- 1 2 3 4 5 6 7 8 UNITED STATES DISTRICT COURT 9 FOR THE EASTERN DISTRICT OF CALIFORNIA 10 11 Michael Harrosh, No. 2:21-cv-01969-KJM-JDP 12 Plaintiff, ORDER 13 v. 14 Tahoe Regional Planning Agency; George and 15 Virginia Johannessen, 16 Defendants. 17 18 George and Virginia Johannessen obtained approval to build a new pier on their lot on the 19 | west shore of Lake Tahoe. Their neighbor to the south, Michael Harrosh, challenges that 20 | approval in this action, which he filed against the Johannessens and the agency charged with the 21 | approval decision, the Tahoe Regional Planning Agency. The Agency has moved to dismiss. As 22 | explained in this order, that motion is denied. At this early stage of the case, the court cannot 23 | conclude the approval was proper. 24 Harrosh now also moves for a preliminary injunction barring construction of a pier while 25 | this case is pending. He has not shown he will suffer irreparable harm in the absence of an 26 | injunction, a prerequisite to injunctive relief. His motion is therefore also denied, as explained in 27 | this order. 1 I. BACKGROUND 2 Lake Tahoe is famous for its beauty, striking blue color, and exceptional clarity. Tahoe- 3 Sierra Pres. Council, Inc. v. Tahoe Reg’l Plan. Agency, 535 U.S. 302, 307 (2002). “It first caught 4 the world’s attention with the 1960 Winter Olympics . . . , when the area became a recreation 5 destination and home to a rapidly expanding population.” Sierra Club v. Tahoe Reg’l Plan. 6 Agency, 840 F.3d 1106, 1108 (9th Cir. 2016). “It has since become the focus not only of 7 admiration for the lake’s beauty and clarity, but of litigation over the efforts to preserve them.” 8 Id. 9 Since the 1950s and ‘60s, greater development in the Lake Tahoe basin has increased 10 runoff and mineral deposits into the lake. Tahoe-Sierra, 535 U.S. at 307. As a result, more algae 11 has begun to grow in the lake’s waters, which have lost their original hue and clarity. See id. at 12 307–08; League to Save Lake Tahoe v. Tahoe Reg’l Plan. Agency, 739 F. Supp. 2d 1260, 1265 13 (E.D. Cal. 2010).1 To address this problem and other concerns, the California and Nevada state 14 legislatures adopted the Tahoe Regional Planning Compact, which Congress approved in the late 15 1960s. See Tahoe-Sierra, 535 U.S. at 309; League to Save Lake Tahoe v. Tahoe Reg’l Plan. 16 Agency, 507 F.2d 517, 518 (9th Cir. 1974) (citing U.S. Const. Art. I, § 10, cl. 3). 17 The Compact is federal law for purposes of a federal court’s subject matter jurisdiction. 18 See League to Save Lake Tahoe, 507 F.2d at 524–25; Lake Tahoe Watercraft Recreation Ass’n v. 19 Tahoe Reg’l Plan. Agency, 24 F. Supp. 2d 1062, 1067–69 (E.D. Cal. 1998). It creates the Tahoe 20 Regional Planning Agency, which adopted a series of regulations. Tahoe-Sierra Pres. Council, 21 Inc. v. Tahoe Reg’l Plan. Agency, 322 F.3d 1064, 1070 (9th Cir. 2003). “Unfortunately,” those 22 regulations “allowed numerous exceptions and did not significantly limit the construction of new 23 residential housing.” Tahoe-Sierra, 535 U.S. at 309. “California became so dissatisfied” with the 24 Agency and its regulations that it “withdrew its financial support and unilaterally imposed stricter 25 regulations on the part of the Basin located in California.” Id. 1 The Ninth Circuit affirmed all relevant portions of this decision in a short, unpublished memorandum disposition. See 469 F. App’x 621 (9th Cir. 2012) (unpublished). It vacated an “alternative holding” that is not relevant for the court’s present purposes. See id. at 621. 1 California and Nevada later amended the Compact and “redefined” the Agency’s 2 “structure, functions, and voting procedures,” and Congress approved these amendments in 1980. 3 Tahoe-Sierra, 535 U.S. at 310. The amended Compact requires the Agency to create 4 “environmental threshold carrying capacities,” that is, environmental standards “necessary to 5 maintain a significant scenic, recreational, educational scientific, or natural value of the region or 6 to maintain public health and safety within the region.” League to Save Lake Tahoe, 739 F. Supp. 7 2d at 1265 (quoting Compact Arts. I(b), II(i), ECF No. 32).2 The amended Compact tasks the 8 Agency with regulating the Lake Tahoe Basin to achieve these thresholds, both by adopting and 9 administering general ordinances, rules and regulations, see, e.g., Compact Art. I(b), and by 10 making decisions about specific projects, see, e.g., id. Art. V(g). 11 This case concerns the second category: specific projects. The Compact defines “project” 12 as “an activity undertaken by any person, including any public agency, if the activity may 13 substantially affect the land, water, air, space or any other natural resources of the region.” Id. 14 Art. II(h); see also Code of Ordinances §§ 2.1.2, 2.2.1, ECF No. 16-2.3 The Compact creates a 15 unique supermajority voting procedure for “approving a project.” Compact Art. III(g)(2). The 16 Agency’s Governing Board conducts the vote. Id. That body is composed of two delegations of 17 seven voting members each. See id. Art. III(a). The members of the first delegation, the 18 “California delegation,” are appointed by the El Dorado and Placer county boards of supervisors, 19 the South Lake Tahoe City Council, the Governor of California, the speaker of the California 20 Assembly, and the California Senate Rules Committee. See id. Art. III(a)(1). Second, the 21 members of the “Nevada delegation” are appointed by the boards of the Douglas and Washoe 22 county commissioners, the Carson City Board of Supervisors, the Governor of Nevada, the 23 Nevada Secretary of State, and the director of the state’s department of conservation and national 24 resources. See id. Art. III(a)(2). Before a project is approved, under subjection (g)(2) of Article 25 III, “the affirmative vote of at least five members from the State in which the project is located 2 The court grants the Agency’s unopposed request for judicial notice of this document’s terms. Those terms are publicly available and cannot reasonably be disputed. See Fed. R. Evid. 201(b). 3 See supra note 2. 1 and the affirmative vote of at least nine members of the governing body are required.” Id. If the 2 Governing Board votes to approve a project, its decision must “be supported by a statement of 3 findings, adopted by the agency.” Id. If a project does not garner the necessary votes, “upon a 4 motion of approval, an action of rejection shall be deemed to have been taken.” Id. 5 The “project” at the center of this case is the Johannessens’ proposal to construct a single- 6 parcel residential pier on their lot. See Compl. ¶¶ 5–7, ECF No. 1. According to the complaint, 7 which for purposes of a motion to dismiss the court accepts as true, Ashcroft v. Iqbal, 556 U.S. 8 662, 678 (2009), the demand for single-parcel residential piers far outstrips available permits, so 9 the Agency holds a lottery in which the winners may apply for a pier permit. See id. ¶¶ 24, 30; 10 Code of Ordinances § 84.4.4(C)(1). In the summer of 2019, the Johannessens won a chance to 11 apply for a permit. Compl. ¶ 40. They submitted their plan to the Agency about six months later. 12 Id. ¶ 41. Harrosh owns land just to the south of the Johannessens. Id. ¶¶ 5, 11. His property 13 already has a pier. Id. ¶¶ 5–6. He claims that if the Johannessens’ planned pier is constructed, it 14 would be difficult and dangerous to approach his own pier from the water. See id. ¶ 7. 15 The Johannessens’ application was referred to the hearings officer, who held a meeting in 16 late Spring 2021. See id. ¶ 50. Harrosh presented evidence in opposition to the Johannessens’ 17 application, id. ¶ 68, but the hearings officer approved the application and issued a permit, id. 18 ¶¶ 70–75. Harrosh pursued an appeal to the Governing Board. See id. ¶ 79. The Agency’s 19 general counsel advised the Board during the appeal. See id. ¶ 87. He told the Board the first 20 step was to decide whether it would “accept” or “reject” the appeal, then to decide whether to 21 modify or reject the permit. Id. He said that if at least five members of the California delegation 22 and at least nine members overall voted “aye,” then the Board would “accept” the appeal and 23 could either modify or reject the hearings officer’s decision. Id. ¶¶ 87–88. Otherwise, counsel 24 explained, the Board would “reject” the appeal, the hearings officer’s decision would stand, and 25 the Agency would issue a permit to the Johannessens. See id. ¶ 88. Counsel recommended 26 rejecting the appeal. Id. ¶ 86. 27 There were two vacancies among the seven-member California delegation at the time. Id. 28 ¶ 81. As a result, given counsel’s instructions, if even a single member of the California 1 delegation did not vote “aye,” then the Governing Board would reject the appeal. This appeared 2 to doom Harrosh’s appeal from the outset: one member of the California delegation, Cindy 3 Gustafson, told the Board at the beginning of the meeting that she had a “long-standing social 4 relationship with the Harrosh family,” she had visited their home and pier for social events, and 5 she had discussed the appeal with the Harrosh family before the hearing. Id. ¶ 85. If she voted 6 for Harrosh, then any decision to accept the appeal and reject the permit could be subject to attack 7 based on the appearance of her partiality. If she voted for the Johannessens, the appeal would 8 necessarily be rejected. The result would be the same if she abstained. 9 The Governing Board heard evidence, the parties’ arguments, and public comments, and 10 board members made comments. Id. ¶¶ 89–90. Board members then voted. Ms. Gustafson 11 abstained, and all other board members voted “no.” See id. ¶¶ 92–97. The Board thus rejected 12 the appeal by default. 13 Harrosh filed this action after the vote, asserting four claims. His first claim can be 14 expressed in a variety of ways, but it boils down to a simple theory: the Governing Board’s vote 15 was invalid because the Compact requires at least five “affirmative” votes from the California 16 delegation to approve a permit, but only four members of the California delegation voted to reject 17 his appeal. See id. ¶¶ 108–20. In his second claim, he alleges the Agency misinterpreted its Code 18 of Ordinances, which imposes specific limits on pier lengths. See id. ¶¶ 121–37. Third, he 19 alleges the Agency was wrong to conclude the Johannessens’ pier would not be a threat to public 20 safety. See id. ¶¶ 138–51. Fourth, he alleges the hearing and appeal procedure violated his Fifth 21 Amendment right to due process. See id. ¶¶ 152–68. He seeks declaratory judgment, an 22 injunction, nominal damages, fees, costs, and any other relief the court deems just and proper 23 under the circumstances. Id. at 25–26. 24 The Agency moves to dismiss the first and fourth claims, but not the second and third. 25 See generally Mot. Dismiss, ECF No. 14; Mem. Dismiss, ECF No. 15. The matter has been fully 26 briefed. See generally Opp’n Dismiss, ECF No. 23; Reply Dismiss, ECF No. 25. The 27 Johannessens joined the Agency’s reply brief, but not its motion. See generally Joinder, ECF No. 28 26. The court heard oral argument at a hearing earlier this year, on March 25, 2022, and 1 submitted the matter for decision. Peter Prows and Anthony Francois appeared for Harrosh. 2 Debbie Leonard and John Marshall appeared for the Tahoe Regional Planning Agency. Kristen 3 Castanos and Lauren Neuhaus appeared for the Johannessens. 4 Before hearing, the parties stipulated to dismissal of Harrosh’s fourth claim under Federal 5 Rule of Civil Procedure 41(a)(1)(A)(ii). See Stip., ECF No. 28. The Ninth Circuit has held 6 litigants may not dismiss claims piecemeal by stipulation under Rule 41(a)(1), as that rule refers 7 to “actions,” not claims. See Hells Canyon Pres. Council v. U.S. Forest Serv., 403 F.3d 683, 8 687–89 (9th Cir. 2005). A district court may, however, construe such a stipulation as an 9 unopposed request to amend the complaint and withdraw the claim in question under Rule 15(a). 10 See id. at 688–89. The court construes the stipulation in this way and grants the request to amend 11 under Rule 15(a). The motion to dismiss, then, challenges only the first claim. 12 After hearing and while the motion to dismiss was pending, the Johannessens obtained 13 other necessary permits for the proposed pier, including from the U.S. Army Corps of Engineers 14 and the California State Lands Commission. See Req. J. Not. ¶¶ 2–4 & Exs. 2–4, ECF No. 36-1.4 15 They began construction in October 2022. S. Harrosh Decl. ¶ 3, ECF No. 34-2. Harrosh then 16 sought a temporary restraining order. See generally App. TRO, ECF No. 34. The court 17 temporarily restrained the pier’s construction until it could hold a hearing on a preliminary 18 injunction in light of the potential environmental harms. See generally TRO, ECF No. 35. The 19 court held the hearing on November 8, 2022 after receiving responses from the defendants. See 20 Johannessen Resp., ECF No. 36; TRPA Resp., ECF No. 37.5 At this hearing, Anthony Francois 21 and Peter Prows appeared for the plaintiff, John Marshall appeared for the Agency, and Kristen 22 Castanos, Gregory Gatto, and Michael Mills appeared for the Johannessens. 23 After hearing, the court dissolved the temporary restraining order and denied the motion 24 for a preliminary injunction by minute order, specifying that a “written order fully explaining the 4 The court takes judicial notice of these documents as undisputed matters of public record. See Fed. R. Civ. P. 201(b). 5 Harrosh objected to some of the evidence submitted with the Johannessens’ response. See Objs., ECF Nos. 38, 44. The court has not relied on any of the evidence in question; Harrosh’s objections are overruled as moot. 1 court’s decision will soon issue.” ECF No. 40. Later that day, Harrosh filed a motion for an 2 injunction pending appeal, ECF No. 42, which the court also denied by minute order, again 3 stating that a written order more fully explaining the court’s decision would soon issue, ECF 4 No. 46. This order explains the court’s decision on the request for a preliminary injunction and 5 addresses the motion for injunction pending appeal. 6 II. MOTION TO DISMISS 7 A party may move to dismiss for “failure to state a claim upon which relief can be 8 granted.” Fed. R. Civ. P. 12(b)(6). The motion may be granted if the complaint lacks a 9 “cognizable legal theory” or if its factual allegations do not support a cognizable legal theory. 10 Godecke v. Kinetic Concepts, Inc., 937 F.3d 1201, 1208 (9th Cir. 2019) (quoting Balistreri v. 11 Pacifica Police Dep’t, 901 F.2d 696, 699 (9th Cir. 1988)). The court assumes all factual 12 allegations are true and construes “them in the light most favorable to the nonmoving party.” 13 Steinle v. City & Cnty. of San Francisco, 919 F.3d 1154, 1160 (9th Cir. 2019) (quoting Parks Sch. 14 of Bus., Inc. v. Symington, 51 F.3d 1480, 1484 (9th Cir. 1995)). If the complaint’s allegations do 15 not “plausibly give rise to an entitlement to relief,” the motion must be granted. Ashcroft v. Iqbal, 16 556 U.S. 662, 679 (2009). 17 The Agency advances three arguments for dismissal. First, it argues Harrosh’s first claim 18 is barred because he did not first raise it during the agency proceedings. Second, it argues the 19 claim was filed after the limitations period had expired. Third, it contends its interpretation of the 20 Compact’s voting procedures is reasonable, entitled to deference, and valid. The court considers 21 each of these arguments in turn. 22 A. Did Harrosh exhaust his claim that the Governing Board’s vote is invalid? 23 “It is a well-known axiom of administrative law that ‘if a petitioner wishes to preserve an 24 issue for appeal, he must first raise it in the proper administrative forum.’” Barron v. Ashcroft, 25 358 F.3d 674, 677 (9th Cir. 2004) (quoting Tajeda-Mata v. I.N.S., 626 F.2d 721, 726 (9th Cir. 26 1980)).6 Congress has often imposed this rule by statute. United States v. L. A. Tucker Truck 6 “Issue exhaustion should not be confused with exhaustion of administrative remedies.” 1 Lines, Inc., 344 U.S. 33, 36–37 & n.6 (1952); see also Sims v. Apfel, 530 U.S. 103, 107–08 (2000) 2 (listing examples). “Similarly, it is common for an agency’s regulations to require issue 3 exhaustion in administrative appeals,” and when they do, “courts reviewing agency action 4 regularly ensure against the bypassing of that requirement by refusing to consider unexhausted 5 issues.” Sims, 530 U.S. at 108. 6 The Supreme Court also has “imposed an issue-exhaustion requirement even in the 7 absence of a statute or regulation.” Id. The judge-made exhaustion rule serves several interests. 8 One is “[s]imple fairness to those who are engaged in the tasks of administration, and to 9 litigants.” L. A. Tucker Truck Lines, 344 U.S. at 36–37. “[C]ourts should not topple over 10 administrative decisions unless the administrative body not only has erred but has erred against 11 objection made at the time appropriate under its practice.” Id. The exhaustion rule also permits 12 agencies to correct their own errors. Weinberger v. Salfi, 422 U.S. 749, 765 (1975). Just as 13 litigants in a trial court should “have the opportunity to offer all the evidence they believe 14 relevant” before an appellate court ultimately weighs in, and just as those same parties have an 15 interest in avoiding surprises on appeal, so, too, the participants in an administrative process have 16 an interest in a complete and final administrative procedure. Hormel v. Helvering, 312 U.S. 552, 17 556 (1941). 18 In addition, agencies often have technical expertise, and Congress may have granted an 19 agency the authority to exercise discretion. If litigants could raise arguments for the first time in 20 a judicial complaint, they might deprive both the court of the agency’s expertise and the agency 21 of its discretionary powers. See McKart v. United States, 395 U.S. 185, 194 (1969). But even 22 when a dispute falls within a court’s traditional area of expertise, such as interpreting a statute, 23 the exhaustion rule may serve an important purpose. A court may ultimately need to consider the 24 agency’s interpretation of its governing statute. See Chevron, U.S.A., Inc. v. Nat. Res. Def. 25 Council, Inc., 467 U.S. 837, 844 (1984); California ex rel. Van de Kamp v. Tahoe Reg’l Plan. 26 Agency, 766 F.2d 1308, 1313 (9th Cir. 1985). The exhaustion rule helps to “ensure that through each step of the hearing and review process laid out in the Compact and the Agency’s regulations before he filed this action; he has thus exhausted his administrative remedies. 1 challenges to an agency’s interpretation of its governing statute are first raised in the 2 administrative forum.” Nuclear Energy Institute, Inc. v. Envt’l Prot. Agency, 373 F.3d 1251, 3 1298 (D.C. Cir. 2004) (quoting Nat. Res. Def. Council v. EPA, 25 F.3d 1063, 1074 (D.C. Cir. 4 1994)). 5 Courts do not enforce this exhaustion rule reflexively. It “should be applied with a regard 6 for the particular administrative scheme at issue.” Weinberger, 422 U.S. at 765. “[L]ike most 7 judicial doctrines,” it is also “subject to numerous exceptions.” McKart, 395 U.S. at 193. For 8 example, a court “may decide an issue not raised in an agency action if the agency lacked either 9 the power or the jurisdiction to decide it.” Reid v. Engen, 765 F.2d 1457, 1460–61 (9th Cir. 10 1985). “This situation is typified by challenges to the constitutionality of a statute or challenges 11 to the constitutionality of a regulation promulgated by the agency.” Id. at 1461 (citations 12 omitted). The Supreme Court “has often observed that agency adjudications are generally ill 13 suited to address structural constitutional challenges, which usually fall outside the adjudicators’ 14 areas of technical expertise.” Carr, 141 S. Ct. at 1360. The Court has also “consistently 15 recognized a futility exception to exhaustion requirements.” Id. at 1361 (collecting authority). “It 16 makes little sense to require litigants to present claims to adjudicators who are powerless to grant 17 the relief requested.” Id. The Supreme Court has boiled the question down to a comparison test. 18 In the absence of a statute or regulation, a court asks whether the administrative proceeding in 19 question is “adversarial” or “inquisitorial.” See Carr, 141 S. Ct. at 1358–59. When “the parties 20 are expected to develop the issues in an adversarial administrative proceeding, . . . the rationale 21 for requiring issue exhaustion is at its greatest.” Sims, 530 U.S. at 110. By contrast, if “an 22 administrative proceeding is not adversarial, . . . the reasons for a court to require issue 23 exhaustion are much weaker.” Id. 24 The statutory law that governs this case—the Tahoe Regional Planning Compact—does 25 not demand that a person raise an issue in an administrative procedure before filing a judicial 26 complaint. It simply permits judicial complaints and defines the standard of review. See 27 Compact Art. VI(j). The Agency does not argue otherwise. See Mem. Dismiss at 10–11; Reply 1 Dismiss at 7–9. As it confirmed at hearing, it relies instead on its regulations. A few more details 2 about those regulations put the parties’ dispute in context. 3 Under the Agency’s Code of Ordinances, some “projects” must be approved by the 4 Governing Board in the first instance. See Code of Ordinances § 2.2.2. This is true, for example, 5 of tour boat operations and airport expansions. See id. § 2.2.2(D)(1)(b), (F)(1)(a). For other 6 projects, such as short recreational trails and smaller commercial projects, the Governing Board 7 has delegated the initial decision to the Agency’s staff, subject to an appeal. See, e.g., id. 8 §2.2.2(E)(2)(a), (G)(1), (G)(3). The Agency has tasked a “hearings officer” with making 9 decisions about project applications. See Rules of Procedure Art. 14, ECF No. 16-3.7 The 10 hearings officer reviews projects in public hearings after giving advance notice to affected 11 property owners. Id. §§ 14.1, 14.3, 14.4. The hearings officer can approve or disapprove the 12 project, continue the hearing, or refer the decision to the Governing Board. Id. § 14.2. 13 After the hearings officer makes a decision, the project’s proponent, any affected property 14 owners, or anyone who participated as a party may appeal the hearings officer’s decision to the 15 Board. See id. § 14.6. If the hearings officer denied the project, the board reviews “de novo . . . 16 subject to the same procedure and vote requirements that would apply had the project or matter 17 originally been reviewed by the Board.” Id. § 11.5. If, on the other hand, the hearings officer 18 approved the project, the board can decline to hear the appeal by the vote of any eight members. 19 See id. § 11.6.1. If the Board hears the appeal, “it may take action to modify or revoke the 20 approval by the same affirmative vote as would have been required to approve the matter before 21 the Board.” Id. § 11.6.2. “Failure to take such action shall be deemed a denial of the appeal.” Id. 22 Then, as noted above, the Compact permits any “aggrieved” party to challenge the Board’s 23 decision “in an appropriate court of the States of California or Nevada or of the United States.” 24 Compact Art. VI(j)(3). 25 The Agency’s rules of procedure impose only one exhaustion requirement over the course 26 of these proceedings. Any appeal from a hearings officer’s decision must include a “written 27 statement of appeal.” Rules of Procedure § 11.2. “The written statement of appeal shall include 7 See supra note 2. 1 the name and address of the appellant and a detailed and specific explanation of the ground for 2 the appeal.” Id. § 11.4 “Arguments and bases for appeals that are not included in the statement 3 of appeal or staff’s position paper shall neither be raised nor considered by the Board.” Id. 4 Harrosh does not say in his complaint whether he challenged the Board’s voting procedure 5 in his statement of appeal. The Agency requests judicial notice of a document it claims is 6 Harrosh’s publicly filed statement of appeal, see Req. J. Not. Ex. 12, ECF No. 16-12, and Harrosh 7 does not oppose that request or contest the document’s authenticity. The court thus grants the 8 Agency’s request for judicial notice and considers that document without converting the motion 9 into a motion for summary judgment. See, e.g., United States v. 14.02 Acres of Land More or 10 Less in Fresno Cty., 547 F.3d 943, 955 (9th Cir. 2008); see also, e.g., Smith v. L.A. Unified Sch. 11 Dist., 830 F.3d 843, 851 n.10 (9th Cir. 2016) (“[C]ourts routinely take judicial notice of . . . 12 records and reports of administrative bodies.” (citation and quotation marks omitted)). 13 Upon review, then, the statement of appeal does not include arguments about the Board’s 14 voting procedure, but that omission is not fatal. The Agency’s procedural rules required Harrosh 15 to describe the grounds for his appeal of the hearings officer’s decision, and he did that. See 16 generally Req. J. Not. Ex. 12 (asserting hearings officer erred procedurally and relied on incorrect 17 findings). The omitted challenge—that the Board’s vote was invalid under the Compact—is not a 18 challenge to the hearings officer’s decision; it targets the Board’s vote. Harrosh could not have 19 challenged the Board’s vote before that vote occurred, so the agency’s procedural rules do not 20 impose an exhaustion requirement that applies to the complaint’s first claim. 21 The Agency characterizes that first claim broadly in an attempt to convert it into a 22 challenge that Harrosh could and should have raised in his statement of appeal. It argues, for 23 example, that when he appeared “before the Hearings Officer, [he] did not dispute the Governing 24 Board’s ability to delegate authority to the Hearings Officer to issue a pier permit.” Mem. 25 Dismiss at 10. But the complaint does not broadly challenge the Agency’s delegation of authority 26 to a hearings officer. Harrosh concedes the Board may delegate authority to a hearings officer, 27 and he admits the appeals procedure does not necessarily violate the Compact. Opp’n Dismiss at 28 18 n.5. For example, at hearing, his counsel suggested it may be possible under the Compact for 1 the Board to delegate authority to a hearings officer to make findings and recommendations, then 2 hold a vote using an abbreviated procedure, such as a consent calendar, if no party objects or 3 appeals. 4 Some allegations in the complaint do suggest, however, that Harrosh is contesting the 5 Agency’s regulations generally. He claims, for example, that the regulations violate the Compact 6 “by allowing the approval of projects without an affirmative vote of five members of the Board 7 from the state in which the project is to take place.” Compl. ¶ 111. Similarly, he claims the 8 regulations wrongly require “a non-applicant appellant from a project approval of the Hearings 9 Officer to obtain five state-specific votes in favor of the appeal, instead of requiring the applicant 10 to obtain five state-specific votes in favor of the application.” Id. ¶ 113. Theoretically, Harrosh 11 could have raised these challenges before the final hearing and vote in his statement of appeal. If 12 he did, however, he would have been forced to raise the issue by guessing what might happen: if 13 the Board required Harrosh to secure five affirmative votes, if he failed to secure those 14 affirmative votes, if the Board ultimately upheld the hearings officer’s decision and issued a 15 permit, and if the disputed voting procedure caused the outcome to change, then the vote would 16 violate the Compact. Nothing in the Agency’s Code of Procedure suggests a person must raise 17 such a conjectural and contingent claim in its statement of appeal. 18 For these reasons, the court concludes Harrosh did not fall short of any statutory or 19 regulatory exhaustion requirement. If there is an exhaustion requirement, then it must arise under 20 the more general, judge-made rule. As noted above, whether to impose that requirement is a 21 question of comparison: if the agency proceedings are analogous to the adversarial fact-finding 22 process of trial-court litigation, then “the rationale for requiring issue exhaustion is at its 23 greatest.” Sims, 530 U.S. at 110. The parties have not addressed this question, and the court 24 declines to answer it conclusively at this early stage. For now, it is enough to note five 25 considerations that weigh against the Agency, which bears the burden “to demonstrate that the 26 requirements of Rule 8(a)(2) have not been met.” Gallardo v. DiCarlo, 203 F. Supp. 2d 1160, 27 1165 (C.D. Cal. 2002). 1 First, as explained above, imposing a strict issue-exhaustion requirement in this case 2 would demand the exhaustion of a hypothetical argument about how the board might eventually 3 vote. The court declines to demand at this point that every contingency be raised and every 4 theory tested in the Agency’s appeals process. 5 Second, nothing in the Compact or the Agency’s regulations suggests a hearings officer 6 has authority to invalidate regulations or relieve Harrosh from compliance with those regulations. 7 If Harrosh had pressed a broad delegation claim in the meeting with the hearings officer, then 8 there were only two possibilities: (1) the hearings officer could decide the Agency’s regulations 9 constrained him and reject the argument out of hand, or (2) the hearings officer could have 10 referred the argument to the full Board. In neither scenario would the hearings officer have added 11 any useful fact-finding or analysis to the record, and the Board would have confronted Harrosh’s 12 claims about the voting procedure in the first instance, just as he alleges it eventually did. See 13 Compl. ¶ 89. 14 Third, similarly, it is unclear whether the Agency could have granted Harrosh the relief he 15 requested. If Harrosh is correct that the Agency’s appeals process violates the Compact in 16 situations like this one, then the Agency would presumably need to amend its regulations or make 17 an ad hoc exception. Whether it had the power to do so in the hearing on Harrosh’s appeal is a 18 question neither party has addressed. If it did not have this power, it would have been futile for 19 Harrosh to raise the issue before the vote. 20 Fourth, the heart of Harrosh’s first claim is a question of statutory interpretation. The 21 Agency’s interpretations of the Compact might be entitled to deference, but not if the relevant 22 statutory is unambiguous. See Van de Kamp, 766 F.2d at 1313 (citing Chevron 467 U.S. 837). 23 Deciding what a statute means and whether it is ambiguous “does not require any particular 24 expertise on the part of the [Agency]; the proper interpretation is certainly not a matter of 25 discretion.” McKart, 395 U.S. at 198. “The judiciary is the final authority on issues of statutory 26 construction and must reject administrative constructions which are contrary to clear 27 congressional intent.” Chevron, 467 U.S. at 843 n.9. 1 Finally, Harrosh alleges he did in fact raise the core of his first claim during his 2 administrative appeal. He alleges he “appeared through counsel and personally at the August 25 3 appeal hearing” and “raised objections . . . to the voting procedure being used in the appeal.” 4 Compl. ¶ 89. The court must assume this allegation is true at this stage. The agency had a fair 5 opportunity to consider his arguments. The court will not dismiss the first claim for failure to 6 exhaust. 7 B. Did Harrosh pursue his claim before the limitations period expired? 8 Under the Compact, any “legal action arising . . . out of the granting or denial of any 9 permit” must begin “within 60 days after the final action by the agency.” Compact Art. VI(j)(4). 10 The parties disagree what the “final action” was in this case. Harrosh argues it was the 11 Governing Board’s decision to reject his appeal. See Compl. ¶ 109. The Board made its decision 12 on August 25, 2021, and he filed this action on October 22, 2021, less than sixty days later. See 13 id. The Agency argues the “final action” was its decision as a matter of policy to delegate permit 14 approvals to a hearings officer, which it made many years ago. See Mem. Dismiss at 9. If it is 15 right, then the first claim is untimely. 16 Both Harrosh and the Agency rely on cases interpreting the Administrative Procedure Act 17 (APA). See Opp’n Dismiss at 11 (citing Cal. Sea Urchin Comm’n v. Bean, 828 F.3d 1046 (9th 18 Cir. 2016)); Reply Dismiss at 7 (citing, among other authorities, Shiny Rock Mining Corp. v. 19 United States, 906 F.2d 1362 (9th Cir. 1990)). The analogy is useful. Like the Compact, the 20 APA includes a limitation period tied to the date of “final agency action.” See, e.g., Bennett v. 21 Spear, 520 U.S. 154, 177–78 (1997) (citing 5 U.S.C. § 704). As the Agency does in this case, 22 defendants in cases brought under the APA have moved to dismiss based on an argument that the 23 “final agency action” in question occurred many years before, i.e., when the agency adopted the 24 rule or regulation behind the plaintiff’s lawsuit. See, e.g., Cal. Sea Urchin Comm’n, 828 F.3d at 25 1049. 26 Two basic accrual rules have emerged in similar cases interpreting the APA. First, if a 27 plaintiff challenges the policy behind an agency rule or regulation or the process the agency used 28 to adopt that rule or regulation, the “final agency action” is the adoption of those rules or 1 regulations. See Wind River Min. Corp. v. United States, 946 F.2d 710, 715 (9th Cir. 1991); 2 Shiny Rock, 906 F.2d at 1365; Sierra Club v. Penfold, 857 F.2d 1307, 1315–16 (9th Cir. 1988). A 3 plaintiff cannot extend the limitations period artificially by arguing the “final agency action” is 4 actually the agency’s application or enforcement of the rule or regulation in question. 5 For example, in Shiny Rock, the Bureau of Land Management (BLM) had withdrawn an 6 area of federal land from appropriation under U.S. mining laws and given notice of its decision in 7 the Federal Register. See 906 F.2d at 1363. Many years later, the BLM denied a mining 8 company’s application for a mineral patent related to the withdrawn land. See id. The mining 9 company sued, arguing the BLM had made procedural errors when it made its decision many 10 years before. See id. The BLM argued the clock had started ticking on the day the notice was 11 published in the Federal Register. See id. at 1364. The court agreed. See id. at 1364–66. The 12 Federal Register put potential challengers on notice, and it did not matter that the mining 13 company did not suffer any injury until its application was denied. See id. Any other rule “would 14 virtually nullify the statute of limitations for challenges to agency orders” by allowing the original 15 rule to be challenged with every permit denial. Id. at 1365. 16 A different rule applies to claims that an agency exceeded its constitutional or statutory 17 authority. See Wind River, 946 F.2d at 715. For these challenges, the “final agency action” can 18 occur later. See id. “The government should not be permitted to avoid all challenges to its 19 actions, even if ultra vires, simply because the agency took the action long before anyone 20 discovered the true state of affairs.” Id. at 715. “The statute of limitations would cease to be a 21 shield against stale claims, and would instead become a sword to vanquish a challenge . . . 22 without ever considering the merits.” Cal. Sea Urchin Comm’n, 828 F.3d at 1051. 23 The Wind River decision adopting this rule illustrates its rationale and application. In the 24 case, another mining company challenged a BLM mining permit decision. See 946 F.2d at 711. 25 As in Shiny Rock, the permit decision was based on a years-old notice designating the land in 26 question a federal “wilderness study area.” See id. By federal law, however, an area could be a 27 wilderness study area only if it contained no roads, among other criteria. See id. The mining 28 company alleged the agency had acted outside its authority because the land in question was not 1 actually roadless, and it alleged the designation represented an unconstitutional taking. See id. at 2 712. “[N]o one was likely to have discovered that the [original designation] was beyond the 3 agency’s authority until someone actually took an interest in that particular piece of property, 4 which only happened when [the plaintiff] staked its mining claims.” Wind River, 946 F.2d at 715. 5 The Ninth Circuit held the mining company’s complaint had been filed within the limitations 6 period. See id. at 715–16. 7 The Ninth Circuit’s decision in California Sea Urchin Commission illustrates another 8 motivation for this second rule: some challenges are too abstract or too theoretical for meaningful 9 litigation until much later. In 1986, Congress authorized the U.S. Fish and Wildlife Service to 10 develop and implement a plan to relocate and manage a population of California sea otters. See 11 828 F.3d at 1047. The Fish and Wildlife Service developed a plan, but its plan included several 12 criteria that might lead to the plan’s termination. See id. at 1048. In 2012, the Fish and Wildlife 13 Service terminated the program, applying these criteria. See id. A number of commercial fishing 14 groups then filed a lawsuit alleging the rule was outside the agency’s statutory authority: 15 Congress had authorized the agency to develop and implement a plan, but not to terminate the 16 plan. See id. The agency argued the challenge had come too late, but the Circuit disagreed, citing 17 Wind River and distinguishing Shiny Rock. See id. at 1049–52. “If parties had to challenge the 18 . . . termination criteria within six years of 1987, then any such challenge predating the program’s 19 termination would necessarily have been theoretical.” Id. at 1052. “A plaintiff cannot be 20 expected to anticipate all possible future challenges to a rule and bring them within six years of 21 the rule’s promulgation, before a later agency action applying the earlier rule leads to an injury.” 22 Id. at 1049–50. 23 Turning back to this case, Harrosh is not challenging the procedure the Agency used when 24 it adopted its rules of procedure or its appellate process. Nor does he contest the policy behind 25 those rules. This case is therefore unlike Shiny Rock. He argues instead that the Agency has 26 created a voting procedure in conflict with the Compact. His claims are thus analogous to the 27 statutory and constitutional claims at issue in Wind River and California Sea Urchin Commission. 28 If the Agency has in fact acted outside its statutory authority, it should not be permitted to 1 continue simply because it has erred for many years. It was unlikely anyone would discover a 2 potential problem until just the right case, or just the wrong case, finally wound its way to a 3 Board vote, i.e., an appeal by a third party challenging a permit approval by a hearings officer 4 decided by a single abstention. If someone had discovered this potential problem, it would have 5 been theoretical before now. The “final action” for purposes of the Compact’s limitations period 6 in this case was thus the Board’s decision to reject Harrosh’s appeal. His complaint was timely. 7 C. Has Harrosh stated a claim for relief based on the Board’s vote? 8 What remains, then, is the core of Harrosh’s claim. Did the Governing Board’s vote 9 conflict with the Compact? The court begins by reviewing the rules for interpreting the 10 Compact’s terms and the Agency’s regulations. 11 The Compact permits courts to hear “[a]ctions arising out of the issuance to a person of a 12 lease, permit, license or other entitlement for use by the agency.” Compact Art. VI(j)(1)(B). 13 When a person challenges the Agency’s decision “to approve or disapprove a project,” the 14 Compact limits the court’s review “to whether there was prejudicial abuse of discretion.” Id. Art. 15 VI(j)(5). “Prejudicial abuse of discretion is established if the agency has not proceeded in a 16 manner required by law or if the act or decision of the agency was not supported by substantial 17 evidence in light of the whole record.” Id. “[T]he court shall not exercise its independent 18 judgment on evidence but shall only determine whether the act or decision was supported by 19 substantial evidence in light of the whole record.” Id. 20 In at least one case, the Ninth Circuit has given deference to the Agency’s administration 21 of the Compact under Chevron. See Van de Kamp, 766 F.2d at 1313 (citing 467 U.S. 837).8 8 Although the Ninth Circuit applied Chevron to the Tahoe Regional Planning Agency’s interpretations of the governing Compact in Van de Kamp, the Agency is not a federal agency; its officers act under color of state law. Lake Country Ests., Inc. v. Tahoe Reg’l Plan. Agency, 440 U.S. 391, 399 (1979); Comm. for Reasonable Regul. of Lake Tahoe v. Tahoe Reg’l Plan. Agency, 365 F. Supp. 2d 1146, 1156 (D. Nev. 2005) (citing Cal. Tahoe Reg’l Plan. Agency v. Sahara Tahoe Corp., 504 F. Supp. 753, 762 (D. Nev. 1980)). State agencies’ interpretations of federal law are not entitled to deference under Chevron. See Orthopaedic Hosp. v. Belshe, 103 F.3d 1491, 1495 (9th Cir. 1997); AT&T Commc’ns of Cal., Inc. v. Pac. Bell, No. 97-0080, 1998 WL 246652, at *4 (N.D. Cal. May 11, 1998), aff’d, 203 F.3d 1183 (9th Cir. 2000). This court need not dwell on this potential mismatch of authority. First, Van de Kamp is binding no matter 1 Under that standard, the court first decides whether the relevant statutory terms are ambiguous. 2 See Chevron, 467 U.S. at 842. If not, then “that is the end of the matter.” Id. If the statute is 3 ambiguous, however, “the court does not simply impose its own construction on the statute, as 4 would be necessary in the absence of an administrative interpretation.” Id. at 843. “[T]he 5 question for the court is whether the agency’s answer is based on a permissible construction of 6 the statute.” Id. “If it is, then the agency’s interpretation controls. A court may not supplant 7 reasonable agency regulations with its own.” Van De Kamp, 766 F.2d at 1313 (citing Chevron, 8 467 U.S. at 843). 9 This court’s first task is thus to decide whether the relevant Compact provisions are 10 ambiguous. Courts interpret the Compact using the ordinary rules of statutory interpretation. See 11 League to Save Lake Tahoe, 739 F. Supp. 2d at 1265. The “plain meaning of the language in 12 question” is the place to start. S & M Inv. Co. v. Tahoe Reg’l Plan. Agency, 911 F.2d 324, 326 13 (9th Cir. 1990). “If the term at issue has a settled meaning,” the court “must infer that the 14 legislature meant to incorporate the established meaning, unless the statute dictates otherwise.” 15 Id. The Compact’s structure and purpose “as a whole” can also inform the court’s decision. Van 16 De Kamp, 766 F.2d at 1314. 17 The relevant Compact provisions are unambiguous. Under the Compact, the construction 18 of a new pier is a “project” if it is an “activity” that “may substantially affect the land, water, air, 19 space or any other natural resources of the region.” Compact Art. II(h). Construction of a new 20 pier is a “project” under this description. The Agency’s regulations list shorezone structures 21 among the “projects” that require its approval. See Code of Ordinances § 2.1.2 (“This chapter 22 identifies activities that may have a substantial effect on the land, air, water, or any other 23 resources and therefore are projects subject to [the Agency’s] review and approval); id. (en banc). Second, the Compact’s language is unambiguous, as explained below, so this court need not decide what deference to accord. Third, even if Chevron were inapplicable, the Agency’s decisions could likely be entitled to deference nonetheless, for example under state law, see, e.g., United Educators of San Francisco etc. v. Cal. Unemployment Ins. Appeals Bd., 8 Cal. 5th 805, 820 (2020), or a case-specific doctrine tailored to the Agency’s unique role as the Compact’s administrator, cf. United States v. Mead Corp., 533 U.S. 218, 228 (2001) (discussing Skidmore v. Swift & Co., 323 U.S. 134 (1944)). 1 §2.2.2(F)(2)(b) (“Shorezone Projects . . . New structures . . .”). The Agency does not argue 2 otherwise. It agreed at hearing that a pier is a “project” under the terms of the Compact. Because 3 pier construction is a “project,” the approval procedure is prescribed by Article III(g)(2): “For 4 approving a project, the affirmative vote of at least five members from the State in which the 5 project is located and the affirmative vote of at least nine members of the governing body are 6 required.” The Johannessens’ pier would be built in California. Compl. ¶¶ 5–7. Applying these 7 provisions together, the Agency could approve the Johannessens’ new pier only if five members 8 of the California delegation voted affirmatively to approve it. According to the complaint, they 9 did not, so the first claim may proceed. 10 The Agency advances a number of counterarguments, but none is persuasive. First, it 11 contends the Compact permits it to delegate approval decisions to an officer or staff member. See 12 Mem. Dismiss at 11–12. It is true the Compact expressly permits the Governing Board to appoint 13 an executive officer and to employ other staff and legal counsel. See Compact Art. IV(a). The 14 Compact also expressly permits the Agency to adopt rules, regulations, and ordinances. See id. 15 Art. I(b)–(c), Art. III(g)(1), Art. VI(a). But the authority to appoint staff and to create rules and 16 regulations is not the authority to modify or contradict the Compact itself. See Van De Kamp, 17 766 F.2d at 1314–15. If it were, then the Agency could override the legislatures of two states and 18 the United States Congress. It does not have that power. “Where Congress has established a 19 clear line, the agency cannot go beyond it; and where Congress has established an ambiguous 20 line, the agency can go no further than the ambiguity will fairly allow.” City of Arlington, Tex. v. 21 F.C.C., 569 U.S. 290, 307 (2013). 22 The Agency cites no exception to the Compact’s voting rules, and the court has found 23 none. Contrary to the Agency’s argument, Article VI(b) does not excuse the pier from approval 24 by requiring approval by “the agency.” The Compact explains expressly how “the agency” can 25 approve a project: a vote by its Governing Board under Article III(g)(2). The Agency contends 26 Article VI(b) contemplates that a staff member could approve a project because it refers to “the 27 agency” rather than, for example, “the board” or “governing body.” See Mem. Dismiss at 11–12. 28 That cannot be. If the Agency could assign a staff member to approve any projects it liked, then 1 it could bypass the voting procedure in Article III entirely. That voting procedure would then be 2 superfluous, a result this court must avoid. Van de Kamp, 766 F.2d at 1314. 3 The Agency cannot sidestep this problem by pointing out that the Board voted implicitly 4 to approve this and other projects when it voted to adopt rules and regulations delegating 5 authority to staff, as it suggested at the hearing before this court. The Compact creates a different 6 voting procedure “[f]or adopting, amending or repealing . . . ordinances, rules and regulations, 7 and for granting variances from the ordinances, rules and regulations.” Compact Art. III(g)(1). 8 That voting procedure requires only four votes from each state’s delegation. See id. If the 9 Agency were correct that it could approve a project by adopting an ordinance or procedural rule, 10 then it could bypass the stricter procedure for approving projects. 11 The Agency also emphasizes the Compact is intended “in part ‘to enhance the efficiency 12 and governmental effectiveness of the region.’” Mem. Dismiss at 12 (quoting Art. I(b)). The 13 Agency argues it would be “unreasonable to construe the Compact to require the Governing 14 Board to vote to approve every permit the agency issues” because doing so would “bog down the 15 approval process and create needless duplication of efforts.” Id. This argument has three flaws. 16 First, broad statements of purpose do not control over specific and express provisions. 17 See, e.g., Bloate v. United States, 559 U.S. 196, 207 (2010). The Compact’s broad hortatory 18 language about efficiency does not supplant its specific language about how to approve projects. 19 Second, the Agency’s argument gives short shrift to the Compact’s structure, history and 20 purposes. Efficiency is only one of the Compact’s goals. Another goal is maintaining “standards 21 for air quality, water quality, soil conversation, vegetation preservation and noise.” Tahoe-Sierra, 22 535 U.S. at 310 (quoting Art. II(i)). The modern Compact has its roots in California’s 23 dissatisfaction with the Agency’s previous regulations, which included “numerous exceptions and 24 did not significantly limit the construction of new residential housing.” Id. at 309. The court 25 hesitates to relegate that history to the background in favor of “efficiency” in approving new 26 projects. 27 Third, in response to a motion to dismiss, the court must confine its review to the 28 complaint and draw reasonable inferences in Harrosh’s favor. Steinle, 919 F.3d at 1160. No 1 factual allegations justify the Agency’s fears that complying with the Compact’s voting rules will 2 bog down its approval process. Nor can the court conclude at this early stage that the voting 3 requirements in Article III(g)(2) are incompatible with efficient regulation. It is reasonable to 4 infer, for example, that the Governing Board could regulate efficiently by voting affirmatively to 5 approve all projects a hearings officer or municipal government recommends absent objections or 6 an appeal. The court will not consider the evidence the Agency has attached to its reply in an 7 attempt to show the Board will be inundated if it were forced to vote affirmatively on every 8 project. See Reply Exs. 14–18, ECF Nos. 25-1 to 25-5. The Agency may present this evidence at 9 summary judgment or another appropriate phase. 10 The Agency suggests in its reply that the Ninth Circuit has approved of its appellate 11 procedure and its authority to delegate project decisions. See Reply Dismiss at 2–3 (citing Sierra 12 Club, 840 F.3d at 1113) and Compact Art. VI(m)–(n)). In Sierra Club, the Ninth Circuit did not 13 consider whether the Agency has authority to delegate approval decisions, let alone whether a 14 delegation would violate Article III(j)(2). It simply mentioned the Agency has adopted “an 15 appeals process for all delegated projects” and a 2012 Regional Plan Update “reduced the 16 maximum size of projects that could be reviewed and approved by other agencies through an 17 Area Plan.” 840 F.3d at 1113. Nor do the Compact’s provisions on contracts and agreements 18 with local government authorities address the voting provisions in Article III. Under those 19 provisions, the Agency has authority “to initiate, negotiate and participate in contracts and 20 agreements among the local governmental authorities of the region, or any other 21 intergovernmental contracts or agreements authorized by State or Federal law.” Compact Art. 22 VI(m). “Each intergovernmental contract or agreement shall provide for its own finding and 23 staffing, but this shall not preclude financial contributions from the local authorities concerned or 24 from supplementary sources.” Id. Art. VI(n). 25 The motion to dismiss the first claim is denied. The court turns to Harrosh’s request for 26 preliminary injunctive relief. 1 III. PRELIMINARY INJUNCTION 2 To obtain a preliminary injunction, Harrosh must prove four things “by a clear showing”: 3 he is “likely to succeed on the merits,” he is “likely to suffer irreparable harm in the absence of 4 preliminary relief,” “the balance of equities tips in [his] favor,” and “an injunction is in the public 5 interest.” City & Cty. of San Francisco v. United States Citizenship & Immigr. Servs., 944 F.3d 6 773, 788–89 (9th Cir. 2019) (emphasis omitted) (first quoting Mazurek v. Armstrong, 520 U.S. 7 968, 972 (1997) (per curiam); then quoting Winter v. Nat. Resources Def. Council, Inc., 555 U.S. 8 7, 20 (2008)). “Alternatively, ‘serious questions going to the merits and a balance of hardships 9 that tips sharply towards the plaintiff can support issuance of a preliminary injunction, so long as 10 the plaintiff also shows that there is a likelihood of irreparable injury and that the injunction is in 11 the public interest.’” Id. at 789 (quoting All. for the Wild Rockies v. Cottrell, 632 F.3d 1127, 1135 12 (9th Cir. 2011)). 13 The court assumes without deciding that Harrosh is likely to obtain judgment in his favor 14 on his first claim. He has not shown a preliminary injunction is necessary to prevent irreparable 15 harms. Harrosh cites three potential irreparable harms: damage to the environment, “harm to the 16 enjoyment of the aesthetics of Lake Tahoe,” and navigability concerns. App. TRO at 11–12; see 17 also M. Harrosh Decl. ¶¶ 1–2, 7; S. Harrosh Decl. ¶¶ 1–2, 7. The court focused on potential 18 environmental harms when it temporarily restrained the pier’s construction, see TRO at 2, and it 19 starts with those potential harms here. 20 As summarized above, the Compact was created to prevent irreparable environmental 21 harms to Lake Tahoe and the surrounding watershed. See Tahoe-Sierra, 535 U.S. at 309; League 22 to Save Lake Tahoe, 739 F. Supp. 2d at 1265. Environmental concerns have thus been at the 23 center of many cases about development on the shores of Lake Tahoe. See, e.g., Tahoe-Sierra, 24 535 U.S. at 307–10 (summarizing Compact’s history and creation); Cal. ex rel. Van De Kamp v. 25 Tahoe Reg’l Plan. Agency, 766 F.2d 1308, 1316 (9th Cir. 1985) (affirming district court’s 26 decision that “algal growth in Lake Tahoe” and resulting “loss of most of the Lake’s clarity” were 27 irreparable harms and justified preliminary injunction); League to Save Lake Tahoe v. Tahoe 28 Reg’l Plan. Agency, No. 08-2828, 2009 WL 3048739, at *8 (E.D. Cal. Sept. 18, 2009) (finding 1 “construction or installation of boating facilities is likely to cause irreparable injury”). As a 2 result, irreparable environmental harms might be the result of noncompliance with the Compact. 3 See, e.g., Van De Kamp, 766 F.2d at 1324; Van De Kamp, 766 F.2d at 1316. For example, if the 4 Agency has adopted a voting procedure that is more permissive than the procedure laid out in 5 Article III of the Compact, and if it uses that procedure repeatedly, then it might approve more 6 projects than it otherwise would have, and these projects might lead to increased sediment 7 deposits and algal growth and irreparable environmental harms. 8 Harrosh cites the Compact’s broad environmental purposes and cases in which federal 9 courts have enjoined actions that risked irreparable harm to the environment. See App. TRO at 10 11–12. At hearing, his counsel argued any unpermitted project is itself an irreparable 11 environment harm. But he has not shown irreparable environmental harm is likely if construction 12 continues on the Johannessen’s pier while this case is pending, a question the court must consider. 13 The evidence weighs in favor of the opposite conclusion. The Johannessens engaged a consultant 14 to prepare an environmental assessment as part of their permit application. See Stock Decl. 15 ¶¶ 6–7, ECF No. 36-2; Envt. Assessment, Stock Decl. Ex. A, ECF No. 36-2. The consultant, 16 whose credentials Harrosh does not challenge, visited the construction site and evaluated the 17 “overall existing environment, the littoral benthic sediment distribution patterns in the area, the 18 fish habitat and fisheries in the area.” Envt. Assessment at 3. He also conducted 19 “[r]econnaissance of the shoreline . . . to evaluate the potential habitat for the endangered (State 20 of California) Tahoe yellow cress,” reviewed “[r]elevant scientific literature,” and interviewed 21 “scientists having expertise in the relevant areas (e.g., fisheries).” Id. He concluded “[o]verall, 22 the construction of a new single-family pier will have no negative impact on the water quality, 23 littoral sediment transport, fisheries, and fish habitat of Lake Tahoe.” Id. at 23. “Therefore,” he 24 wrote, “the project will have no adverse environmental impacts on the environment of Lake 25 Tahoe at this specific location.” Id. Harrosh offers no evidence to rebut or refute these opinions. 26 In short, while irreparable environmental harms are possible, the possibility of 27 environmental harm does not justify a preliminary injunction. See Winter, 555 U.S. at 21. 28 “[P]laintiffs seeking preliminary relief” must “demonstrate that irreparable injury is likely in the 1 absence of an injunction.” Id. at 22 (emphasis in original). “Issuing a preliminary injunction 2 based only on a possibility of irreparable harm is inconsistent with [the Supreme Court’s] 3 characterization of injunctive relief as an extraordinary remedy that may only be awarded upon a 4 clear showing that the plaintiff is entitled to such relief.” Id. Harrosh has not shown irreparable 5 harms to the environmental are likely, so the potential harms do not justify injunctive relief. 6 Harrosh also argues if construction continues while this case is pending, the lake’s 7 “aesthetics” will suffer, as the construction site will be an “eyesore.” App. TRO at 12. He has 8 not shown this harm would be irreparable. If Harrosh ultimately proves, as he alleges, that the 9 Agency’s voting process violates the Compact, then the Agency could still approve the pier in a 10 vote that complies with the Compact. If the Johannessens cannot obtain a permit, the pier could 11 be removed and Harrosh could be compensated with damages, if damages are appropriate.9 He 12 cites no authority to show these remedies would not suffice to remedy a temporary, personal, 13 aesthetic interest, and the court is aware of none. Cf., e.g., Tutein v. Insite Towers, LLC, No. 12- 14 071, 2013 WL 309056, at *5 (D.V.I. Jan. 25, 2013) (finding “unsightly tower,” an alleged 15 “eyesore,” was not “irreparable harm” justifying preliminary injunction); Del Don v. Vilsack, No. 16 10-126, 2010 WL 476719, at *3 (E.D. Cal. Feb. 3, 2010) (holding “temporary restriction” on use 17 of real property improvements was not “irreparable harm” justifying temporary restraining order). 18 Finally, Harrosh argues if the court does not enjoin the pier’s construction, it will be more 19 difficult and dangerous to use the pier on his own property. See App. TRO at 12; M. Harrosh 20 Decl. ¶ 2. He and Samuel Harrosh aver in declarations that “[t]he proposed pier would 21 substantially reduce the existing clearance on the North side of the Harrosh Pier, preventing 22 watercraft . . . from safely operating in the vicinity.” M. Harrosh Decl. ¶ 2; accord S. Harrosh 23 Decl. ¶ 2. Harrosh has not offered information about particular boats, weather and water 24 conditions, clearances, or similar specifics that might support their safety concerns. The court 25 cannot conclude on this record that Michael or Samuel Harrosh are qualified to offer opinions 26 about the pier’s safety beyond their personal knowledge. See Fed. R. Evid. 701, 702. Other 9 Although Harrosh asks for nominal damages expressly, he also asks for “any other relief that the Court deems just and proper under the circumstances of this case.” Compl. at 26. 1 evidence also undercuts their safety claims. According to a Staff Report prepared for the hearings 2 officer, for example, the pier will not “impact navigation or create a threat to public safety.” Staff 3 Report Attachment. A ¶ 2(g), Req. J. Not. Ex. 11, ECF No. 16. Harrosh has not cited evidence 4 showing other agencies that approved the pier, such as the Army Corps of Engineers, voiced 5 concerns about navigation or safety. At the preliminary injunction hearing, his counsel 6 challenged the Corps’s findings and noted an ongoing administrative dispute related to the 7 Corps’s approval, but he did not offer evidence beyond the testimony cited above. 8 On this record, it is possible the Johannessens’ pier will make navigation more difficult or 9 dangerous, but Harrosh has not shown that harm is likely. Finally, even if navigation will likely 10 be more difficult or dangerous, Harrosh has not offered evidence to show these difficulties and 11 dangers cannot be mitigated or otherwise addressed; he has not shown these harms are 12 “irreparable.” 13 IV. INJUNCTION PENDING APPEAL 14 Harrosh also now asks the court to enjoin the pier’s construction while he appeals this 15 order. Mot. Stay Pending Appeal, ECF No. 42. The federal rules give district courts the authority 16 to “suspend, modify, restore, or grant an injunction on terms for bond or other terms that secure 17 the opposing party’s rights” while an appeal is pending. Fed. R. Civ. P. 62(d). The test district 18 courts use when asked to issue injunctions pending appeal is essentially the same as the test that 19 applies to a motion for a preliminary injunction or a stay pending appeal, although they are not 20 identical. See Nken v. Holder, 556 U.S. 418, 426, 429 (2009); Leiva-Perez v. Holder, 640 F.3d 21 962, 966 (9th Cir. 2011). The court considers whether the moving party has demonstrated it is 22 “likely to succeed on the merits” and “likely to suffer irreparable harm in the absence of 23 preliminary relief” and whether the balance of harms and public interests weigh in favor of an 24 injunction. S. Bay United Pentecostal Church v. Newsom, 959 F.3d 938, 939 (9th Cir. 2020). 25 Harrosh argues irreparable environmental harms are likely absent an injunction because an 26 unpermitted pier is a “project” that “by definition . . . may substantially affect the land, water, air, 27 space or any other natural resources of the [Lake Tahoe] region.” Mot. Stay Pending Appeal at 5 28 (emphasis omitted). He points out the Compact “expresses a legislative judgment that 1 development and urbanization of the Lake Tahoe region pose a threat to the ‘irreparable’ 2 environmental and ecological values of the region.” Id. (emphasis omitted) (quoting TRO at 2, in 3 turn quoting Van De Kamp, 766 F.2d at 1324). But an injunction cannot rest on proof that the 4 pier “may substantially affect” the environment; the moving party must identify a “harm” not an 5 effect, and that harm must be both “likely” and “irreparable.” Winter, 555 U.S. at 20; S. Bay 6 United Pentecostal, 959 F.3d at 939. Harrosh has not done so. 7 In his motion for an injunction pending appeal, Harrosh also argues for the first time that 8 irreparable environmental harms are likely because driving piles into the lakebed creates a loud 9 noise. Mot. Stay Pending Appeal at 5–6. He cites Compact provisions establishing decibel limits 10 for a variety of activities. See id. at 6 (citing Prows Decl. Ex. 1 at 13–14, ECF No. 42-3). He also 11 cites a 1971 EPA study reporting that jack hammers, rock drills, and pile drivers can be as loud as 12 90–100 dB at 50 feet, which is higher than some of the limits in the cited Compact pages. See id. 13 (citing Prows Decl. Ex. 2 at 11). This argument is unavailing. The cited Compact limits do not 14 mention construction noise. And even if construction noise would exceed the Compact’s limits, 15 Harrosh again assumes without proof that irreparable environmental harm is the likely result of 16 every Compact violation. Noise and vibration might well disturb plants and animals or cause 17 other harms, but no evidence in the record shows that is so, and no evidence shows those harms 18 would be irreparable. The motion for an injunction pending appeal is denied. 19 V. CONCLUSION 20 In conclusion, the court orders as follows: 21 The stipulation at ECF No. 28, construed as an unopposed request for leave to 22 amend the complaint, is granted. An amended complaint omitting the fourth 23 claim must be filed within seven days. 24 With respect to the complaint’s first claim, the motion to dismiss (ECF No. 14) is 25 denied. With respect to the complaint’s fourth claim, the motion to dismiss is 26 denied as moot. 1 The temporary restraining order (ECF No. 35) is dissolved. The court declines to 2 convert the temporary restraining order into a preliminary injunction. See Fed. R. 3 Civ. P. 65(b)(2)–(4). 4 The motion for an injunction pending appeal (ECF No. 42) is denied. 5 As discussed at the November 8, 2022 hearing, this matter is referred to a 6 settlement conference before the assigned magistrate judge. 7 The deadline for hearing any dispositive motions of any type, including for 8 summary judgment or judgment on the pleadings, is set for March 10, 2023 at 9 10:00 a.m. before the undersigned. This order does not preclude any party from 10 noticing any dispositive motion before that deadline, if otherwise permitted by the 11 Federal Rules of Civil Procedure and this District’s local rules. 12 IT IS SO ORDERED. 13 DATED: November 10, 2022.
Document Info
Docket Number: 2:21-cv-01969
Filed Date: 11/10/2022
Precedential Status: Precedential
Modified Date: 6/20/2024