Shafer & Freeman Lakes Environmental Conservation Corporation v. FERC ( 2021 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued October 5, 2020                 Decided March 26, 2021
    No. 19-1066
    SHAFER & FREEMAN LAKES ENVIRONMENTAL CONSERVATION
    CORPORATION, ET AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    NORTHERN INDIANA PUBLIC SERVICE COMPANY AND
    UNITED STATES DEPARTMENT OF THE INTERIOR,
    INTERVENORS
    On Petition for Review of Orders of the
    Federal Energy Regulatory Commission
    Robert O. Fleming Jr. argued the cause for petitioners.
    With him on the briefs was Alan I. Saltman.
    Elizabeth E. Rylander, Attorney, Federal Energy
    Regulatory Commission, argued the cause for respondent.
    With her on the brief were David L. Morenoff, Acting General
    Counsel at the time the brief was filed, and Robert H. Solomon,
    Solicitor. Robert M. Kennedy Jr. and Beth G. Pacella,
    Attorneys, entered appearances.
    2
    Justin D. Heminger, Attorney, U.S. Department of Justice,
    argued the cause for intervenor U.S. Department of the Interior
    in support of respondent. With him on the brief were Jeffrey
    Bossert Clark, Assistant Attorney General at the time the brief
    was filed, Eric Grant, Deputy Assistant Attorney General at the
    time the brief was filed, and Robert J. Lundman, Attorney.
    Charles R. Sensiba, J. Houston Shaner, Michael Bryan
    Little, and Angela J. Levin were on the brief for intervenor
    Northern Indiana Public Service Company, LLC in support of
    respondent.
    Before: ROGERS and MILLETT, Circuit Judges, and
    SENTELLE, Senior Circuit Judge.
    Opinion for the Court filed by Circuit Judge MILLETT.
    MILLETT, Circuit Judge: In the dry summer of 2012,
    scientists from the United States Fish and Wildlife Service
    discovered that endangered mussels were dying on the banks
    of the Tippecanoe River in northwest Indiana. The Service
    placed responsibility on the upstream Oakdale Dam, which
    significantly restricts the flow of water downstream in order to
    generate hydroelectricity and to create a lake behind the dam.
    In the ensuing years, the Service worked with the dam operator
    to develop new procedures that would require the dam to
    release more water during drought periods. After a lengthy
    process of interagency cooperation and public dialogue, these
    new procedures were approved by the Federal Energy
    Regulatory Commission, which is the federal agency with
    licensing authority over hydroelectric dams on federally
    regulated waters.
    Concerned about these changes to the dam’s operations,
    several local governmental entities and a non-profit
    3
    organization have petitioned for review of both the
    Commission’s decision and the Fish and Wildlife Service’s
    Biological Opinion upon which the Commission relied. We
    conclude that many of the petitioners’ challenges to the validity
    of the Biological Opinion were not raised on rehearing before
    the Commission and so are not properly before us. We
    otherwise find no error in the agencies’ expert scientific
    analyses. But we hold that the agencies failed to adequately
    explain why the new dam procedures do not violate a
    regulation prohibiting the Fish and Wildlife Service from
    requiring more than “minor” changes to the Commission’s
    proposal for dam operations. Because vacating the agencies’
    decisions would subject the dam operator to contradictory legal
    obligations imposed by separate agencies, we grant the petition
    in part, deny the petition in part, dismiss the petition in part,
    and remand to the Commission without vacatur for further
    proceedings consistent with this opinion.
    I
    A
    The Endangered Species Act instructs the Secretary of the
    Interior and the Secretary of Commerce to make a list of all
    species that are either “endangered” or “threatened[.]” 
    16 U.S.C. § 1533
    . The Act then forbids “any person” to “harass,
    harm, pursue, hunt, shoot, wound, kill, trap, capture, or collect”
    any endangered species—a set of prohibited acts collectively
    referred to as “take.”       
    Id.
     §§ 1532(19), 1538(a)(1)(B).
    Violation of this prohibition can lead to civil and criminal
    liability. Id. § 1540.
    The Act also imposes specific responsibilities on all other
    federal agencies. See 
    16 U.S.C. § 1536
    . As relevant here,
    before a federal agency can grant a license or permit to a private
    party, the agency must ensure that its action is “not likely to
    4
    jeopardize the continued existence of any endangered species
    or threatened species or result in the destruction or adverse
    modification of [the critical] habitat of such species[.]” 
    Id.
    § 1536(a)(2).1 To give effect to that obligation, the Act creates
    a system of “[i]nteragency cooperation,” in which the federal
    agency proposing to act (known as the “action agency”) must
    “consult” with one of the two expert wildlife agencies—the
    Fish and Wildlife Service (which is part of the Department of
    the Interior) or the National Marine Fisheries Service (which is
    within the Department of Commerce)—whenever it is
    contemplating a project that might affect a listed species. Id.
    § 1536(a)(3); see City of Tacoma v. FERC, 
    460 F.3d 53
    , 75
    (D.C. Cir. 2006).         This consultation process “reflects
    Congress’s awareness that [those] expert agencies * * * are in
    the best position to make discretionary factual determinations
    about whether a proposed agency action will create a problem
    for a listed species and what measures might be appropriate to
    protect the species.” City of Tacoma, 
    460 F.3d at 75
    .
    While the consultation process can take a variety of forms,
    the action agency often performs a preliminary review to
    determine whether the proposed action could affect any listed
    species. See 
    50 C.F.R. § 402.14
    (a); see also 
    16 U.S.C. § 1536
    (c); 
    50 C.F.R. §§ 402.10
    –402.13. If the action agency
    determines—and the wildlife agency concurs—that no listed
    species or critical habitats are likely to be adversely affected,
    then no formal consultation is required.             
    50 C.F.R. § 402.14
    (b)(1). But if either the action agency or the wildlife
    agency concludes that the proposed action “may affect” a listed
    1
    The phrase “jeopardize the continued existence of” means “to
    engage in an action that reasonably would be expected, directly or
    indirectly, to reduce appreciably the likelihood of both the survival
    and recovery of a listed species in the wild by reducing the
    reproduction, numbers, or distribution of that species.” 
    50 C.F.R. § 402.02
    .
    5
    species or its critical habitat, then a formal consultation begins.
    
    Id.
     § 402.14(a).
    That interagency process culminates in the wildlife agency
    issuing a “biological opinion.” See 
    16 U.S.C. § 1536
    (b); 
    50 C.F.R. § 402.14
    . A Biological Opinion is a document in which
    the wildlife agency comprehensively examines the proposed
    action’s anticipated effects on listed species and critical habitat.
    See 
    16 U.S.C. § 1536
    (b)(3)(A); 
    50 C.F.R. § 402.14
    (h). In
    particular, the wildlife agency must give its opinion on whether
    the proposed action is “likely to jeopardize the continued
    existence of [a listed] species or result in the destruction or
    adverse modification of [critical] habitat”—that is, whether the
    action would violate the Endangered Species Act. See 
    16 U.S.C. § 1536
    (a)(2); 
    50 C.F.R. § 402.14
    (h)(1)(iv). If the
    wildlife agency concludes that the action is likely to jeopardize
    the continued existence of a listed species, its Biological
    Opinion must provide the action agency with “reasonable and
    prudent alternatives” (if any) to the proposed action that would
    prevent such harm and avoid a violation of the Act. See 
    50 C.F.R. § 402.14
    (h)(1)(iv)(A), (h)(2). On the other hand, if the
    wildlife agency concludes that the proposed action is not likely
    to jeopardize the continued existence of any listed species, the
    wildlife agency issues a “no jeopardy” Biological Opinion,
    which gives the action agency a green light to proceed
    consistent with the Endangered Species Act. See 
    50 C.F.R. § 402.14
    (h)(1)(iv)(B).
    Even if the proposed action will not “jeopardize the
    continued existence” of a listed species, it may still cause some
    harm to the species. That type of harm is referred to as
    “incidental take.” See 
    50 C.F.R. § 402.14
    (i). When such harm
    is reasonably certain to occur, the wildlife agency must include
    an “Incidental Take Statement” as part of its Biological
    Opinion.       See 
    16 U.S.C. § 1536
    (b)(4); 50 C.F.R.
    6
    § 402.14(g)(7), (i). As relevant here, the Incidental Take
    Statement (i) specifies the extent of the anticipated take,
    (ii) identifies any “reasonable and prudent measures” that the
    wildlife agency considers “necessary or appropriate to
    minimize such impact,” and (iii) sets forth detailed “terms and
    conditions” that the action agency or licensed private party
    must undertake to implement those reasonable and prudent
    measures. 
    16 U.S.C. § 1536
    (b)(4); see also 
    50 C.F.R. § 402.14
    (i). Most relevantly for this case, the Fish and Wildlife
    Service (“Service”) regulations provide that the “reasonable
    and prudent measures” in an Incidental Take Statement “cannot
    alter the basic design, location, scope, duration, or timing of the
    action and may involve only minor changes” to the proposed
    federal agency action. 
    50 C.F.R. § 402.14
    (i)(2).
    So long as the action agency and private parties implement
    the “reasonable and prudent measures” and the associated
    “terms and conditions[,]” the Incidental Take Statement
    provides a safe harbor from any civil or criminal liability
    associated with incidental take. See 
    16 U.S.C. § 1536
    (o)(2);
    Sierra Club v. United States Army Corps of Eng’rs, 
    803 F.3d 31
    , 36 (D.C. Cir. 2015).
    Once the wildlife agency has issued its Biological Opinion
    (including any Incidental Take Statement), the action agency
    must “determine whether and in what manner to proceed with
    the action in light of its [
    16 U.S.C. § 1536
    ] obligations and the
    Service’s biological opinion.” See 
    50 C.F.R. § 402.15
    (a). The
    Supreme Court has observed that, while the Biological Opinion
    “theoretically serves an advisory function, in reality it has a
    powerful coercive effect on the action agency.” Bennett v.
    Spear, 
    520 U.S. 154
    , 169 (1997) (formatting modified). That
    is because the action agency and private parties are shielded
    from civil and criminal liability only if they comply with the
    wildlife agency’s recommendations. “The action agency is
    7
    technically free to disregard the Biological Opinion and
    proceed with its proposed action, but it does so at its own peril
    (and that of its employees)[.]” 
    Id. at 170
    .
    B
    The Federal Power Act gives the Federal Energy
    Regulatory Commission (“Commission”) responsibility for
    licensing the construction, maintenance, and operation of
    hydroelectric projects, including dams, on waters subject to
    federal jurisdiction. See 
    16 U.S.C. § 797
    (e). 2 When deciding
    whether to issue a license to a hydropower project, the
    Commission not only must consider “the power and
    development purposes for which licenses are issued,” but also
    must “give equal consideration to the purposes of energy
    conservation, the protection, mitigation of damage to, and
    enhancement of, fish and wildlife (including related spawning
    grounds and habitat), the protection of recreational
    opportunities, and the preservation of other aspects of
    environmental quality.” 
    16 U.S.C. § 797
    (e); see also 
    16 U.S.C. § 803
    (a)(1)–(2) (projects must be “best adapted to a
    comprehensive plan” for waterway uses); United States Dep’t
    of Interior v. FERC, 
    952 F.2d 538
    , 544 (D.C. Cir. 1992). Once
    issued, licenses can be altered “only upon mutual agreement
    2
    Congress’s jurisdiction over certain waters derives from its
    authority to regulate interstate and foreign commerce under the
    Constitution. See U.S. CONST. Art. I, § 8, cl. 3; Federal Power
    Comm’n v. Oregon, 
    349 U.S. 435
    , 442 (1955). In particular, the
    Federal Power Act requires the Commission to regulate dams on
    “navigable waters,” which means waters “used or suitable for use”
    for transporting people or property in interstate or foreign commerce.
    See 
    16 U.S.C. §§ 796
    (8), 817(1); Turlock Irrigation Dist. v. FERC,
    
    786 F.3d 18
    , 26 (D.C. Cir. 2015).
    8
    between the licensee and the Commission after thirty days’
    public notice.” 
    16 U.S.C. § 799
    .
    Like all federal agency actions, Commission licensing
    decisions must comply with the Endangered Species Act’s
    requirement to avoid jeopardy to listed species. To that end,
    the Commission consults with that Act’s statutorily designated
    wildlife agencies when deciding whether to issue or amend
    licenses for hydroelectric facilities. See, e.g., City of Tacoma,
    
    460 F.3d at
    75–76.
    II
    A
    Two dams sit on the Tippecanoe River in northern Indiana.
    These dams use the flow of the river to generate electricity, and
    they also typically provide enough water to sustain two large
    reservoirs. The Norway Dam, built in 1923, creates a ten-mile-
    long reservoir called Lake Shafer. Further downstream, the
    Oakdale Dam, built in 1925, creates a reservoir of similar
    length called Lake Freeman. The dams are owned and operated
    by a privately owned utility company, the Northern Indiana
    Public Service Company LLC (“NIPSCO”).
    The lakes are centers of economic and recreational activity
    for the region. More than four thousand private lakefront
    properties surround the reservoirs, and the lakes support
    substantial boating, fishing, tourism, and related activities.
    For almost eighty years, the Commission took the position
    that the portion of the Tippecanoe River near the dams was not
    a navigable water for purposes of federal jurisdiction, and so
    the dams did not require a license from the Commission. See
    Northern Ind. Pub. Serv. Co., 
    12 FERC ¶ 61274
    , 61644 (1980).
    But in 2000, the agency changed course and determined that
    9
    the Norway Dam and Oakdale Dam portions of the Tippecanoe
    River constitute a navigable waterway within the federal
    government’s jurisdiction. Northern Ind. Pub. Serv. Co., 
    92 FERC ¶ 62258
    , 64378 (2000). In 2007, the Commission issued
    a 30-year license to NIPSCO to operate the two dams.
    Northern Ind. Pub. Serv. Co., 
    121 FERC ¶ 62009
    , at 1 (2007)
    (J.A. 92).
    As relevant here, that license required that NIPSCO
    operate the dams “in an instantaneous run-of-river mode.”
    Northern Ind. Pub. Serv. Co., 
    121 FERC ¶ 62009
    , at Article
    403 (J.A. 119). In this mode, NIPSCO must ensure that “the
    outflow from the Norway Dam approximates the sum of
    inflows to Lake Shafer and the outflow from the Oakdale Dam
    approximates the sum of inflows to Lake Freeman.” 
    Id.
     More
    specifically, the license required NIPSCO to prevent the water
    level of the lakes from fluctuating more than three inches above
    or below a target elevation. For Lake Freeman, that elevation
    is roughly 610 feet above sea level (technically, 612.45 feet
    NGVD). 
    Id.
     The license allowed deviation from this rule only
    during periods of “abnormal river conditions[,]” meaning
    abnormally high flows, not abnormally low flows. 
    Id.
    B
    In the summer of 2012, Indiana experienced an extreme
    drought, and water levels on the Tippecanoe River reached
    historic lows. Residents living along the stretch of the
    Tippecanoe downstream of the dams alerted the Indiana
    Department of Natural Resources that the river was drying up
    and large numbers of mussels were dying. That July, biologists
    from Indiana and the U.S. Fish and Wildlife Service surveyed
    the river over several days, and found “substantial numbers of
    fresh dead mussels [and] stranded live mussels[.]” J.A. 1056.
    Among the dead were numerous mussels listed as endangered
    10
    or threatened under the Endangered Species Act, including
    fanshell, clubshell, sheepnose, and rabbitsfoot mussels. See 
    16 U.S.C. § 1533
    .
    The Service determined that low water flow out of the
    dams was contributing to the mussel deaths. In the Service’s
    view, the way in which the dams were being operated caused
    less water to reach the lower Tippecanoe River than would
    reach it in the absence of the dams, and so the dams partially
    caused the mussel deaths in the dried-out river. The Service
    then wrote a letter to NIPSCO informing the company that it
    must increase water flow out of the Oakdale Dam or risk
    potential liability under the Endangered Species Act for “take”
    of listed mussels. Alternatively, the Service said, NIPSCO
    could try to avoid liability by demonstrating that the dams were
    “maintaining the ‘run of the river’ rate of discharge”—in other
    words, demonstrate that the dams had no effect on the flow of
    the river or the mussel deaths caused by insufficient water. See
    J.A. 143.
    NIPSCO opted to increase the water flow out of the
    Oakdale Dam. Over the subsequent years, NIPSCO continued
    to work with the Service to ensure that enough water was
    released from the dams to avoid killing mussels. This
    cooperation required NIPSCO to perform a regulatory
    balancing act: The increased releases that the Fish and Wildlife
    Service requested to protect the mussels forced the company to
    violate the Commission’s license requirement that the
    company maintain relatively stable lake elevations. To remedy
    the situation, NIPSCO sought and received variances from the
    Commission allowing temporary violations of the license’s
    water-level terms.
    In 2014, the Service devised a plan for protecting the
    Tippecanoe River mussels. As described in a “Technical
    11
    Assistance Letter” sent to NIPSCO, the Service suggested that
    NIPSCO could avoid liability under the Endangered Species
    Act by releasing enough water to mimic the natural run-of-river
    flow that would occur if the dams were not there. While
    recognizing that NIPSCO’s license from the Commission
    already required the company to operate the dams in what the
    Commission called “instantaneous run-of-river mode,”
    Northern Ind. Pub. Serv. Co., 
    121 FERC ¶ 62009
    , at Article
    403 (J.A. 119), the Service defined “run-of-river” operations
    differently in its new plan. See J.A. 212. Rather than focusing
    on keeping the lake levels steady, as the Commission had
    required, the Service advised NIPSCO to calculate the amount
    of water needed to approximate the natural flow of water out
    of the Oakdale Dam during low-flow conditions.
    The Service then calculated that, in the absence of the
    dams, more water would flow into the river downstream than
    entered it upstream because of the large watershed surrounding
    the downstream portions of the river. More specifically, the
    water flow directly beneath the Oakdale Dam under natural
    conditions would be 1.9 times the flow measured upstream of
    the dams (as measured at the Winamac gauge on the River).3
    To that end, the Service advised NIPSCO to release enough
    water during low-flow events so that the flow directly below
    the Oakdale Dam was 1.9 times the 24-hour daily average flow
    at the Winamac gauge. In addition, the Service instructed
    NIPSCO to cease electricity generation during low-flow
    events, because the Service concluded that engaging the dam’s
    3
    A watershed is, in essence, “a land area that channels rainfall
    and snowmelt to creeks, streams, and rivers, and eventually to
    outflow points such as reservoirs, bays, and the ocean.” NATIONAL
    OCEANIC AND ATMOSPHERIC ADMINISTRATION, What is a
    Watershed?       (Dec. 4, 2020), https://oceanservice.noaa.gov
    /facts/watershed.html (last visited March 23, 2021).
    12
    turbines caused large fluctuations in water flow that harmed
    mussels.
    C
    Two months later, NIPSCO sought permission from the
    Commission to implement the Service’s plan. Technically, this
    request came in the form of an application to amend the
    definition of “abnormal river conditions” in NIPSCO’s license.
    The proposed amendment removed the lower limit on the
    elevation of Lake Freeman during low-flow events, allowing
    the lake level to fall more than three inches below the target
    elevation.
    After the Commission opened the proceedings, a group of
    local entities (the “Coalition”) intervened to oppose the
    proposed amendment to NIPSCO’s license. The Coalition
    included the Shafer & Freeman Lakes Environmental
    Conservation Corporation, a local non-profit that owns much
    of the land beneath the lakes. It also included Carroll and
    White Counties and the City of Monticello, each of which
    encompasses or borders part of Lake Freeman. The Coalition
    argued that the dams do not alter the natural run of the
    Tippecanoe River, and that the Service’s formula for
    calculating river flow was “‘junk’ science[.]” J.A. 72, 80. In
    the Coalition’s view, the amendment would provide an
    “unnatural” benefit to the mussels by releasing more water
    from Lake Freeman than the Tippecanoe River would provide
    in its natural state. J.A. 45. In support, the Coalition submitted
    two reports from professors with expertise in hydrology.
    In practical terms, the Coalition was concerned that Lake
    Freeman could be drawn down “in excess of 12 feet,”
    preventing almost all recreational use of the lake, with
    concomitant effects on homeowners, local businesses, and
    tourism. J.A. 46. The Coalition also voiced concern that a
    13
    large drawdown could cause significant environmental and
    aesthetic harm to the lakes and lakeshore. For those reasons,
    the Coalition asked the Commission to deny the amendment
    application and to require NIPSCO to operate the dams as it
    previously had.
    As required by the National Environmental Policy Act
    (“NEPA”), 
    42 U.S.C. § 4332
    , the Commission conducted an
    environmental assessment analyzing the consequences of the
    proposed amendment. Draft Environmental Assessment for
    Non-Capacity Related Amendment to License: Norway-
    Oakdale Hydroelectric Project—FERC Project No. 12514-074
    (2015) (J.A. 362–522).             The Commission’s draft
    environmental assessment was released for public comment.
    The assessment evaluated three alternative courses of action:
    (1) a “no-action” alternative, in which the Oakdale Dam would
    continue operating without change under its current license;
    (2) NIPSCO’s “proposed alternative” to operate in accordance
    with the Fish and Wildlife Service’s guidance in the Technical
    Assistance Letter; and (3) the Commission’s “staff
    alternative,” which reflected a potential compromise position.
    Under the staff alternative, during periods of low flow,
    NIPSCO would cease diverting water for the generation of
    electricity, but would still be obligated to prevent Lake
    Freeman’s elevation from falling more than three inches below
    its target elevation.
    Citing its obligation under the Federal Power Act to
    balance wildlife conservation with other interests, the
    Commission proposed its “staff alternative” as the best option,
    reasoning that it would “avoid adverse effects from project
    operations on endangered mussels, while protecting the
    numerous resources of Lake Freeman that depend on stable
    lake levels.” J.A. 371, 449. The Commission also agreed with
    the Coalition’s experts that “[t]here are legitimate concerns”
    14
    with the Service’s approach to calculating water flow.
    J.A. 414.
    The Fish and Wildlife Service submitted comments on the
    draft that strongly opposed adoption of the Commission staff
    alternative, and defended the proposed NIPSCO amendment
    that incorporated the Service’s recommendation. The Service
    explained that the Commission staff alternative was
    “essentially the same” as the no-action status quo because the
    staff alternative maintained the status quo limits on lake level
    fluctuations, and so would continue to result in inadequate
    water flow for mussels. J.A. 528.
    The Commission’s final environmental assessment
    adhered to its original conclusion, rejecting the NIPSCO
    amendment and concluding that the Commission staff
    alternative best balanced the interests of mussels with those
    interests that depend on stable lake levels. The Commission
    added that its staff alternative would have no “new effects on
    environmental and socioeconomic resources associated with
    Lake Freeman,” and on that basis issued a Finding of No
    Significant Impact—a finding that, under NEPA, no further
    environmental review was necessary. J.A. 758. At the same
    time, the Commission acknowledged that, under the
    consultation provisions of the Endangered Species Act, 
    16 U.S.C. § 1536
    , it needed to obtain the Fish and Wildlife
    Service’s agreement that its staff alternative would not
    adversely affect endangered mussels.
    D
    Because the Service decidedly did not agree with the
    Commission’s conclusion, see J.A. 855, the two agencies
    entered into “formal consultation,” and the Service prepared a
    Biological Opinion. See 
    16 U.S.C. § 1536
    (a)(2), (b); 
    50 C.F.R. § 402.14
    . The Biological Opinion laid out the Service’s
    15
    scientific evaluation of the competing options and critiqued the
    reasoning underlying the staff alternative. For example, the
    Service noted that managing the dams to maintain lake level,
    as proposed by the staff alternative, historically had caused
    unnaturally extreme fluctuations in water flow below the dams
    that were harmful to mussels. J.A. 892–893. The Service also
    commented that, because NIPSCO rarely generates power from
    the dams during low flows, the staff alternative would produce
    minimal conservation benefits by merely prohibiting electricity
    generation during those low flows. J.A. 907. Nonetheless, the
    Service concluded that, under the governing Endangered
    Species Act standard, the staff alternative “is not likely to
    jeopardize the continued existence of the clubshell, fanshell,
    sheepnose, or rabbitsfoot mussels and is not likely to destroy
    or adversely modify designated critical habitat.” J.A. 914.
    That “no jeopardy” finding cleared the way for the
    Commission to proceed with the staff alternative.
    The Service then turned to the statutorily required analysis
    of incidental take, and concluded that the staff alternative
    would result in some incidental take of mussels. See 
    16 U.S.C. § 1536
    (b)(4). While this level of incidental take would not
    result in jeopardy to the species, the Service proposed a
    “reasonable and prudent measure” to “minimize impacts of
    incidental take[.]” J.A. 916. Specifically, the Service advised
    that NIPSCO should “restor[e] a more natural flow regime
    downstream of Oakdale Dam during low-flow periods” by
    “[a]dopt[ing] the alternative proposed by NIPSCO in its
    request for a license amendment and implement[ing] the
    Service [Technical Assistance Letter] of 2014[.]” J.A. 916.
    In other words, the “reasonable and prudent measure” to
    minimize incidental take from the staff alternative was to
    proceed with the approach to water-flow management
    originally recommended by the Service—that is, to maintain
    16
    water flow below the dam during low flows at 1.9 times the
    average daily flow at the Winamac gauge. Conditioned on
    those terms, the Service issued the necessary Incidental Take
    Statement, underscoring that the reasonable and prudent
    measure and associated terms and conditions were “non-
    discretionary, and must be undertaken by the [Commission] so
    that they become binding conditions of any grant or permit
    issued to NIPSCO, as appropriate, for the exemption” from
    civil and criminal liability under the Endangered Species Act
    to apply. J.A. 915.
    Both the Coalition and NIPSCO filed comments with the
    Commission on the Biological Opinion. The Coalition argued
    that (i) the Service’s “reasonable and prudent measure” was not
    based on the best available science; (ii) there would be no
    incidental take from the staff alternative; (iii) the “reasonable
    and prudent measure” exceeded the Service’s legal authority
    because it involved more than a “minor” change to the
    Commission’s proposal; and (iv) the Commission need not
    defer to the Service’s Opinion. J.A. 938–948. NIPSCO, for its
    part, expressed concern about “the clear conflicts between the
    Staff Alternative and the measures included in the [Biological
    Opinion] to address [Endangered Species Act] compliance[,]”
    and pleaded with the Commission and the Service to “continue
    to work together to find a solution” that would “provide
    regulatory certainty for NIPSCO going forward.” J.A. 927–
    928. NIPSCO stated that it “cannot be placed in the untenable
    position of choosing between inconsistent compliance
    requirements from two federal agencies.” J.A. 928.
    In June 2018, almost a year after receiving the Biological
    Opinion, the Commission issued its ruling. See Order
    Amending License, Approving Revised Operation and
    Compliance Plan, and Terminating Temporary Variance, 
    163 FERC ¶ 61212
     (2018) (J.A. 969–1013). The Commission
    17
    acknowledged that there was “a difference in opinion [between
    the two agencies] regarding how best to approximate run-of-
    river operations at the Oakdale development.” J.A. 984. The
    Commission reiterated its view that its own method was best,
    and described the Service’s approach as containing
    “inaccuracies” that would “provide greater flows than would
    otherwise occur naturally.” J.A. 984–985.
    But the Commission concluded that the Endangered
    Species Act “constrains [the Commission’s] discretion to
    implement staff’s recommended alternative.” J.A. 985. The
    Commission explained that, while it is required to balance a
    range of interests under the Federal Power Act, its obligations
    under the Endangered Species Act are “more narrowly focused
    on protecting threatened and endangered species.” J.A. 985.
    So while the Commission “might ordinarily prefer staff’s
    alternative to balance non-developmental and developmental
    uses under [the Federal Power Act], in this case the
    [Endangered Species Act] compels a different result.”
    J.A. 985. The Commission added that the risk of “civil and
    criminal penalties, including imprisonment” for actions not in
    compliance with an Incidental Take Statement weighed against
    the staff alternative. J.A. 985.
    In response to the Coalition’s arguments, the Commission
    acknowledged that it “must make an independent decision
    under the [Federal Power Act] as to what measures should be
    included in a license[.]” J.A. 988. But the Commission added
    that it is “unlikely to contradict the consulting agency’s
    recommendation in the absence of a showing that the biological
    opinion and the remainder of the record do not provide
    substantial evidence to support them”—a showing that the
    Coalition “has not made[.]” J.A. 988. While it had agreed with
    the Coalition’s experts, the Commission explained that its
    concerns with the Service’s scientific approach were “not
    18
    sufficient to lead us to reject [the Service’s] determination that
    additional flows are needed to protect listed species[,]” or that
    the staff alternative would result in incidental take. J.A. 988.
    The Commission also refused to “review the validity of the
    biological opinion, substituting our judgment for that of [the
    Service.]” J.A. 989. Rather, “a reviewing court, and not the
    Commission, must decide whether [the Service] considered the
    relevant factors and adequately explained its choices in the
    biological opinion.” J.A. 989. For its part, the Commission
    found it appropriate to rely on the Biological Opinion because
    it was “thorough,” and there was no evidence that it was so
    “fatally flawed” that the Commission would be unreasonable
    or arbitrary to credit its determinations. J.A. 989–990.
    Lastly, the Commission rejected the Coalition’s argument
    that the Service’s “reasonable and prudent measure” was
    contrary to regulation because it constituted a major, rather
    than a “minor” change to the project. Under 
    50 C.F.R. § 402.14
    (i)(2), the Service’s proposed reasonable and prudent
    measures, when included in an Incidental Take Statement, may
    not “alter the basic design, location, scope, duration, or timing”
    of the proposed agency action, and “may involve only minor
    changes.” The Commission concluded that the reasonable and
    prudent measure proposed by the Service was “designed to
    achieve the same purpose” as the staff alternative of
    approximating run-of-river flow and protecting mussels, and
    its adoption would not “change the * * * basic design, location,
    scope, duration, and timing” of the Commission staff
    alternative for river flow. J.A. 989. The Commission added
    that, “even if * * * the measure would result in a major
    change,” it would not reject the measure because it treats the
    implementation of reasonable and prudent measures as
    “nondiscretionary.” J.A. 989.
    19
    For those reasons, the Commission granted NIPSCO’s
    request for an amended license on the terms that NIPSCO and
    the Service had originally requested.
    E
    In July 2018, the Coalition filed a request for rehearing,
    which the Commission denied in January 2019. Order Denying
    Rehearing, 
    166 FERC ¶ 61030
     (2019) (J.A. 1021–1036).
    On March 15, 2019, the Coalition filed a petition for
    review in this court, seeking review of the Commission’s
    orders adopting the license amendment and denying rehearing.
    NIPSCO moved to intervene as a respondent. Subsequently, in
    the Coalition’s Statement of Issues, the Coalition indicated that
    it was also challenging the Service’s Biological Opinion as
    arbitrary and capricious and contrary to law. A week later, the
    Fish and Wildlife Service moved to intervene as a respondent,
    explaining that it had not known prior to the Statement of
    Issues that its own Biological Opinion was being challenged.
    This court granted both motions to intervene.
    III
    After intervening, the Fish and Wildlife Service filed a
    motion for leave to rely upon its own administrative record in
    defending the Biological Opinion against the Coalition’s
    arguments that the Biological Opinion violated the
    Administrative Procedure Act, 
    5 U.S.C. § 706
    , the Endangered
    Species Act, and the Service’s implementing regulations. The
    Coalition opposes the Service’s filing of its administrative
    record. We grant the Service’s motion.
    Under 16 U.S.C. § 825l(b), this court has jurisdiction to
    review not only the Commission’s order amending NIPSCO’s
    license, but also the Service’s Biological Opinion that was
    20
    prepared in the course of the Commission licensing
    proceeding. See American Rivers v. FERC, 
    895 F.3d 32
    , 45
    (D.C. Cir. 2018); City of Tacoma, 
    460 F.3d at 76
    ; see also City
    of Tacoma v. Taxpayers of Tacoma, 
    357 U.S. 320
    , 336 (1958).
    The Administrative Procedure Act, in turn, instructs courts to
    “review the whole record or those parts of it cited by a party”
    when reviewing agency action. 
    5 U.S.C. § 706
    . To do so, we
    necessarily must have before us the “whole record” for each of
    the agency actions we are asked to review. In this case, that
    means we must have not just the Commission’s administrative
    record, but also the record compiled by the Fish and Wildlife
    Service in preparing its Biological Opinion. See Bennett, 
    520 U.S. at 178
     (Biological Opinions are “final agency action”
    subject to review under the Administrative Procedure Act).
    The Coalition insists that “[t]he only agency action to be
    reviewed here is [the Commission’s] orders issuing and
    affirming an operating license amendment.” Coalition Br. 51.
    Not so. In its brief, the Coalition challenges both the
    Commission’s orders and the Service’s Biological Opinion.
    Coalition Br. 2–4. Each of those is an independent challenge
    to distinct agency actions resting on their own administrative
    records. See City of Tacoma, 
    460 F.3d at 75
    .
    Importantly, the Coalition has chosen to go beyond
    challenging just the reasonableness of the Commission’s
    reliance on the Biological Opinion. It challenges the merits of
    that Opinion itself. See Coalition Br. at 29 (“[The Service’s]
    Biological Opinion was arbitrary and capricious, an abuse of
    discretion, unsupported by substantial evidence, and not based
    on the best scientific and commercial data available[.]”).
    Because the Coalition seeks to challenge the Biological
    Opinion directly—and to have the benefit of a more rigorous
    standard of review than we would apply if the Coalition merely
    challenged the Commission’s reliance on the Opinion, see City
    21
    of Tacoma, 
    460 F.3d at
    75—then the Service must be allowed
    to defend its decision directly by relying on the record on which
    it made its decision. See Florida Power & Light Co. v. Lorion,
    
    470 U.S. 729
    , 743–744 (1985) (“The task of the reviewing
    court is to apply the appropriate APA standard of review to the
    agency decision based on the record the agency presents to the
    reviewing court.”). We cannot review either the validity of the
    Coalition’s objections to the Biological Opinion or the
    sufficiency of the Service’s analysis in a vacuum. 4
    IV
    The Coalition raises numerous challenges to the Fish and
    Wildlife Service’s scientific foundation for its Biological
    Opinion, and argues that those purported errors require
    invalidation of both the Biological Opinion and the
    Commission’s decisions relying on that Opinion. We lack
    jurisdiction to address several of the Coalition’s contentions
    because they were not raised in its petition for rehearing before
    the Commission. And we reject the remainder of the
    Coalition’s science-based arguments.
    A
    The Federal Power Act requires petitioners challenging a
    Commission decision to exhaust their administrative remedies
    by “set[ting] forth specifically [in an application for rehearing]
    the ground or grounds” on which the petitioner relies. 16
    U.S.C. § 825l(a). Giving force to that exhaustion requirement,
    the Act expressly limits judicial review to only those matters
    that were “urged before the Commission in the application for
    4
    There is no indication here that the Service, in introducing its
    own record, is seeking to rely on an ex post rationalization for its
    decision. Cf. Walter O. Boswell Mem’l Hosp. v. Heckler, 
    749 F.2d 788
    , 793 (D.C. Cir. 1984).
    22
    rehearing unless there is reasonable ground for failure so to
    do.” 
    Id.
     § 825l(b). Those requirements are jurisdictional, and
    this court’s review is “limited by the extent to which a
    petitioner objected ‘with specificity[.]’”     Indiana Util.
    Regulatory Comm’n v. FERC, 
    668 F.3d 735
    , 739 (D.C. Cir.
    2012) (quoting Allegheny Power v. FERC, 
    437 F.3d 1215
    ,
    1220 (D.C. Cir. 2006)).
    Because exhaustion under the Federal Power Act is
    jurisdictional, this court must assure itself that this requirement
    has been satisfied regardless of whether the parties raise an
    objection. Wabash Valley Power Ass’n v. FERC, 
    268 F.3d 1105
    , 1114 (D.C. Cir. 2001). In that respect, a threshold issue
    in this case is whether the Coalition’s petition to the
    Commission for rehearing adequately put the Commission on
    notice that the Coalition was challenging not only the
    Commission’s reliance on the Biological Opinion, but also the
    substantive validity of the Biological Opinion itself. See Maine
    Council of Atlantic Salmon Fed’n v. FERC, 741 F. App’x 807,
    807–808 (D.C. Cir. 2018) (no jurisdiction where petitioners
    “failed to raise their objections to the [Biological Opinion’s]
    validity in their application for rehearing of [the
    Commission’s] order”).
    We conclude that the Coalition’s rehearing application
    sufficiently raised the validity of the Biological Opinion itself.
    The Coalition’s rehearing application argued that the Service
    had used a “flawed foundation” in its scientific analysis, that
    the Coalition’s experts had “discredited” the Service’s
    methodology, and that the Commission had erred by “blindly
    accept[ing] the [Biological Opinion] as [representing the] ‘best
    science[.]’” J.A. 1016. Tellingly, the Commission itself
    understood the Coalition to be challenging the Biological
    Opinion directly, stating that “[t]he Protest Coalition asks the
    Commission to review the validity of the biological opinion
    23
    and substitute our judgement for that of [the Service.]”
    J.A. 1031. While the Commission’s consideration of an issue
    cannot itself cure a petitioner’s failure to raise that issue on
    rehearing, see Indiana Util. Regulatory Comm’n, 
    668 F.3d at 739
    , the Commission’s statement provides strong evidence that
    the Coalition’s rehearing application put the Commission on
    notice of the issue, see Columbia Gas Transmission Corp. v.
    FERC, 
    404 F.3d 459
    , 462 (D.C. Cir. 2005).
    But while the Coalition adequately indicated that the
    Biological Opinion was a target of its objections, it failed to
    raise on rehearing many of the specific objections on which it
    now relies. In particular, the Coalition argues before this court
    that: (i) the Service improperly “assumed” that the mussel
    deaths below Oakdale Dam in 2012 constituted “take” caused
    by the dams, and failed to consider the presence of dead
    mussels upstream of the dams, Coalition Br. 29–32; (ii) the
    Service wrongly excluded data from 2010 when evaluating
    certain data related to river flows, Coalition Br. 40–41; and
    (iii) the Service used an “improperly large exponent” when
    creating its formula for calculating natural water flow on the
    Tippecanoe River, Coalition Br. 41–42. None of those
    arguments was raised at all, let alone “with specificity,” in the
    Coalition’s petition for rehearing before the Commission. See
    Indiana Util. Regulatory Comm’n, 
    668 F.3d at 739
    ; J.A. 1014–
    1019.
    The Coalition tries to salvage its challenges by pointing to
    the statement in its petition for rehearing that “the protocols
    contained in the [Technical] Assistance Letter were not based
    on best science.” Coalition Reply Br. 9–10; see J.A. 1015. But
    exhaustion is not a Rorschachian enterprise in which the
    Commission is expected to espy specific objections from such
    vague and formless assertions. See Public Serv. Elec. & Gas
    Co. v. FERC, 
    485 F.3d 1164
    , 1170 (D.C. Cir. 2007) (a “single
    24
    opaque sentence” is insufficient to preserve an argument);
    Connecticut Dep’t of Pub. Util. Control v. FERC, 
    593 F.3d 30
    ,
    36 (D.C. Cir. 2010) (no jurisdiction to address particular
    arguments when the petitioners had raised the issue only “in a
    general way”). For that reason, we lack jurisdiction to review
    the Coalition’s unexhausted arguments.
    B
    The Coalition challenges the scientific basis of the Fish
    and Wildlife Service’s new dam operation procedures. But the
    Service’s analysis of the relevant science and record
    comfortably passes administrative review.
    1
    We must uphold the Biological Opinion, as well as the
    Commission’s licensing decision based on it, unless either
    decision was “arbitrary and capricious” or unsupported by
    substantial evidence. 
    5 U.S.C. § 706
    (2); see City of Tacoma,
    
    460 F.3d at
    75–76. Under that standard, we are “not to ask
    whether a regulatory decision is the best one possible or even
    whether it is better than the alternatives.” FERC v. Electric
    Power Supply Ass’n, 
    136 S. Ct. 760
    , 782 (2016). Instead, we
    will vacate the decision only if the agency has “relied on factors
    which Congress has not intended it to consider, entirely failed
    to consider an important aspect of the problem, offered an
    explanation for its decision that runs counter to the evidence
    before the agency, or is so implausible that it could not be
    ascribed to a difference in view or the product of agency
    expertise.” Motor Vehicle Mfrs. Ass’n of U.S., Inc. v. State
    Farm Mut. Auto. Ins. Co., 
    463 U.S. 29
    , 43 (1983). The agency
    must articulate “a rational connection between the facts found
    and the choice made.” 
    Id.
     (quoting Burlington Truck Lines v.
    United States, 
    371 U.S. 156
    , 168 (1962)).
    25
    Under the Endangered Species Act, both the Fish and
    Wildlife Service and the Commission are required to “use the
    best scientific and commercial data available” when making
    their respective decisions. 
    16 U.S.C. § 1536
    (a)(2); 
    50 C.F.R. § 402.14
    (g)(8). This means that the agency “may not base its
    [decisions] on speculation or surmise or disregard superior
    data[.]” Building Indus. Ass’n of Superior Cal. v. Norton, 
    247 F.3d 1241
    , 1246–1247 (D.C. Cir. 2001). But when the science
    is uncertain, courts must “proceed with particular caution,
    avoiding all temptation to direct the agency in a choice between
    rational alternatives.” American Wildlands v. Kempthorne,
    
    530 F.3d 991
    , 1000–1001 (D.C. Cir. 2008) (internal quotation
    omitted). In other words, “we review scientific judgments of
    the agency ‘not as a chemist, biologist, or statistician that we
    are qualified neither by training nor experience to be, but as a
    reviewing court exercising our narrowly defined duty of
    holding agencies to certain minimal standards of rationality.’”
    Troy Corp. v. Browner, 
    120 F.3d 277
    , 283 (D.C. Cir. 1997)
    (quoting Ethyl Corp. v. EPA, 
    541 F.2d 1
    , 36 (D.C. Cir. 1976)
    (en banc)).
    2
    At the outset, the Coalition argues that the Service
    personnel who worked on the Biological Opinion lacked
    hydrological expertise and that the Service’s scientific
    conclusions are therefore undeserving of deference. That is
    incorrect. The Service’s Biological Opinion was based upon
    both hydrology and biology, and it is undisputed that the
    Service personnel had relevant expertise in biology. The
    record also demonstrates that the Service consulted
    hydrologists as part of its decision-making process. The
    Service’s judgment accordingly merits “the deference
    traditionally given to an agency when reviewing a scientific
    26
    analysis within its area of expertise[.]” Appalachian Power
    Co. v. EPA, 
    135 F.3d 791
    , 802 (D.C. Cir. 1998).
    3
    The Coalition’s central scientific complaint is that, in its
    view, the Service wrongly relied on a method of river-flow
    calculation called “linear scaling.” The theory of linear scaling
    holds that, in a comparatively homogeneous landscape, a
    river’s flow at a given point is correlated linearly to the size of
    the river’s watershed at that point. In other words, if a river
    downstream at point B has a total watershed three times the size
    of the watershed upstream at point A, then the river’s flow rate
    at point B will be three times the flow rate at point A.
    As applied here, NIPSCO would take note of the
    Tippecanoe River’s flow rate over a 24-hour period upstream
    of the dam at a place called the Winamac gauge. NIPSCO
    would then release enough water out of the Oakdale Dam such
    that the flow rate directly beneath the dam was 1.9 times the
    24-hour daily average flow rate at the Winamac gauge. That
    multiplier reflects the Service’s determination that the
    Tippecanoe’s watershed at the Oakdale Dam is 1.9 times the
    size of the river’s watershed at the Winamac gauge. In the
    Service’s judgment, linear scaling in this manner is the
    soundest available method for guaranteeing that the water flow
    out of the Oakdale Dam represents the “natural” flow of the
    river during low-flow periods, including with respect to the
    natural water flow’s effects on mussels.
    The Coalition objects to the Service’s reliance on linear
    scaling. In its view, the better method for ensuring “natural”
    flow rates on the Tippecanoe River is not linear scaling, but
    instead keeping lake levels relatively constant. If the lakes are
    not gaining any elevation, the argument goes, then water is
    leaving the lakes at more or less the same rate as it is entering
    27
    them—that is, the “natural” run-of-river flow. The Coalition
    contends more specifically that linear scaling is an
    inappropriate scientific tool for managing the flow out of a dam
    on a day-to-day basis, especially during low flows. For
    instance, Robert Criss, one of the Coalition’s hydrology
    experts, opined that while linear scaling may be an appropriate
    method for measuring “long-term mean flows[,]” there is no
    basis for applying linear scaling to low flows on an hourly or
    daily basis. J.A. 238, 242. In Dr. Criss’s view, linear scaling’s
    predictive approach does not work well in this context because
    low flows behave irregularly, and there are many events
    (interactions with groundwater, evaporation, localized rain
    bursts, withdrawals, additions) that can have an outsized
    impact on relative flow rates when flows are low.
    The record is replete with briefs, letters, scientific reports,
    and agency and expert opinions elaborating and debating the
    merits of the Service’s linear scaling methodology. But the
    only question before us is whether the Fish and Wildlife
    Service acted reasonably in its analysis and used the “best
    scientific and commercial data available,” see 
    16 U.S.C. § 1536
    (a)(2). The Service’s analysis passes muster.
    First, the agency offered a thorough and reasoned
    explanation of its scientific decision-making. The Service’s
    methodology is based on a “fundamental characteristic of
    watersheds”—namely, that a river’s flow “increases from the
    headwaters to the mouth of the river.” J.A. 1104; see J.A. 884
    (“[A]s watershed area increases, flow increases in most river
    systems[.]”). To use the Service’s example: “At its source
    downstream of Lake Itasca in Minnesota, the Mississippi River
    is 18 feet wide and can be waded—[whereas] about 1,300 miles
    downstream, south of Cairo, Illinois, the Mississippi is more
    than 3,500 feet wide.” J.A. 884–885.
    28
    In a letter to the Commission, the Service recognized that
    making predictions of precise daily fluctuations in flow rate is
    beyond the current capacity of science, but explained that
    “across all [low-flow] events and across the duration of those
    events, the Winamac-scaled flows provide the best, science-
    based estimate of what flows at Oakdale would be were the
    Norway and Oakdale Dams not present.” J.A. 1136 (emphasis
    in original; formatting modified).
    The Service substantiated its judgment by conducting its
    own analysis that demonstrated the relevance of linear scaling
    to addressing low flows on the Tippecanoe River. Upon
    evaluating the Tippecanoe River watershed, the Service
    determined that the landscape upstream at Winamac shared key
    drainage features with the landscape downstream at the
    Oakdale Dam.        This conclusion confirmed a “crucial
    assumption” underlying the application of linear scaling: The
    overall watershed is sufficiently homogeneous to permit
    estimation of downstream flow based on upstream flow.
    J.A. 1104. The Service also performed a statistical analysis,
    examining flow data from low-flow events on the Tippecanoe
    River over a period of fourteen-and-a-half years. The Service’s
    analysis showed that, during those low-flow events, flow
    between two points upstream scaled close to linearly. That is,
    downstream flows during those events were similar, on
    average, to what linear scaling would have predicted.
    J.A. 1136–1137. This finding provides support for the
    Service’s approach of applying linear scaling to low-flow
    events on the Tippecanoe River.
    The Service emphasized that a key benefit of its linear-
    scaling approach was to mimic not just the quantity of water
    being released from the Oakdale Dam but also the timing of
    those releases. “The central question is not whether the water
    that comes into the upper part of the Norway-Oakdale system
    29
    * * * ultimately finds its way out of Oakdale Dam, but whether
    or not that flow is interrupted, especially during low flow
    periods.” J.A. 1142. The Service explained that mussels can
    be adversely affected by “even relatively brief episodes of
    inadequate flow downstream.” J.A. 1142, 1157. And
    according to the Service, low-flow data between 2012 and 2014
    shows that, prior to the issuance of the Service’s Technical
    Assistance Letter, NIPSCO routinely permitted “dramatic” and
    “highly unnatural” fluctuations in flow out of the dam.
    J.A. 966–967. The Service’s recommendation aimed to avoid
    inadequate water flows by ensuring a particular amount of
    outflow during low-flow periods.
    Another advantage to linear scaling identified by the
    Service is that it can be implemented despite the technical
    constraints on dam management. As the Biological Opinion
    noted, the “1920s vintage equipment” of the dams makes it
    “impossible” to precisely match inflows to and outflows from
    Lake Freeman, given measurement “lag times” on the river and
    other practical difficulties. J.A. 1227. Indeed, the data show
    that summer flows out of the downstream Oakdale Dam have
    often been less than flows out of the upstream Norway Dam.
    J.A. 1229–1231. But concerns like lag time between gauges
    and localized weather events are “irrelevant” under the
    Service’s approach, because linear scaling “is developed to
    function as a general estimator and not a formula for predicting
    exact flows for each hour of each day of a specific [low-flow]
    event.” J.A. 1137.
    Second, the Service considered and provided a reasoned
    explanation for declining to rely just on maintaining the lake
    level, as the Coalition proposed. The Service produced a chart
    showing that, when the Oakdale Dam was operated to ensure
    stable lake levels during the 2012 drought, the flow rates below
    the Oakdale Dam fluctuated dramatically and erratically in
    30
    contrast to the relatively steady flow rates upstream. J.A. 1170.
    This showed that the lake-level method can result in highly
    variable flow rates that do not correspond to the natural flows
    upstream. The Service also observed that the water level in the
    lake had stayed relatively constant during prior droughts,
    whereas most lakes in Indiana had seen a water elevation drop,
    and it is “contrary to logic that keeping the two Tippecanoe
    Reservoirs level would not deprive water from other parts of
    the system during drought periods.”
    The Service added that keeping lake levels constant
    ignores all the other possible places where inflow water could
    end up rather than downstream, such as into the air through
    evaporation,     underground       through    discharges    into
    groundwater, or sideways on the surface through withdrawals
    from the lakes. The Service acknowledged that, “[h]ad we
    perfect information with respect to the losses from the lakes
    during dry periods, the temporal dimension of flow through this
    long and complex system, and the ability to precisely manage
    two 1920s era dams, estimating flow using lake level * * *
    might be appropriate.” J.A. 1177. But given that “we don’t
    know the water budget for this system[,] * * * we must estimate
    with the uncertainty that entails.” J.A. 1177.
    In sum, the Service concluded that “[n]either of the
    currently available methodologies (instantaneous run-of-river
    and linear scaling) allows us to precisely determine outflows
    from Oakdale Dam that will ‘match’ individual [low-flow]
    events.” J.A. 1147. But while “[n]either approach is perfect,”
    the Service reasonably concluded that its linear scaling
    approach represented “the best currently available science” for
    ensuring the natural flow of the river in a way that would
    “minimize take of mussels caused by the management of the
    Norway-Oakdale Complex.” J.A. 968, 1148.
    31
    The Service’s reasoned and thorough justification for its
    approach to managing the Tippecanoe River’s flow satisfies
    Administrative Procedure Act review. The agency explained
    the scientific basis for its decision, identified substantial
    evidence in the record buttressing its judgment, and responded
    to the Coalition’s concerns. The point of administrative review
    is not to settle the scientific debate, but to ensure that the
    Service “explain[ed] the assumptions and methodology used in
    preparing the model[.]” In re Polar Bear Endangered Species
    Act Listing & Section 4(d) Rule Litig.—MDL No. 1993, 
    709 F.3d 1
    , 13 (D.C. Cir. 2013) (brackets omitted). The Service
    acknowledged that linear scaling was an imperfect method of
    estimating river flow, but reasonably concluded that it was the
    best option and reflected the best science, given the
    demonstrated flaws in other approaches. “That a model is
    limited or imperfect is not, in itself, a reason to remand agency
    decisions based upon it.” Appalachian Power Co. v. EPA, 
    249 F.3d 1032
    , 1052 (D.C. Cir. 2001). That evidence-based
    explanation of the lake-level approach’s drawbacks further
    established that the Service’s approach accorded with the “best
    scientific * * * data available.” See Building Indus. Ass’n, 
    247 F.3d at
    1246–1247; see also Baltimore Gas & Elec. Co. v.
    NRDC, 
    462 U.S. 87
    , 103 (1983) (holding that “a reviewing
    court must generally be at its most deferential” when
    examining an agency decision made “within its area of special
    expertise, at the frontiers of science”).
    4
    Finally, because the Service acted reasonably in using a
    linear scaling methodology, the Commission too acted
    reasonably in relying on the Service’s resulting scientific
    judgments in its Biological Opinion. In reviewing the
    Commission’s granting of the amended license, “the critical
    question is whether the action agency’s reliance was arbitrary
    32
    and capricious, not whether the [Biological Opinion] itself is
    somehow flawed.” City of Tacoma, 
    460 F.3d at 75
     (emphasis
    in original). The Commission “satisf[ies] its obligations under
    the Act if a challenging party can point to no ‘new’
    information—i.e., information the [Service] did not take into
    account—which challenges the [Biological Opinion’s]
    conclusions.” 
    Id. at 76
    .
    Here, the Coalition has made no showing that the
    Commission overlooked new information or evidence in the
    record that had been unavailable to the Service. See J.A. 1031
    (Commission observing that “the Protest Coalition has not
    provided any additional information to lead us to question” the
    Service’s findings). While the Commission agreed with
    several of the Coalition’s critiques of the Service’s
    methodology, it concluded that these concerns were “not
    sufficient to lead us to reject [the Service’s] determination that
    additional flows are needed to protect listed species.” J.A. 988.
    This record demonstrates the reasonableness of that judgment.
    V
    The Coalition also presses a legal objection to the
    Biological Opinion and the Commission’s reliance on it. By
    regulation, the Fish and Wildlife Service requires that the
    “reasonable and prudent measures” it proposes to reduce
    incidental take cannot work more than a “minor change” in the
    proposed agency action. 
    50 C.F.R. § 402.14
    (i)(2). The
    Coalition contends that, by requiring water flow measures that
    accord with its linear scaling model and that can materially
    reduce the level of Lake Freeman during low-flow events, the
    Service’s reasonable and prudent measure is a major change,
    in violation of that regulation. Because neither the Service nor
    the Commission adequately explained why the Service’s
    reasonable and prudent measure qualified as a minor change,
    33
    we conclude that the agencies acted in an arbitrary manner, and
    we remand this issue for consideration by the agencies in the
    first instance.
    A
    Under the Endangered Species Act, the Fish and Wildlife
    Service can prescribe in its Incidental Take Statement
    “reasonable and prudent measures” that it considers “necessary
    or appropriate to minimize” the impacts of any anticipated
    incidental take of an endangered or threatened species. See 
    16 U.S.C. § 1536
    (b)(4)(ii). By regulation, the Service requires
    that any reasonable and prudent measures it proposes “cannot
    alter the basic design, location, scope, duration, or timing of the
    action and may involve only minor changes.” See 
    50 C.F.R. § 402.14
    (i)(2).
    The Service has provided guidance on the contours of a
    minor change and the types of actions that will exceed its
    bounds. In promulgating the minor change rule, the Service
    explained that “[s]ubstantial design and routing changes * * *
    are inappropriate in the context of incidental take statements
    because the action already complies with” the statutory
    prohibition against jeopardizing the continued existence of
    listed species. See Interagency Cooperation—Endangered
    Species Act of 1973, as Amended; Final Rule, 
    51 Fed. Reg. 19,926
    -01, 19,937 (June 3, 1986). While “[r]easonable and
    prudent measures were intended to minimize” incidental take,
    “Congress also intended that the action go forward essentially
    as planned.” 
    Id.
    The Service’s Consultation Handbook provides further
    detail. See U.S. FISH AND WILDLIFE SERV. & NATIONAL
    MARINE     FISHERIES     SERV.,     ENDANGERED     SPECIES
    CONSULTATION HANDBOOK (March 1998), https://www.fws
    .gov/endangered/esa-library/pdf/esa_section7_handbook.pdf.
    34
    The handbook explains that reasonable and prudent measures
    are designed to “minimiz[e] * * * the level of take.” 
    Id.
     at 4-
    53. The Service can include “only actions that occur within the
    action area,” such as “actions like education of employees
    about the species, reduction of predation, removal or avoidance
    of the species, or monitoring.” 
    Id.
     The agency emphasizes that
    “[t]he test for reasonableness is whether the proposed measure
    would cause more than a minor change to the project.” 
    Id.
     And
    the agency suggests that whether a change is “minor” may
    depend on the overall context: “[T]he effect of measures
    costing $10,000 or $100,000 may be critically significant for a
    single family boat dock, but minor for a multi-million dollar
    development complex.” Id.; see also Westlands Water Dist. v.
    United States Dep’t of Interior, 
    376 F.3d 853
    , 876 (9th Cir.
    2004) (holding that measures that would “likely have broad
    system-wide effects” in the Central Valley Water Project and
    require “new, significant action * * * cannot be considered to
    be a minor change”).
    B
    1
    In this case, the Commission adopted its staff alternative
    as the preferred action in its environmental assessment. That
    approach provided that, during low-flow periods, NIPSCO
    would cease generation but would continue to operate the
    Oakdale Dam to maintain a constant elevation for Lake
    Freeman. The Fish and Wildlife Service concluded that plan
    would not jeopardize endangered mussels. But the Service
    then required, as a reasonable and prudent measure designed to
    avoid incidental take, that NIPSCO instead use linear scaling
    to mimic natural flows during low-flow periods. Unlike the
    staff alternative, that approach would allow NIPSCO to draw
    down Lake Freeman during low-flow periods.
    35
    It is unclear whether the Service’s reasonable and prudent
    measure in this case qualifies as only a minor change within the
    meaning of 
    50 C.F.R. § 402.14
    (i)(2). Yet nowhere in its record
    or the record before the Commission did the Service analyze
    whether its proposal satisfied its own governing regulation. An
    agency errs if it wholly fails to address a “significant challenge
    to the rationality of its decision[.]” Darrell Andrews Trucking,
    Inc. v. Federal Motor Carrier Safety Admin., 
    296 F.3d 1120
    ,
    1135 (D.C. Cir. 2002); see also National Env’t. Dev. Ass’n’s
    Clean Air Project v. EPA, 
    752 F.3d 999
    , 1009 (D.C. Cir. 2014)
    (“[An] agency is not free to ignore or violate its regulations
    while they remain in effect.”) (quoting United States Lines, Inc.
    v. Federal Mar. Comm’n, 
    584 F.2d 519
    , 526 n.20 (D.C. Cir.
    1978)). By dropping the ball entirely in analyzing and
    explaining its compliance with the minor change rule, the
    Service failed to address a relevant and substantial matter
    bearing directly on its action. While we express no view on
    whether the Service’s use of linear scaling as a reasonable and
    prudent measure qualifies as a minor change on this record, the
    Service’s wholesale failure to analyze the question was
    arbitrary and capricious. See State Farm, 
    463 U.S. at 43
    .
    In this court (but nowhere in the records before us) the
    Service argues that the relevant comparator for identifying a
    “minor change” is not the Commission’s preferred staff
    alternative, but instead is NIPSCO’s original application for a
    license amendment. Interior Br. 43. And because NIPSCO
    itself had proposed to follow the Service’s guidance, “the
    reasonable and prudent measure made no change at all.”
    Interior Br. 44.
    The Service’s choice of comparator is incorrect. The
    action agency here is the Commission, not NIPSCO. After
    taking input from stakeholders and performing its own
    environmental analysis and studies, the Commission “selected”
    36
    its staff alternative as the “preferred option” for agency action.
    Importantly, that staff alternative is the action that the Service’s
    Biological Opinion analyzed and that the Service concluded
    would not result in jeopardy to listed species. By the same
    token, the Service’s study of incidental take and formulation of
    reasonable and prudent measures focused on the Commission
    staff alternative. Indeed, it would make no statutory sense for
    the incidental take analysis to use as its baseline operations that
    the action agency was not intending to undertake. See 
    16 U.S.C. § 1536
    (b)(4) (Incidental Take Statement must include
    reasonable and prudent measures “that the Secretary considers
    necessary or appropriate to minimize” incidental take resulting
    from “agency action”).
    2
    Unlike the Service, the Commission addressed whether the
    Service’s reasonable and prudent linear scaling measure ran
    afoul of the “minor change” regulation. But the Commission’s
    rationale fell short. The Commission said that the Service’s
    reasonable and prudent measure was only a minor change
    because the Service’s approach was “designed to achieve the
    same purpose—to approximate run-of-river flow and protect
    downstream mussel populations.” J.A. 989. While it may be
    relevant for the agency to consider whether a reasonable and
    prudent measure is consistent with the aims of the proposed
    agency action, “achiev[ing] the same purpose” cannot be the
    sole test of whether a change is “minor.” Purposes can be
    achieved in many ways, and at greater or lesser costs. For
    example, destroying the dam entirely would presumably also
    “approximate run-of-river flow and protect downstream
    mussel populations[.]” J.A. 989. But such a measure could not
    plausibly be labeled “minor.”
    37
    The Commission also reasoned, in the alternative, that
    even if the measure constituted more than a minor change, “we
    would not reject it, because we treat the implementation of a
    reasonable and prudent measure as nondiscretionary.”
    J.A. 989. In the normal course, the Commission could sensibly
    treat proposed reasonable and prudent measures as
    nondiscretionary, given the “powerful coercive effect” of
    Incidental Take Statements issued by the Service. See Bennett,
    
    520 U.S. at 169
    . But here, the Service’s complete failure to
    address an important issue was apparent on the face of the
    Biological Opinion. See City of Tacoma, 
    460 F.3d at 75
     (the
    Commission acts arbitrarily by relying on a “facially flawed”
    Biological Opinion). And since the license amendment granted
    by the Commission incorporated the reasonable and prudent
    measure, the Service’s failure to adequately support that
    reasonable and prudent measure infects the license amendment
    as well.
    Because of the errors by both the Service and the
    Commission in analyzing whether the Service’s reasonable and
    prudent measure qualified as “minor,” we remand for a
    reasoned explanation by the Service of its “minor change”
    regulation’s application. That explanation is necessary before
    the Commission can reasonably rely on the Biological Opinion
    in amending NIPSCO’s license to incorporate that measure.
    VI
    NIPSCO argues that the appropriate remedy for any
    agency error in this case is to remand without vacating either
    the Incidental Take Statement or the Commission’s orders.
    NIPSCO explains that if the Incidental Take Statement were
    vacated, NIPSCO would lose the legal protection from
    Endangered Species Act liability that its compliance with that
    Statement currently provides. And if the Commission’s orders
    38
    are vacated, NIPSCO will be required to revert to maintaining
    Lake Freeman at a stable elevation, trapping it once again
    between the Scylla and Charybdis of violating its Commission
    license or violating the Endangered Species Act.
    We agree with NIPSCO that remand without vacatur is
    warranted. See Humane Soc’y of U.S. v. Zinke, 
    865 F.3d 585
    ,
    614 (D.C. Cir. 2017) (looking to the seriousness of the
    deficiencies in the agency action and the likely disruptive
    consequences of vacatur); Allied-Signal, Inc. v. United States
    Nuclear Regulatory Comm’n, 
    988 F.2d 146
    , 150 (D.C. Cir.
    1993). It is possible that the Commission and the Service “can
    redress [their] failure of explanation on remand while reaching
    the same result.” Black Oak Energy, LLC v. FERC, 
    725 F.3d 230
    , 244 (D.C. Cir. 2013). And the conflicting regulatory
    obligations that vacatur would leave NIPSCO betwixt and
    between also favor remand without vacatur. Cf. Oglala Sioux
    Tribe v. United States Nuclear Regulatory Comm’n, 
    896 F.3d 520
    , 538 (D.C. Cir. 2018) (declining to vacate operating license
    when licensee had reasonably relied on agency ruling and faced
    grave economic harm if license were vacated).
    *****
    For all of the foregoing reasons, we grant in part, deny in
    part, and dismiss in part the Coalition’s petition for review, and
    remand this case to the Commission without vacatur for further
    proceedings consistent with this opinion.
    So ordered.
    

Document Info

Docket Number: 19-1066

Filed Date: 3/26/2021

Precedential Status: Precedential

Modified Date: 3/26/2021

Authorities (25)

allied-signal-inc-v-us-nuclear-regulatory-commission-and-the-united , 988 F.2d 146 ( 1993 )

Fed. Energy Regulatory Comm'n v. Elec. Power Supply Ass'n , 136 S. Ct. 760 ( 2016 )

Troy Corporation v. Carol M. Browner, Administrator, United ... , 120 F.3d 277 ( 1997 )

walter-o-boswell-memorial-hospital-v-margaret-m-heckler-secretary-of , 749 F.2d 788 ( 1984 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

Baltimore Gas & Electric Co. v. Natural Resources Defense ... , 103 S. Ct. 2246 ( 1983 )

westlands-water-district-san-luis-delta-mendota-water-authority-v-united , 376 F.3d 853 ( 2004 )

Darrell Andrews Trucking, Inc. v. Federal Motor Carrier ... , 296 F.3d 1120 ( 2002 )

ethyl-corporation-v-environmental-protection-agency-ppg-industries-inc , 541 F.2d 1 ( 1976 )

Building Industry Ass'n of Superior California v. Norton , 247 F.3d 1241 ( 2001 )

Pub Svc Elec & Gas v. FERC , 485 F.3d 1164 ( 2007 )

united-states-department-of-the-interior-v-federal-energy-regulatory , 952 F.2d 538 ( 1992 )

Appalachian Power Company v. Environmental Protection ... , 135 F.3d 791 ( 1998 )

Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )

City of Tacoma v. Federal Energy Regulatory Commission , 460 F.3d 53 ( 2006 )

American Wildlands v. Kempthorne , 530 F.3d 991 ( 2008 )

United States Lines, Inc. v. Federal Maritime Commission ... , 584 F.2d 519 ( 1978 )

Wabash Valley Power Ass'n v. Federal Energy Regulatory ... , 268 F.3d 1105 ( 2001 )

appalachian-power-company-v-environmental-protection-agency-commonwealth , 249 F.3d 1032 ( 2001 )

Burlington Truck Lines, Inc. v. United States , 83 S. Ct. 239 ( 1962 )

View All Authorities »