PSE&G v. FERC ( 2021 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued January 15, 2021              Decided March 2, 2021
    No. 19-1091
    PUBLIC SERVICE ELECTRIC AND GAS COMPANY ,
    PETITIONER
    v.
    FEDERAL ENERGY REGULATORY COMMISSION ,
    RESPONDENT
    NEW JERSEY BOARD OF PUBLIC UTILITIES, ET AL.,
    INTERVENORS
    Consolidated with 20-1039
    On Petitions for Review of Orders of the
    Federal Energy Regulatory Commission
    John Longstreth argued the cause for petitioners. With
    him on the briefs were Cara J. Lewis, Donald A. Kaplan,
    Kimberly B. Frank, and Steven Nadel. William M. Keyser III
    entered an appearance.
    Gurbir S. Grewal, Attorney General, Office of the
    Attorney General for the State of New Jersey, Paul Youchak,
    Deputy Attorney General, and Stefanie A. Brand, Director,
    2
    New Jersey Division of Rate Counsel, were on the brief for
    intervenor New Jersey Board of Public Utilities and New
    Jersey Division of Rate Counsel in support of petitioners. Alex
    Moreau, Attorney, Office of the Attorney General for the State
    of New Jersey, Stephen C. Pearson, and Scott H. Strauss
    entered appearances.
    Elizabeth E. Rylander, Attorney, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were David L. Morenoff, Acting General
    Counsel, and Robert H. Solomon, Solicitor.
    Robert A. Weishaar, Jr., Kenneth R. Stark, Thomas L.
    Rudebusch, Bhaveeta K. Mody, Timothy G. McCormick,
    William F. Fields, Joseph G. Cleaver, Michael R. Engleman,
    Regina A. Iorii, Miles H. Mitchell, Adrienne E. Clair, and
    Rebecca L. Shelton were on the brief for intervenor Public
    Service Commission for the State of Delaware, et al. in support
    of respondent. Kayla Grant entered an appearance.
    Before: SRINIVASAN, Chief Judge, ROGERS, Circuit Judge,
    and EDWARDS, Senior Circuit Judge.
    Opinion for the Court by Circuit Judge ROGERS.
    ROGERS, Circuit Judge: Public Service Electric and Gas
    Company and PPL Electric Utilities Corporation petition for
    review of three orders of the Federal Energy Regulatory
    Commission concerning cost sharing for certain upgrades to
    the Mid–Atlantic electricity transmission grid. In 2016, the
    Commission approved as just and reasonable cost allocations
    filed by PJM Interconnection, L.L.C. (“PJM”), the Mid–
    Atlantic’s regional transmission organization, for a project to
    improve the reliability of three nuclear power plants in New
    Jersey. In so doing, the Commission denied a complaint lodged
    3
    by Delaware and Maryland alleging a large imbalance between
    the costs imposed on the Delmarva transmission zone and the
    benefits that zone would accrue from the project. On rehearing
    in 2018, however, the Commission reversed course,
    concluding that, upon reexamination of the evidence,
    application of PJM’s cost–allocation method to the project
    violated cost–causation principles and was therefore unjust and
    unreasonable in violation of section 206 of the Federal Power
    Act, 16 U.S.C. § 824e. The Commission’s replacement cost–
    allocation method shifted primary cost responsibility for the
    project from the Delmarva zone to utilities in New Jersey.
    Petitioners, PJM transmission owners, and intervenors
    New Jersey Board of Public Utilities and New Jersey Division
    of Rate Counsel (“New Jersey Agencies”) contest the
    rationality of the Commission’s volte–face. They contend the
    Commission departed from precedent without adequate
    explanation, made findings that are unsupported by substantial
    evidence, and failed to respond meaningfully to objections
    raised during the proceedings. For its part, the Commission,
    with support from a coalition of Delaware and Maryland
    stakeholders, maintains that it engaged in reasoned
    decisionmaking. We conclude the Commission reasonably
    decided to adopt a different cost–allocation method for the type
    of project at issue here and adequately explained its departure
    from the cost allocations it had approved in 2016. Accordingly,
    we deny the petitions for review.
    I.
    The Federal Power Act requires that the Commission
    ensure the rates charged by public utilities to provide electricity
    are “just and reasonable.” 16 U.S.C. § 824d(a). Pursuant to
    section 206 of the Federal Power Act, the Commission may
    investigate — on its own initiative or based on a third–party
    4
    complaint — whether an existing rate is “unjust, unreasonable,
    unduly discriminatory or preferential.” Id. § 824e(a). The
    proponent of the rate change bears the burden of proof, and, if
    the Commission determines that the rate is unlawful, it must
    establish a just and reasonable replacement rate. Id. § 824e(a),
    (b). Section 206 therefore “mandates a two–step procedure”
    whereby the Commission must “make an explicit finding that
    the existing rate is unlawful before setting a new rate.” Emera
    Me. v. FERC, 
    854 F.3d 9
    , 24 (D.C. Cir. 2017). Thus,
    “[w]ithout a showing that the existing rate is unlawful,” the
    Commission “has no authority to impose a new rate.” 
    Id. at 25
    .
    The Commission has long viewed the just–and–reasonable
    requirement to “incorporate a ‘cost–causation principle.’” Old
    Dominion Elec. Coop. v. FERC, 
    898 F.3d 1254
    , 1255 (D.C.
    Cir. 2018). That “principle requires costs ‘to be allocated to
    those who cause the costs to be incurred and reap the resulting
    benefits.’” S.C. Pub. Serv. Auth. v. FERC, 
    762 F.3d 41
    , 87
    (D.C. Cir. 2014) (quoting Nat’l Ass’n of Regul. Util. Comm’rs
    v. FERC, 
    475 F.3d 1277
    , 1285 (D.C. Cir. 2007)). So, although
    the Commission need not “allocate costs with exacting
    precision,” the costs assessed against a party must bear some
    resemblance “to the burdens imposed or benefits drawn by that
    party.” Midwest ISO Transmission Owners v. FERC, 
    373 F.3d 1361
    , 1368–69 (D.C. Cir. 2004). In practice, this means “the
    Commission generally may not single out a party for the full
    cost of a project, or even most of it, when the benefits of the
    project are diffuse.” BNP Paribas Energy Trading GP v.
    FERC, 
    743 F.3d 264
    , 268 (D.C. Cir. 2014).
    Consistent with the cost–causation principle, the
    Commission issued “Order No. 1000” in 2011 to foster the
    efficient development of the transmission grid. Transmission
    Planning and Cost Allocation by Transmission Owning and
    Operating Public Utilities, F.E.R.C. Stats. & Regs. ¶ 31,323,
    5
    
    76 Fed. Reg. 49,842
     (Aug. 11, 2011), petitions for review
    denied, S.C. Pub. Serv. Auth., 
    762 F.3d 41
    . Among other
    things, Order No. 1000 requires utilities to participate in
    regional transmission planning and to include in their tariffs a
    formula “for allocating the costs of new transmission facilities
    selected in the regional transmission plan.” 
    Id.
     at P 558, 76
    Fed. Reg. at 49,929. To comply with Order No. 1000, a
    utility’s cost–allocation method must satisfy six criteria, the
    first of which embodies the cost–causation principle by
    requiring that costs be “allocated in a way that is roughly
    commensurate with benefits.” Id. at P 622, 76 Fed. Reg. at
    49,937.
    A.
    PJM is an independent entity that coordinates the
    transmission of wholesale electricity in the Mid–Atlantic
    region. In accordance with Order No. 1000, Schedule 12 of
    PJM’s Open Access Transmission Tariff outlines its cost–
    sharing requirements, which the Commission accepted in 2013.
    PJM Interconnection, L.L.C., 142 F.E.R.C. ¶ 61,214 at PP
    411–12 (Mar. 22, 2013), order on reh’g & compliance, 147
    F.E.R.C. ¶ 61,128 (May 15, 2014). As relevant here, PJM uses
    a combination of two methods to assign the costs of high–
    voltage transmission facilities built to improve grid reliability.
    Id. at P 412. Half of the cost is allocated under the “postage–
    stamp method,” which assigns costs pro rata based on the level
    of customer demand within each zone. Id. The other half is
    apportioned using the “Solution–Based DFAX method.” Id.
    Relying on “power flow analysis,” that method assigns costs
    according to the relative use of the new facility as measured by
    the amount of power flowing over the new facility to each
    transmission zone. Id. at P 416. Solution–based DFAX
    replaced PJM’s “violation–based DFAX” method, which
    assigned costs retrospectively to the zones that contributed to
    6
    the reliability violation. In approving the new method, the
    Commission touted the advantages of assigning costs
    prospectively to the zones that will benefit from the project,
    noting that the violation–based DFAX method “does not
    account for multiple constraints in multiple areas, and cannot
    account for changes in usage and flow direction over time.” Id.
    at P 427.
    Located on the New Jersey side of the Delaware River,
    Artificial Island is home to three nuclear power plants owned
    by a subsidiary of petitioner Public Service Electric and Gas
    Company. These generating units have long been plagued by
    operational issues stemming from an insufficient number of
    transmission lines connecting Artificial Island to the grid.
    Generation is constrained when one of the lines is out of
    service, and various components of the transmission system
    require careful management to prevent the power plants from
    becoming unstable and losing synchronism with the grid. Such
    losses of synchronism are referred to as “stability” problems.
    B.
    In July 2013, PJM solicited proposals to improve the
    reliability of Artificial Island. See PJM, Artificial Island
    Project Recommendation White Paper 1 (July 29, 2015). After
    two years of study, PJM selected the “Artificial Island Project,”
    which primarily entails the construction of a high–voltage line
    under the Delaware River to connect the power plants to a new
    substation in Delaware. Letter from Terry Boston, PJM, to
    PJM Members Committee (July 29, 2015); PJM 2015 White
    Paper 35–37. Under PJM’s hybrid cost–allocation method,
    nearly 90 percent of the Artificial Island Project’s $275.4
    million cost was assigned to the Delmarva transmission zone.
    PJM 2015 White Paper 38.
    7
    On August 28, 2015, PJM filed with the Commission
    proposed cost allocations for the Artificial Island Project. PJM,
    Tariff Filing (Aug. 28, 2015). The same day, the Delaware and
    Maryland Public Service Commissions filed a complaint with
    the Commission pursuant to section 206 of the Federal Power
    Act protesting PJM’s cost assignments as unjust and
    unreasonable. Applying the solution–based DFAX method to
    the Artificial Island Project was unjust, they argued, because
    when used to allocate the costs of a facility that addresses
    “inadequate outlets for generation output, the solution–based
    DFAX methodology invariably will link cost responsibility
    with the zone that just happens to be the end–point for the new
    or expanded generation output.” Compl. ¶ 32 (Aug. 28, 2015).
    A group of PJM transmission owners intervened in support of
    PJM’s proposed tariff.
    Following a technical conference, the Commission
    accepted PJM’s cost allocations and denied the complaint in
    April 2016. Del. Pub. Serv. Comm’n, 155 F.E.R.C. ¶ 61,090 at
    PP 65–76 (Apr. 22, 2016) (“2016 Order”). The Commission
    rejected the argument that use of the solution–based DFAX
    method was inappropriate, observing that “even if a stability
    violation is the primary driver of a transmission project,” the
    method “allocates costs . . . based on use of the facilities.” Id.
    at P 68. The Commission similarly found unpersuasive the
    argument that PJM’s cost assignments were unjust because the
    Delmarva zone did not contribute to the need for the Artificial
    Island Project. That argument misunderstood the solution–
    based DFAX method, which focuses on “the identification of
    beneficiaries,” “not the initial nature of the reliability
    problem.” Id. at P 69. One Commissioner dissented,
    explaining that, in her view, the record established that PJM’s
    flow–based cost–allocation methodology fails to align costs
    with benefits when the project addresses reliability violations
    8
    unrelated to power flows.          See id. (LaFleur, Comm’r,
    dissenting).
    Delaware and Maryland requested rehearing, but before
    the Commission acted, PJM suspended the Artificial Island
    Project. Letter from Pauline Foley, PJM, to FERC Secretary
    Kimberly D. Bose (Aug. 5, 2016). When PJM lifted the
    suspension in April 2017, it acknowledged that “the DFAX
    Methodology can result in cost allocations that seem
    anomalous where the engineering rationale or need for a
    project is not one driven by power flow.” Letter from Andrew
    Ott, PJM, to PJM Members (Apr. 6, 2017). To that end, PJM
    released a white paper assessing two alternative approaches to
    identify the beneficiaries of the Artificial Island Project. See
    PJM, Alternative Approaches to Identification of Artificial
    Island Beneficiaries (June 9, 2017). Soon after, Delaware and
    Maryland renewed their request for rehearing and also moved
    to reopen the record. See Mot. to Reopen the Record (Sept. 6,
    2017).
    In July 2018, the Commission granted rehearing of the
    2016 Order, concluding that using the solution–based DFAX
    method to assign the cost of the Artificial Island Project
    violated the cost–causation principle and was therefore unjust
    and unreasonable. Del. Pub. Serv. Comm’n, 164 F.E.R.C.
    ¶ 61,035 at PP 36–41 (July 19, 2018) (“2018 Order”). The
    Commission observed that the solution–based DFAX method
    “is a reasonable method for identifying beneficiaries of thermal
    overload and voltage related reliability issues” because when a
    facility resolves a flow–based reliability issue, “the
    beneficiaries of that solution are readily identified based upon
    those power flows.” Id. at P 39. However, “stability–related
    reliability issues” are “analytically unique,” the Commission
    explained, because they “result from an imbalance of
    generation and load” and, “depend[ing] on the nature of the
    9
    problem,” can “be either a very local event or spread into a
    more substantial problem.” Id. at P 40. As a result, the
    Commission found that the benefits of a facility built to
    stabilize a specific generating unit are “not necessarily
    captured” by measuring power flows. Id. P 41. The
    Commission thus determined that the solution–based DFAX
    method “does not allocate the costs of such transmission
    projects in a manner that is at least roughly commensurate with
    their benefits.” Id. at P 38. Having so ruled, the Commission
    established paper hearing procedures to select a new cost–
    allocation method. Id. at P 42.
    This time, the PJM transmission owners and New Jersey
    Agencies filed a request for rehearing. See Req. for Reh’g of
    PJM Transmission Owners (Aug. 20, 2018); Req. for Reh’g of
    N.J. Bd. of Pub. Util. Pub. Utilities & N.J. Div. of Rate Counsel
    (Aug. 20, 2018). They argued the Commission’s reversal of
    the 2016 Order was arbitrary and capricious because it was
    inadequately explained, lacked substantial evidence, and
    improperly focused on assigning costs to violators rather than
    beneficiaries. They also maintained that the 2018 Order was
    inconsistent with Order 1000 and that the Commission failed
    to respond meaningfully to their arguments against rehearing.
    The Commission denied the requests for rehearing in
    February 2019. Del. Pub. Serv. Comm’n, 166 F.E.R.C.
    ¶ 61,161 at PP 38–42 (Feb. 28, 2019) (“2019 Order”). The
    Commission first affirmed its conclusion that the solution–
    based DFAX method does not allocate the cost of the Artificial
    Island Project in a just and reasonable manner. Id. at PP 37–
    40. Next, the Commission responded to the argument that it
    acted arbitrarily because it offered no new evidence to overturn
    the 2016 Order, stating that its decision was “based on further
    consideration of th[e] existing record” and the parties’
    arguments.” Id. at P 41. Finally, the Commission rejected the
    10
    argument that it erred in reopening the record.             The
    Commission explained that it “did not rely on the PJM White
    Paper in granting rehearing” but instead considered that
    evidence only “to determine the just and reasonable alternative
    rate.” Id. at P 42. The Commission then selected a replacement
    method, which was one of two methods advanced in the White
    Paper, and directed PJM to file a revised tariff implementing
    its order. Id. at P 43. Not challenged here, the Commission’s
    new method shifted primary cost responsibility for the
    Artificial Island Project from the Delmarva zone to utilities in
    New Jersey.
    Following minor modifications by the Commission to
    PJM’s compliance filing, see Del. Pub. Serv. Comm’n, 169
    F.E.R.C. ¶ 61,234 (Dec. 19, 2019), Petitioners timely sought
    judicial review.
    II.
    The court’s review of the Commission’s orders is limited
    to determining whether they are “arbitrary, capricious, an abuse
    of discretion, or otherwise not in accordance with law.”
    
    5 U.S.C. § 706
    (2)(A); see FERC v. Elec. Power Supply Ass’n,
    
    136 S. Ct. 760
    , 782 (2016). The court will affirm the
    Commission’s orders so long as it “examined the relevant
    considerations and articulated a satisfactory explanation for its
    action, including a rational connection between the facts found
    and the choice made.” Elec. Power Supply Ass’n, 
    136 S. Ct. at 782
     (alterations adopted) (quoting Motor Vehicle Mfrs. Assn.
    of U.S., Inc. v. State Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43
    (1983)). Further, where, as here, the dispute centers on the
    Commission’s exercise of its rate–setting authority, the court is
    “particularly deferential” to the Commission’s determinations
    “because such matters are either fairly technical or ‘involve
    policy judgments that lie at the core of the regulatory
    11
    mission.’” S.C. Pub. Serv. Auth., 762 F.3d at 55 (quoting Alcoa
    Inc. v. FERC, 
    564 F.3d 1342
    , 1347 (D.C. Cir. 2009)). All that
    said, the court will vacate the Commission’s orders if the
    “allocation of costs [is] either unreasonable or inadequately
    explained.” Old Dominion, 898 F.3d at 1260 (internal citations
    omitted). And, like other agencies, the Commission “cannot
    depart from [its] rulings without ‘provid[ing] a reasoned
    analysis indicating that prior policies and standards are being
    deliberately changed.’” W. Deptford Energy, LLC v. FERC,
    
    766 F.3d 10
    , 17 (D.C. Cir. 2014) (second alteration in original)
    (quoting Alcoa, 
    564 F.3d at 1347
    ).
    Petitioners and New Jersey Agencies challenge the
    Commission’s decision to grant rehearing of the 2016 Order on
    three grounds.       Their principal contention is that the
    Commission failed to adequately justify its finding that the
    solution–based DFAX method is unjust and unreasonable as
    applied to the Artificial Island Project. Petitioners additionally
    contend the Commission’s decision is contrary to Order No.
    1000. Finally, Petitioners and New Jersey Agencies submit the
    Commission failed to meaningfully respond to their arguments
    in support of the solution–based DFAX method and in
    opposition to reopening the record. None of these challenges
    has merit.
    A.
    In the main, Petitioners and New Jersey Agencies contend
    the Commission failed to carry its burden under section 206
    and acted arbitrarily by changing its position from approving
    the use of the solution–based DFAX method to assign the cost
    of the Artificial Island Project to finding those cost allocations
    unjust and unreasonable. The Commission, they maintain,
    failed to address its initial findings in either the 2018 or 2019
    Order. They further maintain the Commission’s decision to
    12
    grant rehearing rests on insufficient evidence because it pointed
    to no new evidence or change in circumstances that undercut
    its prior conclusions that the solution–based DFAX method
    identifies the beneficiaries of stability–related reliability
    projects and that the Delmarva zone will benefit from Artificial
    Island Project.
    The Commission’s decision to grant rehearing of the 2016
    Order is neither arbitrary nor capricious and is consistent with
    its statutory obligations under section 206. As an initial matter,
    the Commission did not, as Petitioners suggest, “swerve[]”
    from the 2016 Order “without any acknowledgment.” Pet’rs’
    Br. 54.       To the contrary, the Commission expressly
    acknowledged its change of position in the 2018 Order. There,
    the Commission stated that, “based on the arguments presented
    in the rehearing requests,” it was “grant[ing] rehearing of the
    April 22, 2016 Order” and therefore would “reopen the record
    and seek additional information . . . to establish the just and
    reasonable rate.” 2018 Order, 164 F.E.R.C. ¶ 61,035 at P 36.
    The Commission then proceeded to explain in detail why it was
    unjust and unreasonable to rely on the solution–based DFAX
    method to distribute the costs of stability–related reliability
    projects — the exact opposite conclusion it reached in 2016.
    This analysis demonstrates that the Commission was
    consciously changing its position.
    That change of position is also adequately explained and
    supported by substantial evidence. In 2016, the Commission
    approved PJM’s cost allocations for the Artificial Island
    Project based on its conclusion that the solution–based DFAX
    method accurately identifies the beneficiaries of transmission
    facilities addressing stability–related reliability issues. See
    2016 Order, 155 F.E.R.C. ¶ 61,090 at PP 67–68. On rehearing,
    the Commission recognized that this conclusion was erroneous
    because flow–based reliability issues and stability–related
    13
    reliability issues are “analytically unique.” 2018 Order, 164
    F.E.R.C. ¶ 61,035 at P 38. For example, reliability issues
    caused by thermal overload are solved by increasing the
    amount of power flowing to the constrained region. In these
    circumstances, “the beneficiaries of that solution are readily
    identified based upon those power flows” because “change[s]
    in power flows are consistent with the intended solution.” 
    Id.
    at P 39. By contrast, stability issues arise from the inability of
    a particular generating unit to maintain synchronism with the
    grid, which in turn can result in constrained generation as well
    as facility outages. 
    Id.
     at P 40. And whereas flow–based issues
    are solved by bringing power to a constrained area, stability–
    related issues are solved by providing additional transmission
    pathways from the generator to the grid. Thus, because “the
    flows on a transmission project to resolve a stability–related
    reliability issue do not necessarily resolve a constraint by
    bringing power to load,” 
    id.,
     the Commission found that the
    beneficiaries of such a project “are not necessarily captured”
    by following the electrons to their end–point, 
    id.
     at P 41.
    Applying this new framework, the Commission reasonably
    found that the solution–based DFAX method was unjust and
    unreasonable as applied to the Artificial Island Project. As the
    Commission explained in the 2019 Order, because the need for
    the Artificial Island Project stems from the inability of
    transmission zones in New Jersey to fully absorb the power
    plants’ generation, those zones “both contribute to the need for,
    and will benefit from, a transmission project that will increase
    stability performance.” 2019 Order, 166 F.E.R.C. ¶ 61,161 at
    P 39. The Delmarva zone, however, “neither caused the need
    for the line nor does it benefit from those flows sufficiently
    because its transmission system already was adequate to serve
    its load without the Artificial Island Project.” 
    Id.
     at P 40.
    Instead, the Delmarva zone was the “unlucky zone that
    happen[ed] to end up as the sink point for the project.” 
    Id.
     at P
    14
    39 n.40. Given these findings, the Commission concluded that
    assigning nearly 90 percent of the Artificial Island Project’s
    cost to the Delmarva zone “would not be at least roughly
    commensurate with the benefits received” as Order No. 1000
    required and violated section 206. 
    Id.
     at P 40. Because this
    explanation is reasonable and supported by the record, we defer
    to the Commission’s technical judgments.
    Petitioners nonetheless insist that the Commission’s orders
    are defective because it never disavowed the finding in the
    2016 Order that the Delmarva zone will benefit from the
    Artificial Island Project. Pet’rs’ Reply Br. 14; Oral Arg.
    Recording 7:00–7:30. Initially, the Commission found that the
    Delmarva zone would “receive significant benefits” from the
    Artificial Island Project.” 2016 Order, 155 F.E.R.C. ¶ 61,090
    at P 72. But Petitioners overlook the context of this finding,
    specifically that these benefits were based on “the results of the
    solution–based DFAX analysis.” 
    Id.
               Subsequently, the
    Commission determined this method does not accurately
    measure the benefits of the Artificial Island Project. As the
    Commission explained in the 2019 Order, although the
    Delmarva zone “will use the Artificial Island Project as
    measured by the solution–based DFAX method,” it would not
    actually derive any “benefit from those flows . . . because its
    transmission system already was adequate to serve its load.”
    2019 Order, 166 F.E.R.C. ¶ 61,161 at P 40. Petitioners’
    contentions therefore provide no basis to set aside the
    Commission’s decision to grant rehearing of the 2016 Order.
    B.
    Petitioners additionally maintain that the Commission’s
    decision to grant rehearing is contrary to Order No. 1000’s
    directive that cost–allocation rules be set ex ante so as to
    15
    prevent ad hoc decisionmaking and internecine conflicts
    among utilities. This contention is not persuasive.
    To begin, Order No. 1000 does not concern the
    Commission; it requires transmission owners to have in place
    cost–allocation methods for certain transmission facilities. Nor
    does Order No. 1000 purport to constrain the Commission’s
    ability to comply with its statutory obligation under section
    206, which provides that the Commission “shall” reform “any
    rate” that is “unjust, unreasonable, unduly discriminatory or
    preferential.” 16 U.S.C. § 824e(a). Insofar as any tension may
    exist between Order No. 1000’s goals and the Commission’s
    exercise of its section 206 authority, “a regulation can never
    ‘trump the plain meaning of a statute.’” Texas v. EPA, 
    726 F.3d 180
    , 195 (D.C. Cir. 2013) (quoting Atl. City Elec. Co. v. FERC,
    
    295 F.3d 1
    , 11 (D.C. Cir. 2002)).
    The Commission’s decision to grant rehearing of the 2016
    Order comports with Order No. 1000. As noted, the animating
    purpose of Order No. 1000 is to promote the efficient and cost–
    effective construction of new transmission facilities that
    provide region–wide benefits. See S.C. Pub. Auth., 762 F.3d at
    52. Order No. 1000’s cost–allocation provisions, which codify
    the cost–causation principle, “further that goal” by requiring
    transmission owners to agree ex ante to rate–distribution
    methods “that avoid free rider problems, that improve
    transparency with respect to the costs of interregional projects,
    and that otherwise align regional and interregional planning
    processes.” Ameren Servs. Co. v. FERC, 
    893 F.3d 786
    , 789
    (D.C. Cir. 2018). Here, the Commission determined in the
    2018 Order that, when applied to stability–related reliability
    projects such as the Artificial Island Project, the solution–based
    DFAX method does not assign costs “in a manner that is at least
    roughly commensurate with their benefits.” 2018 Order, 164
    F.E.R.C. ¶ 61,035 at P 38. In other words, the Commission
    16
    found that PJM’s proposed cost allocations “would violate
    Order 1000’s core cost–allocation principle.” Ameren Servs.,
    893 F.3d at 794. The Commission’s decision to grant rehearing
    and identify a replacement cost–allocation method was
    therefore not inconsistent with Order No. 1000.
    C.
    Finally, Petitioners and New Jersey Agencies contend the
    Commission’s failure to meaningfully respond to their
    arguments against reopening the record and in favor of
    rehearing the 2018 Order renders its orders arbitrary and
    capricious. “It is well established that the Commission must
    ‘respond meaningfully to the arguments raised before it.’” New
    England Power Generators Ass’n, Inc. v. FERC, 
    881 F.3d 202
    ,
    210 (D.C. Cir. 2018) (quoting TransCanada Power Mktg. Ltd.
    v. FERC, 
    811 F.3d 1
    , 12 (D.C. Cir. 2015)). The Commission,
    however, must respond only to “significant comments”; it is
    “free to ignore insignificant ones.” Nat’l Ass’n of Regul. Util.
    Comm’rs, 
    475 F.3d at 1285
    . That is all the Commission did
    here.
    Petitioners raised a single argument in opposing Delaware
    and Maryland’s request for rehearing of the 2016 Order: that
    the existence of superior alternative cost–allocation
    methodologies did not provide a basis to discard the solution–
    based DFAX method. See Answer in Opp’n of the PJM
    Transmission Owners to Mot. to Reopen the Record & Lodge
    6–11 (Sept. 21, 2017). This argument was not ignored. The
    Commission expressly acknowledged the argument in the 2018
    Order. 2018 Order, 164 F.E.R.C. ¶ 61,035 at P 26 n.35. And
    it necessarily rejected the premise of Petitioners’ argument by
    finding that, as applied to the Artificial Island Project, the
    solution–based DFAX method was not inferior to other
    methods but, in fact, unjust and unreasonable. 
    Id.
     at P 41.
    17
    Nor did the Commission disregard Petitioners’ objections
    in their request for rehearing. In pursuit of rehearing,
    Petitioners argued the 2018 Order was defective because the
    Commission (1) changed its position without substantial
    evidence or adequate explanation; (2) improperly focused on
    aligning costs to causes rather than beneficiaries; (3) acted
    inconsistent with Order No. 1000; and (4) failed to address
    their arguments in the 2018 Order. See Req. for Reh’g of the
    PJM Transmission Owners 7–17. Here too, the Commission
    summarized Petitioners’ arguments in the 2019 Order and
    meaningfully responded to them by defending its finding that
    the cost allocations for the Artificial Island Project generated
    by the solution–based DFAX method failed Order No. 1000’s
    cost–causation requirement. 2019 Order, 166 F.E.R.C.
    ¶ 61,161 at PP 33–34, 38–41. To the extent the Commission
    did not expressly address Petitioners’ contention that its
    decision clashed with Order No. 1000, this objection was of no
    significance for the reasons explained, and the Commission did
    not err by ignoring it.
    New Jersey Agencies’ contention that the Commission
    ignored their objections to reopening the record is likewise
    unavailing. They are correct that despite acknowledging their
    opposition to reopening the record in the 2018 Order, see 2018
    Order, 164 F.E.R.C. ¶ 61,035 at P 11, the Commission did not
    address their arguments. Nonetheless, the 2019 Order makes
    clear that these comments were not significant. As the
    Commission explained there, it decided to grant rehearing of
    the 2016 Order based on reconsideration of the existing record
    and the parties’ arguments. 2019 Order, 166 F.E.R.C. ¶ 61,161
    at P 41. Although the Commission granted the motion to
    reopen the record, no basis is offered for the court to question
    the Commission’s statement that it “did not rely on the PJM
    White Paper in granting rehearing of the April 2016 Order,” 
    id.
    18
    at P 42, which is the only decision New Jersey Agencies
    challenge.
    Accordingly, we deny the petitions for review.