Brotherhood of Locomotive Engi v. FRA ( 2020 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued December 5, 2019            Decided August 28, 2020
    No. 18-1235
    BROTHERHOOD OF LOCOMOTIVE ENGINEERS AND TRAINMEN,
    A DIVISION OF THE RAIL CONFERENCE OF THE INTERNATIONAL
    BROTHERHOOD OF TEAMSTERS, AND TRANSPORTATION
    DIVISION OF THE INTERNATIONAL A SSOCIATION OF SHEET
    METAL, A IR, RAIL AND TRANSPORTATION WORKERS,
    PETITIONERS
    v.
    FEDERAL RAILROAD ADMINISTRATION AND UNITED STATES
    DEPARTMENT OF TRANSPORTATION,
    RESPONDENTS
    KANSAS CITY SOUTHERN RAILWAY COMPANY AND TEXAS
    MEXICAN RAILWAY COMPANY ,
    INTERVENORS
    On Petition for Review of a Final Decision of
    the Federal Railroad Administration
    Kathy L. Krieger argued the cause for petitioners. With
    her on the briefs were Michael S. Wolly and Lawrence M.
    Mann.
    2
    Jaynie Lilley, Attorney, U.S. Department of Justice,
    argued the cause for respondents. With her on the briefs were
    H. Thomas Byron III, Attorney, Steven G. Bradbury, General
    Counsel, U.S. Department of Transportation, Paul M. Geier,
    Assistant General Counsel for Litigation and Enforcement, Joy
    K. Park, Senior Trial Attorney, and Rebecca S. Behravesh,
    Senior Attorney, Federal Railroad Administration.
    Aaron S. Markel argued the cause for intervenors. With
    him on the brief was Donald J. Munro.
    Before: TATEL , MILLETT, and PILLARD , Circuit Judges.
    Opinion for the Court filed by Circuit Judge MILLETT.
    Opinion concurring in part and dissenting in part filed by
    Circuit Judge TATEL.
    MILLETT, Circuit Judge: By leave of the Federal Railroad
    Administration, two United States railroads began allowing
    engineers and conductors employed by their Mexican affiliate
    to operate trains on their tracks in the United States. Labor
    unions representing employees of the two railroads petition for
    review of the Railroad Administration’s asserted approval of
    the new rail operations.
    We grant the petition in part and vacate and remand in part
    because of the Railroad Administration’s failure to provide a
    reasoned explanation for its approval of the materially altered
    engineer certification program administered by one of the
    railroads. As to that program approval, we agree with the
    Railroad Administration that it took final agency action and
    entered its decision, as required for jurisdiction to attach under
    the Hobbs Act, 
    28 U.S.C. §§ 2342
    (7), 2344. We also agree
    with the labor unions that their challenge to the approval was
    3
    timely, and that the Railroad Administration’s wholly
    unexplained approval of material decisions directly affecting
    railroad safety was arbitrary and capricious. We dismiss the
    petition’s remaining challenges for lack of jurisdiction.
    I
    A
    1
    Title 49 of the United States Code governs
    “Transportation.” Subtitle V of Title 49 deals specifically with
    “Rail Programs[,]” and Part A of Subtitle V is dedicated to
    “Safety[.]” We deal in this case with Chapter 201 of Part A,
    which Congress enacted “to promote safety in every area of
    railroad operations and reduce railroad-related accidents and
    incidents.” 
    49 U.S.C. § 20101
    . To accomplish those goals,
    Congress directed the Secretary of Transportation, “as
    necessary,” to “prescribe regulations and issue orders for every
    area of railroad safety[.]” 
    Id.
     § 20103(a).
    Congress’s effort to increase rail safety included ensuring
    that only those locomotive engineers and train conductors who
    met federal training and safety standards could operate trains
    in the United States. To that end, Chapter 201 obligates the
    Secretary to “prescribe regulations and issue orders to establish
    a program requiring the * * * certification * * * of any
    operator of a locomotive,” 
    49 U.S.C. § 20135
    (a), and “the
    certification of train conductors,” 
    id.
     § 20163(a).
    Rather than charge the agency with certifying engineers
    and conductors itself, Congress placed the onus on each
    “railroad carrier[]” to develop and operate its own certification
    programs for the engineers and conductors it employs. See 49
    
    4 U.S.C. §§ 20135
    , 20163. Congress then mandated that each
    railroad’s certification program comply with minimum
    program requirements established by the Secretary, and that
    each program be individually approved by the Secretary. See
    
    id.
     §§ 20135, 20162–20163.
    Congress defined a covered “railroad carrier” subject to
    those requirements as “a person providing railroad
    transportation, except that, upon petition by a group of
    commonly controlled railroad carriers that the Secretary
    determines is operating within the United States as a single,
    integrated rail system, the Secretary may by order treat the
    group of railroad carriers as a single railroad carrier[.]” 
    49 U.S.C. § 20102
    (3).
    2
    The Secretary has delegated to the Federal Railroad
    Administration the authority to “[c]arry out the functions and
    exercise the authority vested in the Secretary by * * *
    Subtitle V,” 
    49 C.F.R. § 1.89
    , including the authority to
    approve railroads’ engineer and conductor certification
    programs.
    In exercising its delegated authority, the Railroad
    Administration has promulgated regulations requiring “[e]ach
    railroad” to “have in effect a written program for certifying the
    qualifications of” both engineers and conductors. 
    49 C.F.R. § 240.101
     (engineers); 
    id.
     §§ 242.101–242.103 (conductors).
    Those programs must be approved and in effect “prior to
    commencing operations.” Id.
    A railroad’s certification programs must ensure that the
    railroad’s engineers and conductors satisfy baseline
    requirements set by the Railroad Administration in Part 240
    5
    (engineers) and Part 242 (conductors) of Title 49 of the Code
    of Federal Regulations. See 
    49 C.F.R. §§ 240.1
    , 242.1. Those
    regulatory requirements address such matters as the
    “eligibility, training, testing, certification and monitoring” of
    engineers and conductors. 
    Id.
     For example, to be approved by
    the Railroad Administration, a railroad’s engineer certification
    program must evaluate, among other things, an engineer’s:
    (i) prior safety conduct, 
    id.
     § 240.109; (ii) prior compliance
    with operating rules, id. § 240.117; (iii) history of substance
    abuse disorders and alcohol/drug rules compliance, id.
    § 240.119; (iv) visual and hearing acuity, id. § 240.121;
    (v) initial and continuing education, id. § 240.123; (vi) relevant
    knowledge, id. § 240.125; (vii) skill performance, id.
    § 240.127; and (viii) ongoing operational performance, id.
    § 240.129. See id. §§ 240.101(c), 240.203; see also id.
    §§ 242.101(a), 242.109 (requiring similar evaluations for
    conductor certification programs).
    Each railroad must “submit its written certification
    program and a description of how its program conforms to the
    specific [regulatory] requirements” to the Railroad
    Administration “for approval at least sixty days before
    commencing operations.” 
    49 C.F.R. § 240.103
    (a); see 
    id.
    § 242.103(b).
    The Railroad Administration does not issue any formal
    documentation approving a railroad’s written certification
    program. Rather, the Railroad Administration has adopted a
    passive approval system. Under that scheme, if the Railroad
    Administration does not notify the railroad—in writing and
    within thirty days of submission—that the written certification
    program fails to meet the minimum regulatory criteria, then the
    program “is considered approved and may be implemented” by
    the railroad. 
    49 C.F.R. §§ 240.103
    (c), 242.103(g). The
    6
    Railroad Administration’s regulations are explicit that “[n]o
    formal approval document [regarding certification program
    submissions] will be issued by the [Administration].” 
    Id.
     § 240
    App. B (engineer programs); id. § 242 App. B (conductor
    programs).
    Any material modifications to a previously approved
    certification program must also be submitted for the Railroad
    Administration’s approval either thirty days (engineer
    programs) or sixty days (conductor programs) before
    implementation. See 
    49 C.F.R. §§ 240.103
    (e), 242.103(i).
    Those modifications are likewise approved passively by the
    Railroad Administration if not explicitly rejected within thirty
    days after submission. See 
    id.
     §§ 240.103(e)(3), 242.103(i)(3).
    When a railroad submits an original or modified conductor
    certification program to the Railroad Administration, it must
    simultaneously serve a copy of its submission on the president
    of every labor organization that represents the railroad’s
    employees who are subject to Part 242.              
    49 C.F.R. § 242.103
    (c)(1). There is no similar requirement for Part 240
    engineer certification program submissions. Cf. 
    84 Fed. Reg. 20,472
    , 20,478 (May 9, 2019) (Notice of Proposed Rulemaking
    announcing an intention to make the duty to serve equivalent
    for engineer certification programs). Once the conductor
    submission is shared with the labor organization, however,
    there is no continuing duty on the railroad to notify the labor
    organizations when (and if) the Railroad Administration either
    approves or disapproves the conductor certification program.
    Nor does anything in the Railroad Administration’s regulations
    provide for the agency to “publish or give notice of [a]
    certification [program] approval.” Oral Arg. Tr. 20:23–21:1
    (counsel for Railroad Administration).
    7
    To enforce compliance with the certification requirements,
    Railroad Administration regulations prohibit any person from
    operating a locomotive as an engineer or serving as a conductor
    unless that person has been certified by a railroad under a
    written program approved by the Administration. See 
    49 C.F.R. §§ 240.201
    (d), 242.105(f). Any certificate must,
    among other things, “[i]dentify the railroad or parent company
    that is issuing it[,]” and “[i]dentify the person to whom it is
    being issued[.]” 
    Id.
     §§ 240.223(a), 242.207(a). Any person
    who violates Part 240 or Part 242 is subject to civil penalties
    and potential disqualification from future railroad service. See
    id. §§ 240.11, 242.11.
    Any person may petition the Railroad Administration for
    a formal waiver of compliance with the engineer certification
    requirements of Part 240 or the conductor certification
    requirements of Part 242. See 
    49 C.F.R. §§ 211.7
    , 211.9,
    240.9, 242.9; see also 
    49 U.S.C. § 20103
    (d)–(e). Such a
    waiver may be issued, subject to any conditions the Railroad
    Administration deems necessary, only upon a finding that a
    waiver is “in the public interest” and “consistent with railroad
    safety.” 
    49 U.S.C. § 20103
    (d); 
    49 C.F.R. §§ 240.9
    (c),
    242.9(c). Generally, before granting a petition for a waiver,
    the Railroad Administration must conduct a hearing that
    affords interested parties an opportunity to submit comments
    and to make an “oral presentation” of their views. 
    49 U.S.C. § 20103
    (e). If the Railroad Administration grants the waiver,
    it “shall make public the reasons for” doing so. 
    Id.
     § 20103(d);
    see also 
    49 C.F.R. §§ 240.9
    , 242.9, 211.41.
    3
    In certain circumstances, Railroad Administration
    regulations permit a railroad’s certification program to certify
    engineers or conductors who have not completed the railroad’s
    8
    entire training regimen for new hires. As relevant here, 
    49 C.F.R. § 240.225
     governs railroads’ “[r]eliance on
    qualification determinations made by other railroads” of
    engineers, and 
    49 C.F.R. § 242.125
     governs “[c]ertification
    determinations made by other railroads” of conductors.
    Together, they provide in relevant part:
    A railroad that is considering certification of a person
    as a qualified engineer [or conductor] may rely on
    determinations made by another railroad concerning
    that person’s qualifications.          The railroad’s
    certification program shall address how the railroad
    will administer the training of previously uncertified
    engineers [or conductors] with extensive operating
    experience or previously certified engineers [or
    conductors] who have had their certification expire.
    If a railroad’s certification program fails to specify
    how to train a previously certified engineer [or
    conductor] hired from another railroad, then the
    railroad shall require the newly hired engineer [or
    conductor] to take the hiring railroad’s entire training
    program.
    
    49 C.F.R. § 240.225
    (a); see 
    id.
     § 242.125(a).
    For a railroad to rely on another railroad’s engineer
    certification, it must first determine that (i) the prior
    certification is still valid; (ii) the prior certification was for the
    same classification of service as the certification being issued;
    (iii) the person has received training on and visually observed
    the physical characteristics of the new territory; (iv) the person
    has demonstrated the necessary knowledge concerning the new
    railroad’s operating rules; and (v) the person has demonstrated
    the necessary performance skills concerning the new railroad’s
    operating rules. See 
    49 C.F.R. § 240.225
    (a); see also 
    id.
    9
    § 242.125(b) (imposing similar requirements for relying on
    another railroad’s conductor certifications).
    Other Railroad Administration regulations specifically
    provide that if a United States railroad “conducts joint
    operations with a Canadian railroad,” the United States railroad
    may certify employees of the Canadian railroad based on those
    employees’ satisfaction of Canadian regulatory requirements.
    See 
    49 C.F.R. §§ 240.227
    , 242.127; see also 
    id.
     § 240.229
    (permitting similar reliance for railroads conducting joint
    operations with other railroads); id. § 242.301 (similar).
    There is no similar reciprocity provision for joint
    operations with Mexican railroads.
    Finally, in addition to requiring railroads to train and
    certify the engineers and conductors whom they employ, the
    Railroad Administration’s regulations also require railroads
    and their employees, among other things, to comply with
    standards for (i) the control of alcohol and drug use by
    employees,      see    49    C.F.R.     pt. 219;    (ii) railroad
    communications, see id. pt. 220; (iii) hours of service, see id.
    pt. 228; and (iv) brake maintenance and testing, see id. pt. 232.
    The Railroad Administration may issue waivers of
    compliance for any part of those regulations as well, subject to
    the same procedures for waivers of certification requirements.
    See, e.g., 
    49 U.S.C. § 20103
    (d)–(e).
    B
    Kansas City Southern (“Southern Company”) is a holding
    company that owns several railroads operating trains within
    North America. Collectively, those railroads operate rail lines
    that run from Mexico City, Mexico, across the United States–
    10
    Mexico border at Laredo, Texas, and throughout the United
    States.
    Laredo sits on the northern bank of the Rio Grande River,
    which is part of the natural border between the United States
    and Mexico. Trains crossing the border at Laredo enter or exit
    the United States by way of the International Bridge, which
    runs north–south over the Rio Grande.
    Three of Southern Company’s railroads—two that operate
    in the United States and one that has historically operated only
    in Mexico—are relevant to this case.
    The two railroads that operate in the United States are
    Kansas City Southern Railway Company (“Kansas City
    Railway”) and its wholly owned subsidiary Texas-Mexican
    Railway Company (collectively, “the Railroads”). The
    Railroads own tracks and operate trains on the United States
    side of the border at Laredo and into the interior of the United
    States.
    Kansas City Southern de México (“de México Railway”)
    is the Railroads’ Mexican affiliate. It operates the rail line that
    runs from Mexico City to Laredo, which provides exclusive
    rail access to the United States border crossing at Laredo from
    the Mexican side of the border. The Railroads do not own or
    control de México Railway; they are simply affiliated with it.
    Historically, de México Railway crews operated trains
    only in Mexico, and not in the United States. De México
    Railway’s operations in Mexico and up to the border did not
    require it to certify its engineers or conductors under a program
    approved by the Railroad Administration.
    11
    As a result of Mexico’s and the United States’ differing
    certification regimes, Southern Company trains that crossed
    the border at Laredo have long “interchanged” in the middle of
    the International Bridge. That is, rail cars were transferred
    from one railroad to another, and a new rail crew took over.
    Specifically, southbound trains operated by the Railroads
    heading into Mexico stopped in the middle of the International
    Bridge so that de México Railway crews could recouple the rail
    cars and take them into Mexico. Northbound trains operated
    by de México Railway heading into the United States similarly
    stopped in the middle of the bridge so that the Railroads’ crews
    could recouple the rail cars and take them into the United
    States. Those Railroads’ crews would operate the northbound
    trains to Kansas City Railway’s Laredo Train Yard, which is
    roughly 9.2 miles from the International Bridge. At the Train
    Yard, new crewmembers working for the Railroads would take
    the rail cars on their journeys elsewhere in the United States,
    while the disembarking crew would be shuttled back to the
    International Bridge to take over another northbound train.
    The dedicated crews that operated the Railroads’ trains
    back and forth on the 9.2-mile stretch of track between the
    border and the Laredo Train Yard were busy. They commonly
    operated hundreds of northbound and southbound trips every
    month along that route.
    Those crewmembers are represented by two labor
    organizations: (i) the Brotherhood of Locomotive Engineers
    and Trainmen, a division of the Rail Conference of the
    International Brotherhood of Teamsters, and (ii) the
    Transportation Division of the International Association of
    Sheet Metal, Air, Rail and Transportation Workers
    (collectively, “the Unions”).
    12
    C
    According to the Railroad Administration and a report by
    the Government Accountability Office, this longstanding
    practice of interchanging in the middle of the International
    Bridge caused problems on the storied streets of Laredo, see,
    e.g., JOHNNY CASH, Streets of Laredo, on AMERICAN IV: THE
    MAN COMES A ROUND (American Recordings & Universal
    Records 2002).
    Specifically, stopping each train in the middle of the
    International Bridge to swap crews caused significant backups
    on highway–rail crossings in Laredo. Because the trains can
    be several miles long, a single one stopped on the bridge could
    stretch all the way to nearby Interstate 35, a major highway that
    runs through Laredo and intersects with the rail line. Trains
    were sometimes forced to sit on the bridge for long periods of
    time, waiting for a new crew to arrive and take over. For
    example, the Railroads’ crews that delivered northbound trains
    from the border to the Laredo Train Yard were then driven back
    to the border to pick up the next northbound train, and they
    were sometimes delayed at the Train Yard or on the way back
    to the border by (ironically enough) bridge-induced traffic
    congestion. All things considered, crew changes on the bridge
    could sometimes take two to three hours.
    On top of those crew change delays, when trains entered
    the United States from Mexico, the Railroads’ crews that
    assumed control were generally required to perform what is
    known as a “Class I brake test.” See 
    49 C.F.R. § 232.205
    (a)(1).
    Trains crossing the border are also subject to inspection by
    United States Customs and Border Protection and Mexico’s
    customs agencies. Those brake tests and customs inspections
    added to Laredo’s traffic gridlock.
    13
    D
    Over the years, the Railroad Administration and the
    Railroads have tried to streamline the journey of trains over the
    International Bridge to reduce delays and traffic congestion.
    First, in 2008, Kansas City Railway obtained from the
    Railroad Administration a formal waiver excusing the
    Railroads from having to perform a Class I brake test on the
    International Bridge. Instead, only a less time-consuming
    Class III brake test had to “be performed before departing the
    interchange point[.]”      J.A. 141.     Compare 
    49 C.F.R. § 232.211
    (b) (defining Class III brake tests), with 
    id.
    § 232.205(c) (defining more rigorous Class I brake tests). The
    waiver required Class I brake tests to eventually be performed
    before the northbound trains departed the Laredo Train Yard.
    Kansas City Railway’s brake-test waiver was effective for
    a five-year period. But the Railroad Administration has twice
    extended the waiver, and it is still in effect today. See 
    83 Fed. Reg. 35,052
     (July 24, 2018).
    Second, the Railroads proposed a plan by which they
    would grant de México Railway operating rights over the 9.2
    miles of track between the International Bridge and the Laredo
    Train Yard. As part of that plan, Kansas City Railway would
    certify de México Railway engineers and conductors through
    an abbreviated training program, given the de México
    employees’ experience working in Mexico.                  Those
    certifications would allow de México engineers and conductors
    to operate north- and southbound trains inside the United States
    on that stretch of track. That meant the Railroads’ crews would
    operate northbound trains only after they arrived at the Laredo
    Train Yard, and southbound trains no further than that point.
    14
    As for brake testing (which is required only of the
    northbound trains entering the United States), the plan
    provided that de México Railway crews would avail
    themselves of Kansas City Railway’s existing waiver to skip
    the Class I brake test on the International Bridge. Kansas City
    Railway also petitioned the Railroad Administration for an
    additional brake-test waiver excusing performance of any
    brake test at all at the border. See 83 Fed. Reg. at 35,052–
    35,053.
    On October 26, 2016, Kansas City Railway described its
    proposed crew change plan to a Railroad Administration
    official over email and asked for a meeting to discuss it. At the
    official’s request, Kansas City Railway forwarded its draft
    plan, explaining that it was “not inclusive of everything that
    will need to take place, but [was] intended to start a dialogue.”
    J.A. 44.
    That draft plan—entitled “International Crew Pilot
    Program Draft Implementation Plan”—is dated October 27,
    2016. J.A. 47. Its stated purpose is to identify “the steps for
    Certification, Qualification, and Operation for [Kansas City
    Railway’s] vision of the International Crew Pilot Program”
    intended “to operate between border yards in Mexico and the
    United States without the need to stop on the International
    Bridge for any reason.” J.A. 47. The draft plan describes de
    México Railway crew members as “experienced train
    operators that are certified to operating standards in Mexico,”
    which, the draft asserted without elaboration or citation, “are
    similar to those required by” the Railroad Administration.
    J.A. 47. The Draft Plan added that de México Railway “crew
    members will be certified, to operate trains in the [United
    States], under [Kansas City Railway’s] approved 49 C.F.R.
    [Parts] 240 and 242 submission.” J.A. 47.
    15
    Appendix A to the Draft Plan, entitled “FRA Compliance
    Document,” lists various parts of the Railroad Administration’s
    regulations and “how [Kansas City Railway] will comply with
    information/audit requests from the” Railroad Administration.
    J.A. 50. In that regard, the Draft Plan points to, among other
    things, the regulations governing alcohol and drug use, railroad
    communications, hours of service limitations, and brake
    maintenance and testing.
    Communications between the Railroads and the Railroad
    Administration about the proposed plan continued into 2017.
    In June of that year, the Railroad Administration issued a
    public report stating that the Railroads had “spent the past three
    years attempting to” certify a group of de México Railway
    crew members to operate trains in the United States “in a
    manner that is acceptable from a regulatory standpoint, in
    which [the Railroad Administration] would approve Mexican
    train crew certifications without the need for a waiver” of
    safety regulations. A.R. 1774.
    That same month, a staff member for Congressman Henry
    Cuellar, whose congressional district includes Laredo, emailed
    a Railroad Administration official about the proposed crew
    change procedures. The staff member inquired whether the
    Railroad Administration had or would be approving the new
    procedures and when they would take effect.
    The Railroad Administration official forwarded the email
    internally.     Another Railroad Administration official
    confirmed to his colleague that, in July 2018, de México
    Railway crews would indeed begin operating trains in the
    United States on the 9.2-mile stretch of track between the
    International Bridge and the Laredo Train Yard. J.A. 558–559.
    16
    The Railroad Administration official’s internal email
    further noted that, under the new procedure, southbound trains
    would no longer have any reason to stop on the bridge (though
    they would “still proceed at 5 mph across the bridge to be
    x-rayed by [Customs and Border Patrol]”). J.A. 558. Finally,
    the official added that Kansas City Railway “currently operates
    under a waiver that requires them to stop at the bridge on
    northbound movements to conduct a [Class III] brake test,” and
    that will “still be the case” under the new procedure. J.A. 559.
    That is, “[a]ll northbound trains [operated by de México
    Railway crews] will still be required to stop and conduct a
    [Class III] brake test” on the International Bridge. J.A. 559. 1
    Finally, the official stated that the Railroad Administration had
    “done extensive inspections and review of the plan,” and that
    “Mexican crews will be in compliance with all [Railroad
    Administration] regulations.” J.A. 559.
    On August 16, 2017, the Railroad Administration
    completed a self-described “audit” to determine whether
    Kansas City Railway could certify de México Railway
    engineers and conductors using an abbreviated curriculum
    within its certification programs. See J.A. 390–391.
    In that audit, the Railroad Administration concluded that
    “no changes [were] necessary” to Kansas City Railway’s five-
    year-old conductor certification program to allow it to certify
    de México Railway conductors. J.A. 390. The audit noted that
    1
    The Railroad Administration subsequently denied Kansas City
    Railway’s petition for a waiver of the obligation to perform a
    Class III brake test on the International Bridge. See 83 Fed. Reg. at
    35,052–35,053 (petition for waiver); Letter, Docket No. 2007-28700
    (Fed. R.R. Admin. March 8, 2019) (rejecting waiver petition).
    17
    Kansas City Railway’s existing conductor certification
    program already included language tracking 
    49 C.F.R. § 242.125
    , which, the audit reasoned, allowed it “to train
    previously uncertified conductors with extensive operating
    experience.” J.A. 390; see also J.A. 237–238 (Section 4 of
    Kansas City Railway’s 2012 Part 242 program, entitled
    “Training, Testing and Evaluating Persons Not Previously
    Certified”).
    For Kansas City Railway’s existing engineer certification
    program, however, the Railroad Administration determined
    that the railroad could not certify de México engineers under
    an abbreviated curriculum because some “added language to
    the engineer program” was necessary and “would need to be
    vetted * * * and approved by” Administration officials.
    J.A. 391. Namely, the audit called for language “explicitly
    address[ing] how [de México] engineers working into the
    [United States] would be trained and certified.” J.A. 391. The
    Railroad Administration noted that Kansas City Railway had
    already developed language in consultation with an
    Administration official “to amend [its] program that would
    recognize the experience” of de México engineers and “allow
    [them] to be trained under an amended training program.”
    J.A. 390. The intent of the added language was “to take
    advantage of the previously trained/experienced [de México]
    engineers and avoid having to start retraining from ground
    zero.”     J.A. 390.      The audit added that a Railroad
    Administration attorney “would need time to determine if [the
    Administration] could recognize [de México Railway]
    engineers[’] experience as being compatible with what we
    accept from other railroads in the United States.” J.A. 391
    (emphasis added). But see J.A. 391 (audit team noting that it
    “feels” full training “would be a disproportionate amount of
    training for [the] train movements into the United States”). The
    18
    audit team said nothing about the prospect of a railroad
    certifying engineers that it did not employ and who worked for
    a foreign affiliate that the domestic railroad did not claim to
    control. See J.A. 391.
    Consistent with the results of that internal audit, which
    were not publicly released, Kansas City Railway did not revise
    its previously approved conductor certification program. But
    it did, on January 19, 2018, email to the Railroad
    Administration a revised engineer certification program.
    The revised engineer certification program states that
    Kansas City Railway “will issue all required certificates for
    employees of its affiliate or subsidiary companies,” including
    de México Railway. J.A. 520. The revised program also
    provides that “[e]ngineer candidates that work for a [Kansas
    City Railway] affiliate * * * in the capacity of Locomotive
    Engineer and have previous training on the railroad’s operating
    and safety rules may receive an accelerated training curriculum
    based on their proficiency by a qualified engineer instructor.”
    J.A. 519; see also J.A. 515 (section entitled “Initial
    Certification of Foreign Locomotive Engineers”); J.A. 519
    (noting that “[a]ll international engineers will be kept on a
    separate roster from all [Kansas City Railway] locomotive
    engineers”).2
    2
    The audit notwithstanding, several subsequent Railroad
    Administration communications contemplated that Kansas City
    Railway was actually required to revise both its “240 [engineer] &
    242 [conductor] submissions” to add a “new section” outlining
    “exactly how [it] plan[s] to train [its] new [de México Railway]
    engineers and conductors with previous experience.” J.A. 394; see
    19
    Thirty days came and went, and Kansas City Railway
    received no communication from the Railroad Administration
    rejecting its revised Part 240 engineer certification proposal.
    As a result, the revised engineer certification program was
    passively approved by the Railroad Administration on
    February 19, 2018, and the Administration authorized Kansas
    City Railway to implement it. See 
    49 C.F.R. § 240.103
    (c). For
    good measure, the Railroad Administration sent an email four
    months later confirming to Kansas City Railway that its
    engineer certification submission had previously been
    approved.
    A number of de México Railway crewmembers completed
    their training, medical examinations, background checks, drug
    and alcohol certifications, and field testing, and were certified
    under Kansas City Railway’s modified engineer and existing
    conductor certification programs to operate trains in the United
    States.
    E
    The Unions have consistently opposed Kansas City
    Railway’s efforts to certify de México Railway’s crews to
    operate trains on the 9.2-mile stretch of track between the
    International Bridge and the Laredo Train Yard. In May 2018,
    Kansas City Railway informed the Unions that it would
    implement its new crew change procedure using de México
    Railway crews on July 9, 2018.
    also J.A. 533. But there is no evidence that Kansas City Railway
    ever submitted a revised Part 242 program for certifying conductors.
    Nor does the record indicate that the Railroad Administration ever
    considered or approved a revised conductor certification program.
    20
    The Unions threatened to strike on that date, arguing both
    that the governing collective bargaining agreements did not
    permit the Railroads to move the interchange point unilaterally
    and that the use of de México Railway crews in the United
    States would violate Railroad Administration regulations.
    Shortly thereafter, the Railroads filed suit in the United
    States District Court for the Southern District of Texas to
    enjoin the impending strike. See Kansas City S. Ry. Co. v.
    Brotherhood of Locomotive Eng’rs & Trainmen, No. 5:18-cv-
    00071, 
    2018 WL 7253969
    , at *1 (S.D. Tex. July 6, 2018). The
    Railroads argued that the Railway Labor Act, 
    45 U.S.C. § 151
    et seq., mandated arbitration of the grievance and prohibited
    striking. See 
    id.
    At an evidentiary hearing in the Southern District of Texas
    litigation on July 3, 2018, Kansas City Railway’s Vice
    President     testified   publicly     about    the     Railroad
    Administration’s non-public August 2017 audit and
    subsequent approval of the railroad’s modified Part 240
    engineer certification program. Specifically, he disclosed that
    Kansas City Railway had “developed a written plan” to certify
    de México Railway engineers and conductors, and “that the
    [Railroad Administration] audited[,] reviewed and accepted”
    those plans and concluded that they authorized Kansas City
    Railway “to certify [de México Railway] engineers and
    conductors to operate in the United States.” Transcript of
    Motion Hearing at 68–69, Kansas City, 
    2018 WL 7253969
    (No. 5:18-cv-00071), ECF No. 24.
    On July 6, 2018, a few days before the new crew change
    procedure was set to begin, the district court granted the
    Railroads’ motion for a preliminary injunction and enjoined the
    Unions from striking. See Kansas City, 
    2018 WL 7253969
    , at
    21
    *1, *4, *7. At the parties’ joint request, the district court made
    the injunction permanent.
    On July 9, 2018, the new crew change procedures were
    implemented, with de México Railway crews certified by
    Kansas City Railway operating trains for the first time on the
    9.2-mile stretch of track between the International Bridge and
    the Laredo Train Yard. The Railroad Administration publicly
    participated in the rollout. See A.R. 2150 (Kansas City
    Railway document noting that Railroad Administration staff
    have “been in Laredo and activ[ely] participated in the program
    since launch”); 
    id.
     (also noting that Railroad Administration
    “observers have ridden trains with” the de México Railway
    crewmembers and inspected trains at the Laredo Train Yard,
    where the Unions’ members take over/disembark the affected
    trains).
    F
    On September 4, 2018, the Unions filed a petition for
    review with this court under the Hobbs Act, 
    28 U.S.C. § 2342
    ,
    challenging what they labeled the Railroad Administration’s
    decision to “authorize[] and permit[]” de México Railway “to
    operate freight trains * * * in Laredo” for Kansas City Railway
    in violation of applicable rail safety laws and regulations.
    Petition for Review at 1–3, No. 18-1235 (D.C. Cir. Sept. 4,
    2018). Their petition targets “certain administrative orders
    and/or actions issued and/or taken” by the Railroad
    Administration “as arbitrary and capricious, an abuse of
    discretion, in excess of the [agency’s] statutory authority and
    otherwise contrary to law.” 
    Id.
     at 1–2.
    More specifically, the petition explains that it challenges,
    among other things, (i) the Railroad Administration’s
    “authorization” of “the training, testing and certification of [de
    22
    México Railway’s] non-U.S. locomotive engineers and
    conductors,” and (ii) “the implementation of [de México
    Railway’s] operations taking place in Laredo, Texas on or after
    July 9, 2018, including participation, monitoring and/or
    observation by [Railroad Administration] personnel.” Petition
    at 3.
    As to the Railroad Administration’s approval of Kansas
    City Railway’s modified engineer program—which allowed
    the railroad to certify de México Railway engineers under an
    abbreviated training curriculum—the Unions argue that the
    approval must be set aside for two reasons.
    First, the Unions contend that, under the relevant statutes
    and regulations, it was unlawful to approve a certification
    program permitting one railroad to certify employees of a
    foreign affiliate railroad that it does not control. In the Unions’
    view, de México Railway must operate its own approved
    engineer certification program for its crews to operate in the
    United States. See Unions Br. 5–7, 13, 35–39; Unions Reply
    Br. 20–22.
    Second, the Unions dispute whether a certification
    program may deploy an abbreviated curriculum and training
    protocol to engineers with operating experience only in
    Mexico, where they are governed by a different regulatory
    regime, and lacking any prior certification in the United States.
    See Unions Br. 39; Unions Reply Br. 23.
    The Unions did not attach the challenged Railroad
    Administration decisions or orders to their petition. Instead,
    they explained that the relevant agency “actions have been
    taken * * * without public notice or other published
    documentation,” leaving the Unions “unable to cite or attach a
    copy of a formal [Administration] order, waiver, or other
    23
    Agency decision.” Petition at 3. The Unions then assert, on
    information and belief, that the Railroad Administration
    “maintains internal records reflecting and/or relating to the
    Agency’s authorization [of] and permission” for the challenged
    actions. 
    Id.
    The Railroads intervened in support of the Railroad
    Administration. Both the Railroad Administration and the
    Railroads moved to dismiss the Unions’ petition for lack of
    jurisdiction, contending that it failed to identify and timely
    challenge any final agency action of the Railroad
    Administration subject to judicial review.
    That motion to dismiss and the merits of the Unions’
    petition are now before us.
    II
    We determine de novo whether we have jurisdiction under
    the Hobbs Act, 
    28 U.S.C. § 2342
    . See Blue Ridge Envtl.
    Defense League v. Nuclear Regulatory Comm’n, 
    668 F.3d 747
    ,
    753 (D.C. Cir. 2012).
    Congress subjected “final action of the Secretary of
    Transportation” under the statutory provisions at issue here to
    judicial review exclusively under the Hobbs Act. See 
    49 U.S.C. § 20114
    (c); see also 
    28 U.S.C. § 2342
    (7) (jurisdiction
    over “final agency actions” under 
    49 U.S.C. § 20114
    (c)).
    Included in that jurisdictional grant are final actions taken by
    the Railroad Administration under Chapter 201 of Title 49.
    See Daniels v. Union Pac. R.R. Co., 
    530 F.3d 936
    , 940–941
    (D.C. Cir. 2008); see also 
    49 C.F.R. § 1.89
     (Secretary of
    Transportation’s delegation of authority under Chapter 201 to
    the Railroad Administration).
    24
    The Hobbs Act, in turn, invests federal courts of appeals
    (other than the Federal Circuit) with “exclusive jurisdiction to
    enjoin, set aside, suspend (in whole or in part), or to determine
    the validity of” such final agency actions. 
    28 U.S.C. § 2342
    (7).
    To invoke a court of appeals’ jurisdiction under the Hobbs Act,
    a “party aggrieved” by the agency’s action must file a petition
    for review within sixty days of “entry” of the relevant agency
    decision. 
    28 U.S.C. § 2344
    ; see 
    id.
     § 2342. The Hobbs Act
    separately commands a covered agency, upon entering a final
    and reviewable order, to “promptly give notice thereof by
    service or publication in accordance with its rules.” Id. § 2344.
    The Hobbs Act’s requirements that the agency action be
    final and that the petition timely filed are jurisdictional. See
    Blue Ridge, 
    668 F.3d at 753
     (finality requirement); see also
    Western Union Tel. Co. v. FCC, 
    773 F.2d 375
    , 376 (D.C. Cir.
    1985) (timeliness requirement).
    Applying those terms, we have jurisdiction to review the
    Unions’ challenge to the Railroad Administration’s final action
    approving Kansas City Railway’s revised engineer
    certification program, allowing that railroad to certify for the
    first time de México Railway engineers under an abbreviated
    training curriculum. As the Railroad Administration agrees, its
    approval of that program constituted a final and reviewable
    order under the Hobbs Act. And the Unions have timely
    challenged it. But we lack jurisdiction over the Unions’ other
    claims.
    A
    We begin with the question of our jurisdiction over the
    Unions’ challenge to the approval of Kansas City Railway’s
    modified engineer certification program.
    25
    1
    As to the question of finality, the Railroad
    Administration’s approval of Kansas City Railway’s revised
    engineer certification program is a final agency action
    reviewable under the Hobbs Act, 
    28 U.S.C. §§ 2342
    (7), 2344.
    Agency actions qualify as final if they “mark the
    consummation of the agency’s decisionmaking process” and
    “legal consequences” flow from them. Bennett v. Spear, 
    520 U.S. 154
    , 178 (1997) (internal quotation marks omitted); see
    also Blue Ridge, 
    668 F.3d at 753
     (“An order is final” for
    purposes of the Hobbs Act “if it imposes an obligation, denies
    a right, or fixes some legal relationship, usually at the
    consummation of an administrative process.”) (formatting
    modified). The Railroad Administration’s passive approval of
    Kansas City Railway’s revised Part 240 engineer certification
    program fits that bill.
    First, the Railroad Administration’s judgment allowing
    the revised program to go into operation assuredly had fixed
    legal consequences. By regulation, the revised certification
    program could not be implemented without the Railroad
    Administration’s approval. See 
    49 C.F.R. § 240.103
    (a), (c),
    (e); see also 
    49 U.S.C. § 20135
    . As such, the approval made it
    lawful for Kansas City Railway to, for the first time, certify de
    México Railway engineers through an abbreviated training
    curriculum, and it permitted the engineers who received those
    certificates to operate trains within the United States. So it was
    an action “from which legal consequences [flowed]” and legal
    rights changed. Bennett, 
    520 U.S. at 178
     (internal quotation
    marks omitted).
    Of course, the Railroad Administration’s approval took
    the form of inaction—its declination to intervene—rather than
    26
    the affirmative issuance of an order. But that decision not to
    act, by virtue of the Railroad Administration’s regulatorily
    prescribed passive-approval scheme, naturally had the same
    legal effect regarding the rights and obligations at issue as if
    the Administration had formally stamped “Approved” on
    Kansas City Railway’s submission. See Oral Arg. Tr. 17:18–
    21 (Q: “And if you don’t do anything, then on, shall we say
    the 31st day, [it is as] if [the agency] stamped approved on
    there[?]” Railroad Administration: “Yes[.]”). The particular
    form that the agency’s final approval took did not change the
    “direct and appreciable legal consequences” that flowed from
    it. California Cmtys. Against Toxics v. EPA, 
    934 F.3d 627
    , 640
    (D.C. Cir. 2019).
    Nor is the idea that a document can take full and final legal
    effect if not rejected within a predetermined period of time a
    concept unknown to law. See, e.g., U.S. CONST. Art. I, § 7,
    cl. 2 (“If any Bill [passed by the House of Representatives and
    the Senate] shall not be returned by the President within ten
    Days (Sundays excepted) after it shall have been presented to
    him, the Same shall be a Law, in like Manner as if he had
    signed it[.]”).
    Second, the Railroad Administration’s decision to allow
    the certification program to go into operation marked the
    consummation of the agency’s decisionmaking process. The
    Administration has said so by regulation. See 
    49 C.F.R. § 240.103
    (c) (“A railroad’s program is considered approved
    and may be implemented thirty days after the required filing
    date (or the actual filing date) unless the Administrator notifies
    the railroad in writing that the program does not conform to the
    criteria” of Part 240.) (emphasis added). Lest there be any
    doubt, the Railroad Administration is explicit that it will not
    issue a “formal approval document[.]” 
    Id.
     § 240 App. B. By
    27
    regulation, the completion of the thirty-day period without
    objection itself marks the program’s formal and final approval.
    And that approval legally authorizes the railroad to implement
    its program, id. § 240.103(c), in full compliance with the
    regulatory obligation to have a certification “program in effect
    prior to commencing operations” that has been “approved in
    accordance with § 240.103,” id. § 240.101(b)–(c). Put simply,
    once the passive approval took effect, there was nothing more
    for the agency to review or resolve. Its decisionmaking process
    was at an end. See California Cmtys., 934 F.3d at 636 (What
    “can only reasonably be described as [an agency’s] last word”
    on a question “marks the consummation of [its]
    decisionmaking process.”) (formatting modified).
    And while we must independently evaluate our
    jurisdiction, see Blue Ridge, 
    668 F.3d at 753
    , it bears noting
    that the Railroad Administration agrees that its regulatorily
    prescribed tacit approval of Kansas City Railway’s modified
    Part 240 engineer certification program was final agency action
    reviewable under the Hobbs Act. See Railroad Admin. Supp.
    Br. 3 (“The Agency’s approval of the modified engineer
    certification program is a reviewable final agency action[.]”);
    Oral Arg. Tr. 32:22–33:15.
    Third, though the practice leaves much to be desired, we
    also agree with the Railroad Administration that the absence of
    a written memorialization by the agency does not defeat
    finality. Congress empowered this court to review “final
    agency actions” of the Railroad Administration. See 
    28 U.S.C. § 2342
    (7); 
    49 U.S.C. § 20114
    (c); see also Daniels, 
    530 F.3d at
    940–941; see also 
    id.
     at 944 n.13 (holding that final agency
    action under 
    28 U.S.C. § 2342
    (7) “includes the [Railroad
    Administration’s] administration of the locomotive engineer
    certification program”) (citations omitted). Agency action
    28
    generally need not be committed to writing to be final and
    judicially reviewable. See Venetian Casino Resort, LLC v.
    EEOC, 
    530 F.3d 925
    , 930–931 (D.C. Cir. 2008) (reviewing as
    final agency action under the Administrative Procedure Act an
    unwritten policy that, “[o]n this record[,] it is clear the
    Commission” adopted); see also Blue Ridge, 
    668 F.3d at 753
    (looking to cases “address[ing] the requirement of finality
    under the Administrative Procedure Act, 
    5 U.S.C. § 704
    ,”
    when analyzing finality under the Hobbs Act); Atchison,
    Topeka & Santa Fe Ry. Co. v. Peña, 
    44 F.3d 437
    , 441 (7th Cir.
    1994) (en banc) (“Because it appears that ‘final agency action’”
    in 
    28 U.S.C. § 2342
    (7) “carries the same meaning as it does in
    the Administrative Procedure[] Act, 
    5 U.S.C. § 704
    , we will
    apply the same standards applicable to the APA.”) (citation
    omitted), aff’d sub nom. Brotherhood of Locomotive Eng’rs v.
    Atchison, Topeka & Santa Fe R.R. Co., 
    516 U.S. 152
     (1996).
    In any event, under this scheme, there is a relevant written
    document: Namely, the railroad’s written submission that
    itself, upon the passage of thirty days, becomes the agency’s
    approved program. 
    49 C.F.R. § 240.103
    (c).
    2
    Section 2344 of Title 28 also requires that the agency
    make an “entry of a final order[.]” 
    28 U.S.C. § 2344
    . The
    Railroad Administration admits that, under its passive approval
    process, the agency “entered” its decision formally approving
    Kansas City Railway’s modified engineer certification
    program on the day that marked the passage of the thirty-day
    review period. See Oral Arg. Tr. 32:22–33:7. We agree.
    To start with, we look to the agency’s governing statutes
    and regulations to determine when a final decision has been
    entered.    See Western Union, 
    773 F.2d at
    376–378
    29
    (determining when an FCC order is “deemed to be ‘entered’
    for purposes of § 2344” by turning to the FCC’s governing
    statutes and regulations). For the Railroad Administration, that
    point of entry is when its regulations mark the certification
    program as “approved” and—most critically—allow it to take
    legal effect and to be “implemented” by the submitting
    railroad. 
    49 C.F.R. § 240.103
    (c). Under the Railroad
    Administration’s distinctive passive approval scheme, in
    which no formal approval document is issued or filed, that
    conclusive authorization and formal vesting of legal rights in
    the railroad satisfies the Hobbs Act’s “entry” requirement.
    To be sure, most agencies subject to the Hobbs Act have
    adopted more formalized measures of “entry” that must occur
    before jurisdiction attaches. See Western Union, 
    773 F.2d at
    377–378 (petition for review filed before entry of final FCC
    order was premature and did not establish jurisdiction because
    the FCC statute and implementing regulation explicitly tied
    “entry” to “publication in the Federal Register”) (some
    capitalization omitted) (citing 
    47 U.S.C. § 405
     (1982); 
    47 C.F.R. § 1.4
    (b) (1984)); see also Dissent Op. at 5–6 (noting
    that “most agencies * * * sensibly comply with their Hobbs
    Act obligations”) (citing examples). That is perhaps a
    byproduct of the fact that the Hobbs Act explicitly limits
    courts’ jurisdiction over all other agencies to their “final
    orders,” rules, or regulations. See 
    28 U.S.C. § 2342
    (1)
    (emphasis added) (vesting jurisdiction over specified “final
    orders of the [FCC]”); 
    id.
     § 2342(2) (“final orders of the
    Secretary of Agriculture”); id. § 2342(3) (“all [specified] rules,
    regulations, or final orders of” the Secretary of Transportation
    and the Federal Maritime Commission); id. § 2342(4)
    (specified “final orders of the Atomic Energy Commission”);
    id. § 2342(5) (“all [specified] rules, regulations, or final orders
    of the Surface Transportation Board”); id. § 2342(6) (all
    30
    specified “final orders under section 812 of the Fair Housing
    Act”).
    But the Hobbs Act speaks differently about review of
    Department of Transportation decisions involving railroad
    safety (including those of the Railroad Administration, 
    49 C.F.R. § 1.89
    ). That later-added portion of the Hobbs Act
    more broadly empowers courts to review “all final agency
    actions[.]” 
    28 U.S.C. § 2342
    (7) (emphasis added); see 
    49 U.S.C. § 20114
    (c) (same); see also Rail Safety Enforcement
    and Review Act, Pub. L. No. 102-365, § 5(c), 
    106 Stat. 972
    ,
    975 (1992) (adding subsection 7 to 
    28 U.S.C. § 2342
    );
    Atchison, 
    44 F.3d at 441
    .
    Recognizing, as the Railroad Administration agrees (Oral
    Arg. Tr. 32:22–33:7), that its passive final approval was
    entered upon the passage of the thirty-day approval period,
    then the agency’s endorsement of the plan and the agency’s
    conferral of new legal rights on the railroad falls within Section
    2342(7)’s comprehensive coverage of Railroad Administration
    “actions” dealing with railroad safety. The form that an act of
    “entry” takes in any particular case is very much a product of
    agency regulations and procedures for formalizing in agency
    records the adoption of a final decision. See Western Union,
    
    773 F.2d at
    376–378. As a result, nothing in the Hobbs Act
    requires that entry involve publication or a special form of
    internal documentation. Indeed, the text of Section 2344 itself
    makes plain that “entry” and “notice thereof by service or
    publication” can be two distinct steps in the agency’s process.
    
    28 U.S.C. § 2344
    .
    Entry, in other words, depends on context. And under the
    unusual passive scheme at issue here, entry occurs when the
    document submitted by the railroad as a proposal
    transmogrifies into an agency-approved program conferring
    31
    new rights or authority on the railroad. That, for all practical
    intents and purposes, is the date a railroad’s proposal is
    designated “approved” by the Railroad Administration and
    agency regulations make the railroad aware of the agency’s
    official sanction. Cf. Energy Probe v. Nuclear Regulatory
    Comm’n, 
    872 F.2d 436
    , 438 (D.C. Cir. 1989) (Under Nuclear
    Regulatory Commission regulations, “the date of ‘entry,’
    which commences the running of the sixty-day period for filing
    for review under the Hobbs Act, is the date on which the
    agency’s final decision is signed and served.”).
    A contrary conclusion, under which agencies could take
    undisputedly final actions with concrete legal consequences
    and yet evade judicial review just by declining to formally
    paper them internally, would create an agency-controlled end-
    run of the Hobbs Act. The text enacted by Congress gives no
    quarter to such manipulation. And the well-established
    “principle of statutory construction”—“the presumption
    favoring judicial review of administrative action[]”—counsels
    strongly against reading it into the text. Guerrero-Lasprilla v.
    Barr, 
    140 S. Ct. 1062
    , 1069 (2020) (That “strong presumption”
    requires courts to, where feasible, adopt a reading of a statute
    “that accords with” the “basic principle[] that executive
    determinations generally are subject to judicial review.”)
    (internal quotation marks omitted); see also SAS Inst., Inc. v.
    Iancu, 
    138 S. Ct. 1348
    , 1359 (2018) (noting “the strong
    presumption in favor of judicial review”).
    In sum, we agree with the parties that finality and entry
    have been established. While the Railroad Administration’s
    passive approval process is less common than affirmative
    forms of agency signoff, the Hobbs Act’s provision for review
    of all “final agency actions” by the Railroad Administration
    encompasses such decisions. The agency’s decision had
    32
    material and operative legal consequences, and its entry of that
    order marked the end of the administrative road, licensing
    Kansas City Railway to materially change its operations. That
    entry of approval also transformed what before had been just
    the Kansas City Railway’s proposed document into a program
    bearing the Railroad Administration’s imprimatur of approval.
    3
    a
    The Unions’ challenge to the Railroad Administration’s
    approval of the revised Part 240 engineer certification program
    is also timely.
    The Hobbs Act imposes distinct obligations on both the
    agency and the party seeking judicial review that affect the
    time for filing a petition. Understanding how those duties fit
    together is key to determining the timeliness of the Unions’
    challenge.
    As relevant here, the Hobbs Act provides:
    On the entry of a final order reviewable under this
    chapter, the agency shall promptly give notice thereof
    by service or publication in accordance with its rules.
    Any party aggrieved by the final order may, within 60
    days after its entry, file a petition to review the order
    in the court of appeals wherein venue lies.
    
    28 U.S.C. § 2344
    .
    So the first requirement under the Hobbs Act, once a final
    order is entered, falls on the agency’s shoulders: It must
    “promptly give notice thereof by service or publication in
    33
    accordance with its rules.” 
    28 U.S.C. § 2344
    ; see Public
    Citizen v. Nuclear Regulatory Comm’n, 
    901 F.2d 147
    , 153
    (D.C. Cir. 1990) (noting the Hobbs Act’s “requirement that
    agencies promptly give notice of their final orders by service
    or publication”) (citing 
    28 U.S.C. § 2344
    ).
    The second duty under the Hobbs Act falls on the
    aggrieved party seeking judicial review. That party must,
    “within 60 days after [the final order’s] entry, file a petition to
    review the order” in the appropriate court of appeals. 
    28 U.S.C. § 2344
    . The obligation to file within that sixty-day window “is
    jurisdictional in nature, and may not be enlarged or altered by
    the courts,” Energy Probe, 
    872 F.2d at 437
     (internal quotation
    marks omitted), at least absent “exceptional” circumstances,
    JEM Broadcasting Co. v. FCC, 
    22 F.3d 320
    , 325 (D.C. Cir.
    1994); 
    id. at 326
     (“[W]e have recognized exceptions to the
    limitations period[.]”); see RCA Global Commc’ns, Inc. v.
    FCC, 
    758 F.2d 722
    , 730 (D.C. Cir. 1985); see also Matson
    Navigation Co. v. Department of Transp., 
    895 F.3d 799
    , 804
    (D.C. Cir. 2018) (noting that the Hobbs Act’s limitations
    “period can be tolled by the timely filing of a [permissible]
    motion to reconsider”) (internal quotation marks omitted).
    When an agency publicly issues orders memorializing its
    final actions, that satisfies the agency’s statutory duty of
    providing prompt public notice of entry and generally makes
    calculation of the time for filing petitions for review easy. In
    that context, “the date of ‘entry,’ which commences the
    running of the sixty-day period for filing for review under the
    Hobbs Act, is the date on which the agency’s final decision is
    signed and served” or published, Energy Probe, 
    872 F.2d at 438
    . See also Grier v. Department of Housing & Urban Dev.,
    
    797 F.3d 1049
    , 1054 (D.C. Cir. 2015) (similar); Western
    Union, 
    773 F.2d at
    376–378. If the aggrieved party fails to file
    34
    a petition for review within the ensuing sixty days, the window
    for judicial review will close. See Energy Probe, 
    872 F.2d at 438
    .
    Difficulties arise, though, when the agency internally
    enters a final order but fails to provide the statutorily required
    prompt public notice of that entry. Must petitioners be locked
    out of the courts for failing to file their challenges within sixty
    days of an unknown and secret agency act of entry—
    notwithstanding the Hobbs Act’s clear prohibition on such
    agency behavior?
    That is the problem we confront here. The Railroad
    Administration’s entirely passive approval system already
    presents significant challenges for aggrieved parties to
    establish the finality of its orders, albeit ones that the Unions
    were able to hurdle in this case. Yet this agency has made a
    bad situation worse by completely abdicating its legal duty to
    give prompt public notice of a passively approved final order’s
    entry—or even to establish rules for the provision of such
    public notice. Both of which the Hobbs Act plainly mandates.
    
    28 U.S.C. § 2344
    ; Public Citizen, 
    901 F.2d at 153
    ; contrast
    Oral Arg. Tr. 22:14–19 (Railroad Administration agreeing that
    the approval “[w]as not made public”); 
    id.
     20:23–21:1
    (Railroad Administration agreeing that its regulations do not
    provide for it to “publish or give notice of * * * certification
    approval[s]”).
    Nor does the Railroad Administration provide public
    notice when it disapproves a proposal. See 
    49 C.F.R. § 240.103
    (c) (contemplating that disapprovals will be sent only
    to “the [submitting] railroad in writing”). So while the
    submitting party may be informed of the negative decision, no
    one else is. As a result, no inference of approval can
    reasonably be drawn from agency silence. Either way, the
    35
    Railroad Administration’s regulatory scheme shields its final
    decisions from public view. 3
    Because of the Railroad Administration’s wholesale
    abandonment of its duty to formally serve or publish what it
    agrees was a reviewable final and entered order, or even to
    provide a known regulatory framework for the entry of its
    approval decisions, the agency afforded the Unions—and the
    public at large—no notice of the important and consequential
    action it took when it approved Kansas City Railway’s plan for
    the abbreviated training and certification of de México Railway
    engineers.
    Instead, the Unions first learned from the Railroad
    Administration that the agency had approved Kansas City
    Railway’s revised engineer certification program on July 9,
    2018, when the Unions witnessed Kansas City Railway put the
    crew changes into effect “with [the Administration]’s presence
    and support.” Unions Supp. Reply Br. 6; A.R. 2150; see 
    49 C.F.R. § 240.101
     (requiring each railroad to have an approved
    3
    Strikingly, the Railroad Administration’s approval process is
    so cryptic that it seems to have befuddled itself in this case. While
    the Administration argues (without citation to the record) that its
    order of approval was entered and the clock for filing started to run
    on January 31, 2018, Railroad Admin. Br. 16; Railroad Admin.
    Supp. Br. 3–4, the record indicates that Kansas City Railway
    submitted its revised Part 240 program via email on January 19,
    2018, A.R. 2083, despite the fact that the submission document itself
    is dated January 1, 2018, A.R. 2047. So it would seem that the
    Railroad Administration’s passive approval actually occurred after
    thirty days had passed from the date of the email submission—that
    is, on February 19, 2018. Compare 
    49 C.F.R. § 240.103
    (c), with
    Railroad Admin. Supp. Br. 3–4.
    36
    certification program “in effect prior to commencing
    operations”); see also 
    49 U.S.C. § 20135
    . And the Unions
    diligently filed their petition for review on September 4, 2018,
    within sixty days of the agency’s public rollout of its approval
    and support.
    The Unions did hear a few days earlier, on July 3, 2018
    (during the Southern District of Texas litigation), that the
    Railroad Administration had approved the revised engineer
    program. See Transcript of Motion Hearing, supra, at 68–69.
    But that claim did not come from the Railroad
    Administration—the entity statutorily tasked with making the
    entry that opens the petition-for-review window, 
    28 U.S.C. § 2344
    . It came only from Kansas City Railway’s Vice
    President, during a motion hearing. See Transcript of Motion
    Hearing, supra, at 68–69.           Nor was the Railroad
    Administration even a party to that litigation. Regardless, the
    Unions’ petition for review was also filed within sixty days of
    that disclosure.4
    The Railroad Administration separately asserts that the
    Unions personally learned of the approval no later than June
    4
    By the calendar, the petition was filed on the sixty-second day
    from the July 3, 2018 disclosure. But the Sunday (sixtieth day) and
    Monday (sixty-first day) of the Labor Day weekend do not count in
    calculating the review period. See FED. R. APP. P. 26(a)(1)(C) (“[I]f
    the last day [of the statutory review period] is a Saturday, Sunday, or
    legal holiday, the period continues to run until the end of the next
    day that is not a Saturday, Sunday, or legal holiday.”) Accordingly,
    the petition is timely whether measured from July 3rd or July 9th of
    that year, and we need not resolve whether the earlier disclosure on
    July 3rd was sufficient to open the filing window regarding the
    Railroad Administration’s approval.
    37
    27, 2018, pointing to a letter from the Unions to Kansas City
    Railway on that date. See Railroad Admin. Br. 6. But that
    letter states only that the Unions have “review[ed] * * * the
    revised Part 240 Locomotive Engineer Certification Program”
    submitted to it by the Railway, and consider it to have “several
    glaring deficiencies in the requirements for foreign national
    locomotive engineers[.]” Plaintiffs’ Memorandum of Points
    and Authorities in Support of Motion for Temporary
    Restraining Order and/or Preliminary Injunction at Exhibit 9,
    Kansas City, 
    2018 WL 7253969
     (No. 5:18-cv-00071), ECF
    No. 7-9. The letter provides no hint that the Unions knew that
    the Railroad Administration itself had actually approved
    Kansas City Railway’s program.
    All in all, the parties agree that the agency gave notice of
    the entry of its approval decision sufficient to open the
    jurisdictional window for filing a petition for review no later
    than July 9, 2018—the date de México engineers began driving
    trains in the United States under the watching and
    “support[ing]” eyes of the Railroad Administration, Unions
    Supp. Reply Br. 6; A.R. 2150. Given that agreement, we need
    not determine under what other particular and likely rare
    circumstances an agency’s public actions alone will open the
    Hobbs Act’s filing window. It suffices to say that the Unions’
    petition was timely because it was filed within sixty days of the
    Railroad Administration’s public rollout of its final approval of
    the new engineer certification program.
    b
    The Railroad Administration sees the timeliness issue
    differently. Having completely hidden its already obscured
    passive approval from public view, the Railroad
    Administration argues that the Unions’ petition for review is
    untimely because it was not filed within sixty days of the final
    38
    approval’s entry on February 19, 2018. As noted, that date was
    more than four months before the agency gave any public
    indication of its action that could have alerted the Unions of the
    approval’s existence and entry. As the Administration would
    have it, by dropping the ball, it has successfully hidden the ball
    from judicial review.
    But that is not how the Hobbs Act works. “[B]efore any
    litigant reasonably can be expected to present a petition for
    review” under the Hobbs Act, “he first must be put on fair
    notice” of the reviewable agency action’s existence. Public
    Citizen, 
    901 F.2d at 153
    . So even “[]though the Hobbs Act’s
    limitations period is “jurisdictional, * * * self-evidently the
    calendar does not run until the agency has decided a question
    in a manner that reasonably puts aggrieved parties on notice
    of” the challenged agency action. RCA Global Commc’ns, 
    758 F.2d at 730
    ); see JEM, 
    22 F.3d at 326
     (same); cf. Grier, 797
    F.3d at 1053–1054 (Where an agency’s regulations do not
    establish when an order is “entered” for purposes of a
    jurisdictional statute, it is “untenable” for it to argue that the
    limitations period began when the order was signed but not
    served, because that “would permit an agency to shorten a
    would-be petitioner’s review period by delaying service[.]”)
    (relying on cases construing “entry” under the Hobbs Act).
    This is not the first time an agency has flouted the Hobbs
    Act’s notice-upon-entry requirement and then asked us to
    dismiss a petition as jurisdictionally time-barred. In Public
    Citizen, the Nuclear Regulatory Commission ignored the
    Hobbs Act’s “requirement that agencies promptly give notice
    of their final [reviewable] orders by service or publication,”
    and instead “mere[ly] place[d] a decision in [the] agency’s
    public files, without any other announcement[.]” 
    901 F.2d at 153
    . We rejected the Commission’s argument that such
    39
    “placement” was sufficient to “start the clock running for
    review[.]” 
    Id.
     “Potential petitioners,” we reasoned, “cannot be
    expected to squirrel through the Commission’s public
    document room in search of papers that might reflect final
    agency action.” 
    Id.
    The Hobbs Act instead imposes a sixty-day “filing
    window” rather than “a filing deadline,” Western Union, 
    773 F.2d at 377
    , and we have repeatedly held that the filing window
    does not open until the agency “put[s] aggrieved parties on
    reasonable notice of the” action they seek to challenge, JEM,
    
    22 F.3d at
    326 (citing Eagle-Picher Indus. v. EPA, 
    759 F.2d 905
    , 911–915 (D.C. Cir. 1985); and RCA Global Commc’ns,
    
    758 F.2d at 730
    ).
    Of course, agencies subject to the Hobbs Act can by
    regulation combine the distinct “entry,” contemplated for
    jurisdiction to attach, and the separately mandated public
    notice. The FCC, for one, has done just that. 
    47 C.F.R. § 1.103
    (b) (“Commission action shall be deemed final, for
    purposes of seeking * * * judicial review, on the date of public
    notice,” which is “publication in the Federal Register,” 
    id.
    § 1.4(b)(1)). When an agency does so, the filing of a petition
    for review before such publication is premature and does not
    confer jurisdiction, because the agency decision, by definition,
    is not “final” and entered within the meaning of the Hobbs Act.
    See Council Tree Commc’ns, Inc. v. FCC, 
    503 F.3d 284
    , 287–
    290 (3d Cir. 2007); Western Union, 
    773 F.2d at
    376–377.
    This, however, is the unusual case where an agency has,
    without public knowledge, taken an action that is both final and
    entered, but for which its regulations provide no notice by
    service or publication, in direct violation of the Hobbs Act’s
    commands. Because (as the Railroad Administration agrees)
    the Unions’ petition was filed after the Railroad
    40
    Administration’s approval was finalized and entered, it was not
    filed too early.
    Neither was the petition filed too late. As noted, while the
    sixty-day period is jurisdictional, Western Union, 
    773 F.2d at 377
    , that clock does not start running prior to the agency giving
    “fair notice” of the entry of its action. Public Citizen, 
    901 F.2d at 153
     (unnoticed final agency action cannot “start the clock
    running for review, particularly in view of the Hobbs Act’s
    requirement that agencies promptly give notice of their final
    orders by service or publication, 
    28 U.S.C. § 2344
    ”); RCA
    Global Commc’ns, 
    758 F.2d at
    729–731; JEM, 
    22 F.3d at 326
    (collecting cases).
    By virtue of the Railroad Administration’s presence and
    support, in the company of the Unions, at Kansas City
    Railway’s public rollout of the approved crew changes on July
    9, 2018, the Unions explain that the Railroad Administration’s
    actions alerted them to the agency’s final approval and entry of
    the Railway’s modified engineer certification program.
    To be clear, it is doubtful that the Unions’ observation of
    the Railroad Administration’s on-the-scene actions constituted
    the formal, statutorily required public notice under the Hobbs
    Act. But the only question here is whether Public Citizen’s
    fair-notice-of-entry requirement for opening the jurisdictional
    window to file a petition for review of hidden agency action
    was satisfied, 
    901 F.2d at 153
    . On these unusual facts—and in
    particular because of the agency’s unique, entirely passive
    approval construct—we accept the parties’ agreement that the
    Railroad Administration going public with its approval of and
    support for the revised engineer certification program in the
    presence of the Unions on July 9, 2018, opened the filing
    window. And this petition was filed within sixty days of that
    date.
    41
    4
    The dissenting opinion agrees that the Railroad
    Administration’s approval of Kansas City Railway’s revised
    engineer program constitutes final agency action that was
    entered (albeit in an unreasonable manner, given the non-
    public nature of the entry). See Dissent Op. at 1–3.
    Nonetheless, the dissenting opinion argues that we lack
    jurisdiction over the agency’s enshrouded final approval solely
    because the Railroad Administration subsequently defied the
    Hobbs Act’s mandate that it promptly give formal notice by
    service or publication of its entry. See Dissent Op. at 3. The
    dissenting opinion contends that the consequence of the
    agency’s secrecy and failure to give notice did not simply
    “delay[] the filing period[,]” but also “invalidated the
    jurisdictional effect of the approval’s entry,” wholly insulating
    the agency action from judicial review. Dissent Op. at 3.
    But nothing in the Hobbs Act supports elevating the
    agency’s independent discharge of its formal notice duty to a
    freestanding jurisdictional prerequisite in that way.
    Even when a statutory requirement sits in the company of
    other jurisdiction-conferring provisions, mere proximity alone
    will not make it jurisdictional. Gonzalez v. Thaler, 
    565 U.S. 134
    , 147 (2012) (“Mere proximity will not turn a rule that
    speaks in nonjurisdictional terms into a jurisdictional hurdle.”);
    Sebelius v. Auburn Reg’l Med. Ctr., 
    568 U.S. 145
    , 155 (2013)
    (similar). Rather, courts will treat statutory elements as
    jurisdictional only if “the Legislature clearly states that a
    threshold limitation * * * shall count as jurisdictional[.]”
    Arbaugh v. Y & H Corp., 
    546 U.S. 500
    , 515 (2006); Kaplan v.
    Central Bank of the Islamic Republic of Iran, 
    896 F.3d 501
    ,
    512 (D.C. Cir. 2018).
    42
    For example, in Gonzalez, the Supreme Court looked at
    the certificate of appealability requirement in the Antiterrorism
    and Effective Death Penalty Act, 
    28 U.S.C. § 2253
    , subsection
    by subsection and then paragraph by paragraph to parse out
    which components are jurisdictional and which are not. 
    565 U.S. at
    140–148 (holding that 
    28 U.S.C. §§ 2253
    (a), 2253(b),
    and 2253(c)(1) are jurisdictional, but Section 2253(c)(3) is
    not).
    In the Hobbs Act, the obligation on the agency to promptly
    give notice of or to publish the final order upon entry appears
    in a standalone sentence at the beginning of the statutory
    section: “On the entry of a final order reviewable under this
    chapter, the agency shall promptly give notice thereof by
    service or publication in accordance with its rules.” 
    28 U.S.C. § 2344
    . Notice, service, and publication are not mentioned
    again in Section 2344. Congress, in other words, placed no
    “clear jurisdictional label” on the separate statutory duty of the
    agency to provide prompt notice of its final, entered orders, nor
    did it otherwise hinge jurisdiction on the agency’s compliance.
    Kaplan, 896 F.3d at 512 (quoting Reed Elsevier, Inc. v.
    Muchnick, 
    559 U.S. 154
    , 162 (2010)).
    Rather, it is the next sentence that packs the jurisdictional
    punch. It specifically conditions the availability of judicial
    review on (i) a final order, (ii) its entry, and (iii) the aggrieved
    party filing its petition in the appropriate court of appeals
    within a sixty-day window. 
    28 U.S.C. § 2344
     (“Any party
    aggrieved by the final order may, within 60 days after its entry,
    file a petition to review the order in the court of appeals
    wherein venue lies.”); Western Union, 
    773 F.2d at 377
    (Section 2344 establishes a sixty-day “filing window,” not “a
    filing deadline”).
    43
    To be sure, Congress presupposed that agencies would
    comply with the public notice or service command of the first
    sentence so that the jurisdictionally required “entry” would be
    proximate to the notice necessary to file a petition. And where
    agencies issue formal orders that are signed and served, such
    orders are deemed “entered” that day, ensuring that those
    subject to the orders have fair notice of the opening of the filing
    window. Energy Probe, 
    872 F.2d at 438
    ; Grier, 797 F.3d at
    1054. After all, without the agency providing notice of its
    decision, how else would affected parties even know they are
    aggrieved? But that does not make the agency’s provision of
    post-entry notice itself a jurisdictional element.
    Also of jurisdictional note, the obligation to provide notice
    is not “a burden that” the parties affected by agency action
    “bear[.]” Gonzalez, 
    565 U.S. at 144
    . The petitioning party,
    who “may have done everything required of him by law,” has
    “no control over” the agency’s nonfeasance. 
    Id.
     Nothing in
    the statutory text or structure supports assigning jurisdictional
    consequence to the petitioner’s agency-induced haplessness.
    And the “strong presumption” in favor of judicial review
    weighs heavily against making the agency’s flouting of a
    statutory requirement the very instrument for locking the
    agency’s challengers out of court. See Guerrero-Lasprilla, 140
    S. Ct. at 1069.
    The dissenting opinion points to the Supreme Court’s
    recent decision in Rotkiske v. Klemm, 
    140 S. Ct. 355
     (2019), as
    support for the general proposition that courts should not
    rewrite statutory limitations periods to include an across-the-
    board discovery-rule limitation that Congress did not enact.
    See Dissent Op. at 2. We agree. But this case is about the
    provision of statutorily required agency notice of its action, not
    plaintiffs’ discovery of their injury caused by an asserted legal
    44
    error in that agency action. Contrary to the dissenting
    opinion’s assumption (Dissent Op. 2–3), those are not the same
    things.
    Plus, the Supreme Court in Rotkiske expressly left open
    the “application of equitable [tolling] doctrines[.]” 140 S. Ct.
    at 361 n.3. That would seem to include the very reasonable
    notice principle adopted by this court in Public Citizen,
    endorsed by the dissenting opinion (at 3–4) and applied here,
    where an agency has openly flouted its statutory duty to
    provide formal notice of its indiscernible, entirely passive, and
    unwritten entry process.
    More specifically, in Rotkiske, the Supreme Court
    declined to read the limitations period in the Fair Debt
    Collection Practices Act that permitted certain suits to “be
    brought * * * within one year from the date on which the
    [statutory] violation occurred,” 15 U.S.C. § 1692k(d), as never
    running in any case until “the date the [violation] is discovered
    [by the plaintiff].” 140 S. Ct. at 360. The Court stressed that
    it is not for the judiciary to “second-guess” the legislature’s
    decision not to adopt an across-the-board discovery rule to start
    the filing period, and that courts instead must “simply enforce
    the value judgments made by Congress.” Id. at 361
    (emphasizing that “many [other] statutes included provisions
    that, in certain circumstances, would begin the running of a
    limitations period upon the discovery of a violation, injury, or
    some other event”) (citing examples).
    This case bears little resemblance to the issue decided in
    Rotkiske. The Unions do not seek, and we do not read into the
    Hobbs Act, an across-the-board—or any—“de facto discovery
    rule.” Dissent Op. at 2. Here, it was Congress, not this court,
    that mandated in no uncertain terms that covered agencies
    promptly provide notice by service or publication after entering
    45
    their orders. 
    28 U.S.C. § 2344
    . We simply give the same effect
    to that statutory notice requirement as Public Citizen did,
    hinging the opening of the window for filing a petition for
    review on the agency providing some reasonable form of notice
    to the Unions, and not on the Unions’ independent discovery
    of agency action.
    Likewise, it was Congress that declined to make
    jurisdictional the agency’s post-entry provision of notice. By
    applying Public Citizen’s fair-notice-of-entry requirement to
    the distinctive facts of this record and the agency’s unique
    purely passive-approval process, and accepting the parties’
    agreement that it was eventually satisfied, we do no surgery on
    the Hobbs Act—certainly none that differs from the dissenting
    opinion’s agreement that “reasonabl[e]” notice is required,
    Dissent Op. at 3–4. Holding that the Railroad Administration
    had to provide “fair notice” to be entitled to repose, Public
    Citizen, 
    901 F.2d at 153
    , “enforce[s,]” rather than supplants,
    “the value judgments made by Congress” regarding this
    limitations period, Rotkiske, 140 S. Ct. at 361. To the extent
    the dissenting opinion dismisses the application of a “fair
    notice” requirement under the Hobbs Act, it is at war with
    thirty-year-old circuit precedent that binds this panel.
    Compare Dissent Op. at 2–3 (“More fundamentally, the court’s
    ‘fair-notice-of-entry doctrine’ contravenes the Hobbs Act,
    which keys commencement of the sixty-day filing period to
    ‘entry’ itself, 
    28 U.S.C. § 2344
    , and not to when aggrieved
    parties receive ‘fair notice’ of such entry.”), with Public
    Citizen, 
    901 F.2d at 153
     (petitioner “first must be put on fair
    notice” of the agency’s entry of its action before the sixty-day
    filing period runs).
    Of course, if the notice requirement were jurisdictional,
    our hands would be tied. See e.g., Arbaugh, 
    546 U.S. at
    513–
    46
    516. The agency’s failure to provide such notice would be a
    jurisdictional defect fatal to the Unions’ petition. But Congress
    did not make the provision of notice itself a jurisdictional
    hurdle—a reading of the statute with which the dissenting
    opinion agrees. Dissent Op. at 5 (agreeing that the agency’s
    provision of notice, “on its own, is of no jurisdictional
    consequence”). Yet by fusing together the reasonable
    provision of notice and the jurisdictional requirement of an
    entry—such that only a “reasonably” noticed entry creates
    jurisdiction, 
    id.
     at 4—the dissenting opinion necessarily
    elevates the notice requirement to jurisdictional effect. That is
    Congress’s job, not the courts’.
    The dissenting opinion acknowledges that its approach
    would allow agencies to evade judicial review of their final
    actions just by violating the Hobbs Act’s notice requirements.
    Dissent Op. at 5. But it says not to worry because “most
    agencies * * * sensibly comply with their Hobbs Act
    obligations.” Dissent Op. at 5–6 (citing examples). Thank
    goodness they do. But that is no help to those parties aggrieved
    by a recalcitrant agency’s statutory defiance.
    The dissenting opinion would relegate those parties to the
    extraordinary remedy of mandamus relief. Dissent Op. at 6;
    see Dunlap v. Presidential Advisory Comm’n on Election
    Integrity, 
    944 F.3d 945
    , 950 (D.C. Cir. 2019) (Mandamus relief
    is a “drastic and extraordinary remedy reserved for really
    extraordinary causes.”) (quoting Cheney v. United States Dist.
    Court, 
    542 U.S. 367
    , 380 (2004)); see also 
    id.
     (noting that
    mandamus petitioners must demonstrate, among other things,
    “a clear and indisputable right to” the relief they seek)
    (emphasis added).
    That approach, however, is at least a half—if not a total—
    victory for the misbehaving agency. Requiring aggrieved
    47
    parties to navigate the convoluted mandamus road would long
    delay judicial review and confine it to those few (if any)
    aggrieved parties who have the resources, time, and legal
    wherewithal to first pursue mandamus and then, months and
    months later, start the judicial review process. Still worse,
    because the Railroad Administration has also disregarded the
    statutory obligation to establish “rules” for the provision of
    notice, 
    28 U.S.C. § 2344
    , there might first need to be a
    mandamus action to require the creation of such rules and—if
    that succeeded—another mandamus action to compel notice in
    accordance with those rules. And only then could a petition for
    review follow.
    It is hard to wring that crabbed route to judicial review out
    of the Hobbs Act’s text. Or to explain how the Unions’ petition
    is premature when it challenges an (undisputedly) final and (as
    the agency acknowledges) entered Administration order that
    has been in operation now for over two and a half years,
    allowing engineers not properly certified for safety to operate
    hundreds of northbound and southbound train trips every
    month on domestic rail lines. It is even harder when analyzed
    against the strong presumption in favor of judicial review of
    Railroad Administration action. See Guerrero-Lasprilla, 140
    S. Ct. at 1069.
    5
    The Railroad Administration separately argues that the
    Unions’ petition does not actually include a challenge to its
    approval of Kansas City Railway’s modified engineer
    certification program. Railroad Admin. Supp. Br. 3. As the
    Railroad Administration sees it, the Unions’ petition fails to
    specifically point to the Part 240 approval and, instead, raises
    only a general challenge to the agency’s “purported decision”
    to allow de México Railway “to operate freight trains in the
    48
    United States,” Railroad Admin Br. 14, without first requiring
    de México “to submit its own engineer certification program,”
    Railroad Admin. Supp. Br. 3.
    That argument only half reads the petition. Alongside
    those more general complaints, the Unions’ petition also
    specifies that its challenge includes, among other things,
    “the * * * certification of” de México Railway’s “non-U.S.
    locomotive engineers and conductors, as well as the review,
    vetting and approval of such * * * certification by” the
    Railroad Administration. Petition at 3. That language directly
    challenges the Railroad Administration’s approval of Kansas
    City Railway’s modified engineer certification program.
    Especially since a petitioner’s intent to seek review of a
    specific order need only be “fairly inferred from the petition
    for review or other contemporaneous filings[.]” Entravision
    Holdings, LLC v. FCC, 
    202 F.3d 311
    , 313 (D.C. Cir. 2000).
    The Unions’ petition satisfies that requirement.
    To the extent that the Railroad Administration separately
    objects that the Unions did not “attach to the petition, as
    exhibits, copies of the” Railroad Administration’s approval of
    the modified Part 240 engineer certification program, Railroad
    Admin. Br. 14 (quoting 
    28 U.S.C. § 2344
    ), that is pure
    chutzpah. It was the Railroad Administration that chose to act
    through a passive approval process and entirely failed to
    provide the statutorily required notice of its final order’s entry.
    So there was no paper that the Unions could attach. It should
    go without saying that we will not dismiss the petition for
    failing to attach a document that, by agency design, does not
    exist. But apparently we do have to say it after all.
    49
    *****
    For all of those reasons, we have jurisdiction under the
    Hobbs Act to address the Unions’ timely petition from the
    Railroad Administration’s final approval of Kansas City
    Railway’s modified engineer certification program.
    B
    The Unions’ petition also challenges several other actions
    of the Railroad Administration relating to the Railroads’
    implementation of the new crew change procedures. First, the
    Unions seek to overturn the agency’s acquiescence in Kansas
    City Railway’s application of its existing Part 242 conductor
    certification program to de México Railway conductors.
    Second, they argue that the Railroad Administration
    unlawfully modified or reassigned Kansas City Railway’s
    brake-test waiver by permitting de México Railway workers to
    operate northbound trains without performing a Class I brake
    test at the International Bridge. Third, the Unions broadly seek
    review of multiple other Railroad Administration failures to act
    pertaining to Kansas City Railway’s revised crew change
    procedures.
    Because the administrative record does not show that the
    Railroad Administration entered a final approval for any of
    those actions, we do not have jurisdiction under the Hobbs Act
    to review them.
    1
    Recall that, unlike the engineer certification program, the
    Railroad Administration’s August 2017 audit concluded that
    “no changes [were] necessary to” Kansas City Railway’s
    existing Part 242 conductor program to enable it to certify de
    50
    México Railway conductors under an abbreviated training
    curriculum. J.A. 390. So Kansas City Railway never
    submitted a revised, modified, or amended (or even
    resubmitted its existing) conductor certification program to the
    Railroad Administration for approval. And the Railroad
    Administration did not review (let alone approve) any
    modifications to that conductor certification program.
    So there is nothing in the administrative record to point to
    as a reviewable final agency action taken by the Railroad
    Administration with respect to Kansas City Railway’s
    certification of de México Railway’s conductors under an
    abbreviated training program.
    To be sure, the Railroad Administration took final and
    reviewable agency action in 2012 when it first approved
    Kansas City Railway’s conductor certification program. But
    the Unions do not purport to challenge that approval, nor could
    they timely do so at this juncture.
    Neither does the Railroad Administration’s audit in 2017
    amount to a final and reviewable agency action. The audit
    itself reached “a merely tentative or interlocutory” decision on
    the Railroad’s proposed cross-border program. Bennett, 
    520 U.S. at 178
    . The internal audit was sent from two Railroad
    Administration officials to another official, and it concluded by
    stating that, subject to further review, the audit team
    “believe[s]” that Kansas City Railway “has completed the due
    diligence necessary to certify [de México] engineers and
    conductors.” J.A. 391.
    The Railroad Administration explains that the audit
    represents only “the preliminary views of a subordinate agency
    official,” and not a final determination of the Administration
    itself. Railroad Admin. Supp. Br. 6. We agree. Without any
    51
    showing that the recipient of the audit or any official with
    authority to bind the Railroad Administration ever ratified the
    audit team’s conclusions, we cannot conclude that the audit
    constitutes final agency action. See, e.g., Holistic Candlers &
    Consumers Ass’n v. FDA, 
    664 F.3d 940
    , 944 (D.C. Cir. 2012);
    cf. California Cmtys., 934 F.3d at 636; Her Majesty the Queen
    in Right of Ontario v. EPA, 
    912 F.2d 1525
    , 1531–1532 (D.C.
    Cir. 1990).
    True, Kansas City Railway began, after the audit, to allow
    de México Railway conductors it had certified to operate on its
    tracks in the United States. But without more, “[p]ractical
    consequences” independently put into effect by private parties
    alone “are insufficient to bring an agency’s conduct under our
    purview.” Independent Equip. Dealers Ass’n v. EPA, 
    372 F.3d 420
    , 428 (D.C. Cir. 2004).
    The Unions nonetheless argue that there was final agency
    action in that, by allowing Kansas City Railway to operate with
    de México Railway conductors that it had certified, the
    Railroad Administration must have implicitly waived
    regulatory and statutory requirements that, in the Unions’ view,
    required de México Railway to obtain its own approved
    Part 242 certification program for conductors. See Unions
    Reply Br. 9–10.
    But the administrative record contains no sign of final
    agency action whatsoever granting such a waiver, either
    actively or passively. As far as the record shows, Kansas City
    Railway’s certification of conductors seems to be purely a
    decision of its own making.
    At bottom, the Unions’ challenge is to what they see as the
    Railroad Administration’s failure to enforce the laws
    governing conductor certifications against Kansas City
    52
    Railway and de México Railway. That argument runs up
    against the “well-established tradition” that “an agency’s
    decision not to prosecute or enforce is generally committed to
    an agency’s absolute discretion.” Department of Homeland
    Sec. v. Regents of the Univ. of Cal., 
    140 S. Ct. 1891
    , 1906
    (2020) (internal quotation marks omitted). And from a
    practical perspective, a challenge like the Unions’ that targets
    an agency’s refusal to act, leaves courts without an “action to
    provide a focus for judicial review.” 
    Id.
     (formatting modified).
    Relabeling that same inaction a “waiver” of legal requirements
    does not suddenly make the unreviewable reviewable.
    For those reasons, there is no final agency action regarding
    Kansas City Railway’s decision to begin certifying de México
    conductors under its preexisting Part 242 conductor
    certification program, and we lack jurisdiction under 
    28 U.S.C. § 2342
     to entertain the Unions’ objections to that program’s
    operation.
    2
    The Unions also seek our review of the Railroad
    Administration’s asserted indication that Kansas City
    Railway’s brake-test waiver can also be used by de México
    Railway conductors. The Unions point in particular to an
    internal June 6, 2018 Railroad Administration email noting that
    Kansas City Railway “currently operates under a [brake-test]
    waiver” for northbound trains, and that, under the new crew
    change procedure, “this will still be the case.” J.A. 559; see
    also Oral Arg. Tr. 51:17–23.
    The Railroad Administration argues that the email is
    nothing more than a lone staffer’s response to “questions about
    how the new crew change procedures work.” Railroad Admin.
    Br. 18.   That is in some tension with the Railroad
    53
    Administration’s repeated arguments in this court that,
    “[c]ontrary to the [U]nions’ views[,] * * * the existing brake
    test waiver applies to all trains operating on [Kansas City
    Railway’s] tracks at the border, including trains operated by
    [de México Railway] crews (who are certified under [Kansas
    City Railway’s] engineer and conductor certification
    programs).” Railroad Admin. Br. 22. And the Railroad
    Administration does not dispute its own knowledge that de
    México Railway crewmembers are, and have been for quite
    some time, using Kansas City Railway’s brake-test waiver for
    their own operations.
    But like the conductor certifications, the record shows
    only that the Railroad Administration has knowingly allowed
    the Class I brake-test waiver’s use by de México Railway
    crews. Nothing in the administrative record surfaces an actual
    final action by the agency granting an extension of Kansas City
    Railway’s brake-test waiver or otherwise assigning it to de
    México Railway. Nor can counsel’s argument to this court
    retroactively create final agency action that the administrative
    record itself does not reveal. Cf. SEC v. Chenery Corp., 
    332 U.S. 194
    , 196 (1947). “[W]e have held often enough that when
    an agency has not yet made any determination or issued any
    order imposing any obligation, denying any right, or fixing any
    legal relationship, the agency action was not reviewable.”
    Independent Equip., 
    372 F.3d at 427
     (formatting modified).
    Neither may we review the Railroad Administration’s failure
    to bring an enforcement action regarding the asserted violation
    of brake-test regulations. See Regents, 140 S. Ct. at 1906.
    3
    Apart from those discrete objections to the Railroad
    Administration’s actions or inaction, the Unions describe their
    petition as more broadly challenging the Railroad
    54
    Administration’s approval of a “Pilot Program allowing a
    Mexican railroad company, using Mexican train crews, to
    regularly operate freight trains within the United States free
    from U.S. rail safety requirements.” Unions Br. 1. In addition
    to the engineer certifications, conductor certifications, and
    expanded brake-test waiver, the Unions assert that the Railroad
    Administration has wrongly permitted de México Railway
    crews to operate in violation of agency regulations governing
    communication protocols and hours of service restrictions,
    without going through the necessary procedural requirements
    for granting regulatory waivers. See Unions Br. 43–47.
    The Railroad Administration, for its part, categorically
    denies that it has adopted a “so-called ‘Pilot Program,’” and
    denies that it has granted any regulatory waivers, de facto or
    otherwise. Railroad Admin. Br. 11–12, 15–20. Far from it, the
    Railroad Administration insists that de México Railway must
    fully comply with all regulations when operating within the
    United States, and that the Administration “may initiate
    enforcement proceedings” if it does not. See Railroad Admin.
    Br. 22.
    Because the Unions’ arguments sound in terms of a failure
    to enforce the law, rather than final-action review, we likewise
    lack jurisdiction to entertain these portions of the petition for
    review. The Unions have failed to identify anything in the
    administrative record evidencing that the Railroad
    Administration has either excused any of the railroads from
    complying with the regulations, or otherwise reached a final
    determination that all planned and ongoing operations are in
    full compliance with statutory and regulatory requirements.
    Instead, the Unions simply assert that the de México Railway
    crews have been or must be violating certain specific safety
    55
    regulations and fault the Railroad Administration for not
    stopping them.
    For example, the Unions assert that the Railroad
    Administration has provided “[u]nlawful relief from” various
    hours of service regulatory provisions. Unions Br. 43–47. But
    as evidence of such “unlawful relief,” the Unions point only to
    the absence of any agency documentation definitively proving
    that the crews are (or are not) in compliance. See Unions
    Br. 43–47.
    The Unions also cite Kansas City Railway’s July 2017
    draft implementation document entitled “Int[ernational] Crew
    Hours of Service Reporting Use Case.” Unions Br. 46–47;
    J.A. 362. The Unions insist that the draft Railway plan “is
    patently inadequate in scope and substance” to ensure
    compliance by de México Railway crews with hours of service
    limitations. Unions Br. 46.
    But nothing in the administrative record shows that the
    Railroad Administration ever finally approved—either
    affirmatively or passively—the Railway’s draft document.
    Neither is there any evidence that the Administration has
    otherwise made a final determination that ongoing operations
    comply with any or all of the regulatory limitations on hours of
    service. Nor does anything in the record indicate that the
    Railroad Administration “exempted [de México Railway]
    crews from hours-of-service regulations when operating within
    the United States,” or otherwise “granted” the Railroads “de
    facto general waiver[s]” from other applicable regulations,
    Railroad Admin. Br. 22.
    At bottom, what the Unions denominate final agency
    action granting a regulatory waiver is, on this record, nothing
    more than the Railroad Administration’s failure to bring
    56
    enforcement actions for alleged regulatory violations.
    Whatever tools parties may have to prod an agency off the
    regulatory sidelines, they do not on this record include judicial
    review under the Hobbs Act.
    To be sure, Kansas City Railway did share with the
    Railroad Administration its “International Crew Pilot
    Program” early on as it went about developing its proposal for
    new crew change procedures. See, e.g., J.A. 44–47. Also, in a
    June 6, 2018 internal email, a Railroad Administration official
    stated that “the plan” had been reviewed, and that “Mexican
    crews will be in compliance with all [Railroad Administration]
    regulations.” J.A. 559.
    But that is of no help to the Unions. Reviewing a plan is
    not the same as approving or adopting it. Back and forth
    communications between a regulatory official and the party it
    regulates are commonplace. That does not transform every
    document drafted by the regulated party or comment made by
    a regulatory official into final action by the agency. Internal
    Railroad Administration communications expressing opinions
    about whether various features of the cross-border program
    would comply with regulatory requirements do not “mark the
    consummation of the agency’s decisionmaking process” that
    could confer legally enforceable rights on the Railroads.
    Bennett, 
    520 U.S. at 178
     (internal quotation marks omitted).
    There is little doubt that the Railroad Administration’s
    shadowy and unwritten processes make it difficult for
    aggrieved parties to navigate the Hobbs Act’s jurisdictional
    constraints. But this court cannot exercise judicial review of
    agency action beyond what Congress permits. Nor does this
    57
    case involve a challenge to the Railroad Administration’s
    procedures themselves.5
    III
    Finally, we turn to the merits of the Unions’ challenge to
    the one final agency action over which we have jurisdiction—
    the Railroad Administration’s approval of Kansas City
    Railway’s revised engineer certification program that allows
    that railroad to use its abbreviated program to certify de
    México Railway engineers.             Because the Railroad
    Administration chose to passively approve that program
    without any explanation or discernible reasoning, the track to
    invalidation is short.
    In reviewing final orders under the Hobbs Act, we use “the
    familiar standards [of review] set forth in the” Administrative
    Procedure Act, see 
    5 U.S.C. § 706
    . BNSF Ry. Co. v.
    Department of Transp., 
    566 F.3d 200
    , 203 (D.C. Cir. 2009);
    see also Interstate Commerce Comm’n v. Brotherhood of
    Locomotive Eng’rs, 
    482 U.S. 270
    , 282 (1987) (While the
    Hobbs Act includes a general grant of jurisdiction, “it is the
    Administrative Procedure Act * * * that codifies the nature and
    attributes of judicial review.”).
    The APA, in turn, “requires agencies to engage in
    reasoned decisionmaking,” Regents, 140 S. Ct. at 1905
    (internal quotation marks omitted), and mandates that
    5
    Because we conclude that none of these three challenges arises
    from a final agency action, we need not address the parties’
    arguments about the timeliness of these portions of the Unions’
    petition.
    58
    reviewing courts “hold unlawful and set aside agency action,
    findings, and conclusions found to be * * * arbitrary,
    capricious, an abuse of discretion, or otherwise not in
    accordance with law,” 
    5 U.S.C. § 706
    (2)(A). To put a finer
    point on it, the APA requires agencies to reasonably explain to
    reviewing courts the bases for the actions they take and the
    conclusions they reach. See Regents, 140 S. Ct. at 1907.
    The Railroad Administration’s approval of Kansas City
    Railway’s Engineer Certification Program empowered that
    Railway, for the first time, to train and certify engineers of a
    different and foreign railroad over which it exercises no
    apparent control—de México Railway—under an abbreviated
    curriculum.
    Recall that de México Railway is only a foreign affiliate
    of Kansas City Railway, and there is no indication that Kansas
    City Railway exerts any control over de México Railway or the
    performance of its railway crews. Cf. Agency for Int’l Dev. v.
    Alliance for Open Soc’y Int’l, Inc., 
    140 S. Ct. 2082
    , 2087
    (2020) (“[I]t is long settled as a matter of American corporate
    law that separately incorporated organizations are separate
    legal units with distinct rights and obligations.”) (citations
    omitted); 
    id.
     (“Even though the foreign organizations have
    affiliated with the American organizations, the foreign
    organizations remain legally distinct from the American
    organizations.”). Indeed, as part of developing the new crew
    change operations, the Railroads separately had to grant de
    México Railway operating rights over their 9.2-mile stretch of
    track in the United States.
    Yet Railroad Administration regulations require “[e]ach
    railroad” operating within the United States to submit to and
    receive from the Railroad Administration approval for its
    training program for the engineers it employs. 49 C.F.R.
    59
    § 240.101(a) (“Each railroad subject to this part shall have in
    effect a written program for certifying the qualifications of
    locomotive engineers.”); id. § 240.101(b) (“Each railroad shall
    have such a program in effect prior to commencing
    operations.”); id. § 240.103 (“Each railroad shall submit its
    written certification program and a description of how its
    program conforms to the specific requirements of this part
    * * * and shall submit this written certification program for
    approval at least 60 days before commencing operations.”)
    (emphases added).
    The statute likewise instructs the Railroad Administration
    to “establish a program requiring the licensing or
    certification * * * of any operator of a locomotive” “through
    review and approval of each railroad carrier’s operator
    qualification standards[.]” 
    49 U.S.C. § 20135
    (a), (b)(1)
    (emphasis added); see also 
    id.
     § 20102 (defining a “railroad
    carrier” as “a person providing railroad transportation”). To be
    sure, the statute also allows the Railroad Administration, “upon
    petition by a group of commonly controlled railroad carriers
    that the [Administration] determines is operating within the
    United States as a single, integrated rail system,” to “by order
    treat the group of railroad carriers as a single railroad carrier[.]”
    Id. § 20102(3). But there has been no such petition, let alone
    order making those determinations, in this case.
    Also, once a certification program is approved, Railroad
    Administration regulations require each railroad that crosses an
    operating-revenue threshold to satisfy various monitoring and
    reporting requirements “concerning the administration of its
    program for responding to detected instances of poor safety
    conduct by” the engineers it certifies. See 
    49 C.F.R. § 240.309
    (emphasis added); see also 
    id.
     § 1201.1-1 (classifications of
    railroad carriers).
    60
    As the Unions see it, the Railroad Administration acted
    unlawfully when it formally approved Kansas City Railway’s
    modified engineer certification program, allowing that railroad
    to fulfill de México Railway’s independent statutory and
    regulatory certification obligations. The Unions also challenge
    the approval on the ground that it permits Kansas City Railway
    to rely on de México Railway’s engineers’ operating
    experience in Mexico—experience gained under a different
    regulatory regime—as a basis for providing only an
    abbreviated training protocol normally reserved for engineers
    previously certified under federal regulations. Unions Reply
    Br. 23; see 
    49 C.F.R. §§ 240.225
    , 242.125.
    By virtue of the Railroad Administration’s passive
    approval system and the complete absence of any
    accompanying explanation for the agency’s approval of
    Kansas City Railway’s modified engineer certification
    program, the administrative record is devoid of any
    explanation or reasoning for the administrative steps taken and
    legal determinations made by the agency in approving the
    engineer certification program. Likewise, in searching the
    administrative record for the rationale by which the agency
    allowed Kansas City Railway to certify the engineers of
    another railroad, despite the former’s apparent lack of control
    over de México Railway’s crew members, we come up empty-
    handed. And in a hunt for the reason that service under a
    foreign regulatory system was credited to allow an abbreviated
    certification program, we hear only crickets.
    All that we have are the Railroad Administration’s
    attorneys’ arguments to this court that “it is sufficient for
    [Kansas City Railway] to certify [de México Railway] crews
    under its own engineer * * * certification program[,]” and the
    61
    approved program “compl[ies] with [Railroad Administration]
    requirements[.]” Railroad Admin Br. 22.
    That will not do. Putting aside the entirely conclusory
    nature of the arguments, “[i]t is a ‘foundational principle of
    administrative law’ that judicial review of agency action is
    limited to ‘the grounds that the agency invoked when it took
    the action.’” Regents, 140 S. Ct. at 1907 (quoting Michigan v.
    EPA, 
    576 U.S. 743
    , 758 (2015)). The “basic rule here is clear:
    An agency must defend its actions based on the reasons it gave
    when it acted.” 
    Id. at 1909
    .
    Here, there are no reasons. Instead, what we confront in
    this case is a total explanatory void. There is no reason—not
    one word—in the administrative record for the Railroad
    Administration’s material and consequential decisionmaking
    on important matters of railroad safety. Not even Kansas City
    Railway’s certification program itself, as submitted to the
    agency, provides an explanation for the relevant
    determinations that the Agency presumably reached. When the
    reasons that an agency provided at the time it took the
    challenged action “are inadequate[,]” the agency’s action may
    not be sustained. See, e.g., Regents, 140 S. Ct. at 1907; City of
    Oberlin v. FERC, 
    937 F.3d 599
    , 605 (D.C. Cir. 2019). The
    Railroad Administration’s reasons in this case are even less
    than “inadequate.” They are non-existent.
    Vacatur “is the normal remedy” when we are faced with
    unsustainable agency action. Allina Health Servs. v. Sebelius,
    
    746 F.3d 1102
    , 1110 (D.C. Cir. 2014). In this case, the
    Railroad Administration has neither asked the court nor given
    us any reason to depart from that standard course of action. So
    we vacate and remand for the Railroad Administration either
    to “offer a fuller explanation of the agency’s reasoning at the
    time of the agency action,” or to “deal with the problem afresh
    62
    by taking new agency action.” Regents, 140 S. Ct. at 1907–
    1908 (formatting modified).
    IV
    For all of those reasons, we grant the Unions’ petition for
    review as to the Railroad Administration’s approval of Kansas
    City Railway’s use of its modified Part 240 engineer
    certification program to train and certify de México Railway
    engineers, and we vacate and remand for further agency action
    consistent with this opinion. We otherwise dismiss the petition
    for lack of jurisdiction.
    So ordered.
    TATEL, Circuit Judge, concurring in part and dissenting in
    part: I share my colleagues’ exasperation with the Railroad
    Administration’s conduct and agree with much of the court’s
    excellent analysis. But because I believe we lack jurisdiction at
    this time to review the revised engineer certification program,
    I reluctantly dissent from that portion of the court’s opinion.
    The Hobbs Act requires that “[o]n the entry of a final
    order,” an agency “shall promptly give notice thereof by
    service or publication in accordance with its rules” and that a
    party aggrieved by that order must file any petition for review
    “within 60 days after its entry.” 
    28 U.S.C. § 2344
    . The sixty-
    day period acts as a “filing window,” barring consideration not
    only of “petitions filed more than sixty days after entry” but
    also of “petitions filed prior to entry of the agency orders to
    which they pertain.” Western Union Telegraph Co. v. FCC,
    
    773 F.2d 375
    , 377, 378 (D.C. Cir. 1985).
    In this case, although the Railroad Administration
    ostensibly entered the certification program’s approval in
    February 2018, it wholly ignored its statutory duty to
    “promptly give notice thereof”; indeed, the agency has never
    even promulgated “rules” for the “service or publication” of
    such decisions. 
    28 U.S.C. § 2344
    . The court readily
    acknowledges these failures and that, as a result, the Unions
    filed their petition more than sixty days after entry occurred.
    See Majority Op. at 35, 38. It nevertheless finds the petition
    timely on the ground that the Hobbs Act’s sixty-day clock did
    not begin running until the Unions had “‘fair notice’ of the
    entry,” 
    id. at 40
     (quoting Public Citizen v. Nuclear Regulatory
    Commission, 
    901 F.2d 147
    , 153 (D.C. Cir. 1990)), namely,
    when, on July 9, 2018, “the Unions witnessed Kansas City
    Railway put the crew changes into effect ‘with [the
    Administration]’s presence and support,’” id. at 36 (quoting
    Unions Supp. Reply Br. 6) (citing Administrative Record
    (A.R.) 1250). On the court’s account, then, the petition was not
    too early because it came after the program’s entry and not too
    2
    late because it was filed within sixty days of when the Unions
    “first learned” of the agency’s decision. Id.
    The court’s holding is difficult to square with its own “fair-
    notice-of-entry requirement,” id. at 41, as the court fails to
    explain how the Railroad Administration’s mere “presence and
    support,” id. at 36 (quoting Unions Supp. Reply Br. 6),
    “reasonably put[] aggrieved parties on notice” of the
    challenged agency action, RCA Global Communications, Inc.
    v. FCC, 
    758 F.2d 722
    , 730 (D.C. Cir. 1985). Surely not all
    potentially aggrieved parties happened to “witness[]” the crew
    change go into effect, as did the Unions. Majority Op. at 36.
    And even if they had, it would take something like divine
    guidance to deduce from the Railroad Administration’s opaque
    involvement in the rollout that the agency, months earlier, had
    passively approved the railway’s revised engineer program.
    See A.R. 2150 (detailing the agency’s limited participation in
    the program’s launch). True, the Unions had a rough notion of
    the program’s approval by July 9, see Unions Supp. Reply Br.
    6, though that might well have been because they were
    informed of the decision days earlier, see Transcript of Motion
    Hearing at 68–69, Kansas City, 
    2018 WL 7253969
     (No. 5:18-
    cv-00071), ECF No. 24. In any event, if the measure of fair
    notice is actual notice for one set of aggrieved parties, then the
    court’s fair-notice requirement collapses into nothing more
    than a de facto discovery rule, with petitions’ timeliness turning
    on the happenstance of when aggrieved parties (or just one
    aggrieved party) learn of the agency’s action. But see Rotkiske
    v. Klemm, 
    140 S. Ct. 355
    , 360 (2019) (cautioning against
    reading notice-based discovery exceptions into statutory filing
    requirements and calling such “[a]textual judicial
    supplementation . . . inappropriate”).
    More fundamentally, the court’s “fair-notice-of-entry
    requirement” contravenes the Hobbs Act, which keys
    3
    commencement of the sixty-day filing period to “entry” itself,
    
    28 U.S.C. § 2344
    , and not to when aggrieved parties receive
    “fair notice” of such entry, Majority Op. at 40 (quoting Public
    Citizen, 
    901 F.2d at 153
    ). Tellingly, because the Hobbs Act
    requires agencies to give notice only “promptly,” i.e., not
    simultaneously with entry, 
    28 U.S.C. § 2344
    , the statute
    expressly contemplates orders being entered and the filing
    window opening before aggrieved parties learn of agency
    action, see, e.g., Energy Probe v. Nuclear Regulatory
    Commission, 
    872 F.2d 436
    , 437 (D.C. Cir. 1989) (explaining
    that “[t]he Secretary’s letter informing petitioners of the
    Commission’s final action was signed and stamped ‘served’ on
    September 13” and that “[t]he sixty-day period therefore began
    to run from that date,” even though petitioners did not receive
    the letter “until September 26”).
    In my view, rather than delaying the filing period, the
    Railroad Administration’s failure to give notice invalidated the
    jurisdictional effect of the approval’s entry. Put differently,
    instead of pushing back the start of the filing window, the lack
    of notice meant the window never opened. This is evident from
    our court’s decision in Public Citizen v. Nuclear Regulatory
    Commission, 
    901 F.2d 147
     (D.C. Cir. 1990). There, the agency
    argued that the Hobbs Act’s sixty-day filing period should be
    measured not from when the challenged action was published
    in the Federal Register but from when, prior to such
    publication, a paper reflecting that decision “was made
    available to the public in the [agency’s] public document
    room.” 
    Id. at 153
     (internal quotation marks omitted). Rejecting
    that argument out of hand, we explained that although agencies
    have “considerable latitude in determining the event that
    triggers commencement of the judicial review period, [they]
    must do so reasonably.” 
    Id.
     (citation omitted) (internal
    quotation marks omitted). And because “[p]otential petitioners
    [should not] be expected to squirrel through [an agency’s]
    4
    public document room in search of papers that might reflect
    final agency action,” we concluded that the “mere placement
    of a decision in an agency’s public files, without any other
    announcement,” could not reasonably “start the clock running
    for review.” 
    Id.
    Under the plain terms of the Hobbs Act, the jurisdiction-
    triggering event—that is, the event that opens the filing
    window—is “entry.” 
    28 U.S.C. § 2344
    . Public Citizen, then,
    necessarily stands for the proposition that however agencies
    choose to enter orders, they “must do so reasonably.” 
    901 F.2d at 153
    . And entering an order “without any other
    announcement” is simply unreasonable, 
    id.,
     as agency action
    “cannot be said to have been issued for purposes of defining
    rights . . . if its substance is merely in the bosom of the
    [agency],” Skelly Oil Co. v. Phillips Petroleum Co., 
    339 U.S. 667
    , 676 (1950). In such circumstances, the filing window
    remains shut because the “event that triggers commencement
    of the judicial review period,” i.e., entry, has not “reasonably”
    occurred. Public Citizen, 
    901 F.2d at 153
     (internal quotation
    marks omitted). Only when the agency properly enters its
    order—by, for example, publishing it in the Federal Register—
    does the “clock” start “running for review.” 
    Id.
    That logic controls here. The Railroad Administration
    gave no notice—prompt, fair, or otherwise—of the
    certification’s February 2018 approval. Contrary to the court’s
    conclusion, then, the Hobbs Act’s filing window did not open
    at that time because entry, the jurisdiction-triggering event, had
    not reasonably occurred. And unlike in Public Citizen, where
    the agency eventually entered its decision properly by
    publishing it, thereby “start[ing] the clock running for review,”
    
    901 F.2d at 153
    , to this day the Railroad Administration has yet
    to publish or serve its decision, see Majority Op. at 35, meaning
    that the program’s approval was invalidly entered and that the
    5
    sixty-day window never opened. Because the Union’s petition
    was “filed prior to entry of the action[] to which [it] pertain[s],”
    Western Union, 
    773 F.2d at 378
    , we lack jurisdiction.
    The court criticizes this approach for “fusing together” the
    Hobbs Act’s “reasonable provision of notice and the
    jurisdictional requirement of an entry,” thus “elevat[ing] the
    notice requirement to jurisdictional effect.” Majority Op. at 46.
    But as explained above, it is entry, and entry alone, that, as the
    court says, “packs the jurisdictional punch.” Id. at 43. Notice is
    merely an indicator of whether entry has “reasonably”
    occurred, Public Citizen, 
    901 F.2d at 153
    , and, on its own, is of
    no jurisdictional consequence. Thus, the Hobbs Act’s sixty-day
    window may open even before parties receive notice of an
    order’s entry, see, e.g., Energy Probe, 
    872 F.2d at 437
    , just as
    it may remain shut even after they first learn of final agency
    action, see, e.g., Western Union, 
    773 F.2d at
    377–78. In fact,
    by holding that a petition’s timeliness depends on when
    aggrieved parties receive fair notice of an order’s entry, it is the
    court that “elevates” notice’s “jurisdictional effect.” Majority
    Op. at 46.
    The court rightly worries about agencies ignoring their
    statutory duties in order to evade judicial review. See 
    id.
     But
    most agencies, including other constituent agencies of the
    Department of Transportation, sensibly comply with their
    Hobbs Act obligations. See, e.g., 
    10 C.F.R. § 2.305
    (a) (Nuclear
    Regulatory Commission) (“[T]he Commission shall serve all
    orders, decisions, notices, and other documents to all
    participants, by the same delivery method those participants
    use to file and accept service.”); 
    49 C.F.R. § 397.219
    (d)
    (Federal Motor Carrier Safety Administration) (“The
    Administrator         serves  a    copy      of    the    order
    upon . . . any . . . person readily identifiable by the
    Administrator as one who may be affected by the order. A copy
    6
    of each order is [also] placed on file in the public docket.”).
    And we have a ready-made solution for an outlaw agency, like
    this one, that insulates itself from review only by blatantly
    flouting its statutory obligations, i.e., mandamus. See In re
    Public Employees for Environmental Responsibility, 
    957 F.3d 267
    , 273 (D.C. Cir. 2020) (explaining that “mandamus relief is
    appropriate” where “agencies have failed to comply with their
    statutory mandate”). To be sure, the Unions would first have to
    initiate proceedings to force the Railroad Administration’s
    compliance with the Hobbs Act before they could challenge the
    agency’s decision on the merits. But aggrieved parties must
    occasionally take such additional steps where, as here, an
    agency has “clear[ly] and indisputab[ly]” violated its statutory
    mandate, and they “have no other adequate means to attain the
    relief [they] desire[].” Cheney v. U.S. District Court for D.C.,
    
    542 U.S. 367
    , 381–82 (2004) (internal quotation marks
    omitted). Indeed, had the Unions styled their petition as one for
    mandamus relief, I would have surely voted to grant it.
    Anyway, I trust that the Railroad Administration will take
    this court’s unanimous condemnation of its “statutory
    defiance,” Majority Op. at 47, as a clear message that it should
    revise its procedures to ensure that, however it chooses to enter
    final orders, it “promptly give[s] notice thereof,” 
    28 U.S.C. § 2344
    .
    

Document Info

Docket Number: 18-1235

Filed Date: 8/28/2020

Precedential Status: Precedential

Modified Date: 8/28/2020

Authorities (25)

her-majesty-the-queen-in-right-of-ontario-ian-g-scott-qc-attorney , 912 F.2d 1525 ( 1990 )

Gonzalez v. Thaler , 132 S. Ct. 641 ( 2012 )

Council Tree Communications, Inc. v. Federal Communications ... , 503 F.3d 284 ( 2007 )

Indep Equip Dlrs v. EPA , 372 F.3d 420 ( 2004 )

SAS Institute Inc. v. Iancu , 200 L. Ed. 2d 695 ( 2018 )

Interstate Commerce Commission v. Brotherhood of Locomotive ... , 107 S. Ct. 2360 ( 1987 )

Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )

western-union-telegraph-co-mci-telecommunications-corporation-and , 773 F.2d 375 ( 1985 )

Entravision Holdings, LLC v. Federal Communications ... , 202 F.3d 311 ( 2000 )

Energy Probe and Western Reserve Alliance v. United States ... , 872 F.2d 436 ( 1989 )

Securities & Exchange Commission v. Chenery Corp. , 332 U.S. 194 ( 1947 )

Sebelius v. Auburn Regional Medical Center , 133 S. Ct. 817 ( 2013 )

eagle-picher-industries-inc-v-united-states-environmental-protection , 759 F.2d 905 ( 1985 )

Reed Elsevier, Inc. v. Muchnick , 130 S. Ct. 1237 ( 2010 )

Skelly Oil Co. v. Phillips Petroleum Co. , 70 S. Ct. 876 ( 1950 )

Arbaugh v. Y & H Corp. , 126 S. Ct. 1235 ( 2006 )

Jem Broadcasting Company, Inc. v. Federal Communications ... , 22 F.3d 320 ( 1994 )

BNSF Railway Co. v. United States Department of ... , 566 F.3d 200 ( 2009 )

Holistic Candlers & Consumers Ass'n v. Food & Drug ... , 664 F.3d 940 ( 2012 )

Blue Ridge Environmental Defense League v. Nuclear ... , 668 F.3d 747 ( 2012 )

View All Authorities »