansions consist of a variety of new
    components attached to or built near existing facilities. The
    only apparent distinction is that Texas Eastern’s expansion
    included a 15.2 mile pipeline segment that was significantly
    longer than the pipeline connecting Entergy’s power plant and
    the Index 198-3 loop. See Texas Eastern, 139 FERC ¶ 61,138
    at ¶ 7. Again, this court cannot evaluate FERC’s conclusion
    without further explanation from the agency.
    If there is a rational explanation for why Texas Eastern and
    Gulf South should be treated differently, FERC has failed to
    articulate it. Both companies proposed to build expansions that
    (1) were integrated; (2) were operationally distinct in such a
    way that would allow the pipeline to avoid burdening existing
    shippers with the costs of construction; and (3) were
    dramatically more expensive than the pipeline’s existing
    facilities. Indeed, the rate disparity in this case (442 percent) is
    far higher than in Texas Eastern. Absent reasonable grounds to
    distinguish the two, FERC should have offered Gulf South the
    same opportunity to charge incremental-plus rates—whether
    through the creation of a new rate zone or as an additional rate
    within the existing Lake Charles Zone. See ANR Storage Co. v.
    FERC, 
    904 F.3d 1020
    , 1025 (D.C. Cir. 2018) (emphasizing
    “FERC’s statutory duty … to provide some reasonable
    justification for any adverse treatment relative to similarly
    17
    situated competitors”); W. Deptford Energy, LLC v. FERC, 
    766 F.3d 10
    , 20 (D.C. Cir. 2014) (“It is textbook administrative law
    that an agency must provide a reasoned explanation for
    departing from precedent or treating similar situations
    differently.”) (quotation marks and alterations omitted). 2
    2
    According to FERC, Gulf South failed to exhaust the argument that
    its desired rates could be achieved through a new rate zone. We
    disagree. The Natural Gas Act provides that “[n]o objection to the
    order of the Commission shall be considered by the court unless such
    objection shall have been urged before the Commission in the
    application for rehearing unless there is reasonable ground for failure
    so to do.” 15 U.S.C. § 717r(b). Here, Gulf South indisputably raised
    the question of a new rate zone in its rehearing application, thus
    satisfying the statute’s exhaustion requirement. See Rehearing
    Request at 18 (“[T]he Commission should allow Gulf South the
    opportunity to create a new rate zone for the expansion facilities,
    consistent with Texas Eastern.”).
    Nonetheless, FERC argues that if a party raises an argument for
    the first time in its rehearing request (rather than in the initial
    application) and FERC rejects it, then the party must raise the
    argument again in a second rehearing application. Nothing in the
    Natural Gas Act nor our case law requires that a party file two
    duplicative rehearing applications. In arguing otherwise, FERC
    mistakenly relies on four cases addressing an unrelated issue. Those
    cases hold that if FERC modifies its order on rehearing, a party
    generally must raise any new complaints in a subsequent rehearing
    application, rather than raise them for the first time in court. See
    Columbia Gas Transmission Corp. v. FERC, 
    477 F.3d 739
    , 741–42
    (D.C. Cir. 2007); Canadian Ass’n of Petroleum Producers v. FERC,
    
    254 F.3d 289
    , 296–97 (D.C. Cir. 2001); Town of Norwood, Mass. v.
    FERC, 
    906 F.2d 772
    , 774–75 (D.C. Cir. 1990); Tenn. Gas Pipeline
    Co. v. FERC, 
    871 F.2d 1099
    , 1109–10 (D.C. Cir. 1989). FERC’s
    rehearing order did not raise a new source of complaint, and Gulf
    South raised its new-rate-zone argument for the first time before the
    18
    Because FERC did not adequately explain its action, we
    hold that the rejection of Gulf South’s proposed incremental-
    plus rates was arbitrary and capricious. See 5 U.S.C.
    § 706(2)(A). While Congress has conferred substantial
    discretion on FERC in the context of rate setting, our review
    under the APA requires the agency to offer reasonable
    explanations for the rates it sets. “If we are to hold that a given
    rate is reasonable just because the Commission has said it was
    reasonable, review becomes a costly, time-consuming pageant
    of no practical value to anyone.” Fed. Power Comm’n v. Hope,
    
    320 U.S. 591
    , 645 (1944) (Jackson, J., dissenting). Here, FERC
    set rates that would require shippers to pay amounts vastly
    disproportionate to the value of the benefits they draw, and
    FERC failed to show why such rates were reasonable. We
    therefore vacate the part of FERC’s order rejecting Gulf
    South’s proposed incremental-plus rates and remand for further
    proceedings. On remand, FERC must also address the
    possibility of a new rate zone, as it did in Texas Eastern in
    materially similar circumstances. 3
    Commission, not in court. FERC was “adequately apprised of” the
    objection, Tenn. 
    Gas, 871 F.2d at 1110
    , and we may consider it on
    appeal.
    3
    In addition to the problems discussed above, Gulf South argues that
    FERC failed to respond to the possibility that shippers will game the
    system by reserving capacity in the Lake Charles Zone solely to take
    advantage of the pricing disparity. Yet FERC reasonably concluded
    that such gamesmanship would be an unlikely and risky endeavor
    given that Entergy has already contracted for 100 percent of the
    facilities’ capacity. Rehearing Order at ¶ 24. FERC’s conclusion was
    neither arbitrary nor capricious. Still, that does not absolve FERC of
    the problems discussed above. FERC has not explained why existing
    19
    B.
    Next, Gulf South challenges FERC’s denial of its proposed
    initial rate of return—i.e., the amount the company is permitted
    to charge in addition to its rate base and operating costs “to
    ensure that pipeline investors are fairly compensated.” N.C.
    Utils. Comm’n v. FERC, 
    42 F.3d 659
    , 661 (D.C. Cir. 1994).
    FERC set an initial rate of return of 10.41 percent, which is
    equal to Gulf South’s last approved rate of return. Rehearing
    Order at ¶ 29. Gulf South claims that FERC should have
    adjusted that rate to reflect recent changes in the company’s
    capital structure.
    When setting initial rates of return for integrated
    expansion facilities in Section 7 proceedings, FERC’s general
    policy is to use the pipeline’s last approved rate.
    Id. at ¶
    ¶ 27–
    28. The company is then free to seek a different rate of return
    in its next general rate filing under Section 4 of the Natural Gas
    Act. See 15 U.S.C. § 717c. The Supreme Court has consistently
    upheld FERC’s policy of deferring the consideration of fact-
    intensive rate questions to the company’s next general rate
    case, because initial Section 7 proceedings are meant only “to
    hold the line awaiting adjudication of a just and reasonable
    rate.” Atl. Ref. 
    Co., 360 U.S. at 392
    ; see also United Gas Imp.
    Co. v. Callery Properties, Inc., 
    382 U.S. 223
    , 227–28 (1965).
    Gulf South argues that this general policy is unreasonable
    as applied to this case because the pipeline’s last approved rate
    of return was set over 20 years ago and because it cannot set a
    new rate until 2023. Yet Gulf South had an opportunity to set
    a new rate of return in 2015 in its most recent rate case, but it
    shippers should pay a lower rate when they secure capacity on the
    expansion facilities, even if it will be rare.
    20
    agreed to settle with FERC and other interested parties without
    doing so. Moreover, both Gulf South and FERC agree that the
    only reason Gulf South cannot set a new rate of return until
    2023 is that the company agreed in its 2015 settlement to a
    moratorium on rate filings. FERC Br. 43; Gulf South Br. 15.
    Thus, the existing rate of return is the result of Gulf South’s
    contractual choices.
    Gulf South asks the court to look past the 2015 settlement
    because it was a “black box” agreement, a settlement in which
    the parties agree to the overarching terms without “explain[ing]
    how the rates were derived. In other words, parties to black box
    settlements agree to rates without identification or attribution
    of costs or adjustments for any particular component of those
    rates.” El Paso Nat. Gas Co., 132 FERC ¶ 61,139, ¶ 82 (Aug.
    17, 2010). Because prices are determined without specifying
    the component parts, no new rate of return is submitted to
    FERC for approval. Yet nothing compels parties to agree to
    black-box settlements. To the contrary, FERC has repeatedly
    encouraged parties to discuss rates of return when reaching
    settlements. See Rehearing Order at ¶ 28 (“Given this policy
    [of setting Section 7 rates based on the most recent approved
    rate of return], the commission encourages companies and
    parties in rate cases to address concerns relating to the rate of
    return that should be used in calculating initial rates in future
    certificate proceedings.”); Transcon. Gas Pipe Line Co., LLC,
    156 FERC ¶ 61,022, ¶ 25 (July 7, 2016) (likewise advising
    parties to “use that opportunity to address issues of concern
    relating to the rate of return”). Other companies have heeded
    this advice. See, e.g., E. Shore Nat. Gas Co., 138 FERC
    ¶ 61,050, ¶ 2 (Jan. 24, 2012) (specifying a rate of return in what
    was otherwise a black-box settlement). Gulf South agreed to
    settle the 2015 rate case without adjusting its rate of return; it
    also agreed to enter an eight year moratorium on rate filings.
    21
    Gulf South’s freely made contractual choices are no reason to
    depart from a longstanding policy, repeatedly upheld by the
    Supreme Court, to use the last approved rate of return.
    Gulf South also argues that FERC should have adjusted
    the rate of return because the formula is so simple it “can be
    calculated with a pencil on the back of an envelope.” Reply Br.
    25. Specifically, Gulf South claims that its rate of return can be
    adjusted by changing a single variable: its capital structure. In
    support, Gulf South cites Missouri Public Service Commission
    v. FERC, where this court held that it was unreasonable for
    FERC to include a premium in a merged pipeline’s Section 7
    rates without conducting the particularized inquiry that would
    normally be required to include a premium of that kind. 
    601 F.3d 581
    , 586–88 (D.C. Cir. 2010). Central to our decision was
    the fact that “FERC easily could have resolved the threshold
    issue on the basis of the uncontested paper record before it in
    the § 7 proceeding.”
    Id. at 587.
    In this case, it was not arbitrary or capricious for FERC to
    conclude that a full Section 4 hearing was necessary before
    adjusting Gulf South’s rate of return. First, it was reasonable
    for FERC to conclude that a full evidentiary hearing would be
    necessary to account for variables other than capital structure—
    for instance, the company’s growth rates and its “position
    within the zone of reasonableness with regard to risk.”
    Rehearing Order at ¶ 28. As the Commission notes, rates of
    return are determined based on a discounted cash flow method,
    which is much more involved than simply adjusting capital
    structure figures. See Bos. Edison Co. v. FERC, 
    885 F.2d 962
    ,
    965 (1st Cir. 1989) (Breyer, J.) (explaining the discounted cash
    flow method in length). Moreover, FERC was understandably
    hesitant to accept Gulf South’s capital structure figures without
    a hearing. In the rehearing order, FERC noted that Gulf South
    22
    inexplicably amended its proposed rate in its rehearing request
    from 10.81 to 10.68 percent. Rehearing Order at ¶ 29. Gulf
    South explained in its opening brief that it “updated the rate of
    return to 10.68 percent, based on its most-recently reported
    capital structure” and “[i]n response to a FERC data request.”
    Gulf South Br. 15 n.4. The fact that Gulf South’s capital
    structure figures fluctuated with more data bolsters FERC’s
    position that it should not adjust the approved rate of return
    without a hearing to assess Gulf South’s data. This case is
    readily distinguishable from Missouri Public Service, where
    the relevant analysis could easily be done without a full
    hearing. 
    See 601 F.3d at 586
    –88. We therefore reject Gulf
    South’s challenge to the initial rate of return of 10.41 percent,
    its last approved rate of return.
    C.
    Finally, Gulf South challenges the rejection of its proposed
    depreciation rate. In this context, “[d]epreciation is generally
    defined as ‘the loss, not restored by current maintenance, which
    is due to all the factors causing the ultimate retirement of the
    property.’” Memphis Light, Gas & Water Div. v. Fed. Power
    Comm’n, 
    504 F.2d 225
    , 228 (D.C. Cir. 1974) (quoting
    Lindheimer v. Ill. Bell Tel. Co., 
    292 U.S. 151
    , 167 (1934)).
    Pipeline companies may include depreciation charges as “a
    legitimate part of [their] operating expenses.”
    Id. To set
    depreciation rates, FERC must “forecast[ ] the probable useful
    life of the specific pipeline systems in question, based both on
    wear and tear and on the exhaustion of natural resources.” Petal
    Gas Storage, LLC v. FERC, 
    496 F.3d 695
    , 702 (D.C. Cir. 2007)
    (quotation marks omitted). A shorter useful life means a higher
    depreciation rate, which in turn “will necessarily increase gas
    prices to current consumers.” Memphis Light, Gas & Water
    
    Div., 504 F.2d at 231
    . As with initial rates of return, FERC’s
    23
    general policy in Section 7 proceedings involving integrated
    expansions is to use the pipeline’s last approved deprecation
    rate. See, e.g., Wyo. Interstate Co., Ltd., 119 FERC ¶ 61,251,
    ¶ 22 (June 7, 2007). Gulf South’s last approved depreciation
    rate was based on the 76 year useful life of the Lake Charles
    Zone facilities, which results in a depreciation rate of 1.32
    percent. Rehearing Order at ¶ 30.
    While Gulf South does not challenge FERC’s policy as a
    general matter, it argues that this case falls within an exception
    for laterals built for a single customer. In those cases, FERC
    has approved depreciation rates based on the length of the
    contract at issue. See, e.g., Millennium Pipeline Co., LLC, 157
    FERC ¶ 61,096, ¶ 32 n.58 (Nov. 9, 2016); Gas Transmission
    Nw., LLC, 142 FERC ¶ 61,186, ¶ 17 (Mar. 14, 2013). Gulf
    South claims those cases should apply here because the length
    of the contract with Entergy is effectively the useful life of the
    expansion facilities. Nonetheless, rather than request a
    depreciation rate based on the 20 year length of the contract
    with Entergy, Gulf South requested a depreciation rate based
    on a useful life of 35 years (2.86 percent). Gulf South’s counsel
    was asked at oral argument why the company requested a
    depreciation rate based on a useful life that is 15 years longer
    than the length of the contract, when the company’s entire
    argument is premised on the notion that the length of the
    contract is the correct benchmark. Counsel responded that Gulf
    South “knew that 20 [years] probably wasn’t the right answer,”
    so it chose a more “practical and realistic” lifespan
    “somewhere between the 76 and the 20” reflecting the “typical
    power plant operational life.” Oral Argument at 8:20.
    That concession is dispositive. Gulf South does not dispute
    that it is generally appropriate in Section 7 proceedings to use
    a pipeline’s last approved depreciation rate. Although FERC
    24
    has recognized an exception for cases in which the length of
    the contract is the more appropriate useful life, Gulf South has
    conceded that the length of the contract “wasn’t the right
    answer” here.
    Id. Gulf South
    has offered no rationale nor cited
    any precedent for an initial depreciation rate based instead on
    a useful life of 35 years. Nor did Gulf South argue in its briefs
    that the depreciation rate should be based on the typical power
    plant’s operational life. See U.S. ex rel. Davis v. D.C., 
    793 F.3d 120
    , 127 (D.C. Cir. 2015) (“[A]rguments raised for the first
    time at oral argument are forfeited.”). We therefore reject Gulf
    South’s challenge to the 1.32 percent depreciation rate.
    ***
    We grant Gulf South’s petition for review in part and
    vacate the part of FERC’s order rejecting incremental-plus
    rates. We deny the petition for review in all other respects and
    remand for further proceedings. FERC must reconsider
    whether to grant incremental-plus rates—whether within the
    Lake Charles Zone or through the creation of a new rate zone—
    and provide an adequate explanation for its action consistent
    with this opinion.
    So ordered.
    

Document Info

Docket Number: 19-1074

Filed Date: 4/10/2020

Precedential Status: Precedential

Modified Date: 4/10/2020

Authorities (19)

Fed. Energy Regulatory Comm'n v. Elec. Power Supply Ass'n , 136 S. Ct. 760 ( 2016 )

Lindheimer v. Illinois Bell Telephone Co. , 54 S. Ct. 658 ( 1934 )

Columbia Gas Transmission Corp. v. Federal Energy ... , 448 F.3d 382 ( 2006 )

Columbia Gas Transmission Corp. v. Ederal Energy Regulatory ... , 477 F.3d 739 ( 2007 )

memphis-light-gas-and-water-division-v-federal-power-commission-united , 504 F.2d 225 ( 1974 )

Securities & Exchange Commission v. Chenery Corp. , 332 U.S. 194 ( 1947 )

Federal Power Commission v. Hope Natural Gas Co. , 64 S. Ct. 281 ( 1944 )

Chippewa & Flambeau Improvement Co. v. Federal Energy ... , 325 F.3d 353 ( 2003 )

boston-edison-company-v-federal-energy-regulatory-commission-towns-of , 885 F.2d 962 ( 1989 )

FL Muni Power Agcy v. FERC , 315 F.3d 362 ( 2003 )

Town of Norwood, Massachusetts v. Federal Energy Regulatory ... , 906 F.2d 772 ( 1990 )

United Distribution Companies v. Federal Energy Regulatory ... , 88 F.3d 1105 ( 1996 )

canadian-association-of-petroleum-producers-v-federal-energy-regulatory , 254 F.3d 289 ( 2001 )

tennessee-gas-pipeline-company-v-federal-energy-regulatory-commission , 871 F.2d 1099 ( 1989 )

Petal Gas Storage, L.L.C. v. Federal Energy Regulatory ... , 496 F.3d 695 ( 2007 )

North Carolina Utilities Commission v. Federal Energy ... , 42 F.3d 659 ( 1994 )

Missouri Public Service Commission v. Federal Energy ... , 601 F.3d 581 ( 2010 )

battle-creek-gas-company-illinois-power-company-intervenor-v-federal , 281 F.2d 42 ( 1960 )

carnegie-natural-gas-company-v-federal-energy-regulatory-commission-ugi , 968 F.2d 1291 ( 1992 )

View All Authorities »