Sierra Club v. FERC ( 2023 )


Menu:
  •  United States Court of Appeals
    FOR THE DISTRICT OF COLUMBIA CIRCUIT
    Argued April 7, 2022                  Decided May 26, 2023
    No. 20-1512
    SIERRA CLUB, ET AL.,
    PETITIONERS
    v.
    FEDERAL ENERGY REGULATORY COMMISSION,
    RESPONDENT
    EQUITRANS, L.P., ET AL.,
    INTERVENORS
    Consolidated with 21-1040
    On Petitions for Review of Orders
    of the Federal Energy Regulatory Commission
    Benjamin A. Luckett argued the cause for petitioners. With
    him on the briefs were Elizabeth F. Benson and Julie
    Gantenbein.
    Matthew W.S. Estes, Attorney, Federal Energy Regulatory
    Commission, argued the cause for respondent. With him on
    the brief were Matthew R. Christiansen, General Counsel, and
    2
    Robert H. Solomon, Solicitor.       Scott R. Ediger, Attorney
    Advisor, entered an appearance.
    Jeremy C. Marwell argued the cause for respondent-
    intervenors Mountain Valley Pipeline, LLC, et al. With him
    on the joint brief were Matthew Eggerding, Matthew X.
    Etchemendy, James T. Dawson, Jennifer Leigh Flint Brough,
    Thomas Knight, Randall S. Rich, Valerie Layne Green,
    Charlotte Taylor, and James Olson.
    Before: SRINIVASAN, Chief Judge, MILLETT and WILKINS,
    Circuit Judges.
    Opinion for the Court filed by Chief Judge SRINIVASAN.
    SRINIVASAN, Chief Judge: For years, Mountain Valley
    Pipeline, LLC has been trying to build its eponymous Mountain
    Valley Pipeline through West Virginia and Virginia. In 2017,
    the Federal Energy Regulatory Commission first issued a
    certificate approving the project. Our court affirmed that order.
    But to build an interstate natural gas pipeline, a company often
    needs additional federal permits from agencies other than the
    Commission. Mountain Valley needed approvals from the
    Bureau of Land Management, Forest Service, Army Corps of
    Engineers, and Fish and Wildlife Service. While Mountain
    Valley initially obtained each of those additional permits, the
    United States Court of Appeals for the Fourth Circuit vacated
    all of them over time.
    The Commission responded with a series of follow-up
    orders. As Mountain Valley reacquired permits from the other
    agencies, the Commission extended the deadline for
    completing construction and authorized work to resume.
    Several environmental groups now petition for review of the
    Commission’s orders allowing the project to proceed.
    3
    We deny most of their claims and conclude that one is
    moot. But we agree with one of the claims: that the
    Commission inadequately explained its decision not to prepare
    a supplemental environmental impact statement addressing
    unexpectedly severe erosion and sedimentation along the
    pipeline’s right-of-way. While we grant the petitions for
    review in part on that ground, we do not vacate the
    Commission’s orders allowing work on the project to resume.
    Instead, we remand the orders without vacatur to enable the
    Commission either to prepare a supplemental environmental
    impact statement or to better explain why one is unnecessary.
    I.
    A.
    The Natural Gas Act authorizes the Federal Energy
    Regulatory Commission to regulate the interstate
    transportation of natural gas. 
    15 U.S.C. § 717
    . A company
    desiring to build a natural gas pipeline must first obtain a
    certificate of “public convenience and necessity” from the
    Commission. 
    Id.
     § 717f(c).
    The Commission’s certificate process incorporates review
    of proposed projects under the National Environmental Policy
    Act (NEPA), 
    42 U.S.C. § 4321
     et seq. See Food & Water
    Watch v. FERC, 
    28 F.4th 277
    , 282 (D.C. Cir. 2022). NEPA
    “declares a broad national commitment to protecting and
    promoting environmental quality, and brings that commitment
    to bear on the operations of the federal government.” Sierra
    Club v. FERC, 
    867 F.3d 1357
    , 1367 (D.C. Cir. 2017)
    (quotation marks and citation omitted). To that end, NEPA
    requires federal agencies to “identify the reasonable
    alternatives to a contemplated action and look hard at the
    4
    environmental effects of their decisions.” City of Bos.
    Delegation v. FERC, 
    897 F.3d 241
    , 246 (D.C. Cir. 2018)
    (alteration, quotation marks, and citation omitted).
    Agencies first prepare a draft environmental impact
    statement discussing the effects of the proposed action and of
    reasonable alternatives. 
    40 C.F.R. § 1502.9
    (b). A final
    environmental impact statement then accompanies an agency’s
    ultimate decision. 
    Id.
     § 1502.9(c). But an agency’s obligations
    under NEPA do not always end there. An agency must
    supplement its environmental analysis if “substantial changes
    to the proposed action” or “significant new circumstances or
    information” raise additional concerns about the action’s
    environmental impact. Id. § 1502.9(d)(1)(i)–(ii).
    B.
    In 2017, the Commission issued a certificate of public
    convenience and necessity for the Mountain Valley Pipeline.
    Order Issuing Certificates and Granting Abandonment
    Authority, Mountain Valley Pipeline, LLC, 
    161 FERC ¶ 61,043
    (Oct. 13, 2017) (Certificate Order), J.A. 86–221. The Pipeline
    would carry natural gas 303.5 miles across the Appalachian
    Mountains, from Wetzel County, West Virginia, to an
    interconnection with a compressor station in Pittsylvania
    County, Virginia. The Commission determined that Mountain
    Valley had shown market demand for the Pipeline based on
    five shipping contracts, known as precedent agreements,
    covering the Pipeline’s full capacity.
    In its final environmental impact statement, the
    Commission recognized that construction of the Pipeline
    would cause at least some soil erosion and sedimentation. To
    build the Pipeline, Mountain Valley would clear a 125-foot-
    wide corridor along the route, which would expose the soil to
    5
    wind and rain. The company would then dig or blast a trench
    in which to bury the Pipeline, dislodging more dirt for runoff.
    And much of the construction would occur near and across
    waterbodies. In those circumstances, sedimentation would be
    unavoidable.       But the Commission concluded in the
    environmental impact statement that control measures such as
    silt fences would minimize effects on waterbodies. And in the
    end, Mountain Valley planned to return the route to as close to
    its original state as practicable. The Certificate Order adopted
    the final environmental impact statement and declared the
    Pipeline “environmentally acceptable.” 
    Id. ¶ 308
    .
    When approving the project, the Commission also
    imposed conditions concerning when construction could begin
    and by when it needed to end. At the front end, the Certificate
    Order’s Environmental Condition 9 required Mountain Valley,
    “before commencing construction of any project facilities,” to
    submit “documentation that it has received all applicable
    authorizations required under federal law.” Certificate Order,
    App. C, Environmental Condition 9. At the back end, the
    Commission directed Mountain Valley to complete
    construction within three years, by October 13, 2020.
    Certificate Order ¶ 310.
    Several environmental groups petitioned our court for
    review of the Certificate Order. We rejected their challenge.
    Appalachian Voices v. FERC, Nos. 17-1271, 18-1002, 18-
    1175, 18-1177, 18-1186, 18-1216, 18-1223, 
    2019 WL 847199
    (D.C. Cir. Feb. 19, 2019) (per curiam). We concluded that the
    Commission had reasonably found a market need for the
    Pipeline based on the “precedent agreements for 100 percent of
    the Project’s capacity.” 
    Id. at *1
    . As for the order’s
    environmental analysis, we determined that the Commission
    had “adequately considered and disclosed erosion and
    sedimentation impacts on aquatic resources.” 
    Id. at *2
    .
    6
    C.
    In addition to obtaining a certificate from the Commission,
    a pipeline project must also “comply with all other federal,
    state, and local regulations not preempted by the [Natural Gas
    Act].” Dominion Transmission, Inc. v. Summers, 
    723 F.3d 238
    ,
    240 (D.C. Cir. 2013). Depending on a pipeline’s proposed
    route and potential impacts, permits from various other federal
    agencies might be needed.
    The Mountain Valley Pipeline would traverse more than
    three hundred waterbodies, requiring a permit from the Army
    Corps of Engineers. The Pipeline would also cut across
    Jefferson National Forest, requiring authorization from the
    Department of Interior’s Bureau of Land Management and the
    Department of Agriculture’s Forest Service. And the Pipeline
    would intersect with the habitats of endangered species,
    requiring the approval of the Fish and Wildlife Service.
    Mountain Valley obtained all of those necessary permits,
    and, pursuant to Environmental Condition 9, received the
    Commission’s authorization to break ground, which it did in
    February 2018. In the ensuing months, though, the United
    States Court of Appeals for the Fourth Circuit vacated each of
    the other federal permits.
    First, in July 2018, the Fourth Circuit vacated the
    authorizations from the Bureau of Land Management and the
    Forest Service allowing pipeline construction through
    Jefferson National Forest. Sierra Club, Inc. v. U.S. Forest
    Serv., 
    897 F.3d 582
     (4th Cir. 2018). The Commission initially
    responded with a stop work order due to the possibility that the
    Bureau of Land Management and Forest Service might require
    the Pipeline to follow a different route through the national
    7
    forest. Within a few weeks, though, the Commission allowed
    construction to resume along most of the Pipeline’s route. The
    Commission reasoned that completing construction and
    restoration work on non-federal lands would best serve the
    environment. Still, the Commission continued to prohibit
    construction within a 25-mile “exclusion zone” encompassing
    the crossing of the national forest and the adjacent watersheds.
    The Fourth Circuit subsequently set aside Mountain
    Valley’s verification from the Army Corps of Engineers. There
    are two ways for Mountain Valley to obtain approval from the
    Army Corps of Engineers: it can comply with an existing
    nationwide permit, or it can acquire an individual permit
    specific to the Pipeline. See Sierra Club v. W. Va. Dep’t of
    Env’t Prot., 
    64 F.4th 487
    , 495 (4th Cir. 2023). Mountain
    Valley chose the first route, and the Huntington District of the
    Army Corps of Engineers verified that construction of the
    Pipeline could proceed under an existing nationwide permit. In
    October 2018, however, the Fourth Circuit vacated that
    verification. Sierra Club v. U.S. Army Corps of Eng’rs, 
    905 F.3d 285
     (4th Cir. 2018) (mem.) (order vacating verification);
    Sierra Club v. U.S. Army Corps of Eng’rs, 
    909 F.3d 635
     (4th
    Cir. 2018) (opinion explaining order). Two other Army Corps
    of Engineers districts then also suspended their authorizations
    for the Pipeline. Mountain Valley paused work on all stream
    crossings in those districts.
    Next, Mountain Valley lost its approval from the Fish and
    Wildlife Service. In August 2019, in response to new
    information about the Pipeline’s potential impact on certain
    listed species, Mountain Valley suspended construction in
    various watersheds where those species live. The Commission
    then asked the Fish and Wildlife Service to reopen consultation
    on the Pipeline under the Endangered Species Act. Given those
    developments, the Fourth Circuit granted a stay of the Service’s
    8
    prior approval of the Pipeline. See Wild Va. v. U.S. Dep’t of
    Interior, No. 19-1866 (4th Cir. Oct. 11, 2019) (order granting
    stay).
    At that point, Mountain Valley had lost three federal
    authorizations it needed for construction: from the Bureau of
    Land Management and Forest Service to build in Jefferson
    National Forest, from the Army Corps of Engineers to cross
    streams, and from the Fish and Wildlife Service to build the
    Pipeline despite its impact on listed species. The Commission
    again ordered Mountain Valley to stop construction. Letter
    from Terry L. Turpin, Dir., Off. of Energy Projects, Fed.
    Energy Regul. Comm’n, to Matthew Eggerding, Counsel,
    Mountain Valley Pipeline, LLC (Oct. 15, 2019) (Stop Work
    Order), J.A. 633–34.
    D.
    By the time the Commission halted work in response to the
    Fourth Circuit’s decisions, Mountain Valley had already built
    a substantial portion of the Pipeline. Along the way, state
    regulators cited the company for violations related to the
    project’s sedimentation impacts.
    In 2018, inspections by the Virginia Department of
    Environmental Quality of sites along the Pipeline route
    revealed repeated violations of state water-quality regulations.
    Some control measures intended to mitigate erosion and
    sedimentation had been improperly installed, while others had
    been inadequately maintained or repaired. Those faulty
    controls allowed stormwater to escape the Pipeline right-of-
    way, depositing sediment in nearby streams. The Department
    sued Mountain Valley in state court, and the parties reached a
    settlement requiring the company to pay more than $2 million
    in fines. Press Release, Off. of the Virginia Att’y Gen., MVP,
    9
    LLC to Pay More than $2 Million, Submit to Court-Ordered
    Compliance and Enhanced, Independent Third-Party
    Environmental Monitoring (Oct. 11, 2019).
    Similarly, the West Virginia Department of
    Environmental Protection issued forty-six violation notices to
    Mountain Valley in 2018 and 2019, many of which concerned
    sedimentation.       The Department attached scores of
    photographs showing failed erosion controls along the Pipeline
    right-of-way. West Virginia fined Mountain Valley several
    hundred thousand dollars for those violations of state water-
    quality laws. See Mike Tony, Mountain Valley Pipeline Faces
    $303,000 State Fine for Continued Erosion, but Pipeline
    Opponents Call for Bigger Penalty, Charleston Gazette-Mail
    (Feb. 5, 2021), https://tinyurl.com/yckw3ryn.
    E.
    In September 2020, Mountain Valley regained two of the
    three permits it had lost. First, the Fish and Wildlife Service
    issued a revised biological opinion concluding that the Pipeline
    would not threaten the existence of listed species or adversely
    affect critical habitat. That same month, the relevant districts
    of the Army Corps of Engineers reauthorized the Pipeline
    under the same national permit they had relied on before.
    With those authorizations in hand, Mountain Valley
    returned to the Commission. It asked for an extension of the
    three-year deadline to complete construction and approval to
    resume work outside Jefferson National Forest. (Construction
    within the national forest remained on hold pending renewed
    approvals from the Bureau of Land Management and the Forest
    Service.) The Commission responded to Mountain Valley’s
    request in a series of orders, which petitioners challenge here.
    10
    1.
    The Commission began with Mountain Valley’s request to
    extend the construction deadline. In the initial Certificate
    Order, the Commission directed Mountain Valley to finish
    building the Pipeline within three years, by October 2020. But
    as of September 2020, construction on the Pipeline remained
    stalled. Mountain Valley asked for an extension of the deadline
    by two years, to October 2022. The Commission granted
    Mountain Valley’s request, finding a continued market need
    for the Pipeline. Order Granting Requests for Extension of
    Time, Mountain Valley Pipeline, LLC, 
    173 FERC ¶ 61,026
    (Oct. 9, 2020) (First Extension Order).
    2.
    Mountain Valley also asked for the Commission’s
    approval to resume work along most of the Pipeline’s route,
    except for the 3.5 miles within Jefferson National Forest. By
    that time, Mountain Valley had put 256 miles of pipe in the
    ground and finished restoring 155 miles of the Pipeline right-
    of-way. The company contended that resuming construction
    would protect the environment and benefit landowners by
    allowing final restoration of additional portions of the route.
    In a companion order issued alongside the First Extension
    Order, the Commission granted in part Mountain Valley’s
    request to resume construction. Order Partially Lifting Stop
    Work Order and Allowing Certain Construction to Proceed,
    Mountain Valley Pipeline, LLC, 
    173 FERC ¶ 61,027
     (Oct. 9,
    2020) (Resume Work Order). The Commission permitted
    work to resume, but only outside the same 25-mile exclusion
    zone (encompassing the crossing of Jefferson National Forest
    and adjacent watersheds) that the Commission had exempted
    from its prior order allowing resumed construction. The
    11
    Commission agreed with Mountain Valley that completing
    construction and restoration along most of the route—and thus
    replacing temporary erosion controls with permanent
    measures—would best serve the environment and affected
    landowners. 
    Id. ¶¶ 30, 32
    .
    Of relevance here, the Commission concluded that
    preparation of a supplemental environmental impact statement
    was unnecessary. Although the project’s sedimentation
    impacts had been “slightly different” than projected due in part
    to “unpredictable rainfall events,” the Commission determined
    that any deviation from its initial projections was “not
    significant enough to warrant” a supplemental impact
    statement. 
    Id. ¶ 39
    .
    The Commission also rejected arguments from petitioners
    that allowing construction to resume would violate
    Environmental Condition 9 to the original Certificate Order.
    That Condition, as noted, required Mountain Valley to obtain
    all necessary permits before commencing construction. The
    Commission understood that requirement to apply only to the
    initial commencement of construction, not to a later resumption
    of work.
    3.
    Less than a week after the Commission issued the Resume
    Work Order, Mountain Valley resubmitted its request to
    resume construction within the 25-mile exclusion zone (except
    for the 3.5 miles within Jefferson National Forest, where the
    company still lacked authorization to build). Mountain Valley
    presented sedimentation modeling showing that construction in
    the exclusion zone would not send sediment into the national
    forest. The Commission granted the company’s request to
    resume building in the portion of the exclusion zone outside
    12
    Jefferson National Forest. Order Partially Lifting Stop Work
    Orders and Allowing Certain Construction to Resume,
    Mountain Valley Pipeline, LLC, 
    173 FERC ¶ 61,252
     (Dec. 17,
    2020) (Exclusion Zone Order).
    4.
    Petitioners, who are various environmental groups who
    had intervened in the proceedings before the Commission,
    sought rehearing of the First Extension, Resume Work, and
    Exclusion Zone Orders. Because the Commission failed to act
    on those rehearing requests within thirty days, they were
    deemed denied as a matter of law for purposes of enabling
    judicial review. See 15 U.S.C. § 717r(a); Allegheny Def.
    Project v. FERC, 
    964 F.3d 1
    , 5 (D.C. Cir. 2020) (en banc). But
    the Commission retained power to modify its orders. See 15
    U.S.C. § 717r(a). In December 2020, the Commission issued
    an order modifying the First Extension and Resume Work
    Orders. Order Addressing Arguments Raised on Rehearing,
    Mountain Valley Pipeline, LLC, 
    173 FERC ¶ 61,222
     (Dec. 11,
    2020) (First Modification Order). In March 2021, the
    Commission modified the Exclusion Zone Order. Order
    Addressing Arguments Raised on Rehearing and Denying
    Stay, Mountain Valley Pipeline, LLC, 
    174 FERC ¶ 61,192
    (Mar. 24, 2021) (Second Modification Order).
    F.
    Despite getting the green light from the Commission to
    resume construction, Mountain Valley ran into further
    roadblocks in the Fourth Circuit. In December 2020, that court
    stayed decisions from the Huntington and Norfolk districts of
    the Army Corps of Engineers reverifying that construction of
    the Pipeline could proceed under an existing nationwide
    permit. Sierra Club v. U.S. Army Corps of Eng’rs, 
    981 F.3d 13
    251 (4th Cir. 2020). Mountain Valley then shifted gears,
    ceasing its reliance on a nationwide permit and instead
    applying to the Army Corps of Engineers for an individual
    permit. Sierra Club, 64 F.4th at 496. In that connection, the
    West Virginia Department of Environmental Protection
    certified that construction of the Pipeline would not violate the
    state’s water quality standards. Id. at 498. Absent that
    certification, Mountain Valley could not obtain an individual
    permit. See id. at 496 (citing 
    33 U.S.C. § 1341
    (a)(1)).
    Meanwhile, the Bureau of Land Management and the
    Forest Service issued new decisions authorizing construction
    in Jefferson National Forest. But in January 2022, after the
    close of briefing in this case, the Fourth Circuit vacated those
    renewed authorizations. Wild Va. v. U.S. Forest Serv., 
    24 F.4th 915
     (4th Cir. 2022). About a week later, the Fourth Circuit also
    vacated the Fish and Wildlife Service’s latest approvals.
    Appalachian Voices v. U.S. Dep’t of Interior, 
    25 F.4th 259
     (4th
    Cir. 2022). Those decisions again left Mountain Valley
    without three federal permits necessary to complete
    construction.
    G.
    In June 2022, Mountain Valley again asked the
    Commission to extend the construction deadline, this time by
    four years, until October 2026. The Commission granted that
    request. Order Granting Request for Extension of Time,
    Mountain Valley Pipeline, LLC, 
    180 FERC ¶ 61,117
     (Aug. 23,
    2022) (Second Extension Order). With the First Extension
    Order having lapsed during the pendency of this case (in
    October 2022), the Second Extension Order—and its deadline
    of October 2026— now governs the project.
    14
    In February and May 2023, Mountain Valley regained two
    federal permits. First, the Fish and Wildlife Service issued a
    further revised biological opinion concluding that the Pipeline
    would not threaten the existence of listed species or adversely
    affect critical habitat. Letter from Cindy Schulz, Field
    Supervisor, Va. Ecological Servs., U.S. Fish & Wildlife Serv.,
    to Kimberly Bose, Sec’y, Fed. Energy Regul. Comm’n (Feb.
    28, 2023), https://tinyurl.com/3ytrnrkr. Second, the Forest
    Service and the Bureau of Land Management issued new
    decisions authorizing construction in Jefferson National Forest.
    Forest Serv., U.S. Dep’t of Agric., Record of Decision,
    Mountain Valley Pipeline and Equitrans Expansion Project
    (May 2023), https://tinyurl.com/3mrpnubp; Bureau of Land
    Mgmt., U.S. Dep’t of Interior, Record of Decision, Mountain
    Valley Pipeline and Equitrans Expansion Project Decision to
    Grant Right-of-Way and Temporary Use Permit (May 2023),
    https://tinyurl.com/2tts6zky.
    Meanwhile, in April, Mountain Valley met another,
    separate setback in the Fourth Circuit: that court vacated the
    West Virginia Department of Environmental Protection’s
    certification that the Pipeline’s construction would not violate
    the state’s water quality standards. Sierra Club, 
    64 F.4th 487
    .
    That decision leaves uncertain whether Mountain Valley will
    be able to obtain required authorization from the Army Corps
    of Engineers through an individual permit.
    II.
    Petitioners challenge the following Commission orders:
    (i) the First Extension Order, which extended the construction
    deadline for the Pipeline from October 2020 until October
    2022; (ii) the Resume Work Order, which permitted Mountain
    Valley to resume work outside the 25-mile exclusion zone
    encompassing the crossing of Jefferson National Forest and the
    15
    adjacent watersheds; (iii) the Exclusion Zone Order, which
    allowed Mountain Valley to build in the portion of the
    exclusion zone outside Jefferson National Forest; (iv) the First
    Modification Order, which modified the First Extension and
    Resume Work Orders by addressing certain issues raised in
    petitioners’ requests for rehearing; and (v) the Second
    Modification Order, which modified the Exclusion Zone Order
    by elaborating on the Commission’s reasons for allowing
    Mountain Valley to move forward with its project in response
    to arguments raised in the requests for rehearing.
    Before turning to the merits of those challenges, we
    consider our jurisdiction to address them. We conclude that we
    retain jurisdiction to consider all of petitioners’ claims except
    their challenge to the First Extension Order.
    A.
    Because Article III of the Constitution grants federal
    courts power to resolve only “actual, ongoing controversies,”
    we lose jurisdiction over a pending claim if it becomes moot.
    Planned Parenthood of Wis., Inc. v. Azar, 
    942 F.3d 512
    , 516
    (D.C. Cir. 2019) (quotation marks and citation omitted). A
    claim is moot if intervening events mean the court’s “decision
    will neither presently affect the parties’ rights nor have a more-
    than-speculative chance of affecting them in the future.”
    Clarke v. United States, 
    915 F.2d 699
    , 701 (D.C. Cir. 1990)
    (quotation marks and citation omitted). The operative question
    is whether we can grant “any effectual relief whatever to the
    prevailing party.” Campbell-Ewald Co. v. Gomez, 
    577 U.S. 153
    , 161 (2016). The “initial heavy burden of establishing
    mootness lies with the party asserting” mootness, and “the
    opposing party bears the burden of showing an exception
    applies.” Honeywell Int’l, Inc. v. Nuclear Regul. Comm’n, 628
    
    16 F.3d 568
    , 576 (D.C. Cir. 2010) (quotation marks and citation
    omitted).
    1.
    We first consider whether the Fourth Circuit’s latest
    decisions vacating three agencies’ authorizations for the
    Pipeline render this case moot. Although no party so argues,
    we also “have an independent obligation to ensure that appeals
    before us are not moot.” Planned Parenthood, 942 F.3d at 516
    (quotation marks and citation omitted).
    Petitioners ask us to redress their asserted injuries by
    vacating the Commission’s orders allowing construction of the
    Pipeline to continue. If the Fourth Circuit’s decisions
    invalidating other agencies’ actions completely foreclosed any
    possibility of future construction, then a decision in this case
    vacating the Commission’s orders might have no effect on
    petitioners’ rights. But none of the Fourth Circuit’s decisions,
    whether considered individually or in combination, sweeps so
    broadly.
    Most obviously, the Fourth Circuit’s decisions vacating
    authorizations (or more accurately, reauthorizations) from the
    Bureau of Land Management, Forest Service, and Fish and
    Wildlife Service do not affect this case. Mountain Valley
    subsequently regained those permits, as described above. See
    p. 14, supra.
    That leaves the Fourth Circuit’s decisions vacating the
    Army Corps of Engineers’ approval to build the Pipeline across
    waterbodies and the West Virginia Department of
    Environmental Protection’s certification pertaining to
    obtaining an individual permit from the Army Corps of
    Engineers. Mountain Valley represents that it has completed
    17
    some 94 percent of Pipeline construction. And at least some of
    the remaining 6 percent entails building across streams,
    protected habitats, or both, such that construction in those areas
    could not be completed until Mountain Valley regains the
    approvals that have been vacated by the Fourth Circuit.
    But nothing in the record establishes that the Fourth
    Circuit’s decisions entirely preclude Mountain Valley from
    engaging in construction on the project. To the contrary,
    construction could continue in certain areas adjacent to
    wetlands, even while the company awaits permission from the
    Army Corps of Engineers to build within wetlands. That
    remains true after the Fourth’s Circuit’s recent April 2023
    decision, which affects only whether Mountain Valley can
    obtain permission from the Army Corps of Engineers to build
    within wetlands. Petitioners’ challenge to the Commission’s
    orders, by contrast, seeks to halt Pipeline construction
    everywhere along the right-of-way, beyond the specific areas
    covered by the other federal permits.
    There is also a more-than-speculative chance that
    Mountain Valley will reacquire the vacated Army Corps of
    Engineers’ permit, freeing the company to resume building in
    the affected areas. (Indeed, Mountain Valley has already
    regained approvals from the Bureau of Land Management,
    Forest Service, and Fish and Wildlife Service, as noted above.)
    But a decision from this court vacating the Commission’s
    approval for the project as a whole would preclude a
    resumption of work regardless. For those reasons, the Fourth
    Circuit’s decisions do not moot this case.
    2.
    We next consider whether the expiration of the First
    Extension Order during the pendency of this case moots
    18
    petitioners’ challenge to that particular order. Mountain Valley
    contends in a post-argument submission that it does. The
    company argues that, because the October 2022 deadline set
    out in the First Extension Order has passed, and that order has
    been superseded by the Second Extension Order’s
    establishment of a new deadline of October 2026, petitioners
    can no longer “show[] that they have suffered some actual
    injury that can be redressed” by our review of the First
    Extension Order. Freeport-McMoRan Oil & Gas Co. v. FERC,
    
    962 F.2d 45
    , 46 (D.C. Cir. 1992) (quotation marks and citation
    omitted). We agree.
    When a challenged order expires during the pendency of
    litigation, the challenge generally becomes moot—at least
    when, as here, the challenger seeks only prospective relief. See
    id.; Nw. Pipeline Corp. v. FERC, 
    863 F.2d 73
    , 75–77 (D.C. Cir.
    1988); Md. People’s Counsel v. FERC, 
    761 F.2d 768
    , 773
    (D.C. Cir. 1985). The First Extension Order has expired and
    has been superseded by a subsequent order that now governs.
    A decision on the First Extension Order’s validity thus would
    “neither presently affect the parties’ rights nor have a more-
    than-speculative chance of affecting them in the future.”
    Clarke, 
    915 F.2d at 701
    .
    Petitioners contend that a live controversy remains
    because the First Extension Order’s collateral consequences
    continue to harm them. They reason that the Commission
    could not have issued the Second Extension Order if not for the
    First Extension Order, without which the initial Certificate
    Order would have already expired. But even so, it does not
    follow that petitioners’ challenge to the First Extension Order
    remains live. Petitioners could separately seek review of the
    Second Extension Order, but their challenge to the First
    Extension Order—which no longer has any legal effect—does
    not remain justiciable merely because that order’s one-time
    19
    existence enabled the Commission to issue a subsequent
    extension order that now governs.
    Nor have petitioners carried their burden of showing that
    an exception to mootness applies. Petitioners invoke two cases
    in which we have applied the “capable of repetition, yet
    evading review” exception to mootness. See Montgomery
    Env’t Coal. v. Costle, 
    646 F.2d 568
    , 578–79 (D.C. Cir. 1980);
    Humane Soc’y v. EPA, 
    790 F.2d 106
    , 112–14 (D.C. Cir. 1986).
    Under that exception, a claim is not moot if “the challenged
    action was in its duration too short to be fully litigated prior to
    its cessation or expiration” and “there was a reasonable
    expectation that the same complaining party would be
    subjected to the same action again.” Trump v. Mazars USA,
    LLP, 
    39 F.4th 774
    , 786 (D.C. Cir. 2022) (quoting Weinstein v.
    Bradford, 
    423 U.S. 147
    , 149 (1975) (per curiam)).
    That exception is inapplicable here. Even if the First
    Extension Order was “in its duration too short to be fully
    litigated prior to its . . . expiration,” petitioners have not shown
    that their challenge to it is “capable of repetition.” 
    Id.
     A
    challenge is “capable of repetition” only if “the legal wrong
    complained of by the plaintiff is reasonably likely to recur,”
    Ralls Corp. v. Comm. on Foreign Inv. in U.S., 
    758 F.3d 296
    ,
    324 (D.C. Cir. 2014) (quotation marks and citation omitted),
    framed “in terms of the legal questions [the challenge] presents
    for decision,” J.T. v. Dist. of Columbia, 
    983 F.3d 516
    , 524
    (D.C. Cir. 2020) (quotation marks and citation omitted). It is
    therefore not enough that the Commission can—or did—issue
    another order extending the timeline for the Pipeline. It must
    also be the case that the Second Extension Order—or any other
    orders “reasonably likely to recur” in the future—presents the
    same alleged legal wrong and the same legal question as the
    First Extension Order.
    20
    The “legal wrong” of which petitioners complain in their
    challenge to the First Extension Order is the Commission’s
    finding of continued market need for the Pipeline. Petitioners
    ask us to decide whether that finding was supported by
    substantial evidence based on the record before the
    Commission at the time it issued the First Extension Order.
    That is “not the type of legal question that is capable of
    repetition as it is sharply focused on a unique factual context.”
    J.T., 983 F.3d at 527–28 (quotation marks and citation
    omitted). To be sure, petitioners suggest that the Commission
    repeats its legal wrongs from the First Extension Order in the
    Second Extension Order. But an analysis of market need
    “necessarily varies from one . . . period to the next, depending
    upon the circumstances the [Commission] considers,” such that
    any challenge to the Second Extension Order would “require
    review of a different record from the one on which the [First
    Extension Order was] issued.” See Nat’l Ass’n of Home
    Builders v. U.S. Army Corps of Eng’rs, 
    264 F. App’x 10
    , 13
    (D.C. Cir. 2008).
    Petitioners thus have not shown that their challenge to the
    First Extension Order is “capable of repetition,” or that any
    other mootness exception applies. As a result, petitioners’
    challenge to that order is moot.
    B.
    We turn next to statutory jurisdiction. Mountain Valley
    contends that we lack jurisdiction under the Natural Gas Act to
    consider petitioners’ challenge to the Exclusion Zone and
    Second Modification Orders. The problem, according to
    Mountain Valley, is that petitioners never filed a separate
    petition seeking judicial review of the Second Modification
    Order, which amended the Exclusion Zone Order. We are
    unpersuaded.
    21
    Under the Natural Gas Act, a party aggrieved by an order
    of the Commission has thirty days to seek rehearing before the
    agency and must do so before coming to court. 15 U.S.C.
    § 717r(a). Petitioners timely sought rehearing of the Exclusion
    Zone Order. The Act gives the Commission thirty days to act
    on a request for rehearing. Otherwise, the rehearing request is
    “deemed to have been denied,” and an aggrieved party is free
    to petition for judicial review. Id.
    In the past, the Commission frequently issued tolling
    orders to extend its deadline for resolving requests for
    rehearing. But in Allegheny Defense Project, we held that such
    tolling orders “are not the kind of action on a rehearing
    application that can fend off a deemed denial and the
    opportunity for judicial review.” 964 F.3d at 3–4.
    Here, the Commission failed to act on petitioners’ request
    for rehearing of the Exclusion Zone Order within thirty days.
    The resulting denial of rehearing as a matter of law put both
    petitioners and the Commission on the clock. Petitioners had
    sixty days to petition for judicial review. 15 U.S.C. § 717r(b).
    As for the Commission, although it had missed the deadline for
    resolving the rehearing requests on their merits, it retained
    authority to “modify or set aside” its original orders in response
    to the arguments raised on rehearing, “[u]ntil the record in [the]
    proceeding [was] filed in [the] court of appeals.” Id. § 717r(a).
    After petitioners’ application for rehearing of the
    Exclusion Zone Order was deemed denied as a matter of law,
    petitioners sought judicial review of that order. But the
    Commission could still modify the order until the record of the
    proceeding was filed in our court. The Commission exercised
    that authority by issuing the Second Modification Order, in
    which it updated its discussion in the Exclusion Zone Order to
    22
    address arguments raised on rehearing. Petitioners did not file
    a separate petition for review to challenge the Second
    Modification Order.
    Mountain Valley contends that we lack jurisdiction to
    consider petitioners’ challenges to the Exclusion Zone and
    Second Modification Orders. According to Mountain Valley,
    the Exclusion Zone Order was not final agency action for
    purposes of judicial review, despite the denial of rehearing as a
    matter of law, because the Commission later took final action
    on the rehearing application in the Second Modification Order.
    And we also lack jurisdiction over the Second Modification
    Order, Mountain Valley maintains, because petitioners failed
    to file a petition for review designating that order as among
    those they challenged.
    Our decision in Allegheny Defense Project forecloses
    Mountain Valley’s arguments. As we explained there, when
    the Commission fails to act on a rehearing application within
    thirty days, “the applicant may deem its rehearing application
    denied and seek judicial review of the now-final agency
    action.” Allegheny Def. Project, 964 F.3d at 13. Here,
    accordingly, when the Commission failed to act on petitioners’
    rehearing request within thirty days, petitioners were free to
    deem it denied and seek judicial review, which they did.
    To be sure, in its notice that rehearing had been denied by
    operation of law, the Commission expressed its intention to
    address the arguments raised on rehearing in a future order
    modifying the Exclusion Zone Order. But if mere mention of
    a desire to amend the original order at some unspecified future
    time had the effect of forestalling judicial review, then the
    Commission’s notice of denial by operation of law would be
    no different from the tolling orders we rejected in Allegheny
    Defense Project. As we said there, “the question is not one of
    23
    labels, but of signification.” Id. No statement of intent to act
    in the future, regardless of what the order containing that
    statement may be called, can prevent an action from becoming
    final if the Commission fails to decide the merits of a rehearing
    application within thirty days. The Exclusion Zone Order thus
    became final agency action subject to challenge in court when
    the Commission failed to decide petitioners’ rehearing request
    within the allotted time.
    We also have jurisdiction to consider the Second
    Modification Order. A petition for review must “specify the
    order or part thereof to be reviewed.” Fed. R. App. P. 15(a)(2).
    It is undisputed that petitioners complied with that requirement
    when initially seeking review of the Exclusion Zone Order.
    After petitioners sought review in our court but before the
    record in the proceeding was filed with us, the Commission
    exercised its discretion to modify the Exclusion Zone Order by
    issuing the Second Modification Order.
    Petitioners were under no obligation to file a new petition
    for review challenging that additional order. Mountain Valley
    portrays the Second Modification Order as a “rehearing order”
    requiring a separate petition. But as we have explained, when
    the Commission failed to act on petitioners’ rehearing request
    within thirty days, rehearing was denied as a matter of law. At
    that point, the Commission was limited to updating the
    Exclusion Zone Order rather than granting rehearing of it. The
    Second Modification Order, then, was not a new order, but was
    an amendment to the Exclusion Zone Order. Because the
    Exclusion Zone Order, as amended, remains the operative
    order that petitioners challenge, their petitions adequately
    specify the orders to be reviewed.
    In any event, we have held that “inexact specification of
    the order to be reviewed will not be fatal to the petition . . . if
    24
    the petitioner’s intent to seek review of a specific order can be
    fairly inferred from the petition for review or from other
    contemporaneous filings, and the respondent is not misled by
    the mistake.” LaRouche’s Comm. for a New Bretton Woods v.
    FEC, 
    439 F.3d 733
    , 739 (D.C. Cir. 2006) (quotation marks and
    citation omitted). We can fairly infer from the petitions for
    review that petitioners intended to seek review not only of the
    Exclusion Zone Order but also of any amendment to it. And
    the Commission could not have been misled, given our
    explanation in Allegheny Defense Project of how the statutory
    scheme operates, including the Commission’s power to modify
    orders up to the time when the record is filed in court. Indeed,
    the Commission does not join Mountain Valley in contesting
    our jurisdiction over the Second Modification Order.
    We therefore have jurisdiction to review the Second
    Modification and Exclusion Zone Orders (and also the Resume
    Work and First Modification Orders, as to which there is no
    challenge to our jurisdiction and over which we undoubtedly
    have jurisdiction).
    III.
    We assess petitioners’ challenges to the Commission’s
    orders under the APA’s arbitrary-or-capricious standard of
    review. See 
    5 U.S.C. § 706
    (2)(A). The Commission’s orders
    must be sustained so long as they “examined the relevant
    considerations and articulated a satisfactory explanation for its
    action, including a rational connection between the facts found
    and the choice made.” FERC v. Elec. Power Supply Ass’n, 
    577 U.S. 260
    , 292 (2016) (alterations adopted) (quoting Motor
    Vehicle Mfrs. Ass’n of the U.S., Inc. v. State Farm Mut. Auto.
    Ins. Co., 
    463 U.S. 29
    , 43 (1983)).
    25
    A.
    We first consider whether the Commission erred in the
    Resume Work and Exclusion Zone Orders by allowing
    construction to resume before Mountain Valley reacquired all
    its other permits. We reject those challenges.
    1.
    Petitioners contend that the Commission violated
    Environmental Condition 9 to the Certificate Order by
    permitting construction to resume even though Mountain
    Valley was still waiting on reauthorization to build in Jefferson
    National Forest. Environment Condition 9 required Mountain
    Valley to “receive written authorization” from the Commission
    “before commencing construction of any project facilities.”
    Certificate Order, App. C, Environmental Condition 9. And to
    obtain that authorization from the Commission, Mountain
    Valley needed to show “that it ha[d] received all applicable
    authorizations required under federal law.” 
    Id.
    The Commission interpreted that condition to require
    obtaining “all relevant authorizations before the company can
    commence construction” at the outset of the project, without
    carrying any “ongoing obligation once those authorizations
    have been obtained and the Commission has” permitted
    construction to begin. Second Modification Order ¶ 16. On
    that reading, “Environmental Condition 9 applies to newly-
    certificated and unconstructed facilities,” but not in “a scenario
    where applicable federal authorizations are vacated after a
    company has obtained necessary federal authorizations and
    commenced construction.”        
    Id.
         That is because “the
    invalidation of a specific federal authorization does not
    necessarily invalidate an authorization to construct generally,
    26
    particularly if significant construction is already underway.”
    Resume Work Order ¶ 17.
    We sustain the Commission’s interpretation of
    Environmental Condition 9, particularly in view of the
    deference we accord to the Commission’s interpretation of its
    own adjudicatory orders. See Cellco P’ship v. FCC, 
    700 F.3d 534
    , 544 (D.C. Cir. 2012); Sw. Gas Corp. v. FERC, 
    145 F.3d 365
    , 370 (D.C. Cir. 1998). The condition’s use of the word
    “commencing” suggests that it applies at the start of
    construction. Petitioners argue that the phrase “of any project
    facilities” suggests that all authorizations must be in place
    before Mountain Valley constructs each successive portion of
    the Pipeline. But the word “any” is just as naturally read to
    indicate that all necessary authorizations needed to be in place
    before Mountain Valley could initially commence construction
    on even one—i.e., any—project facility.
    As the Commission explained, moreover, if a particular
    federal authorization is vacated after construction has begun,
    the Commission’s staff “evaluates the circumstances along the
    pipeline’s right-of-way as they exist at the time and determines
    what course of action would be most protective of the
    environment.” Resume Work Order ¶ 19. In some situations,
    especially if a substantial portion of construction is already
    underway, “it may be most protective of the environment for
    additional construction to proceed.” 
    Id.
     For instance, if
    construction is nearly complete on one segment of a pipeline
    when a court vacates an authorization affecting a different
    segment, it might be prudent to allow construction to continue
    along the first segment, hastening final restoration of the right-
    of-way for the benefit of the environment and landowners. The
    Commission’s interpretation of Environmental Condition 9
    enables that choice, whereas petitioners’ competing
    interpretation would deny it.
    27
    The Commission also adequately explained why resuming
    construction was advisable in this case. At the time of the
    Resume Work Order, there were about 100 miles of the
    Pipeline right-of-way where Mountain Valley had put pipe in
    the ground but had yet to complete restoration work. The
    Commission explained that leaving temporarily stabilized
    areas exposed to the elements can cause “slips, overwhelmed
    erosion control devices, and gradual degradation of
    annual/seasonal cover crops and/or mulch,” while temporary
    controls require regular upkeep. Id. ¶ 30. Moving more of the
    Pipeline right-of-way into final restoration would ameliorate
    those issues. Replacing temporary erosion and sedimentation
    controls with permanent measures “would more effectively
    stabilize slip-prone areas, eliminate or significantly reduce
    erosion and sedimentation off the right-of-way, and protect
    sensitive resources such as waterbodies, wetlands, and habitats
    for wildlife and aquatic species.” Id. The Commission
    reasonably concluded, then, that allowing construction to
    resume would benefit the environment, even without all other
    authorizations in place. Id.
    Petitioners cite a Fourth Circuit decision addressing a
    challenge to a permit issued by the National Park Service for a
    different pipeline project. See Sierra Club v. U.S. Dep’t of
    Interior, 
    899 F.3d 260
     (4th Cir. 2018). That decision suggests
    in a footnote that a condition identical to Environmental
    Condition 9 required all federal authorizations to be in place
    not only for construction to begin but also for construction to
    continue. 
    Id.
     at 284 n.11. In the Resume Work Order, the
    Commission acknowledged that decision but clarified that “the
    invalidation of a specific federal authorization does not
    necessarily invalidate an authorization to construct generally,
    particularly if significant construction is already underway.”
    Resume Work Order ¶ 17.
    28
    The Fourth Circuit’s brief discussion of the condition in
    that decision does not govern here. As the Commission
    underscores, the Fourth Circuit’s decision addressed only a
    pipeline’s ability to unilaterally proceed to construction after
    the invalidation of a federal authorization. See Sierra Club,
    
    899 F.3d at
    284 & n.11. It did not contend with a scenario in
    which, as here, the Commission expressly authorized
    construction to resume following invalidation of a federal
    authorization.     See Comm’n Br. 37.            Moreover, the
    Commission was not a party in the Fourth Circuit’s case and so
    had no opportunity to present its explanation of the meaning of
    the condition to that court. This case afforded the Commission
    its first opportunity to explain its interpretation, which we
    sustain.
    The Resume Work and Exclusion Zone Orders are thus
    consistent with Environmental Condition 9, as interpreted by
    the Commission.
    2.
    Petitioners next contend that constructing segments of the
    Pipeline up to the border of Jefferson National Forest will
    create unwarranted bureaucratic momentum pressuring the
    Bureau of Land Management and Forest Service to allow
    construction within the national forest. Relying on the Fourth
    Circuit’s decision in Maryland Conservation Council v.
    Gilchrist, 
    808 F.2d 1039
     (4th Cir. 1986), petitioners imagine
    the partially completed segments of the Pipeline “stand[ing]
    like gun barrels pointing into the heartland” of the national
    forest. Pet’rs’ Br. 51 (quoting Gilchrist, 
    808 F.2d at 1042
    ).
    Our court has rejected the “bureaucratic momentum”
    analysis from the Fourth Circuit’s Gilchrist decision, observing
    29
    that it “lacks vitality.” Karst Env’t Educ. & Prot., Inc. v. EPA,
    
    475 F.3d 1291
    , 1297 (D.C. Cir. 2007). In the Exclusion Zone
    Order, however, the Commission seemed to acknowledge that,
    at least in some situations, one agency’s approval of a project
    could create bureaucratic momentum unduly affecting another
    agency’s consideration of the project. See Exclusion Zone
    Order ¶¶ 12–13. But because the Bureau of Land Management
    and Forest Service had already approved the Pipeline’s route
    through Jefferson National Forest, the Commission concluded
    that its own decision allowing construction to resume would
    impose no undue pressure on those agencies.
    By their nature, interstate pipeline projects frequently
    require multiple federal permits, as this case illustrates. And
    no agency could be the first to approve such a project if it were
    forbidden from creating any bureaucratic momentum that
    might influence other agencies. But even assuming without
    deciding that a bureaucratic momentum argument could be
    viable in certain situations, we conclude that the Commission
    reasonably rejected petitioners’ argument here.
    By the time of the Exclusion Zone Order, the Bureau of
    Land Management and the Forest Service had twice rejected
    all possible alternative routes through Jefferson National
    Forest. Id. ¶ 13. In that context, the Commission could allow
    construction of the Pipeline up to the border of the national
    forest without putting any undue pressure on those other
    agencies, which had already decided that the Pipeline’s sole
    viable path through the national forest was one corresponding
    to the route of Mountain Valley’s construction outside the
    forest. In the circumstances of this case, petitioners’
    bureaucratic momentum argument thus fails.
    30
    B.
    Petitioners’ final two challenges pertain to the
    Commission’s decision not to prepare a supplemental
    environmental impact statement before permitting construction
    to resume. An agency must supplement its environmental
    impact statement when “significant new circumstances or
    information” raise additional concerns about an action’s
    impact. 
    40 C.F.R. § 1502.9
    (d)(1)(ii). As we have emphasized,
    a supplemental environmental impact statement “must be
    prepared only where new information ‘provides a seriously
    different picture of the environmental landscape.’” Stand Up
    for California! v. U.S. Dep’t of Interior, 
    994 F.3d 616
    , 629
    (D.C. Cir. 2021) (quoting Friends of Cap. Crescent Trail v.
    FTA, 
    877 F.3d 1051
    , 1060 (D.C. Cir. 2017)).
    1.
    Petitioners contend that the Commission should have
    prepared a supplemental environmental impact statement to
    consider the effects of blasting activity along the Pipeline right-
    of-way. They rely on one line in the final environmental
    impact statement noting that Mountain Valley had “not
    determined whether blasting would be necessary for
    construction” of the Pipeline. Final Environmental Impact
    Statement 4-203, J.A. 71. In practice, blasting has been
    required along much of the right-of-way. Petitioners argue that
    the widespread use of blasting constitutes significant new
    information warranting a supplemental impact statement. The
    Commission reasonably rejected that contention.
    The final environmental impact statement included a
    thorough discussion of the potential impacts of blasting. The
    Commission recognized that blasting likely would be
    necessary along much of the Pipeline’s route. The final
    31
    environmental impact statement explained that Pipeline
    construction “would cross 216 miles of shallow depth to
    bedrock,” id. at 4-44, J.A. 16, and “the potential for blasting
    exists at all locations where shallow bedrock may be
    encountered,” id. at 4-43, J.A. 15. Given the likelihood of
    blasting, the Commission explored in detail the potential
    environmental harms that could result, including the impact on
    aquifers, fish and other aquatic species, bald and golden eagles,
    people and animals who are bothered by loud noises, and so
    forth.
    Nothing in the record, moreover, suggests that the actual
    impacts of blasting to this point have differed in any material
    respect from the impacts the Commission anticipated in the
    final environmental impact statement. The Commission thus
    reasonably determined in the Resume Work Order that
    “impacts from blasting and construction [on] steep slopes were
    adequately addressed” in the final environmental impact
    statement. Resume Work Order ¶ 40.
    2.
    Petitioners next contend that the Commission’s final
    environmental impact statement “vastly overestimated” the
    effectiveness of Mountain Valley’s erosion and sedimentation
    controls, necessitating a supplemental analysis addressing
    sedimentation before construction can resume. Pet’rs’ Br. 41.
    We conclude that the Commission failed to provide an
    adequate explanation in rejecting that claim. While petitioners
    primarily take issue with the Commission’s rejection of that
    claim in the Resume Work Order, they frame their challenge as
    encompassing all orders on review, see id. at 15–17, 45, and
    the Commission does not argue otherwise. We accordingly
    treat the challenge as reaching all challenged orders.
    32
    In the final environmental impact statement, the
    Commission repeatedly stated that Mountain Valley’s
    proposed control measures would “minimize” erosion and
    sedimentation associated with Pipeline construction. For
    instance, Mountain Valley would “minimize or avoid” any
    “minor temporary fluctuations in surface water turbidity”
    associated with digging the Pipeline trench by
    “implement[ing] . . . the construction practices outlined” in the
    company’s erosion and sedimentation control plans. Final
    Environmental Impact Statement 4–137, J.A. 53.
    Petitioners submit that Mountain Valley’s controls
    significantly failed to minimize sedimentation impacts to the
    extent the Commission predicted. In supporting that claim,
    petitioners rely on information arising from state enforcement
    actions brought by Virginia and West Virginia. Virginia, in
    suing Mountain Valley for environmental violations,
    documented numerous instances in which construction of the
    Pipeline resulted in deposits of significant levels of sediment in
    streambeds. And West Virginia likewise issued dozens of
    violation notices to Mountain Valley associated with failed
    sediment controls along the Pipeline right-of-way, leading to
    substantial fines. Before the Commission, petitioners invoked
    the record underlying those enforcement actions as proof that
    the sedimentation impacts of Pipeline construction have been
    “seriously different” than originally anticipated. Stand Up for
    California!, 994 F.3d at 629 (quotation marks, citation, and
    emphasis omitted).
    In the face of petitioners’ presentation of that information,
    the Commission needed to explain why it was inadequate to
    show a substantial deviation from the prior environmental
    impact analysis. See Marsh v. Or. Nat. Res. Council, 
    490 U.S. 360
    , 374 (1989). But the Commission failed to offer a reasoned
    33
    explanation in that regard. Even under our deferential standard
    of review, we cannot sustain its decision.
    The Commission “acknowledge[d] that there have been
    slightly different outcomes than those projected” in the final
    environmental impact statement. Resume Work Order ¶ 39.
    The Commission summarily attributed those different
    outcomes to “unpredictable rainfall events,” and stated without
    elaboration that “the resulting impacts” from erosion and
    sedimentation “are not significant enough to warrant a
    supplemental [environmental impact statement].” 
    Id.
     But that
    bare conclusion, without any support or explanation, is
    insufficient to pass muster. The Commission further noted that
    its compliance monitors regularly inspect Pipeline construction
    sites to ensure Mountain Valley’s implementation of required
    controls. 
    Id.
     Those controls, though, failed to prevent the
    sedimentation documented by state regulators. And the
    Commission did not explain why those controls would more
    likely be effective going forward (aside from the one passing
    reference to unusual rainfall in the past). Nor did the
    Commission clarify or update its rationale after petitioners
    argued in their request for rehearing that the Commission had
    wrongfully dismissed post-certification evidence about
    sedimentation. First Modification Order ¶¶ 9–10.
    With respect to petitioners’ reliance on the state
    enforcement actions, the Commission offered just one sentence
    in response: “Mountain Valley reached consent decrees with
    both Virginia [] and West Virginia [] to resolve violations of
    state environmental standards and regulations and no
    additional action by the Commission is necessary at this time.”
    First Extension Order ¶ 27. But the mere fact that state
    regulators may have settled their actions against Mountain
    Valley does not itself afford a basis for declining to prepare a
    supplemental environmental impact statement.               State
    34
    enforcement of environmental laws in response to worse-than-
    anticipated impacts does not absolve the Commission of its
    duty to assess the environmental impacts of the project under
    federal law.
    Those consent decrees require Mountain Valley to
    implement additional sedimentation controls. Consent Decree
    at 7–9, Paylor v. Mountain Valley Pipeline, LLC, No.
    CL18006874-00 (Va. Cir. Ct. Dec. 11, 2019). And perhaps
    those additional measures will ensure that the remainder of
    construction produces no significant sedimentation impacts
    beyond those already anticipated. But the challenged orders do
    not offer that or any other explanation for why the consent
    decrees eliminate the need for a supplemental environmental
    impact statement.
    The Commission also points out that the final
    environmental impact statement predicted that building the
    Pipeline would lead to some sedimentation. Comm’n Br. 60–
    61 (citing Certificate Order ¶ 146). But a supplemental
    environmental impact statement is necessary not only when the
    nature of a project’s environmental impacts is significantly
    different than anticipated, but also when the extent of those
    impacts is significantly greater than predicted. Marsh, 
    490 U.S. at 374
    . The Commission failed to engage with whether
    the level of sedimentation observed along the Pipeline right-of-
    way was substantially different than expected. For those
    reasons, the Commission’s explanation of its decision not to
    prepare a supplemental environmental impact statement was
    arbitrary and capricious.
    C.
    Because the Commission inadequately addressed whether
    a supplemental environmental impact statement was necessary
    35
    in light of the project’s sedimentation impacts, we must remand
    that matter to the Commission. We remand all of the
    challenged orders (except the now-moot First Extension Order)
    because of that deficiency. We do so, however, without
    vacating the challenged orders’ approval of resuming
    construction.
    “The decision to vacate depends on two factors: the
    likelihood that ‘deficiencies’ in an order can be redressed on
    remand, even if the agency reaches the same result, and the
    ‘disruptive consequences’ of vacatur.” Black Oak Energy, LLC
    v. FERC, 
    725 F.3d 230
    , 244 (D.C. Cir. 2013) (quoting Allied–
    Signal v. Nuclear Regul. Comm’n, 
    988 F.2d 146
    , 150–51 (D.C.
    Cir. 1993)). With regard to the first factor, “[w]hen an agency
    bypasses a fundamental procedural step, the vacatur inquiry
    asks not whether the ultimate action could be justified, but
    whether the agency could, with further explanation, justify its
    decision to skip that procedural step.” Standing Rock Sioux
    Tribe v. U.S. Army Corps of Eng’rs, 
    985 F.3d 1032
    , 1052 (D.C.
    Cir. 2021).
    Here, the Commission failed to adequately explain its
    decision not to prepare a supplemental environmental impact
    statement. But after adequately accounting for the evidence of
    sedimentation impacts along the Pipeline’s right-of-way, the
    Commission could again conclude that a new impact statement
    is unnecessary, perhaps in part because of additional control
    measures required by the state consent decrees. As for the
    second factor, construction of the Pipeline is more than ninety
    percent complete, with many portions of the route nearing final
    restoration. And in the Commission’s view, the completion of
    restoration would help ameliorate the project’s sedimentation
    impacts. See pp. 10–11, supra. In those circumstances,
    vacating the Commission’s orders would be “quite disruptive.”
    Food & Water Watch, 28 F.4th at 292 (quoting City of Oberlin
    36
    v. FERC, 
    937 F.3d 599
    , 611 (D.C. Cir. 2019)). We thus
    exercise our discretion to remand without vacatur.
    *    *   *    *   *
    For the foregoing reasons, we dismiss in part, grant in part,
    and deny in part the petitions for review. We dismiss as moot
    the petitions insofar as they challenge the First Extension
    Order. We grant the petitions insofar as they challenge the
    Commission’s explanation of its decision not to prepare a
    supplemental environmental impact statement concerning the
    project’s sedimentation impacts, and we deny the petitions with
    respect to petitioners’ other arguments. Accordingly, we
    remand the Resume Work, Exclusion Zone, First Modification,
    and Second Modification Orders to the Commission without
    vacatur for further proceedings consistent with this opinion.
    So ordered.
    

Document Info

Docket Number: 20-1512

Filed Date: 5/26/2023

Precedential Status: Precedential

Modified Date: 5/26/2023

Authorities (19)

Friends of the Capital Crescent Trail v. Federal Transit ... , 877 F.3d 1051 ( 2017 )

Sierra Club, Inc. v. U.S. Forest Service , 897 F.3d 582 ( 2018 )

Sierra Club v. U.S. Army Corps of Engineers , 905 F.3d 285 ( 2018 )

Northwest Pipeline Corporation v. Federal Energy Regulatory ... , 863 F.2d 73 ( 1988 )

Motor Vehicle Mfrs. Assn. of United States, Inc. v. State ... , 103 S. Ct. 2856 ( 1983 )

Sierra Club v. U.S. Army Corps of Engineers , 909 F.3d 635 ( 2018 )

City of Bos. Delegation v. Fed. Energy Regulatory Comm'n , 897 F.3d 241 ( 2018 )

Karst Environmental Education & Protection, Inc. v. ... , 475 F.3d 1291 ( 2007 )

Ralls Corp. v. Committee on Foreign Investment in the ... , 758 F.3d 296 ( 2014 )

Southwest Gas Corp. v. Federal Energy Regulatory Commission , 145 F.3d 365 ( 1998 )

The Humane Society of the United States v. Environmental ... , 790 F.2d 106 ( 1986 )

Sierra Club v. U.S. Dep't of the Interior , 899 F.3d 260 ( 2018 )

Weinstein v. Bradford , 96 S. Ct. 347 ( 1975 )

Marsh v. Oregon Natural Resources Council , 109 S. Ct. 1851 ( 1989 )

Maryland Conservation Council, Inc. v. Gilchrist , 808 F.2d 1039 ( 1986 )

David A. Clarke v. United States , 915 F.2d 699 ( 1990 )

Black Oak Energy, LLC v. Federal Energy Regulatory ... , 725 F.3d 230 ( 2013 )

Cellco Partnership v. Federal Communications Commission , 700 F.3d 534 ( 2012 )

Dominion Transmission, Inc. v. Robert Summers , 723 F.3d 238 ( 2013 )

View All Authorities »